CN106988330A - 软土地基分层降水施工结构以及施工方法 - Google Patents
软土地基分层降水施工结构以及施工方法 Download PDFInfo
- Publication number
- CN106988330A CN106988330A CN201710314240.2A CN201710314240A CN106988330A CN 106988330 A CN106988330 A CN 106988330A CN 201710314240 A CN201710314240 A CN 201710314240A CN 106988330 A CN106988330 A CN 106988330A
- Authority
- CN
- China
- Prior art keywords
- well casing
- electric osmose
- diving
- depth
- soft soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Water Treatment By Electricity Or Magnetism (AREA)
Abstract
一种软土地基分层降水施工结构,包括:电渗井管,潜水井管,隔水层,阳级棒;潜水井管布置为第一深度,电渗井管布置为大于第一深度的第二深度;电渗井管设置为第一管径,潜水井管设置为大于第一管径的第二管径;电渗井管与潜水井管同心设置;隔水层设置于电渗井管和潜水井管之间的环状通道内;电渗井管内部形成电渗降水通道,潜水井管与电渗井管之间形成潜水井管降水通道;阳级棒对应于电渗井管设置,阳级棒和电渗井管分别与供电电路的阳极和阴级相连接,形成电渗降水回路。
Description
技术领域
本发明设计一种建筑工程地下基础的施工结构以及施工方法。
背景技术
随着我国经济建设的高速发展,为了更充分地利用土地,一方面,高层、超高层建筑不断增加,另一方面,人们也越来越多地利用地下空间,建设大规模的市政工程如地下停车场、大型地铁车站、地下变电站、地下商场、地下民防工事等。无论是高层建筑深基础的施工,还是地下空间的利用,都需要进行大规模的地下开挖,促使基坑工程快速发展。
基坑工程施工过程中,基坑降水技术对工程质量的保证起着非常重要的作用,基坑降水往往是决定深基坑工程成败的一个重要因素。基坑降水法就是把地下水位通过井点的方法进行降低。其中,对基坑降水在施工过程中处理地下水是非常重要的,如果没有做好基坑降水,就可能出现因流砂现象而出现的塌方和地址破坏而影响施工的进行,同时内部基坑土体发生较大的位移,会影响邻近建筑物的安全。
对基坑降水进行具体设计时,通常根据地质勘查结果对含水层进行划分划成两个部分:第一层含水层较浅,为潜水含水层,地层主要由粉砂和粉土组成,在基坑降水时需要进行疏干:第二层为较深处的承压含水层,主要来自大气降水和生活用水的渗漏补给,基坑开挖至一定深度时形成基坑突涌需要采用对于承压含水层进行减压降水。
现有技术中,对于基坑的降水通常采用在潜水含水层和承压含水层分别设置疏干井和降压井的方式,在基坑开挖前使用疏干井对潜水含水层进行疏干,在基坑开挖到承压含水层后,通过降压井对承压含水层进行减压直到基坑强度符合条件。但是该方法使使得基坑工程中管井数量多,施工成本大,施工操作过程拉长,给施工带来不便。
为了解决上述技术问题,在200710041603的发明专利中提出了一种改进的基坑降水施工结构,其将疏干井和降压井合而为一,在井管中设置可控止水装置,在进行潜水含水层疏干时关闭可控止水装置,使用潜水泵进行排水;在开挖到承压含水层时,开启可控止水装置,取出潜水泵,将深井泵置于底部,进行减压降水。通过该方法,能够减少布井数量,降低施工费用,节约施工成本。但是,该发明中需要在管井中设置可控止水装置避免潜水含水层抽水抽取到承压含水层的水,其设置复杂,在疏干和降压的过程中需要进行可控止水装置状态的切换,开启和关闭并不方便,并且需要进行潜水泵和深井泵的替换。
在先发明提出了一种改进的软土地基分层降水施工结构以及施工方法,能够实现将疏干井和降压井合并,同时不需要设置可控止水装置,也不需要进行潜水泵和深井泵的替换。但是,对于承压含水层使用深水泵进行降水,只适用于中、强透水层,对于渗透系数较小的软土地基,很难处理。
发明内容
作为本发明的一个方面,提供了一种软土地基分层降水施工结构,包括:电渗井管,潜水井管,隔水层,阳级棒;所述潜水井管布置为第一深度,所述电渗井管布置为大于第一深度的第二深度;所述电渗井管设置为第一管径,所述潜水井管设置为大于第一管径的第二管径;所述电渗井管设置于所述潜水井管内,与所述潜水井管同心设置;所述隔水层设置于所述电渗井管和潜水井管之间的环状通道内;所述电渗井管内部形成电渗降水通道,所述潜水井管与所述电渗井管之间形成潜水井管降水通道;所述阳级棒对应于所述电渗井管设置,阳级棒和电渗井管分别与供电电路的阳极和阴级相连接,形成电渗降水回路。
优选的,所述第一深度对应于地基潜水含水层深度;所述第二深度对应于地基承压含水层深度。
优选的,所述阳极棒的深度大于所述电渗井管深度。
优选的,所述阳极棒的深度比所述电渗井管深度大50~100cm。
优选的,所述阳极棒与所述电渗井管间隔设置。
优选的,所述隔水层设置于潜水含水层与所述地基承压含水层之间。
优选的,所述电渗井管为铝管。
优选的,所述电渗井管低于所述隔水层的管壁设置透水通孔,高于所述隔水层的管壁设置为密封状态。
优选的,所述潜水井管管径为所述电渗井管管径的1.4~1.7倍。
优选的,所述电渗井管高于所述隔水层的管壁外表面喷涂一层绝缘漆,使其与潜水井管电绝缘。
优选的,所述软土地基分层降水施工结构用于基坑降水施工。
优选的,所述阳极棒套从顶部开始设一层硅橡胶层,所述硅橡胶层的深度位于潜水含水层与地基承压含水层之间的中间层。
作为发明的另外一个方面,提供上述软土地基分层降水施工结构的降水施工方法,包括如下步骤:(1)设置完毕软土地基分层降水施工结构;(2)基坑开挖前,通过潜水井管对于潜水含水层进行疏干性降水;(3)进行基坑开挖,基坑开挖到需要降压的深度后,根据开挖进度通过电渗井管间歇对于承压含水层进行降水,控制地下水位;(4)基坑开挖完毕并且结构强度达到要求,结束降水施工。
附图说明
图1是本发明实施例的软土地基分层降水施工结构的示意图。
图2是本发明优选实施例的软土地基分层降水施工结构的示意图。
图3是本发明另一个优选实施例的软土地基分层降水施工结构的示意图。
具体实施方式
为了更清楚地说明本发明的技术方案,下面将使用实施例对本发明进行简单地介绍,显而易见地,下面描述中的仅仅是本发明的一个实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些实施例获取其他的技术方案,也属于本发明的公开范围。
本发明实施例的软土地基分层降水施工结构,参见图1,包括:潜水井管10,电渗井管20,隔水层30,阳级棒40。潜水井管10,用于基坑施工前潜水含水层内含水的疏干,其为圆形管道,管壁设置透水通孔,深度为在潜水含水层和承压含水层的中间层位置。潜水井管10外填充滤料,滤料可以是填砂。
电渗井管20用于承压含水层进行降压,其底部设置于承压含水层内。电渗井管20为圆形管路,设置于潜水井管10内,与潜水井管10同心设置。可以使用铝管作为电渗井管20。潜水井管10管径为电渗井管20管径的1.4~1.7倍,从而潜水井管10与电渗井管20之间形成用于潜水含水层疏干的降水通道11。
电渗井管20的顶部与潜水井管10一致,电渗井管20的深度大于潜水井管10的深度,设置于承压含水层内。电渗井管20的底部设置隔水层23,隔水层23可以使用例如粘土防渗层。
在潜水井管10的底部以及电渗井管20外环外设置隔水层30,隔水层30的深度设置于潜水含水层与承压含水层之间。隔水层30可以设置为例如粘土防渗层。
电渗井管20包括第一部分21以及第二部分22,第一部分21为低于隔水层30的部分,其管壁设置透水通孔,用于引入承压含水层的水;第二部分22为高于隔水层30的部分,其管壁设置为密封状态。电渗井管20内形成承压含水层的降水通道24。优选的,可以在电渗井管20的第一部分外表面喷涂一层绝缘漆,使其与潜水井管10电绝缘,从而在电渗降水时减少电流泄漏。
阳级棒40对应于电渗井管20设置,例如阳极棒40可以与电渗井管20间隔设置,阳极棒40可以使用钢管或者钢筋作为材料。阳级棒40和电渗井管50分别与供电电路的阳极和阴级相连接,形成电渗降水回路。优选的,使用钢管作为阳极棒40的材料,在钢管上进行横向拉缝,使钢管管壁存在细缝,从而使阳极棒40反应生成的气体排出,从而使阳极棒40与土体紧密接触。进一步优选的,可以在阳极棒套40从顶部开始设一层硅橡胶层,该硅橡胶层的深度位于潜水含水层与地基承压含水层之间的中间层,从而使阳极棒40与潜水层隔水。
本发明实施例的软土地基分层降水施工结构,可以在降水通道中设置滤料层,以在潜水泵40或者深井泵50之前对于降水进行过滤。
软土地基分层降水施工结构的降水施工方法,包括如下步骤:(1)设置软土地基分层降水施工结构;(2)基坑开挖前,开启潜水泵40通过潜水井管10对于潜水含水层进行疏干性降水;(3)进行基坑开挖,基坑开挖到需要降压的深度后,开启深井泵50根据开挖进度通过电渗井管20间歇对于承压含水层进行降水,控制地下水位;(4)基坑开挖完毕并且结构强度达到要求,结束降水施工。
通过本发明上述实施例的设置,对于承压含水层使用电渗降水,从而对于渗透系数较小的软土地基,也能够进行处理。
发明的一个优选的实施例,可以参见图2,在电渗井管20底部设置环绕其外壁的第一底盘25,在第一底盘25上特定位置设置环绕其外壁的第二底盘26;第一底盘25和第二底盘26可以通过螺纹连接与第二管井20固定。第一底盘25和第二底盘26的外径与潜水井管10的管径相同。通过这样的设置,能够在潜水含水层进行降水时,固定电渗井管20,避免其出现位置偏移影响基坑降水。
本发明的一个进一步优选的实施例,参见图3,隔水层30包括左侧部31以及右侧部32,潜水泵40设置于左侧部31上,设置隔水层30左侧部31和右侧部32的高度,使右侧部32的高度高于左侧部31的高度,从而使降水通道24的水能够充分到达潜水泵40的位置,进一步促进潜水泵40的排水。
在本发明提及的所有文献都在本申请中引用参考,就如同每一篇文献被单独引用作为参考那样。此外应理解,在阅读了本发明的上述公开内容之后,本发明的保护范围并不仅局限于上述实施例,本领域技术人员可以对本发明作各种改动或修改,在不脱离本发明原理前提下,这些等价形式同样落于本申请所附权利要求书所限定的范围。
Claims (8)
1.一种软土地基分层降水施工结构,包括:电渗井管,潜水井管,隔水层,阳级棒;其特征在于:所述潜水井管布置为第一深度,所述电渗井管布置为大于第一深度的第二深度;所述电渗井管设置为第一管径,所述潜水井管设置为大于第一管径的第二管径;所述电渗井管设置于所述潜水井管内,与所述潜水井管同心设置;所述隔水层设置于所述电渗井管和潜水井管之间的环状通道内;所述电渗井管内部形成电渗降水通道,所述潜水井管与所述电渗井管之间形成潜水井管降水通道;所述阳级棒对应于所述电渗井管设置,阳级棒和电渗井管分别与供电电路的阳极和阴级相连接,形成电渗降水回路。
2.根据权利要求1所述的软土地基分层降水施工结构,其特征在于:所述阳极棒的深度大于所述电渗井管深度。
3.根据权利要求2所述的软土地基分层降水施工结构,其特征在于:所述阳极棒的深度比所述电渗井管深度大50~100cm。
4.根据权利要求3所述的软土地基分层降水施工结构,其特征在于:所述阳极棒与所述电渗井管间隔设置。
5.根据权利要求4所述的软土地基分层降水施工结构,其特征在于:所述电渗井管为铝管。
6.根据权利要求6所述的软土地基分层降水施工结构,其特征在于:所述潜水井管管径为所述电渗井管管径的1.4~1.7倍。
7.根据权利要求1所述的软土地基分层降水施工结构,其特征在于:其用于基坑降水施工。
8.软土地基分层降水施工结构的降水施工方法,包括如下步骤:(1)设置完毕软土地基分层降水施工结构;(2)基坑开挖前,通过潜水井管对于潜水含水层进行疏干性降水;(3)进行基坑开挖,基坑开挖到需要降压的深度后,根据开挖进度通过电渗井管间歇对于承压含水层进行降水,控制地下水位;(4)基坑开挖完毕并且结构强度达到要求,结束降水施工。
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811152743.5A CN108978693B (zh) | 2017-05-06 | 2017-05-06 | 基坑工程软土地基降水施工结构 |
CN201710314240.2A CN106988330B (zh) | 2017-05-06 | 2017-05-06 | 基坑工程软土地基分层降水施工结构以及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710314240.2A CN106988330B (zh) | 2017-05-06 | 2017-05-06 | 基坑工程软土地基分层降水施工结构以及施工方法 |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811152743.5A Division CN108978693B (zh) | 2017-05-06 | 2017-05-06 | 基坑工程软土地基降水施工结构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106988330A true CN106988330A (zh) | 2017-07-28 |
CN106988330B CN106988330B (zh) | 2019-02-26 |
Family
ID=59417465
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710314240.2A Expired - Fee Related CN106988330B (zh) | 2017-05-06 | 2017-05-06 | 基坑工程软土地基分层降水施工结构以及施工方法 |
CN201811152743.5A Active CN108978693B (zh) | 2017-05-06 | 2017-05-06 | 基坑工程软土地基降水施工结构 |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811152743.5A Active CN108978693B (zh) | 2017-05-06 | 2017-05-06 | 基坑工程软土地基降水施工结构 |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN106988330B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109580368A (zh) * | 2018-11-19 | 2019-04-05 | 同济大学 | 一种多层承压水分层地层中深基坑开挖变形性状离心模型试验装置 |
CN113338262A (zh) * | 2021-05-20 | 2021-09-03 | 江南大学 | 三维电渗固结软土集排水装置及其施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1932165A (zh) * | 2006-09-01 | 2007-03-21 | 叶凝雯 | 大面积软地基处理分层分遍电渗降水联合真空降水方法 |
CN101070704A (zh) * | 2007-06-04 | 2007-11-14 | 上海地矿工程勘察有限公司 | 可控式一井分层降水施工方法 |
CN201176596Y (zh) * | 2008-06-05 | 2009-01-07 | 上海广联建设发展有限公司 | 能同时用于疏干和减压降水的管井 |
CN206090597U (zh) * | 2016-09-28 | 2017-04-12 | 上海广联环境岩土工程股份有限公司 | 单孔多管管井 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61242216A (ja) * | 1985-04-19 | 1986-10-28 | Teruhiko Takano | 土木工事における地下水位の低下方法 |
CN100375819C (zh) * | 2005-12-30 | 2008-03-19 | 叶吉 | 双控动力固结处理软地基的方法 |
CN102162239B (zh) * | 2011-04-02 | 2013-05-15 | 河海大学 | 联合化学溶液注入电渗法处理软土地基及其施工方法 |
CN104563206A (zh) * | 2014-12-26 | 2015-04-29 | 北京中科华誉能源技术发展有限责任公司 | 一种负压式抽、灌两用一体井 |
-
2017
- 2017-05-06 CN CN201710314240.2A patent/CN106988330B/zh not_active Expired - Fee Related
- 2017-05-06 CN CN201811152743.5A patent/CN108978693B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1932165A (zh) * | 2006-09-01 | 2007-03-21 | 叶凝雯 | 大面积软地基处理分层分遍电渗降水联合真空降水方法 |
CN101070704A (zh) * | 2007-06-04 | 2007-11-14 | 上海地矿工程勘察有限公司 | 可控式一井分层降水施工方法 |
CN201176596Y (zh) * | 2008-06-05 | 2009-01-07 | 上海广联建设发展有限公司 | 能同时用于疏干和减压降水的管井 |
CN206090597U (zh) * | 2016-09-28 | 2017-04-12 | 上海广联环境岩土工程股份有限公司 | 单孔多管管井 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109580368A (zh) * | 2018-11-19 | 2019-04-05 | 同济大学 | 一种多层承压水分层地层中深基坑开挖变形性状离心模型试验装置 |
CN113338262A (zh) * | 2021-05-20 | 2021-09-03 | 江南大学 | 三维电渗固结软土集排水装置及其施工方法 |
CN113338262B (zh) * | 2021-05-20 | 2022-06-28 | 江南大学 | 三维电渗固结软土集排水装置及其施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN108978693B (zh) | 2021-07-23 |
CN106988330B (zh) | 2019-02-26 |
CN108978693A (zh) | 2018-12-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102352757B (zh) | 盾构机空推过矿山法隧道时控制管片上浮的方法 | |
CN105714762B (zh) | 换填夯实改进软黏土电渗加固方法 | |
CN203174616U (zh) | 一种粘土地基降水节水系统 | |
CN103526766A (zh) | 一种深基坑减压井封堵方法 | |
CN103967028A (zh) | 一种沉管降水结构及其采用此结构处理突发性基坑水涌、喷泉的方法 | |
CN103114599A (zh) | 深基坑封闭降水装置及其施工方法 | |
CN110984200B (zh) | 二元地质结构层的基坑降排水的方法 | |
CN112281885A (zh) | 防渗膜接头自粘接装置及其自粘接式截水帷幕构筑方法 | |
CN108867673A (zh) | 一种基于抽水帷幕的基坑中地下水治理方法 | |
CN106988330B (zh) | 基坑工程软土地基分层降水施工结构以及施工方法 | |
CN103615014B (zh) | 一种软土基坑的降水装置及其使用方法 | |
CN103061351B (zh) | 防止地下室底板隆起、渗水的装置 | |
CN204940314U (zh) | 一种扩大端降压井及其深基坑结构 | |
CN107023013A (zh) | 一种充分利用水文地质特性的绿色降水方法 | |
CN103556641A (zh) | 一种既有地下室坑内地下连续墙成槽辅助方法 | |
CN206956754U (zh) | 一种用于基坑局部降水的简易装置 | |
CN104975610A (zh) | 一种扩大端降压井、深基坑结构及其施工方法 | |
CN203188226U (zh) | 防止地下室底板隆起、渗水的装置 | |
CN106894429B (zh) | 基坑工程软土地基分层降水施工结构以及施工方法 | |
CN205348204U (zh) | 一种轻型井点降水系统 | |
CN203475453U (zh) | 桥梁深埋式承台帷幕结构 | |
CN114164869A (zh) | 一种磁吸防渗膜垂向隐蔽铺设装置及截水帷幕构筑方法 | |
CN209603160U (zh) | 一种人防工程管井封堵构造 | |
CN105386471A (zh) | 一种地下连续墙h型钢接缝施工刷壁器 | |
CN206706793U (zh) | 一种用于降低承压水头压力的组合式减压井 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20190115 Address after: 315100 No. 156 Dongyu Road, Hehe Street, Yinzhou District, Ningbo City, Zhejiang Province Applicant after: Ningbo Yinzhou City Government Garden Engineering Co., Ltd. Address before: No. 79, Gao Zhuang Qiao Road, Xingtai, Hebei Province Applicant before: Han Shaopeng |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190226 Termination date: 20210506 |
|
CF01 | Termination of patent right due to non-payment of annual fee |