CN107059650A - Suspension bridge main push device - Google Patents
Suspension bridge main push device Download PDFInfo
- Publication number
- CN107059650A CN107059650A CN201710504417.5A CN201710504417A CN107059650A CN 107059650 A CN107059650 A CN 107059650A CN 201710504417 A CN201710504417 A CN 201710504417A CN 107059650 A CN107059650 A CN 107059650A
- Authority
- CN
- China
- Prior art keywords
- thrustor
- girder
- fining twisted
- twisted steel
- main push
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000000725 suspension Substances 0.000 title claims abstract description 13
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 52
- 239000010959 steel Substances 0.000 claims abstract description 52
- 238000005096 rolling process Methods 0.000 claims abstract 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 22
- 229910052742 iron Inorganic materials 0.000 claims description 11
- 238000004804 winding Methods 0.000 claims description 9
- 230000006872 improvement Effects 0.000 abstract description 2
- 238000000034 method Methods 0.000 abstract 2
- 238000010276 construction Methods 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/02—Suspension bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a suspension bridge main cable pushing device; after improvement, the front pushing device and the main cable are wound by a steel wire rope, and the hollow pushing jack realizes pushing; in the pushing process, the rear pushing device is positioned through the finish rolling deformed steel bar nut, the jack is operated manually to push the main cable to move for the single pushing stroke length corresponding to the support number, then the front pushing device is positioned through the finish rolling deformed steel bar nut, the rear pushing device is pushed for the same stroke length, and the process is circulated until the main cable is pushed to the target position. The device has simple integral structure, and can quickly realize the pushing operation of the main cable through the hollow pushing jack.
Description
Technical field
It is specifically a kind of main rope of suspension bridge thrustor the present invention relates to a kind of main push-towing rope incremental launching device.
Background technology
Suspension bridge, also known as suspension bridge, including Sarasota, anchorage, main push-towing rope, hoist cable, cord clip, cable saddle, steel girder(Or concrete master
Beam)Constructed Deng part.
Main push-towing rope is anchored in two sides by the cable saddle on Sarasota(Or bridge two ends)Basis(Anchorage)On, it is used as primary load bearing knot
Structure, is typically made up of steel wire or steel chain rope, as the main beam structure of the main supporting member of traffic loading, then passes through hoist cable and rope
Folder is contacted with main push-towing rope.
Its main push-towing rope geometry is determined that linear typically on upright plane is catenary by the equilibrium condition of power.And lead at present
The projection of cable in the plane is generally parallel lines, is easy to construct and controls.
But for some particular designs, to increase the monolithic stability meter of structure, constructed using space main push-towing rope, i.e. plane projection
For curve, this is calculated to design and construction process control brings great challenge, to ensure construction precision, it is necessary in erection of main beam
Before, in advance by main push-towing rope by special device lateral pushing to design attitude, and high-altitude more than hundred meters completes above-mentioned operation, this
It is the technical barrier not run into the past.Due to lacking efficient main push-towing rope thrustor, when to the urging action of bridge main push-towing rope, show
Inefficiency is obtained, security is poor, cost is high.
The content of the invention
Therefore, in order to solve above-mentioned deficiency, the present invention provides a kind of main rope of suspension bridge thrustor herein;Lead to after improvement
Wirerope-winding is crossed on preceding thrustor and main push-towing rope, hollow pushing tow jack realizes pushing tow;During pushing tow, pass through essence first
Roll screw-thread steel nut to position rear thrustor, manually operated jack, promote the single top of main push-towing rope movement respective support numbering
Haul distance is pushed away, then preceding thrustor is positioned by fining twisted steel nut, promotes equal stroke long rear thrustor
Degree, circulates this flow, until main push-towing rope is pushed into target location.The device overall structure of the invention is simple, passes through hollow pushing tow thousand
Quickly realize main push-towing rope urging action in jin top.
The present invention is achieved in that a kind of main rope of suspension bridge thrustor of construction, it is characterised in that:The main push-towing rope pushing tow
Device includes girder, and the two ends of girder are respectively arranged with one group of preceding thrustor, rear thrustor;The two ends of girder are set respectively
It is equipped with one group of screw thread bridle iron;Screwed on after passing through screw thread bridle iron by fining twisted steel nuts and washers fining twisted steel one end
Fixed, the other end is fixed by the screw-thread steel support base on girder;Wherein, fining twisted steel is through preceding thrustor, rear top
Pushing device, and preceding thrustor, rear thrustor pass through the fining twisted steel nut positioning on fining twisted steel;Preceding pushing tow
Jack is provided between device, rear thrustor, the wirerope-winding between preceding thrustor and main push-towing rope;
The pushing tow work of the main push-towing rope adjusting apparatus is by wirerope-winding on preceding thrustor and main push-towing rope, and hollow pushing tow is very heavy
Realize pushing tow in top;During pushing tow, rear thrustor is positioned by fining twisted steel nut first, manually operated jack,
The single pushing tow haul distance of main push-towing rope movement respective support numbering is promoted, then by fining twisted steel nut by preceding thrustor
Positioning, promotes equal haul distance by rear thrustor, this flow is circulated, until main push-towing rope is pushed into target location.
According to main rope of suspension bridge thrustor of the present invention, it is characterised in that:Thrustor is installed as follows:
Step 1:Girder is sling, positioned;
Step 2:Successively rear thrustor, preceding thrustor are installed on girder from end carriage side;
Step 3:Screw thread bridle iron, screw-thread steel support base are installed to girder relevant position;
Step 4:Fining twisted steel is passed through into preceding thrustor, rear thrustor;
Step 5:Forward and backward thrustor is positioned by fining twisted steel nut, it is ensured that equipment safety, and installed simultaneously very heavy
Top;
Step 6:End carriage side fining twisted steel nuts and washers is screwed on, girder, urging portion are installed.
The invention has the advantages that:The present invention provides a kind of main rope of suspension bridge thrustor herein by improving, described
Main push-towing rope thrustor includes girder, and the two ends of girder are respectively arranged with one group of preceding thrustor, rear thrustor;The two ends of girder
Head is respectively arranged with one group of screw thread bridle iron;Fining twisted steel one end pass through after screw thread bridle iron by fining twisted steel nut and
Packing ring screws on fixation, and the other end is fixed by the screw-thread steel support base on girder;Wherein, fining twisted steel is through preceding pushing tow dress
Put, rear thrustor, and preceding thrustor, rear thrustor determined by the fining twisted steel nut on fining twisted steel
Position;Jack is provided between preceding thrustor, rear thrustor, the wirerope-winding between preceding thrustor and main push-towing rope.This
After invention is improved, the pushing tow work of the main push-towing rope adjusting apparatus passes through wirerope-winding on preceding thrustor and main push-towing rope, empty
Heart pushing tow jack realizes pushing tow;During pushing tow, rear thrustor is positioned by fining twisted steel nut first, manually behaviour
Make jack, promote the single pushing tow haul distance of main push-towing rope movement respective support numbering, then will by fining twisted steel nut
Preceding thrustor positioning, promotes equal haul distance, this circulates this flow, until main push-towing rope is pushed into target by rear thrustor
Position.
Brief description of the drawings
Fig. 1 is the overall structure diagram of main push-towing rope thrustor of the present invention;
Fig. 2 is main push-towing rope thrustor overall structure top view of the present invention
Fig. 3 is main push-towing rope thrustor overall structure side schematic view of the present invention;
Fig. 4 is the right part schematic diagram of shown main push-towing rope thrustor.
Embodiment
Below in conjunction with accompanying drawing 1- Fig. 4, the present invention is described in detail, and the technical scheme in the embodiment of the present invention is entered
Row is clearly and completely described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole realities
Apply example.Based on the embodiment in the present invention, those of ordinary skill in the art are obtained under the premise of creative work is not made
Every other embodiment, belong to the scope of protection of the invention.
The present invention provides a kind of main rope of suspension bridge thrustor herein by improving, as Figure 1-Figure 4, can be according to such as
Under type is practiced;The main push-towing rope thrustor includes girder 1, and the two ends of girder 1 are respectively arranged with thrustor before one group
2nd, rear thrustor 3;The two ends of girder 1 are respectively arranged with one group of screw thread bridle iron 4;The one end of fining twisted steel 5 passes through screw thread
Fixation is screwed on by fining twisted steel nuts and washers after bridle iron 4, the other end is consolidated by the screw-thread steel support base 6 on girder 1
It is fixed;Wherein, fining twisted steel 5 is through preceding thrustor 2, rear thrustor 3, and preceding thrustor 2, rear thrustor
3 are positioned by the fining twisted steel nut on fining twisted steel 5;It is provided between preceding thrustor 2, rear thrustor 3 very heavy
Top 7, the wirerope-winding between preceding thrustor 2 and main push-towing rope 8.
The installation of main push-towing rope thrustor of the present invention is as follows:
1. girder 1 is sling, position;
2. rear thrustor 3, preceding thrustor 2 are installed on girder 1 by priority from end carriage side;
3. screw thread bridle iron 4, screw-thread steel support base 6 are installed to the relevant position of girder 1;
4. fining twisted steel 5 is passed through into preceding thrustor 2, rear thrustor 3;
5. forward and backward thrustor is positioned by fining twisted steel nut, it is ensured that equipment safety, and jack 7 is installed simultaneously;
6. end carriage side fining twisted steel nuts and washers is screwed on, girder, urging portion are installed.
Thrustor function:
The pushing tow work of main push-towing rope adjusting apparatus passes through wirerope-winding on preceding thrustor 2 and main push-towing rope 8, hollow pushing tow jack
7 realize pushing tow;During pushing tow, rear thrustor 3 is positioned by fining twisted steel nut first, manually operated jack 7,
The single pushing tow haul distance of the movement respective support numbering of main push-towing rope 8 is promoted, then preceding pushing tow is filled by fining twisted steel nut
2 positioning are put, rear thrustor 3 is promoted into equal haul distance, this flow is circulated, until main push-towing rope is pushed into target location.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or using the present invention.
A variety of modifications to these embodiments will be apparent for those skilled in the art, as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, it is of the invention
The embodiments shown herein is not intended to be limited to, and is to fit to and principles disclosed herein and features of novelty phase one
The most wide scope caused.
Claims (2)
1. a kind of main rope of suspension bridge thrustor, it is characterised in that:The main push-towing rope thrustor includes girder(1), girder(1)'s
Two ends are respectively arranged with thrustor before one group(2), rear thrustor(3);Girder(1)Two ends be respectively arranged with one group of spiral shell
Line bridle iron(4);Fining twisted steel(5)One end passes through screw thread bridle iron(4)Screwed on afterwards by fining twisted steel nuts and washers
Fixed, the other end passes through girder(1)On screw-thread steel support base(6)It is fixed;Wherein, fining twisted steel(5)It is through preceding pushing tow
Device(2), rear thrustor(3), and preceding thrustor(2), rear thrustor(3)Pass through fining twisted steel(5)On
Fining twisted steel nut is positioned;Preceding thrustor(2), rear thrustor(3)Between be provided with jack(7), in preceding pushing tow dress
Put(2)And main push-towing rope(8)Between wirerope-winding;
The pushing tow work of the main push-towing rope adjusting apparatus is by wirerope-winding in preceding thrustor(2)And main push-towing rope(8)On, hollow top
Push away jack(7)Realize pushing tow;During pushing tow, first by fining twisted steel nut by rear thrustor(3)Positioning, manually
Operate jack(7), promote main push-towing rope(8)The single pushing tow haul distance of mobile respective support numbering, then passes through finish rolling screw thread
Steel nut is by preceding thrustor(2)Positioning, by rear thrustor(3)Equal haul distance is promoted, this flow is circulated, until that will lead
Cable is pushed into target location.
2. main rope of suspension bridge thrustor according to claim 1, it is characterised in that:Thrustor is installed as follows:
Step 1:By girder(1)Sling, position;
Step 2:Successively by rear thrustor(3), preceding thrustor(2)Girder is installed to from end carriage side(1)On;
Step 3:By screw thread bridle iron(4), screw-thread steel support base(6)It is installed to girder(1)Relevant position;
Step 4:By fining twisted steel(5)Through preceding thrustor(2), rear thrustor(3);
Step 5:Forward and backward thrustor is positioned by fining twisted steel nut, it is ensured that equipment safety, and jack is installed simultaneously
(7);
Step 6:End carriage side fining twisted steel nuts and washers is screwed on, girder, urging portion are installed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710504417.5A CN107059650B (en) | 2017-06-28 | 2017-06-28 | Suspension bridge main push device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710504417.5A CN107059650B (en) | 2017-06-28 | 2017-06-28 | Suspension bridge main push device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107059650A true CN107059650A (en) | 2017-08-18 |
CN107059650B CN107059650B (en) | 2019-06-28 |
Family
ID=59613506
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710504417.5A Active CN107059650B (en) | 2017-06-28 | 2017-06-28 | Suspension bridge main push device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107059650B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110468724A (en) * | 2019-08-30 | 2019-11-19 | 西安市政设计研究院有限公司 | A kind of cable of space cable suspension bridge main cable construction auxiliary device and main cable construction method |
CN110565535A (en) * | 2019-09-29 | 2019-12-13 | 中铁大桥局集团有限公司 | Suspension bridge space main cable linear adjusting device and adjusting method |
CN113356054A (en) * | 2021-06-26 | 2021-09-07 | 山东省公路桥梁建设有限公司 | Cable tower and construction method thereof |
CN113356072A (en) * | 2021-06-26 | 2021-09-07 | 山东省公路桥梁建设有限公司 | Suspension bridge main push device |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2932139B2 (en) * | 1993-09-06 | 1999-08-09 | 東京製綱株式会社 | Railing structure of suspension bridge |
CN101418542A (en) * | 2008-11-21 | 2009-04-29 | 上海市政工程设计研究总院 | Cable system construction method of spatial self-anchored rope-suspension bridge |
CN102251465A (en) * | 2011-05-03 | 2011-11-23 | 张志新 | Suspension bridge with bearing cable having X-shaped curve |
CN104060540A (en) * | 2014-06-03 | 2014-09-24 | 长安大学 | Temporary cross bracing of space cable suspension bridge and lifting-constructing method of temporary cross bracing |
CN106284093A (en) * | 2016-08-31 | 2017-01-04 | 中铁局集团有限公司 | A kind of large span cable crane continuous cross sliding type construction method |
CN206189285U (en) * | 2016-08-31 | 2017-05-24 | 中铁十八局集团第五工程有限公司 | Running gear who hangs basket is pour to bridge cantilever |
-
2017
- 2017-06-28 CN CN201710504417.5A patent/CN107059650B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2932139B2 (en) * | 1993-09-06 | 1999-08-09 | 東京製綱株式会社 | Railing structure of suspension bridge |
CN101418542A (en) * | 2008-11-21 | 2009-04-29 | 上海市政工程设计研究总院 | Cable system construction method of spatial self-anchored rope-suspension bridge |
CN102251465A (en) * | 2011-05-03 | 2011-11-23 | 张志新 | Suspension bridge with bearing cable having X-shaped curve |
CN104060540A (en) * | 2014-06-03 | 2014-09-24 | 长安大学 | Temporary cross bracing of space cable suspension bridge and lifting-constructing method of temporary cross bracing |
CN106284093A (en) * | 2016-08-31 | 2017-01-04 | 中铁局集团有限公司 | A kind of large span cable crane continuous cross sliding type construction method |
CN206189285U (en) * | 2016-08-31 | 2017-05-24 | 中铁十八局集团第五工程有限公司 | Running gear who hangs basket is pour to bridge cantilever |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110468724A (en) * | 2019-08-30 | 2019-11-19 | 西安市政设计研究院有限公司 | A kind of cable of space cable suspension bridge main cable construction auxiliary device and main cable construction method |
CN110565535A (en) * | 2019-09-29 | 2019-12-13 | 中铁大桥局集团有限公司 | Suspension bridge space main cable linear adjusting device and adjusting method |
CN110565535B (en) * | 2019-09-29 | 2021-01-26 | 中铁大桥局集团有限公司 | Suspension bridge space main cable linear adjusting device and adjusting method |
CN113356054A (en) * | 2021-06-26 | 2021-09-07 | 山东省公路桥梁建设有限公司 | Cable tower and construction method thereof |
CN113356072A (en) * | 2021-06-26 | 2021-09-07 | 山东省公路桥梁建设有限公司 | Suspension bridge main push device |
CN113356072B (en) * | 2021-06-26 | 2023-02-10 | 山东省公路桥梁建设集团有限公司 | Suspension bridge main push device |
CN113356054B (en) * | 2021-06-26 | 2023-02-14 | 山东省公路桥梁建设集团有限公司 | Cable tower and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN107059650B (en) | 2019-06-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107059650A (en) | Suspension bridge main push device | |
CN202012047U (en) | Steel strand inclined pulling and buckling system of tower | |
CN106522362A (en) | Construction device and construction method of steel structure beam of corridor system | |
CN107700367A (en) | A kind of integrated bridge machine | |
CN106368493A (en) | Two-arm hydraulic drive-in type hard capping lattice type crossing frame | |
CN105155828A (en) | Lifting platform and four-upright guide rail bracket thereof | |
CN203333185U (en) | Trussed gantry crane | |
CN104164837A (en) | Automatic-locating continuous pushing device for large box beams | |
CN202848946U (en) | Rope guide wheel of construction winding engine | |
CN201118145Y (en) | Powerline aerial spanning device | |
CN104452594A (en) | Multi-support cable guide method cable replacement device | |
CN211142832U (en) | Suspension bridge catwalk system | |
CN209308433U (en) | A kind of multi-functional trolley of Cast-in-situ Beam steel reinforcement cage binding installation | |
CN105484155B (en) | Crossing floor system for on-line high-speed railway crossing equipment | |
CN210714046U (en) | Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure | |
CN207646617U (en) | A kind of integration bridge machine | |
CN203612860U (en) | Steel wire rope winding device of large portal crane | |
CN205442204U (en) | Steel strand wires pay -off | |
CN205206273U (en) | Lift platform and four vertical guideway framves thereof | |
CN204847572U (en) | Support frame that cable laying used | |
CN212000614U (en) | Large cable clamp transport trolley walking on main cable of suspension bridge | |
CN203832507U (en) | Flexible vehicle blocking bar lifting device | |
CN203096742U (en) | Difunctional supporting hanging plate | |
CN202787930U (en) | Hanging basket for high-place operations | |
CN103803436A (en) | Automatic drilling line guide device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |