CN107165671A - A kind of tailing-filled overall height dehydration barricade - Google Patents
A kind of tailing-filled overall height dehydration barricade Download PDFInfo
- Publication number
- CN107165671A CN107165671A CN201710569969.4A CN201710569969A CN107165671A CN 107165671 A CN107165671 A CN 107165671A CN 201710569969 A CN201710569969 A CN 201710569969A CN 107165671 A CN107165671 A CN 107165671A
- Authority
- CN
- China
- Prior art keywords
- overall height
- dehydration
- barricade
- tailing
- filled
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000018044 dehydration Effects 0.000 title claims abstract description 37
- 238000006297 dehydration reaction Methods 0.000 title claims abstract description 37
- 239000010902 straw Substances 0.000 claims abstract description 5
- 238000005553 drilling Methods 0.000 claims abstract description 4
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 3
- 239000010959 steel Substances 0.000 claims abstract description 3
- 238000000605 extraction Methods 0.000 claims description 3
- 239000004744 fabric Substances 0.000 claims 1
- 239000007787 solid Substances 0.000 claims 1
- 239000002184 metal Substances 0.000 abstract description 6
- 238000010276 construction Methods 0.000 abstract description 4
- 239000000463 material Substances 0.000 abstract description 2
- 238000001914 filtration Methods 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/02—Supporting means, e.g. shuttering, for filling-up materials
- E21F15/04—Stowing mats; Goaf wire netting; Partition walls
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
The invention discloses a kind of tailing-filled overall height dehydration barricade, belong to metal mine technical field, overall height dehydration window is disposed with the middle part of rigid concrete wall, both are closely coupled integral in construction, there are horizontal crossbeam and vertical column in concrete wall, crossbeam and column can be processed by discarded rail or I-steel, and crossbeam and column are welded with anchor pole, and anchor pole is tightly fastened by drilling with palisades.Overall height dehydration window is made up of filtering materials such as wire netting, linen, straw curtains, reasonable Arrangement, convenient dehydration.The present invention can solve metal mine during tailing-filled, and barricade bears pressure and is difficult to estimate, and the problem of the dehydration difficulty of dead zone.Construction is simple, reliability is high, wide application, and the disadvantage present in traditional two kinds of barricades is overcome, it is that metal mine is tailing-filled there is provided a kind of simple and easy to do, safe and reliable overall height dehydration barricade for having rigid retaining walls robustness and flexible retaining wall dewatering concurrently.
Description
Technical field
The invention belongs to metal mine technical field, and in particular to a kind of tailing-filled overall height dehydration barricade.
Background technology
At present, the tailing-filled multi-purpose filling counterfort enclosed empty regions in mine, filling counterfort is broadly divided into two classes, rigid retaining walls and
Flexible retaining wall.Rigid retaining walls intensity is reached, situations such as be not in compression damage, but can not realize the dehydration work of dead zone tailings
Make;Flexible retaining wall can realize that tunneling boring is dehydrated, but its insufficient strength, because unpredictable filling mortar pressure usually destroys by rush of water
The serious problems such as leakage.How in the case where ensureing filling counterfort strength conditions, it is always mining production face to realize dead zone tailings dehydration
The huge difficult problem faced.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of tailing-filled overall height dehydration barricade, existed with solving metal mine
During tailing-filled, barricade bears pressure and is difficult to estimate, and the problem of the dehydration difficulty of dead zone.
The technical solution of the present invention is as follows:
A kind of tailing-filled overall height dehydration barricade, including column 1, anchor pole 2, overall height dehydration window 4, crossbeam 5, concrete wall
6;At the middle part of concrete wall 6, being disposed with overall height dehydration window 4, concrete wall 6 has two laterally positioned crossbeams 5 and perpendicular
To the two root posts 1 of placement, crossbeam 5 and column 1 are arranged in well word structure, and the two ends of crossbeam 5 and the two ends of column 1 are and anchor pole
2 welding, anchor pole 2 is tightly fastened by drilling with palisades 3, will not loosen extraction.
Further, described crossbeam 5 and column 1 are processed by discarded rail or I-steel.
Further, described overall height dehydration window 4 links into an integrated entity with concrete wall 6, seamless each other, will not
Situations such as there is spillage.
Further, described overall height dehydration window 4 height is filling counterfort overall height, and width can suitably be adjusted according to barricade size
It is whole, generally 1/10th of barricade width.
Further, described overall height dehydration window 4 is followed successively by wire netting 7, linen 8 and straw curtain 9 from outside to inside,
Linen also can with other water penetrations preferably, intensity meet require material replace.
Compared with prior art, advantages of the present invention is as follows:
Present invention construction is simple, reliability is high, wide application, and overcomes the disadvantage present in traditional two kinds of barricades, is
Metal mine is tailing-filled to have rigid retaining walls robustness and simple and easy to do, the safety of flexible retaining wall dewatering concurrently there is provided a kind of
Reliable overall height dehydration barricade.
Brief description of the drawings
Fig. 1 is dehydrated the positive structure diagram of barricade for the overall height of the present invention;
Fig. 2 is dehydrated the side structure schematic view of barricade for the overall height of the present invention;
Fig. 3 is dehydrated the overlooking the structure diagram of barricade for the overall height of the present invention;
Fig. 4 is dehydrated the partial enlarged drawing of window for the overall height of the present invention;
In figure:Column 1, anchor pole 2, palisades 3, overall height dehydration window 4, crossbeam 5, concrete wall 6, wire netting 7, linen 8,
Straw curtain 9.
Embodiment
The present invention is further described below in conjunction with the accompanying drawings.
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of tailing-filled overall height dehydration barricade, including column 1, anchor pole 2, overall height dehydration window
4th, crossbeam 5, concrete wall 6.At the rigid middle part of concrete wall 6, being disposed with overall height dehydration window 4, concrete wall 6 has
Two laterally positioned crossbeams 5 and the two root posts 1 vertically disposed, crossbeam 5 and column 1 arrange in well word structure, crossbeam 5 and vertical
Post 1 can be processed by discarded rail, and crossbeam 5 and column 1 are welded with anchor pole 2, and anchor pole 2 is close with palisades 3 by drilling
It is fixed, extraction will not be loosened.
Wherein, described overall height dehydration window 4 links into an integrated entity with concrete wall 6, seamless each other, is not in
Situations such as spillage.Described overall height dehydration window 4 is highly filling counterfort overall height, and width can suitably be adjusted according to barricade size, one
As be barricade width 1/10th.
Wherein, overall height dehydration window 4 includes described wire netting 7, linen 8, straw curtain 9 and part composition, during construction
Order it must arrange from outside to inside successively as described above.
Claims (5)
1. a kind of tailing-filled overall height dehydration barricade, it is characterised in that including column (1), anchor pole (2), overall height dehydration window (4),
Crossbeam (5), concrete wall (6);In the middle part of concrete wall (6), it is disposed with overall height dehydration window (4), concrete wall (6)
There are two laterally positioned crossbeams (5) and the two root posts (1) vertically disposed, crossbeam (5) and column (1) are in well word structure cloth
Put, the two ends of crossbeam (5) and the two ends of column (1) are welded with anchor pole (2), anchor pole (2) is closely solid with palisades (3) by drilling
It is fixed, extraction will not be loosened.
2. a kind of tailing-filled overall height dehydration barricade as claimed in claim 1, it is characterised in that:Described crossbeam (5) and vertical
Post (1) is processed by discarded rail or I-steel.
3. a kind of tailing-filled overall height dehydration barricade as claimed in claim 1, it is characterised in that:Described overall height dehydration window
(4) linked into an integrated entity with concrete wall (6), it is seamless each other, be not in spillage situation.
4. a kind of tailing-filled overall height dehydration barricade as claimed in claim 1, it is characterised in that:Described overall height dehydration window
(4) height is filling counterfort overall height, and width can be adjusted according to barricade size.
5. a kind of tailing-filled overall height dehydration barricade as claimed in claim 1, it is characterised in that described overall height dehydration window
(4) wire netting (7), linen (8) and straw curtain (9) are followed successively by from outside to inside.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710569969.4A CN107165671A (en) | 2017-07-13 | 2017-07-13 | A kind of tailing-filled overall height dehydration barricade |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710569969.4A CN107165671A (en) | 2017-07-13 | 2017-07-13 | A kind of tailing-filled overall height dehydration barricade |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107165671A true CN107165671A (en) | 2017-09-15 |
Family
ID=59824091
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710569969.4A Pending CN107165671A (en) | 2017-07-13 | 2017-07-13 | A kind of tailing-filled overall height dehydration barricade |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107165671A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107882556A (en) * | 2017-11-19 | 2018-04-06 | 武汉木兰博耀赛车文化有限公司 | A kind of administering method of high-risk mine tailing |
CN108104870A (en) * | 2017-12-15 | 2018-06-01 | 山东河西黄金集团有限公司 | A kind of mine route fill method |
CN109356644A (en) * | 2018-12-25 | 2019-02-19 | 江苏师范大学 | A kind of paste body filling wall system and its installation method |
CN111894669A (en) * | 2020-07-09 | 2020-11-06 | 中南大学 | Novel purification barrier structure and rapid construction method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202431302U (en) * | 2011-12-22 | 2012-09-12 | 铜陵有色金属集团控股有限公司 | Filling retaining wall device for high large-scale mining stope in roadway |
CN103696803A (en) * | 2013-12-06 | 2014-04-02 | 西北矿冶研究院 | Be used for mine underground tailings cemented filling barricade device |
CN203702245U (en) * | 2014-01-27 | 2014-07-09 | 长沙矿山研究院有限责任公司 | Water draining pressure relief filling retaining wall structure |
CN205422813U (en) * | 2016-03-07 | 2016-08-03 | 马钢(集团)控股有限公司 | Detachable filling and retaining wall |
CN205532706U (en) * | 2016-01-27 | 2016-08-31 | 金诚信矿业管理股份有限公司 | A barricade device that is used for shutoff admission passage to fill |
CN106545361A (en) * | 2016-11-24 | 2017-03-29 | 贵州开磷集团股份有限公司 | A kind of mine down-hole high permeability filling counterfort and its construction method |
CN106894838A (en) * | 2017-02-21 | 2017-06-27 | 长沙矿山研究院有限责任公司 | Large area insertion dead zone bag type partition substep filling administering method |
CN106917635A (en) * | 2017-04-21 | 2017-07-04 | 中国矿业大学(北京) | A kind of goaf filling dewatering system and its application method |
-
2017
- 2017-07-13 CN CN201710569969.4A patent/CN107165671A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202431302U (en) * | 2011-12-22 | 2012-09-12 | 铜陵有色金属集团控股有限公司 | Filling retaining wall device for high large-scale mining stope in roadway |
CN103696803A (en) * | 2013-12-06 | 2014-04-02 | 西北矿冶研究院 | Be used for mine underground tailings cemented filling barricade device |
CN203702245U (en) * | 2014-01-27 | 2014-07-09 | 长沙矿山研究院有限责任公司 | Water draining pressure relief filling retaining wall structure |
CN205532706U (en) * | 2016-01-27 | 2016-08-31 | 金诚信矿业管理股份有限公司 | A barricade device that is used for shutoff admission passage to fill |
CN205422813U (en) * | 2016-03-07 | 2016-08-03 | 马钢(集团)控股有限公司 | Detachable filling and retaining wall |
CN106545361A (en) * | 2016-11-24 | 2017-03-29 | 贵州开磷集团股份有限公司 | A kind of mine down-hole high permeability filling counterfort and its construction method |
CN106894838A (en) * | 2017-02-21 | 2017-06-27 | 长沙矿山研究院有限责任公司 | Large area insertion dead zone bag type partition substep filling administering method |
CN106917635A (en) * | 2017-04-21 | 2017-07-04 | 中国矿业大学(北京) | A kind of goaf filling dewatering system and its application method |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107882556A (en) * | 2017-11-19 | 2018-04-06 | 武汉木兰博耀赛车文化有限公司 | A kind of administering method of high-risk mine tailing |
CN108104870A (en) * | 2017-12-15 | 2018-06-01 | 山东河西黄金集团有限公司 | A kind of mine route fill method |
CN109356644A (en) * | 2018-12-25 | 2019-02-19 | 江苏师范大学 | A kind of paste body filling wall system and its installation method |
CN109356644B (en) * | 2018-12-25 | 2021-03-19 | 江苏师范大学 | Paste filling retaining wall system and mounting method thereof |
CN111894669A (en) * | 2020-07-09 | 2020-11-06 | 中南大学 | Novel purification barrier structure and rapid construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107165671A (en) | A kind of tailing-filled overall height dehydration barricade | |
CN208294566U (en) | A kind of high concentration tailing cemented filling metal mesh structure barricade | |
CN104481568B (en) | A kind of fully mechanized coal face gob side entry retaining technique and method of ventilation | |
CN102979535B (en) | Draining type section of jurisdiction is used in a kind of tunnel lining | |
CN103670470B (en) | Full coal roadway safe and speedy drivage supporting method | |
US11021954B2 (en) | Method of recovering room-and-pillar coal pillar by using external replacement supports | |
CN110130978B (en) | Method for plugging broken coal side of thick coal seam in broken area of filling and re-mining small kiln | |
CN106089207A (en) | Super high seam work surface gob side entry driving thin coal pillar stays equipment, method | |
CN103470289A (en) | Contiguous coal seam mining support method | |
CN206205903U (en) | A kind of base plate release ruggedized construction of control deep tunnel bottom distension | |
CN107956481B (en) | Supporting device for gob-side entry retaining of ultra-high roadway | |
CN206092056U (en) | Steel structure for circulated profit | |
CN207944987U (en) | A kind of high concentration tailing cemented filling hollow block construction barricade | |
CN103821559A (en) | Mould bag type rapidly-formed hermetic retaining wall | |
CN203742020U (en) | Novel frame wall structure | |
CN116044398A (en) | Mining method for island working face of near-horizontal coal seam of rock burst mine | |
CN214366192U (en) | Mine tunnel roof infiltration drainage device | |
CN205532706U (en) | A barricade device that is used for shutoff admission passage to fill | |
CN203742021U (en) | Novel frame wall structure with door opening or window opening | |
CN104141286A (en) | Construction adit blocking structure | |
CN202991057U (en) | Pipe piece for a water release type tunnel lining | |
CN102086771A (en) | Filling template bracket | |
CN112855211B (en) | Supporting and reinforcing device and method for unstable stope in mine | |
CN106481358A (en) | A kind of board wall telescopic column of mine filling recoverable | |
CN114233379B (en) | Large-mining-height gob-side entry retaining roadside filling structure and filling body construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170915 |