CN107161886A - The auxiliary self installation method of crane, from method for dismounting and from disassembly system - Google Patents
The auxiliary self installation method of crane, from method for dismounting and from disassembly system Download PDFInfo
- Publication number
- CN107161886A CN107161886A CN201710578542.0A CN201710578542A CN107161886A CN 107161886 A CN107161886 A CN 107161886A CN 201710578542 A CN201710578542 A CN 201710578542A CN 107161886 A CN107161886 A CN 107161886A
- Authority
- CN
- China
- Prior art keywords
- auxiliary
- principal arm
- crane
- supporting construction
- dollie
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/64—Jibs
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
Abstract
The invention discloses a kind of auxiliary self installation method of crane, from method for dismounting and from disassembly system.The auxiliary self installation method of crane is hung in the supporting construction including controlling the principal arm of the crane to hang supporting construction on dollie and by the auxiliary;The principal arm action is controlled with close to the auxiliary;Connect the principal arm and the auxiliary.The auxiliary self installation method of the present invention completes the installation to auxiliary by using the principal arm of crane itself, it is no longer necessary to auxiliary hoist, reduces the requirement to crane subsidiary arm fabricating yard.Further, it is not necessary to which auxiliary hoist just saves auxiliary hoist and its expense of driver for user, and scale that is cost-effective and can reducing crane fleet is conducive to quick transition.
Description
Technical field
The present invention relates to engineering machinery field, the auxiliary self installation method of more particularly to a kind of crane, from method for dismounting
With from disassembly system.
Background technology
Large-tonnage telescopic arm crane (lifting capacity at 200 tons and more than) is larger due to conducting oneself with dignity, will to meet highway transportation
Ask, in transition, auxiliary needs to be removed and use dollie independent transport.Recycle and aid in after lifting scene is reached
Auxiliary is installed on principal arm by heavy-duty machine.
Auxiliary is installed using auxiliary hoist, user needs to bear auxiliary hoist and its expense of driver, especially
It is costly during long range transition.And following for auxiliary hoist causes Fleet size larger, it is unfavorable for quick transition.Separately
Outside, when auxiliary is installed on principal arm using auxiliary hoist, it is necessary to site area it is larger, to lifting scene requirement compared with
It is high.
The content of the invention
It is it is an object of the invention to provide a kind of auxiliary self installation method of crane, from method for dismounting and from dismounting
System, to reduce the requirement to auxiliary fabricating yard and reduce user cost.
First aspect present invention provides a kind of auxiliary self installation method of crane, controls the principal arm of the crane and will prop up
Support structure is hung to be hung in the supporting construction on dollie and by the auxiliary;Control principal arm action with by
The nearly auxiliary;Connect the principal arm and the auxiliary.
Further, the principal arm of the crane is controlled to hang supporting construction in described including control on dollie
Longitudinal direction interval of the principal arm by supporting construction described at least two along the dollie is hung in the dollie
On.
Further, the supporting construction includes being used to support the supporting part of the auxiliary, by the auxiliary hang in
Height of the supporting part relative to the dollie is adjusted before on the supporting part.
Further, control longitudinal direction interval of the principal arm along the dollie to hang described at least two to prop up
Support structure and the auxiliary is positioned at least two supporting construction, adjusted respectively at least two supporting construction
Supporting part to different height so that the auxiliary has certain angle of inclination.
Further, the hangers on the auxiliary is mounted with the hanging scroll on the principal arm and be connected by connecting shaft
The auxiliary and the principal arm.
Further, the principal arm is controlled after the hanging scroll on the hangers on the auxiliary and the principal arm is mounted
Upward luffing is to cause the principal arm connecting hole on the auxiliary connecting hole and the principal arm on the auxiliary to align;Again by the connection
Axle is each passed through the auxiliary connecting hole and the principal arm connecting hole to connect the principal arm and the auxiliary.
Further, master of the upward luffing of principal arm to the auxiliary locating piece on the auxiliary and the principal arm is controlled
When arm locating piece is abutted, the auxiliary connecting hole and principal arm connecting hole alignment.
Second aspect of the present invention provides a kind of auxiliary of crane from method for dismounting, controls the principal arm action of the crane
So that the auxiliary is positioned in the supporting construction;The principal arm is released with the auxiliary and is connected;Control the principal arm will
The auxiliary hangs the supporting construction and the supporting construction is hung into the dollie.
Third aspect present invention provides a kind of auxiliary of crane from disassembly system, and the crane includes principal arm and pair
Arm, including dollie and supporting construction, the supporting construction are connected on the dollie and described for supporting
Auxiliary by the auxiliary to be raised to certain altitude jointly with the dollie.
Further, the supporting construction includes the matrix part being fixedly installed on the dollie and for supporting
The supporting part of the dollie, the supporting part saves land setting relative to the height adjustable in described matrix portion.
Further, the supporting construction also includes the lifting portion being arranged in described matrix portion, and the lifting portion is used for
Coordinate the lifting to complete the supporting construction with the principal arm and be used to be connected with the dollie.
Based on the present invention provide crane auxiliary self installation method, from method for dismounting and from disassembly system, pass through profit
The installation to auxiliary is completed with the principal arm of crane itself, it is no longer necessary to auxiliary hoist, reduced to crane subsidiary arm erecting bed
The requirement on ground.Further, it is not necessary to which auxiliary hoist just saves auxiliary hoist and its expense of driver for user, saves
Cost and the scale that can reduce crane fleet, are conducive to quick transition.
By referring to the drawings to the detailed description of the exemplary embodiment of the present invention, further feature of the invention and its
Advantage will be made apparent from.
Brief description of the drawings
Accompanying drawing described herein is used for providing a further understanding of the present invention, constitutes the part of the application, this hair
Bright schematic description and description is used to explain the present invention, does not constitute inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 to Fig. 2 is the step schematic diagram of the auxiliary self installation method of the crane of the embodiment of the present invention;
Fig. 3 be Fig. 2 in M portions partial enlargement structural representation;
Fig. 4 be Fig. 1 in supporting construction dimensional structure diagram;
Fig. 5 is the main structure diagram of the supporting construction shown in Fig. 4.
Each reference is represented respectively:
1- dollies;2- supporting constructions;21- matrix parts;22- supporting parts;23- liftings portion;24- bearing pins;3- auxiliarys;
31- hangers;32- the first auxiliary connecting holes;33- the second auxiliary connecting holes;34- auxiliary locating pieces;4- principal arms;41- hanging scrolls;42-
First principal arm connecting hole;43- the second principal arm connecting holes;44- principal arm locating pieces.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.Below
Description only actually at least one exemplary embodiment is illustrative, is never used as to the present invention and its application or makes
Any limitation.Based on the embodiment in the present invention, those of ordinary skill in the art are not making creative work premise
Lower obtained every other embodiment, belongs to the scope of protection of the invention.
Unless specifically stated otherwise, the part and positioned opposite, the digital table of step otherwise illustrated in these embodiments
Do not limited the scope of the invention up to formula and numerical value.Simultaneously, it should be appreciated that for the ease of description, each portion shown in accompanying drawing
The size divided not is to be drawn according to actual proportionate relationship.For technology, side known to person of ordinary skill in the relevant
Method and equipment may be not discussed in detail, but in the appropriate case, the technology, method and apparatus should be considered as authorizing explanation
A part for book.In shown here and discussion all examples, any occurrence should be construed as merely exemplary, and
Not by way of limitation.Therefore, the other examples of exemplary embodiment can have different values.It should be noted that:Similar label
Similar terms is represented in following accompanying drawing with letter, therefore, once it is defined in a certain Xiang Yi accompanying drawing, then subsequent attached
It need not be further discussed in figure.
For the ease of description, space relative terms can be used herein, such as " ... on ", " ... top ",
" ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy
The spatial relation levied.It should be appreciated that space relative terms are intended to comprising the orientation except device described in figure
Outside different azimuth in use or operation.If for example, the device in accompanying drawing is squeezed, be described as " in other devices
It will be positioned as " under other devices or construction after the device of part or construction top " or " on other devices or construction "
Side " or " under other devices or construction ".Thus, exemplary term " ... top " can include " ... top " and
" in ... lower section " two kinds of orientation.The device can also other different modes positioning (being rotated by 90 ° or in other orientation), and
And respective explanations are made to the relative description in space used herein above.
As depicted in figs. 1 and 2, the auxiliary self installation method of the crane of the embodiment of the present invention comprises the following steps:
Step one:Control crane principal arm by supporting construction 2 hang on dollie 1 and by auxiliary 3 hang in
In supporting construction 2.
Step 2:Control principal arm 4 is acted with close to auxiliary 3.
Step 3:Connect principal arm 4 and with auxiliary 3.
The auxiliary self installation method of the crane of the embodiment of the present invention is completed to pair by using the principal arm of crane itself
The installation of arm, it is no longer necessary to auxiliary hoist, reduces the requirement to crane subsidiary arm fabricating yard.Further, it is not necessary to auxiliary
Help crane and just save auxiliary hoist and its expense of driver for user, it is cost-effective and crane fleet can be reduced
Scale, be conducive to quick transition.
The auxiliary self installation method of the crane of the present embodiment on dollie by hanging supporting construction by pair
Arm raises certain altitude.In order to which auxiliary is smoothly positioned on dollie, before lifting auxiliary, principal arm edge is first controlled
The longitudinal direction interval of dollie hangs at least two supporting constructions and auxiliary is positioned at least two supporting constructions again.
Fig. 1 and Fig. 2 show that the present embodiment hangs two supporting constructions on transport flat panel.
As shown in Figure 4 and Figure 5, the supporting construction 2 of the present embodiment includes matrix part 21 and supporting part 22.Matrix part 21 is fixed
It is connected on dollie 1, supporting part 22 is movably set relative to matrix part 21 to adjust the height of supporting part 22, and then
Regulation is positioned over the height of the auxiliary on supporting part 22.
In the present embodiment, supporting part 22 and matrix part 21 are square casing structure.Supporting part 22 is located at matrix part 21
Inside and be movably disposed relative to matrix part 21.The side wall of matrix part 21 is provided with a matrix connecting hole.Supporting part
22 side wall be provided with multiple support connecting holes, control supporting part 22 relative to matrix part 21 move so that matrix connecting hole with
One in multiple support connecting holes is alignd and passes through to connect supporting part and matrix part by bearing pin 24.Matrix connecting hole with it is multiple
Different support connecting holes in support connecting hole align that when connecting supporting part using bearing pin with matrix part supporting part can be made
With different height.
Preferably, supporting construction 2 also includes lifting portion 23.Specifically, lifting portion 23 is suspension ring.Lifting portion 23 is in lifting branch
During support structure and principal arm suspension hook coordinate;Hung by supporting construction after on dollie, using rope or slide fastener etc. even
Lifting portion 23 and dollie are connect, so that supporting construction more can be firmly secured on dollie.Therefore hang
Dress portion can both realize the lifting to supporting construction, while the fixation to supporting construction can also be realized.
In the present embodiment, supporting construction is support.Can certainly be counterweight block, sleeper etc., as long as can be by pair
Arm is raised to the structure of certain altitude can be with.
Preferably, drive mechanism can be set to drive supporting part to move relative to matrix part.Drive mechanism can be oil
Cylinder etc..
Motion of the supporting part relative to matrix part is also not necessarily limited to linear motion, can also be swung relative to matrix part,
To improve the flexibility of auxiliary motion, so as to facilitate the centering of auxiliary connecting hole and principal arm connecting hole.
When auxiliary is installed, height of the supporting part relative to dollie is adjusted before on supporting part auxiliary is hung
Degree.
In order that auxiliary has certain angle of inclination, auxiliary is being hung before in two supporting constructions, adjusted respectively
The supporting part of two supporting constructions is saved to different height so that auxiliary has certain angle of inclination.
Hung by auxiliary after in supporting construction, as shown in Figures 2 and 3, by the hangers 31 on auxiliary 3 and principal arm 4
On hanging scroll 41 mounted and auxiliary 3 and principal arm 4 connected by connecting shaft.
In the present embodiment, principal arm is telescopic arm.When controlling principal arm action to be connected with auxiliary, principal arm can be controlled to become
Width, flexible and revolution are adjusted with the position to principal arm, so as to realize principal arm close to auxiliary and realization and the connection of auxiliary.
Specifically, control principal arm 41 becomes upwards after the hanging scroll 41 on the hangers 31 on auxiliary 3 and principal arm 4 is mounted
Width is to cause the principal arm connecting hole on the auxiliary connecting hole and principal arm 4 on auxiliary 3 to align.Connecting shaft is now each passed through pair again
Arm connecting hole and principal arm connecting hole are to connect principal arm and auxiliary.
It should be noted that needing the slight luffing upwards of control principal arm after hangers and hanging scroll mounting so that principal arm and pair
The direction motion that arm aligns towards principal arm connecting hole and auxiliary connecting hole.
Preferably, as shown in figure 3, being additionally provided with auxiliary locating piece 34 on the auxiliary 3 of the present embodiment.Principal arm 4 is provided with principal arm
Locating piece 44.After hangers 31 and hanging scroll 41 are mounted on the control upward luffing of principal arm to the auxiliary locating piece on auxiliary and principal arm
When principal arm locating piece is abutted, auxiliary connecting hole and the alignment of principal arm connecting hole.
In the present embodiment, auxiliary 3, provided with two auxiliary connecting holes, is the first auxiliary connecting hole 32 and the second auxiliary respectively
Connecting hole 33.Principal arm 4, provided with two principal arm connecting holes, is the first principal arm connecting hole 42 and the second principal arm connecting hole 43 respectively.
When connecting auxiliary with principal arm, the first auxiliary connecting hole 32 is connected with the first principal arm connecting hole 41 using bearing pin, while second
Auxiliary connecting hole 32 is connected with the second principal arm connecting hole 42.Now, two pairs of connecting holes are connected respectively and hangers and extension
The mounting of axle, forms three-point mount, so that the connection of auxiliary and principal arm is relatively reliable.
When dismantling auxiliary, the principal arm of control crane itself acts auxiliary being positioned in supporting construction and by principal arm
Release and be connected with auxiliary.Then auxiliary is hung supporting construction and supporting construction then is hung into dollie by control principal arm.
The crane of the present embodiment realizes the dismounting to auxiliary using the principal arm of itself, eliminates auxiliary hoist of the prior art
Setting, reduce cost.
The auxiliary of the present embodiment can be that truss arm configuration can also be box-structure.Auxiliary can also be wind-powered electricity generation arm head knot
Structure.
The self installation method of the auxiliary of the present embodiment is described below in detail:
Crane branch is put in suitable place first;Auxiliary is assembled on the ground again, after auxiliary is assembled
Dollie is adjusted to suitable place.
Using crane by two supporting constructions hang successively on dollie, now need adjustment two support tie
Supporting construction is simultaneously firmly connected on dollie by the spacing of structure using rope.Meanwhile, tied by each support of regulation
The link position of the bearing pin of structure is to adjust the height of each supporting construction so that auxiliary has certain angle of inclination.
The auxiliary assembled is steadily hung in supporting construction and controlling telescopic arm using the telescopic arm of crane itself
Lie prone and put down to horizontality.
Above step has been carried out the preliminary preparation of the installation of auxiliary.
Next control telescopic arm luffing, it is flexible or turn round with enable telescopic arm arm end close to auxiliary, flexible
Be close between arm and auxiliary very little apart from when, the hanging scroll on the hangers and telescopic arm on auxiliary is mounted and determined in auxiliary
Auxiliary is connected by position block after being abutted with principal arm locating piece using bearing pin with principal arm, now just completes the connection of auxiliary.
Afterwards, hydraulic pressure, electric elements and its attached component of auxiliary are reconnected.
Finally it should be noted that:The above embodiments are merely illustrative of the technical scheme of the present invention and are not intended to be limiting thereof;To the greatest extent
The present invention is described in detail with reference to preferred embodiments for pipe, those of ordinary skills in the art should understand that:Still
The embodiment of the present invention can be modified or equivalent substitution is carried out to some technical characteristics;Without departing from this hair
The spirit of bright technical scheme, it all should cover among claimed technical scheme scope of the invention.
Claims (11)
1. a kind of auxiliary self installation method of crane, it is characterised in that
Control the principal arm of the crane to hang supporting construction to hang in the branch on dollie and by the auxiliary
On support structure;The principal arm action is controlled with close to the auxiliary;Connect the principal arm and the auxiliary.
2. the auxiliary self installation method of crane according to claim 1, it is characterised in that the master of the control crane
Arm hangs supporting construction in including controlling the principal arm by supporting construction described at least two along the fortune on dollie
The longitudinal direction interval of defeated flat car is hung on the dollie.
3. the auxiliary self installation method of crane according to claim 1, it is characterised in that the supporting construction includes using
In the supporting part for supporting the auxiliary, the auxiliary is hung adjusted before on the supporting part supporting part relative to
The height of the dollie.
4. the auxiliary self installation method of crane according to claim 3, it is characterised in that the control principal arm is described in
The longitudinal direction interval of dollie hangs supporting construction described at least two and the auxiliary is positioned over into described at least two
In individual supporting construction, the supporting part at least two supporting construction is adjusted respectively to different height so that the auxiliary has
There is certain angle of inclination.
5. the auxiliary self installation method of crane according to claim 1, it is characterised in that by the hangers on the auxiliary
Mounted with the hanging scroll on the principal arm and the auxiliary and the principal arm are connected by connecting shaft.
6. the auxiliary self installation method of crane according to claim 5, it is characterised in that by the extension on the auxiliary
Ear controls the upward luffing of the principal arm with so that the auxiliary on the auxiliary is connected after being mounted with the hanging scroll on the principal arm
Principal arm connecting hole alignment on hole and the principal arm;The connecting shaft is each passed through the auxiliary connecting hole and the principal arm again
Connecting hole is to connect the principal arm and the auxiliary.
7. the auxiliary self installation method of crane according to claim 6, it is characterised in that the control principal arm becomes upwards
When auxiliary locating piece on width to the auxiliary is abutted with the principal arm locating piece on the principal arm, the auxiliary connecting hole and described
Principal arm connecting hole aligns.
8. a kind of auxiliary of crane is from method for dismounting, it is characterised in that the principal arm of the control crane is acted with will be described
Auxiliary is positioned in the supporting construction;The principal arm is released with the auxiliary and is connected;The principal arm is controlled by the auxiliary
Hang the supporting construction and the supporting construction is hung into the dollie.
9. a kind of auxiliary of crane is from disassembly system, the crane includes principal arm and auxiliary, it is characterised in that including transport
Flat car and supporting construction, the supporting construction be connected on the dollie and for support the auxiliary with it is described
The auxiliary is raised to certain altitude by dollie jointly.
10. the auxiliary of crane according to claim 9 is from disassembly system, it is characterised in that the supporting construction includes
The matrix part being fixedly installed on the dollie and the supporting part for supporting the dollie, the supporting part
Height adjustable relative to described matrix portion saves land setting.
11. the auxiliary of crane according to claim 10 is from disassembly system, it is characterised in that the supporting construction is also wrapped
The lifting portion being arranged in described matrix portion is included, the lifting portion is used to coordinate to complete the supporting construction with the principal arm
Lift and for being connected with the dollie.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710578542.0A CN107161886B (en) | 2017-07-17 | 2017-07-17 | The auxiliary self installation method of crane, from method for dismounting and from disassembly system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710578542.0A CN107161886B (en) | 2017-07-17 | 2017-07-17 | The auxiliary self installation method of crane, from method for dismounting and from disassembly system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107161886A true CN107161886A (en) | 2017-09-15 |
CN107161886B CN107161886B (en) | 2019-10-25 |
Family
ID=59817911
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710578542.0A Active CN107161886B (en) | 2017-07-17 | 2017-07-17 | The auxiliary self installation method of crane, from method for dismounting and from disassembly system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107161886B (en) |
Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3426914A (en) * | 1967-03-13 | 1969-02-11 | Frederik R Waleson | Ejector type boom |
JPH06206692A (en) * | 1992-10-06 | 1994-07-26 | Werner Haefliger | Wheel crane |
JPH06271286A (en) * | 1993-03-18 | 1994-09-27 | Tadano Ltd | Jib mounting and demounting device for boom having jib |
CN101712439A (en) * | 2009-11-27 | 2010-05-26 | 三一汽车制造有限公司 | Crane transition auxiliary device, transport trailer and method for dismantling crane |
CN101759105A (en) * | 2008-09-19 | 2010-06-30 | 马尼托瓦克起重机有限公司 | Boom hoist transportation system and crane using same |
CN101880010A (en) * | 2009-05-07 | 2010-11-10 | 马尼托沃克起重机集团(法国)公司 | Method with telescopic crane and fittable slackening device of self-fittable slackening device |
CN201864495U (en) * | 2010-11-22 | 2011-06-15 | 沈阳航天新乐有限责任公司 | On-vehicle double-hoisting transport vehicle |
CN202170224U (en) * | 2011-07-28 | 2012-03-21 | 徐州重型机械有限公司 | Hoist improving self-detachment positioning device and wheel type crane |
CN102774756A (en) * | 2011-05-09 | 2012-11-14 | 利勃海尔爱茵根有限公司 | Method for assembling a mobile crane and mobile crane |
CN202766156U (en) * | 2012-09-27 | 2013-03-06 | 中联重科股份有限公司 | Super-lifting device of crane and crane |
CN103010971A (en) * | 2012-12-27 | 2013-04-03 | 徐州重型机械有限公司 | Crane and hanging mechanism thereof |
CN103058075A (en) * | 2012-12-26 | 2013-04-24 | 三一重工股份有限公司 | Retrieving method for fly jib of crane and retrieving apparatus for fly jib |
CN103420281A (en) * | 2013-07-24 | 2013-12-04 | 三一汽车起重机械有限公司 | Disassembly and assembly device, disassembly method and mounting method for crane and accessory structures thereof |
CN203428810U (en) * | 2013-08-23 | 2014-02-12 | 徐州重型机械有限公司 | Crane and boom system thereof |
CN103863956A (en) * | 2014-03-31 | 2014-06-18 | 徐州重型机械有限公司 | Crane with self-dismounting over-lifting device and dismounting method of over-lifting device |
CN104210967A (en) * | 2013-06-03 | 2014-12-17 | 株式会社多田野 | Jib attachment/detachment mechanism |
CN104495648A (en) * | 2014-11-05 | 2015-04-08 | 中联重科股份有限公司 | Crane boom loading and unloading method and crane boom |
CN105060142A (en) * | 2015-08-06 | 2015-11-18 | 徐工集团工程机械股份有限公司 | Integrally mounted and transported luffing fly jib of crawler crane |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6271286B2 (en) * | 2014-02-18 | 2018-01-31 | 神東塗料株式会社 | Repair method for slab track |
-
2017
- 2017-07-17 CN CN201710578542.0A patent/CN107161886B/en active Active
Patent Citations (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3426914A (en) * | 1967-03-13 | 1969-02-11 | Frederik R Waleson | Ejector type boom |
JPH06206692A (en) * | 1992-10-06 | 1994-07-26 | Werner Haefliger | Wheel crane |
JPH06271286A (en) * | 1993-03-18 | 1994-09-27 | Tadano Ltd | Jib mounting and demounting device for boom having jib |
JP3238976B2 (en) * | 1993-03-18 | 2001-12-17 | 株式会社タダノ | Jib removal device for jib boom |
CN101759105A (en) * | 2008-09-19 | 2010-06-30 | 马尼托瓦克起重机有限公司 | Boom hoist transportation system and crane using same |
CN101880010A (en) * | 2009-05-07 | 2010-11-10 | 马尼托沃克起重机集团(法国)公司 | Method with telescopic crane and fittable slackening device of self-fittable slackening device |
CN101712439A (en) * | 2009-11-27 | 2010-05-26 | 三一汽车制造有限公司 | Crane transition auxiliary device, transport trailer and method for dismantling crane |
CN201864495U (en) * | 2010-11-22 | 2011-06-15 | 沈阳航天新乐有限责任公司 | On-vehicle double-hoisting transport vehicle |
CN102774756A (en) * | 2011-05-09 | 2012-11-14 | 利勃海尔爱茵根有限公司 | Method for assembling a mobile crane and mobile crane |
CN202170224U (en) * | 2011-07-28 | 2012-03-21 | 徐州重型机械有限公司 | Hoist improving self-detachment positioning device and wheel type crane |
CN202766156U (en) * | 2012-09-27 | 2013-03-06 | 中联重科股份有限公司 | Super-lifting device of crane and crane |
CN103058075A (en) * | 2012-12-26 | 2013-04-24 | 三一重工股份有限公司 | Retrieving method for fly jib of crane and retrieving apparatus for fly jib |
CN103010971A (en) * | 2012-12-27 | 2013-04-03 | 徐州重型机械有限公司 | Crane and hanging mechanism thereof |
CN104210967A (en) * | 2013-06-03 | 2014-12-17 | 株式会社多田野 | Jib attachment/detachment mechanism |
CN103420281A (en) * | 2013-07-24 | 2013-12-04 | 三一汽车起重机械有限公司 | Disassembly and assembly device, disassembly method and mounting method for crane and accessory structures thereof |
CN203428810U (en) * | 2013-08-23 | 2014-02-12 | 徐州重型机械有限公司 | Crane and boom system thereof |
CN103863956A (en) * | 2014-03-31 | 2014-06-18 | 徐州重型机械有限公司 | Crane with self-dismounting over-lifting device and dismounting method of over-lifting device |
CN104495648A (en) * | 2014-11-05 | 2015-04-08 | 中联重科股份有限公司 | Crane boom loading and unloading method and crane boom |
CN105060142A (en) * | 2015-08-06 | 2015-11-18 | 徐工集团工程机械股份有限公司 | Integrally mounted and transported luffing fly jib of crawler crane |
Also Published As
Publication number | Publication date |
---|---|
CN107161886B (en) | 2019-10-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5580975B2 (en) | How to raise a crane boom | |
CN205687426U (en) | Indoor middle-size and small-size equipment boom hoisting | |
JP2009107842A (en) | Erecting method of crane boom | |
KR20100121409A (en) | Telescopic crane with self-mounting bracing device and method of mounting a bracing device | |
US10450170B2 (en) | Mobile crane having adjustable ballast mounting apparatus | |
EP1735233A1 (en) | Mobile crane system comprising a mobile crane and an auxiliary device for assembly of a bracing device | |
CN109319652A (en) | A kind of superimposed sheet hoisting fixture and superimposed sheet hanging method | |
CN211689943U (en) | Assembled pier stud template upset buffer | |
CN102359302A (en) | Extra-high voltage large-span iron tower assembling method | |
CN109236012A (en) | A kind of dry font Guywire tower hanging method of transmission line of electricity | |
CN109231023B (en) | Method for installing jib system of portal crane | |
CN205527410U (en) | Balanced heavy device of installing and removing by oneself of tower crane | |
CN103276907B (en) | Hoisting method for large-span hinged type herringbone steel arch | |
CN208415485U (en) | The aerial steel vestibule Lift-on/Lift-off System of multilayer | |
CN107161886A (en) | The auxiliary self installation method of crane, from method for dismounting and from disassembly system | |
CN209481045U (en) | A kind of intelligent hanging apparatus of wind power hub | |
CN105152001B (en) | For lifting the special hanger and hanging method of radio telescope reflecting surface unit | |
CN208981167U (en) | Suspension type constructing tie beam device | |
JP2018150089A (en) | Operation method of tower crane | |
CN207759922U (en) | Large span suspender | |
CN103407906B (en) | A kind of super lifting device and surpassed supporting leg | |
CN107777587A (en) | A kind of tower crane assembly technology | |
CN215797889U (en) | Anti-deformation hoisting device for pile foundation reinforcement cage | |
CN206957175U (en) | A kind of planar dimension and adjustable for height operating platform | |
CN202379690U (en) | Laterally arranged arm frame device and elevating fire truck and overhead working truck with the device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |