CN107227745A - A kind of group's anchor cable mat foundation of power transmission tower - Google Patents
A kind of group's anchor cable mat foundation of power transmission tower Download PDFInfo
- Publication number
- CN107227745A CN107227745A CN201710479888.5A CN201710479888A CN107227745A CN 107227745 A CN107227745 A CN 107227745A CN 201710479888 A CN201710479888 A CN 201710479888A CN 107227745 A CN107227745 A CN 107227745A
- Authority
- CN
- China
- Prior art keywords
- foundation
- anchor
- power transmission
- transmission tower
- anchor cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 30
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 78
- 239000010959 steel Substances 0.000 claims abstract description 78
- 239000004567 concrete Substances 0.000 claims abstract description 17
- 230000000712 assembly Effects 0.000 claims description 7
- 238000000429 assembly Methods 0.000 claims description 7
- 230000000694 effects Effects 0.000 claims description 2
- 239000000725 suspension Substances 0.000 claims 2
- 238000005266 casting Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 description 14
- 238000009412 basement excavation Methods 0.000 description 10
- 238000005452 bending Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- 238000011065 in-situ storage Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000003912 environmental pollution Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种输电塔用群锚索板式基础,包括基础上板、位于基础上板下方地面内的基础下部球体、设置在基础上板上的上承载钢垫板,以及若干预应力锚索,所述预应力锚索包括钢绞线、上联接板、下联接板以及预拉力弹簧,所述钢绞线从基础上板穿过且上端与上承载钢垫板固定,所述钢绞线的下端与上联接板连接,所述预拉力弹簧设置在上联接板和下联接板之间,所述上联接板和下联接板之间设有可收缩和扩张的伸缩锚组件,所述基础下部球体由混凝土浇筑而成且与扩张后的伸缩锚组件浇筑结合为一体。本发明能使上部输电杆塔具有较好的抵抗动荷载能力。
The invention discloses a group anchor cable slab foundation for a power transmission tower, which comprises a foundation upper slab, a sphere at the lower part of the foundation located in the ground below the foundation upper slab, an upper bearing steel backing plate arranged on the foundation upper slab, and several prestressed anchors The prestressed anchor cable includes a steel strand, an upper connecting plate, a lower connecting plate and a pretension spring. The steel strand passes through the upper plate of the foundation and the upper end is fixed to the upper bearing steel backing plate. The steel strand The lower end of the line is connected to the upper connecting plate, the pretension spring is arranged between the upper connecting plate and the lower connecting plate, and a retractable and expandable telescopic anchor assembly is arranged between the upper connecting plate and the lower connecting plate. The lower sphere of the foundation is formed by pouring concrete and integrated with the expanded telescopic anchor assembly. The invention can make the upper part of the power transmission tower have a better ability to resist dynamic loads.
Description
技术领域technical field
本发明属于输电技术,具体涉及输电塔基础。The invention belongs to the power transmission technology, and in particular relates to the foundation of a power transmission tower.
背景技术Background technique
目前,在覆盖层较厚的地区,主要使用传统的输电线路基础,例如“大开挖”、“掏挖扩底”、“灌注桩”等基础,但是这些传统基础都有缺陷,大开挖基础开挖面积大,占地多;掏挖基础的施工比较困难;灌注桩基础的造价比较高。At present, in areas with thick overburden, traditional transmission line foundations are mainly used, such as "big excavation", "excavation and bottom expansion", "cast-in-situ piles" and other foundations, but these traditional foundations have defects, and large excavation The excavation area of the foundation is large and occupies a lot of land; the construction of the excavated foundation is relatively difficult; the cost of the cast-in-situ pile foundation is relatively high.
传统基础地下部分占用空间较大,当对基础地下部分的占用空间存在较高的约束条件时,常规的板式基础由于计算模型的限制,地下大板的面积往往较大,易不满足应用条件;而灌注桩基础虽占地面积小很多,但对于环境要求较高或交通运输不便的地区,采用灌注桩基础时,由于施工工艺的限制,对于场地和运输条件均有一定要求,往往由于无法很好的解决而造成环境污染。The underground part of the traditional foundation occupies a large space. When there are high constraints on the occupied space of the underground part of the foundation, due to the limitation of the calculation model of the conventional slab foundation, the area of the large underground slab is often large, and it is easy to fail to meet the application conditions; Although the cast-in-situ pile foundation covers a much smaller area, for areas with high environmental requirements or inconvenient transportation, when using cast-in-place pile foundations, due to the limitation of construction technology, there are certain requirements for the site and transportation conditions, often due to inability to quickly Environmental pollution caused by a good solution.
传统基础主要依靠基础整体来抵抗上拔力、下压力和水平力,但抵抗某一控制荷载时往往传统基础的局部并不受力或受力较小,导致材料的浪费,增加基础造价,使得传统基础的造价较高。The traditional foundation mainly relies on the whole foundation to resist the uplift force, downward pressure and horizontal force, but when resisting a certain control load, the local part of the traditional foundation is often not stressed or the force is small, resulting in waste of materials, increasing the cost of the foundation, and making Traditional foundations are more expensive.
发明内容Contents of the invention
本发明所要解决的技术问题就是提供一种输电塔用群锚索板式基础,施工方便,且能使输电塔具有较好的抵抗动荷载能力。The technical problem to be solved by the present invention is to provide a group anchor cable slab foundation for a power transmission tower, which is convenient for construction and enables the power transmission tower to have better resistance to dynamic loads.
为解决上述技术问题,本发明采用如下技术方案:一种输电塔用群锚索板式基础,包括基础上板、位于基础上板下方地面内的基础下部球体、设置在基础上板上的上承载钢垫板,以及若干预应力锚索,所述预应力锚索包括钢绞线、上联接板、下联接板以及预拉力弹簧,所述钢绞线从基础上板穿过且上端与上承载钢垫板固定,所述钢绞线的下端与上联接板连接,所述预拉力弹簧设置在上联接板和下联接板之间,所述上联接板和下联接板之间设有可收缩和扩张的伸缩锚组件,所述伸缩锚组件在自然状态下受预拉力弹簧作用向外周向扩张,所述基础下部球体由混凝土浇筑而成且与扩张后的伸缩锚组件浇筑结合为一体。In order to solve the above-mentioned technical problems, the present invention adopts the following technical solutions: a group anchor cable slab foundation for transmission towers, including the foundation upper slab, the foundation lower sphere located in the ground below the foundation upper slab, and the upper bearing set on the foundation upper slab A steel backing plate, and several prestressed anchor cables, the prestressed anchor cables include steel strands, upper connecting plates, lower connecting plates and pretension springs, the steel strands pass through the upper plate of the foundation and the upper end and the upper bearing The steel backing plate is fixed, the lower end of the steel strand is connected to the upper connecting plate, the pretension spring is arranged between the upper connecting plate and the lower connecting plate, and a retractable spring is arranged between the upper connecting plate and the lower connecting plate. and the expanded telescopic anchor assembly, the telescopic anchor assembly expands outward circumferentially under the action of a pre-tension spring in a natural state, and the sphere at the lower part of the foundation is formed by pouring concrete and integrated with the expanded telescopic anchor assembly.
进一步的,所述伸缩锚组件包括上连杆和下连杆,所述上连杆以及下连杆的一端铰接在一起,所述上连杆的另一端与上联接板铰接,所述下连杆的另一端与下联板铰接。Further, the telescopic anchor assembly includes an upper link and a lower link, one end of the upper link and the lower link are hinged together, the other end of the upper link is hinged with the upper connecting plate, and the lower link The other end of the rod is hinged with the lower connecting plate.
进一步的,所述伸缩锚组件设置有四组且沿上联接板和下联接板的周向均布。Further, the telescopic anchor assemblies are provided in four groups and are evenly distributed along the circumferential direction of the upper connecting plate and the lower connecting plate.
进一步的,所述上承载钢垫板上设置有第一通孔,所述上承载钢垫板的上方设有固定盘,所述钢绞线从第一通孔中穿过并与固定盘固定。Further, a first through hole is provided on the upper bearing steel backing plate, a fixing plate is arranged above the upper bearing steel backing plate, and the steel strand passes through the first through hole and is fixed to the fixing plate .
进一步的,所述固定盘上设有预应力夹片锚具,所述钢绞线的上端采用预应力夹片锚具固定。Further, the fixed plate is provided with a prestressed clip anchor, and the upper end of the steel strand is fixed with a prestressed clip anchor.
进一步的,所述基础上板下方地面内设有供预应力锚索通过的锚孔,所述锚孔的底部设有容纳基础下部球体的扩张孔,所述钢绞线外套有钢套管,所述钢套管与锚孔孔壁之间的空腔内浇筑有填充混凝土且该填充混凝土与基础下部球体一体浇筑成型。Further, an anchor hole is provided in the ground below the upper plate of the foundation for the passage of the prestressed anchor cable, and the bottom of the anchor hole is provided with an expansion hole for accommodating the lower sphere of the foundation, and the steel strand is covered with a steel sleeve. Filling concrete is poured into the cavity between the steel casing and the wall of the anchor hole, and the filling concrete is integrally cast with the lower sphere of the foundation.
进一步的,所述钢套管可拆卸连接有提拉绳,所述钢套管的口部设有吊环,所述提拉绳的底部设有与吊环配合的挂钩。Further, the steel sleeve is detachably connected with a lifting rope, the mouth of the steel sleeve is provided with a lifting ring, and the bottom of the lifting rope is provided with a hook matching with the lifting ring.
进一步的,所述基础上板由钢筋混凝土浇筑而成。Further, the upper slab of the foundation is poured from reinforced concrete.
进一步的,所述基础上板与上承载钢垫板通过锚栓相连接。Further, the upper plate of the foundation is connected with the upper bearing steel backing plate through anchor bolts.
进一步的,所述基础上板浇筑在下承载钢垫板上。Further, the upper slab of the foundation is poured on the lower bearing steel backing slab.
本发明采用上述技术方案后,带来的有益效果为:After the present invention adopts above-mentioned technical scheme, the beneficial effect that brings is:
基础上板可以看作浅基础,基础上板和基础下部球体通过预应力锚索装配连接,通过对锚索施加预应力把基础上板与基础下部球体连接在一起,基础下部球体由混凝土浇筑而成后与扩张后的伸缩锚组件浇筑结合为一体。基础上板的主要作用为抵抗竖直向下的压力、水平力和弯矩,当基础受下压力作用时,下压力完全由基础上板承受,防止基础出现侧向滑移和倾覆;基础下部球体的主要作用为抵抗上部结构由于风载荷等因素产生的上拔力,当基础受上拔力作用时,上拔力通过上承载钢垫板及预应力锚索传递给基础多个基础下部球体,完全由基础下部球体联动承受,防止基础被拔出。因此,能使上部输电杆塔具有较好的抵抗动荷载能力,随着极端气候的不断出现,动荷载在以后输电线路设计地位将逐步提高。The upper slab of the foundation can be regarded as a shallow foundation. The upper slab and the lower sphere of the foundation are assembled and connected by prestressed anchor cables. The upper slab of the foundation is connected with the lower sphere of the foundation by applying prestress to the anchor cables. After it is completed, it is integrated with the expanded telescopic anchor component pouring. The main function of the upper plate of the foundation is to resist the vertical downward pressure, horizontal force and bending moment. When the foundation is subjected to the downward pressure, the downward force is completely borne by the upper plate of the foundation to prevent the foundation from lateral slipping and overturning; the lower part of the foundation The main function of the sphere is to resist the uplift force of the upper structure due to factors such as wind loads. When the foundation is subjected to the uplift force, the uplift force is transmitted to the multiple foundation lower spheres through the upper bearing steel backing plate and prestressed anchor cables. , It is completely supported by the linkage of the lower part of the foundation to prevent the foundation from being pulled out. Therefore, it can make the upper transmission tower have a better ability to resist dynamic loads. With the continuous emergence of extreme weather, the status of dynamic loads in the design of future transmission lines will gradually increase.
上承载钢垫板及预应力锚索主要起传递上拔力的作用,基础上板主要承受下压力、水平力,基础下部球体主要承受上拔力,这样基础荷载传递明确、基础受力清晰。The upper load-bearing steel backing plate and prestressed anchor cable mainly play the role of transmitting the uplift force, the upper plate of the foundation mainly bears the down pressure and horizontal force, and the sphere at the bottom of the foundation mainly bears the uplift force, so that the foundation load transmission is clear and the foundation force is clear.
基础上板的主要作用为抵抗竖直向下的压力、水平力和弯矩,可以减小一定厚度,预应力锚索采用地下扩张结构,可以减小锚孔直径,因此可以节省混凝土用量及山区土体开挖方量,降低了工程造价,降低大面积开挖对环境造成的破坏,从而保护生态环境;同时本基础施工机械化程度高,使得施工周期短,提高施工效率,降低施工成本。The main function of the upper slab on the foundation is to resist the vertical downward pressure, horizontal force and bending moment, which can reduce a certain thickness. The prestressed anchor cable adopts an underground expansion structure, which can reduce the diameter of the anchor hole, so it can save concrete consumption and mountainous areas. The amount of soil excavation reduces the cost of the project, reduces the damage caused by large-scale excavation to the environment, and thus protects the ecological environment; at the same time, the foundation construction has a high degree of mechanization, which makes the construction period short, improves construction efficiency, and reduces construction costs.
附图说明Description of drawings
下面结合附图和具体实施方式对本发明作进一步描述:The present invention will be further described below in conjunction with accompanying drawing and specific embodiment:
图1为输电塔用群锚索板式基础在预应力锚索处于收缩状态下的示意图;Fig. 1 is the schematic diagram of the group anchor cable slab foundation with the prestressed anchor cable in the shrinking state for the transmission tower;
图2为输电塔用群锚索板式基础在预应力锚索处于扩张状态下的示意图;Fig. 2 is the schematic diagram of the group anchor cable slab foundation with the prestressed anchor cable in the expanded state for the transmission tower;
图3为预应力锚索处于扩张状态下的结构示意图;Fig. 3 is the structural schematic diagram of prestressed anchor cable under expansion state;
图4为固定盘的结构示意图。Fig. 4 is a schematic diagram of the structure of the fixed disk.
具体实施方式detailed description
参照图1至图4对本发明一种输电塔用群锚索板式基础的实施例做进一步说明。Referring to Fig. 1 to Fig. 4, an embodiment of a group anchor cable slab foundation for a power transmission tower according to the present invention will be further described.
如图1至图4所示,一种输电塔用群锚索板式基础,包括基础上板2、位于基础上板下方地面内的基础下部球体、设置在基础上板上的上承载钢垫板,以及若干预应力锚索1,所述预应力锚索包括钢绞线11、上联接板12、下联接板14以及预拉力弹簧13,所述钢绞线11从基础上板2穿过且上端与上承载钢垫板固定,所述钢绞线的下端与上联接板12连接,所述预拉力弹簧13设置在上联接板12和下联接板14之间,所述上联接板12和下联接板14之间设有可收缩和扩张的伸缩锚组件15。As shown in Figures 1 to 4, a group anchor cable slab foundation for a transmission tower includes a foundation upper plate 2, a base lower sphere located in the ground below the foundation upper plate, and an upper bearing steel backing plate arranged on the foundation upper plate , and several prestressed anchor cables 1, the prestressed anchor cables include a steel strand 11, an upper connecting plate 12, a lower connecting plate 14 and a pretension spring 13, and the steel strand 11 passes through the upper plate 2 of the foundation and The upper end is fixed with the upper bearing steel backing plate, the lower end of the steel strand is connected with the upper connecting plate 12, and the pretension spring 13 is arranged between the upper connecting plate 12 and the lower connecting plate 14, and the upper connecting plate 12 and the lower connecting plate 14 are connected. A retractable and expandable telescopic anchor assembly 15 is arranged between the lower connecting plates 14 .
其中,如图3所示,所述伸缩锚组件15包括上连杆151和下连杆152,所述上连杆151以及下连杆152的一端铰接在一起,所述上连杆151的另一端与上联接板12铰接,所述下连杆152的另一端与下联板14铰接。伸缩锚组件15借助钢套管3安装在锚孔4中,伸缩锚组件15向中心收缩,即可放入钢套管3内。锚孔的底部设有容纳基础下部球体的扩张孔41。所述钢套管3可拆卸连接有提拉绳32,用于向上提拉钢套管3,所述钢套管的口部设有吊环31,所述提拉绳的底部设有与吊环配合的挂钩。提拉绳32设置有两个且沿钢套管口部均布,使得提拉绳32在提升钢套管3时,钢套管3受力更加均匀,拉动钢套管3更加方便省力。Wherein, as shown in FIG. 3 , the telescopic anchor assembly 15 includes an upper link 151 and a lower link 152, one end of the upper link 151 and the lower link 152 are hinged together, and the other end of the upper link 151 One end is hinged to the upper connecting plate 12 , and the other end of the lower connecting rod 152 is hinged to the lower connecting plate 14 . The telescopic anchor assembly 15 is installed in the anchor hole 4 by means of the steel sleeve 3, and the telescopic anchor assembly 15 shrinks toward the center, and then it can be put into the steel sleeve 3. The bottom of the anchor hole is provided with an expansion hole 41 for accommodating the lower sphere of the foundation. The steel casing 3 is detachably connected with a lifting rope 32 for lifting the steel casing 3 upwards. The mouth of the steel casing is provided with a lifting ring 31, and the bottom of the lifting rope is provided with a ring to cooperate with the lifting ring. the hook. Two lifting ropes 32 are arranged and evenly distributed along the mouth of the steel sleeve, so that when the lifting rope 32 lifts the steel sleeve 3, the force on the steel sleeve 3 is more uniform, and the pulling of the steel sleeve 3 is more convenient and labor-saving.
当伸缩锚组件15在收紧状态时,预拉力弹簧13处于拉伸状态,同时拉伸伸缩锚组件15,使伸缩锚组件15穿进钢套管3内,以便置于锚孔4中;当伸缩锚组件15与钢套管3底部一起位于扩张孔41内时,可以进行扩张,通过刚性支撑杆顶住上联接板12,用提拉绳32通过钢套管上的吊环31上提,同时由于预拉力弹簧13的作用,使伸缩锚组件15呈扩张状态时。再向钢套管3与锚孔孔孔壁之间的空腔内内浇筑混凝土,使基础下部球体与扩张后的伸缩锚组件15浇筑结合为一体。预应力锚索1采用地下扩张结构,可以减小锚孔直径,节省混凝土用量及山区土体开挖方量,降低了工程造价,降低大面积开挖对环境造成的破坏,从而保护生态环境。在本实施例中,所述伸缩锚组件15设置有四组且沿上联接板12和下联接板14的周向均布。使得伸缩锚组件15从四个方向上向锚孔4延伸,使得浇注混凝土之后的包裹着的预应力锚索在各个方向上的受力更加均匀。而预应力锚索采用弹簧式的伸缩扩张结构可自由伸缩,便于运输及施工。When the telescopic anchor assembly 15 is in a tightened state, the pretension spring 13 is in a stretched state, and the telescopic anchor assembly 15 is stretched simultaneously, so that the telescopic anchor assembly 15 penetrates into the steel casing 3 so as to be placed in the anchor hole 4; When the telescopic anchor assembly 15 is located in the expansion hole 41 together with the bottom of the steel casing 3, it can be expanded, and the upper connecting plate 12 is supported by the rigid support rod, and the lifting ring 31 on the steel casing is used to lift the lifting rope 32, and at the same time Due to the effect of the pretension spring 13, the telescopic anchor assembly 15 is in an expanded state. Concrete is poured into the cavity between the steel casing 3 and the wall of the anchor hole, so that the spheroid at the bottom of the foundation is combined with the expanded telescopic anchor assembly 15 pouring. The prestressed anchor cable 1 adopts an underground expansion structure, which can reduce the diameter of the anchor hole, save the amount of concrete and the amount of soil excavation in mountainous areas, reduce the cost of the project, reduce the damage to the environment caused by large-scale excavation, and thus protect the ecological environment. In this embodiment, the telescopic anchor assemblies 15 are provided in four groups and are evenly distributed along the circumferential direction of the upper connecting plate 12 and the lower connecting plate 14 . The telescopic anchor assembly 15 extends toward the anchor hole 4 from four directions, so that the wrapped prestressed anchor cable after pouring concrete is more evenly stressed in all directions. The prestressed anchor cable adopts a spring-type telescopic expansion structure, which can be freely expanded and contracted, which is convenient for transportation and construction.
基础上板2由钢筋混凝土浇筑而成,基础上板2与上承载钢垫板通过锚栓相连接,同时基础上板浇筑在下承载钢垫板上。The foundation upper plate 2 is formed by pouring reinforced concrete, the foundation upper plate 2 is connected with the upper bearing steel backing plate through anchor bolts, and the foundation upper plate is poured on the lower bearing steel backing plate.
基础上板的主要作用为抵抗竖直向下的压力、水平力和弯矩,当基础受下压力作用时,下压力完全由基础上板承受,防止基础出现侧向滑移和倾覆;基础下部球体的主要作用为抵抗上部结构由于风载荷等因素产生的上拔力,当基础受上拔力作用时,上拔力通过上承载钢垫板及预应力锚索传递给基础多个基础下部球体,完全由基础下部球体联动承受,防止基础被拔出。因此,能使上部输电杆塔具有较好的抵抗动荷载能力。The main function of the upper plate of the foundation is to resist the vertical downward pressure, horizontal force and bending moment. When the foundation is subjected to the downward pressure, the downward force is completely borne by the upper plate of the foundation to prevent the foundation from lateral slipping and overturning; the lower part of the foundation The main function of the sphere is to resist the uplift force of the upper structure due to factors such as wind loads. When the foundation is subjected to the uplift force, the uplift force is transmitted to the multiple foundation lower spheres through the upper bearing steel backing plate and prestressed anchor cables. , It is completely supported by the linkage of the lower part of the foundation to prevent the foundation from being pulled out. Therefore, the upper transmission tower can have a better ability to resist dynamic loads.
上承载钢垫板及预应力锚索主要起传递上拔力的作用,基础上板主要承受下压力、水平力,基础下部球体主要承受上拔力,这样基础荷载传递明确、基础受力清晰。而钢绞线11与上承载钢垫板固定后,可以加大钢绞线与基础上板之间连接的接触面积,防止出现过大的应力集中现象。The upper load-bearing steel backing plate and prestressed anchor cable mainly play the role of transmitting the uplift force, the upper plate of the foundation mainly bears the down pressure and horizontal force, and the sphere at the bottom of the foundation mainly bears the uplift force, so that the foundation load transmission is clear and the foundation force is clear. And after the steel strand 11 is fixed with the upper load-bearing steel backing plate, the contact area connected between the steel strand and the foundation upper plate can be increased to prevent excessive stress concentration from occurring.
基础上板的主要作用为抵抗竖直向下的压力、水平力和弯矩,可以减小一定厚度,因此可以节省混凝土用量及山区土体开挖方量,降低了工程造价,降低大面积开挖对环境造成的破坏,从而保护生态环境;同时本基础施工机械化程度高,使得施工周期短,提高施工效率,降低施工成本。The main function of the slab on the foundation is to resist the vertical downward pressure, horizontal force and bending moment, and can reduce a certain thickness, so it can save the amount of concrete and the excavation volume of soil in mountainous areas, reduce the project cost, and reduce large-scale excavation The damage caused to the environment, thereby protecting the ecological environment; at the same time, the high degree of mechanization of the foundation construction makes the construction period short, improves the construction efficiency, and reduces the construction cost.
进一步的,上承载钢垫板上设置有第一通孔,所述上承载钢垫板的上方设有固定盘5,所述钢绞线11从第一通孔中穿过并与固定盘5固定,固定盘可以通过螺栓52与上承载钢垫板及基础上板固定为一体。固定盘5增大了钢绞线11与上承载钢垫板之间的接触面积,防止出现过大的应力集中现象。固定盘5上设有预应力夹片锚具51,用于固定钢绞线的上端。Further, a first through hole is provided on the upper bearing steel backing plate, and a fixed disk 5 is arranged above the upper bearing steel backing plate, and the steel strand 11 passes through the first through hole and connects with the fixed disk 5 Fixed, the fixed disc can be fixed as one with the upper bearing steel backing plate and the foundation upper plate by bolts 52. The fixed disc 5 increases the contact area between the steel strand 11 and the upper bearing steel backing plate, preventing excessive stress concentration. The fixed plate 5 is provided with a prestressed clip anchor 51 for fixing the upper end of the steel strand.
参照图4所示,所述固定盘上设有第二通孔50,第二通孔为倒圆台形,预应力夹片锚具51采用分体式的楔形夹头。所述钢绞线从第一通孔和第二通孔中穿过并由分体式的楔形夹头固定。分体式的楔形夹头便于夹持钢绞线,楔形夹头对钢绞线进行夹持的过程中具有自锁功能,不易产生滑移现象;倒圆台形的通孔和楔形夹头相配合,对通孔中的楔形夹头进行固定,防止楔形夹头滑落。而钢绞线端头采用预应力夹片锚具固定,通过对钢绞线施加预应力,使上下混凝土通过钢绞线连接在一起。Referring to FIG. 4 , the fixed plate is provided with a second through hole 50 , the second through hole is rounded and truncated, and the prestressed clip anchor 51 is a split wedge chuck. The steel strand passes through the first through hole and the second through hole and is fixed by a split wedge clamp. The split-type wedge-shaped chuck is convenient for clamping the steel strand. The wedge-shaped chuck has a self-locking function during the clamping of the steel strand, and is not easy to slip; Fix the wedge-shaped collet in the through hole to prevent the wedge-shaped collet from slipping off. The ends of the steel strands are fixed with prestressed clip anchors, and the upper and lower concrete are connected together through the steel strands by applying prestress to the steel strands.
本发明还提供了一种输电塔用群锚索板式基础的施工方法,步骤如下:The present invention also provides a construction method for group anchor cable slab foundations for power transmission towers, the steps are as follows:
(1)在选定的地面上开挖基坑,在基坑的底部向下竖直钻若干锚孔,采用扩孔设备将锚孔底部扩孔至设计大小;(1) Excavate a foundation pit on the selected ground, drill several anchor holes vertically downward at the bottom of the foundation pit, and use reaming equipment to ream the bottom of the anchor holes to the designed size;
(2)上联接板与钢绞线连接(可以采用楔形夹头固定),将钢套管套接在伸缩锚组件外侧并一起放入锚孔中,此时预拉力弹簧处于拉伸状态,同时拉伸伸缩锚组件,使伸缩锚组件处于收缩状态;(2) The upper connecting plate is connected with the steel strand (wedge chuck can be used to fix it), and the steel sleeve is sleeved on the outside of the telescopic anchor assembly and put into the anchor hole together. At this time, the pretension spring is in a stretched state, and at the same time Stretch the telescopic anchor component so that the telescopic anchor component is in a contracted state;
(3)利用支撑杆等器械伸入锚孔中抵住上联接板的顶部,向上拉动提拉绳,提拉绳带动钢套管向上移动,使得伸缩锚组件在锚孔底部的扩孔中伸出钢套管,预拉力弹簧回缩,使得使伸缩锚组件向外扩张,然后取出支撑杆;(3) Use support rods and other instruments to extend into the anchor hole against the top of the upper connecting plate, pull the lifting rope upward, and the lifting rope drives the steel casing to move upward, so that the telescopic anchor assembly extends in the reamed hole at the bottom of the anchor hole. Out of the casing, the pre-tension spring is retracted, so that the telescopic anchor assembly is expanded outward, and then the support rod is taken out;
(4)向锚孔中注入混凝土,使得锚孔中的混凝土和预应力锚索凝结成一体,也形成了基础下部球体,多个预应力锚索施工时,需由内向外依次进行(即先浇筑中间部位预应力锚索,然后浇筑中间部位周围的预应力锚索);(4) Inject concrete into the anchor hole, so that the concrete in the anchor hole and the prestressed anchor cable are condensed into one, and a sphere under the foundation is also formed. When constructing multiple prestressed anchor cables, it must be carried out from the inside to the outside (that is, first Pouring the prestressed anchor cables in the middle part, and then pouring the prestressed anchor cables around the middle part);
(5)在基坑中浇注混凝土,形成基础上板。(5) Concrete is poured in the foundation pit to form the upper slab on the foundation.
最后,基础上板与上承载钢垫板通过锚栓相连接,在上承载钢垫板上放置固定盘,利用分体式的楔形夹头将钢绞线锁紧在固定盘上。Finally, the upper plate of the foundation is connected with the upper load-bearing steel backing plate through anchor bolts, a fixed plate is placed on the upper load-bearing steel backing plate, and the steel strand is locked on the fixed plate by a split wedge-shaped chuck.
使用该基础有以下优点:Using this basis has the following advantages:
(1)能充分的发挥不同种材料的物理力学性能,节省材料,降低造价。(1) It can give full play to the physical and mechanical properties of different materials, save materials and reduce the cost.
(2)可充分利用原状土体,基础抗拔可靠性较高。(2) The undisturbed soil can be fully utilized, and the reliability of the foundation's pull-out resistance is high.
(3)随着极端气候的不断出现,动荷载在以后输电线路设计地位将逐步提高,采用柔性基础,能使上部杆塔具有较好的抵抗动荷载能力。(3) With the continuous emergence of extreme climates, the status of dynamic loads in the design of transmission lines will gradually increase in the future. The use of flexible foundations can make the upper towers have better resistance to dynamic loads.
(4)可以减少弃土量,从而保护生态环境。(4) The amount of spoil can be reduced, thereby protecting the ecological environment.
(5)拆卸方便,降低了基础拆除工程量。(5) It is easy to disassemble, which reduces the amount of foundation demolition work.
(6)该基础结构荷载传递明确,结构计算和施工较简便。(6) The load transfer of the foundation structure is clear, and the structure calculation and construction are relatively simple.
以上所述仅是本发明的优选实施方式,本发明的保护范围并不仅局限于上述实施例,凡属于本发明思路下的技术方案均属于本发明的保护范围。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理前提下的若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above descriptions are only preferred implementations of the present invention, and the protection scope of the present invention is not limited to the above-mentioned embodiments, and all technical solutions under the idea of the present invention belong to the protection scope of the present invention. It should be pointed out that for those skilled in the art, some improvements and modifications without departing from the principles of the present invention should also be regarded as the protection scope of the present invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710479888.5A CN107227745A (en) | 2017-06-22 | 2017-06-22 | A kind of group's anchor cable mat foundation of power transmission tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710479888.5A CN107227745A (en) | 2017-06-22 | 2017-06-22 | A kind of group's anchor cable mat foundation of power transmission tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107227745A true CN107227745A (en) | 2017-10-03 |
Family
ID=59936634
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710479888.5A Pending CN107227745A (en) | 2017-06-22 | 2017-06-22 | A kind of group's anchor cable mat foundation of power transmission tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107227745A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108060820A (en) * | 2017-12-13 | 2018-05-22 | 北京市建筑工程研究院有限责任公司 | A kind of wind power tower prestress wire supporting installation device and its construction method |
CN116950116A (en) * | 2023-08-07 | 2023-10-27 | 江苏昊天龙集团有限公司 | Communication tower pre-buried connecting piece and pipe bolt basis |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102900094A (en) * | 2012-10-11 | 2013-01-30 | 甘肃省电力公司电力经济技术研究院 | Transmission tower plate-type three-rope foundation structure |
CN103982214A (en) * | 2014-05-26 | 2014-08-13 | 北方工业大学 | Novel round platform type anchor rod structure |
CN205653821U (en) * | 2016-03-12 | 2016-10-19 | 溫州设计集团有限公司 | Anti device that floats of soft soil foundation basement |
-
2017
- 2017-06-22 CN CN201710479888.5A patent/CN107227745A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102900094A (en) * | 2012-10-11 | 2013-01-30 | 甘肃省电力公司电力经济技术研究院 | Transmission tower plate-type three-rope foundation structure |
CN103982214A (en) * | 2014-05-26 | 2014-08-13 | 北方工业大学 | Novel round platform type anchor rod structure |
CN205653821U (en) * | 2016-03-12 | 2016-10-19 | 溫州设计集团有限公司 | Anti device that floats of soft soil foundation basement |
Non-Patent Citations (1)
Title |
---|
罗恒勇: "《建筑力学与结构》", 31 July 2016, 中国轻工业出版社 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108060820A (en) * | 2017-12-13 | 2018-05-22 | 北京市建筑工程研究院有限责任公司 | A kind of wind power tower prestress wire supporting installation device and its construction method |
CN108060820B (en) * | 2017-12-13 | 2019-07-12 | 北京市建筑工程研究院有限责任公司 | A kind of wind power tower prestress wire supporting installation device and its construction method |
CN116950116A (en) * | 2023-08-07 | 2023-10-27 | 江苏昊天龙集团有限公司 | Communication tower pre-buried connecting piece and pipe bolt basis |
CN116950116B (en) * | 2023-08-07 | 2024-05-03 | 广西德明通信有限公司 | Communication tower pre-buried connecting piece and pipe bolt basis |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104179178B (en) | A flexible umbrella-shaped support bolt and its method for supporting soil slopes | |
CN101812842B (en) | Tensionless filling pile structure | |
CN204080802U (en) | A kind of flexible umbrella support anchor rod | |
CN204982864U (en) | Insert steel reinforcement cage behind long spiral pore -forming guncreting | |
CN105155572A (en) | Cast-in-place pre-stressed anchor cable draught fan foundation system and construction method thereof | |
CN107386310B (en) | A building support structure applied to hillside terrain and its construction method | |
CN204456167U (en) | Prestress anchoraging blower foundation | |
CN108867684A (en) | Offshore wind turbine gravity caisson basis and its installation method | |
CN111663444B (en) | A composite anchoring structure of suspension bridge tunnel anchor and rock anchor and construction method | |
CN110284420A (en) | Full precast pier-the suspended deck structure of Self-resetting and its assembly method for being easy to repair after shaking | |
CN102900094B (en) | Transmission tower plate-type three-rope foundation structure | |
CN102900095B (en) | Transmission tower plate-type single rope foundation structure | |
CN102900093B (en) | Plate-type double-cable foundation structure of transmission tower | |
CN107227745A (en) | A kind of group's anchor cable mat foundation of power transmission tower | |
CN201649071U (en) | Unstressing cast-in-place pile | |
CN107165186B (en) | Single-anchor cable-slab foundation and construction method for transmission tower | |
CN212358029U (en) | Tunnel type anchorage structure for cable crane | |
CN105297763A (en) | Assembled type flexible half-excavation foundation for electric transmission lines in mountainous areas | |
CN210395407U (en) | Anchor rod gravity type offshore wind power foundation | |
CN205171537U (en) | Mountain area transmission line assembled flexibility is partly drawn and is dug basis | |
CN104929101B (en) | Resistance to plucking prestress anchoraging broken stone pile and construction method that a kind of base expanding and base expanding multistage side is expanded | |
CN206887987U (en) | A kind of power transmission tower group's anchor cable | |
CN219411005U (en) | Reinforcing apparatus of single pile basis | |
CN208328968U (en) | A kind of upper stake suitable for large-scale cyclic load is casted anchor novel foundation | |
CN209308011U (en) | A kind of variable diameters steel reinforcement cage of concise structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171003 |
|
RJ01 | Rejection of invention patent application after publication |