CN107142848A - A kind of equipment for bridge construction - Google Patents

A kind of equipment for bridge construction Download PDF

Info

Publication number
CN107142848A
CN107142848A CN201710327327.3A CN201710327327A CN107142848A CN 107142848 A CN107142848 A CN 107142848A CN 201710327327 A CN201710327327 A CN 201710327327A CN 107142848 A CN107142848 A CN 107142848A
Authority
CN
China
Prior art keywords
sliding
trolley shoe
post
face
sliding groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710327327.3A
Other languages
Chinese (zh)
Other versions
CN107142848B (en
Inventor
方明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Teng Teng Intellectual Property Advisory Co., Ltd.
Original Assignee
Xiamen Chenglei Import And Export Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Chenglei Import And Export Co Ltd filed Critical Xiamen Chenglei Import And Export Co Ltd
Priority to CN201710327327.3A priority Critical patent/CN107142848B/en
Publication of CN107142848A publication Critical patent/CN107142848A/en
Application granted granted Critical
Publication of CN107142848B publication Critical patent/CN107142848B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finish Polishing, Edge Sharpening, And Grinding By Specific Grinding Devices (AREA)
  • Cleaning In General (AREA)

Abstract

A kind of equipment for bridge construction of disclosure of the invention, including framework, provided with polishing chamber in framework, the left side at the top of intracavitary is polished provided with the first sliding groove, polish on the right side of chamber provided with the second sliding groove, the beginning set on the right side of framework below second sliding groove provided with left-hand end with polishing chamber UNICOM, polishing intracavitary bottom is respectively arranged on the left side and the right side fastemer and sinker, the the first spiral bar set in first sliding groove provided with left and right expansion, screw thread is connected with the trolley shoe that polishing intracavitary is pierced into bottom on first spiral bar, provided with the first sliding chamber in trolley shoe, first sliding intracavitary is slidably connected with the trolley shoe that rises and falls, rise and fall the raised trolley shoe for being provided with the side roof part of trolley shoe two and being connected with the first sliding chamber both sides sliding fit inside;The present invention is simple in construction, easy to operate, safe, can automatically control the opening and closing of partition panel, and good dustproof effect polishes precisely and stability is high.

Description

A kind of equipment for bridge construction
Technical field
The present invention relates to bridge facility technical field, specifically a kind of equipment for bridge construction.
Background technology
As urban construction is continued to develop, the construction of bridge is also more and more, bridge be generally all erected on rivers lake because This bridge both sides must install railing, and railing is essential safety devices, and when bridge railing moulds shaping, its surface leads to Often uneven, workmen will be processed by shot blasting to railing, generally, and workmen is that hand-held polishing machine is polished, work People's labor intensity is big, wastes time and energy, the surface irregularity after polishing, polishing effect is poor, poor, the traditional stone material of polishing accuracy During processing polished, effective automatism isolation can not be often carried out to railing, and then scene can be caused to kick up substantial amounts of dust And chip disorderly splashes, this not only pollutes environment, also causes great injury to the health of human body of operating personnel.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of equipment for bridge construction, and it can solve the problem that above-mentioned present technology Middle the problem of.
The present invention is achieved through the following technical solutions:A kind of equipment for bridge construction of the present invention, including framework, institute State in framework provided with polishing chamber, the left side at the top of the polishing intracavitary is provided with the first sliding groove, provided with the on the right side of the polishing chamber Provided with left-hand end and opening that the polishing chamber UNICOM is set on the right side of the framework below two sliding grooves, the described second sliding groove End, the polishing intracavitary bottom is respectively arranged on the left side and the right side in fastemer and sinker, the described first sliding groove provided with a left side Screw thread is connected with the cunning that the polishing intracavitary is pierced into bottom on the first spiral bar that right expansion is set, the first spiral bar Connect provided with the first sliding chamber in block, the trolley shoe, the described first sliding intracavitary is slidably connected with the trolley shoe that rises and falls, described Rise and fall the raised trolley shoe for being provided with the side roof part of trolley shoe two and being connected with the described first sliding chamber both sides sliding fit inside, described The trolley shoe bottom end face and sliding connection are ganged up in trolley shoe bottom of rising and falling, be provided with the top of the described first sliding intracavitary to The vertical slot that upper expansion is set, the trolley shoe bottom right side is provided with recessed channel, the female groove provided with left-hand end and described Fall in the post that connects being fixedly connected on the right side of trolley shoe, the trolley shoe that rises and falls provided with the second sliding chamber, the described second sliding chamber top Slipped provided with the 4th sliding groove, the described 4th sliding groove inner top provided with the 3rd in groove, the described 3rd sliding groove provided with left and right in portion Deploy the second spiral bar set, the second spiral bar is provided with the first ejection block that screw thread is connected, and the described 4th slides The second ejection block is provided with access slot, the second ejection block bottom is provided with the joining beam for ganging up the trolley shoe bottom end face that rises and falls, The joining beam caudal is provided with connection block, and the block is interior provided with polishing driving machine, and the polishing driving motor spindle is connected with mounting head And the rubbing head contacted with rail surface, be provided with the rubbing head in multiple mounting grooves, the mounting head provided with it is multiple with Provided with the sliding post for deploying to set to the left in the installation spring that the mounting groove coordinates, the described second sliding groove.
Preferably technical scheme, the first spiral bar left-hand end is matched somebody with somebody with internal turn on the left of the described first sliding groove Connection is closed, the first spiral bar right-hand end is connected with the first driving machine.
Preferably technical scheme, the second spiral bar left-hand end is matched somebody with somebody with internal turn on the left of the described 3rd sliding groove Connection is closed, the second spiral bar right-hand end is connected with the second driving machine.
Preferably technical scheme, the first ejection block bottom is pierced into the described 4th sliding groove, and described first pushes away Jacking block left bottom is provided with the first oblique angle face, and the second ejection block right hand top, which is provided with, to be used to and first oblique angle face ejection Second oblique angle face of sliding connection, second oblique angle face oblique angle length exceeds the oblique angle length in first oblique angle face, The first ejection bullet is wound with outside the described second sliding joining beam between intracavitary bottom and the second ejection block bottom end face Bar.
Provided with arm is connected surely in preferably technical scheme, the described second sliding groove, the arm that connects surely gangs up described Post is connect provided with sideslip in the sliding post and sliding connection in second sliding groove, the sliding post left end face, it is described Connect post right-hand end and pierce into the sideslip and connect in post and at caudal provided with trolley shoe is limited out, it is described to limit out two side ends above and below trolley shoe Face connects with the sideslip respectively to be abutted against above and below post and is slidably matched inside both sides.
Preferably technical scheme, the sideslip connects in the sliding post between post and the second sliding groove and slided Be connected with sliding post, the sliding column top is provided with restraint protruding block, the sliding column bottom is provided with partition panel, it is described every Be wound with the second ejection spring outside the sliding post at the top of disconnected plate between the sliding post, the partition panel bottom end face with The sinker is engaged.
Cleaning plant is provided with the left of preferably technical scheme, the framework, the cleaning plant is by being fixedly installed The dust excluder of outer end on the left of the framework, is fixed on the dust-proof adapter of the dust excluder its right end face and is fixed on described anti- The dust-proof mouth composition of dirt adapter its right end face.
Preferably technical scheme, the fastemer is by pressure-reducing pad and is fixed on end face at the top of the pressure-reducing pad Clamping piece is constituted.
Is fixedly connected in preferably technical scheme, the vertical slot provided with bottom with the trolley shoe top end face that rises and falls Inner thread tube barrel, the inner thread tube barrel screw-internal thread fit is connected with the 3rd spiral bar, connected at the top of the 3rd spiral bar There is the 3rd driving machine, the 3rd driving machine is installed in the vertical slot inner top and is fixedly connected.
The beneficial effects of the invention are as follows:
1. setting the first sliding groove by polishing the left side at the top of intracavitary, first slips the first spiral that left and right expansion setting is set in groove The trolley shoe of polishing intracavitary is pierced into screw thread mating connection bottom on bar, the first spiral bar, and the first spiral bar left-hand end is slided with first Internal turn is connected on the left of access slot, and the first spiral bar right-hand end is connected with the first driving machine, and throwing is automatically controlled so as to realize Bare headed moves left and right polishing.
Set and first 2. being slidably connected by the first sliding intracavitary at the trolley shoe that rises and falls, the side roof part of trolley shoe two that rises and falls The raised trolley shoe of sliding chamber both sides sliding fit inside connection, trolley shoe bottom end face and slip are ganged up in trolley shoe bottom of rising and falling It is connected, is set at the top of the first sliding intracavitary and the second sliding chamber is set in the vertical slot that expansion is set upwards, the trolley shoe that rises and falls, second slides Connect top of chamber and set the 4th sliding groove, the 4th sliding groove inner top, which is set, to be set left and right expansion in the 3rd sliding groove, the 3rd sliding groove and set The second spiral bar, set on the second spiral bar in the first ejection block of screw thread mating connection, the 4th sliding groove and set the second ejection block, Second ejection block bottom sets the joining beam for ganging up the trolley shoe bottom end face that rises and falls, and joining beam caudal sets connection block, so as to realize on rubbing head Lower fine setting work, improves polishing precision.
3. being slidably connected the trolley shoe that rises and falls by the first sliding intracavitary, trolley shoe bottom right side sets recessed channel, recessed Set in groove in left-hand end and the post that connects being fixedly connected on the right side of the trolley shoe that rises and falls, the second sliding groove and set the cunning for deploying to set to the left Connect setting in post, the second sliding groove and connect arm, sliding post and sliding connection that arm is ganged up in the second sliding groove are connected surely, it is sliding Connect and set sideslip in post left end face and connect post, connect post right-hand end and pierce into sideslip and connect in post and trolley shoe of being limited out at caudal, limit out Both sides end face connects with sideslip respectively above and below trolley shoe abuts against above and below post and is slidably matched inside both sides, so as to realize that sliding post edge is fixed Connect arm direction to move up and down, drive partition panel to move up and down, sideslip connects in the sliding post between post and the second sliding groove and slided Be connected sliding post, and sliding column top is limited dynamic protruding block, sliding column bottom set at the top of partition panel, partition panel with sliding post it Between sliding post external rings winding the second ejection spring, partition panel bottom end face is engaged with sinker, so as to realize partition panel With the mating connection of sinker, the opening and closing work to the beginning is realized.
4. the present invention is simple in construction, easy to operate, safe, the opening and closing of partition panel can be automatically controlled, it is dust-proof Effect is good, and polishing is precisely and stability is high.
Brief description of the drawings
For ease of explanation, the present invention is described in detail by following specific embodiment and accompanying drawing.
Fig. 1 is a kind of equipment for bridge construction internal structure schematic diagram of the invention;
Structural representation when Fig. 2 is cut-off plate closing of the invention;
Structural representation when Fig. 3 connects for the rubbing head of the present invention with railing;
Fig. 4 moves left and right structural representation during polishing for a kind of equipment for bridge construction of the present invention;
Fig. 5 is the partial enlarged drawing in Fig. 1 of the present invention.
Embodiment
As Figure 1-Figure 5, provided with polishing in a kind of equipment for bridge construction of the invention, including framework 5, the framework 5 Chamber 51, the left side of the polishing inner top of chamber 51 is provided with the first sliding groove 53, and the right side of polishing chamber 51 is provided with the second sliding groove 54, the right side of the framework 5 of the described second sliding lower section of groove 54 is provided with the beginning that left-hand end is set with polishing chamber 51 UNICOM 52, the polishing inner bottom part of chamber 51 is respectively arranged on the left side and the right side in fastemer 7 and sinker 55, the described first sliding groove 53 The the first spiral bar 531 for deploying to set provided with left and right, on the first spiral bar 531 screw thread be connected with bottom pierce into it is described Polish to slip provided with first in the trolley shoe 6 in chamber 51, the trolley shoe 6 and be slidably matched in chamber 61, the described first sliding chamber 61 It is connected with the trolley shoe 62 that rises and falls, the described 62 liang of side roof parts of trolley shoe that rise and fall and is provided with being slided inside the described first sliding both sides of chamber 61 The dynamic raised trolley shoe 621 being connected, the bottom of trolley shoe 62 of rising and falling, which is ganged up the bottom end face of trolley shoe 6 and slided, matches somebody with somebody Connection is closed, the described first sliding inner top of chamber 61 is provided with the vertical slot 68 that expansion is set upwards, and the bottom right side of trolley shoe 6 is provided with Recessed channel 66, in the female groove 66 provided with left-hand end be fixedly connected on the right side of the trolley shoe 62 that rises and falls connect post 661, institute State and rise and fall provided with the second sliding chamber 63 in trolley shoe 62, the described second sliding top of chamber 63 is provided with the 4th sliding groove 64, described the The four sliding inner tops of groove 64 are provided with the 3rd sliding groove 65, interior the second spiral set provided with left and right expansion of the described 3rd sliding groove 65 Bar 651, the second spiral bar 651 is provided with the first ejection block 653 that screw thread is connected, the described 4th sliding groove 64 and set There is the second ejection block 641, the bottom of the second ejection block 641 is provided with the joining beam for ganging up the bottom end face of trolley shoe 62 that rises and falls 631, the caudal of joining beam 631 is provided with connection block 67, and the block 67 is interior provided with polishing driving machine 671, the polishing driving machine 671 Bottom is connected with mounting head 673 and the rubbing head contacted with rail surface 672, the rubbing head 672 installs provided with multiple Provided with multiple installation springs 674 coordinated with the mounting groove 675 in groove 675, the mounting head 673, by installing spring 674 So as to facilitate rubbing head 672 to mount and dismount, provided with the sliding post 542 for deploying to set to the left in the described second sliding groove 54.
Wherein, the left-hand end of the first spiral bar 531 is connected with the described first sliding left side internal turn of groove 53, institute State the right-hand end of the first spiral bar 531 to be connected with the first driving machine 532, so as to realize that automatically control trolley shoe 6 moves left and right work Make.
Wherein, the left-hand end of the second spiral bar 651 is connected with the described 3rd sliding left side internal turn of groove 65, institute State the right-hand end of the second spiral bar 651 to be connected with the second driving machine 652, so as to realize the left and right for automatically controlling the first ejection block 653 Mobile working.
Wherein, the bottom of the first ejection block 653 is pierced into the described 4th sliding groove 64, and the first ejection block 653 is left Side bottom is provided with the first oblique angle face 6531, and the right hand top of the second ejection block 641, which is provided with, to be used to and first oblique angle face Second oblique angle face 642 of 6531 ejections sliding connection, the oblique angle length of second oblique angle face 642 exceeds first oblique angle The oblique angle length in face 6531, described second is sliding described between the inner bottom part of chamber 63 and the bottom end face of the second ejection block 641 The first ejection spring 632 is wound with outside joining beam 631, so as to realize that the ejection of the first ejection block 653 and the second ejection block 641 is slided Coordinate, control the fine setting work of rubbing head 672, accurately control polishing thickness.
Wherein, provided with arm 541 is connected surely in the described second sliding groove 54, the arm 541 that connects surely gangs up second cunning In the sliding post 542 and sliding connection in access slot 54, the sliding left end face of post 542 post is connect provided with sideslip 5421, it is described connect the right-hand end of post 661 and pierce into the sideslip connect in post 5421 and at caudal provided with trolley shoe 662 is limited out, it is described Limit out trolley shoe about 662 both sides end face post is connect with the sideslip respectively abut against inside both sides and be slidably matched about 5421, from And realize that sliding post 542 is moved up and down along connecting the direction of arm 541 surely, drives partition panel 545 to move up and down.
Wherein, the sideslip connects in the sliding post 542 between post 5421 and the second sliding groove 54 and is slidably matched Sliding post 544 is connected with, the sliding top of post 544 is provided with restraint protruding block 543, and the sliding bottom of post 544 is provided with cut-off The second ejection spring is wound with outside plate 545, the sliding post 544 between the top of partition panel 545 and the sliding post 542 546, the bottom end face of partition panel 545 is engaged with the sinker 55, so as to realize matching somebody with somebody for partition panel 545 and sinker 55 Connection is closed, the opening and closing work to the beginning 52 is realized.
Wherein, cleaning plant 8 is provided with the left side of framework 5, the cleaning plant 8 is by being fixedly installed on the framework 5 The dust excluder 81 of left side outer end, is fixed on the dust-proof adapter 82 of its right end face of dust excluder 81 and is fixed on described dust-proof connect The dust-proof mouth 83 of its right end face of pipe 82 is constituted, so as to prevent airborne dust and chip from causing environmental pollution and health of human body.
Wherein, the fastemer 7 is by pressure-reducing pad 71 and is fixed on the clamping piece 72 of the top end face of pressure-reducing pad 71 Composition, so as to realize the strong fix connection of railing.
Wherein, the riffled tube being fixedly connected in the vertical slot 68 provided with bottom with the top end face of trolley shoe 62 that rises and falls Cylinder 681, the screw-internal thread fit of inner thread tube barrel 681 is connected with the 3rd spiral bar 683, and the top of the 3rd spiral bar 683 connects The 3rd driving machine 684 is connected to, the 3rd driving machine 684 is installed in the inner top of vertical slot 68 and is fixedly connected, so that real Now rise and fall the lifting work of trolley shoe 62 and partition panel 545.
During original state, the top end face of trolley shoe 62 that rises and falls connects with the first sliding inner top of chamber 61, now, connects post 661 top end faces connect with the inner top of recessed channel 66, meanwhile, connect post 661 and drive sliding post 542 to be located at the second sliding groove 54 Top position, now, the ultimate range of partition panel 545 away from sinker 55, meanwhile, the first ejection block 653 be located at the 3rd slide Access slot 65 and the 4th slips the right-most position of groove 64, now, ejection of the second ejection block 641 by the first ejection spring 632 Power, makes the top end face of the second ejection block 641 be connect with the 4th sliding inner top of groove 64, meanwhile, the right side section of the second oblique angle face 642 Connect with the first oblique angle face 6531, now, the connection top end face of block 67 connects with the bottom end face of trolley shoe 62 that rises and falls.
When needing to be polished railing, railing is moved to the top of fastemer 7 after the beginning 52 first, then Railing is engaged by clamping with clamping piece 72, now control the 3rd spiral bar 683 to turn to by the 3rd driving machine 684, by the 3rd spiral shell Shape bar 683 drives inner thread tube barrel 681 and is fixed on the trolley shoe 62 that rises and falls of the bottom of inner thread tube barrel 681 and moves down, this When, the trolley shoe 62 that rises and falls drives the sliding post 542 for connecting post 661 and connecting on post 661 to slip groove 54 in downward direction along second It is mobile, until the raised top end face of trolley shoe 621 connects with the first sliding inner bottom part of chamber 61 as shown in Figure 2, now, cunning of rising and falling Connecing block 62 drives the sliding post 542 for connecting post 661 and connecting on post 661 to be connect with the second sliding inner bottom part of groove 54, meanwhile, In the fully-inserted sinker 55 of the bottom end of partition panel 545, so as to complete close fit connection, the 3rd driving machine 684 is then controlled Stop turning to, while controlling the second driving machine 652 to drive the second spiral bar 651 to turn to, make the second spiral bar 651 drive first to push away Jacking block 653 is moved along the 3rd sliding right direction of groove 65, now, and the first oblique angle face 6531 and the ejection of the second oblique angle face 642 are slided Coordinate, make the second ejection block 641 overcome the ejection force of the first ejection spring 632 in downward direction to be moved along the second sliding chamber 63, this When, the second ejection block 641 drives the connection block 67 of joining beam 631 and the bottom of joining beam 631 to move down, until polishing as shown in Figure 3 First 672 bottom end face connects with banister top end face, now, and the second driving machine 652 of control stops turning to, and finally controls simultaneously Polishing driving machine 671 drives rubbing head 672 to turn to, and the first driving machine 532 drives the positive and reverse steering of the first spiral bar 531 and cleaning Device 8 works, and rubbing head 672 is polished work to banister top end face, while completing dust-proof work by cleaning plant 8 Make, the positive and reverse steering of the first spiral bar 531 is driven by the first driving machine 532, the first spiral bar 531 is driven trolley shoe 6 along the The one sliding left and right directions of groove 53 movement, so as to realize that rubbing head 672 moves left and right polishing to banister top end face, trolley shoe 6 is left Drive to connect post 661 and connect the left and right directions of post 5421 along sideslip and move, now, partition panel 545 and sinker 55 during moving right Keep constant, when needing regulation polishing thickness, by controlling the second driving machine 652 to turn to, the second spiral bar 651 is driven the One ejection block 653 is moved, and railing polishing thickness is automatically adjusted so as to realize.
The beneficial effects of the invention are as follows:
1. setting the first sliding groove by polishing the left side at the top of intracavitary, first slips the first spiral that left and right expansion setting is set in groove The trolley shoe of polishing intracavitary is pierced into screw thread mating connection bottom on bar, the first spiral bar, and the first spiral bar left-hand end is slided with first Internal turn is connected on the left of access slot, and the first spiral bar right-hand end is connected with the first driving machine, and throwing is automatically controlled so as to realize Bare headed moves left and right polishing.
Set and first 2. being slidably connected by the first sliding intracavitary at the trolley shoe that rises and falls, the side roof part of trolley shoe two that rises and falls The raised trolley shoe of sliding chamber both sides sliding fit inside connection, trolley shoe bottom end face and slip are ganged up in trolley shoe bottom of rising and falling It is connected, is set at the top of the first sliding intracavitary and the second sliding chamber is set in the vertical slot that expansion is set upwards, the trolley shoe that rises and falls, second slides Connect top of chamber and set the 4th sliding groove, the 4th sliding groove inner top, which is set, to be set left and right expansion in the 3rd sliding groove, the 3rd sliding groove and set The second spiral bar, set on the second spiral bar in the first ejection block of screw thread mating connection, the 4th sliding groove and set the second ejection block, Second ejection block bottom sets the joining beam for ganging up the trolley shoe bottom end face that rises and falls, and joining beam caudal sets connection block, so as to realize on rubbing head Lower fine setting work, improves polishing precision.
3. being slidably connected the trolley shoe that rises and falls by the first sliding intracavitary, trolley shoe bottom right side sets recessed channel, recessed Set in groove in left-hand end and the post that connects being fixedly connected on the right side of the trolley shoe that rises and falls, the second sliding groove and set the cunning for deploying to set to the left Connect setting in post, the second sliding groove and connect arm, sliding post and sliding connection that arm is ganged up in the second sliding groove are connected surely, it is sliding Connect and set sideslip in post left end face and connect post, connect post right-hand end and pierce into sideslip and connect in post and trolley shoe of being limited out at caudal, limit out Both sides end face connects with sideslip respectively above and below trolley shoe abuts against above and below post and is slidably matched inside both sides, so as to realize that sliding post edge is fixed Connect arm direction to move up and down, drive partition panel to move up and down, sideslip connects in the sliding post between post and the second sliding groove and slided Be connected sliding post, and sliding column top is limited dynamic protruding block, sliding column bottom set at the top of partition panel, partition panel with sliding post it Between sliding post external rings winding the second ejection spring, partition panel bottom end face is engaged with sinker, so as to realize partition panel With the mating connection of sinker, the opening and closing work to the beginning is realized.
4. the present invention is simple in construction, easy to operate, safe, the opening and closing of partition panel can be automatically controlled, it is dust-proof Effect is good, and polishing is precisely and stability is high.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, any The change or replacement expected without creative work, should all be included within the scope of the present invention.Therefore, it is of the invention Protection domain should be determined by the scope of protection defined in the claims.

Claims (9)

1. a kind of equipment for bridge construction, including framework, it is characterised in that:Provided with polishing chamber in framework, the left side at the top of polishing intracavitary Side is provided with the first sliding groove, and polishing chamber right side is provided with the right side of the framework below the second sliding groove, the second sliding groove provided with left-hand end The beginning set with polishing chamber UNICOM, polishing intracavitary bottom is respectively arranged on the left side and the right side fastemer and sinker, and first slides Screw thread is connected with bottom and pierces into polishing intracavitary on the first spiral bar set in access slot provided with left and right expansion, the first spiral bar Trolley shoe, provided with the first sliding chamber in trolley shoe, the first sliding intracavitary is slidably connected with the trolley shoe that rises and falls, risen and fallen sliding The raised trolley shoe being connected with the first sliding chamber both sides sliding fit inside is provided with the side roof part of block two, rise and fall trolley shoe bottom string Provided with the vertical slot that expansion is set upwards, trolley shoe at the top of logical trolley shoe bottom end face and sliding connection, the first sliding intracavitary Bottom right side is provided with recessed channel, connects post provided with what left-hand end and trolley shoe right side of rising and falling were fixedly connected in recessed channel, cunning of rising and falling Connect provided with the second sliding chamber in block, the second sliding top of chamber is slided provided with the 4th sliding groove, the 4th sliding groove inner top provided with the 3rd The the second spiral bar set in access slot, the 3rd sliding groove provided with left and right expansion, the second spiral bar is connected provided with screw thread The second ejection block is provided with first ejection block, the 4th sliding groove, the second ejection block bottom is provided with and gangs up trolley shoe bottom end of rising and falling The joining beam in face, joining beam caudal provided with connection block, connection block in provided with polishing driving machine, polishing driving motor spindle be connected with mounting head and It is provided with multiple mounting grooves, mounting head and matches somebody with somebody provided with multiple with the mounting groove in the rubbing head contacted with rail surface, rubbing head Provided with the sliding post for deploying to set to the left in the installation spring of conjunction, the second sliding groove.
2. a kind of equipment for bridge construction according to claim 1, it is characterised in that:The first spiral bar left-hand end and institute State internal turn on the left of the first sliding groove to be connected, the first spiral bar right-hand end is connected with the first driving machine.
3. a kind of equipment for bridge construction according to claim 1, it is characterised in that:The second spiral bar left-hand end and institute State internal turn on the left of the 3rd sliding groove to be connected, the second spiral bar right-hand end is connected with the second driving machine.
4. a kind of equipment for bridge construction according to claim 1, it is characterised in that:Institute is pierced into the first ejection block bottom State in the 4th sliding groove, the first ejection block left bottom is provided with the first oblique angle face, and the second ejection block right hand top is set There is the second oblique angle face to be slidably connected with the ejection of first oblique angle face, face oblique angle length in second oblique angle exceeds The oblique angle length in first oblique angle face, the described second sliding institute between intracavitary bottom and the second ejection block bottom end face State and the first ejection spring is wound with outside joining beam.
5. a kind of equipment for bridge construction according to claim 1, it is characterised in that:It is provided with and leads surely in described second sliding groove Arm is connect, described to connect the sliding post and the sliding connection that arm is ganged up in the described second sliding groove surely, the sliding post is left Connect post provided with sideslip in side end face, it is described connect post right-hand end and pierce into the sideslip connect in post and sliding provided with limiting out at caudal Block, it is described limit out both sides end face above and below trolley shoe and connect respectively with the sideslip above and below post abut against and be slidably matched inside both sides.
6. a kind of equipment for bridge construction according to claim 5, it is characterised in that:The sideslip connects post and slided with described second Sliding post is slidably connected with the sliding post between access slot, the sliding column top is provided with restraint protruding block, described Sliding column bottom is wound with second provided with partition panel, outside the sliding post between the partition panel top and the sliding post and pushed away Spring is pushed up, the partition panel bottom end face is engaged with the sinker.
7. a kind of equipment for bridge construction according to claim 1, it is characterised in that:Provided with cleaning dress on the left of the framework Put, the cleaning plant is fixed on the dust excluder its right end face by being fixedly installed on the dust excluder of outer end on the left of the framework Dust-proof adapter and be fixed on the dust-proof adapter its right end face dust-proof mouth composition.
8. a kind of equipment for bridge construction according to claim 1, it is characterised in that:The fastemer by pressure-reducing pad and It is fixed on the clamping piece composition of end face at the top of the pressure-reducing pad.
9. a kind of equipment for bridge construction according to claim 1, it is characterised in that:In the vertical slot provided with bottom with it is described The inner thread tube barrel that the trolley shoe top end face that rises and falls is fixedly connected, the inner thread tube barrel screw-internal thread fit is connected with the 3rd spiral Be connected with the 3rd driving machine at the top of bar, the 3rd spiral bar, the 3rd driving machine be installed in the vertical slot inner top and It is fixedly connected.
CN201710327327.3A 2017-05-10 2017-05-10 A kind of equipment for bridge construction Active CN107142848B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710327327.3A CN107142848B (en) 2017-05-10 2017-05-10 A kind of equipment for bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710327327.3A CN107142848B (en) 2017-05-10 2017-05-10 A kind of equipment for bridge construction

Publications (2)

Publication Number Publication Date
CN107142848A true CN107142848A (en) 2017-09-08
CN107142848B CN107142848B (en) 2019-02-26

Family

ID=59778064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710327327.3A Active CN107142848B (en) 2017-05-10 2017-05-10 A kind of equipment for bridge construction

Country Status (1)

Country Link
CN (1) CN107142848B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107583926A (en) * 2017-11-01 2018-01-16 毛利英 A kind of vessel cleaning equipment
CN107795275A (en) * 2017-10-13 2018-03-13 王世美 A kind of mining machine
CN108212981A (en) * 2017-11-01 2018-06-29 韦华新 A kind of follow-on vessel cleaning equipment
CN108212982A (en) * 2017-11-01 2018-06-29 韦华新 A kind of novel vessel cleaning equipment

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110219554A1 (en) * 2010-03-15 2011-09-15 Aumuller Paul M Bridge construction and method of replacing bridges
CN104480857A (en) * 2014-12-04 2015-04-01 熊达煜 Highway bridge outer edge modularized guardrail structure and mounting construction method thereof
CN104631496A (en) * 2015-02-16 2015-05-20 中交四航局第二工程有限公司 Temporary passage above ballast tank and passage mounting method
KR200479049Y1 (en) * 2015-08-07 2015-12-11 (주)효명 Footbridge of bridge extended structure
CN105568850A (en) * 2015-12-24 2016-05-11 上海市城市建设设计研究总院 Prefabricated crash barrier connecting structure facilitating installation of telescopic device and assembling method thereof
CN106245526A (en) * 2016-09-30 2016-12-21 中铁上海工程局集团有限公司 The splicing structure of mining under railways protecting wall, straight wall and shield and construction method
CN106400691A (en) * 2016-10-29 2017-02-15 中交航局第工程有限公司 Integrated construction process for anti-collision wall formwork

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110219554A1 (en) * 2010-03-15 2011-09-15 Aumuller Paul M Bridge construction and method of replacing bridges
CN104480857A (en) * 2014-12-04 2015-04-01 熊达煜 Highway bridge outer edge modularized guardrail structure and mounting construction method thereof
CN104631496A (en) * 2015-02-16 2015-05-20 中交四航局第二工程有限公司 Temporary passage above ballast tank and passage mounting method
KR200479049Y1 (en) * 2015-08-07 2015-12-11 (주)효명 Footbridge of bridge extended structure
CN105568850A (en) * 2015-12-24 2016-05-11 上海市城市建设设计研究总院 Prefabricated crash barrier connecting structure facilitating installation of telescopic device and assembling method thereof
CN106245526A (en) * 2016-09-30 2016-12-21 中铁上海工程局集团有限公司 The splicing structure of mining under railways protecting wall, straight wall and shield and construction method
CN106400691A (en) * 2016-10-29 2017-02-15 中交航局第工程有限公司 Integrated construction process for anti-collision wall formwork

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795275A (en) * 2017-10-13 2018-03-13 王世美 A kind of mining machine
CN107583926A (en) * 2017-11-01 2018-01-16 毛利英 A kind of vessel cleaning equipment
CN108212981A (en) * 2017-11-01 2018-06-29 韦华新 A kind of follow-on vessel cleaning equipment
CN108212982A (en) * 2017-11-01 2018-06-29 韦华新 A kind of novel vessel cleaning equipment

Also Published As

Publication number Publication date
CN107142848B (en) 2019-02-26

Similar Documents

Publication Publication Date Title
CN107142848A (en) A kind of equipment for bridge construction
CN106985055A (en) One kind is used for equipment for bridge construction
CN106041663B (en) A kind of sleeve part endoporus burr remover
CN107088799A (en) A kind of Decorative Building Stone sanding apparatus of dustless environment protecting
CN204868488U (en) Bearing axial burnishing machine
CN107081659A (en) A kind of stone material sanding apparatus of dustless environment protecting
CN107097112B (en) A kind of Decorative Building Stone grinding device of environmental protection
CN103240772A (en) Cutting device for processing butt joint between guitar neck and upper end of guitar case
CN106002585A (en) Automatic polishing machine for outer wall of cylinder
CN112792645A (en) A kind of building wall automatic grinding robot and automatic grinding method
CN107009241B (en) A kind of be used to polish building stone and the sander with unilateral chamfering polishing function
CN209579048U (en) A kind of automatic wall grinding equipment
CN204248640U (en) Optical mirror slip milling and grinding machine automatic feeder
CN206383041U (en) a repairing machine
CN105478932A (en) Automatic bolt finish-machining device and bolt finish-machining method adopting same
CN214869244U (en) Automatic polishing robot for building wall surface
CN206200687U (en) An automatic glue spraying and polishing equipment based on vision positioning
CN205587966U (en) Portable and efficient processingequipment of processing head
CN105773185A (en) Machining device with movable machining head and controlled by motor to ascend and descend
CN203236556U (en) Cutting device for processing butt joint site of guitar neck and upper end part of guitar box
CN204525069U (en) A kind of lock core automatic end facing sand grinding machine
CN205437501U (en) Processingequipment of portable and liftable of processing head
CN209986753U (en) VR reduction gear part grinder
CN106312835A (en) Efficient and rapid sand blasting device for mold
CN105798764A (en) Horizontal numerical control glue scraping grinder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20181228

Address after: Room 1, 1903, No. 3, Marriott City, 298 Yinhuan Road, Xihu District, Nanchang City, Jiangxi Province

Applicant after: Jiangxi golden Xuan Enterprise Consulting Service Co., Ltd.

Address before: 361021 2nd Floor, 72 Le'an Dongli, Qiaoying Street, Jimei District, Xiamen City, Fujian Province

Applicant before: XIAMEN CHENGLEI IMPORT AND EXPORT CO., LTD.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190114

Address after: 234000 north of Yinhe two road, Suzhou, Anhui. Room 1602, building B1, south of the chime Road,

Applicant after: Suzhou Teng Teng Intellectual Property Advisory Co., Ltd.

Address before: Room 1, 1903, No. 3, Marriott City, 298 Yinhuan Road, Xihu District, Nanchang City, Jiangxi Province

Applicant before: Jiangxi golden Xuan Enterprise Consulting Service Co., Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant