CN106968437A CN201710264843.6A CN201710264843A CN106968437A CN 106968437 A CN106968437 A CN 106968437A CN 201710264843 A CN201710264843 A CN 201710264843A CN 106968437 A CN106968437 A CN 106968437A
Authority
CN
China
Prior art keywords
components
mounting surface
installation method
adjusting
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710264843.6A
Other languages
Chinese (zh)
Other versions
CN106968437B (en
Inventor
卫世全
任长文
陈洪根
陈超平
梅国栋
耿洪振
龙蔚莹
张安明
刘绪飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
中国建筑第五工程局有限公司安徽分公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国建筑第五工程局有限公司安徽分公司 filed Critical 中国建筑第五工程局有限公司安徽分公司
Priority to CN201710264843.6A priority Critical patent/CN106968437B/en
Publication of CN106968437A publication Critical patent/CN106968437A/en
Application granted granted Critical
Publication of CN106968437B publication Critical patent/CN106968437B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The invention discloses a kind of installation method of PC components, two sleeve locators are at least installed in the bottom of PC components;Sleeve locator is adjusted, aperture is sent and is centered around around the spacer bar on mounting surface;PC member position adjusting brackets are adjusted to heeling condition, PC components are placed on inclined PC member positions adjusting bracket, then PC member position adjusting brackets are adjusted to plumbness, the position of PC components is checked, then PC components are drop to mounting surface using PC member positions adjusting bracket so that the bottom sleeves of PC components are socketed in spacer bar;Sleeve locator and PC member position adjusting brackets are removed, accurate adjustment then is carried out to PC member positions, PC components are promoted to the position of wall line on mounting surface.PC component adjustment positions by the spacer bar on laser alignment mounting surface, are then put into spacer bar by the present invention by the sleeve of PC member bottom sections, then are adjusted by equipment to standard wall line, and whole process needs artificial less, fast power-saving of constructing.

Description

A kind of installation method of PC components
Technical field
The present invention relates to a kind of construction techniques, more particularly to a kind of installation method of PC components.
Background technology
Precast concrete (PC components) is the prefabricated basis of realization body structure.Its feature is as follows:Structural behaviour is good Good, structural mechanics can be effectively ensured by being made using batch production, and discreteness is small.Speed of application is fast, good product quality, any surface finish Degree is high, can reach the decorative effect of clear-water concrete, structure is uniformly coordinated with building.Factorial praluction is saved, and is conducive to ring Protect, reduce the noise of site operation.Fire protecting performance is good.
During the construction building of present high-rise, after the completion of cast-in-place Rotating fields, the installation of PC components is carried out, is led to Cross and reinforcing bar posting is positioned on connection reinforcing bar, reinforcing bar posting is one block of steel plate, it is fixed to be got above according to the position of reinforcing bar Position hole, positioning hole is enclosed on reinforcing bar, then poured, it is ensured that the position of reinforcing bar is certain.PC components are risen with tower crane hook Operating surface is hung to, during apart from flooring certain distance, the mounting hole of its bottom is directed at steel by operating personnel with hand steered prefabricated panel Muscle, then by the sleeve of the bottom of prefabricated panel on reinforcing bar.
Then the internal diameter of the sleeve of existing PC member bottom sections can be more than spacer bar, therefore, when socket, can cause Whole PC components have certain error from standard wall line.
Simultaneously as the process being entirely aligned is that needs are manually-operated, it is necessary to which workman, which squats down even to fall, checks PC The sleeve of member bottom section and the alignment case of spacer bar, had so both added artificial burden, can increase the dangerous of production again Property.
Whole PC components are dropped on mounting surface from tower crane, and whole process needs several workmans with hand steered PC components, Slowly alignment is moved on mounting surface, and whole process needs the lifting operation of long period, while needing enough artificial progress Coordinative construction, wastes time and energy.
The content of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of installation method of PC components, meet whole The safety in production of individual PC components needs.
The present invention is achieved by the following technical solutions, a kind of installation method of PC components of the invention, including following Step:
(1) tower crane slings PC components, when PC components are from 1.3~1.8m of mounting surface, is at least installed in the bottom of PC components Two sleeve locators;
(2) position of PC components is adjusted so that the aperture that the sleeve locator of PC member bottom sections absorption is sent is centered around peace Around spacer bar on dress face;
(3) PC member position adjusting brackets are placed according to the position of mounting surface, PC member position adjusting brackets is adjusted to tilt State, PC components are placed on inclined PC member positions adjusting bracket, distinguish spacing to PC member uppers, left side and right side;
(4) and then by PC member position adjusting brackets it is adjusted to plumbness so that PC components are perpendicular to mounting surface;
(5) position of PC components is checked using sleeve locator, manual adjustment PC is needed if position is offset The sleeve of component is located at the surface of correspondence spacer bar, and PC components then are drop into installation using PC member positions adjusting bracket Face so that the bottom sleeves of PC components are socketed in spacer bar;
(6) sleeve locator and PC member position adjusting brackets are removed, accurate adjustment then is carried out to PC member positions, PC structures are promoted Part is to the position of wall line on mounting surface.
When the PC components drop to mounting surface, PC components are inclined to the direction away from wall line so that PC components are dropped to After mounting surface, there is gap between PC components and wall line.
When PC components drop to mounting surface, due to the gap of sleeve and spacer bar, make between PC components and wall line always It can not be aligned completely, if PC components are pressed on wall line, when accurate adjustment and bad operation, and if PC components and wall line There is certain gap, as long as being pushed to wall line from PC component another sides during accurate adjustment.
The sleeve locator includes luminous aperture and positioning top piece, and the luminous aperture includes laser light belt and positioning base Seat, the positioning pedestal is loop configuration, and the positioning top piece is set on the ring part of the positioning pedestal and raised in positioning The surface of pedestal, the laser light belt is arranged in positioning pedestal.
The positioning pedestal is the magnet of two arcs, and the end of described two magnet is hinged, described two magnet Head end be attached together for synonyms pole.
The positioning top piece includes bottom base and projection piece, and one end of the projection piece is fixed in bottom base, separately One end passes through the annular of positioning pedestal, and the length of the projection piece is more than the height of the ring part of positioning pedestal, the bottom base The external diameter of seat is more than the internal diameter of the ring part.
The PC member positions adjusting bracket is spacing including regulation pedestal, adjusting post, crane, upper limit part, side Part, bottom locating part, the first actuator and the second actuator;The bottom of the adjusting post is hinged on regulation pedestal, described The top connection upper limit part of adjusting post, the first actuator driving adjusting post is rotated around regulation pedestal, the liter The two ends of drop frame are slidably connected on adjusting post, and the bottom locating part is connected on crane, and the side locating part connects It is connected on adjusting post, the second actuator driving crane is moved up and down.
Chute is opened up on the inside of the adjusting post, the two ends of the crane, which are located in corresponding chute, to be slided up and down.
The upper limit part includes gag lever post, upper stopper and extension, and the gag lever post is arranged on the top of adjusting post Portion, the upper stopper is connected on gag lever post parallel to regulation pedestal, one end of the upper stopper, other end connection extension, The extension be arranged in parallel with gag lever post.
The accurate adjustment of the PC components realizes that the accurate adjustment frame includes right angle rack, movement by accurate adjustment frame Actuator, locating part and firm banking;The right angle rack at least has a movement being placed on the mounting surface of PC components Support body and a promotion support body for being used to promote PC components, the movable support body are connected as a single entity with the promotion support body and mutually hung down Directly, one end of the mobile actuator is connected on right angle rack, and the other end is connected on firm banking by locating part.
Having on the firm banking is used for the holding tank that movable support body is slided, and the locating part is fixed on through holding tank In movable support body.
The present invention has advantages below compared with prior art:Present invention process is simple, and mentality of designing is scientific and reasonable, by PC structures Then PC component adjustment positions are put into spacer bar by the sleeve of part bottom by the spacer bar on laser alignment mounting surface It is interior, then adjusted by equipment to standard wall line, whole process needs artificial less, fast power-saving of constructing.
Brief description of the drawings
Fig. 1 is the construction process figure of the present invention;
Fig. 2 is the structural representation of sleeve locator;
Fig. 3 is the structural representation of luminous aperture;
Fig. 4 is the structural representation of positioning top piece;
Fig. 5 is the sectional view of sleeve locator;
Fig. 6 is the structural representation of PC member position adjusting brackets;
Fig. 7 is the use flow chart of PC member position adjusting brackets;
Fig. 8 is the structural representation of accurate adjustment frame;
Fig. 9 is the explosive view of accurate adjustment frame.
Embodiment
Embodiments of the invention are elaborated below, the present embodiment is carried out lower premised on technical solution of the present invention Implement, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to following implementations Example.
As shown in figure 1, the installation method for the PC components that the present embodiment includes, comprises the following steps:
(1) tower crane slings PC components 1, when PC components 1 are from 1.3~1.8m of mounting surface, at least pacifies in the bottom of PC components 1 Fill two sleeve locators 2;Sleeve locator 2 may be mounted on the bottom two ends of PC components 1, by the principle of two points one lines, Position can be determined;
(2) position of PC components is adjusted so that the aperture that the sleeve locator 2 of PC member bottom sections absorption is sent is centered around peace Around spacer bar 3 on dress face;
(3) PC member positions adjusting bracket 4 is placed according to the position of mounting surface, PC member positions adjusting bracket 4 is adjusted to incline Ramp-like state, PC components 1 are placed on inclined PC member positions adjusting bracket 4, and the top of PC components 1, left side and right side are limited respectively Position, holding is carried out for the bottom of PC components 1;
(4) and then by PC member positions adjusting bracket 4 it is adjusted to plumbness so that PC components 1 are perpendicular to mounting surface;
(5) position of PC components 1 is checked using sleeve locator 2, manual adjustment is needed if position is offset The sleeve of PC components 1 is located at the surface of correspondence spacer bar 3, and then PC components 1 are landed using PC member positions adjusting bracket 4 To mounting surface so that the bottom sleeves of PC components 1 are socketed in spacer bar 3;
(6) sleeve locator 2 and PC member positions adjusting bracket 4 are removed, accurate adjustment then is carried out to the position of PC components 1, is promoted PC components 1 are to the position of wall line on mounting surface.
When the PC components 1 drop to mounting surface, PC components 1 are inclined to the direction away from wall line so that PC components 1 land To after mounting surface, there is gap between PC components 1 and wall line.
When PC components 1 drop to mounting surface, due to the gap of sleeve and spacer bar 3, make total between PC components 1 and wall line To be aligned completely, if PC components 1 are pressed on wall line, when accurate adjustment and bad operation, and if PC components 1 with Wall line has certain gap, as long as being pushed to wall line from the other direction of PC components 1 during accurate adjustment.
As shown in Figure 2-5, the sleeve locator 2 of the present embodiment includes luminous aperture and positioning top piece 23, the luminous light Circle includes laser light belt 21 and positioning pedestal 22, and the positioning pedestal 22 is loop configuration, and the positioning top piece 23 is set on institute The ring part and projection of positioning pedestal 22 are stated on the surface of positioning pedestal 22, the laser light belt 21 is arranged on positioning pedestal 22 On.
The positioning pedestal 22 of the present embodiment is the magnet of two arcs, and the end of described two magnet is hinged, described The head end of two magnet is attached together for synonyms pole.
In other embodiment, there is magnetic portion as long as ensureing the one side of positioning pedestal 22, can adsorb on sleeve, it is another Face connects laser light belt 21, can be radiated on mounting surface.
The laser light belt 21 is sticked in the loop configuration of positioning pedestal 22, the aperture of the formation of laser light belt 21 It is centrally located on spacer bar 3.
The positioning top piece 23 of the present embodiment includes bottom base 231 and projection piece 232, and one end of the projection piece 232 is consolidated It is scheduled in bottom base 231, the other end passes through the annular of positioning pedestal 22, the length of the projection piece 232 is more than positioning pedestal The height of 22 ring part, the external diameter of the bottom base 231 is more than the internal diameter of the ring part.
The one side of laser light belt 21 is connected in the positioning pedestal 22 has what is matched with the height of bottom base 231 Sunk structure, the bottom base 231 is located in the sunk structure.
The projection piece 232 of positioning top piece 23 is being connected rear projection outside with positioning pedestal 22, and workman is in operation, Ke Yi When invisible PC 1 bottom sleeves of component, groped to put into the projection piece 232 of whole sleeve locator 2 in sleeve with hand, So it is able to ensure that accurate positioning, it is not necessary to manually go carefully to see, allows workman there are more energy to go concern to keep the safety in production, Simplify labor intensity.
Then after pedestal 22 to be positioned is adsorbed on sleeve, positioning top piece 23 can be removed, the position of whole PC components 1 is adjusted Put so that the aperture that the sleeve locator 2 of the bottom of PC components 1 absorption is sent is centered around around the spacer bar 3 on mounting surface.
As shown in Figures 6 and 7, the PC member positions adjusting bracket 4 of the present embodiment includes regulation pedestal 41, adjusting post 42, risen Frame 43, upper limit part 44, side locating part 45, bottom locating part 46, the first actuator 47 and the second actuator 48 drop;It is described The bottom of adjusting post 42 is hinged on regulation pedestal 41, the top connection upper limit part 44 of the adjusting post 42, described First actuator 47 drives adjusting post 42 to be rotated around regulation pedestal 41, and the two ends of the crane 43 are slidably connected at regulation and stood On post 42, the bottom locating part 46 is connected on crane 43, and the side locating part 45 is connected on adjusting post 42, institute The second actuator 48 driving crane 43 is stated to move up and down.
First actuator 47 and the second actuator 48 of the present embodiment are jack.
The inner side of the present embodiment adjusting post 42 opens up chute, and the two ends of the crane 43 are located in corresponding chute Lower slider.Meet crane 43 regulation operation when the need for.
The adjusting post 42 of the present embodiment is provided with connecting rod 49, and the connecting rod 49 is hollow-core construction, the connecting rod 49 are be arranged in parallel with the crane 43, and the side locating part 45 is set in the hollow-core construction of the connecting rod 49.
The top of the adjusting post 42 of the present embodiment has the hollow part for being used for placing upper limit part 44.
The upper limit part 44 of the present embodiment includes gag lever post 441, upper stopper 442 and extension 443, the gag lever post 441 are arranged on the top of adjusting post 42, and the upper stopper 442 connects parallel to regulation pedestal 41, one end of the upper stopper 442 It is connected on gag lever post 441, other end connection extension 443, the extension 443 be arranged in parallel with gag lever post 441.Coordinate left and right The side locating part 45 of both sides so that the upper limit part 44 of formation not only has the restriction of the tip position of PC components 1, moreover it is possible to anti- The only run-off the straight of PC components 1 and skew.
The regulation pedestal 41 of the present embodiment is made I-shaped for channel-section steel.The adjusting post 42, the and of connecting rod 49 of the present embodiment Crane 43 is made up of square steel.Convenient material drawing, can be convenient movable from construction site, and fixation can be used and is welded and fixed, Construction is simple.
The PC member positions adjusting bracket 4 of the present embodiment tilts certain angle first, then puts PC components 1, first PC components 1 are held with bottom locating part 46, the both sides for limiting PC components 1 with two side locating parts 45 are not moved, and are then adjusted Upper limit part 44, whole PC components 1 are clamped on PC member positions adjusting bracket 4, then PC member positions adjusting bracket 4 is adjusted For plumbness, vertical reduction so that the sleeve of the bottom of PC components 1 can just fall on spacer bar 3, then remove PC components Position adjustments frame 4 and sleeve locator 2, PC components are fallen.
As shown in FIG. 8 and 9, the accurate adjustment of PC components 1 is realized by accurate adjustment frame 5, and the accurate adjustment frame 5 includes straight Angle support 51, mobile actuator 52, locating part 53 and firm banking 54;The right angle rack 51 at least has one and is placed on PC Movable support body 511 and a promotion support body 512 for being used to promote PC components 1 on the mounting surface of component 1, the movable support body 511 are connected as a single entity and are mutually perpendicular to the promotion support body 512, and one end of the mobile actuator 52 is connected to right angle rack 51 On, the other end is connected on firm banking 54 by locating part 53.
The firm banking 54 is fixed on by expansion bolt on the mounting surface of PC components 1.Have on firm banking 54 and use The holding tank 542 slided in movable support body 511, the locating part 53 is fixed in movable support body 511 through holding tank 542.
The locating part 53 of the present embodiment is spacer pin.
There is the support block 541 for holding movable actuator 52, the mobile actuator 52 on the firm banking 54 Bottom be arranged in the support block 541, the top of the mobile actuator 52 is provided with keeper 55, the keeper 55 It is connected on right angle rack 51.
The keeper 55 of the present embodiment is alignment pin.
The mobile actuator 52 of the present embodiment is jack.
The movable support body 511 of the present embodiment is channel-section steel or square steel.
After whole PC components 1 drop into mounting surface, due to sleeve and the size difference of spacer bar 3, it can cause whole 1~5cm of PC components 1 and actual standard wall line alternate position spike, this distance is more small, with hand or sticks up bar and goes movement, it is laborious and Bad precise positioning.Using the right angle rack 51 of the present embodiment, in the presence of mobile actuator 52, right angle rack ensure that 51 move integrally to promote whole PC components 1 to be moved on standard wall line position.After PC components 1 are installed in place, equipment is removed .
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention Any modifications, equivalent substitutions and improvements made within refreshing and principle etc., should be included in the scope of the protection.

Claims (10)

1. a kind of installation method of PC components, it is characterised in that comprise the following steps:
(1) tower crane slings PC components, and when PC components are from 1.3~1.8m of mounting surface, two are at least installed in the bottom of PC components Sleeve locator;
(2) position of PC components is adjusted so that the aperture that the sleeve locator 2 of PC member bottom sections absorption is sent is centered around mounting surface On spacer bar 3 around;
(3) PC member position adjusting brackets are placed according to the position of mounting surface, PC member position adjusting brackets are adjusted to heeling condition, PC components are placed on inclined PC member positions adjusting bracket, distinguish spacing to PC member uppers, left side and right side;
(4) and then by PC member position adjusting brackets it is adjusted to plumbness so that PC components are perpendicular to mounting surface;
(5) position of PC components is checked using sleeve locator, manual adjustment PC components is needed if position is offset Sleeve be located at correspondence spacer bar surface, PC components are then drop to mounting surface using PC member positions adjusting bracket, So that the bottom sleeves of PC components are socketed in spacer bar;
(6) sleeve locator and PC member position adjusting brackets are removed, accurate adjustment then is carried out to PC member positions, promotes PC components to arrive The position of wall line on mounting surface.
2. the installation method of a kind of PC components according to claim 1, it is characterised in that the PC components drop to installation During face, PC components are inclined to the direction away from wall line so that PC components are dropped to after mounting surface, are had between PC components and wall line Gap.
3. a kind of installation method of PC components according to claim 1, the sleeve locator includes luminous aperture and fixed Position head part, the luminous aperture includes laser light belt and positioning pedestal, and the positioning pedestal is loop configuration, the positioning top piece The ring part and projection of the positioning pedestal are set on the surface of positioning pedestal, the laser light belt is arranged on positioning pedestal On.
4. a kind of installation method of PC components according to claim 3, the positioning pedestal is the magnet of two arcs, institute The end for stating two magnet is hinged, and the head end of described two magnet is attached together for synonyms pole.
5. a kind of installation method of PC components according to claim 3, the positioning top piece includes bottom base and projection Part, one end of the projection piece is fixed in bottom base, and the other end passes through the annular of positioning pedestal, the length of the projection piece More than the height of the ring part of positioning pedestal, the external diameter of the bottom base is more than the internal diameter of the ring part.
6. a kind of installation method of PC components according to claim 1, it is characterised in that the PC member positions adjusting bracket Including regulation pedestal, adjusting post, crane, upper limit part, side locating part, bottom locating part, the first actuator and the Two actuators;The bottom of the adjusting post is hinged on regulation pedestal, the top connection upper limit part of the adjusting post, The first actuator driving adjusting post is rotated around regulation pedestal, and the two ends of the crane are slidably connected at adjusting post On, the bottom locating part is connected on crane, and the side locating part is connected on adjusting post, second actuator Driving crane is moved up and down.
7. the installation method of a kind of PC components according to claim 6, it is characterised in that opened on the inside of the adjusting post If chute, the two ends of the crane, which are located in corresponding chute, to be slided up and down.
8. the installation method of a kind of PC components according to claim 6, it is characterised in that the upper limit part includes limit Position bar, upper stopper and extension, the gag lever post are arranged on the top of adjusting post, the upper stopper parallel to regulation pedestal, One end of the upper stopper is connected on gag lever post, and other end connection extension, the extension be arranged in parallel with gag lever post.
9. the installation method of a kind of PC components according to claim 1, it is characterised in that the accurate adjustment of the PC components passes through Accurate adjustment frame realizes that the accurate adjustment frame includes right angle rack, mobile actuator, locating part and firm banking;It is described Right angle rack at least is used to promote pushing away for PC components with a movable support body being placed on the mounting surface of PC components and one Moving frame body, the movable support body is connected as a single entity and is mutually perpendicular to the promotion support body, one end connection of the mobile actuator On right angle rack, the other end is connected on firm banking by locating part.
10. the installation method of a kind of PC components according to claim 9, it is characterised in that have on the firm banking The holding tank slided for movable support body, the locating part is fixed in movable support body through holding tank.
CN201710264843.6A 2017-04-21 2017-04-21 A kind of installation method of PC component Expired - Fee Related CN106968437B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710264843.6A CN106968437B (en) 2017-04-21 2017-04-21 A kind of installation method of PC component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710264843.6A CN106968437B (en) 2017-04-21 2017-04-21 A kind of installation method of PC component

Publications (2)

Publication Number Publication Date
CN106968437A true CN106968437A (en) 2017-07-21
CN106968437B CN106968437B (en) 2019-02-15

Family

ID=59333346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710264843.6A Expired - Fee Related CN106968437B (en) 2017-04-21 2017-04-21 A kind of installation method of PC component

Country Status (1)

Country Link
CN (1) CN106968437B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222285A (en) * 2018-01-31 2018-06-29 合肥建工集团有限公司 A kind of assembly concrete member reinforcing steel bar magnetic suspension connects localization method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0960302A (en) * 1995-08-17 1997-03-04 Fudo Kenken Kk Erection method for precast concrete column and adjuster metal tool for adjustment of column level
JP2913509B2 (en) * 1990-02-07 1999-06-28 大成建設株式会社 How to build PC members
CN104746884A (en) * 2015-04-10 2015-07-01 华东建筑设计研究院有限公司 Method for hoisting prefabricated parts of assembled building
CN105507154A (en) * 2015-11-30 2016-04-20 中铁大桥局集团有限公司 Precast beam hoisting positioner and precast beam hoisting construction method
CN205713144U (en) * 2016-06-15 2016-11-23 北京城建建设工程有限公司 Positioner checked by a kind of reinforcing bar installing body of wall PC plate

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2913509B2 (en) * 1990-02-07 1999-06-28 大成建設株式会社 How to build PC members
JPH0960302A (en) * 1995-08-17 1997-03-04 Fudo Kenken Kk Erection method for precast concrete column and adjuster metal tool for adjustment of column level
CN104746884A (en) * 2015-04-10 2015-07-01 华东建筑设计研究院有限公司 Method for hoisting prefabricated parts of assembled building
CN105507154A (en) * 2015-11-30 2016-04-20 中铁大桥局集团有限公司 Precast beam hoisting positioner and precast beam hoisting construction method
CN205713144U (en) * 2016-06-15 2016-11-23 北京城建建设工程有限公司 Positioner checked by a kind of reinforcing bar installing body of wall PC plate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222285A (en) * 2018-01-31 2018-06-29 合肥建工集团有限公司 A kind of assembly concrete member reinforcing steel bar magnetic suspension connects localization method

Also Published As

Publication number Publication date
CN106968437B (en) 2019-02-15

Similar Documents

Publication Publication Date Title
CN206681392U (en) A kind of accurate adjustment frame
CN112304566B (en) Three-dimensional arbitrary-form debris flow groove simulation experiment system and experiment method
CN105569054A (en) Device and method for controlling direction and elevation of lattice column below ground
CN106968437A (en) A kind of installation method of PC components
CN202265778U (en) High-precision precast-beam positioning structure
KR20190041189A (en) Modular work platform of a long span bridge main tower rebar and construction method using the same
CN208650087U (en) Steel pipe column fast-positioning device for contrary sequence method
CN109179222A (en) A kind of pre-buried section gradient of derrick crane and levelness control construction method
CN106948603A (en) Wall plate member switching mechanism and its method for turning
CN109968522A (en) The mounting device and installation method of prefabricated case beam bottom web reinforcement skeleton
CN206859705U (en) A kind of PC member positions adjusting bracket
CN206681390U (en) A kind of sleeve locator
CN102392540B (en) High-precision method and structure for positioning high-precision precast beam
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
KR101243703B1 (en) Apparatus for Manufacturing Caisson Comprising Exterior Form and Interior Form
CN113309256A (en) Construction device and construction method for prefabricated shear wall with post-pouring section
CN209323691U (en) A kind of huge diagonal brace of overlength superelevation
CN109252590A (en) A kind of huge diagonal brace of overlength superelevation and its seek connections with formula construction method
CN108385710B (en) Reusable tower foundation and installation method thereof
CN112324153A (en) A reinforcement auxiliary device for job site
CN109372242A (en) A kind of construction of lift well security improvement stage apparatus and application method
CN217998829U (en) Prefabricated assembled stair guide installation device
CN205475256U (en) Control is less than device of ground lattice column direction and elevation
CN212103549U (en) Positioning structure for deep barrel lamp
CN219260736U (en) Temporary support frame for steel structure bridge construction

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181219

Address after: 410000 No. 158 Zhongyi Road, Yuhua District, Changsha, Hunan

Applicant after: China Construction Fifth Engineering Division Co., Ltd.

Address before: 236000 floor 12, C8 building, Times Square, Binhu New District, Hefei, Anhui.

Applicant before: China Construction Fifth Engineering Bureau Co., Ltd. Anhui branch

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190215

Termination date: 20210421