CN107109837A - Possess the precast concrete part and the precast concrete component bonding method using the precast concrete part of engagement member - Google Patents
Possess the precast concrete part and the precast concrete component bonding method using the precast concrete part of engagement member Download PDFInfo
- Publication number
- CN107109837A CN107109837A CN201680004575.8A CN201680004575A CN107109837A CN 107109837 A CN107109837 A CN 107109837A CN 201680004575 A CN201680004575 A CN 201680004575A CN 107109837 A CN107109837 A CN 107109837A
- Authority
- CN
- China
- Prior art keywords
- precast concrete
- pca
- steel bar
- concrete part
- joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/61—Connections for building structures in general of slab-shaped building elements with each other
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B1/4114—Elements with sockets
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/02—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
- E04B1/04—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
- E04B1/043—Connections specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B1/4114—Elements with sockets
- E04B1/4135—Elements with sockets receiving removal bolt heads
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B1/4157—Longitudinally-externally threaded elements extending from the concrete or masonry, e.g. anchoring bolt with embedded head
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/12—Mounting of reinforcing inserts; Prestressing
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B2001/4192—Connecting devices specially adapted for embedding in concrete or masonry attached to concrete reinforcing elements, e.g. rods or wires
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2103/00—Material constitution of slabs, sheets or the like
- E04B2103/02—Material constitution of slabs, sheets or the like of ceramics, concrete or other stone-like material
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
- Mechanical Engineering (AREA)
Abstract
Description
技术领域technical field
本发明涉及具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法。The present invention relates to a precast concrete part including a joining member and a precast concrete part joining method using the precast concrete part.
背景技术Background technique
一直以来,作为建筑物的省力化施工法,使用了预制混凝土(以下,存在标记为“PCa”的情况)部件。这样的PCa部件在工厂里制造,因此,与在建筑现场装入钢筋并浇筑混凝土的情况相比,由于能够不受雨等天气影响地进行养护等,因此质量稳定,并且具有建筑现场的模板工或钢筋工较少即可从而能够节省劳动力、以及建筑方法简单且能够缩短工期等许多优点,广泛应用于建筑物的柱或梁、(抗震)壁、楼板或者阳台等。Conventionally, as a labor-saving construction method for buildings, precast concrete (hereinafter, sometimes referred to as "PCa") components have been used. Such PCa parts are manufactured in a factory, so compared with the case of installing steel bars and pouring concrete at the construction site, since it can be cured without being affected by weather such as rain, the quality is stable, and there is a formwork at the construction site. Or reinforcement workers can save labor, and the construction method is simple and can shorten the construction period and many other advantages. It is widely used in columns or beams, (seismic) walls, floors or balconies of buildings.
并且,在将这样的PCa部件彼此相互接合在一起的情况下,例如采用图22或图23所示那样的接合结构。And, when joining such PCa members to each other, for example, a joining structure as shown in FIG. 22 or FIG. 23 is employed.
其中,上述的图22所示的例子是这样的结构:在上述那样的PCa部件2100和2200的侧面,分别预先突出地形成有构成所述PCa部件自身的钢筋900P。并且,在上述的图22中,示出了将上述钢筋900P在水平方向上设置成双钢筋配置的例子,并且示出了在上述PCa部件2100和2200的侧面的接合部分处设有楔的例子。However, the example shown in FIG. 22 mentioned above has a structure in which reinforcing bars 900P constituting the PCa members themselves are respectively protrudingly formed on the side surfaces of the above-mentioned PCa members 2100 and 2200 . In addition, in the above-mentioned FIG. 22 , an example in which the above-mentioned reinforcing bar 900P is arranged in the horizontal direction as a double-bar configuration is shown, and an example in which a wedge is provided at the junction of the side surfaces of the above-mentioned PCa members 2100 and 2200 is shown. .
因此,在进行上述图22所示结构的PCa部件的接合的情况下,使上述PCa部件2100和2200相互接近,在接合部分处,使上述的各个PCa部件的钢筋互相重合、或者使接合筋抵靠在一起后进行喇叭形坡口焊接来实现连接,进而,在上述接合部分现场浇筑而浇筑混凝土从而实现一体化,确保了结构上的安全性。Therefore, in the case of joining the PCa members of the structure shown in FIG. 22, the above-mentioned PCa members 2100 and 2200 are approached to each other, and at the joint portion, the reinforcing bars of the above-mentioned PCa members are overlapped with each other, or the joint ribs are abutted against each other. After they are close together, they are connected by trumpet-shaped groove welding, and then concrete is poured on-site at the above-mentioned joint parts to realize integration and ensure structural safety.
另外,上述的图23所示的例子例如是这样的结构:在进行上下层的PCa壁的接合的情况下,如图23的(A)那样在PCa部件2300的侧面突出地形成有钢筋900P,在与该PCa部件2300接合的PCa部件2400的侧面侧,如图23的(B)所示,埋入有钢筋接头2410。In addition, the example shown in the above-mentioned FIG. 23 is, for example, such a structure: when the PCa walls of the upper and lower layers are joined, as shown in FIG. On the side surface of the PCa member 2400 joined to the PCa member 2300 , as shown in FIG. 23(B) , a reinforcing bar joint 2410 is embedded.
因此,在进行上述图23所示结构的PCa部件的接合的情况下,成为了如下的结构:如图23的(C)所示,在接合部分设置20mm左右的间隙后,将在上述PCa部件2300上突出的钢筋900P插入到被埋入于上述PCa部件2400中的钢筋接头2410内,利用灰浆注入口2413将砂浆等灰浆注入上述钢筋接头2410内和上述接合部分的间隙中,从灰浆排出口2415确认填充,然后将插入的钢筋900P固定。Therefore, in the case of joining the PCa member having the structure shown in FIG. 23 above, it becomes a structure as follows: As shown in FIG. The rebar 900P protruding from 2300 is inserted into the rebar joint 2410 embedded in the PCa member 2400, and mortar such as mortar is injected into the rebar joint 2410 and the gap between the joint parts through the mortar injection port 2413, and then discharged from the mortar outlet. 2415 Confirm the filling, and then fix the inserted reinforcement 900P.
可是,在采用了上述那样的结构的方法中,关于使用了上述PCa部件的壁体等的接合,由于需要通过上述图23的方法来接合上下层的PCa壁,对于同层的PCa壁或PCa柱与PCa壁的接合,为了进行上述钢筋相互的连接作业,需要在确保了一定以上的间隔来进行上述那样的钢筋连接后在建筑现场进行混凝土的浇筑,因此,具有难以实现完全预制化这样的课题,还存在现场的作业上的负担增大而导致成本升高这样的课题。However, in the method adopting the above-mentioned structure, regarding the joining of the walls and the like using the above-mentioned PCa members, since it is necessary to join the PCa walls of the upper and lower layers by the method of the above-mentioned FIG. The connection between the column and the PCa wall requires concrete pouring at the construction site after securing a certain interval or more to connect the steel bars as described above in order to perform the above-mentioned connection work of the steel bars. Therefore, it is difficult to realize complete prefabrication. As a problem, there is also a problem that the burden on the on-site work increases, resulting in an increase in cost.
另外,在预先在上述那样的PCa部件的侧面突出地形成有钢筋的情况下,也存在如下可能:使上述的突出的钢筋形成为在末端相互封闭这样的形状,或者弯折90度而形成上述的突出的钢筋,从而结构变得复杂,PCa部件在工厂的制造变得复杂,成为成本上升的重要原因。In addition, when reinforcing bars are protrudingly formed on the side surfaces of the above-mentioned PCa members in advance, it is also possible to form the above-mentioned protruding reinforcing bars into a shape that is closed to each other at the ends, or to form the above-mentioned bars by bending them at 90 degrees. The protruding steel bars make the structure complicated, and the manufacturing of PCa parts in the factory becomes complicated, which becomes an important reason for the cost increase.
另外,在如上述那样预先在PCa部件的侧面突出地形成有钢筋的情况下,由于还存在这些突出的钢筋如上述那样在末端具有复杂结构的情况等,因此,具有上述突出的钢筋在运输过程中变形而弯折的问题,由于钢筋突出,因此还存在危险性,还存在需要保管的场所等问题。In addition, in the case where reinforcing bars are protrudingly formed on the side surfaces of the PCa member as described above, since these protruding reinforcing bars may have complicated structures at the ends as described above, the protruding reinforcing bars may be damaged during transportation. There is also the problem of deformation and bending in the middle, because the steel bars protrude, so there is still danger, and there are also problems such as places that need to be kept.
因此,作为不像这样预先使钢筋从PCa部件的侧面突出的结构,例如公开了日本特开2015-200146号公报(专利文献1)所记载的技术。Therefore, as a structure that does not protrude the reinforcing bar from the side surface of the PCa member in advance, for example, the technique described in JP 2015-200146 A (Patent Document 1) is disclosed.
并且,在上述专利文献1中公开了一种预制混凝土部件的接合方法,其特征在于,在一个预制混凝土部件中内设特殊套筒,在该特殊套筒中内置有嵌筋(连接用的钢筋)和嵌筋(连接用的钢筋)的推出机构,利用推出机构将嵌筋朝向对方侧预制混凝土部件的套筒推出而插入。And, in the above-mentioned patent document 1, disclose a kind of joining method of precast concrete part, it is characterized in that, set special sleeve in one precast concrete part, in this special sleeve, insert bar (reinforcing bar for connection) ) and the inserting bar (reinforcement for connection) push-out mechanism, use the push-out mechanism to push the inserting bar toward the sleeve of the precast concrete part on the other side and insert it.
在先技术文献prior art literature
专利文献patent documents
专利文献1:日本特开2015-200146号公报Patent Document 1: Japanese Patent Laid-Open No. 2015-200146
发明内容Contents of the invention
发明所要解决的课题The problem to be solved by the invention
可是,对于上述专利文献1所记载的技术,其技术课题与本发明不同,课题在于,在使梁部件接合的情况下,使钢筋在进行接合的部件之间穿过而未伴随有上述梁部件的横向移动,因此上述专利文献1所记载的技术适用于以柱、梁为中心的轴组结构,而不适用于壁或地板等壁式(抗震壁)结构。因此,壁或地板等壁式(抗震壁)结构采用不预先使钢筋从PCa部件的侧面突出的结构,并不会容易地进行PCa部件的接合。However, the technology described in the above-mentioned Patent Document 1 has a technical problem different from that of the present invention. The problem is that, in the case of joining beam members, the steel bar is passed between the members to be joined without the above-mentioned beam member. Therefore, the technology described in Patent Document 1 above is applicable to shaft group structures centered on columns and beams, but not to wall (seismic wall) structures such as walls or floors. Therefore, if a wall-type (seismic-resistant wall) structure such as a wall or a floor does not have a structure in which reinforcing bars protrude from the side surfaces of the PCa members, it is not easy to join the PCa members.
另外,在上述专利文献1所公开的技术中,还采用了如下这样的复杂结构:在预制混凝土部件中不但内置嵌筋,还内置有螺旋弹簧等的嵌筋的推出机构。因此,在将这些部件设置于上述预制混凝土部件内部的情况下,需要将上述螺旋弹簧等压缩后设置于特殊套筒内的嵌筋后部,此外还需要设置卡定止动件等,从而在制造工序上花的工夫过大。In addition, the technology disclosed in the above-mentioned Patent Document 1 adopts a complicated structure in which not only the bead is built into the precast concrete member, but also a mechanism for pushing out the bead, such as a coil spring, is built in. Therefore, when these components are installed inside the above-mentioned precast concrete parts, it is necessary to compress the above-mentioned coil springs and the like and install them at the rear of the ribs in the special sleeve, and also to provide locking stoppers, etc., so that Too much effort is spent on the manufacturing process.
另外,在上述专利文献1所公开的技术中,预先设置了上述推出机构,结果是,被推出的嵌筋的长度预先被推出机构确定,因此存在无法对应于待接合的预制混凝土部件进行长度的调整这一问题。另外,一旦卸下上述卡定止动件,则无法使如上述那样被推出的嵌筋复原,因此还存在如下问题:即使需要对应于建设现场的情况重新进行作业,也无法重新进行作业。In addition, in the technology disclosed in the above-mentioned Patent Document 1, the above-mentioned push-out mechanism is provided in advance, and as a result, the length of the bead to be pushed out is determined in advance by the push-out mechanism, so there is a possibility that the length cannot be determined corresponding to the precast concrete parts to be joined. Adjust this question. In addition, once the locking stopper is removed, the bead pushed out as described above cannot be restored. Therefore, there is also a problem that even if the work needs to be carried out again according to the situation of the construction site, the work cannot be carried out again.
因此,本发明的目的在于解决上述课题或问题,本发明的课题在于提供如下的具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法:尽可能消除后浇筑的现场混凝土,实现完全预制化,同时以建筑物的壁或地板等壁式(抗震壁)结构为中心,不预先使钢筋从PCa部件的侧面突出,并且使用比较简便的结构就能够容易地进行PCa部件的接合。Therefore, the object of the present invention is to solve the above-mentioned problems or problems, and the subject of the present invention is to provide a precast concrete part having a joining member and a method for joining precast concrete parts using the precast concrete part as follows: , to achieve complete prefabrication, and at the same time center on the wall (seismic wall) structure such as the wall or floor of the building, without pre-protruding the reinforcement from the side of the PCa component, and use a relatively simple structure to easily carry out the PCa component join.
用于解决问题的手段means of solving problems
为了解决上述课题,本发明提供具备接合构件的预制混凝土部件,其特征在于,所述接合构件具备:管状部件,其设置于所述预制混凝土部件;和钢筋,其以能够移动的方式装入于所述管状部件内,所述钢筋构成为,在接合时能够从所述预制混凝土部件的侧面拉出任意长度。In order to solve the above-mentioned problems, the present invention provides a precast concrete part including a joining member, wherein the joining member includes: a tubular member provided on the precast concrete part; In the tubular part, the reinforcement is configured to be able to be pulled out to any length from the side of the precast concrete part when joined.
另外,为了解决上述课题,本发明提供第2预制混凝土部件,其是具备引导通道的预制混凝土部件(第2预制混凝土部件),所述引导通道用于将所述钢筋从所述具备接合构件的预制混凝土部件(第1预制混凝土部件)的所述管状部件(第1管状部件)拉出,所述第2预制混凝土部件与所述第1预制混凝土部件的侧面侧接合,所述引导通道由管状部件(第2管状部件)形成,所述第2管状部件的一个开口部在所述第2预制混凝土部件的和所述第1预制混凝土部件接合的侧面侧,与设置于所述第1预制混凝土部件中的第1管状部件的开口部对置地设置,所述第2管状部件的另一个开口部形成于所述第2预制混凝土部件的正面侧,从所述第2预制混凝土部件的所述另一个开口部向所述一个开口部的方向插入钢筋拉出构件,从而能够将装入于所述第1预制混凝土部件的所述第1管状部件中的所述钢筋拉出。In addition, in order to solve the above-mentioned problems, the present invention provides a second precast concrete part which is a precast concrete part (second precast concrete part) provided with a guide passage for guiding the steel bar from the joint member provided with the connecting member. The tubular part (first tubular part) of the precast concrete part (first precast concrete part) is pulled out, the second precast concrete part is joined to the side of the first precast concrete part, and the guide channel is formed by a tubular member (second tubular member), one opening of the second tubular member is provided on the side surface side of the second precast concrete member joined to the first precast concrete member, and is provided on the first precast concrete member. The openings of the first tubular member in the parts are oppositely arranged, the other opening of the second tubular member is formed on the front side of the second precast concrete part, and the other opening of the second precast concrete part One opening is inserted in the direction of the one opening so that the reinforcing bar inserted into the first tubular member of the first precast concrete part can be drawn out.
另外,为了解决上述课题,本发明提供一种预制混凝土部件的接合方法,其是所述具备接合构件的第1预制混凝土部件和所述第2预制混凝土部件接合的接合方法,将所述第1预制混凝土部件的侧面和所述第2预制混凝土部件的侧面抵接,从所述第2预制混凝土部件的另一个开口部插入所述钢筋拉出构件,将所述钢筋的一部分拉出至所述第2预制混凝土部件的引导通道内,并将所述钢筋分别固定于所述第1预制混凝土部件和所述第2预制混凝土部件,由此进行接合。In addition, in order to solve the above-mentioned problems, the present invention provides a joining method of precast concrete parts, which is a joining method of joining the first precast concrete part including the joining member and the second precast concrete part, wherein the first The side surface of the precast concrete part is in contact with the side surface of the second precast concrete part, and the reinforcing bar pulling member is inserted from the other opening of the second precast concrete part to pull out a part of the reinforcing bar to the second precast concrete part. In the guide passage of the second precast concrete part, the steel bars are respectively fixed to the first precast concrete part and the second precast concrete part to join together.
另外,为了解决上述课题,本发明提供一种具备接合构件的预制混凝土部件,其特征在于,所述接合构件具备:钢筋接头,其设置于所述预制混凝土部件;和钢筋,其以能够移动的方式装入于所述钢筋接头内,所述钢筋构成为,在接合时能够从所述预制混凝土部件的侧面拉出任意长度。In addition, in order to solve the above-mentioned problems, the present invention provides a precast concrete part including a connecting member, wherein the connecting member includes: a steel bar joint provided on the precast concrete part; The steel bars are installed in the joints of the steel bars in such a way that they can be pulled out to any length from the sides of the precast concrete parts when they are joined.
另外,为了解决上述课题,本发明提供第4预制混凝土部件,其是具备引导通道的预制混凝土部件(第4预制混凝土部件),所述引导通道用于将所述钢筋从所述的具备接合构件的预制混凝土部件(第3预制混凝土部件)的所述钢筋接头(第1钢筋接头)拉出,所述钢筋在一端侧形成有卡定件,所述第4预制混凝土部件与所述第3预制混凝土部件的侧面侧接合,所述引导通道由钢筋接头(第2钢筋接头)形成,所述第2钢筋接头的一端侧在与所述第4预制混凝土部件的和所述第3预制混凝土部件接合的侧面侧,与设置于所述第3预制混凝土部件中的第1钢筋接头的一端侧对置地设置,在所述第2钢筋接头的另一端侧贯插有构成所述第4预制混凝土部件的钢筋,在所述第2钢筋接头的轴向的中央部设置有线贯插部,该线贯插部是与所述第4预制混凝土部件的正面侧连通的开口部,从所述第4预制混凝土部件的所述线贯插部向所述第2钢筋接头的内部插入线,将所述线与装入于所述第3预制混凝土部件的所述第1钢筋接头中的所述钢筋的卡定部连接,从而能够将所述钢筋拉出至所述第2钢筋接头的内部。In addition, in order to solve the above-mentioned problems, the present invention provides a fourth precast concrete part which is a precast concrete part (fourth precast concrete part) provided with a guide passage for guiding the steel bar from the joint member provided with the above-mentioned The steel bar joint (first steel bar joint) of the precast concrete part (the third precast concrete part) is pulled out, and a locking part is formed on one end side of the steel bar, and the fourth precast concrete part is connected to the third precast concrete part. The side faces of the concrete parts are joined, the guide channel is formed by a steel bar joint (second steel bar joint), and one end side of the second steel bar joint is joined to the fourth precast concrete part and the third precast concrete part The side surface side of the third precast concrete part is provided to face one end side of the first steel bar joint provided in the third precast concrete part, and the other end side of the second steel bar joint is inserted to form the fourth precast concrete part. The steel bar is provided with a line insertion portion at the axial center of the second steel bar joint, and the line insertion portion is an opening communicating with the front side of the fourth precast concrete member. The wire insertion portion of the component inserts a wire into the second steel bar joint, and locks the wire with the steel bar incorporated in the first steel bar joint of the third precast concrete component. part connection, so that the steel bar can be pulled out to the inside of the second steel bar joint.
另外,为了解决上述课题,本发明提供一种预制混凝土部件的接合方法,其是所述具备接合构件的第3预制混凝土部件和所述第4预制混凝土部件接合的接合方法,将所述第3预制混凝土部件的侧面和所述第4预制混凝土部件的侧面抵接,从形成于所述第4预制混凝土部件中的所述第2钢筋接头的线贯插部插入所述线,将所述线与装入于所述第3预制混凝土部件的所述第1钢筋接头中的所述钢筋的卡定部连接,将所述钢筋拉出至所述第2钢筋接头内部,并将所述钢筋分别固定于所述第3预制混凝土部件的所述第1钢筋接头的内部和所述第4预制混凝土部件的第2钢筋接头的内部。In addition, in order to solve the above-mentioned problems, the present invention provides a method of joining precast concrete parts, which is a method of joining the third precast concrete part including the joining member and the fourth precast concrete part, and the third precast concrete part is combined with the third precast concrete part. The side surface of the precast concrete part is in contact with the side surface of the fourth precast concrete part, the wire is inserted from the wire insertion part of the second reinforcement joint formed in the fourth precast concrete part, and the wire connected to the locking portion of the steel bar installed in the first steel bar joint of the third precast concrete part, the steel bar is pulled out to the inside of the second steel bar joint, and the steel bars are respectively It is fixed inside the first steel bar joint of the third precast concrete part and inside the second steel bar joint of the fourth precast concrete part.
另外,为了解决上述课题,本发明提供一种具备接合构件的预制混凝土部件,其特征在于,所述接合构件具备:管状部件,其设置于所述预制混凝土部件;和钢筋,其以能够移动的方式装入于所述管状部件内,所述管状部件是螺纹钢筋接头,所述钢筋是螺纹钢筋,在接合前能够将所述螺纹钢筋装入到所述螺纹钢筋接头的内侧,所述螺纹钢筋构成为,在进行所述接合时能够从所述预制混凝土部件的侧面拉出任意长度。In addition, in order to solve the above-mentioned problems, the present invention provides a precast concrete part including a joining member, wherein the joining member includes: a tubular member provided on the precast concrete part; The tubular part is loaded into the tubular part in a manner, the tubular part is a threaded steel bar joint, the steel bar is a threaded steel bar, and the threaded steel bar can be loaded into the inner side of the threaded steel bar joint before joining, and the threaded steel bar It is configured such that it can be pulled out to an arbitrary length from the side surface of the precast concrete member when performing the joining.
另外,为了解决上述课题,本发明提供一种具备接合构件的预制混凝土部件,其特征在于,所述接合构件具备:管状部件,其设置于所述预制混凝土部件;和钢筋,其以能够移动的方式装入于所述管状部件内,在所述管状部件的内侧形成有内螺纹,所述钢筋是与所述内螺纹螺合的全螺纹螺栓,在接合前能够使所述内螺纹螺纹进给而装入到所述管状部件的内侧,所述内螺纹构成为,在进行所述接合时能够螺纹进给而从所述预制混凝土部件的侧面拉出任意长度。In addition, in order to solve the above-mentioned problems, the present invention provides a precast concrete part including a joining member, wherein the joining member includes: a tubular member provided on the precast concrete part; The internal thread is formed on the inner side of the tubular part, and the steel bar is a fully threaded bolt that is screwed with the internal thread, so that the internal thread can be threaded before being engaged. While being incorporated into the inner side of the tubular member, the internal thread is configured to be able to be threaded and pulled out from the side of the precast concrete member by an arbitrary length during the joining.
另外,为了解决上述课题,本发明提供一种预制混凝土部件的接合方法,在向所述管状部件中装入钢筋时,将密封用管状部件与所述钢筋一起装入,其中该密封用管状部件绕所述钢筋的轴向而围绕在所述管状部件的入口侧的周围,在接合所述具备接合构件的预制混凝土部件和另一预制混凝土部件时,使所述密封用管状部件与所述钢筋一起在所述钢筋的周围连通在所述具备接合构件的预制混凝土部件和另一预制混凝土部件之间来进行接合。In addition, in order to solve the above-mentioned problems, the present invention provides a method of joining precast concrete parts, wherein when a reinforcing bar is inserted into the tubular part, a sealing tubular part is put together with the reinforcing bar, wherein the sealing tubular part Wrapping around the entrance side of the tubular member around the axial direction of the reinforcing bar, when joining the precast concrete part including the joining member and another precast concrete part, the sealing tubular part and the reinforcing bar Jointing is performed between the precast concrete part provided with the joint member and another precast concrete part through the periphery of the reinforcing bar together.
发明效果Invention effect
在本发明中,采用了如下的结构和方法:预先将钢筋以能够移动的方式装入到设置有管状部件的第1PCa部件的所述管状部件内,在使所述第1PCa部件相互之间、或者所述第1PCa部件和另一PCa部件(例如,第2PCa部件)相互接合的情况下,将钢筋从所述第1PCa部件拉出至另一第1PCa部件或者将所述钢筋从所述第2PCa部件拉出至所述第1PCa部件,连通在所述第1PCa部件相互之间、或者连通在所述第1PCa部件和第2PCa部件之间,将所述钢筋配置成跨越这些欲接合的PCa部件相互之间,并且将所述移动后的钢筋的两端侧分别固定于所述待接合的PCa部件,从而能够使所述PCa部件相互接合。In the present invention, the following structure and method are adopted: the steel bar is preliminarily loaded into the tubular member of the first PCa member provided with the tubular member in a movable manner, and the first PCa members are connected to each other, Or when the first PCa part and another PCa part (for example, the second PCa part) are joined to each other, the steel bar is pulled out from the first PCa part to another first PCa part or the steel bar is pulled out from the second PCa part. The components are pulled out to the first PCa components, communicated between the first PCa components, or communicated between the first PCa components and the second PCa components, and the steel bars are arranged to straddle the PCa components to be joined. and fixing both ends of the moved steel bars to the PCa members to be joined, so that the PCa members can be joined to each other.
另外,在本发明中,采用了如下的结构和方法:预先将钢筋以能够移动的方式装入到设置有第1钢筋接头的第3PCa部件的所述第1钢筋接头中,在将所述第3PCa部件和包含所述第4PCa部件在内的装入有钢筋接头的另一PCa部件相互接合的情况下,将所述钢筋从所述第3PCa部件拉出至装入有所述钢筋接头的另一PCa部件中,连通在所述第3PCa部件和装入有所述钢筋接头的另一PCa部件之间,将所述钢筋配置成跨越所述第3PCa部件和装入有所述钢筋接头的另一PCa部件之间,并将所述移动后的钢筋的两端侧分别固定于所述第3PCa部件和装入有所述钢筋接头的另一PCa部件,从而能够使所述第3PCa部件和装入有所述钢筋接头的另一PCa部件相互接合。In addition, in the present invention, the following structure and method are adopted: a steel bar is preliminarily loaded into the first steel bar joint of the 3rd PCa part provided with the first steel bar joint in a movable manner, and the first steel bar joint is placed In the case where the 3PCa part and another PCa part including the 4th PCa part in which the reinforcing bar joint is incorporated are joined to each other, the reinforcing bar is pulled out from the 3rd PCa part to the other PCa part in which the reinforcing bar joint is incorporated. In one PCa part, it communicates between the 3rd PCa part and another PCa part in which the steel bar joint is installed, and the steel bar is arranged to straddle the third PCa part and the other PCa part in which the steel bar joint is installed. between one PCa part, and the two ends of the moved steel bar are respectively fixed to the third PCa part and another PCa part in which the steel bar joint is installed, so that the third PCa part and the installation Another PCa component incorporating the rebar joint is joined to each other.
另外,在本发明中,也可以在所述管状部件的内侧形成内螺纹或者使用螺纹接头来作为所述管状部件,也可以将全螺纹螺栓(长螺钉)或螺纹钢筋装入到这些形成有内螺纹的管状部件或螺纹钢筋接头的内部,并在接合时拉出任意长度来使用。In addition, in the present invention, it is also possible to form internal threads on the inner side of the tubular member or use a threaded joint as the tubular member, and it is also possible to incorporate fully threaded bolts (long screws) or threaded steel bars into these formed internal threads. Threaded tubular components or the inside of threaded rebar joints, and are drawn to any length for use when spliced.
另外,在本发明中,在将钢筋以能够移动的方式装入到所述管状部件的内侧时,也能够装入密封用管状部件,所述密封用管状部件绕所述钢筋的轴向而围绕在所述管状部件的入口侧的周围。并且,在装入有那样的密封用管状部件的情况下,在进行PCa部件的接合时,通过将灰浆填充于上述密封用管状部件的内侧,能够使上述PCa部件的接合部之间的钢筋牢固地结合。In addition, in the present invention, when a steel bar is movably installed inside the tubular member, it is also possible to incorporate a sealing tubular member that surrounds the steel bar in the axial direction. around the inlet side of the tubular member. And, when such a sealing tubular member is incorporated, when the PCa members are joined, by filling the inner side of the sealing tubular member with mortar, the steel bars between the joint portions of the PCa members can be made firm. combined.
因此,根据本发明,对于包含有用于建筑物的壁或地板等的结构的PCa部件相互间的接合,能够在不将预先从上述PCa部件突出的钢筋相互焊接的情况下完成连接作业,且能够使接合部分的间隔比以往更窄,几乎能够实现完全预制化。Therefore, according to the present invention, for the joining of PCa parts including structures such as walls or floors used in buildings, the connection work can be completed without welding the reinforcing bars protruding from the above-mentioned PCa parts in advance, and can The gap between joint parts has been made narrower than before, and almost complete prefabrication can be realized.
因此,根据本发明,能够尽可能消除后浇筑的现场混凝土以实现完全预制化,同时,对于建筑物的壁或地板等壁式(抗震壁)结构,不预先使钢筋从PCa部件的侧面突出,并且,采用比较简便的结构就能够容易且可靠地进行PCa部件的接合。并且,在本发明中,在PCa壁―PCa壁或PCa柱―PCa壁的铅直接合部,例如,在上述的现有技术中,上下层的PCa壁的水平接合部的接合方法是利用机械式接头将从下层突出的钢筋接合,因此,在上述的同层的PCa壁―PCa壁或PCa柱―PCa壁的铅直接合部处的接合方法中,需要用于钢筋的重合接头或喇叭形坡口焊接的空间,该部分不得不依赖现场浇筑的混凝土,与此相对,在本发明中,几乎能够实现完全预制化。Therefore, according to the present invention, it is possible to eliminate as far as possible post-poured in-situ concrete to achieve complete prefabrication, and at the same time, for wall-type (seismic-resistant wall) structures such as walls or floors of buildings, reinforcement bars are not protruded from the sides of PCa components in advance, In addition, the PCa member can be joined easily and reliably with a relatively simple structure. And, in the present invention, in the lead joint portion of PCa wall-PCa wall or PCa column-PCa wall, for example, in above-mentioned prior art, the joint method of the horizontal joint portion of the PCa wall of upper and lower layer is to utilize mechanical The steel bar protruding from the lower layer is joined by the joint type joint, therefore, in the above-mentioned joint method at the direct joint of the PCa wall-PCa wall or the PCa column-PCa wall of the same floor, a coincident joint or trumpet joint for the steel bar is required. In contrast to the space for groove welding, which has to rely on concrete poured on site, in the present invention, almost complete prefabrication can be realized.
另外,在本发明中,利用待接合的PCa部件与部件的侧面(铅直接合部)的间隙、即能够传递力的楔形槽和接缝宽度、且是存在能够通过人手移动的空间的间隙,将钢筋、密封用管状部件等拉出。In addition, in the present invention, using the gap between the PCa component to be joined and the side surface (lead joint) of the component, that is, the wedge-shaped groove and the width of the joint that can transmit force, and the gap that has a space that can be moved by human hands, Pull out reinforcement bars, sealing tubular parts, etc.
附图说明Description of drawings
图1是概要地示出本发明的具备接合构件的预制混凝土部件(抗震壁)的例子的立体图。FIG. 1 is a perspective view schematically showing an example of a precast concrete member (seismic wall) provided with joint members according to the present invention.
图2示出了图1所记载的本发明的具备接合构件的预制混凝土部件(抗震壁)的例子,(A)是从正面观察上述抗震壁的一部分的局部主视图,图2(B)是从上表面观察上述抗震壁中的埋入有上述管状部件的部分的局部俯视图,图2(C)是与上述的图2(B)同样的图,但却是示出使装入管状部件中的钢筋移动后的例子的局部俯视图。Fig. 2 has shown the example of the prefabricated concrete part (seismic wall) that possesses the joint member of the present invention described in Fig. 1, (A) is a partial front view of a part of the above-mentioned seismic wall viewed from the front, and Fig. 2 (B) is A partial top view of the part where the above-mentioned tubular member is embedded in the above-mentioned anti-seismic wall is observed from the upper surface. Fig. 2 (C) is the same figure as the above-mentioned Fig. A partial top view of an example of rebar movement.
在图3中,针对根据本发明埋入PCa部件中的管状部件的截面的一部分(管状部件的两端侧的部分)的例子,省略中央部将其示出。In FIG. 3 , an example of a part of the cross section of the tubular member embedded in the PCa member according to the present invention (portions on both ends of the tubular member) is shown with the central portion omitted.
图4图示了杆引导件的例子,(A)是示出从管轴方向观察的例子的图,(B)是示出从垂直于管轴的方向观察(A)的X-X部分的例子的剖视图。Fig. 4 illustrates an example of a rod guide, (A) is a diagram showing an example viewed from the direction of the pipe axis, and (B) is a diagram showing an example of the X-X portion of (A) viewed from a direction perpendicular to the pipe axis cutaway view.
图5示出了PCa部件的形成有管状部件的开放端侧(开口部侧)的侧面的例子,(A)是示出在侧面形成有楔形槽的例子的侧剖视图,(B)是示出在同样的情况下将卡定部设置于钢筋的靠近开放端侧的位置处的例子的侧剖视图。Fig. 5 shows an example of the side surface of the open end side (opening part side) of the PCa member formed with the tubular member, (A) is a side sectional view showing an example in which a wedge-shaped groove is formed on the side surface, and (B) is a side sectional view showing It is a side sectional view of the example which provided the locking part in the position close to the open end side of a reinforcing bar under the same situation.
图6是示出将密封用管状部件700安装于所述管状部件110的开放端侧的例子的剖视图。FIG. 6 is a cross-sectional view showing an example of attaching the sealing tubular member 700 to the open end side of the tubular member 110 .
图7示出了在第1PCa部件的侧面侧观察使用密封用管状部件700的例子的例子,图7(A)是将钢筋和与轴向平行地包围钢筋的外周的所述密封用管状部件配置于管状部件的开放端侧的情况下的侧剖视图,图7(B)是示出将钢筋拉出并将密封用管状部件的端面周围与管状部件的开放端侧的接合部密封起来的例子的侧剖视图。Fig. 7 shows an example of an example of using a sealing tubular member 700 as viewed from the side of the first PCa member. Fig. 7(A) is a configuration of the reinforcing bar and the sealing tubular member surrounding the outer periphery of the reinforcing bar parallel to the axial direction. In the case of the open end side of the tubular member, Fig. 7(B) is a side sectional view showing an example in which the steel bar is pulled out and the periphery of the end surface of the tubular member for sealing is sealed with the joint portion on the open end side of the tubular member. Side cutaway view.
图8是示出作为钢筋拉出构件的手动剪的概要结构的俯视图。Fig. 8 is a plan view showing a schematic structure of a hand shear as a reinforcing bar pulling member.
图9是示出使用了第1PCa部件和第2PCa部件的情况下的相互的接合步骤的流程图。FIG. 9 is a flowchart showing a mutual bonding procedure when a first PCa member and a second PCa member are used.
图10是针对将本发明的具备接合构件的预制混凝土部件用于地板的接合的例子以接合部的周边区域为中心示出该例子的图,图10(A)是示出使钢筋移动前的状态的侧剖视图,图10(B)是示出使钢筋移动后的状态的侧剖视图。Fig. 10 is a diagram showing an example of using the precast concrete part including the joining member of the present invention for the joining of floors, centering on the surrounding area of the joining part, and Fig. 10(A) shows the situation before moving the reinforcing bar The side sectional view of a state, FIG. 10(B) is a side sectional view which shows the state after moving a reinforcement.
图11是针对将本发明的具备接合构件的预制混凝土部件用于地板的接合的例子以接合部的周边区域为中心示出使用了密封用管状部件的例子的图,图11(A)是示出使钢筋和密封用管状部件移动前的状态的侧剖视图,图11(B)是示出使钢筋和密封用管状部件移动后的状态的侧剖视图。Fig. 11 is a diagram showing an example of using a sealing tubular member centered on the peripheral area of the joint for an example in which the precast concrete part equipped with the joint member of the present invention is used for the joint of the floor, and Fig. 11 (A) is a diagram showing 11(B) is a side sectional view showing a state after moving the reinforcing bar and the sealing tubular member.
图12是示出在进行了PCa地板的接合后将混凝土浇筑于所述PCa地板的上表面的例子的侧剖视图。Fig. 12 is a side sectional view showing an example in which concrete is poured on the upper surface of the PCa floor after the PCa floor has been joined.
图13是针对本发明的具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法,与图2(B)、(C)的情况同样地示出使用钢筋接头作为管状部件的例子的局部俯视图。Fig. 13 is a precast concrete part equipped with a joint member and a precast concrete part joining method using the precast concrete part according to the present invention, showing the use of a steel bar joint as a tubular part similarly to the case of Fig. 2(B) and (C) A partial top view of an example.
图14是示出螺纹式套筒接头的例子的侧剖视图。Fig. 14 is a side sectional view showing an example of a threaded sleeve joint.
图15是示出将钢筋接头埋入PCa部件时的所述PCa部件自身的钢筋的结构例的剖视图。Fig. 15 is a cross-sectional view showing a structural example of the reinforcement of the PCa member itself when a reinforcement joint is embedded in the PCa member.
图16是示出使用密封用管状部件来接合第3PCa部件和另一PCa部件的例子的图,图16(A)是示出在构成第1钢筋接头的套筒的内侧的钢筋拉出侧预先设置有密封用管状部件的例子的侧剖视图,其中,所述密封用管状部件围绕在钢筋的轴向的周围而进行密封。另外,图16(B)是示出埋入有图23(B)所示的钢筋接头的现有的预制部件来作为与第3PCa部件接合的PCa部件的例子的侧剖视图,图16(C)是示出将第3PCa部件和现有的预制部件接合在一起的状态的侧剖视图。16 is a diagram showing an example of joining a third PCa member and another PCa member using a sealing tubular member. FIG. A side sectional view of an example provided with a sealing tubular member that wraps around the axial circumference of the steel bar to seal. In addition, Fig. 16 (B) is a side sectional view showing an example of a PCa member joined with the 3rd PCa member as the existing prefabricated part embedded with the reinforcing bar joint shown in Fig. 23 (B), and Fig. 16 (C) It is a side sectional view showing the state where the 3rd PCa member and the conventional prefabricated part are joined together.
图17示出了与图16对应的结构的立体图,图17(A)是示出接合前的第3PCa部件和另一PCa部件各自的状态的立体图,图17(B)是示出接合后的第3PCa部件和另一PCa部件的状态的立体图。Fig. 17 shows a perspective view of the structure corresponding to Fig. 16, Fig. 17 (A) is a perspective view showing the respective states of the 3rd PCa member and another PCa member before joining, and Fig. 17 (B) is showing the state after joining Perspective view of the state of the 3rd PCa component and another PCa component.
图18是示出使用了第3PCa部件和第4PCa部件的情况下的相互的接合步骤的流程图。FIG. 18 is a flowchart showing a mutual bonding procedure when a third PCa member and a fourth PCa member are used.
图19是对使用螺纹钢筋接头作为本发明的管状部件、并使用螺纹钢筋作为所述钢筋的例子进行图示的侧剖视图。Fig. 19 is a side sectional view illustrating an example of using a threaded steel bar joint as the tubular member of the present invention and using a threaded steel bar as the reinforcing bar.
图20是对下述例子进行图示的侧剖视图:使用在内侧形成有内螺纹的长螺母来作为本发明的管状部件,并使用与所述长螺母螺合的全螺纹螺栓来作为钢筋。20 is a side sectional view illustrating an example in which a long nut with internal threads formed inside is used as the tubular member of the present invention, and a full-thread bolt screwed with the long nut is used as a reinforcement.
图21是示意性地示出本发明的第1管状部件等接合构件相对于PCa部件的配置例的主视图。Fig. 21 is a front view schematically showing an example of arrangement of joining members such as the first tubular member of the present invention with respect to the PCa member.
图22是针对PCa部件的接合部分图示出现有例子的立体图。FIG. 22 is a perspective view illustrating a conventional example of a joint portion of a PCa component.
图23是针对PCa部件的接合部分图示出使用了钢筋接头的现有例子的剖视图。Fig. 23 is a cross-sectional view illustrating a conventional example using a steel bar joint for a joint portion of PCa members.
具体实施方式detailed description
以下,参照附图,对本发明的具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法进行说明。并且,在以下的说明中,对于同一构成要素,即使对于能够采用其它方式的构成要素,使用同一标号,对于重复的说明、结构甚至表述,有时进行局部省略。另外,为了便于说明,附图所示的各构成要素的大小或比率等有时与实际不同。Hereinafter, a precast concrete part provided with a joining member and a precast concrete part joining method using the precast concrete part according to the present invention will be described with reference to the drawings. In addition, in the following description, the same reference numerals are used for the same constituent elements, even for constituent elements that can be adopted in other forms, and overlapping descriptions, structures, and expressions may be partially omitted. In addition, for convenience of description, the size, ratio, etc. of each component shown in the drawings may differ from actual ones.
在本发明中,如图1和图2所示,例如在抗震壁那样的第1PCa部件100中预先设置第1管状部件110,并预先将钢筋900能够移动地装入所述管状部件110的内部,由此,能够将所述第1PCa部件100中的装入有钢筋的第1PCa部件100和未装入钢筋的第1PCa部件100等的相互之间接合起来,同时,也能够构成与所述第1PCa部件100接合的另一PCa部件(第2PCa部件200),并将其与所述第2PCa部件200组合来进行接合。In the present invention, as shown in FIG. 1 and FIG. 2 , for example, a first tubular member 110 is preliminarily installed in a first PCa member 100 such as an anti-seismic wall, and a steel bar 900 is movably installed inside the tubular member 110 in advance. Thus, among the first PCa members 100, the first PCa members 100 with steel bars incorporated therein and the first PCa members 100 with no steel bars filled with them can be joined to each other, and at the same time, it is also possible to form a joint with the first PCa members 100 Another PCa member (second PCa member 200 ) joined to the 1 PCa member 100 is combined with the second PCa member 200 for joining.
因此,在所述第2PCa部件200中设有引导通道,该引导通道由用于将装入于所述第1PCa部件100中的钢筋900拉出的第2管状部件210构成,从与所述第2管状部件200连通的钢筋拉出构件插入孔213插入钢筋拉出构件600,将装入于所述第1PCa部件100中的钢筋900拉出而使所述第1PCa部件100与第2PCa部件200之间连通,从而将钢筋900配置成跨越所述第1PCa部件100与第2PCa部件200之间,将所述钢筋900固定于所述第1PCa部件100和第2PCa部件200。Therefore, a guide channel is provided in the second PCa member 200, and the guide channel is constituted by a second tubular member 210 for pulling out the reinforcing bar 900 contained in the first PCa member 100, and is connected with the second PCa member 100. 2 Insert the reinforcing bar drawing member insertion hole 213 connected to the tubular member 200 into the reinforcing bar drawing member 600, and pull out the reinforcing bar 900 contained in the first PCa member 100 to make the first PCa member 100 and the second PCa member 200 The steel bar 900 is arranged to span between the first PCa member 100 and the second PCa member 200 , and the steel bar 900 is fixed to the first PCa member 100 and the second PCa member 200 .
因此,以下,首先针对构成本发明的第1PCa部件100和第2PCa部件200的各构成要素依次进行说明。Therefore, below, first, each component constituting the first PCa component 100 and the second PCa component 200 of the present invention will be sequentially described.
并且,在此,上述的图1是概要地示出本发明的具备接合构件的预制混凝土部件的例子的立体图。并且,在上述的图1中,作为本发明的具备接合构件的预制混凝土部件,示出了例示抗震壁的一部分的、包含有局部透视图的立体图,但没有示出预制混凝土部件自身的详细结构,主要仅示出了本发明的管状部件110、同样由管状部件210构成的引导通道的部分、以及安装于管状部件110的钢筋900。另外,图2示出了在上述的图1所记载的抗震壁中设置有本发明的接合构件的例子,图2(A)是从正面观察上述抗震壁的一部分的局部主视图,图2(B)是从上表面观察上述抗震壁中的埋入有上述管状部件的部分的局部俯视图,图2(C)是与上述的图2(B)同样的图,但却是示出使装入管状部件中的钢筋移动后的例子的局部俯视图。并且,在上述图2中,与上述图1同样地未示出预制混凝土部件自身的详细结构。另外,对于上述的正面,为了方便,将与作为接合部分的侧面相邻且垂直的面表述为正面,在抗震壁的情况下,壁面相当于正面。另外,在上述的图1和图2中,示出了将本发明的管状部件和钢筋设置为双钢筋配置的例子,钢筋配置方法不限于此,也可以是单钢筋配置等。In addition, FIG. 1 mentioned above is a perspective view which schematically shows the example of the precast concrete part provided with the joining member of this invention here. In addition, in the above-mentioned FIG. 1 , as the precast concrete part provided with the joining member of the present invention, a perspective view including a partial perspective view illustrating a part of the earthquake-resistant wall is shown, but the detailed structure of the precast concrete part itself is not shown. , mainly only shows the tubular member 110 of the present invention, the part of the guide channel also formed by the tubular member 210 , and the steel bar 900 installed on the tubular member 110 . In addition, FIG. 2 shows an example in which the joint member of the present invention is provided in the above-mentioned anti-seismic wall described in FIG. 1, and FIG. B) is a partial top view of the part of the above-mentioned anti-seismic wall where the above-mentioned tubular member is embedded from the upper surface, and Fig. 2 (C) is the same figure as the above-mentioned Fig. Partial top view of an example after the rebar in the tubular part has been moved. In addition, in the above-mentioned FIG. 2 , similarly to the above-mentioned FIG. 1 , the detailed structure of the precast concrete member itself is not shown. In addition, regarding the above-mentioned front, for convenience, the surface adjacent to and perpendicular to the side as the joining portion is referred to as the front, and in the case of an anti-seismic wall, the wall corresponds to the front. In addition, in above-mentioned Fig. 1 and Fig. 2, have shown the example that the tubular member of the present invention and reinforcing bar are arranged as double reinforcing bar arrangement, reinforcing bar arrangement method is not limited to this, also can be single reinforcing bar arrangement etc.
关于本发明的构成要素中的第1和第2预制混凝土(PCa)部件(100、200),包括后述的第3和第4PCa部件(300、400),可以使用预先在PCa工厂等中制造的一般的PCa部件,其种类并不特别限定。因此,除了图1或图2中例示的那样的建筑物的(抗震)壁之外,也可以用于楼板、阳台等,或者也可以用于柱或梁等。但是,在本发明中,在制造所述PCa部件时,由于需要埋入管状部件110等或后述那样的钢筋接头310等,因此,所述PCa部件需要具有如下这样的结构:能够埋入所述管状部件或钢筋接头,并且不会由此使得所需要的强度下降。Regarding the 1st and 2nd precast concrete (PCa) parts (100, 200) among the constituent elements of the present invention, including the 3rd and 4th PCa parts (300, 400) described later, it is possible to use The type of general PCa parts is not particularly limited. Therefore, in addition to the (seismic) wall of a building as illustrated in FIG. 1 or FIG. 2 , it can also be used for floors, balconies, etc., or can also be used for columns, beams, etc. However, in the present invention, when manufacturing the PCa member, since it is necessary to embed the tubular member 110 or the like or a steel bar joint 310 as described later, the PCa member needs to have a structure that can be embedded in the PCa member. tubular components or rebar joints without thereby reducing the required strength.
另外,如后述的图3所示,埋入于所述第1PCa部件100中的管状部件110(在与后述的第2PCa部件的关系中成为第1管状部件,因此有时也称作第1管状部件)成为一端被盖体119被密封且另一端开放的内部中空的管状。In addition, as shown in FIG. 3 described later, the tubular member 110 embedded in the first PCa member 100 (it becomes the first tubular member in relation to the second PCa member described later, is therefore sometimes referred to as the first tubular member). Tubular member) has a hollow tube shape with one end sealed by the lid body 119 and the other end open.
并且,所述第1管状部件110是将钢筋900装入其内侧的结构,所述被装入的钢筋900被收纳成,在将所述第1PCa部件100和所述第2PCa部件200接合的情况下,能够将所述钢筋900拉出。In addition, the first tubular member 110 has a structure in which a reinforcing bar 900 is incorporated inside, and the incorporated reinforcing bar 900 is accommodated so that when the first PCa member 100 and the second PCa member 200 are joined Next, the steel bar 900 can be pulled out.
另外,关于钢筋900相对于这样的所述第1管状部件100的装入,可以在例如于PCa工厂中制造所述第1PCa部件100时装入,或者,也可以在建设现场等使所述PCa部件相互接合之前装入。In addition, regarding the loading of the steel bar 900 relative to the first tubular member 100, it may be installed when the first PCa member 100 is manufactured in a PCa factory, or the PCa member may be installed at a construction site or the like. Loaded before mutual engagement.
另外,在所述第1管状部件110的内侧部分中,使装入的钢筋900移动,使所述第1PCa部件100和所述第2PCa部件200之间连通而将该钢筋900配置成跨越所述第1PCa部件100和所述第2PCa部件200之间,然后填充砂浆等灰浆。In addition, in the inner portion of the first tubular member 110, the loaded reinforcing bar 900 is moved to communicate between the first PCa member 100 and the second PCa member 200, and the reinforcing bar 900 is arranged to straddle the Between the first PCa member 100 and the second PCa member 200, mortar such as mortar is filled.
因此,所述第1管状部件110如上述那样是能够平滑地进行钢筋900的装入和拉出的圆管状的部件,只要随后不阻碍灰浆的填充,就不特别限定,例如也可以使用护套管等。Therefore, the first tubular member 110 is a circular tubular member capable of smoothly inserting and pulling out the reinforcing bar 900 as described above, and is not particularly limited as long as it does not impede the filling of mortar later on. For example, a sheath may be used. tube etc.
另外,对于所述第1管状部件110,在预先考虑了不会对后续填充的灰浆的流动产生障碍的形态的基础上,可以在构成所述管状部件110的圆管的沿管轴的内表面上形成多个未图示的圆环状的突起,或者也可以沿着所述管轴的内表面设置螺旋状的突起。因此,在所述第1管状部件110的内表面形成有上述那样的突起的情况下,为了在预先于PCa工厂等装入所述钢筋900这样的情况下、以及随后向建筑现场等运输时防止所述钢筋900脱开,也可以预先考虑在所述第1管状部件110的内表面形成的突起与钢筋900的摩擦等而调整成产生一定的保持力。In addition, for the first tubular member 110, on the basis of pre-considering the shape that will not hinder the flow of the mortar to be filled later, the inner surface of the circular tube constituting the tubular member 110 along the tube axis can be A plurality of not-shown annular protrusions may be formed on the pipe shaft, or helical protrusions may be provided along the inner surface of the tube shaft. Therefore, in the case where the above-mentioned protrusions are formed on the inner surface of the first tubular member 110, in order to prevent the steel bar 900 from being installed in advance in a PCa factory or the like, and when transporting to a construction site or the like later, The detachment of the reinforcing bar 900 may be adjusted so as to generate a certain holding force in consideration of the friction between the protrusion formed on the inner surface of the first tubular member 110 and the reinforcing bar 900 .
另外,如图3所示,也可以在所述第1管状部件110的内侧适当地设置杆引导件800。例如如图4所示,所述杆引导件800可以沿着所述管状部件110的内周方向等间隔地设置多个,并沿管轴方向连续地或断续地设置,所述杆引导件800可以由合成树脂或金属板等形成。并且,在此,在上述的图3中,针对根据本发明埋入PCa部件中的管状部件的截面的一部分(两端侧的部分)的例子,省略中央部将其示出。另外,上述的图4图示了杆引导件800的例子,图4(A)是示出从管轴方向观察上述杆引导件800的例子的图,图4(B)是示出从垂直于管轴的方向观察图4(A)的X-X部分的例子的剖视图。In addition, as shown in FIG. 3 , a rod guide 800 may be appropriately provided inside the first tubular member 110 . For example, as shown in FIG. 4 , the rod guides 800 may be provided at equal intervals along the inner peripheral direction of the tubular member 110, and continuously or intermittently provided along the tube axis direction. The rod guides The 800 may be formed of synthetic resin, metal plate, or the like. In addition, in FIG. 3 described above, for an example of a part (parts on both ends) of the cross section of the tubular member embedded in the PCa member according to the present invention, the central portion is omitted and shown. In addition, the aforementioned FIG. 4 illustrates an example of the rod guide 800. FIG. A cross-sectional view of an example of the X-X portion of FIG. 4(A) viewed from the direction of the tube axis.
并且,所述杆引导件800使钢筋的移动平滑,以便容易地实现钢筋900的装入和拉出,由此,在建筑现场进行接合作业之前将钢筋900装入管状部件110的情况下,能够调整装入方向而使钢筋900的插入作业变得容易,还能够使被装入的钢筋900的拉出变得平滑。And, the rod guide 800 smoothes the movement of the steel bar so that the loading and unloading of the steel bar 900 can be easily realized, whereby when the steel bar 900 is loaded into the tubular member 110 before the joining work is performed at the construction site, it is possible to Inserting the reinforcing bar 900 is facilitated by adjusting the inserting direction, and pulling out the inserted reinforcing bar 900 can also be made smooth.
另外,所述第1管状部件110如上述那样具有圆管状的形态,但如上述的图1至4所示,其一端侧成为被埋入于所述第1PCa部件100中且被盖体119密封的密封端,另一端侧被设置成于所述第1PCa部件100的侧面,形成为开放端以进行所述钢筋900的安装或拉出。并且,所述第1管状部件100与对所述第1PCa部件100进行接合的侧面垂直地构成有多个。因此,作为所述第1PCa部件100,在使用图1所示那样的抗震壁的情况下,所述第1管状部件110相对于垂直地形成的接合面沿水平方向配置。In addition, the first tubular member 110 has a circular tubular form as described above, but as shown in FIGS. The sealed end is provided at the side of the first PCa member 100, and the other end is formed as an open end for installing or pulling out the reinforcing bar 900. In addition, a plurality of first tubular members 100 are formed perpendicularly to the side surface to which the first PCa member 100 is joined. Therefore, when using an anti-seismic wall as shown in FIG. 1 as the first PCa member 100 , the first tubular member 110 is arranged in the horizontal direction with respect to the joint surface formed vertically.
另外,所述第1PCa部件100的形成有上述第1管状部件110的开放端的侧面可以是图1、图2或图5(A)所示那样的形成楔形槽100C的凹部的凹坑部分,或,虽然未图示,但也可以是不具有如上述那样形成楔形槽的凹部的平坦侧面。In addition, the side of the first PCa member 100 on which the open end of the first tubular member 110 is formed may be a concave portion forming a concave portion of the wedge-shaped groove 100C as shown in FIG. 1 , FIG. 2 or FIG. 5(A), or , although not shown, may be a flat side surface that does not have a concave portion forming a wedge-shaped groove as described above.
并且,在如上述那样形成楔形槽的凹部的凹坑内设有上述第1管状部件110的开放端的情况下,如后所述,在与另一PCa部件进行接合时,通过也在该另一PCa部件(例如第2PCa部件)中预先设置楔形槽(例如,第2PCa部件的情况下为200C),由此能够使由所述楔形槽形成的接合部之间的间隔D为例如80mm左右。因此,在形成为这样的结构的情况下,将设置于待接合的PCa部件中的钢筋900拉出时的目视确认性变得良好,也能够通过手动作业从上述楔形槽(例如,100C和200C)的部分将所述钢筋900拉出,在将砂浆等灰浆填充于所述楔形槽内时,也能够在具有所述钢筋900的所述第1管状部件110内填充灰浆,从而将所述钢筋900固定于进行接合的PCa部件之间。并且,在此,上述图5示出了PCa部件的形成有管状部件的开放端的侧面的例子,(A)是示出在侧面形成有楔形槽的例子的侧剖视图,(B)是示出在与(A)同样的情况下将卡定部910设置于钢筋的靠开放端侧的位置处的例子的侧剖视图。And, in the case where the open end of the first tubular member 110 is provided in the recess of the concave portion of the wedge-shaped groove as described above, as described later, when joining with another PCa member, the other PCa is also connected to the other PCa. By preliminarily providing a wedge-shaped groove (for example, 200C in the case of the second PCa member) in a member (for example, the second PCa member), the distance D between joints formed by the wedge-shaped groove can be set to about 80 mm, for example. Therefore, in the case of such a structure, the visual confirmation when pulling out the reinforcing bar 900 provided in the PCa member to be joined becomes good, and it is also possible to manually work from the above-mentioned wedge-shaped groove (for example, 100C and 100C). 200C) to pull out the steel bar 900, and when filling mortar such as mortar into the wedge-shaped groove, it is also possible to fill the first tubular member 110 with the steel bar 900 with mortar, so that the Rebar 900 is secured between the joined PCa components. And, here, the above-mentioned FIG. 5 shows an example of the side surface of the open end of the PCa member formed with the tubular member, (A) is a side sectional view showing an example in which a wedge-shaped groove is formed on the side surface, and (B) is a side sectional view showing an example of a wedge-shaped groove formed on the side surface. It is a side cross-sectional view of an example in which the locking portion 910 is provided at a position closer to the open end side of the reinforcing bar in the same case as (A).
另外,对于所述第1管状部件110的长度,并不特别限定,可以对应于相互接合的PCa部件的种类或大小、以及接合所需要的钢筋900的长度来预先确定。因此,例如在用于由水平方向的长度为6米左右的PCa部件构成的抗震壁的情况下,在将所安装的钢筋的长度设定为1.2米的情况下,也可以将第1管状部件110的长度确定为至少与此同等程度或者这以上的长度。但是,上述钢筋900在被安装于上述第1管状部件110后,在用于所述PCa部件(例如,100和200)的接合时,如后述那样被钢筋拉出构件600拉出。因此,对应于上述钢筋拉出构件600的形态或功能,调整所述第1管状部件110的长度和钢筋900的长度,使上述钢筋900的端部形成为从开放端侧伸出的结构,或者处于与开放端侧相同的面上,或者相对于开放端侧位于内部。In addition, the length of the first tubular member 110 is not particularly limited, and may be predetermined according to the type or size of the PCa members to be joined together, and the length of the reinforcing bar 900 required for joining. Therefore, for example, in the case of an anti-seismic wall made of PCa members with a length of about 6 meters in the horizontal direction, if the length of the installed reinforcement is set to 1.2 meters, the first tubular member The length of 110 is determined to be at least as long as this or longer than this. However, the reinforcing bar 900 is pulled out by the reinforcing bar pulling member 600 as described later when it is used for joining the PCa parts (for example, 100 and 200 ) after being attached to the first tubular member 110 . Accordingly, the length of the first tubular member 110 and the length of the steel bar 900 are adjusted corresponding to the shape or function of the above-mentioned steel bar drawing member 600, so that the end of the above-mentioned steel bar 900 is formed into a structure protruding from the open end side, or On the same face as the open end side, or inwardly with respect to the open end side.
另外,如上述的图1至图3所示,也可以在所述第1管状部件上设置砂浆等灰浆的注入口113和排出口115。所述灰浆采用砂浆等,将所述钢筋900的一部分从设置于所述第1PCa部件100的所述第1管状部件110中拉出并与所述第2PCa部件200连通,然后将所述钢筋900固定于所述第1PCa部件100和所述第2PCa部件200。因此,上述灰浆的注入可以如上述那样经由楔形槽100C而从所述第1管状部件110的开放端侧进行,但是,例如如上述的图1至图3所示,也可以采用如下的结构:在所述第1管状部件110的密封端侧附近的侧面侧设置与所述第1PCa部件100的正面侧连通的注入口113,并在所述第1管状部件110的开放端侧附近设置与所述第1PCa部件的正面侧连通的排出口115,从而进行上述灰浆的注入和多余的灰浆的排出。并且,在此,PCa部件的正面侧被用作用于表示与所述PCa部件的接合面侧垂直的面中的任一个面的方便的称呼,例如,在所述PCa部件是抗震壁的情况下,是壁面侧。In addition, as shown in the above-mentioned FIGS. 1 to 3 , an injection port 113 and a discharge port 115 for mortar such as mortar may be provided in the first tubular member. Mortar or the like is used for the mortar, and a part of the steel bar 900 is pulled out from the first tubular member 110 provided on the first PCa member 100 and communicated with the second PCa member 200, and then the steel bar 900 is It is fixed to the first PCa member 100 and the second PCa member 200 . Therefore, the injection of the above-mentioned mortar can be performed from the open end side of the first tubular member 110 through the wedge-shaped groove 100C as described above, but, for example, as shown in the above-mentioned FIGS. An injection port 113 communicating with the front side of the first PCa member 100 is provided on the side surface near the sealed end side of the first tubular member 110, and is connected to the open end side of the first tubular member 110. The discharge port 115 communicating with the front side of the first PCa member is used to inject the above-mentioned mortar and discharge excess mortar. And, here, the front side of the PCa component is used as a convenient name for indicating any one of the surfaces perpendicular to the joint surface side of the PCa component, for example, when the PCa component is an anti-seismic wall , is the wall side.
接下来,用于上述的本发明的钢筋900并不特别限定,在本发明中,希望如异形钢筋那样在表面具备肋或节等凹凸。即,通过形成有基于这些凹凸而成的突起,如上述那样在管状部件110的内表面上提高了上述钢筋900与灰浆的接触面积,因此,在进行上述那样的接合时能够提高砂浆等的固定性。Next, the steel bar 900 used in the above-mentioned present invention is not particularly limited, and in the present invention, it is desirable to have irregularities such as ribs and knuckles on the surface like a special-shaped steel bar. That is, by forming protrusions based on these concavities and convexities, the contact area between the steel bar 900 and the mortar is increased on the inner surface of the tubular member 110 as described above, and therefore, when performing the above-mentioned joining, the fixing of the mortar and the like can be improved. sex.
另外,所述钢筋900的长度也由装入所述钢筋900的所述第1管状部件110的长度决定,但可以以下述情况为前提,预先考虑所接合的PCa部件的尺寸或部件之间的间隙等来确定:如上述那样与钢筋拉出构件600的形态或功能相应地留出能够把持的部分,同时收纳于所述第1管状部件110的内部。另外,所述钢筋900的拉出量能够在建设现场与待接合的所述PCa部件相应地进行调整,因此能够根据现场的状况或需要将所述钢筋拉出任意的长度。In addition, the length of the steel bar 900 is also determined by the length of the first tubular member 110 to which the steel bar 900 is incorporated, but it is possible to pre-consider the size of the PCa parts to be joined or the distance between the parts on the premise of the following: It is determined by a gap or the like: as described above, a portion that can be grasped is left in accordance with the form or function of the reinforcing bar drawing member 600, and is accommodated inside the first tubular member 110 at the same time. In addition, the pulling out amount of the steel bar 900 can be adjusted correspondingly to the PCa components to be joined at the construction site, so the steel bar can be pulled out to any length according to the conditions or needs of the site.
另外,所述钢筋900的粗细并不特别限定,只要能够收纳于所述管状部件110的内部即可,由于是在所述钢筋900如上述那样收纳于所述管状110的内部的状态下将灰浆填充于所述管状部件110与所述钢筋900之间的,因此,需要考虑不妨碍所述灰浆的流动的程度的粗细。并且,如上所述,在将所述钢筋900预先在PCa工厂等中装入的情况下,可以考虑采用与所述管状部件110内部产生适当摩擦的程度的粗细。而且,在使用后述的密封用管状部件700的情况下,选择能够将该密封用管状部件700收纳于所述钢筋900与所述管状部件110等之间进行移动的程度的粗细。In addition, the thickness of the steel bar 900 is not particularly limited, as long as it can be accommodated inside the tubular member 110, since the mortar is poured in the state in which the steel bar 900 is accommodated in the tubular member 110 as described above. For filling between the tubular member 110 and the reinforcing bar 900 , it is necessary to have a thickness that does not interfere with the flow of the mortar. In addition, as described above, when the steel bar 900 is preliminarily installed in a PCa factory or the like, it may be considered that the steel bar 900 has a thickness that causes appropriate friction with the inside of the tubular member 110 . Furthermore, when using the sealing tubular member 700 described later, the thickness is selected so that the sealing tubular member 700 can be housed and moved between the reinforcing bar 900 and the tubular member 110 .
另外,关于所述钢筋900,可以直接使用现有的异形钢筋等,但例如如上述的图5(B)所示,也可以是:在所述钢筋900的一端设置环状等的卡定部910等,并配置成所述卡定部910在所述钢筋900装入于所述第1管状部件110的情况下成为开放端侧,提高了拉出所述钢筋900的作业时的便利性。In addition, as for the reinforcing bar 900, existing special-shaped reinforcing bars and the like can be directly used, but, for example, as shown in the above-mentioned FIG. 910 etc., and the locking part 910 is arranged so that when the steel bar 900 is installed in the first tubular member 110, it becomes an open end side, which improves the convenience of pulling out the steel bar 900.
根据具有如上述那样构成的接合构件的第1PCa部件100,预先在所述第1PCa部件100中埋入第1管状部件110,并在其中能够移动地装入钢筋900。因此,在将所述第1PCa部件100与另一PCa部件接合的情况下,例如也能够与同样地埋入有第1管状部件110但未装入钢筋的另一第1PCa部件100接合,这种情况下,能够利用由构成上述那样的楔形槽100C的凹部产生的接合部之间的间隔D,通过手动作业将所述钢筋900连通在两个PCa部件之间,然后,将所述钢筋900分别固定于两个PCa部件。因此,在本发明中,利用待接合的PCa部件与部件的侧面(铅直接合部)之间的间隙、即能够传递力的楔形槽和接缝宽度、且是存在能够通过人手移动的空间的间隙,将钢筋、密封用管状部件等拉出。According to the first PCa member 100 having the joint member configured as described above, the first tubular member 110 is embedded in the first PCa member 100 in advance, and the reinforcing bar 900 is movably incorporated therein. Therefore, in the case of joining the first PCa member 100 to another PCa member, for example, it can also be joined to another first PCa member 100 in which the first tubular member 110 is similarly embedded but not loaded with reinforcement. In this case, the steel bar 900 can be connected between the two PCa members by manual work using the gap D between the joints produced by the recesses constituting the wedge-shaped groove 100C as described above, and then the steel bar 900 can be connected separately. Fixed to two PCa parts. Therefore, in the present invention, the gap between the PCa part to be joined and the side of the part (lead joint), that is, the wedge-shaped groove and the width of the seam that can transmit force, and the space that can be moved by human hands are utilized. To close the gap, pull out the steel bars, sealing tubular parts, etc.
另外,在使用了与所述第1PCa部件100组合起来使用的后述的第2PCa部件200的情况下,能够更容易地拉出所述钢筋900,也能够实现PCa部件相互间的接合。In addition, when the second PCa member 200 described later used in combination with the first PCa member 100 is used, the reinforcing bar 900 can be pulled out more easily, and the joining of the PCa members can also be realized.
另外,在如上述那样将所述钢筋900装入第1PCa部件100时,如图6和图7所示,也可以在所述管状部件110的内侧的所述钢筋900的拉出侧预先一起装入密封用管状部件700,该密封用管状部件700围绕在所述钢筋900的轴向的周围,在与上述待接合的PCa部件的接合部之间对所述钢筋900的周围密封。并且,在此,图6是示出将上述密封用管状部件700安装于所述管状部件110的开放端侧的例子的剖视图。另外,图7是示出在所述第1PCa部件100的侧面侧观察使用这样的密封用管状部件700的例子的示例,图7(A)是在所述管状部件110的开放端侧配置有钢筋900和所述密封用管状部件700的情况下的侧剖视图,其中,所述密封用管状部件700与钢筋900的轴向平行地包围该钢筋900的外周,图7(B)是示出拉出所述钢筋900并对所述密封用管状部件700的端面周围与所述管状部件110的开放端侧接合的接合部730进行密封的例子的侧剖视图。In addition, when installing the steel bar 900 into the first PCa member 100 as described above, as shown in FIGS. A sealing tubular member 700 is inserted, and the sealing tubular member 700 surrounds the axial periphery of the steel bar 900 and seals the surrounding of the steel bar 900 between the junction with the PCa member to be joined. Here, FIG. 6 is a cross-sectional view showing an example in which the sealing tubular member 700 is attached to the open end side of the tubular member 110 . In addition, FIG. 7 is an example showing an example in which such a sealing tubular member 700 is used when viewed from the side of the first PCa member 100, and FIG. 900 and the sealing tubular member 700, wherein the sealing tubular member 700 surrounds the outer periphery of the reinforcing bar 900 parallel to the axial direction of the reinforcing bar 900, and Fig. 7(B) shows the A side sectional view of an example in which the reinforcing bar 900 seals the joint portion 730 where the circumference of the end surface of the sealing tubular member 700 is joined to the open end side of the tubular member 110 .
并且,所述密封用管状部件700采用护套管等圆筒状的部件,并且在将所述第1PCa部件100与另一PCa部件(例如,后述的第2PCa部件200)接合时,以如下方式使用:将所述密封用管状部件700从所述管状部件110与所述钢筋900一起拉出,将所述密封用管状部件700与所述钢筋一起在所述钢筋900的周围连通到与所述另一PCa部件之间而进行接合。In addition, the sealing tubular member 700 adopts a cylindrical member such as a sheath tube, and when joining the first PCa member 100 to another PCa member (for example, the second PCa member 200 described later), the following Way of use: the sealing tubular member 700 is pulled out from the tubular member 110 together with the steel bar 900, and the sealing tubular member 700 is connected with the steel bar 900 around the steel bar 900 to the steel bar 900. between the other PCa components described above.
因此,上述密封用管状部件700的外径被设定成能够使上述密封用管状部件700在上述管状部件110的内侧与所述钢筋900一起移动的程度,并且,其内径构成为能够确保灰浆在所述钢筋900与所述密封用管状部件700之间流通这样的间隔的程度。因此,上述密封用管状部件700的外径被设定为与上述管状部件110的内侧大致接触的程度,并且构成为只要能够相对于上述管状部件110装入和拉出即可。另外,这样拉出的所述密封用管状部件700例如如上述的图7(B)的例子所示那样来使用:在所述接合部之间围绕所述钢筋900的轴向的周围,同时如上述那样与欲与所述第1PCa部件100接合的所述另一个第1PCa部件100或后述的第2PCa部件的管状部件200等连通,然后,在所述待接合的各个PCa部件的侧面,利用粘接剂等将所述密封用管状部件700与所述管状部件200接合的接合部730密封。Therefore, the outer diameter of the sealing tubular member 700 is set to such an extent that the sealing tubular member 700 can move together with the steel bar 900 inside the tubular member 110, and the inner diameter is configured to ensure that the mortar is There is such a gap between the steel bar 900 and the sealing tubular member 700 . Therefore, the outer diameter of the sealing tubular member 700 is set so as to be substantially in contact with the inside of the tubular member 110 , and it only needs to be able to be inserted into and pulled out from the tubular member 110 . In addition, the sealing tubular member 700 pulled out in this way is used, for example, as shown in the above-mentioned example of FIG. As mentioned above, it communicates with the tubular member 200 of the other first PCa member 100 to be joined with the first PCa member 100 or the second PCa member described later, and then, on the side of each PCa member to be joined, use An adhesive or the like seals the junction portion 730 where the sealing tubular member 700 and the tubular member 200 are joined.
因此,在使用了这样的密封用管状部件700的情况下,如上所述,即使在待接合的2个PCa部件的接合部之间形成有楔形槽100C等间隙的情况下,也能够将所述待接合的2个PCa部件各自的管状部件110等从外部密闭并使其连通,由此,在将灰浆填充于所述管状部件110等的内部的情况下,能够在所述待接合的2个PCa部件之间没有泄漏地进行填充从而固定所述钢筋900。Therefore, when such a sealing tubular member 700 is used, as described above, even if a gap such as a wedge-shaped groove 100C is formed between the joining portions of the two PCa members to be joined, the above-mentioned The tubular members 110 and the like of the two PCa members to be joined are hermetically sealed from the outside and communicated with each other, thereby filling the inside of the tubular members 110 and the like with mortar, and the two PCa members to be joined can be closed. The reinforcement 900 is fixed by filling between the PCa parts without leakage.
接下来,对所述第2PCa部件200进行说明。所述第2PCa部件200基本上在可以采用预先在PCa工厂等制造的一般的PCa部件的方面等与所述第1PCa部件100相同。但是,所述第2PCa部件200具有用于与所述第1PCa部件100相互接合的结构,且在下述方面不同:所使用的管状部件210构成为一部分的形态和功能也与所述第1管状部件110不同的第2管状部件。Next, the second PCa member 200 will be described. The second PCa component 200 is basically the same as the first PCa component 100 in that a general PCa component manufactured in advance at a PCa factory or the like can be used. However, the second PCa member 200 has a structure for mutual engagement with the first PCa member 100, and is different in that the form and function of the used tubular member 210 are also different from those of the first tubular member. 110 different second tubular members.
即,如图1和图2所示,所述第2PCa部件200是具备用于从所述第1PCa部件100的所述第1管状部件110拉出所述钢筋900的引导通道210的PCa部件,所述第2PCa部件200与所述第1PCa部件100的侧面侧接合。因此,对于所述第2PCa部件200,在与所述第1PCa部件100接合的接合位置处,在所述第2PCa部件200的与所述第1PCa部件100接合的侧面侧的、与设置于所述第1PCa部件100中的第1管状部件110的开放端对置的位置,设置有由第2管状部件210构成的引导通道的出口。That is, as shown in FIGS. 1 and 2 , the second PCa member 200 is a PCa member provided with a guide channel 210 for pulling out the steel bar 900 from the first tubular member 110 of the first PCa member 100 , The second PCa member 200 is bonded to the side surface of the first PCa member 100 . Therefore, as for the second PCa member 200 , at the joining position with the first PCa member 100 , on the side of the second PCa member 200 joined with the first PCa member 100 , and on the In the first PCa member 100 , at a position facing the open end of the first tubular member 110 , the outlet of the guide passage constituted by the second tubular member 210 is provided.
并且,所述第2管状部件210可以与所述第1管状部件110同样地采用护套管等圆管状的部件,但由于被用作所述引导通道,因此被弯曲来使用。因此,由于所述第2管状部件210收纳从所述第1管状部件110拉出的钢筋900的一部分,因此从所述第2PCa部件200的侧面垂直地形成且保持原样地呈直线状延伸,但是,由所述第2管状部件210构成的引导通道的与出口侧不同的另一开口端侧具有使所述第2管状部件210在中途弯曲的形态,由此作为后述的钢筋拉出构件600的插入口213形成在所述第2PCa部件200的正面侧。In addition, the second tubular member 210 may be a circular tubular member such as a sheath tube similarly to the first tubular member 110, but it is bent and used because it is used as the guide channel. Therefore, since the second tubular member 210 accommodates a part of the steel bar 900 pulled out from the first tubular member 110, it is formed vertically from the side surface of the second PCa member 200 and extends linearly as it is. , the other opening end side of the guide passage constituted by the second tubular member 210 different from the outlet side has a shape in which the second tubular member 210 is bent in the middle, thereby serving as a reinforcing bar drawing member 600 described later. The insertion port 213 is formed on the front side of the second PCa member 200 .
另外,所述第2管状部件210的长度并不特别限定,但是,关于所述第2管状部件210,如上所述,将所述钢筋900的一部分从所述第1PCa部件200的所述第1管状部件110拉出,收纳于上述第2管状部件210的内部,从而将所述第1PCa部件100和所述第2PCa部件200连通来进行接合。因此,关于被拉出而进行连通的所述钢筋900的长度,希望是在所述第1PCa部件100和所述第2PCa部件200中同等程度,因此,考虑将所述钢筋900分别固定于所述第1PCa部件100和所述第2PCa部件200的情况下的长度、以及所述第1PCa部件100与所述第2PCa部件200接合的接合部的接合面之间的间隔(例如,楔形槽(100C、200C)之间的宽度等)来确定。In addition, the length of the second tubular member 210 is not particularly limited, however, as for the second tubular member 210, as described above, a part of the reinforcing bar 900 is separated from the first part of the first PCa member 200. The tubular member 110 is pulled out and accommodated in the second tubular member 210 so that the first PCa member 100 and the second PCa member 200 are communicated and bonded. Therefore, it is desirable that the lengths of the steel bars 900 that are pulled out and communicated be the same as those of the first PCa member 100 and the second PCa member 200, so it is considered to fix the steel bars 900 to the The length of the first PCa member 100 and the second PCa member 200, and the distance between the joint surfaces of the joint portion of the first PCa member 100 and the second PCa member 200 (for example, wedge-shaped grooves (100C, 200C) between the width, etc.) to determine.
另外,所述第2管状部件210也可以具备用于在将钢筋900拉出并移动后填充上述的灰浆进行固定的灰浆的插入口213和排出口215,在本发明的上述实施方式的情况下,上述灰浆的插入口213可以直接使用上述钢筋拉出构件600的插入口213。In addition, the second tubular member 210 may include an insertion port 213 and a discharge port 215 for filling and fixing the above-mentioned mortar after pulling out and moving the reinforcing bar 900. In the case of the above-mentioned embodiment of the present invention, , the insertion port 213 of the above-mentioned mortar can directly use the insertion port 213 of the above-mentioned reinforcing bar drawing member 600 .
接下来,利用图8对从所述第2管状部件210的插入口213插入的钢筋拉出构件进行说明。在此,图8是示出钢筋拉出构件600的概要结构的俯视图。所述钢筋拉出构件600并不设计特别限定,可以使用通常在市场上销售的手动剪或手动拾取器等。并且,关于所述手动剪等,例如在图8中作为钢筋拉出构件600示出手动剪的例子那样,由操作部610、与所述操作部610连接的柔性轴630、以及设置在所述柔性轴630的与操作部侧不同的端部侧的把持部650构成。并且,使用者能够把持所述手动剪的所述操作部610,将所述柔性轴630末端的把持部650引导至把持对象,在将所述把持部650引导至把持对象后通过所述把持部650把持把持对象并将所述手动剪整体拉近,从而将把持对象拉出。另外,关于上述把持部650,也存在具有机械手这样的结构的操纵器型的把持部,不过还存在末端为磁铁型的把持部,通过使把持部650接近所述钢筋900相当的程度,由此,能够将所述钢筋900拉出而接触,在接触的状态下将所述钢筋900拉出。因此,在所述手动剪等的把持部为操纵器型的情况下,能够把持从所述第1管状部件110的开放端侧伸出的钢筋900,在所述手动剪等的把持部为磁铁型的情况下,即使所述钢筋900位于距所述第1管状部件110等的开放端侧较靠里的位置处也能够将其拉出。Next, the reinforcement drawing member inserted from the insertion opening 213 of the said 2nd tubular member 210 is demonstrated using FIG. 8. FIG. Here, FIG. 8 is a plan view showing a schematic structure of the reinforcing bar pulling member 600 . The design of the steel bar pulling member 600 is not particularly limited, and a manual shear or a manual picker that is usually sold in the market can be used. And, about the manual scissors, etc., for example, as an example of the manual scissors shown as the steel bar pulling member 600 in FIG. The flexible shaft 630 is constituted by a gripping portion 650 on an end side different from the operating portion side. Moreover, the user can hold the operating part 610 of the manual scissors, guide the holding part 650 at the end of the flexible shaft 630 to the holding object, and pass the holding part 650 to the holding object after guiding the holding part 650 to the holding object. 650 grasps the object to be held and pulls the manual scissors in as a whole, thereby pulling out the object to be held. In addition, regarding the above-mentioned holding part 650, there is also a manipulator-type holding part having a structure such as a manipulator, but there is also a holding part whose end is a magnet-shaped holding part. , the steel bar 900 can be pulled out to make contact, and the steel bar 900 can be pulled out in the state of contact. Therefore, when the gripping portion of the manual scissors or the like is a manipulator type, the steel bar 900 protruding from the open end side of the first tubular member 110 can be gripped, and the gripping portion of the manual shears or the like is a magnet. In the case of the type, even if the reinforcing bar 900 is located relatively farther back from the open end side of the first tubular member 110 or the like, it can be pulled out.
如以上那样,根据所述第2PCa部件200,按照图9所示那样的流程图所记载的步骤,能够非常容易地进行如所述第1PCa部件100那样构成的具有接合构件的PCa部件、和所述第2PCa部件200的接合。在此,图9是示出使用了第1PCa部件100和第2PCa部件200的情况下的相互的接合步骤的流程图。As described above, according to the second PCa part 200, the PCa part having the bonding member configured as the first PCa part 100 and the PCa part having a joint member configured as the first PCa part 100 can be very easily performed in accordance with the steps described in the flowchart shown in FIG. 9 . The bonding of the second PCa member 200 will be described. Here, FIG. 9 is a flowchart showing a mutual bonding procedure when the first PCa member 100 and the second PCa member 200 are used.
即,最初,预先将所述钢筋900如上述那样能够移动地装入到所述第1PCa部件100的第1管状部件110内(步骤S10)。此时,上述钢筋900可以如上所述那样预先在PCa部件的制造工厂中装入,也可以在建筑现场进行PCa部件的相互接合之前装入。然后,接下来,使所述第1PCa部件100的侧面和所述第2PCa部件200的侧面抵接(步骤S20)。在此,所述第1PCa部件100的进行抵接的侧面是所述第1管状部件110的设置有开放端的一侧的侧面,所述第2PCa部件200的进行抵接的侧面是设置有基于所述第2管状部件110的引导通道的出口侧的一侧,所述开放端和所述出口侧需要预先形成并配置在相互对置这样的位置。并且,上述侧面可以如上述那样形成有构成楔形槽(100C,200C)的凹部。That is, first, the reinforcing bar 900 is movably incorporated in the first tubular member 110 of the first PCa member 100 as described above (step S10 ). At this time, the steel bar 900 may be installed in advance in a PCa member manufacturing factory as described above, or may be installed at a construction site before the PCa members are joined together. Next, the side surface of the first PCa member 100 and the side surface of the second PCa member 200 are brought into contact (step S20 ). Here, the abutting side of the first PCa member 100 is the side of the first tubular member 110 on the side where the open end is provided, and the abutting side of the second PCa member 200 is the side where the open end is provided based on the On the outlet side of the guide passage of the second tubular member 110, the open end and the outlet side need to be formed in advance and arranged to face each other. In addition, the side surfaces may be formed with recesses constituting wedge-shaped grooves ( 100C, 200C) as described above.
在如上述那样配置了第1PCa100和第2PCa部件200后,接下来从所述第2PCa部件200的钢筋拉出构件插入口(另一个开口部)213插入所述钢筋拉出构件600而将所述钢筋900的一部分拉出至所述第2PCa部件200的引导通道210内,所述钢筋900被配置成跨越所述第1PCa部件100与所述第2PCa部件200之间(步骤S30)。因此,通过像这样将所述钢筋900配置成跨越所述第1PCa部件100的第1管状部件110和所述第2PCa部件200的第2管状部件210之间,由此,所述第1管状部件110和第2管状部件210经由所述钢筋900成为能够连接的状态。并且,所述钢筋900从所述第1管状部件110拉出的拉出量可以任意设定,但从使所述钢筋900的两端侧的保持力相同的观点出发,希望被拉出至所述第2PCa部件200的第2管状部件210内部的长度、和通过被拉出而残存在所述第1PCa部件100的所述第1管状部件110内部的长度相同。After the first PCa 100 and the second PCa member 200 are arranged as described above, next, the reinforcement drawing member 600 is inserted from the reinforcement drawing member insertion port (another opening) 213 of the second PCa member 200 to insert the A part of the reinforcing bar 900 is pulled out into the guide channel 210 of the second PCa member 200, and the reinforcing bar 900 is arranged to span between the first PCa member 100 and the second PCa member 200 (step S30). Therefore, by arranging the reinforcing bar 900 so as to straddle between the first tubular member 110 of the first PCa member 100 and the second tubular member 210 of the second PCa member 200, the first tubular member 110 and the second tubular member 210 are in a connectable state via the reinforcing bar 900 . In addition, the pulling-out amount of the steel bar 900 from the first tubular member 110 can be set arbitrarily, but from the viewpoint of making the holding force at both ends of the steel bar 900 the same, it is desirable to be pulled out to the desired length. The length inside the second tubular member 210 of the second PCa member 200 is the same as the length remaining inside the first tubular member 110 of the first PCa member 100 after being pulled out.
接下来,在上述那样的配置结束后,在所述第1PCa部件100的第1管状部件110和所述第2PCa部件200的第2管状部件210中填充砂浆等灰浆(步骤S40)。因此,通过上述灰浆的注入和随后的固化,能够将所述钢筋900稳定地保持于所述第1管状部件110和所述第2管状部件110。并且,此时,在如上述那样在接合部分形成有楔形槽(100C、200C)的情况下,通过一并在所述楔形槽(100C、200C)部分中填充灰浆,能够进一步强化所述接合部分的强度。Next, after the arrangement as described above is completed, mortar such as mortar is filled in the first tubular member 110 of the first PCa member 100 and the second tubular member 210 of the second PCa member 200 (step S40 ). Therefore, the reinforcing bar 900 can be stably held by the first tubular member 110 and the second tubular member 110 through the injection of the mortar and the subsequent curing. In addition, at this time, when the wedge-shaped grooves (100C, 200C) are formed in the joint portion as described above, the joint portion can be further strengthened by filling the portion of the wedge-shaped grooves (100C, 200C) with mortar. Strength of.
如以上那样,根据本发明的具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法,能够尽可能消除后浇筑的现场混凝土而实现完全预制化,并且,对于建筑物的壁或地板等壁式(抗震壁)结构,不预先使钢筋从PCa部件的侧面突出,并且使用比较简便的结构就能够容易且可靠地进行PCa部件的接合。As described above, according to the precast concrete part including the joining member and the precast concrete part joining method using the precast concrete part of the present invention, it is possible to eliminate as much as possible post-cast on-site concrete and realize complete prefabrication. In a wall (seismic wall) structure such as a wall or a floor, the PCa members can be easily and reliably joined using a relatively simple structure without protruding reinforcing bars from the side surfaces of the PCa members.
并且,在上述的实施方式中,使用了抗震壁作为PCa部件,但是,如上述那样应用了本发明的PCa部件不限于此,也可以用于柱、梁、地板等。因此,例如,如图10所示,也可以用于PCa地板相互的接合。并且,在此,上述图10是针对将本发明的具备接合构件的预制混凝土部件用于地板的接合的例子,以接合部的周边区域为中心示出该例子的图,图10(A)是示出使钢筋900移动前的状态的侧剖视图,图10(B)是示出使钢筋900移动后的状态的侧剖视图。另外,在附图中,上方表示所述地板的上表面。Furthermore, in the above-mentioned embodiment, an anti-seismic wall was used as the PCa member, but the PCa member to which the present invention is applied as described above is not limited thereto, and may be used for columns, beams, floors, and the like. Therefore, for example, as shown in FIG. 10, it can also be used for jointing of PCa floor boards. And, here, above-mentioned Fig. 10 is for the example that the precast concrete part that has the joint member of the present invention is used for the joint of floor, the figure that shows this example centering on the peripheral area of joint part, Fig. 10 (A) is 10(B) is a side sectional view showing the state after moving the reinforcing bar 900. FIG. In addition, in the drawings, upper means the upper surface of the floor.
在上述图10所示的例子中,用于地板的PCa部件具有与上述的第1PCa部件100和第2PCa部件200基本相同的结构,该图中的100B相当于第1PCa部件100,200B相当于第2PCa部件200,但接合部分的侧面部的形态不同。(并且,在此,为了方便,将100B称作第1PCa部件100B,将200B称作第2PCa部件200B。)In the above example shown in FIG. 10, the PCa parts used for the floor have basically the same structure as the above-mentioned first PCa part 100 and the second PCa part 200, and 100B in the figure corresponds to the first PCa part 100, and 200B corresponds to the first PCa part 100. 2PCa component 200, but the shape of the side surface of the joint part is different. (And here, for convenience, 100B is referred to as a first PCa member 100B, and 200B is referred to as a second PCa member 200B.)
即,在上述接合部分的侧面部沿上述PCa地板的上下方向设有阶梯差,下侧的阶梯在上述的2个PCa地板(100B、200B)之间相互抵接而形成抵接面AS,而上侧的阶梯从所述抵接面AS后退而在所述PCa地板之间设有空间,面对所述空间垂直地形成上述的阶梯的侧面,并在所述侧面形成有所述第1PCa部件100B的开口部和所述第2PCa部件200B的开口部。并且,形成于所述上侧的阶梯的所述PCa地板之间的空间也由所述PCa部件整体的大小决定,例如可以选取80mm左右。That is, a step is provided on the side portion of the joint portion along the vertical direction of the above-mentioned PCa floor, and the lower step is abutted against each other between the above-mentioned two PCa floor (100B, 200B) to form an abutment surface AS, and The upper step recedes from the abutment surface AS to form a space between the PCa floor boards, and a side surface of the above-mentioned step is formed vertically facing the space, and the first PCa member is formed on the side surface 100B and the opening of the second PCa member 200B. In addition, the space between the PCa floor and the step formed on the upper side is also determined by the overall size of the PCa components, for example, it can be selected as about 80mm.
并且,在进行上述那样的PCa地板(100B、200B)的相互接合的情况下,从所述第1PCa部件100B的管状部件110拉出钢筋900,将所述钢筋的一部分插入到所述第2PCa部件200B的管状部件210内,所述钢筋900被配置成跨越所述第1PCa部件100B的管状部件110与所述第2PCa部件200B的管状部件210之间,利用灰浆的注入口和排出口在上述各个管状部件内(110、210)和上述接合部之间进行砂浆等灰浆的填充。并且,在上述的例子中,灰浆的注入口和排出口可以相互用于任何用途,例如,上述灰浆的注入口213也可以作为排出口215来利用。And, in the case where the PCa floors (100B, 200B) are joined together as described above, the steel bar 900 is pulled out from the tubular member 110 of the first PCa member 100B, and a part of the steel bar is inserted into the second PCa member. In the tubular member 210 of 200B, the steel bar 900 is arranged to straddle between the tubular member 110 of the first PCa member 100B and the tubular member 210 of the second PCa member 200B, and the injection port and the discharge port of the mortar are used in each of the above-mentioned Filling of mortar such as mortar is performed between the interior of the tubular member (110, 210) and the joint. In addition, in the above-mentioned example, the injection port and the discharge port of the mortar can be mutually used for any purpose, for example, the above-mentioned mortar injection port 213 can also be utilized as the discharge port 215 .
另外,在进行上述那样的PCa地板(100B、200B)的相互接合时,如图11所示,也可以使用上述那样的密封用管状部件700。在此,所述图11是针对将本发明的具备接合构件的预制混凝土部件用于地板的接合的例子,以接合部的周边区域为中心示出使用了密封用管状部件700的例子的图,图11(A)是示出使钢筋900和密封用管状部件700移动前的状态的侧剖视图,图11(B)是示出使钢筋900和密封用管状部件700移动后的状态的侧剖视图。In addition, when the above-mentioned PCa floor boards ( 100B, 200B) are joined together, as shown in FIG. 11 , the above-mentioned sealing tubular member 700 can also be used. Here, FIG. 11 is an example in which the precast concrete part provided with the joint member of the present invention is used for the joint of the floor, and shows an example in which the sealing tubular member 700 is used centering on the peripheral area of the joint part. 11(A) is a side sectional view showing a state before the reinforcing bar 900 and the sealing tubular member 700 are moved, and FIG. 11(B) is a side sectional view showing a state after the reinforcing bar 900 and the sealing tubular member 700 are moved.
因此,如图11(A)所示,在使用所述密封用管状部件700的情况下,在将钢筋900装入到所述第1PCa部件100B的管状部件110等时,预先将密封用管状部件700一起装入到所述管状部件110的内侧的所述钢筋900的拉出侧,其中,所述密封用管状部件700围绕所述钢筋900的轴向的周围,在上述待接合的PCa部件的接合部之间对所述钢筋900的周围进行密封。Therefore, as shown in FIG. 11(A), in the case of using the sealing tubular member 700, when the reinforcing bar 900 is incorporated into the tubular member 110 of the first PCa member 100B, etc., the sealing tubular member 700 is installed together into the pull-out side of the steel bar 900 inside the tubular member 110, wherein the sealing tubular member 700 surrounds the axial circumference of the steel bar 900, and is placed on the PCa member to be joined. The surroundings of the steel bars 900 are sealed between the joints.
因此,与关于上述的图6、7所说明的相同,上述密封用管状部件700的外径被设定成能够使上述密封用管状部件700在上述管状部件110的内侧与所述钢筋900一起移动,并且,其内径构成为能够确保灰浆在所述钢筋900与所述密封用管状部件700之间流通这样的间隔的程度。因此,上述密封用管状部件700的外径被设定为与上述管状部件110的内侧大致接触的程度,并且构成为只要能够相对于上述管状部件110装入和拉出即可。Therefore, as described above with respect to FIGS. 6 and 7 , the outer diameter of the sealing tubular member 700 is set so that the sealing tubular member 700 can move together with the reinforcing bar 900 inside the tubular member 110 . , and the inner diameter thereof is configured to ensure a gap such that mortar flows between the reinforcing bar 900 and the sealing tubular member 700 . Therefore, the outer diameter of the sealing tubular member 700 is set so as to be substantially in contact with the inside of the tubular member 110 , and it only needs to be able to be inserted into and pulled out from the tubular member 110 .
并且,在进行所述接合时,将所述密封用管状部件700与所述钢筋900一起从所述管状部件110拉出,如图11(B)所示那样在所述接合部之间围绕所述钢筋900的轴向的周围,与此同时,和欲与所述第1PCa部件100B接合的所述第2PCa部件200的管状部件210连通,然后,在所述待接合的各个PCa部件(100B、200B)的上侧的阶梯的侧面上,利用粘接剂等将所述密封用管状部件700的端部的周围与所述管状部件(110、210)的接合部730密封而封闭,仅在所述密封用管状部件700和所述待接合的各个所述管状部件(110、210)的内侧填充灰浆,能够实现所述钢筋900的固定。And, when performing the joining, the sealing tubular member 700 is pulled out from the tubular member 110 together with the reinforcing bar 900, and the sealing member 700 is surrounded between the joining portions as shown in FIG. 11(B). At the same time, it communicates with the tubular member 210 of the second PCa member 200 to be joined with the first PCa member 100B, and then, in the respective PCa members (100B, 100B, 200B) on the side surface of the upper side of the step, use an adhesive or the like to seal and seal the periphery of the end portion of the sealing tubular member 700 and the joint portion 730 of the tubular member (110, 210), and only The inside of the sealing tubular member 700 and each of the tubular members ( 110 , 210 ) to be joined is filled with mortar, so that the reinforcement 900 can be fixed.
并且,在将上述那样的PCa地板(100B、200B)作为一半PCa楼板来使用的情况下,如图12所示,在接合后的所述PCa地板(100B、200B)上侧另行装入钢筋等,并通过后浇筑的混凝土等整体固定。在此,上述图12是示出在进行了图11(B)所示的PCa地板(100B、200B)的接合之后将混凝土浇筑于所述PCa地板(100B、200B)的上表面的例子的侧剖视图。And, in the case of using the PCa floor (100B, 200B) as described above as a half PCa floor, as shown in FIG. , and is integrally fixed by post-poured concrete. Here, the above-mentioned FIG. 12 is a side view showing an example of pouring concrete on the upper surface of the PCa floor (100B, 200B) after joining the PCa floor (100B, 200B) shown in FIG. 11(B). cutaway view.
接下来,参照图13等,对本发明的具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法的再一个不同的实施方式的例子进行说明。Next, an example of still another different embodiment of the precast concrete part including the joining member and the precast concrete part joining method using the precast concrete part of the present invention will be described with reference to FIG. 13 and the like.
在此,上述图13是与图2(B)、(C)的情况同样地示出本发明的具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法的不同例子的局部俯视图。Here, the above-mentioned FIG. 13 shows a different example of a precast concrete part equipped with a joining member and a precast concrete part joining method using the precast concrete part of the present invention similarly to the case of FIGS. 2(B) and (C). Partial top view.
上述图13所示的实施方式的例子在下述方面不同:作为本发明中的预制混凝土部件的接合构件,不是如上述的例子那样将钢筋900能够移动地安装在设置于所述第1预制混凝土部件100的管状部件110中,而是将钢筋能够移动地设置在钢筋接头的内侧,其中,该钢筋接头设置于预制混凝土部件。The example of the embodiment shown in FIG. 13 above is different in the following respects: As the joining member of the precast concrete part in the present invention, the steel bar 900 is not movably installed on the first precast concrete part as in the above example. In the tubular part 110 of 100, instead, the steel bars are movably arranged inside the steel bar joints, wherein the steel bar joints are arranged in the precast concrete parts.
因此,在上述实施方式中,例如如上述图13所示,预先将钢筋接头(根据与后述的第4PCa部件的关系而成为第1钢筋接头,因此有时也称作第1钢筋接头)310设置于第3PCa部件300中,并将钢筋900能够移动地装入到所述第1钢筋接头310的内部,在进行与另一PCa部件的接合的情况下,使所述钢筋900的一部分移动至该另一PCa部件的内部,将所述钢筋900固定成跨越欲接合的PCa部件双方,从而能够使所述PCa部件双方相互接合。Therefore, in the above-mentioned embodiment, for example, as shown in FIG. 13 above, a steel bar joint (it becomes a first steel bar joint due to a relationship with a 4th PCa member described later, so it may be called a first steel bar joint) 310 is provided in advance. In the third PCa member 300, the steel bar 900 is movably installed inside the first steel bar joint 310, and in the case of joining with another PCa member, a part of the steel bar 900 is moved to the inside of the first steel bar joint 310. Inside the other PCa member, the reinforcing bar 900 is fixed so as to straddle both PCa members to be joined, so that the two PCa members can be joined to each other.
并且,与上述那样的第3PCa部件300接合的PCa部件可以是上述的第1PCa部件100、或者上述的图23所示那样的在内部具备现有的钢筋接头2410的PCa部件2400,也可以是具备后述那样的钢筋拉出口417的第4PCa部件400。And, the PCa member joined with the third PCa member 300 as described above may be the first PCa member 100 described above, or the PCa member 2400 having an existing steel joint 2410 inside as shown in FIG. The fourth PCa member 400 of the reinforcement outlet 417 will be described later.
因此,以下,依次对本发明的上述第3PCa部件300和第4PCa部件400进行说明。并且,关于本发明的上述第3PCa部件300和第4PCa部件400,除了如上述那样将管状部件置换为钢筋接头(310、410)这一点之外,与上述第1PCa部件100及第2PCa部件200相同的部分较多,因此以不同点为中心进行说明。Therefore, below, the said 3rd PCa member 300 and the 4th PCa member 400 of this invention are demonstrated sequentially. In addition, the third PCa member 300 and the fourth PCa member 400 of the present invention are the same as the first PCa member 100 and the second PCa member 200 except that the tubular members are replaced with steel bar joints (310, 410) as described above. There are many parts, so the explanation will focus on the differences.
上述的说明中的第3PCa部件300如通过上述的第1PCa部件100所说明的那样并不特别限定于壁、梁或柱等,但在本发明的实施方式的情况下,由于是如后述那样埋入钢筋接头310的结构,因此,需要具有这样的结构:即使埋入所述钢筋接头310,也不会导致强度降低。The third PCa member 300 in the above description is not particularly limited to walls, beams, columns, etc. as described above with the above first PCa member 100 , but in the case of the embodiment of the present invention, since it is as described later The structure of embedding the reinforcing bar joint 310, therefore, needs to have such a structure that even if the reinforcing bar joint 310 is buried, the strength will not be lowered.
另外,通过预先埋入于所述第3PCa部件300而具备的钢筋接头310可以使用例如被称作大致圆筒形状的套筒接头的结构。In addition, the reinforcement joint 310 provided by embedding in advance in the said 3rd PCa member 300 can use what is called a substantially cylindrical sleeve joint, for example.
并且,在本发明的上述实施方式中使用的所述套筒接头例如是也被称为灰浆填充式接头的结构,其中,该灰浆填充式接头为:在所述套筒的内侧配置欲进行连接的钢筋900并设置防漏密封件(ノロ止めシール)NS等之后,将灰浆填充于所述套筒的内侧来固定所述钢筋900。In addition, the socket joint used in the above-described embodiment of the present invention is, for example, a structure also called a mortar-filled joint, wherein the mortar-filled joint is such that a joint to be connected is disposed inside the sleeve. After installing the steel bar 900 and installing leak-proof seals (Norostopmeshier) NS, etc., the inside of the sleeve is filled with mortar to fix the steel bar 900.
另外,对于所述灰浆填充式接头,存在多种形式,但在本发明中并不特别限定,例如可以将图14所示那样的螺纹式套筒接头3000等延伸后使用。并且,所述螺纹式套筒接头3000例如是如下等结构:成为在构成钢筋接头的圆筒形状的套筒3100的一端侧的内侧切出螺纹3110、并在另一端侧插入钢筋900的形式,还设置有灰浆的注入口3130和排出口3150。因此,在使用该螺纹式套筒接头的情况下,将构成所述预制部件300自身的钢筋900P插入到在所述一端侧的内侧切出有螺纹的部分3110,然后形成预制部件300,然后,将用于接合构件的钢筋900装入到所述套筒3100的另一端侧。In addition, there are various forms of the mortar-filled joint, but it is not particularly limited in the present invention. For example, a threaded sleeve joint 3000 such as that shown in FIG. 14 may be extended and used. In addition, the threaded sleeve joint 3000 is, for example, a structure in which a thread 3110 is cut inside one end side of a cylindrical sleeve 3100 constituting a steel bar joint, and a steel bar 900 is inserted into the other end side, An injection port 3130 and a discharge port 3150 for mortar are also provided. Therefore, in the case of using this threaded sleeve joint, the reinforcing bar 900P constituting the prefabricated part 300 itself is inserted into the threaded part 3110 cut out inside the one end side, and then the prefabricated part 300 is formed, and then, A reinforcing bar 900 for joining members is incorporated into the other end side of the sleeve 3100 .
返回图13继续说明,所述钢筋接头310如上述那样被预先埋入所述第3PCa部件300,但其构成为:在其埋入时,将构成所述第3PCa部件300的钢筋900P配置并固定成从构成所述钢筋接头310的套筒的一端侧延伸至所述钢筋接头310的内侧的适当位置,然后在对能够移动地装入到所述钢筋接头310中的钢筋900进行固定时,实现功能上的一体性。Returning to FIG. 13 to continue the description, the reinforcing bar joint 310 is embedded in the third PCa member 300 in advance as described above, but it is configured such that the reinforcing bar 900P constituting the third PCa member 300 is arranged and fixed when it is embedded. Extend from one end side of the sleeve forming the steel bar joint 310 to an appropriate position inside the steel bar joint 310, and then when fixing the steel bar 900 movably loaded into the steel bar joint 310, realize functional unity.
并且,在埋入上述钢筋接头310的情况、且使用柱或梁作为所述第3PCa部件300的情况下,所述钢筋接头310相对于所述第3PCa部件300的尺寸所占的长度可能变得过大。可是,在该情况下,例如如图15所示,也可以是,使预先与所述第1钢筋接头310等连接的、构成所述第3PCa部件300等的钢筋900P弯折,来构成所述第3PCa部件300等。并且,在此,图15是示出将钢筋接头埋入于PCa部件时的所述PCa部件自身的钢筋900P的结构例的剖视图。In addition, in the case of embedding the above-mentioned steel bar joint 310 and using a column or beam as the third PCa member 300, the length occupied by the steel bar joint 310 with respect to the size of the third PCa member 300 may become is too big. However, in this case, for example, as shown in FIG. 15 , the steel bar 900P that is connected to the first steel bar joint 310 and the like in advance to form the third PCa member 300 and the like may be bent to form the steel bar 900P. 3rd PCa part 300 etc. In addition, FIG. 15 is a cross-sectional view showing a configuration example of a reinforcing bar 900P of the PCa member itself when a reinforcing bar joint is embedded in the PCa member.
另外,所述钢筋接头310中的未埋入于所述第3PCa部件300的部件内的开口部侧可以在所述第3PCa部件300与另一PCa部件进行接合的侧面上相对于所述侧面沿垂直方向设置,并且所述第3PCa部件300的侧面也可以与所述第1PCa部件的情况同样地设置楔形槽。In addition, the opening side of the reinforcing bar joint 310 that is not embedded in the third PCa member 300 may be along the side of the third PCa member 300 that is joined to another PCa member with respect to the side surface. It is provided in the vertical direction, and the side surface of the third PCa member 300 may also be provided with wedge-shaped grooves similarly to the case of the first PCa member.
另外,在所述钢筋接头310上,也可以与所述第1PCa部件100同样地设置砂浆等灰浆的注入口313和排出口315。并且,在该情况下,例如可以构成为:在所述钢筋接头310上的、从所述第3PCa部件300固定有钢筋900P的一侧,设置有从所述钢筋接头310的侧面与所述第3PCa部件300的正面连通的灰浆排出口315,在所述钢筋接头310上的、所述第3PCa部件300的接合面侧的开放端侧,设置有灰浆的注入口313。In addition, the injection port 313 and the discharge port 315 of mortar such as mortar may be provided in the reinforcement joint 310 similarly to the first PCa member 100 . In addition, in this case, for example, on the side of the reinforcing bar joint 310 on which the reinforcing bar 900P is fixed from the third PCa member 300 , a connection between the side surface of the reinforcing bar joint 310 and the third PCa member 300 may be provided. The mortar discharge port 315 connected to the front of the 3PCa member 300 is provided with a mortar injection port 313 on the open end side of the joint surface side of the third PCa member 300 on the steel bar joint 310 .
并且,在所述钢筋接头310的内侧,(虽然未图示,但)也可以与所述第1管状部件110的情况同样地设置圆环状的突起或螺旋状的突起、甚至用于使能够移动地装入于所述第钢筋接头310内的钢筋900平滑地移动的杆引导件800等。In addition, on the inner side of the steel bar joint 310, (although not shown in the figure), it is also possible to provide an annular protrusion or a helical protrusion similarly to the case of the first tubular member 110, and even to enable The rod guide 800 and the like that move the rebar 900 movably incorporated into the first rebar joint 310 move smoothly.
接下来,关于设在所述钢筋接头310内的钢筋900的长度,与所述第1PCa部件110的情况同样地,在被装入到了所述钢筋接头310的内部的情况下,形成为收纳于所述钢筋接头310的内部的长度,使得不从所述第3PCa部件300的接合侧的侧面大幅地突出,与此同时,考虑待接合的PCa部件相互之间的间隔或PCa部件整体的尺寸来确定。另外,所述钢筋900可以与上述同样地直接使用现有的异形钢筋等,但在所述钢筋900的端部也可以设置例如环状等卡定部910,从而能够利用卡定部910进行所述钢筋900的拉出。另外,当然,在所述钢筋900的周围,由于在所述钢筋接头310内随后填充灰浆,因此,需要考虑能够使所述灰浆在所述钢筋接头310内流通的程度的外径。Next, regarding the length of the reinforcing bar 900 provided in the reinforcing bar joint 310, similarly to the case of the first PCa member 110, when it is incorporated into the inside of the reinforcing bar joint 310, it is formed to be stored in The length of the inside of the steel bar joint 310 is such that it does not protrude greatly from the side surface of the joint side of the third PCa member 300, and at the same time, the distance between the PCa members to be joined or the size of the entire PCa member is considered. Sure. In addition, the steel bar 900 can directly use the existing special-shaped steel bar or the like in the same manner as above, but the end of the steel bar 900 can also be provided with, for example, a ring-shaped locking part 910, so that the locking part 910 can be used to perform all operations. The pulling out of steel bar 900 is described. In addition, as a matter of course, since mortar is subsequently filled in the reinforcement joint 310 around the reinforcement bar 900 , it is necessary to consider an outer diameter to the extent that the mortar can flow through the reinforcement joint 310 .
根据如上述那样构成的第3PCa部件300,能够预先在所述第3PCa部件300中埋入所述钢筋接头310,并将钢筋900能够移动地装入所述钢筋接头310中。According to the third PCa member 300 configured as above, the rebar joint 310 can be embedded in the third PCa member 300 in advance, and the rebar 900 can be movably incorporated into the rebar joint 310 .
因此,在使所述第3PCa部件300与另一PCa部件接合的情况下,例如也能够与图23所示那样的埋入有钢筋接头2410的现有的预制部件2400、或者埋入有第1管状部件110但未装入钢筋900的上述那样的另一个第1PCa部件100等接合在一起。并且,这种情况下,能够利用构成上述那样的楔形槽100C等的凹部,通过手动作业将所述钢筋900连通到欲接合的上述那样的PCa部件(2400等)之间,然后,将所述钢筋900分别固定于这些欲接合的PCa部件。Therefore, in the case of joining the third PCa member 300 to another PCa member, for example, it can also be used with an existing prefabricated member 2400 embedded with a reinforcement joint 2410 as shown in FIG. The tubular member 110 is jointed with another first PCa member 100 as described above which does not incorporate the reinforcing bar 900 . And, in this case, the reinforcing bar 900 can be communicated between the above PCa members (2400 etc.) Rebar 900 is respectively fixed to these PCa members to be joined.
另外,在采用了与所述第3PCa部件300组合起来使用的后述的第4PCa部件400的情况下,能够更容易地拉出所述钢筋900,实现PCa部件相互间的接合。In addition, when the fourth PCa member 400 described later that is used in combination with the third PCa member 300 is used, the reinforcing bar 900 can be pulled out more easily, and the PCa members can be joined to each other.
另外,在如上述那样将所述钢筋900装入到第3PCa部件300时,与将所述钢筋900装入到上述的第1PCa部件100的情况同样地,如图16(A)和图17所示,也可以在构成所述第1钢筋接头310的套筒的内侧的所述钢筋900的拉出侧预先一起安装密封用管状部件700,其中,该密封用管状部件700围绕所述钢筋900的轴向的周围,并在上述待接合的PCa部件的接合部之间将所述钢筋900的周围密封。In addition, when the steel bar 900 is incorporated into the third PCa member 300 as described above, it is the same as the case where the steel bar 900 is incorporated into the first PCa member 100 described above, as shown in FIGS. 16(A) and 17 . As shown, a sealing tubular member 700 may be installed together in advance on the pull-out side of the steel bar 900 inside the sleeve constituting the first steel bar joint 310, wherein the sealing tubular member 700 surrounds the steel bar 900. The periphery of the axial direction, and seal the periphery of the steel bar 900 between the joints of the PCa components to be joined.
在此,上述图16是示出使用所述密封用管状部件700来接合所述第3PCa部件300和另一PCa部件的例子的图,图16(A)是示出如下例子的侧剖视图:在构成所述第1钢筋接头310的套筒的内侧的所述钢筋900的拉出侧预先设置密封用管状部件700,其中,该密封用管状部件700围绕所述钢筋900的轴向的周围,并在上述待接合的PCa部件的接合部之间将所述钢筋900的周围密封。另外,图16(B)是示出埋入有图23(B)所示那样的钢筋接头2410的现有的预制部件2400来作为与所述第3PCa部件300接合的PCa部件的例子的侧剖视图,图16(C)是示出通过上述的结构将第3PCa部件300和所述现有的预制部件2400接合在一起的状态的侧剖视图。另外,上述图17示出了与上述图16对应的结构的立体图,图17(A)是示出接合前的所述第3PCa部件300和另一PCa部件各自的状态的立体图,图17(B)是示出接合后的所述第3PCa部件300和另一PCa部件的状态的立体图。并且,在上述图17(B)中,接合部730上的基于粘接剂等的密封状态省略示出。Here, the above-mentioned FIG. 16 is a diagram showing an example of joining the third PCa member 300 and another PCa member using the sealing tubular member 700, and FIG. 16(A) is a side sectional view showing an example of: The pull-out side of the steel bar 900 inside the sleeve constituting the first steel bar joint 310 is pre-set with a sealing tubular member 700, wherein the sealing tubular member 700 surrounds the axial circumference of the steel bar 900, and The periphery of the reinforcing bar 900 is sealed between the joint portions of the PCa members to be joined. In addition, FIG. 16(B) is a side cross-sectional view showing an example of a PCa member joined to the third PCa member 300 using a conventional prefabricated member 2400 embedded with a reinforcing bar joint 2410 as shown in FIG. 23(B) , FIG. 16(C) is a side sectional view showing a state in which the third PCa member 300 and the existing prefabricated member 2400 are joined together by the above-mentioned structure. In addition, the above-mentioned FIG. 17 shows a perspective view of the structure corresponding to the above-mentioned FIG. 16, and FIG. ) is a perspective view showing the state of the third PCa member 300 and another PCa member after bonding. In addition, in the above-mentioned FIG. 17(B), the sealing state of the joint portion 730 by an adhesive or the like is omitted from illustration.
并且,所述密封用管状部件700可以与针对上述第1PCa部件的接合所说明的同样地使用护套管等圆筒状的部件,在将所述第3PCa部件与另一PCa部件接合时,将所述密封用管状部件700与所述钢筋一起从所述第1钢筋接头拉出来使用。这样拉出的所述密封用管状部件700在所述接合部之间围绕所述钢筋的轴向的周围,同时和欲与所述第3PCa部件300接合的所述另一个第1PCa部件100的管状部件110、或者在上述图16(B)所例示那样的现有的PCa部件2400中埋入的钢筋接头2410、或者后述的第4PCa部件400的第2钢筋接头410等连通,然后在所述待接合的各个PCa部件的侧面通过粘接剂等对所述密封用管状部件700与所述各钢筋接头接合的接合部730密封。In addition, the sealing tubular member 700 may use a cylindrical member such as a sheath tube in the same manner as described above for joining the first PCa member, and when joining the third PCa member to another PCa member, the The sealing tubular member 700 is pulled out from the first steel bar joint together with the steel bar for use. The sealing tubular member 700 drawn out in this way surrounds the axial periphery of the steel bar between the joints, and at the same time engages with the tubular member of the other first PCa member 100 to be joined with the third PCa member 300 . Component 110, or the reinforced joint 2410 embedded in the existing PCa component 2400 as illustrated in the above-mentioned Fig. 16 (B), or the second reinforced joint 410 of the 4th PCa component 400 described later, etc. The side surfaces of the respective PCa members to be joined are sealed with an adhesive or the like to the junction portion 730 where the sealing tubular member 700 is joined to the respective steel bar joints.
因此,在使用了这样的密封用管状部件700的情况下,与用于上述的第1PCa部件100的情况同样地,即使在欲接合的所述第3PCa部件和另一PCa部件的接合部之间形成有楔形槽100C等间隙的情况下,也能够将所述待接合的所述第3PCa部件300和另一PCa部件各自的钢筋接头310或管状部件110等从外部密闭而连通。因此,通过采用这样的结构,在将灰浆填充于所述钢筋接头310或管状部件110内的情况下,能够在所述待接合的所述第3PCa部件300和另一PCa部件之间没有泄漏地进行填充从而固定所述钢筋900。并且,在上述的例子中,例如也可以是:利用所述第3PCa部件300的灰浆注入口313进行灰浆的注入,并利用现有的PCa部件2400的灰浆排出口2415进行多余的灰浆的排出,这种情况下,如上述图16所示,也可以构成为省略现有的PCa部件2400的灰浆注入口。Therefore, when such a sealing tubular member 700 is used, as in the case of using the above-mentioned first PCa member 100, even between the junction between the third PCa member to be joined and another PCa member When gaps such as the wedge-shaped groove 100C are formed, the third PCa member 300 to be joined and the other PCa member each have their respective rebar joints 310 or tubular members 110 sealed from the outside to communicate with each other. Therefore, by adopting such a structure, when the mortar is filled in the reinforcing bar joint 310 or the tubular member 110, it is possible to ensure that there is no leakage between the third PCa member 300 to be joined and another PCa member. Filling is performed to fix the reinforcement 900 . In addition, in the above-mentioned example, for example, the mortar injection port 313 of the third PCa member 300 may be used to inject the mortar, and the mortar discharge port 2415 of the existing PCa member 2400 may be used to discharge excess mortar. In this case, as shown in FIG. 16 above, the mortar injection port of the conventional PCa member 2400 may be omitted.
接下来,对所述第4PCa部件400进行说明。如图13(B)、(C)所示,所述第4PCa部件400与所述第2PCa200部件等同样地具备用于拉出钢筋的结构即引导通道,但在下述方面不同:作为用于将装入于所述第3PCa部件300的第1钢筋接头310中的钢筋900拉出的路径,使用第2钢筋接头410而不是上述的管状部件210等。Next, the fourth PCa member 400 will be described. As shown in Fig. 13(B) and (C), the 4th PCa member 400 has the same structure as the 2nd PCa200 member and the like, that is, a guide channel for pulling out a steel bar, but differs in the following respects: The route for pulling out the steel bar 900 incorporated in the first steel bar joint 310 of the third PCa member 300 uses the second steel bar joint 410 instead of the above-mentioned tubular member 210 or the like.
更具体来说,如图13(B)所示,所述第4PCa部件400是具备用于将所述钢筋900从所述第3PCa部件300的所述第1钢筋接头310拉出的引导通道(第2钢筋接头)410的PCa部件,在使用所述第4PCa部件400的情况下,对于装入于所述第3PCa部件300中的钢筋900,使用在一端侧形成有卡定件910的钢筋。这是因为:所述第4PCa部件400如后述那样采用将线从线贯插部417贯插并将钢筋900拉出的结构,因此,希望在钢筋900侧也具有与此相对应的结构。并且,上述卡定件910的结构并不特别限定,也可以如针对上述的图5(B)或图13(A)所示的钢筋900所示出的例子那样,是设置于异形钢筋的末端的环状的结构等。More specifically, as shown in FIG. 13(B), the 4th PCa member 400 is equipped with a guide channel for pulling the steel bar 900 out of the first steel bar joint 310 of the 3rd PCa member 300 ( When the fourth PCa member 400 is used as the PCa member of the second steel bar joint) 410, as the reinforcing bar 900 incorporated in the third PCa member 300, a reinforcing bar having a locking piece 910 formed on one end side is used. This is because the fourth PCa member 400 has a structure in which a wire is inserted through the wire insertion portion 417 to pull out the reinforcing bar 900 as will be described later, and therefore it is desirable to have a corresponding structure on the reinforcing bar 900 side. And, the structure of above-mentioned locking part 910 is not particularly limited, also can be arranged on the end of special-shaped steel bar as the example shown for the steel bar 900 shown in above-mentioned Fig. 5 (B) or Fig. 13 (A) ring structure, etc.
另外,由于所述第4PCa部件400与所述第3PCa部件300的侧面侧接合,因此,所述引导通道410如上述那样由所述第2钢筋接头410形成,所述第2钢筋接头410的一端侧在所述第4PCa部件400的和所述第3PCa部件300接合的侧面侧与设置于所述第3PCa部件300的第1钢筋接头310的一端侧(开口端侧)对置地设置。In addition, since the fourth PCa member 400 is joined to the side surface of the third PCa member 300, the guide channel 410 is formed by the second reinforcement joint 410 as described above, and one end of the second reinforcement joint 410 The side surface of the fourth PCa member 400 joined to the third PCa member 300 is provided to face one end side (open end side) of the first rebar joint 310 provided on the third PCa member 300 .
另外,在所述第2钢筋接头310的另一端侧,与所述第3PCa部件300的情况相同地预先埋入构成所述第4PCa部件400的钢筋900P。即,通过预先埋入于所述第4PCa部件400中而具备所述第2钢筋接头410,但其构成为:在其埋入时,构成所述第4PCa部件400的钢筋900P配置并固定成,从构成所述第2钢筋接头410的套筒的一端侧延伸至所述第2钢筋接头410的内侧的适当位置,然后在对能够移动地装入于所述第2钢筋接头410中的钢筋900进行固定时,通过将它们组合起来,由此实现了功能上的一体性。In addition, on the other end side of the second reinforcing bar joint 310 , a reinforcing bar 900P constituting the fourth PCa member 400 is embedded in advance in the same manner as in the case of the third PCa member 300 . That is, the second steel bar joint 410 is provided by being embedded in the fourth PCa member 400 in advance, but it is configured such that the reinforcing bars 900P constituting the fourth PCa member 400 are arranged and fixed at the time of embedding, Extend from one end side of the sleeve constituting the second steel bar joint 410 to an appropriate position inside the second steel bar joint 410 , and then place the steel bar 900 movably loaded in the second steel bar joint 410 When fixing, by combining them, functional unity is achieved.
另外,在所述第2钢筋接头410的轴向的中央部设置有线贯插部417,该线贯插部417是从所述第2钢筋接头410的侧面与所述第4PCa部件400的正面侧连通的开口部。所述线贯插部417形成为如下的目的:将线从所述第4PCa部件400的所述线贯插部417插入所述第2钢筋接头410的内部,将所述线与装入于所述第3PCa部件300的所述第1钢筋接头310中的所述钢筋900的卡定部910连接,从而将所述钢筋900拉出至所述第2钢筋接头410的内部。并且,在此,也可以在所述线上设置与设置于所述钢筋900的卡定部910卡合的钩等卡定构件。In addition, a wire insertion portion 417 is provided at the central portion of the second reinforcement joint 410 in the axial direction. connected opening. The wire insertion portion 417 is formed for the purpose of inserting a wire from the wire insertion portion 417 of the fourth PCa member 400 into the second rebar joint 410, and inserting the wire into the second reinforcement joint 410. The locking part 910 of the steel bar 900 in the first steel bar joint 310 of the third PCa member 300 is connected, so that the steel bar 900 is pulled out to the inside of the second steel bar joint 410 . In addition, here, a locking member such as a hook that engages with the locking portion 910 provided on the reinforcing bar 900 may be provided on the wire.
另外,上述线贯插部417的目的在于,如上述那样将线插入,将装入于所述第1钢筋接头310中的所述钢筋900拉出,因此,只要能够实现该目的,上述线贯插部417的形态并不特别限定。因此,例如在上述图13(B)、(C)中,所述线贯插部417从所述第2钢筋接头410的侧方与所述第4PCa部件400的正面垂直地延伸,但也可以斜着延伸,另外,也可以使所述开口部朝向内侧成为漏斗状,以便容易从所述线贯插部417的处于PCa部件400的正面的开口部对内侧进行目视确认。In addition, the purpose of the above-mentioned wire insertion portion 417 is to insert the wire as described above and pull out the steel bar 900 inserted in the first steel bar joint 310. Therefore, as long as this purpose can be achieved, the above-mentioned wire penetration The shape of the insertion portion 417 is not particularly limited. Therefore, for example, in the above-mentioned FIG. 13(B) and (C), the wire insertion portion 417 extends perpendicularly from the side of the second reinforcement joint 410 to the front of the fourth PCa member 400, but it may be It extends obliquely, and the opening may be funnel-shaped toward the inside so that it is easy to visually confirm the inside from the opening of the thread insertion portion 417 on the front surface of the PCa member 400 .
如以上那样,根据所述第4PCa部件400,按照图18所示的流程图所记载的步骤,能够非常容易地进行如所述第3PCa部件300那样构成的具有接合构件的PCa部件、和所述第4PCa部件400的接合。并且,在此,图18是示出使用了所述第3PCa部件300和所述第4PCa部件400的情况下的相互的接合步骤的流程图。As described above, according to the fourth PCa component 400, the PCa component having the joint member configured as the third PCa component 300 and the PCa component configured as the third PCa component 300 and the Bonding of 4th PCa component 400 . In addition, FIG. 18 is a flowchart showing a mutual bonding procedure when the third PCa member 300 and the fourth PCa member 400 are used.
即,最初,预先将所述钢筋900如上述那样能够移动地装入到所述第3PCa部件300的第1钢筋接头310的套筒内(步骤S100)。此时,上述钢筋900采用了在一端侧形成有卡定部910的结构,但其向上述第1钢筋接头410中的装入可以预先在PCa部件的制造工厂中进行,也可以在建筑现场进行PCa部件的相互接合之前来进行。That is, first, the rebar 900 is movably inserted into the sleeve of the first rebar joint 310 of the third PCa member 300 as described above (step S100 ). At this time, the reinforcing bar 900 has a structure in which the locking portion 910 is formed on one end side, but its insertion into the first reinforcing bar joint 410 may be carried out in advance at the PCa component manufacturing factory, or may be carried out at the construction site. The mutual bonding of the PCa components is performed before.
然后,接下来,使所述第3PCa部件300的侧面和所述第4PCa部件400的侧面抵接(步骤S200)。在此,所述第3PCa部件300的进行抵接的侧面是设置有构成所述第1钢筋接头310的套筒的开放端的一侧的侧面,所述第4PCa部件400的侧面是设置有由所述第2钢筋接头420形成的引导通道的出口侧的一侧,所述开放端和所述出口侧需要预先形成并配置在相互对置的位置。并且,上述侧面可以与上述的第1PCa部件100等同样地形成有构成楔形槽的凹部。Next, the side surface of the third PCa member 300 is brought into contact with the side surface of the fourth PCa member 400 (step S200 ). Here, the abutting side of the third PCa member 300 is the side on which the open end of the sleeve constituting the first steel bar joint 310 is provided, and the side of the fourth PCa member 400 is provided with the On the outlet side of the guide channel formed by the second steel bar joint 420, the open end and the outlet side need to be formed in advance and arranged at positions facing each other. In addition, the side surface may be formed with a concave portion constituting a wedge-shaped groove in the same manner as the first PCa member 100 described above.
如上述那样进行了第3PCa部件300和第4PCa部件400的配置后,接下来,从所述第4PCa部件400的线插入部417的开口端插入线,将所述线卡挂于所述钢筋900的卡定部910,将所述钢筋900的一部分拉出至所述第4PCa部件400的第2钢筋接头410,从而将所述钢筋900配置成跨越所述第3PCa部件300与所述第4PCa部件400之间(步骤S300)。因此,通过像这样将所述钢筋900配置成跨越所述第3PCa部件300的第1钢筋接头310和所述第4PCa部件400的第2钢筋接头410之间,由此,上述第1钢筋接头310和第2钢筋接头410经由所述钢筋900成为能够连接的状态。After the third PCa member 300 and the fourth PCa member 400 are arranged as described above, next, a wire is inserted from the opening end of the wire insertion portion 417 of the fourth PCa member 400, and the wire is hooked to the reinforcing bar 900. part of the reinforcing bar 900 to the second reinforcing bar joint 410 of the fourth PCa member 400, so that the reinforcing bar 900 is arranged to straddle the third PCa member 300 and the fourth PCa member 400 (step S300). Therefore, by arranging the rebar 900 so as to straddle between the first rebar joint 310 of the third PCa member 300 and the second rebar joint 410 of the fourth PCa member 400, the first rebar joint 310 The second steel bar joint 410 is in a connectable state via the steel bar 900 .
接下来,在上述那样的配置结束后,利用灰浆的注入口(413、313)将砂浆等灰浆填充到所述第3PCa部件300的第1钢筋接头310和所述第4PCa部件400的第2钢筋接头410(步骤S400)。因此,通过上述灰浆的注入和随后的固化,能够将所述钢筋900稳定地保持于所述第1钢筋接头310和所述第2钢筋接头410。并且,此时,在如上述那样在接合部分形成有楔形槽的情况下,通过一并在所述楔形槽部分中也填充灰浆,能够进一步强化所述接合部分的强度。Next, after the arrangement as described above is completed, mortar such as mortar is filled into the first reinforcing bar joint 310 of the third PCa member 300 and the second reinforcing bar of the fourth PCa member 400 through the mortar injection port (413, 313). Connector 410 (step S400). Therefore, the reinforcing bar 900 can be stably held by the first reinforcing bar joint 310 and the second reinforcing bar joint 410 through the injection of the mortar and subsequent curing. In addition, at this time, when the wedge-shaped groove is formed in the joint portion as described above, the strength of the joint portion can be further strengthened by also filling the wedge-shaped groove portion with mortar.
如以上那样,根据本发明的具备接合构件的预制混凝土部件和使用了该预制混凝土部件的预制混凝土部件接合方法,能够尽可能消除后浇筑的现场混凝土而实现完全预制化,并且,对于建筑物的壁或地板等壁式(抗震壁)结构,不预先使钢筋从PCa部件的侧面突出,并且使用比较简便的结构就能够容易且可靠地进行PCa部件的接合。As described above, according to the precast concrete part including the joining member and the precast concrete part joining method using the precast concrete part of the present invention, it is possible to eliminate as much as possible post-cast on-site concrete and realize complete prefabrication. In a wall (seismic wall) structure such as a wall or a floor, the PCa members can be easily and reliably joined using a relatively simple structure without protruding reinforcing bars from the side surfaces of the PCa members.
并且,在本发明中,在PCa壁―PCa壁或PCa柱―PCa壁的铅直接合部,例如,在上述的现有技术中,上下层的PCa壁的水平接合部的接合方法是利用机械式接头将从下层突出的钢筋接合,因此,在上述的同层的PCa壁―PCa壁或PCa柱―PCa壁的铅直接合部处的接合方法中,需要用于钢筋的重合接头或喇叭形坡口焊接的空间,该部分不得不依赖现场浇筑的混凝土,与此相对,在本发明中,几乎能够实现完全预制化。And, in the present invention, in the lead joint portion of PCa wall-PCa wall or PCa column-PCa wall, for example, in above-mentioned prior art, the joint method of the horizontal joint portion of the PCa wall of upper and lower layer is to utilize mechanical The steel bar protruding from the lower layer is joined by the joint type joint, therefore, in the above-mentioned joint method at the direct joint of the PCa wall-PCa wall or the PCa column-PCa wall of the same floor, a coincident joint or trumpet joint for the steel bar is required. In contrast to the space for groove welding, which has to rely on concrete poured on site, in the present invention, almost complete prefabrication can be realized.
另外,在本发明中,利用待接合的PCa部件与部件的侧面(铅直接合部等)的间隙、即能够传递力的楔形槽和接缝宽度、且是存在能够通过人手移动的空间的间隙,将钢筋、密封用管状部件等拉出。In addition, in the present invention, the gap between the PCa component to be joined and the side surface of the component (lead joint, etc.), that is, the wedge-shaped groove and the width of the joint that can transmit force, and the gap that has a space that can be moved by human hands is used. , pull out the steel bars, sealing tubular parts, etc.
另外,上述的实施方式示出了本发明的结构的一例,本发明不限于上述的实施方式,能够在其主旨的范围内进行各种变形。In addition, the above-mentioned embodiment has shown an example of the structure of this invention, This invention is not limited to the above-mentioned embodiment, Various deformation|transformation is possible within the range of the summary.
因此,例如关于在所述第3PCa部件300或第4PCa部件400中使用的钢筋接头,可以使转矩固定方式的钢筋接头、无机或有机灰浆方式、或者并用了这些方式的螺纹钢筋接头、端部螺纹加工接头、砂浆填充式接头等各种金属接头形成为本发明规定的管状部件(110、310等)的尺寸来使用。另外,在本发明中使用的钢筋也能够与这些钢筋接头相对应地使用,除了上述的异形钢筋外,也可以使用螺纹钢筋等。Therefore, for example, with regard to the steel bar joint used in the third PCa member 300 or the fourth PCa member 400, a torque-fixed steel bar joint, an inorganic or organic mortar system, or a threaded steel bar joint using these systems in combination, and an end portion may be used. Various metal joints such as threaded joints and mortar-filled joints are formed into the dimensions of the tubular members (110, 310, etc.) specified in the present invention and used. In addition, the steel bar used by this invention can also be used corresponding to these steel bar joints, and threaded steel bars etc. can also be used other than the above-mentioned special-shaped steel bar.
并且,图19示出了如下的例子;作为上述那样的钢筋接头,例如,使用螺纹钢筋接头510A作为管状部件,其中,该螺纹钢筋接头510A形成为具有收纳钢筋并能够使钢筋移动的空间,作为在螺纹钢筋接头510A中使用的钢筋,使用了螺纹钢筋900N。在此,上述图19是对使用螺纹钢筋接头作为本发明的管状部件、并使用螺纹钢筋900N作为所述钢筋的例子进行图示的侧剖视图。And, Fig. 19 shows the following example; As the steel bar joint as described above, for example, a threaded steel bar joint 510A is used as a tubular member. As the reinforcing bar used in the threaded reinforcing bar joint 510A, the threaded reinforcing bar 900N was used. Here, the aforementioned FIG. 19 is a side sectional view illustrating an example in which a threaded steel bar joint is used as the tubular member of the present invention and a threaded steel bar 900N is used as the reinforcing bar.
在上述图19所示的例子中,如图19(A)所示,所述螺纹钢筋接头510A被埋入于PCa部件500A的内部,构成所述PCa部件500A的螺纹钢筋900Q被埋入于所述螺纹钢筋接头510A的一端侧。并且,另一端侧与所述PCa部件500A的和另一PCa部件接合的面的一侧相接而成为开放端,并且形成为能够将所述螺纹钢筋900N从所述开放端的一侧装入到所述螺纹钢筋接头510A内。In the above example shown in FIG. 19 , as shown in FIG. 19(A), the threaded steel joint 510A is embedded in the PCa member 500A, and the threaded steel bar 900Q constituting the PCa member 500A is embedded in the PCa member 500A. One end side of the threaded rebar joint 510A. In addition, the other end side is in contact with one side of the surface of the PCa member 500A that is joined to another PCa member to form an open end, and the rebar 900N can be inserted into the PCa member from the side of the open end. Inside the threaded rebar joint 510A.
另外,对于与上述PCa部件500A接合的另一PCa部件500B,如图19(B)所示,在其内部埋入有能够用于所述螺纹钢筋900N的钢筋接头510B,在钢筋接头510B的一端侧,与所述PCa部件500A的情况同样地埋入有构成所述PCa部件500B的螺纹钢筋900Q,另一端侧朝向接合面而成为开放端。In addition, for another PCa member 500B joined to the above-mentioned PCa member 500A, as shown in FIG. As in the case of the PCa member 500A, the threaded steel bar 900Q constituting the PCa member 500B is buried on one side, and the other end side is open toward the joining surface.
并且,所述PCa部件500B和埋入于所述PCa部件500B中的钢筋接头510B并不特别限定,对于所述钢筋接头510B,只要是能够用于所述螺纹钢筋900N的钢筋接头,可以使用任意的结构。因此,例如也可以使用作为市面上出售的エポック接头(注册商标)等所公知的、在日本特许第3807604号公报中记载的ネジフシ钢筋用接头等。In addition, the PCa member 500B and the reinforcement joint 510B embedded in the PCa member 500B are not particularly limited, and any steel joint 510B can be used as long as it can be used for the threaded steel bar 900N. Structure. Therefore, for example, a joint for rebars such as Nejifushi, which is known as a commercially available Epock joint (registered trademark) or the like and described in Japanese Patent No. 3807604, may also be used.
并且,在使用上述图19所示那样的结构来进行所述PCa部件500A和所述PCa部件500B的接合的情况下,如图19(A)所示,在接合前预先将螺纹钢筋900N装入到所述螺纹钢筋接头510A内,在接合时,如图19(C)所记载的那样,将所述螺纹钢筋900N以跨越所述PCa部件500A与所述PCa部件500B之间的方式拉出任意长度,借助所述螺纹钢筋900N连接所述PCa部件500A和所述PCa部件500B,并根据需要将环氧系树脂灰浆剂等从设置于所述PCa部件500A和所述PCa部件500B的灰浆注入口(513A,513B)注入并使其固化,从而完成所述PCa部件500A和所述PCa部件500B的接合。并且,考虑到如上述那样注入灰浆,也可以在所述螺纹钢筋900N上如图19(D1)、(D2)所示那样形成有无节部900NB,该无节部900NB是沿着所述螺纹钢筋900N的轴向将螺纹部分削除而成的。在此,上述图19(D1)是从轴向观察在所述螺纹钢筋上设置有无节部900NB的例子的图,图19(D2)是从与轴向垂直的方向观察的图。And, in the case where the PCa member 500A and the PCa member 500B are joined using the structure shown in FIG. 19, as shown in FIG. Into the threaded steel joint 510A, at the time of joining, as shown in FIG. 19(C), the threaded steel bar 900N is pulled out arbitrarily in a manner spanning between the PCa member 500A and the PCa member 500B. length, connect the PCa part 500A and the PCa part 500B by means of the threaded steel bar 900N, and inject epoxy resin mortar and the like from the mortar injection port provided on the PCa part 500A and the PCa part 500B (513A, 513B) is injected and allowed to cure, thereby completing the bonding of the PCa part 500A and the PCa part 500B. In addition, considering the injection of mortar as described above, it is also possible to form a no-knot portion 900NB on the threaded steel bar 900N as shown in FIG. 19(D1) and (D2). The 900N steel bar is made by cutting off the threaded part in the axial direction. Here, the above-mentioned FIG. 19 (D1) is a view of an example in which the no-knot portion 900NB is provided on the threaded steel bar viewed from the axial direction, and FIG. 19 (D2) is a view viewed from a direction perpendicular to the axial direction.
因此,如上述那样,通过使用螺纹钢筋接头510A作为本发明的管状部件,并灵活使用螺纹钢筋900N作为用于本发明的钢筋,由此也能够实现本发明的PCa部件相互间的接合。Therefore, as described above, by using the threaded steel bar joint 510A as the tubular member of the present invention and utilizing the threaded steel bar 900N as the steel bar used in the present invention, the joining of the PCa members of the present invention can also be realized.
另外,在上述的例子中使用了螺纹钢筋接头510A,但存在上述螺纹钢筋的尺寸精度较差的情况,也需要注入灰浆。因此,在本发明中,也可以是:不使用上述那样的螺纹钢筋接头,如图20所示,使用在本发明的管状部件的内侧形成有内螺纹的结构(例如,长螺母)和全螺纹螺栓(长螺钉)。并且,在此,上述图20是对下述例子进行图示的侧剖视图:使用在内侧形成有内螺纹的长螺母来作为本发明的管状部件,并使用与所述长螺母螺合的全螺纹螺栓来作为钢筋。In addition, in the above-mentioned example, the threaded steel bar joint 510A is used, but the dimensional accuracy of the above-mentioned threaded steel bar may be poor, and it is also necessary to inject mortar. Therefore, in the present invention, instead of using the threaded steel bar joint as described above, as shown in FIG. Bolts (long screws). 20 is a side sectional view illustrating an example in which a long nut having an internal thread formed inside is used as the tubular member of the present invention, and a full thread threaded with the long nut is used. Bolts come as reinforcement.
在上述图20所示的例子中,被用作本发明的管状部件的长螺母1010A是在内侧形成有内螺纹的结构,只要是如下的结构则也可以使用通常在市面上售卖的长螺母:将后述那样的全螺纹螺栓1900装入,并具有能够在接合时将全螺纹螺栓1900拉出任意长度的尺寸等。In the above-mentioned example shown in FIG. 20, the long nut 1010A used as the tubular member of the present invention has a structure in which an internal thread is formed on the inside, and a long nut generally sold on the market can also be used as long as it has the following structure: A full-thread bolt 1900 as described later is incorporated, and has a dimension such that the full-thread bolt 1900 can be pulled out to an arbitrary length at the time of joining.
并且,如图20(A)所示,所述长螺母1010A被埋入于PCa部件1000A的内部,在其一端侧连接有构成所述PCa部件1000A的钢筋900R。并且,在此,所述长螺母1010A与所述钢筋900R的连接结构并不特别限定,但在本实施方式中,预先在所述钢筋900R的所述长螺母1010A侧设置切削螺纹部900RS,将所述切削螺纹部900RS借助锁定螺母1030通过螺纹作用以嵌合(螺合)的方式连接于所述长螺母1010A。And, as shown in FIG. 20(A), the long nut 1010A is embedded in the PCa member 1000A, and a steel bar 900R constituting the PCa member 1000A is connected to one end thereof. In addition, here, the connection structure between the long nut 1010A and the steel bar 900R is not particularly limited, but in this embodiment, the cutting thread portion 900RS is provided in advance on the side of the long nut 1010A of the steel bar 900R, and the The cutting thread portion 900RS is connected to the long nut 1010A in a fitted (screwed) manner by screw action via a lock nut 1030 .
另外,所述长螺母1010A的另一端侧与所述PCa部件1000A的和另一PCa部件接合的面的一侧相接而成为开放端,并且构成为能够从所述开放端的一侧将所述全螺纹螺栓1900向所述长螺母1010A内外进行螺纹进给(螺送)。并且,在所述图20(A)的例子中,示出了所述全螺纹螺栓1900被螺纹进给至所述长螺母1010A的内部的状态,在所述开放端侧,在所述全螺纹螺栓1900上设有双螺母(1030A、1030B),能够利用所述双螺母(1030A、1030B)等使所述全螺纹螺栓1900移动。In addition, the other end side of the long nut 1010A is in contact with one side of the surface of the PCa member 1000A that is bonded to another PCa member to form an open end, and the long nut 1010A is configured so that the The fully threaded bolt 1900 is screw-fed (screw-fed) inside and outside the long nut 1010A. In addition, in the example of FIG. 20(A), the state in which the full-thread bolt 1900 is screw-fed into the inside of the long nut 1010A is shown, and on the open end side, the full-thread Double nuts (1030A, 1030B) are provided on the bolt 1900, and the full thread bolt 1900 can be moved by using the double nuts (1030A, 1030B) or the like.
另外,对于在本发明的上述实施方式中使用的所述全螺纹螺栓1900,并不特别限定设计,但需要至少能够与形成于所述长螺母1010A的内螺纹螺合。另外,所述全螺纹螺栓1900的直径也可以采用构成所述PCa部件1000A的钢筋900R的直径以外的直径,因此,也可以使用直径比所述钢筋900R更大的全螺纹螺栓。In addition, the design of the full-thread bolt 1900 used in the above-mentioned embodiment of the present invention is not particularly limited, but it needs to be capable of screwing at least with the internal thread formed in the long nut 1010A. In addition, the diameter of the full-thread bolt 1900 may be other than the diameter of the reinforcing bar 900R constituting the PCa member 1000A, and therefore, a full-thread bolt having a larger diameter than the reinforcing bar 900R may be used.
另外,关于与上述PCa部件1000A接合的另一PCa部件1000B,如图20(B)所示,在其内部埋入有能够与所述全螺纹螺栓1900螺合的长螺母1010B,在长螺母1010B的一端侧,与所述PCa部件1000A的情况同样地连接有构成所述PCa部件1000B的钢筋900R,另一端侧朝向接合面而成为开放端。In addition, regarding another PCa member 1000B joined to the above-mentioned PCa member 1000A, as shown in FIG. In the same manner as in the case of the PCa member 1000A, the steel bar 900R constituting the PCa member 1000B is connected to one end side thereof, and the other end side is an open end facing the joining surface.
因此,在使用上述图20所示那样的结构进行所述PCa部件1000A与所述PCa部件1000B的接合的情况下,如图20(A)所示,在接合前预先使全螺纹螺栓1900螺纹进给而将其装入到构成所述管状部件的长螺母1010A内。然后,在接合时,如图20(C)所记载的,通过利用双螺母(1030A、1030B)等来使所述全螺纹螺栓1900螺纹进给而移动,将其以跨越所述PCa部件1000A与所述PCa部件1000B之间的方式拉出任意长度,从而借助所述全螺纹螺栓1900N连接所述PCa部件1000A和所述PCa部件1000B。然后,接着将构成所述双螺母(1030A、1030B)的各个螺母在所述PCa部件1000A和所述PCa部件1000B中作为所述全螺纹螺栓1900的锁定螺母来使用,完成接合。Therefore, in the case of joining the PCa member 1000A and the PCa member 1000B using the structure shown in FIG. 20 above, as shown in FIG. Instead, it is loaded into the long nut 1010A constituting the tubular member. Then, at the time of engagement, as shown in FIG. 20(C), the fully threaded bolt 1900 is moved by screw-feeding the full-threaded bolt 1900 by using double nuts (1030A, 1030B) or the like, to straddle the PCa member 1000A and The way between the PCa parts 1000B is pulled out to any length, so as to connect the PCa part 1000A and the PCa part 1000B by means of the full thread bolt 1900N. Then, the respective nuts constituting the double nuts (1030A, 1030B) are then used as lock nuts for the full-thread bolt 1900 in the PCa component 1000A and the PCa component 1000B to complete the joint.
因此,在使用了本发明的PCa部件的如下的接合构件的情况下,不进行灰浆的填充就能够实现PCa部件相互间的接合:如上述那样将长螺母1010A用作管状部件,并将全螺纹螺楔形槽1900用作钢筋。另外,虽然未图示,但作为应用例,如果利用PCa部件1000A与PCa部件1000B的间隙在间隙部分中使用与1010B同样的长螺母,则也能够缩短1010A的长度,从而缩短移动距离。Therefore, in the case of using the joining member of the PCa parts of the present invention, the joint between the PCa parts can be realized without filling the mortar: the long nut 1010A is used as the tubular part as described above and the full thread Spiral wedge grooves 1900 serve as reinforcing bars. Also, although not shown, as an application example, if the gap between PCa member 1000A and PCa member 1000B is used and the same long nut as 1010B is used in the gap, the length of 1010A can be shortened to shorten the moving distance.
另外,作为本发明的再一个不同的展开例,在上述实施方式的例子中,关于上述接合构件的配置,示出了配置于PCa部件的一个侧面的情况,但不限于此,也可以采用其它的配置。In addition, as yet another different development example of the present invention, in the example of the above-mentioned embodiment, the arrangement of the above-mentioned joining member was shown as being arranged on one side of the PCa member, but it is not limited thereto, and other arrangements may also be adopted. Configuration.
因此,可以将上述的第1管状部件110等例如如图21(A)示意性地所示那样配置于构成PCa部件的对置的侧面上、或者同样如图21(B)所示那样配置于PCa部件的包含四方在内的周围的各侧面上,然后装入钢筋900来使用,这对于包含有上述的钢筋接头(310、410)的接合构件也是同样的。并且,例如也可以将上述接合构件沿着使壁面相互连接的水平方向或者使柱和柱连接这样的垂直方向进行设置。并且,在此,图21是示意性地示出本发明的第1管状部件等接合构件相对于PCa部件的配置例的、包含有局部透视图的主视图。Therefore, the above-mentioned first tubular member 110 and the like may be arranged, for example, as schematically shown in FIG. Reinforcing bars 900 are incorporated into the surrounding sides of the PCa member including the squares, and the same applies to joint members including the aforementioned reinforcing bar joints ( 310 , 410 ). In addition, for example, the joint member may be provided along a horizontal direction connecting wall surfaces or a vertical direction connecting pillars. Here, FIG. 21 is a front view schematically showing an example of arrangement of joining members such as the first tubular member with respect to the PCa member according to the present invention, including a partial perspective view.
另外,也可以将构成为上述那样的第1PCa部件100的由第1管状部件110等构成的接合构件、和构成为第2PCa部件200的由第2管状部件210等构成的接合构件设置于一个PCa部件的对置的侧面上。即,如图21(C)示意性地所示,可以构成为:在单一的PCa部件的一个侧面侧设置装入有钢筋的所述第1管状部件110,在另一个侧面侧设置用于将钢筋拉出的第2管状部件210,这对于包含有上述的钢筋接头(310、410)的接合构件也是同样的。In addition, the bonding member composed of the first tubular member 110 and the like constituting the first PCa member 100 as described above and the bonding member composed of the second tubular member 210 and the like constituting the second PCa member 200 may be provided in one PCa. on the opposite side of the component. That is, as shown schematically in FIG. 21 (C), it may be configured as follows: the first tubular member 110 in which a reinforcing bar is loaded is provided on one side of a single PCa member, and the first tubular member 110 is provided on the other side for The second tubular member 210 from which the steel bar is pulled out is the same for the joining member including the above-mentioned steel bar joints (310, 410).
标号说明Label description
100、100B:第1PCa部件;100, 100B: 1st PCa component;
100C:形成于第1PCa部件的侧面上的楔形槽;100C: a wedge-shaped groove formed on the side of the 1st PCa component;
110:第1管状部件;110: the first tubular part;
113:灰浆注入口;113: Mortar injection port;
119:盖体;119: cover body;
200、200B:第2PCa部件;200, 200B: Part 2 PCa;
200C:形成于第2PCa部件的侧面上的楔形槽;200C: wedge-shaped groove formed on the side of the 2nd PCa component;
210:第2管状部件;210: the second tubular part;
213:钢筋拉出构件插入口;213: Insertion port of steel bar pulling member;
300:第3PCa部件;300: Part 3PCa;
310:第1钢筋接头;310: the first steel bar joint;
313:灰浆注入口;313: mortar injection port;
315:灰浆排出口;315: Mortar outlet;
400:第4PCa部件;400: Part 4PCa;
410:第2钢筋接头;410: the second steel bar joint;
413:灰浆注入口;413: Mortar injection port;
417:线插入部;417: line insertion part;
500A、500B:PCa部件(使用螺纹钢筋接头的结构);500A, 500B: PCa components (structures using threaded steel joints);
510A、510B:螺纹钢筋接头;510A, 510B: threaded steel joints;
513A、513B:灰浆注入口;513A, 513B: Mortar injection port;
600:手动剪;600: manual shear;
610:操作部;610: Operation Department;
630:柔性轴;630: flexible shaft;
650:把持部;650: control department;
700:密封用管状部件;700: Tubular part for sealing;
730:密封用管状部件与管状部件接合的接合部;730: a junction where the sealing tubular member is joined to the tubular member;
800:杆引导件;800: rod guide;
900、900P、900R:钢筋;900, 900P, 900R: steel bar;
900N、900Q:螺纹钢筋;900N, 900Q: threaded steel bar;
900NB:无节部;900NB: no section;
900RS:切削螺纹部;900RS: cutting thread;
910:设置于钢筋上的卡定部;910: the locking part arranged on the steel bar;
1000A、1000B:PCa部件(使用了长螺母的结构);1000A, 1000B: PCa parts (structure using long nuts);
1010A、1010B:长螺母;1010A, 1010B: long nuts;
1030:锁定螺母;1030: lock nut;
1030A、1030B:双螺母;1030A, 1030B: double nuts;
1900:全螺纹螺栓;1900: Fully threaded bolts;
2100、2200、2300、2400:PCa部件;2100, 2200, 2300, 2400: PCa components;
2413:具备钢筋接头的现有的PCa部件的灰浆注入口;2413: Mortar inlet for existing PCa components with rebar joints;
2415:具备钢筋接头的现有的PCa部件的灰浆排出口;2415: Mortar outlet for existing PCa components with rebar joints;
3000:螺纹式套筒接头;3000: threaded sleeve joint;
3100:套筒;3100: sleeve;
3110:切削螺纹部;3110: cutting thread;
3130:灰浆注入口;3130: Mortar injection port;
D:管状部件的开口部之间的间隔;D: spacing between the openings of the tubular member;
AS:地板相互的抵接面;AS: mutual abutment surfaces of floors;
NS:防漏密封件。NS: Leak-proof seal.
Claims (9)
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PCT/JP2016/070314 WO2018008152A1 (en) | 2016-07-08 | 2016-07-08 | Precast concrete member comprising connection means and method for connecting precast concrete member using same |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN107109837A true CN107109837A (en) | 2017-08-29 |
| CN107109837B CN107109837B (en) | 2018-10-02 |
Family
ID=58666333
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201680004575.8A Active CN107109837B (en) | 2016-07-08 | 2016-07-08 | The joint method of 2nd and the 4th precast concrete component and precast concrete component |
Country Status (3)
| Country | Link |
|---|---|
| JP (1) | JP6108422B1 (en) |
| CN (1) | CN107109837B (en) |
| WO (1) | WO2018008152A1 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108086483A (en) * | 2017-11-21 | 2018-05-29 | 北京建筑大学 | A kind of level can the pre-buried external member of pull and prefabricated assembled wall structure |
| CN115370001A (en) * | 2022-09-09 | 2022-11-22 | 龙信建设集团有限公司 | Grouting construction process for prestress assembly type concrete frame joint |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6978901B2 (en) * | 2017-11-08 | 2021-12-08 | 株式会社安藤・間 | Joining structure and joining method of precast concrete beam members |
| CN110005200B (en) * | 2019-04-24 | 2020-12-15 | 中建七局第一建筑有限公司 | Construction process for concrete pouring compaction of horizontal hidden beam |
| JP7574111B2 (en) | 2021-03-11 | 2024-10-28 | 株式会社フジタ | Reinforcing bar insertion tool and reinforcing bar assembly method |
| KR102840337B1 (en) * | 2024-05-14 | 2025-07-31 | (주)자연과환경 | Prefabricated house using precast-concrete module and its construction method |
| KR102958034B1 (en) * | 2024-08-21 | 2026-04-27 | 한국수력원자력 주식회사 | Method for constructing sheathed tendon |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1058821A (en) * | 1991-05-24 | 1992-02-19 | 钟莉 | Reinforcing bar connector |
| CN101356318A (en) * | 2006-06-15 | 2009-01-28 | 株式会社大宇建设 | Precast concrete block with connection structure using steel pipes and connection structure thereof |
| CN101603330A (en) * | 2009-06-29 | 2009-12-16 | 中国建筑第五工程局有限公司东莞分公司 | Steel-concrete combined structure non-welding node connector |
| JP2015200146A (en) * | 2014-04-10 | 2015-11-12 | 鹿島建設株式会社 | Precast concrete member joining method and precast concrete member |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5532136B1 (en) * | 1976-03-25 | 1980-08-22 | ||
| JPH0462808U (en) * | 1990-10-09 | 1992-05-28 | ||
| JP2009281102A (en) * | 2008-05-26 | 2009-12-03 | Takenaka Komuten Co Ltd | Grout tool, and method for confirming grout filling in slide joint construction method of precast concrete beam using the same |
| JP5620062B2 (en) * | 2009-01-05 | 2014-11-05 | 株式会社竹中工務店 | Column wall structure and building having column wall structure |
| JP6243147B2 (en) * | 2013-06-18 | 2017-12-06 | 日本スプライススリーブ株式会社 | Method for connecting curved precast members and connecting structure thereof |
-
2016
- 2016-07-08 CN CN201680004575.8A patent/CN107109837B/en active Active
- 2016-07-08 WO PCT/JP2016/070314 patent/WO2018008152A1/en not_active Ceased
- 2016-07-08 JP JP2016565081A patent/JP6108422B1/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1058821A (en) * | 1991-05-24 | 1992-02-19 | 钟莉 | Reinforcing bar connector |
| CN101356318A (en) * | 2006-06-15 | 2009-01-28 | 株式会社大宇建设 | Precast concrete block with connection structure using steel pipes and connection structure thereof |
| CN101603330A (en) * | 2009-06-29 | 2009-12-16 | 中国建筑第五工程局有限公司东莞分公司 | Steel-concrete combined structure non-welding node connector |
| JP2015200146A (en) * | 2014-04-10 | 2015-11-12 | 鹿島建設株式会社 | Precast concrete member joining method and precast concrete member |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108086483A (en) * | 2017-11-21 | 2018-05-29 | 北京建筑大学 | A kind of level can the pre-buried external member of pull and prefabricated assembled wall structure |
| CN115370001A (en) * | 2022-09-09 | 2022-11-22 | 龙信建设集团有限公司 | Grouting construction process for prestress assembly type concrete frame joint |
| CN115370001B (en) * | 2022-09-09 | 2024-04-09 | 龙信建设集团有限公司 | Grouting construction process for prestressed assembled concrete frame joints |
Also Published As
| Publication number | Publication date |
|---|---|
| WO2018008152A1 (en) | 2018-01-11 |
| JP6108422B1 (en) | 2017-04-05 |
| JPWO2018008152A1 (en) | 2018-07-05 |
| CN107109837B (en) | 2018-10-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107109837B (en) | The joint method of 2nd and the 4th precast concrete component and precast concrete component | |
| CN100408791C (en) | High-strength grouting pipe joint | |
| US5366672A (en) | Method of forming concrete structures with a grout splice sleeve which has a threaded connection to a reinforcing bar | |
| KR101433654B1 (en) | Sleeve Lib Joint usable with precast concrete, Manufacturing method for precast concrete having the same, and Installing method for precast concreat structure having the same | |
| CN1167515A (en) | Filled Mortar Type Rebar Joints | |
| GB2034857A (en) | Connecting reinforcement rods | |
| KR101829826B1 (en) | Segment type arch structure and method for constructing this same | |
| KR101371216B1 (en) | Fitted Coupler with Spiral or Deformed Rebar | |
| JP2018178365A (en) | Rebar fitting coupler | |
| JP5213249B2 (en) | Pile head structure of precast concrete pile and pile head formation method | |
| CN107724541B (en) | Building element connection structure | |
| KR101939949B1 (en) | Half-pc column based on framed rebar column | |
| JP6279962B2 (en) | Precast concrete member joining method and precast concrete member | |
| JP2013036269A (en) | Sc pile | |
| JP2019035244A (en) | Joining structure and joining method | |
| EP1861562B1 (en) | Device for coupling sheaths | |
| KR102230819B1 (en) | Connector device and construction method for connecting precast concrete structures | |
| JP4272572B2 (en) | PC member joining method and PC member | |
| JP2005325518A (en) | Prestress introduction unit and prestress introduction method | |
| JP5008522B2 (en) | Precast concrete member joint structure, building, and building construction method | |
| JP2010185205A (en) | Reinforcement joint and method for connecting reinforcement | |
| JP4677792B2 (en) | Joining structure and joining method | |
| JP2006200270A (en) | Joining structure and joining method | |
| JP5584642B2 (en) | Method for fixing shear reinforcement member | |
| JPH07292770A (en) | Connection structure of corner columns and beams |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20210518 Address after: Tokyo, Japan Patentee after: FUJITA Corp. Address before: Kanagawa Prefecture, Japan Patentee before: Sampei Akihiko |