CN107179943A - A kind of device for allocating resources and resource allocation method - Google Patents
A kind of device for allocating resources and resource allocation method Download PDFInfo
- Publication number
- CN107179943A CN107179943A CN201610134153.4A CN201610134153A CN107179943A CN 107179943 A CN107179943 A CN 107179943A CN 201610134153 A CN201610134153 A CN 201610134153A CN 107179943 A CN107179943 A CN 107179943A
- Authority
- CN
- China
- Prior art keywords
- resource
- items
- resource items
- server
- bag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F9/00—Arrangements for program control, e.g. control units
- G06F9/06—Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
- G06F9/46—Multiprogramming arrangements
- G06F9/50—Allocation of resources, e.g. of the central processing unit [CPU]
- G06F9/5005—Allocation of resources, e.g. of the central processing unit [CPU] to service a request
- G06F9/5027—Allocation of resources, e.g. of the central processing unit [CPU] to service a request the resource being a machine, e.g. CPUs, Servers, Terminals
Landscapes
- Engineering & Computer Science (AREA)
- Software Systems (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Information Transfer Between Computers (AREA)
Abstract
The embodiment of the present invention provides the device for allocating resources and resource allocation method that a kind of resource items to application program are modified.During the individual attribute of the layout of the page, the pattern of individual views or some view, related resource plug bag is obtained from server end in application program to be changed for the embodiment of the present invention, the i.e. executable corresponding replacement after loading.Device for allocating resources and resource allocation method provided in an embodiment of the present invention are without repeating modification code, need not issue redaction and need not increase the resource file of client installation kit, you can the resource to application program is modified, and effectively reduces development cost.
Description
Technical field
The present invention relates to data processing field, in particular to a kind of resource distribution
Device and resource allocation method.
Background technology
At present, in Android client, if to change the cloth of the page in application program
Office, the individual attribute of the pattern of individual views or some view, application program are opened
Originator needs to issue new client release, could realize, if to change line adjustment of the printing plate
This visual effect, developer can only be by way of sending out redaction or Dynamical Deployment
Modify.Adopt in manner just described, the split originator of modification cost of resource and user
All than larger, and efficiency comparison is low;Content if necessary to modification is more, shared
Resource file it is bigger, and then cause the file size of client installation kit larger,
Influence Consumer's Experience.
The content of the invention
In view of this, the purpose of the embodiment of the present invention is to provide a kind of resource distribution dress
Put and resource allocation method.
A kind of device for allocating resources provided in an embodiment of the present invention, is serviced applied to one
The client of device communication connection, the device for allocating resources includes:
Resource obtains module, for obtaining the money including needing to change from the server
The resource plug bag of source item;
Resource load-on module, for being loaded to the resource plug bag, obtains institute
State the resource items in resource plug bag;
Resource items searching modul, for the operation according to the configuration resource items currently performed
Search whether there are resource items corresponding with the operation in the resource items of acquisition;
Resource changes module, for completing what is currently performed using the resource items found
Configure the operation of resource items.
Preferably, the device for allocating resources also includes request sending module,
Request sending module, under being sent according to default strategy to the server
The solicited message of resource plug bag is carried, so that the server is according to the solicited message
Down distributing resource plug-in unit bag is to the client.
Preferably, the default strategy includes at least one of following three kinds of modes:
The request sending module is sent according to default time interval to the server
The solicited message;
The request sending module sends institute in application program launching to the server
State solicited message;
The request sending module the resource items searching modul do not find with currently
During the corresponding resource items of operation of the configuration resource items of execution, sent to the server
The solicited message.
Preferably, the device for allocating resources also includes control instruction receiving module,
Control instruction receiving module, for receiving that the server sends to the money
Resource items in the plug-in unit bag of source carry out the control instruction of configuration control;
The resource items searching modul receives described in the control instruction receiving module
After control instruction, according to currently perform configuration resource items operation acquisition resource
Search whether there are resource items corresponding with the operation in.
Preferably, when the resource items searching modul find it is multiple with currently performing
When configuring the corresponding resource items of operation of resource items, the resource changes module according to institute
The content for stating control instruction completes what is currently performed using the corresponding resource items found
Configure the operation of resource items.
Preferably, the resource load-on module is used to set the resource to insert by generation
The mode of the explorer of resource items in part bag is loaded to resource plug bag.
Preferably, the operation of the configuration resource items currently performed is included to view
Rendering operations,
The resource items searching modul according to current view to be rendered acquisition resource
Search whether exist and corresponding resource items in;
The resource change module is completed to current to be rendered using the resource items found
View Rendering operations.
A kind of resource allocation method provided in an embodiment of the present invention, is serviced applied to one
The client of device communication connection, the resource allocation method includes:
The resource plug bag of the resource items including needing to change is obtained from the server;
The resource plug bag is loaded, the money in the resource plug bag is obtained
Source item;
Searched according to the operation of the configuration resource items currently performed in the resource items of acquisition
With the presence or absence of resource items corresponding with the operation;
The operation for the configuration resource items for completing currently to perform using the resource items found.
Preferably, the resource allocation method also includes:
The request for downloading resource plug bag is sent to the server according to default strategy
Information, so that the server is according to the solicited message down distributing resource plug-in unit bag to institute
State client.
Preferably, the default strategy includes at least one of following three kinds of modes:
According to default time interval the solicited message is sent to the server;
In application program launching the solicited message is sent to the server;
The corresponding resource items of operation of the configuration resource items with currently performing are not being found
When, send the solicited message to the server.
Preferably, the resource allocation method also includes:
Receive being carried out to the resource items in the resource plug bag for the server transmission
Configure the control instruction of control;
After the control instruction is received, the configuration that the basis is currently performed is performed
The operation of resource items is searched whether in the resource items of acquisition in the presence of corresponding with the operation
The step of resource.
Preferably, when the operations pair for finding configuration resource items that are multiple and currently performing
During the resource items answered, found according to the content of the control instruction using corresponding
Resource items complete the operation of the configuration resource items currently performed.
Preferably, by generating the resource items being used to set in the resource plug bag
The mode of explorer is loaded to resource plug bag.
Preferably, the operation of the configuration resource items currently performed is included to view
Rendering operations, methods described includes:
According to current view to be rendered search whether to exist in the resource items of acquisition with
Corresponding resource items;
Complete to render behaviour to current view to be rendered using the resource items found
Make.
Compared with prior art, device for allocating resources and resource allocation method of the invention,
In application program to be changed the layout of the page, the pattern of individual views or some regard
During the individual attribute of figure, it is only necessary to related resource plug bag is obtained from server end,
The i.e. executable corresponding replacement after loading, without repeating modification code and hair
Cloth redaction can meet the demand that user modifies to the resource of application program, together
When also effectively reduce development cost.
To enable the above objects, features and advantages of the present invention to become apparent,
Preferred embodiment cited below particularly, and coordinate appended accompanying drawing, it is described in detail below.
Brief description of the drawings
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be to reality
The accompanying drawing used required for applying in example is briefly described, it will be appreciated that the following drawings
Certain embodiments of the present invention is illustrate only, therefore is not construed as the limit to scope
It is fixed, for those of ordinary skill in the art, before creative work is not paid
Put, other related accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 interacts for the server that present pre-ferred embodiments are provided with client
Schematic diagram.
The square frame for the client shown in Fig. 1 that Fig. 2 provides for present pre-ferred embodiments
Figure.
The resource for the client shown in Fig. 2 that Fig. 3 provides for present pre-ferred embodiments
The functional block diagram of configuration device.
Fig. 4 matches somebody with somebody for the resource being applied to shown in Fig. 3 that present pre-ferred embodiments are provided
Put the flow chart of the resource allocation method of device.
Main element symbol description
Embodiment
Below in conjunction with accompanying drawing in the embodiment of the present invention, to the skill in the embodiment of the present invention
Art scheme is clearly and completely described, it is clear that described embodiment is only
A part of embodiment of the present invention, rather than whole embodiments.Usual accompanying drawing here
Described and illustrated in the embodiment of the present invention component can with it is a variety of configuration come
Arrangement and design.Therefore, below to the embodiments of the invention that provide in the accompanying drawings
It is described in detail and is not intended to limit the scope of claimed invention, but only table
Show the selected embodiment of the present invention.Based on embodiments of the invention, people in the art
The every other embodiment that member is obtained on the premise of creative work is not made,
Belong to the scope of protection of the invention.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing,
Therefore, once being defined in a certain Xiang Yi accompanying drawing, then in subsequent accompanying drawing not
Need that it is further defined and explained.Meanwhile, in the description of the invention,
Term " first ", " second " etc. be only used for distinguish description, and it is not intended that indicate or
Imply relative importance.
As shown in figure 1, being the server 100 and visitor that present pre-ferred embodiments are provided
The schematic diagram that family end 200 is interacted.The server 100 passes through network and one
Or multiple client 200 is communicatively coupled, to enter row data communication or interaction.Institute
At least one application journey for being applied to various operating systems can be provided by stating server 100
The installation kit of sequence (Application, APP) is downloaded for the client 200.It is described
, can be by described after client 200 is by server 100 described in the network access
Network downloads the application of the operating system suitable for the client 200 from server 100
The installation kit of program, the application program is installed in the client 200.
In the present embodiment, the client 200 is provided with what is downloaded from the server 100
Suitable for the application program of the operating system of the client 200.The client 200
After the application program is installed, the client 200 can be from the server
100 obtain the plug-in unit bag about the application program.
The server 100 may be, but not limited to, network (Web) server,
Ftp (file transfer protocol, FTP) server, database service
Device etc..The client 200 may be, but not limited to, smart mobile phone, flat board electricity
Brain, Intelligent worn device etc..The operating system of the client 200 can be, but
It is not limited to, Android (Android) system, IOS systems, Windows Phone systems
System etc..Preferably, in the present embodiment, the operating system of the client 200 is peace
Tall and erect system.
As shown in Fig. 2 being the client shown in Fig. 1 of present pre-ferred embodiments offer
The block diagram at end 200.The client 200 includes device for allocating resources 10, storage
Device 20 and processor 30.
The memory 20 and processor 30 are directly or indirectly electrical each other
Connection, to realize the transmission or interaction of data.For example, one can be passed through each other
Or a plurality of communication bus or signal wire are realized and are electrically connected with.
Wherein, memory 20 may be, but not limited to, random access memory
(Random Access Memory, RAM), read-only storage (Read Only
Memory, ROM), programmable read only memory (Programmable Read-Only
Memory, PROM), erasable read-only memory (Erasable Programmable
Read-Only Memory, EPROM), electricallyerasable ROM (EEROM) (Electric
Erasable Programmable Read-Only Memory, EEPROM) etc..Its
In, memory 20 is used for storage program, and the processor 30 refers to receiving execution
After order, described program is performed.
Shown processor 30 is probably a kind of IC chip, the processing with signal
Ability.Above-mentioned processor 30 can be general processor, including central processing unit
(Central Processing Unit, abbreviation CPU), network processing unit
(Network Processor, abbreviation NP) etc.;It can also be digital signal processor
(DSP), application specific integrated circuit (ASIC), ready-made programmable gate array (FPGA) or
Other PLDs, discrete gate or transistor logic, discrete hardware
Component.It can realize or perform disclosed each method, the step in the embodiment of the present invention
Rapid and logic diagram.General processor can be microprocessor or the processor 30
It can be any conventional processor etc..
The device for allocating resources 10 includes at least one or more can be with software or solid
The form of part (firmware) is stored in the memory 20 or is solidificated in the visitor
Software function mould in the operating system (operating system, OS) at family end 200
Block.The processor 30 is used to perform the executable module stored in memory 20,
Software function module or computer program that such as described device for allocating resources 10 includes.
In the present embodiment, the client 200 is provided with from the server 100 and downloaded
The operating system suitable for the client 200 application program, the operation system
Unite as Android system.The device for allocating resources 10 can be mounted to client 200
A single application program, or from server 100 download install application
A part (such as One function module) for program.
Referring to Fig. 3, the client shown in the Fig. 2 provided for present pre-ferred embodiments
The functional block diagram of the device for allocating resources 10 at end 200.The device for allocating resources
10, which include resource, obtains module 101, resource load-on module 102, resource items lookup mould
Block 103, resource change module 104, request sending module 105 and control instruction connect
Receive module 106.
Resource obtains module 101, for being obtained from the server 100 including needs
The resource plug bag of the resource items of change.
(for example change page in application program when the resource of client 200 needs change
The individual attribute of the layout in face, the pattern of individual views or some view), server
100 can actively issue the resource plug bag of the resource items including change in need.Wherein,
It is the object for needing to change that the resource items are corresponding, for example, it may be picture, regarding
Frequently, various types of files such as audio, word.The resource items are in server 100
In be packaged after, in the form of plug-in unit bag carry out be handed down to client 200.Resource
Plug-in unit bag can be uploaded by the terminal device being connected with server 100, can also be in clothes
Direct-on-line generation on business device 100.
Resource load-on module 102, for being loaded to the resource plug bag, is obtained
Take the resource items in the resource plug bag.
Client 200 obtains resource plug bag from server 100, is decompressed first
And be stored under default store path.In this way, the resource load-on module 102 can
The resource plug bag is loaded by the default store path, money therein is obtained
Source item.In the present embodiment, the resource load-on module 102 is used to set by generation
The mode of explorer of resource items in the resource plug bag is put to resource plug
Bag is loaded., will not be right because resource plug bag is present in the form of plug-in unit
Application program installed in client 200 is impacted, and application program can pass through
The explorer of generation uses the resource items in resource plug bag.When there is new resource
Item is by resource plug bag when being issued to client 200, it is not necessary in client 200
Corresponding application program is reinstalled, can be to resource by the explorer of generation
Resource items in plug-in unit bag are configured.
Resource items searching modul 103, for according to the configuration resource items currently performed
Operation searches whether there are resource items corresponding with the operation in the resource items of acquisition.
Specifically, it is installed on the application program of client 200 operationally, including it is big
The operation of the configuration resource items of amount, it may for example comprise to rendering, to animation for view
Play etc..Each operation has corresponding resource items to be configured upon execution.Adding
Carry resource plug bag to obtain after resource items therein, provided according to the configuration currently performed
The operation of source item searches whether there is money corresponding with the operation in the resource items of acquisition
Source item.If it is present illustrate that the corresponding resource items of the operation need replacing, if
It is not present, then explanation need not be changed.
Resource changes module 104, for completing currently to hold using the resource items found
The operation of capable configuration resource items.
For the resource items for needing to change, current perform is completed with the resource items found
Configuration resource items operation, realize the replacing of resource items.In the operation of application program
During, client 200 sends solicited message and receives the operation of resource plug bag all
Influence will not be produced in itself on application program.And in the resource plug bag newly obtained
Resource items can be loaded immediately, and the behaviour of the configuration resource items performed in client 200
Change is realized when making.For example, when being rendered to some view, using resource plug
Picture file in bag, instead of original picture file for rendering, to be rendered
View rendered.
By taking Android system as an example, client 200 obtain and be loaded with resource plug bag it
Afterwards, it is not necessary to re-launching applications, it is only necessary to restart current Activity, you can real
The change of existing resource items.Wherein, the Activity is most base in Android components
This four big components (including Activity, Service, Content Provider,
One of Broadcast Receiver).The resource of correspondence Android system, is either preserved
Resources under assets catalogues, the resource being also stored under res catalogues all may be used
To be changed.The resource items in resource plug bag are loaded, not by original money
Source is covered, but the method for using the configuration resource items of Android system itself,
During the operation of the configuration resource items of execution, the resource items in resource plug bag are regard as quilt
The object of configuration.
Request sending module 105, for according to default tactful to the server 100
The solicited message for downloading resource plug bag is sent, so that the server 100 is according to institute
Solicited message down distributing resource plug-in unit bag is stated to the client 200.
Server 100 is inserted except active to the down distributing resource of client 200 being attached thereto
Beyond part bag, the solicited message that can be also sent according to client 200 is fed back, right
That answers issues corresponding resource plug bag.
In the present embodiment, client 200 sends the default strategy of solicited message and included
At least one of three kinds of modes below:
The request sending module 105 is according to default time interval to the server
100 send the solicited message;
The request sending module 105 is in application program launching to the server
100 send the solicited message;And
The request sending module 105 is not searched in the resource items searching modul 103
During to corresponding resource items of operation with the configuration resource items currently performed, to the clothes
Business device 100 sends the solicited message.
The request sending module 105 sends solicited message according to default time interval
In the way of asking resource plug bag, it can timely obtain newborn in server 100
Into resource plug bag.And the solicited message is sent in application program launching, can
To ensure that application program can configure newest resource items after opening.In addition, described
Resource items searching modul 103 does not find the operation of the configuration resource items with currently performing
The solicited message is sent during corresponding resource items, can be to not loading or loading mistake
The resource items lost are effectively supplemented.
By the sending method of above-mentioned several solicited messages, client 200 can be fast
Speed, the resource plug bag for obtaining server 100 in time, and carry out corresponding resource
Configuration.
In the present embodiment, solicited message can be directed to some specific resource plug
Bag makes requests on or asked the resource plug bag being currently newly generated.Service
Device 100 is received after solicited message, according to the content of solicited message to send solicited message
Client 200 send corresponding resource plug bag.Server 100 can also be to hair
The state of the client 200 of solicited message is sent to be judged, if warp-wise client
End 200 issued the corresponding resource plug bag of solicited message, then can not feed back,
Or the information of feedback repetitive requests.
Control instruction receiving module 106, sends for receiving the server 100
Resource items in the resource plug bag are carried out with the control instruction of configuration control.
The resource items searching modul 103 connects in the control instruction receiving module 106
Receive after the control instruction, obtained according to the operation of the configuration resource items currently performed
Search whether there are resource items corresponding with the operation in the resource items taken.
In some specific cases, after loading resource plug bag, client 200 is simultaneously
Do not perform the operation of resource change at once, but waiting for server 100 is sent further
Control instruction, according to the content of control instruction carry out resource change.
The control instruction that server 100 is sent can indicate that client 200 is opened at once
Begin to carry out the instruction of the operation of resource change or include instruction client 200
Perform the time and perform object relevant information instruction.
Client 200 performs corresponding operation according to the content of the control instruction received.
Being searched according to the operation of configuration resource items currently performed in the resource items of acquisition and
During the corresponding resource items of the operation, it is possible that finding multiple with currently performing
Configure the situation of the corresponding resource items of operation of resource items.Now, client 200
According to the relevant information for performing time and the object performed in control instruction, correspondence is used
The resource items that find complete the operations of the configuration resource items currently performed.By connecing
Control instruction is received, the operation that client 200 is changed to resource is more flexible.
To sum up, device for allocating resources 10 provided in an embodiment of the present invention can cause client
End 200 can be to applying journey by loading the resource plug bag obtained from server 100
The resource of sequence is modified, without reinstalling client installation kit, while effectively drop
The low development cost of developer.
Referring to Fig. 4, be present pre-ferred embodiments provide be applied to Fig. 3 shown in
Device for allocating resources 10 resource allocation method flow chart.Face will be to shown in Fig. 4
Idiographic flow be described in detail.
Step S401, solicited message is sent to server 100.
Client 200 sends the solicited message for downloading resource plug bag to server 100,
Sending the strategy of solicited message includes at least one of following three kinds of modes:
The request is sent according to default time interval to the server 100 to believe
Breath;In application program launching the solicited message is sent to the server 100;
When not finding the corresponding resource items of operation with the configuration resource items currently performed,
The solicited message is sent to the server 100.
By to server 100 send solicited message so that server 100 according to please
Ask information to make feedback, and then issue corresponding resource plug bag.
Step S402, the resource items including needing to change are obtained from the server 100
Resource plug bag.
After the down distributing resource plug-in unit bag of server 100, client 200 receives the resource
Plug-in unit bag is simultaneously preserved.
Step S403, is loaded to the resource plug bag, is obtained the resource and is inserted
Resource items in part bag.
In the present embodiment, the resource load-on module 102 is used to set by generation
The mode of the explorer of resource items in the resource plug bag is to resource plug bag
Loaded.After loading successfully, the explorer generated can be to resource plug
Resource items in bag are configured.
Step S404, receive that the server 100 sends to the resource plug bag
In resource items carry out configuration control control instruction.
Load after resource plug bag, client 200 is not to perform resource change at once
Operation, but waiting for server 100 sends further control instruction, according to control
The content of system instruction carries out resource change.The control instruction that server 100 is sent can be with
It is to indicate that client 200 proceeds by the instruction of the operation of resource change at once, also may be used
Be include indicate client 200 the execution time and perform object it is related believe
The instruction of breath.
Step S405, according to currently perform configuration resource items operation acquisition money
Search whether there are resource items corresponding with the operation in source item, if it is, performing
Step S406, if it is not, then performing step S401.
If there is the corresponding resource items of operation of the configuration resource items with currently performing,
Then illustrate that the corresponding resource items of the operation need replacing.If it does not exist, then explanation is needed
The resource items to be changed are not loaded successfully, it is necessary to send request letter to server 100
Breath, it is desirable to load the resource plug bag where the resource items.
Step S406, the configuration resource for completing currently to perform using the resource items found
The operation of item.
For the resource items for needing to change, current perform is completed with the resource items found
Configuration resource items operation, realize the replacing of resource items.
In the present embodiment, if finding multiple and configuration resource items that are currently performing
The corresponding resource items of operation.Execution time of the client 200 in control instruction
With the relevant information of the object of execution, complete to work as using the corresponding resource items found
The operation of the configuration resource items of preceding execution.By receiving control instruction, client 200
The operation changed to resource is more flexible.
The resource allocation method provided below by a specific example the present invention enters
Row is further described in detail.
For example, client 200 be provided with from server 100 download application program (such as
Browser), device for allocating resources 10 can be mounted to client 200 (such as intelligence
Mobile phone) browser part of functions module.When server 100 has clear for this
Look at device resource plug bag generation when, server 100 can actively it is clear to this is provided with
The client 200 of device of looking at issues the resource plug bag.Either server 100 is received
After the solicited message that some client 200 is sent, to the client for sending the solicited message
End 200 issues the resource plug bag.The Spring Festival arrives, and many application programs can be all in the spring
Its interactive interface is carried out during section to change skin, becomes the style for having red-letter day to celebrate atmosphere,
It is accomplished by carrying out audio of view, animation or broadcasting for showing on interactive interface etc.
Adjustment.Now, server 100 issue a picture for including red-letter day style and
The resource plug bag of other kinds resource items.Client 200 is obtained at server 100
Resource plug bag is obtained, resource plug bag is stored under predetermined directory, and to the resource
Plug-in unit bag is loaded.Then it is that generation one can set money by taking Android system as an example
The explorer of each resource items in the plug-in unit bag of source.In order to ensure that browser can be
Festive occasion in the Spring Festival, which normally completes, changes skin, and resource plug bag may be when being also less than in the Spring Festival
Just issue in advance.Client 200 is loaded after the resource plug bag, is not stood
Carve to perform and change the operation of skin, but the control instruction that waiting for server 100 is sent, clothes
The control instruction that business device 100 is sent to client 200 includes both sides information, one
Side is to perform the time for changing skin operation, is on the other hand the object for changing skin.In order to ensure
The variation of operation interface, the resource plug bag that server 100 is issued includes correspondence
The resource items of many set different skins.Control instruction can indicate client 200 at which
The individual time carries out changing skin using which set skin.Come interim when the Spring Festival, client 200
According to the instruction of control instruction, corresponding hold is selected from the resource items of resource plug bag
Row changes skin operation.During execution, some clients 200 may be due to some
Other factors cause the resource items indicated by some control instruction not load success, this
When the client 200 to server 100 send download resource plug bag solicited message,
Server 100 is again to the down distributing resource plug-in unit bag of client 200, to complete to change skin
Operation.Simultaneously as the resource items that loading resource plug bag is obtained do not cover original
The resource items come in the file of client 200.After the Spring Festival, client 200 can be with
Under the control for the control command that server 100 is sent, institute was replaced by before the Spring Festival once
The skin used.
In summary, device for allocating resources and resource allocation method of the invention,
Change the layout of the page in application program, the pattern of individual views or some view
During individual attribute, it is only necessary to related resource plug bag is obtained from server end, pass through
I.e. executable corresponding replacement after loading.Without repeating modification code, version need not be sent out
Originally under conditions of the resource file that client installation kit, need not be increased, correspondence is met
Enter the demand that Mobile state is changed with the resource of program, while also effectively reducing developer
Development cost.
In several embodiments provided herein, it should be understood that disclosed
Apparatus and method, can also be realized by another way.Device described above
Embodiment is only schematical, for example, the flow chart and block diagram in accompanying drawing are shown
According to the device of multiple embodiments of the present invention, method and computer program product can
Architectural framework, function and the operation that can be realized.At this point, in flow chart or block diagram
Each square frame can represent a part for a module, program segment or code, it is described
A part for module, program segment or code is comprising one or more defined for realizing
The executable instruction of logic function.It should also be noted that in some realizations as replacement
In mode, the function of being marked in square frame can also be with different from being marked in accompanying drawing
Order occurs.For example, two continuous square frames can essentially be performed substantially in parallel,
They can also be performed in the opposite order sometimes, and this is depending on involved function.
It is also noted that each square frame and block diagram in block diagram and/or flow chart and/
Or the combination of the square frame in flow chart, can be with function or action as defined in performing it is special
Hardware based system is realized, or can be referred to specialized hardware with computer
The combination of order is realized.
In addition, each functional module in each embodiment of the invention can be integrated in one
Rise and form an independent part or modules individualism, can also
Two or more modules are integrated to form an independent part.
If the function is realized using in the form of software function module and is used as independent production
Product are sold or in use, can be stored in a computer read/write memory medium.
Understood based on such, technical scheme is substantially in other words to prior art
The part contributed or the part of the technical scheme can be in the form of software products
Embody, the computer software product is stored in a storage medium, if including
Dry instruction to cause a computer equipment (can be personal computer, server,
Or the network equipment etc.) perform whole or the portion of each embodiment methods described of the invention
Step by step.And foregoing storage medium includes:USB flash disk, mobile hard disk, read-only storage
Device (ROM, Read-Only Memory), random access memory (RAM, Random
Access Memory), magnetic disc or CD etc. are various can be with Jie of store program codes
Matter.It should be noted that herein, such as first and second or the like relation
Term is used merely to distinguish an entity or operation with another entity or operation
Come, and not necessarily require or imply these entities or exist between operating any this
Actual relation or order.Moreover, term " comprising ", "comprising" or its is any
Other variants are intended to including for nonexcludability, so that including a series of key elements
Process, method, article or equipment not only include those key elements, but also including
Other key elements being not expressly set out, or also include for this process, method,
Article or the intrinsic key element of equipment.In the absence of more restrictions, by language
The key element that sentence "including a ..." is limited, it is not excluded that including the mistake of the key element
Also there is other identical element in journey, method, article or equipment.
The preferred embodiments of the present invention are the foregoing is only, this is not limited to
Invention, for those skilled in the art, the present invention can have it is various change and
Change.Within the spirit and principles of the invention, it is any modification for being made, equivalent
Replace, improve etc., it should be included in the scope of the protection.It should be noted that:
Similar label and letter represents similar terms in following accompanying drawing, therefore, once certain
One is defined in an accompanying drawing, then it need not be carried out in subsequent accompanying drawing
Further definition and explanation.
The foregoing is only a specific embodiment of the invention, but the protection of the present invention
Scope is not limited thereto, and any one skilled in the art is in the present invention
In the technical scope of exposure, change or replacement can be readily occurred in, should all be covered in this hair
Within bright protection domain.Therefore, protection scope of the present invention described should be wanted with right
The protection domain asked is defined.
Claims (14)
1. a kind of device for allocating resources, applied to the client being connected with a server communication
End, it is characterised in that the device for allocating resources includes:
Resource obtains module, for obtaining the money including needing to change from the server
The resource plug bag of source item;
Resource load-on module, for being loaded to the resource plug bag, obtains institute
State the resource items in resource plug bag;
Resource items searching modul, for the operation according to the configuration resource items currently performed
Search whether there are resource items corresponding with the operation in the resource items of acquisition;
Resource changes module, for completing what is currently performed using the resource items found
Configure the operation of resource items.
2. device for allocating resources according to claim 1, it is characterised in that institute
Stating device for allocating resources also includes request sending module,
Request sending module, under being sent according to default strategy to the server
The solicited message of resource plug bag is carried, so that the server is according to the solicited message
Down distributing resource plug-in unit bag is to the client.
3. device for allocating resources according to claim 2, it is characterised in that institute
Stating default strategy includes at least one of following three kinds of modes:
The request sending module is sent according to default time interval to the server
The solicited message;
The request sending module sends institute in application program launching to the server
State solicited message;
The request sending module the resource items searching modul do not find with currently
During the corresponding resource items of operation of the configuration resource items of execution, sent to the server
The solicited message.
4. device for allocating resources according to claim 1, it is characterised in that institute
Stating device for allocating resources also includes control instruction receiving module,
Control instruction receiving module, for receiving that the server sends to the money
Resource items in the plug-in unit bag of source carry out the control instruction of configuration control;
The resource items searching modul receives described in the control instruction receiving module
After control instruction, according to currently perform configuration resource items operation acquisition resource
Search whether there are resource items corresponding with the operation in.
5. device for allocating resources according to claim 4, it is characterised in that when
The resource items searching modul finds multiple behaviour with configuration resource items that are currently performing
When making corresponding resource items, the resource changes module according in the control instruction
Hold the behaviour of the configuration resource items currently performed using the corresponding resource items completion found
Make.
6. device for allocating resources according to claim 1, it is characterised in that institute
State resource load-on module is used to set the resource items in the resource plug bag by generating
The mode of explorer resource plug bag is loaded.
7. device for allocating resources according to claim 1, it is characterised in that institute
Stating the operation of the configuration resource items currently performed includes the Rendering operations to view,
The resource items searching modul according to current view to be rendered acquisition resource
Search whether exist and corresponding resource items in;
The resource change module is completed to current to be rendered using the resource items found
View Rendering operations.
8. a kind of resource allocation method, applied to the client being connected with a server communication
End, it is characterised in that the resource allocation method includes:
The resource plug bag of the resource items including needing to change is obtained from the server;
The resource plug bag is loaded, the money in the resource plug bag is obtained
Source item;
Searched according to the operation of the configuration resource items currently performed in the resource items of acquisition
With the presence or absence of resource items corresponding with the operation;
The operation for the configuration resource items for completing currently to perform using the resource items found.
9. resource allocation method according to claim 8, it is characterised in that institute
Stating resource allocation method also includes:
The request for downloading resource plug bag is sent to the server according to default strategy
Information, so that the server is according to the solicited message down distributing resource plug-in unit bag to institute
State client.
10. resource allocation method according to claim 9, it is characterised in that institute
Stating default strategy includes at least one of following three kinds of modes:
According to default time interval the solicited message is sent to the server;
In application program launching the solicited message is sent to the server;
The corresponding resource items of operation of the configuration resource items with currently performing are not being found
When, send the solicited message to the server.
11. resource allocation method according to claim 8, it is characterised in that institute
Stating resource allocation method also includes:
Receive being carried out to the resource items in the resource plug bag for the server transmission
Configure the control instruction of control;
After the control instruction is received, the configuration that the basis is currently performed is performed
The operation of resource items is searched whether in the resource items of acquisition in the presence of corresponding with the operation
The step of resource.
12. resource allocation method according to claim 11, it is characterised in that
When finding multiple corresponding resource items of operation with configuration resource items that are currently performing
When, completed according to the content of the control instruction using the corresponding resource items found
The operation of the configuration resource items currently performed.
13. resource allocation method according to claim 8, it is characterised in that logical
Cross the side that generation is used to set the explorer of the resource items in the resource plug bag
Formula is loaded to resource plug bag.
14. resource allocation method according to claim 8, it is characterised in that institute
Stating the operation of the configuration resource items currently performed includes the Rendering operations to view, described
Method includes:
According to current view to be rendered search whether to exist in the resource items of acquisition with
Corresponding resource items;
Complete to render behaviour to current view to be rendered using the resource items found
Make.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610134153.4A CN107179943A (en) | 2016-03-09 | 2016-03-09 | A kind of device for allocating resources and resource allocation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610134153.4A CN107179943A (en) | 2016-03-09 | 2016-03-09 | A kind of device for allocating resources and resource allocation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107179943A true CN107179943A (en) | 2017-09-19 |
Family
ID=59829637
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610134153.4A Pending CN107179943A (en) | 2016-03-09 | 2016-03-09 | A kind of device for allocating resources and resource allocation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107179943A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109213536A (en) * | 2018-08-13 | 2019-01-15 | 阿里巴巴集团控股有限公司 | Resource exhibition method, resource show configuration method, device and the equipment of class control |
CN111565211A (en) * | 2020-01-14 | 2020-08-21 | 西安奥卡云数据科技有限公司 | CDN configuration distribution network system |
CN112015482A (en) * | 2020-07-20 | 2020-12-01 | 北京达佳互联信息技术有限公司 | Page loading method and device and server |
CN112740714A (en) * | 2018-09-11 | 2021-04-30 | 公共电视公司 | Techniques to configure and manage user interfaces for content guides for multiple device types |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2007101734A1 (en) * | 2006-01-30 | 2007-09-13 | International Business Machines Corporation | Plug-in update and management |
CN102707977A (en) * | 2012-05-17 | 2012-10-03 | 江苏中科梦兰电子科技有限公司 | Increment upgrading method based on Android application software |
-
2016
- 2016-03-09 CN CN201610134153.4A patent/CN107179943A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2007101734A1 (en) * | 2006-01-30 | 2007-09-13 | International Business Machines Corporation | Plug-in update and management |
CN102707977A (en) * | 2012-05-17 | 2012-10-03 | 江苏中科梦兰电子科技有限公司 | Increment upgrading method based on Android application software |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109213536A (en) * | 2018-08-13 | 2019-01-15 | 阿里巴巴集团控股有限公司 | Resource exhibition method, resource show configuration method, device and the equipment of class control |
CN112740714A (en) * | 2018-09-11 | 2021-04-30 | 公共电视公司 | Techniques to configure and manage user interfaces for content guides for multiple device types |
CN111565211A (en) * | 2020-01-14 | 2020-08-21 | 西安奥卡云数据科技有限公司 | CDN configuration distribution network system |
CN111565211B (en) * | 2020-01-14 | 2023-05-23 | 西安奥卡云数据科技有限公司 | CDN configuration distribution network system |
CN112015482A (en) * | 2020-07-20 | 2020-12-01 | 北京达佳互联信息技术有限公司 | Page loading method and device and server |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8620998B2 (en) | Mobile application deployment for distributed computing environments | |
CN107179943A (en) | A kind of device for allocating resources and resource allocation method | |
CN105700925B (en) | A kind of interface implementing method and device of APP | |
CN105787077A (en) | Data synchronizing method and device | |
CN114244717B (en) | Configuration method and device of virtual network card resources, computer equipment and medium | |
CN109522068A (en) | The edit methods of the methods of exhibiting and system of the page, page data | |
CN108279882B (en) | Framework generation method, device, equipment and computer readable medium | |
CN103577207A (en) | Loading method and loading device for interface components in custom interface system | |
CN106961454A (en) | Document down loading method, device and terminal device | |
CN105786606A (en) | Data transferring method and system for intelligent terminals | |
CN106034247A (en) | Configuration method and apparatus for smart television application | |
CN108600282A (en) | Micro services dissemination method, device, storage medium and computer equipment | |
CN108733370B (en) | Stylized display method, device, terminal and storage medium of native APP | |
CN114612279A (en) | Watermark adding method and device | |
CN110708423A (en) | Message content display method and device and storage medium | |
CN105700886B (en) | The display methods and terminal of plug-in interface | |
CN106506163B (en) | ROM packet processing method and device | |
CN108052401A (en) | System property monitor method, terminal device and computer readable storage medium | |
CN111367561A (en) | Software program remote development method and device | |
CN110780864A (en) | Control method and device for class method replacement, storage medium and electronic equipment | |
CN110347468A (en) | Textures switching method, textures switching device and electronic equipment | |
CN106155722A (en) | A kind of software method for updating pages and terminal | |
CN108614844A (en) | Multimedia file producting method and device | |
CN113902483A (en) | Advertisement putting method and device, electronic equipment and storage medium | |
CN113467776A (en) | Access method and device of equipment, storage medium and electronic device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20200611 Address after: 310052 room 508, floor 5, building 4, No. 699, Wangshang Road, Changhe street, Binjiang District, Hangzhou City, Zhejiang Province Applicant after: Alibaba (China) Co.,Ltd. Address before: 510627 Guangdong city of Guangzhou province Whampoa Tianhe District Road No. 163 Xiping Yun Lu Yun Ping square B radio tower 15 layer self unit 02 Applicant before: GUANGZHOU UC NETWORK TECHNOLOGY Co.,Ltd. |
|
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170919 |