CN107142923A - Drainpipe and the method that side slope downslide is handled using the drainpipe - Google Patents

Drainpipe and the method that side slope downslide is handled using the drainpipe Download PDF

Info

Publication number
CN107142923A
CN107142923A CN201710379832.2A CN201710379832A CN107142923A CN 107142923 A CN107142923 A CN 107142923A CN 201710379832 A CN201710379832 A CN 201710379832A CN 107142923 A CN107142923 A CN 107142923A
Authority
CN
China
Prior art keywords
drainpipe
inner tube
barricade
outer tube
side slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710379832.2A
Other languages
Chinese (zh)
Inventor
罗世谋
曹宁
罗博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUNAN KEXIN ELECTRIC POWER DESIGN CO Ltd
Original Assignee
HUNAN KEXIN ELECTRIC POWER DESIGN CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN KEXIN ELECTRIC POWER DESIGN CO Ltd filed Critical HUNAN KEXIN ELECTRIC POWER DESIGN CO Ltd
Priority to CN201710379832.2A priority Critical patent/CN107142923A/en
Publication of CN107142923A publication Critical patent/CN107142923A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Abstract

Drainpipe and the method that side slope downslide is handled using the drainpipe, the drainpipe include being provided with inner tube in outer tube, the outer tube, and inner tube is flexibly connected with outer tube, and inner tube can be extracted out out of outer tube, and the end of inner tube is provided with scoop, and scoop is fixedly connected with inner tube.Present invention additionally comprises handle the method that side slope glides using the drainpipe.Drainpipe of the present invention can discharge the soil layer seepage in underground such as bank protection, the aqueous sand in barricade top and completely weathered granite, also bank protection can be discharged, the concentration spring that the inconvenience above barricade is excluded, so as to effectively reduce the soil layer levels of ground water such as bank protection, the aqueous sand in the side of blocking and completely weathered granite, strengthen the mechanical property of side slope soil, reach that stable side slope, processing side slope glide, it is easy to bank protection Retaining wall, the construction quality of bank protection barricade is improved, is effectively smoothly implemented using place, cost-effective, Support Construction project and ensures the purpose of workmen's personal safety.

Description

Drainpipe and the method that side slope downslide is handled using the drainpipe
Technical field
The present invention relates to reduction side slope sandy soils level of ground water, a kind of drainpipe is specifically related to and using at the drainpipe Manage the method that side slope glides.
Background technology
At the larger side slope of the discrepancy in elevation, it will usually build bank protection 9 and barricade 10.Spent in the sand and completely decomposed of rich groundwater The soil layers such as Gang Yan, especially in Used in Rainy Seasons of Southern Cities, when bank protection 9 and the construction of barricade 10, often because of sand above bank protection barricade and completely decomposed flower The soil layer such as Gang Yan level of ground water is high, causes slope instability, forms landslide 3.Reference picture 1, existing processing method is at landslide 3 Shaped steel friction pile 4 is squeezed into, but treatment effect is not often good, and mainly phreatic line 6 of tracing it to its cause is too high, sand above side slope And the soil layer such as completely weathered granite is under many Groundwater Flow environment, engineering mechanics property extreme difference, so not only bank protection barricade Construction quality be cannot be guaranteed, and the construction of project can not be carried out, and also take planning construction project land used, waste of resource, seriously Jeopardize construction project implementation and the personal safety of workmen.
The content of the invention
The technical problems to be solved by the invention are to overcome the shortcomings of above-mentioned background technology there is provided a kind of drainpipe and profit The method that side slope glides is handled with the drainpipe, drainpipe can discharge the soil layer such as aqueous sand and completely weathered granite above side slope Seepage in underground, can also discharge the concentration spring that the inconvenience above side slope is excluded, thus effectively above reduction side slope aqueous sand and The soil layer level of ground water such as completely weathered granite, the mechanical property of enhancing side slope soil reaches the mesh that stable side slope, processing side slope glide 's.
The present invention solves the technical scheme that its technical problem uses, a kind of drainpipe, including outer tube, is set in the outer tube There is inner tube, said inner tube is flexibly connected with outer tube, said inner tube can be extracted out out of outer tube, the end of said inner tube is provided with scoop, The scoop is fixedly connected with inner tube.
Further, the front portion of the outer tube is provided with water hole.
Further, the outer tube and the circular in cross-section of inner tube.
A kind of method glided using described drainpipe processing side slope, is comprised the following steps:
(1)By the one end of drainpipe with scoop forward, drainpipe is headed into landslide;
(2)Extract the inner tube of drainpipe, the sand taken out in inner pipe end shovel out, underground water is discharged along drainpipe;
(3)Inner tube is put into outer tube, drainpipe is headed into landslide by continuation;
(4)Extract the inner tube of drainpipe, the sand taken out in inner pipe end scoop out, underground water is discharged along drainpipe;
(5)It is repeated in step(3)、(4), wait that the phreatic line in coming down drops to 1-2m or so under landslide surface, excavate and slide Slope soil, until drainpipe heads into landslide depths;
(6)After landslide soil to barricade bottom is excavated, build barricade by laying bricks or stones, build barricade bottom by laying bricks or stones and set tapping pipe, further arrange underground water, drop Phreatic low;
(7)Treat that barricade solidifies, and the phreatic line in landslide is dropped under barricade top surface after 1-2m or so, utilizes barricade bottom Tapping pipe draining lowering of watertable.
Further, step(1)Before, there is the neighbouring excavation sump at spring on bank protection top.
Compared with prior art, advantages of the present invention is as follows:Drainpipe can discharge aqueous sand and completely decomposed above side slope The soil layer seepage in underground such as granite, can also discharge the concentration spring that the inconvenience above side slope is excluded, can using drainpipe of the present invention The soil layer level of ground water such as aqueous sand and completely weathered granite effectively above reduction side slope, the mechanical property of enhancing side slope soil, place Manage side slope to glide, it is ensured that stability of slope, be easy to bank protection Retaining wall, improve the construction quality of bank protection barricade, it is ensured that engineering construction It is timely completed, using place, cost-effective, Support Construction project smooth implementation and the person of workmen effectively can be ensured Safety.
Brief description of the drawings
Fig. 1 is the schematic diagram of existing conventional landslide barricade processing method.
Fig. 2 is the structural representation of the drainpipe of the embodiment of the present invention 1.
Fig. 3 is the structural representation of the outer tube of the drainpipe of embodiment illustrated in fig. 21.
Fig. 4 is the structural representation of the inner tube of the drainpipe of embodiment illustrated in fig. 21.
Fig. 5 is the processing procedure schematic diagram at initial stage of the utilization drainpipe processing side slope downslide of the embodiment of the present invention 1,2.
Fig. 6 is that the processing side slope of embodiment illustrated in fig. 5 glides(Downslide side slope adjacent upper part is without spring or has spring but spring Water is smaller)After the completion of schematic diagram.
Fig. 7 is that the utilization drainpipe processing side slope of the embodiment of the present invention 2 glides(Downslide side slope adjacent upper part has spring and spring Eye water is larger)After the completion of schematic diagram.
In figure:1-outer tube, 2-water hole, 3-landslide, 4-shaped steel friction pile, 5-sump, 6-phreatic line, 9-bank protection, 10-barricade, 12-tapping pipe, 13-inner tube, 14-scoop, 15-spring.
Embodiment
Below in conjunction with the accompanying drawings and specific embodiment is described in further detail to the present invention.
Embodiment 1
Reference picture 2, Fig. 3, Fig. 4, the drainpipe of the present embodiment include outer tube 1, and the front portion of outer tube 1 is provided with water hole 2, outer tube 1 Provided with inner tube 13, inner tube 13 is flexibly connected with outer tube 1, and inner tube 13 can be extracted out out of outer tube 1, and the end of inner tube 13 is provided with scoop 14, scoop 14 is fixedly connected with inner tube 13, the circular in cross-section of outer tube 1 and inner tube 13.
The method for reducing slope sandy soils level of ground water using drainpipe of the present embodiment is applied to no spring or has spring Eye but the less situation of spring water, specific method are as follows:
(1)Reference picture 5, by the one end of drainpipe with scoop 14 forward, landslide 3 is headed into by drainpipe;
(2)Extract the inner tube 13 of drainpipe, the sand taken out in the end scoop 14 of inner tube 13 out, underground water is discharged along drainpipe 1;
(3)Inner tube 13 is put into outer tube 1, drainpipe is headed into landslide 3 by continuation;
(4)Extract the inner tube 13 of drainpipe, the sand taken out in the end scoop 14 of inner tube 13 out, underground water is discharged along drainpipe 1;
(5)It is repeated in step(3)、(4), treat that the phreatic line 6 in landslide 3 drops to 1-2m or so under landslide surface, excavate Landslide soil, until drainpipe heads into 3 depths of landslide;
(6)Reference picture 6, after landslide soil to the bottom of barricade 10 is excavated, builds barricade 10 by laying bricks or stones, builds the bottom of barricade 10 by laying bricks or stones and set tapping pipe 12, Further arrange underground water, lowering of watertable;
(7)Treat that barricade 10 solidifies, and the phreatic line in landslide 3 is dropped under barricade top surface after 1m or so, can extract draining out The outer tube 1 of pipe, utilizes the draining lowering of watertable of tapping pipe 12 of barricade bottom.
Embodiment 2
The drain structure of the present embodiment is same as Example 1.
The method for reducing slope sandy soils level of ground water using drainpipe of the present embodiment is applied to have spring and spring water The larger situation of amount, specific method is as follows:
(1)There is the neighbouring excavation sump 5 at spring 15 on the top of bank protection 9;
(2)Reference picture 5, by the one end of drainpipe with scoop 14 forward, landslide 3 is headed into by drainpipe;
(3)The inner tube 13 for extracting drainpipe out, the sand underground water taken out in the end scoop 14 of inner tube 13 are discharged along drainpipe 1;
(4)Inner tube 13 is put into outer tube 1, drainpipe is headed into landslide 3 by continuation;
(5)Extract the inner tube 13 of drainpipe, the sand taken out in the end scoop 14 of inner tube 13 out;Underground water is discharged along drainpipe 1;
(6)It is repeated in step(4)、(5), treat that the phreatic line 6 in landslide 3 drops to 1-2m or so under landslide surface, excavate Landslide soil, until drainpipe is stretched into sump 5;
(7)Reference picture 7, after landslide soil to the bottom of barricade 10 is excavated, builds barricade 10 by laying bricks or stones, builds the bottom of barricade 10 by laying bricks or stones and set tapping pipe 12, Further arrange underground water, lowering of watertable;
(8)Treat that barricade 10 solidifies, and the phreatic line in landslide 3 is dropped under barricade top surface after 1-2m or so, can the row of extraction out The outer tube 1 of water pipe, utilizes the draining lowering of watertable of tapping pipe 12 of barricade bottom.
Drainpipe of the present invention can discharge the soil layer undergrounds such as bank protection 9, the aqueous sand in the top of barricade 10 and completely weathered granite and ooze Water, can also discharge bank protection 9, the concentration that the inconvenience of the top of barricade 10 is excluded and the larger spring of water, be received specifically by sump 5 Collect bank protection 9, the concentration spring of the top of barricade 10, excluded by drainpipe.
The soil such as bank protection 9, the aqueous sand in the top of barricade 10 and completely weathered granite can be effectively reduced using drainpipe of the present invention Layer level of ground water, it is ensured that bank protection is stable, is easy to bank protection Retaining wall, improves the construction quality of bank protection barricade, it is ensured that engineering construction It is timely completed, using place, cost-effective, Support Construction project smooth implementation and the person of workmen effectively can be ensured Safety.
The present invention is also applied to side slope and landslide sign but the situation not come down has occurred, prevents slope and land slide, reduction construction Aquifer underground water above side slope, is easy to bank protection Retaining wall.
Those skilled in the art can carry out various modifications and variations to the present invention, if these modifications and variations are at this Within the scope of invention claim and its equivalent technologies, then these modifications and variations are also within protection scope of the present invention.
The prior art that the content not being described in detail in specification is known to the skilled person.

Claims (5)

1. a kind of drainpipe, it is characterised in that:Including outer tube, inner tube is provided with the outer tube, said inner tube connects with outer tube activity Connect, said inner tube can be extracted out out of outer tube, the end of said inner tube is provided with scoop, and the scoop is fixedly connected with inner tube.
2. drainpipe as claimed in claim 1, it is characterised in that:The front portion of the outer tube is provided with water hole.
3. drainpipe as claimed in claim 1, it is characterised in that:The circular in cross-section of the outer tube and inner tube.
4. described in a kind of one of utilization claim 1-3 drainpipe processing side slope glide method, it is characterised in that including with Lower step:
(1)By the one end of drainpipe with scoop forward, drainpipe is headed into landslide;
(2)Extract the inner tube of drainpipe, the sand taken out in inner pipe end shovel out, underground water is discharged along drainpipe;
(3)Inner tube is put into outer tube, drainpipe is headed into landslide by continuation;
(4)Extract the inner tube of drainpipe, the sand taken out in inner pipe end scoop out, underground water is discharged along drainpipe;
(5)It is repeated in step(3)、(4), wait that the phreatic line in coming down drops to 1-2m or so under landslide surface, excavate and slide Slope soil, until drainpipe heads into landslide depths;
(6)After landslide soil to barricade bottom is excavated, build barricade by laying bricks or stones, build barricade bottom by laying bricks or stones and set tapping pipe, further arrange underground water, drop Phreatic low;
(7)Treat that barricade solidifies, and the phreatic line in landslide is dropped under barricade top surface after 1-2m or so, utilizes barricade bottom Tapping pipe draining lowering of watertable.
5. the method that the drainpipe processing side slope described in a kind of utilization claim 4 glides, it is characterised in that step(1)Before, There is the neighbouring excavation sump at spring on bank protection top.
CN201710379832.2A 2017-05-25 2017-05-25 Drainpipe and the method that side slope downslide is handled using the drainpipe Pending CN107142923A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710379832.2A CN107142923A (en) 2017-05-25 2017-05-25 Drainpipe and the method that side slope downslide is handled using the drainpipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710379832.2A CN107142923A (en) 2017-05-25 2017-05-25 Drainpipe and the method that side slope downslide is handled using the drainpipe

Publications (1)

Publication Number Publication Date
CN107142923A true CN107142923A (en) 2017-09-08

Family

ID=59780784

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710379832.2A Pending CN107142923A (en) 2017-05-25 2017-05-25 Drainpipe and the method that side slope downslide is handled using the drainpipe

Country Status (1)

Country Link
CN (1) CN107142923A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108166513A (en) * 2018-01-02 2018-06-15 深圳市勘察测绘院有限公司 Anchor hole and the pore-forming technique in the dual-purpose hole of osculum in a kind of dregs side slope
CN113089695A (en) * 2021-05-08 2021-07-09 中国科学院西北生态环境资源研究院 Landslide body side slope ecological restoration structure and method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1427770A (en) * 1973-10-23 1976-03-10 Watanabe H Water duct pipe set for preventing landslides
CN201040878Y (en) * 2007-05-14 2008-03-26 董再发 Excavating-free jacking type drainage pipe
CN201330404Y (en) * 2008-12-25 2009-10-21 归真 Anti-displacement retaining wall
CN201433344Y (en) * 2009-06-07 2010-03-31 中铁西北科学研究院有限公司 Composite protection structure for stabilizing road bed in mountain road
CN102444134A (en) * 2011-10-09 2012-05-09 东南大学 Slope protecting method based on slope with soil layer as upper part and rock layer as lower part
CN103410159A (en) * 2013-08-13 2013-11-27 南昌工程学院 Expansive soil cut slope support structure and construction method thereof
CN103556612A (en) * 2013-10-30 2014-02-05 柏发忠 Water seepage and drainage pipe and construction method thereof
CN106120822A (en) * 2016-08-23 2016-11-16 中国电建集团贵阳勘测设计研究院有限公司 A kind of method for protecting support preventing mud stone from coming down and device
CN106400647A (en) * 2016-09-21 2017-02-15 南京工业大学 Draining pipe applied to drainage and reinforcement of existing expressway side slope and construction method of draining pipe

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1427770A (en) * 1973-10-23 1976-03-10 Watanabe H Water duct pipe set for preventing landslides
CN201040878Y (en) * 2007-05-14 2008-03-26 董再发 Excavating-free jacking type drainage pipe
CN201330404Y (en) * 2008-12-25 2009-10-21 归真 Anti-displacement retaining wall
CN201433344Y (en) * 2009-06-07 2010-03-31 中铁西北科学研究院有限公司 Composite protection structure for stabilizing road bed in mountain road
CN102444134A (en) * 2011-10-09 2012-05-09 东南大学 Slope protecting method based on slope with soil layer as upper part and rock layer as lower part
CN103410159A (en) * 2013-08-13 2013-11-27 南昌工程学院 Expansive soil cut slope support structure and construction method thereof
CN103556612A (en) * 2013-10-30 2014-02-05 柏发忠 Water seepage and drainage pipe and construction method thereof
CN106120822A (en) * 2016-08-23 2016-11-16 中国电建集团贵阳勘测设计研究院有限公司 A kind of method for protecting support preventing mud stone from coming down and device
CN106400647A (en) * 2016-09-21 2017-02-15 南京工业大学 Draining pipe applied to drainage and reinforcement of existing expressway side slope and construction method of draining pipe

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108166513A (en) * 2018-01-02 2018-06-15 深圳市勘察测绘院有限公司 Anchor hole and the pore-forming technique in the dual-purpose hole of osculum in a kind of dregs side slope
CN113089695A (en) * 2021-05-08 2021-07-09 中国科学院西北生态环境资源研究院 Landslide body side slope ecological restoration structure and method

Similar Documents

Publication Publication Date Title
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN104480974B (en) Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN105862887A (en) Ecological slope protection structure for ion rare earth mine
CN103736720A (en) In-situ obstruction governing method of heavy-metal polluted soil
CN106087953B (en) A kind of drainage and construction method for preventing and treating mountain area large size spoil ground mud-rock flow
CN106703044A (en) Flow-plastic-shaped flushing and filling soil weak stratum sloping combination support method
CN111042053A (en) Permanent temporary combined retaining wall structure in urban hydraulic engineering and construction method thereof
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN102535289B (en) Variable-cross-section structure for deep sewer of roadbed and construction method thereof
CN108661073A (en) A kind of barrier wall structure and its construction method
CN107142923A (en) Drainpipe and the method that side slope downslide is handled using the drainpipe
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN208934002U (en) A kind of barrier wall structure
CN208346836U (en) A kind of hidden drainage system
CN106638633A (en) In-situ stable system of clinosol cut slope
CN204551510U (en) A kind of filled-up ground catchments pressure reduction well drop and drainage structure
CN106703053A (en) Construction method for reinforced soil drainage composite revetment structure
CN106245916A (en) The three-dimensional construction method of Group Buildings
CN105112652A (en) Structure of channel for recovering in-situ leaching mother solution of rare earth ore
CN205530299U (en) Ecological slope protection structure in ion type rare earth mine mountain
CN109940033B (en) Foreign soil restoration method for farmland heavy metal pollution
CN206887974U (en) A kind of drainpipe
CN208219672U (en) A kind of rainwater side slope based on mine reclamation
CN110804994A (en) Reservoir dam construction method
CN110106886A (en) A kind of deep pit digging method of underground high water level

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination