CN106996197A - The correcting device and its application method misplaced for steel construction vertical member counterpart - Google Patents

The correcting device and its application method misplaced for steel construction vertical member counterpart Download PDF

Info

Publication number
CN106996197A
CN106996197A CN201610046984.6A CN201610046984A CN106996197A CN 106996197 A CN106996197 A CN 106996197A CN 201610046984 A CN201610046984 A CN 201610046984A CN 106996197 A CN106996197 A CN 106996197A
Authority
CN
China
Prior art keywords
tripod
vertical member
bottom plate
plate
counterpart
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610046984.6A
Other languages
Chinese (zh)
Inventor
王军
刘明路
王馥琴
张建生
朱术文
常华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mcc No13 Construction Co Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
Shanghai Mcc No13 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mcc No13 Construction Co Ltd filed Critical Shanghai Mcc No13 Construction Co Ltd
Priority to CN201610046984.6A priority Critical patent/CN106996197A/en
Publication of CN106996197A publication Critical patent/CN106996197A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to Installation Technique of Steel Structure field, specifically a kind of correcting device misplaced for steel construction vertical member counterpart;It is characterized in that:It includes bottom plate, tripod, limiting plate, limiting plate ribbed stiffener, jack, wing plate;Tripod is welded and fixed with hypomere vertical member;Bottom plate is fixed at the top of tripod;Limiting plate is welded and fixed with bottom plate and sets limiting plate ribbed stiffener to strengthen;Jack is held between limiting plate and epimere vertical member, and bottom plate both sides add wing plate.This steel construction vertical member counterpart dislocation correcting device adjusts upper and lower section of vertical member counterpart position by adjusting the top lifting height of jack, reduce the vertical error of steel structure hoisting, and present apparatus convenient disassembly, other devices are reused in addition to tripod simultaneously, and steel construction vertical member counterpart position can be finely adjusted using the device.

Description

The correcting device and its application method misplaced for steel construction vertical member counterpart
Technical field
The present invention relates to Installation Technique of Steel Structure field, specifically a kind of correcting device misplaced for steel construction vertical member counterpart and its application method.
Background technology
As the variation of high-rise building moulding is with complicating, application of the steel construction in high-rise building field is more and more extensive.Super high steel structure component physical dimension is big, structural segmented to increase due to Lifting Capacity limitation, adds the size Control difficulty of structure high-altitude group pair.The counterpart dislocation of the vertical members such as steel pipe column, stiffened column, box steel plate shear force wall, special-shaped steel structure post easily occurs, so as to cause malformation and the inclination and offset of super high steel structure.
The content of the invention
It is an object of the present invention to provide a kind of easy device for being used to reduce the dislocation of steel construction vertical member counterpart in work progress and be easy to operation, so as to avoid counterpart dislocation excessive, it is ensured that the installation accuracy of steel construction vertical member.
In order to achieve the above object, the present invention is realized in:
A kind of correcting device misplaced for steel construction vertical member counterpart, it includes bottom plate, tripod, limiting plate, limiting plate ribbed stiffener, jack, wing plate;Tripod is welded and fixed with hypomere vertical member;Bottom plate is fixed at the top of tripod;Limiting plate is welded and fixed with bottom plate and sets limiting plate ribbed stiffener to strengthen;Jack is held between limiting plate and epimere vertical member, and bottom plate both sides add wing plate.
Described is used for the correcting device that steel construction vertical member counterpart misplaces, and tripod is fixed with bottom plate using three groups of bolt connection pairs.
The application method of the correcting device, including
Step 1, tripod and hypomere vertical member be welded and fixed, tripod absolute altitude is high less than hypomere vertical member top mark;
Step 2, according to jack specification positioning limit plate, wing plate and it is fixedly welded on bottom plate, and sets limiting plate ribbed stiffener;
Step 3, three groups of bolt connection tripods and bottom plate formation stable triangular system, it is ensured that connection is firm, and floor level is high concordant with hypomere component top mark;
Step 4, jack is shelved on bottom plate, regulation jack top lifting height is to adjust upper and lower section of component counterpart position;
After step 5, the adjustment of steel structure member counterpart are finished, erecting and welding is completed;
Step 6, other devices except tripod are unloaded, the counterpart for other vertical members, which misplaces, corrects, and cuts tripod.
This steel construction vertical member counterpart dislocation correcting device adjusts upper and lower section of vertical member counterpart position by adjusting the top lifting height of jack, reduce the vertical error of steel structure hoisting, and present apparatus convenient disassembly, other devices are reused in addition to tripod simultaneously, and steel construction vertical member counterpart position can be finely adjusted using the device.
Brief description of the drawings
Fig. 1 is structural representation of the invention.
Fig. 2 is base arrangement schematic diagram of the invention.
Fig. 3 is tripod structure schematic diagram of the invention.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
As shown in Figure 1, Figure 2 and Figure 3, a kind of correcting device misplaced for steel construction vertical member counterpart, it includes bottom plate 1, tripod 2, limiting plate 3, limiting plate ribbed stiffener 4, jack 5, wing plate 6;Tripod 2 is welded and fixed with hypomere steel column component 7;Bottom plate 1 is arranged on the top of tripod 2, is connected by screw bolts;Limiting plate 3 is welded and fixed with bottom plate 1 and strengthened using limiting plate ribbed stiffener 4;Jack 5 is held between limiting plate 3 and epimere steel column 8, and bottom plate 1 adds wing plate 6 to prevent the laterally landing of jack 5.
Above-mentioned steel construction counterpart dislocation correcting device,
Bottom plate 1 is that the thick steel plates of 20mm, tripod 2 are that the thick steel plates of 15mm, limiting plate 3 are that the thick steel plates of 10mm, limiting plate ribbed stiffener 4 are that the thick steel plates of 10mm, wing plate 6 are the thick steel plates of 5mm.
The construction method of above-mentioned steel construction counterpart dislocation correcting device:
Step 1, tripod 2 is welded and fixed with hypomere steel column 7, the absolute altitude of tripod 2 is high less than the top mark of hypomere steel column 7, and weld seam form uses angle welding, and Size of welds is 12mm;
Step 2, by positioning limit plate 3, wing plate 6 and it is fixedly welded on bottom plate 1, and sets limiting plate ribbed stiffener 4, weld seam form uses angle welding, and Size of welds is 8mm;
Step 3, three groups of connection tripods 2 of bolt 9 and the formation stable triangular system of bottom plate 1, it is ensured that connection is firm, and floor level is high concordant with the top mark of hypomere steel column 7;
Step 4, jack 5 is shelved on bottom plate 1, the regulation top lifting height of jack 5 is to adjust steel column 7, the counterpart position of steel column 8;
After step 5, the adjustment of steel structure member counterpart are finished, erecting and welding is completed;
Step 6, other devices except tripod 2 are unloaded, the counterpart for other vertical members, which misplaces, corrects, and cuts tripod 2.
In above-mentioned construction operation, step 2 can be completed in steel construction processing factory, be transported after the completion of batch production to building site, be connected before steel column counterpart with tripod 2.

Claims (3)

1. a kind of correcting device misplaced for steel construction vertical member counterpart, it is characterized in that:It includes bottom plate, tripod, limiting plate, limiting plate ribbed stiffener, jack, wing plate;Tripod is welded and fixed with hypomere vertical member;Bottom plate is fixed at the top of tripod;Limiting plate is welded and fixed with bottom plate and sets limiting plate ribbed stiffener to strengthen;Jack is held between limiting plate and epimere vertical member, and bottom plate both sides add wing plate.
2. the correcting device according to claim 1 misplaced for steel construction vertical member counterpart, it is characterized in that:Tripod is fixed with bottom plate using three groups of bolt connection pairs.
3. the application method of correcting device described in claim 1, it is characterized in that:Including
Step 1, tripod and hypomere vertical member be welded and fixed, tripod absolute altitude is high less than hypomere vertical member top mark;
Step 2, according to jack specification positioning limit plate, wing plate and it is fixedly welded on bottom plate, and sets limiting plate ribbed stiffener;
Step 3, three groups of bolt connection tripods and bottom plate formation stable triangular system, it is ensured that connection is firm, and floor level is high concordant with hypomere component top mark;
Step 4, jack is shelved on bottom plate, regulation jack top lifting height is to adjust upper and lower section of component counterpart position;
After step 5, the adjustment of steel structure member counterpart are finished, erecting and welding is completed;
Step 6, other devices except tripod are unloaded, the counterpart for other vertical members, which misplaces, corrects, and cuts tripod.
CN201610046984.6A 2016-01-25 2016-01-25 The correcting device and its application method misplaced for steel construction vertical member counterpart Pending CN106996197A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610046984.6A CN106996197A (en) 2016-01-25 2016-01-25 The correcting device and its application method misplaced for steel construction vertical member counterpart

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610046984.6A CN106996197A (en) 2016-01-25 2016-01-25 The correcting device and its application method misplaced for steel construction vertical member counterpart

Publications (1)

Publication Number Publication Date
CN106996197A true CN106996197A (en) 2017-08-01

Family

ID=59428253

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610046984.6A Pending CN106996197A (en) 2016-01-25 2016-01-25 The correcting device and its application method misplaced for steel construction vertical member counterpart

Country Status (1)

Country Link
CN (1) CN106996197A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109972515A (en) * 2019-04-20 2019-07-05 中铁六局集团石家庄铁路建设有限公司 A kind of cable-stayed bridge steel plate concrete mating type Sarasota micromatic setting and its alignment methods
CN110172914A (en) * 2019-05-20 2019-08-27 中交路桥华东工程有限公司 A kind of armored concrete high tower prevents the device and construction method of segment faulting of slab ends generation
CN112796527A (en) * 2021-01-04 2021-05-14 上海振华重工(集团)股份有限公司 Assembly deviation adjusting method for machine room of shore crane
CN113982283A (en) * 2021-10-26 2022-01-28 中铁七局集团有限公司 Steel structure leveling process

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4588207B2 (en) * 2000-12-26 2010-11-24 テクノス株式会社 Steel column misalignment correction jig
CN103924787A (en) * 2014-05-08 2014-07-16 江苏中南建筑产业集团有限责任公司 Steel column butt joint plane position correction device
CN203808535U (en) * 2014-01-15 2014-09-03 天津二十冶建设有限公司 Device for adjusting column axis in cup-rim-shaped building

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4588207B2 (en) * 2000-12-26 2010-11-24 テクノス株式会社 Steel column misalignment correction jig
CN203808535U (en) * 2014-01-15 2014-09-03 天津二十冶建设有限公司 Device for adjusting column axis in cup-rim-shaped building
CN103924787A (en) * 2014-05-08 2014-07-16 江苏中南建筑产业集团有限责任公司 Steel column butt joint plane position correction device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109972515A (en) * 2019-04-20 2019-07-05 中铁六局集团石家庄铁路建设有限公司 A kind of cable-stayed bridge steel plate concrete mating type Sarasota micromatic setting and its alignment methods
CN110172914A (en) * 2019-05-20 2019-08-27 中交路桥华东工程有限公司 A kind of armored concrete high tower prevents the device and construction method of segment faulting of slab ends generation
CN112796527A (en) * 2021-01-04 2021-05-14 上海振华重工(集团)股份有限公司 Assembly deviation adjusting method for machine room of shore crane
CN113982283A (en) * 2021-10-26 2022-01-28 中铁七局集团有限公司 Steel structure leveling process

Similar Documents

Publication Publication Date Title
CN106996197A (en) The correcting device and its application method misplaced for steel construction vertical member counterpart
CN105926958B (en) A kind of installation method for the sill anchor combined support frame for being used for high-rise building steel construction shear wall and outline border suspension column
CN206722404U (en) Horizontal reinforcing apparatus of narrow end wall unilateral formwork
CN105643174A (en) Adjustable pairing jig frame for self-made H-shaped steel
CN204278223U (en) Prefabricated case beam steel bar binding clamping fixture
CN110093977A (en) Prefabricated component mounting structure and its installation method
CN107869195A (en) A kind of shaped steel steel column and column cap sizing punching block construction method
CN104032969A (en) Precise positioning and process regulation and control device for vibration isolation support embedded plate
CN207227968U (en) T beam beams bottom steel plate supertronic device
CN102691412B (en) Prefabricated frame structure connection supporting template with adjustable vertical height
CN103669432B (en) A deflection correcting and jacking device for transmission towers in coal mine mining areas
CN103031892B (en) Steel truss brace and manufacturing method for steel truss platform
CN214462738U (en) Butt joint section steel column stagger correction device
CN109972847A (en) A positioning and vertical adjustment device for a structural column
CN205000354U (en) Rim of a cup basis steel column installation elevation control structure
CN104652277A (en) Support and regulation device for pillar-penetrating bent cap construction
CN202559747U (en) Foot portion supporting and size control device of aluminum alloy shear wall template
CN206562771U (en) The support meanss of concrete frame template
CN203361735U (en) Sliding mode system with function of efficient adjustment
CN207260607U (en) A kind of accumulation slippage construction equal proportion plays fall girder apparatus
CN103556577B (en) Elevation adjusting device for steel truss and method for adjusting elevation of steel truss
CN203361633U (en) Template regulating system of sliding form system
CN109436990B (en) Elevator well adjusting device
CN209131949U (en) A scaffolding vertical stability bearing capacity test device
CN203475870U (en) Adjustable support device for top of bearing row rack

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170801