CN107165181A - It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization - Google Patents

It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization Download PDF

Info

Publication number
CN107165181A
CN107165181A CN201710559904.1A CN201710559904A CN107165181A CN 107165181 A CN107165181 A CN 107165181A CN 201710559904 A CN201710559904 A CN 201710559904A CN 107165181 A CN107165181 A CN 107165181A
Authority
CN
China
Prior art keywords
foundation pit
dewatering well
layer
filter
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710559904.1A
Other languages
Chinese (zh)
Inventor
成晓青
刘金山
孙建平
王旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Tunnel Engineering Co Ltd
Original Assignee
CCCC Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Tunnel Engineering Co Ltd filed Critical CCCC Tunnel Engineering Co Ltd
Priority to CN201710559904.1A priority Critical patent/CN107165181A/en
Publication of CN107165181A publication Critical patent/CN107165181A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明公开了一种具有监测减压作用的地铁基坑降水井,包括上层的给水层和下层的滤水层两部分,井内设置钢筋笼由上至下贯穿给水层和滤水层;给水层在钢筋笼内部设置有钢管,在钢筋笼外填充粘土;滤水层在钢筋笼内部设置有钢筋滤水管,在钢筋笼外部设置有双层尼龙布并填充有滤料。本发明降水井装置不仅实现了地下水变化情况的实时监测,同时对基坑开挖过程中坑内回灌用水等应急措施提供了保障,避免造成基坑开挖过程中的隆起破坏,进而减少周边地面、交通和建筑物等的沉降影响,保护了周围环境的安全,避免了不必要的损失。

The invention discloses a subway foundation pit dewatering well with the function of monitoring decompression, which comprises two parts, an upper water supply layer and a lower water filtration layer, and a steel cage is arranged in the well to penetrate the water supply layer and the water filtration layer from top to bottom; the water supply layer A steel pipe is arranged inside the reinforcement cage, and clay is filled outside the reinforcement cage; the water filter layer is provided with a reinforcement water filter pipe inside the reinforcement cage, and double-layer nylon cloth is arranged outside the reinforcement cage and filled with filter material. The dewatering well device of the present invention not only realizes the real-time monitoring of groundwater changes, but also provides protection for emergency measures such as water recharge in the pit during the excavation of the foundation pit, avoiding uplift damage during the excavation of the foundation pit, and reducing the surrounding ground. , traffic and buildings, etc., to protect the safety of the surrounding environment and avoid unnecessary losses.

Description

一种具有监测减压作用的地铁基坑降水井A subway foundation pit dewatering well with monitoring and decompression function

技术领域technical field

本发明涉及地铁基坑开挖中地下水安全领域,尤其涉及一种高承压水深大基坑开挖过程中地下水应急监测的降水井装置,具体为一种具有监测减压作用的地铁基坑降水井,用于探明地下水位变化情况、推演基坑开挖稳定性等。The invention relates to the field of groundwater safety in the excavation of subway foundation pits, in particular to a dewatering well device for emergency monitoring of groundwater during the excavation of large foundation pits with high pressure water depth, in particular to a dewatering well device for subway foundation pits with the function of monitoring decompression Wells are used to detect changes in groundwater levels and deduce the stability of foundation pit excavation.

背景技术Background technique

目前,对于具有高承压水的深大基坑,常规采取的措施主要是在开挖范围内施作降水井,基坑开挖前进行地下水抽排加以解决。此种方法存在浪费大量地下水资源的缺点,尤其对于以北京为代表的北方缺水城市,具有很大的制约。At present, for deep and large foundation pits with highly confined water, the conventional measures are mainly to construct dewatering wells within the excavation range, and to pump groundwater before excavation of the foundation pit to solve the problem. This method has the disadvantage of wasting a large amount of groundwater resources, especially for water-scarce cities in the north represented by Beijing, which has great constraints.

鉴于此,在不降水的情况下采用一种基坑带水开挖的方法应运而生,施工中对地下水位的实时监测、平衡基坑内外水位高差及紧急情况下减压回灌等成为保证开挖过程中衡量基坑稳定性的关键。这是新的地铁基坑开挖工艺施工中产生的新问题,寻找一种工期短、功能全面、成本低、安全可靠的处理方法,尤其对于高承压水地层,成为地铁基坑带水开挖过程中迫切需要解决的问题。In view of this, a method of excavating a foundation pit with water under the condition of no precipitation came into being. The real-time monitoring of the groundwater level during construction, the balance of the water level difference between the inside and outside of the foundation pit, and decompression and recharge in emergency situations have become It is the key to measure the stability of the foundation pit during the excavation process. This is a new problem arising in the construction of the new subway foundation pit excavation process. It is necessary to find a treatment method with short construction period, comprehensive functions, low cost, and safety and reliability. Problems that urgently need to be solved during the excavation process.

发明内容Contents of the invention

本发明目的在于克服现有技术中的不足之处,提供了一种具有监测减压作用的地铁基坑降水井。本发明的目的是通过以下技术方案实现的:The purpose of the invention is to overcome the deficiencies in the prior art, and provide a subway foundation pit dewatering well with the function of monitoring decompression. The purpose of the present invention is achieved through the following technical solutions:

一种具有监测减压作用的地铁基坑降水井,包括上层的给水层和下层的滤水层两部分,井内设置钢筋笼由上至下贯穿给水层和滤水层;所述给水层在钢筋笼内部设置有钢管,在钢筋笼外填充粘土;所述滤水层在钢筋笼内部设置有钢筋滤水管,在钢筋笼外部设置有双层尼龙布并填充有滤料。A subway foundation pit dewatering well with the function of monitoring decompression, comprising two parts: an upper water supply layer and a lower water filter layer, and a steel cage is arranged in the well to run through the water supply layer and the water filter layer from top to bottom; A steel pipe is arranged inside the cage, and clay is filled outside the steel cage; the water filter layer is provided with a steel filter pipe inside the steel cage, and a double-layer nylon cloth is arranged outside the steel cage and filled with filter material.

进一步的,所述降水井设置于地下水水位线以上。Further, the dewatering well is set above the groundwater level.

进一步的,降水井的底端距离地下水水位线8.11~11.51m。Further, the bottom of the precipitation well is 8.11~11.51m away from the groundwater level.

进一步的,降水井的底端距离地下水水位线0.01~8.11m。Further, the bottom of the precipitation well is 0.01-8.11m away from the groundwater level.

进一步的,所述给水层的钢管采用Φ480型,钢筋笼外填充的粘土封闭并捣实。Further, the steel pipe of the water supply layer adopts Φ480 type, and the clay filled outside the reinforcement cage is closed and compacted.

进一步的,所述滤水层的钢筋滤水管采用Φ508型,双层尼龙布均为40目。Further, the reinforced water filter pipe of the water filter layer adopts a Φ508 type, and the double-layer nylon cloth is 40 mesh.

进一步的,所述钢筋笼包括纵向的主筋和横向的加强筋,加强筋导向环焊在主筋上,所述主筋采用9Φ14型,所述加强筋采用Φ12@250型。Further, the reinforcement cage includes longitudinal main ribs and transverse reinforcing ribs, the guiding ring of the reinforcing ribs is welded on the main ribs, the main ribs are of 9Φ14 type, and the reinforcing ribs are of Φ12@250 type.

进一步的,位于过滤层的钢筋笼外侧捆绑竹条,竹条分布于每两个主筋中间。Further, bamboo strips are bound outside the reinforcement cage on the filter layer, and the bamboo strips are distributed between every two main reinforcements.

进一步的,过滤层的钢筋笼和双层尼龙布之间设置有滤网,双层尼龙布缠绕在滤网外,滤料填充在双层尼龙网外部。Further, a filter screen is arranged between the reinforcement cage of the filter layer and the double-layer nylon cloth, the double-layer nylon cloth is wound outside the filter screen, and the filter material is filled outside the double-layer nylon cloth.

进一步的,所述滤料为砂石滤料,砂石为级配砂石,级配的质量比例为:7mm~12mm的碎石:3mm~7mm的碎石:砂子=45:25:30。Further, the filter material is sand and gravel filter material, and the sand and gravel are graded gravel, and the mass ratio of the gradation is: gravel of 7 mm to 12 mm: gravel of 3 mm to 7 mm: sand = 45:25:30.

本发明的有益效果:Beneficial effects of the present invention:

本发明的具有监测减压作用的地铁基坑降水井,采用该降水井装置不仅实现了地下水变化情况的实时监测,同时对基坑开挖过程中坑内回灌用水等应急措施提供了保障,避免造成基坑开挖过程中的隆起破坏,进而减少周边地面、交通和建筑物等的沉降影响,保护了周围环境的安全,避免了不必要的损失。The subway foundation pit dewatering well with monitoring and decompression function of the present invention not only realizes real-time monitoring of groundwater changes by using the dewatering well device, but also provides guarantee for emergency measures such as water recharge in the pit during the excavation process of the foundation pit, avoiding It causes the uplift damage during the excavation of the foundation pit, thereby reducing the settlement impact of the surrounding ground, traffic and buildings, protecting the safety of the surrounding environment and avoiding unnecessary losses.

下面结合附图和实施例对发明作一详细描述。The invention will be described in detail below in conjunction with the accompanying drawings and embodiments.

附图说明Description of drawings

图1为本发明地铁基坑降水井结构示意图(穿透隔水层);Fig. 1 is a schematic diagram of the structure of the subway foundation pit dewatering well of the present invention (penetrating the water-resisting layer);

图2为本发明地铁基坑降水井结构示意图(不穿透隔水层);Fig. 2 is a schematic diagram of the structure of the subway foundation pit dewatering well of the present invention (does not penetrate the water-resistant layer);

图3 为本发明中的钢筋笼结构示意图;Fig. 3 is the structural representation of reinforcement cage among the present invention;

图4为图3的A-A剖视图;Fig. 4 is A-A sectional view of Fig. 3;

图5为图3的B-B剖视图。Fig. 5 is a B-B sectional view of Fig. 3 .

符号说明:Symbol Description:

1.钢管 ;2.粘土 ;3.钢筋滤水管;4.双层尼龙布及滤料 ;5.隔水层;6.钢筋笼;7.加强筋;8.主筋。1. Steel pipe; 2. Clay; 3. Reinforced water filter pipe; 4. Double-layer nylon cloth and filter material;

地层土质分布:Ⅰ.房渣土;Ⅱ.粉砂-细砂 ;Ⅲ. 粉质粘土;Ⅳ.卵石 。Soil distribution in strata: Ⅰ. House dregs; Ⅱ. Silt-fine sand; Ⅲ. Silty clay; Ⅳ. Pebbles.

具体实施方式detailed description

实施例1Example 1

如图1所示,一种具有监测减压作用的地铁基坑降水井,包括上层的给水层和下层的滤水层两部分,井内设置钢筋笼6由上至下贯穿给水层和滤水层;所述给水层在钢筋笼6内部设置有钢管1,在钢筋笼外填充粘土2;所述滤水层在钢筋笼6内部设置有钢筋滤水管3,在钢筋笼6外部设置有双层尼龙布及滤料4。As shown in Figure 1, a subway foundation pit dewatering well with monitoring and decompression functions includes two parts: the upper water supply layer and the lower water filter layer, and a steel cage 6 is installed in the well to run through the water supply layer and the water filter layer from top to bottom ; The water supply layer is provided with a steel pipe 1 inside the reinforcement cage 6, and clay 2 is filled outside the reinforcement cage; Cloth and filter material 4.

所述降水井设置于地下水水位线以上,降水井的底端距离地下水水位线8.11~11.51m;降水井的底端穿透地下隔水层5(距地下水水位线8.11~11.51m处)。The dewatering well is set above the groundwater level, and the bottom of the dewatering well is 8.11-11.51m away from the groundwater level; the bottom of the dewatering well penetrates the underground aquifer 5 (8.11-11.51m away from the groundwater level).

本实施例中:In this example:

给水层的钢管1采用Φ480型,钢筋笼6外填充的粘土2封闭并捣实。滤水层的钢筋滤水管3采用Φ508型,双层尼龙布均为40目。The steel pipe 1 of the water supply layer adopts Φ480 type, and the clay 2 filled outside the steel cage 6 is closed and compacted. The steel bar filter pipe 3 of water filter layer adopts Φ 508 type, and double-layer nylon cloth is 40 orders.

如图3~5所示,钢筋笼6包括纵向的主筋8和横向的加强筋7,加强筋7导向环焊在主筋8上,所述主筋采用9Φ14型,所述加强筋采用Φ12@250型。As shown in Figures 3 to 5, the reinforcement cage 6 includes longitudinal main ribs 8 and transverse reinforcing ribs 7, the guiding ring of the reinforcing ribs 7 is welded on the main ribs 8, the main ribs are 9Φ14 type, and the reinforcing ribs are Φ12@250 type .

位于过滤层的钢筋笼外侧捆绑竹条,竹条分布于每两个主筋中间。竹条采用绑丝固定于加强筋上。钢筋笼满布竹条后,外侧安装一根Φ50pvc花管,与钢筋笼固定牢固。过滤层的钢筋笼和双层尼龙布之间设置有滤网,双层尼龙布缠绕在滤网外,滤料填充在双层尼龙网外部。Bamboo strips are bound outside the reinforcement cage on the filter layer, and the bamboo strips are distributed between every two main reinforcements. The bamboo strips are fixed on the reinforcing ribs by binding wires. After the reinforcement cage is covered with bamboo strips, a Φ50 pvc flower tube is installed on the outside, which is firmly fixed with the reinforcement cage. A filter mesh is arranged between the reinforcement cage of the filter layer and the double-layer nylon cloth, the double-layer nylon cloth is wound outside the filter mesh, and the filter material is filled outside the double-layer nylon mesh.

所述滤料为砂石滤料,砂石为级配砂石,级配的质量比例为:7mm~12mm的碎石:3mm~7mm的碎石:砂子=45:25:30。滤料应为圆形或亚圆形,禁止使用片状、针状的碎石,砾料含泥量(包括石粉)应≤3%,人工将砾料填入井管与井孔的环状空隙中,各方向填料速度应均匀进行,保持连续,均匀、足量填入,填料过程中严禁带入其它杂物,填料量允许偏差为±10%,洗井后滤料下沉应及时补充滤料,实际填料量不小于95%理论计算量。The filter material is sand and gravel filter material, and the sand and gravel are graded sand and gravel, and the mass ratio of the gradation is: gravel of 7 mm to 12 mm: gravel of 3 mm to 7 mm: sand = 45:25:30. The filter material should be round or sub-round. It is forbidden to use flaky or needle-shaped gravel. The mud content of the gravel (including stone powder) should be ≤3%. The gravel should be manually filled into the ring between the well pipe and the well hole. In the gap, the filling speed in all directions should be uniform, keep continuous, uniform and sufficient filling, and other sundries are strictly prohibited during the filling process, the allowable deviation of the filling amount is ±10%, and the filter material should be replenished in time after the well is washed. For filter material, the actual amount of filler is not less than 95% of the theoretically calculated amount.

实施例2Example 2

如图2所示,本实施例中的降水井仅深度不同于实施例1,其他特征与实施例1相同,降水井的底端距离地下水水位线0.01~8.11m;降水井的底端不穿透地下隔水层5(距地下水水位线8.11~11.51m处)。As shown in Figure 2, only the depth of the dewatering well in this embodiment is different from embodiment 1, and other features are the same as in embodiment 1. The bottom of the dewatering well is 0.01 ~ 8.11m away from the groundwater level line; Permeable underground water-resisting layer 5 (8.11~11.51m away from the groundwater level).

在工程进行的过程中,施工人员使用水位尺测量降水井中的水位高低,通过连通器原理可知,基坑内的水位与降水井中的水位是一致的,据此判断基坑内水位的高低,是否超标。一旦发现基坑内水位超出了合理的计算数值,施工人员及时使用抽水泵把水从降水井中抽出,降水井中水位下降,基坑水压力把基坑内的水源源不断的挤压到降水井中再被抽出去,这样基坑内的水位下降到工程需要的水位在停止抽水,保证了基坑内水压力保持在合理的范围内,避免造成基坑的隆起破坏,进而减少周围地面、交通和建筑物的沉降,起到了保护环境和施工安全的作用。During the process of the project, the construction personnel used the water gauge to measure the water level in the dewatering well. According to the principle of the connector, the water level in the foundation pit is consistent with the water level in the dewatering well. Based on this, it can be judged whether the water level in the foundation pit exceeds the standard. Once it is found that the water level in the foundation pit exceeds the reasonable calculation value, the construction personnel will use the pump to pump the water out of the dewatering well in time, the water level in the dewatering well will drop, and the water pressure in the foundation pit will continuously squeeze the water in the foundation pit into the dewatering well and then be pumped out In this way, the water level in the foundation pit drops to the water level required by the project and the pumping is stopped, ensuring that the water pressure in the foundation pit remains within a reasonable range, avoiding the uplift damage of the foundation pit, and reducing the settlement of the surrounding ground, traffic and buildings. Played a role in protecting the environment and construction safety.

Claims (10)

1.一种具有监测减压作用的地铁基坑降水井,其特征在于:包括上层的给水层和下层的滤水层两部分,井内设置钢筋笼由上至下贯穿给水层和滤水层;所述给水层在钢筋笼内部设置有钢管,在钢筋笼外填充粘土;所述滤水层在钢筋笼内部设置有钢筋滤水管,在钢筋笼外部设置有双层尼龙布并填充有滤料。1. A subway foundation pit dewatering well with monitoring decompression effect, is characterized in that: comprise two parts of the water supply layer of upper strata and the water filter layer of lower floor, in the well, reinforcement cage is set to run through water supply layer and water filter layer from top to bottom; The water supply layer is provided with a steel pipe inside the steel cage, and clay is filled outside the steel cage; the water filter layer is provided with a steel filter pipe inside the steel cage, and is provided with double-layer nylon cloth and filled with filter material outside the steel cage. 2.根据权利要求1所述的地铁基坑降水井,其特征在于:所述降水井设置于地下水水位线以上。2. The subway foundation pit dewatering well according to claim 1, characterized in that: the dewatering well is arranged above the groundwater level. 3.根据权利要求2所述的地铁基坑降水井,其特征在于:降水井的底端距离地下水水位线8.11~11.51m。3. The subway foundation pit dewatering well according to claim 2, characterized in that: the bottom of the dewatering well is 8.11-11.51m away from the groundwater level. 4.根据权利要求2所述的地铁基坑降水井,其特征在于:降水井的底端距离地下水水位线0.01~8.11m。4. The subway foundation pit dewatering well according to claim 2, characterized in that: the bottom of the dewatering well is 0.01-8.11m away from the groundwater level. 5.根据权利要求1所述的地铁基坑降水井,其特征在于:所述给水层的钢管采用Φ480型,钢筋笼外填充的粘土封闭并捣实。5. The subway foundation pit dewatering well according to claim 1, characterized in that: the steel pipe of the water supply layer adopts Φ480 type, and the clay filled outside the reinforcement cage is closed and compacted. 6.根据权利要求1所述的地铁基坑降水井,其特征在于:所述滤水层的钢筋滤水管采用Φ508型,双层尼龙布均为40目。6. The subway foundation pit dewatering well according to claim 1, characterized in that: the steel filter pipe of the filter layer adopts Φ508 type, and the double-layer nylon cloth is 40 mesh. 7.根据权利要求1所述的地铁基坑降水井,其特征在于:所述钢筋笼包括纵向的主筋和横向的加强筋,加强筋导向环焊在主筋上,所述主筋采用9Φ14型,所述加强筋采用Φ12@250型。7. The subway foundation pit dewatering well according to claim 1, characterized in that: the reinforcement cage includes longitudinal main reinforcement and transverse reinforcement, the reinforcement guide ring is welded on the main reinforcement, the main reinforcement adopts 9Φ14 type, the The reinforcing rib mentioned above adopts Φ12@250 type. 8.根据权利要求7所述的地铁基坑降水井,其特征在于:位于过滤层的钢筋笼外侧捆绑竹条,竹条分布于每两个主筋中间。8. The subway foundation pit dewatering well according to claim 7, characterized in that bamboo strips are bound outside the reinforcement cage located in the filter layer, and the bamboo strips are distributed between every two main reinforcements. 9.根据权利要求1所述的地铁基坑降水井,其特征在于:过滤层的钢筋笼和双层尼龙布之间设置有滤网,双层尼龙布缠绕在滤网外侧,滤料填充在双层尼龙网外部。9. The subway foundation pit dewatering well according to claim 1, characterized in that: a filter screen is arranged between the steel cage of the filter layer and the double-layer nylon cloth, the double-layer nylon cloth is wound on the outside of the filter screen, and the filter material is filled in Double layer nylon mesh exterior. 10.根据权利要求1所述的地铁基坑降水井,其特征在于:所述滤料为砂石滤料,级配质量比为7mm~12mm的碎石:3mm~7mm的碎石:砂子=45:25:30。10. The subway foundation pit dewatering well according to claim 1, characterized in that: the filter material is a sand filter material, and the gradation mass ratio is 7mm-12mm gravel: 3mm-7mm gravel: sand = 45:25:30.
CN201710559904.1A 2017-07-11 2017-07-11 It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization Pending CN107165181A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710559904.1A CN107165181A (en) 2017-07-11 2017-07-11 It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710559904.1A CN107165181A (en) 2017-07-11 2017-07-11 It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization

Publications (1)

Publication Number Publication Date
CN107165181A true CN107165181A (en) 2017-09-15

Family

ID=59823618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710559904.1A Pending CN107165181A (en) 2017-07-11 2017-07-11 It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization

Country Status (1)

Country Link
CN (1) CN107165181A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456056A (en) * 2020-04-29 2020-07-28 中冶建工集团有限公司 Construction method of dewatering well in deep foundation pit
CN111608171A (en) * 2020-05-27 2020-09-01 中国一冶集团有限公司 Sandbar underground soft base pipe, well precipitation anti-floating pipe pile structure and construction method
CN112012790A (en) * 2020-09-02 2020-12-01 中铁第一勘察设计院集团有限公司 Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well
CN113250220A (en) * 2021-05-13 2021-08-13 中铁五局集团成都工程有限责任公司 Novel dewatering method for deep foundation pit close to existing building

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020291A (en) * 1999-07-12 2001-01-23 Ohbayashi Corp Groundwater draining method
CN204163092U (en) * 2014-09-15 2015-02-18 中铁十二局集团有限公司 Dewatering well bamboo cage chimney filter
CN204311464U (en) * 2014-12-12 2015-05-06 中铁二十局集团第三工程有限公司 A kind of foundation pit dewatering constructing structure
CN104831762A (en) * 2015-04-30 2015-08-12 宁波大学 Dynamic monitoring system and monitoring method of deep foundation pit confined water drawdown
CN105133581A (en) * 2015-09-10 2015-12-09 深圳市市政工程总公司 Three-in-one construction method for uplift pile, lattice column and precipitation well in supporting structure
CN105696611A (en) * 2014-11-25 2016-06-22 中冶天工上海十三冶建设有限公司 Foundation pit dewatering device for sand layer with high water permeability
CN205934947U (en) * 2016-07-29 2017-02-08 辽宁大学 Dark foundation pit dewatering tubular well structure
CN207193993U (en) * 2017-07-11 2018-04-06 中交隧道工程局有限公司 A kind of subway foundation pit dewatering well with monitoring depressurization

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020291A (en) * 1999-07-12 2001-01-23 Ohbayashi Corp Groundwater draining method
CN204163092U (en) * 2014-09-15 2015-02-18 中铁十二局集团有限公司 Dewatering well bamboo cage chimney filter
CN105696611A (en) * 2014-11-25 2016-06-22 中冶天工上海十三冶建设有限公司 Foundation pit dewatering device for sand layer with high water permeability
CN204311464U (en) * 2014-12-12 2015-05-06 中铁二十局集团第三工程有限公司 A kind of foundation pit dewatering constructing structure
CN104831762A (en) * 2015-04-30 2015-08-12 宁波大学 Dynamic monitoring system and monitoring method of deep foundation pit confined water drawdown
CN105133581A (en) * 2015-09-10 2015-12-09 深圳市市政工程总公司 Three-in-one construction method for uplift pile, lattice column and precipitation well in supporting structure
CN205934947U (en) * 2016-07-29 2017-02-08 辽宁大学 Dark foundation pit dewatering tubular well structure
CN207193993U (en) * 2017-07-11 2018-04-06 中交隧道工程局有限公司 A kind of subway foundation pit dewatering well with monitoring depressurization

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456056A (en) * 2020-04-29 2020-07-28 中冶建工集团有限公司 Construction method of dewatering well in deep foundation pit
CN111608171A (en) * 2020-05-27 2020-09-01 中国一冶集团有限公司 Sandbar underground soft base pipe, well precipitation anti-floating pipe pile structure and construction method
CN112012790A (en) * 2020-09-02 2020-12-01 中铁第一勘察设计院集团有限公司 Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well
CN113250220A (en) * 2021-05-13 2021-08-13 中铁五局集团成都工程有限责任公司 Novel dewatering method for deep foundation pit close to existing building

Similar Documents

Publication Publication Date Title
CN107246019B (en) A kind of slope underground water drilling self-starting drainage by suction method
CN104727319B (en) A kind of side slope is from drainage anchor rod and construction method
CN103967507B (en) A kind of curtain-grouting technique being suitable for rich water mine down-hole exploitation water blockoff
CN106638669B (en) Existing subway station building enclosure hardened system and method are worn under a kind of shield
CN110016922A (en) A new type of integral drainage anti-sliding pile structure and its construction method
WO2013159749A1 (en) Method for distributed storage and use of underground water in mine
CN101560764B (en) Method for calking exploratory hole by intermittent high-pressure rotary jet grouting
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN106337426A (en) Dewatering method used for improving surging-resisting stability of confined water stratum foundation pit
CN205387712U (en) Quick treatment device of foundation pit piping
CN107165181A (en) It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN115787693A (en) Water stopping method for water gushing in deep foundation pit under riverside slow-dip interbed
CN108590716A (en) A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method
CN107816051A (en) Pressure-bearing property phreatic aquifer deep basal pit combination well dewatering construction method
CN110805052A (en) Comprehensive treatment method for inrush surge in ultra-deep foundation pit
CN206971199U (en) A kind of new independent well point integrate draining combined vacuum ground preloading system
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN115992525A (en) Precipitation structure and precipitation method of deep foundation pit penetrating through pebble mudstone interface
CN207193993U (en) A kind of subway foundation pit dewatering well with monitoring depressurization
CN110424416A (en) A kind of solenoid drain friction pile and its construction method
CN103669333B (en) It is easy to the friction pile of vacuum-dewatering
CN104863185A (en) Blocking and seepage-proofing technology of leaky well
CN202187360U (en) A Well Point Positioning Pumping Tube Well
CN110409474A (en) Tube Well Dewatering Wells Placed at the Bottom of an Underground Diaphragm Wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170915