CN106968334A - 一种现浇混凝土框架二次结构构造柱的施工方法 - Google Patents
一种现浇混凝土框架二次结构构造柱的施工方法 Download PDFInfo
- Publication number
- CN106968334A CN106968334A CN201710288478.2A CN201710288478A CN106968334A CN 106968334 A CN106968334 A CN 106968334A CN 201710288478 A CN201710288478 A CN 201710288478A CN 106968334 A CN106968334 A CN 106968334A
- Authority
- CN
- China
- Prior art keywords
- constructional column
- secondary structure
- cage bar
- floor
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
- E04B1/21—Connections specially adapted therefor
- E04B1/215—Connections specially adapted therefor comprising metallic plates or parts
Abstract
本发明公开了一种现浇混凝土框架二次结构构造柱的施工方法,步骤为:1)在各楼板上预留矩形洞口;2)在首层混凝土地面上植入构造柱甩筋;3)绑扎二次结构构造柱的主筋与箍筋,将主筋的下端与构造柱甩筋连接,上端穿过楼板上预留矩形洞口;4)支设构造柱模板;5)从预留矩形洞口向下浇筑混凝土;6)重复步骤3)、4)和5),完成各楼层二次结构构造柱的施工;本发明实现了二次结构构造柱主筋上、下贯通,精确控制二次结构构造柱的位置;一次搭接连接,使主筋搭接接头减少了50%,节约了钢筋;从预留孔洞直接浇筑混凝土,简化了二次结构构造柱支模工艺,节省了剔凿工序,节约了混凝土,保证了其混凝土的外观质量。
Description
技术领域
本发明属于建筑施工领域,具体涉及一种现浇混凝土框架二次结构中构造柱的施工方法。
背景技术
二次结构构造柱是在主体结构施工完成后,砌填充墙时施工完成的。按照施工图设计要求,在每一层间设置的二次结构构造柱,其根部与顶部均需与楼层的混凝土楼板与顶板锚固连接。现有技术的做法是:按照二次结构构造柱的位置在楼板内和顶板内预埋或后植入一定长度的构造柱甩筋,二次结构构造柱施工时,其主筋的两端分别与上、下构造柱甩筋连接。
通过预埋构造柱甩筋在楼板混凝土浇筑过程中其位置很难控制,经常因混凝土浇筑操作不当发生构造柱甩筋位移的现象。因此,预埋构造柱甩筋的方法在实际施工中采用的越来越少。
后植入构造柱甩筋的方法可准确的控制二次结构构造柱的位置,但该方法工序较多,且增加施工成本,施工速度慢。另外,在现有技术中由于二次结构构造柱内的混凝土浇筑是在楼板和顶板之间完成的,为了保证混凝土的浇筑密实,通常将二次结构构造柱模板的一侧近顶部支设成楔形状,作为混凝土浇筑口,当混凝土浇筑完成硬化后拆除楔形模板,将墙面凸出的混凝土剔除掉。因此,现有技术的二次结构构造柱混凝土浇筑也存在操作复杂,人工耗时,材料浪费的不足。
发明内容
本发明的目的是克服现有技术的不足,提供一种现浇混凝土框架二次结构构造柱的施工方法。
本发明的技术方案概述如下:
一种现浇混凝土框架二次结构构造柱的施工方法,包括如下步骤:
1)按照施工图设计要求的二次结构构造柱的位置,在各楼板1上预留矩形洞口2;
2)在首层混凝土地面3上植入构造柱甩筋4,构造柱甩筋的长度满足设计要求;
3)绑扎二次结构构造柱的主筋5与箍筋6,将主筋的下端与构造柱甩筋连接,主筋的上端穿过上一层楼板1上预留矩形洞口2,伸出上一层楼板的长度满足构造柱甩筋的长度设计要求;
4)支设构造柱模板7;
5)从预留矩形洞口2向下浇筑混凝土8;
6)重复步骤3)、4)和5),完成除顶层外各楼层二次结构构造柱的施工,
7)绑扎顶层二次结构构造柱的主筋5与箍筋6,将主筋的下端与下一层主筋伸出的部分连接,顶层的主筋的上端位于顶层顶板的预留矩形洞口内并距顶板上表面2-3cm,支设构造柱模板,从预留矩形洞口向下浇筑混凝土,并将顶板上表面抹平。
本发明的施工方法,通过在混凝土楼板中预留矩形洞口,实现了二次结构构造柱主筋上、下贯通,精确控制二次结构构造柱的位置;本发明的方法将现有技术中每层构造柱主筋要两次搭接连接,改变为一次搭接连接,使二次结构构造柱主筋搭接接头减少了50%,节约了钢筋材料;可以从预留孔洞直接浇筑混凝土,简化了二次结构构造柱支模工艺,节省了二次结构构造柱顶部的剔凿工序,节约了混凝土材料,保证了其混凝土的外观质量。
附图说明
图1为本发明的方法从步骤1)到步骤4)形成的结构示意图。
图2为混凝土浇筑形成二次结构构造柱示意图。
具体实施方式
下面结合附图对本发明作进一步的说明。
一种现浇混凝土框架二次结构构造柱的施工方法,包括如下步骤:
1)按照施工图设计要求的二次结构构造柱的位置,在各楼板1上预留矩形洞口2;
2)在首层混凝土地面3上植入构造柱甩筋4,构造柱甩筋的长度满足设计要求;
3)绑扎二次结构构造柱的主筋5与箍筋6,将主筋的下端与构造柱甩筋连接,主筋的上端穿过上一层楼板1上预留矩形洞口2,伸出上一层楼板的长度满足构造柱甩筋的长度设计要求;
4)支设构造柱模板7,见图1;
5)从预留矩形洞口2向下浇筑混凝土8,见图2;
6)重复步骤3)、4)和5),完成除顶层外各楼层二次结构构造柱的施工,
7)绑扎顶层二次结构构造柱的主筋5与箍筋6,将主筋的下端与下一层主筋伸出的部分连接,顶层的主筋的上端位于顶层顶板的预留矩形洞口内并距顶板上表面2cm,也可以是3cm,支设构造柱模板,从预留矩形洞口向下浇筑混凝土,并将顶板上表面抹平。
Claims (1)
1.一种现浇混凝土框架二次结构构造柱的施工方法,其特征是包括如下步骤:
1)按照施工图设计要求的二次结构构造柱的位置,在各楼板(1)上预留矩形洞口(2);
2)在首层混凝土地面(3)上植入构造柱甩筋(4),构造柱甩筋的长度满足设计要求;
3)绑扎二次结构构造柱的主筋(5)与箍筋(6),将主筋的下端与构造柱甩筋连接,主筋的上端穿过上一层楼板(1)上预留矩形洞口(2),伸出上一层楼板的长度满足构造柱甩筋的长度设计要求;
4)支设构造柱模板(7);
5)从预留矩形洞口(2)向下浇筑混凝土(8);
6)重复步骤3)、4)和5),完成除顶层外各楼层二次结构构造柱的施工;
7)绑扎顶层二次结构构造柱的主筋(5)与箍筋(6),将主筋的下端与下一层主筋伸出的部分连接,顶层的主筋的上端位于顶层顶板的预留矩形洞口内并距顶板上表面2-3cm,支设构造柱模板,从预留矩形洞口向下浇筑混凝土,并将顶板上表面抹平。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710288478.2A CN106968334A (zh) | 2017-04-25 | 2017-04-25 | 一种现浇混凝土框架二次结构构造柱的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710288478.2A CN106968334A (zh) | 2017-04-25 | 2017-04-25 | 一种现浇混凝土框架二次结构构造柱的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106968334A true CN106968334A (zh) | 2017-07-21 |
Family
ID=59333608
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710288478.2A Pending CN106968334A (zh) | 2017-04-25 | 2017-04-25 | 一种现浇混凝土框架二次结构构造柱的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106968334A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113565263A (zh) * | 2021-07-23 | 2021-10-29 | 华北冶建工程建设有限公司 | 构造柱施工方法 |
CN114856033A (zh) * | 2022-04-25 | 2022-08-05 | 北京崇建工程有限公司 | 一种二次结构构造柱免植筋施工工艺 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103556819A (zh) * | 2013-11-23 | 2014-02-05 | 中建四局第六建筑工程有限公司 | 一种在梁板上预留构造柱孔洞的施工方法 |
CN103938864A (zh) * | 2013-01-21 | 2014-07-23 | 高行友 | 填充墙构造柱施工工法 |
CN104088411A (zh) * | 2014-07-23 | 2014-10-08 | 闫妍 | 一种建筑物抗震逃生楼梯 |
CN204850445U (zh) * | 2015-07-24 | 2015-12-09 | 新七建设集团有限公司 | 一种与楼板连接构造柱浇筑装置 |
CN105155843A (zh) * | 2015-08-05 | 2015-12-16 | 中国华冶科工集团有限公司 | 构造柱的施工方法及装置 |
CN105155669A (zh) * | 2015-09-15 | 2015-12-16 | 成都市第四建筑工程公司 | 暗梁楼板构造柱结构以及施工方法 |
CN105464382A (zh) * | 2014-09-03 | 2016-04-06 | 中国建筑第四工程局有限公司 | 一种砌块与构造柱一体化施工方法及构造柱模板砌块 |
CN106567543A (zh) * | 2016-10-26 | 2017-04-19 | 上海中锦建设集团股份有限公司 | 一种板底构造柱预留洞施工法 |
-
2017
- 2017-04-25 CN CN201710288478.2A patent/CN106968334A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103938864A (zh) * | 2013-01-21 | 2014-07-23 | 高行友 | 填充墙构造柱施工工法 |
CN103556819A (zh) * | 2013-11-23 | 2014-02-05 | 中建四局第六建筑工程有限公司 | 一种在梁板上预留构造柱孔洞的施工方法 |
CN104088411A (zh) * | 2014-07-23 | 2014-10-08 | 闫妍 | 一种建筑物抗震逃生楼梯 |
CN105464382A (zh) * | 2014-09-03 | 2016-04-06 | 中国建筑第四工程局有限公司 | 一种砌块与构造柱一体化施工方法及构造柱模板砌块 |
CN204850445U (zh) * | 2015-07-24 | 2015-12-09 | 新七建设集团有限公司 | 一种与楼板连接构造柱浇筑装置 |
CN105155843A (zh) * | 2015-08-05 | 2015-12-16 | 中国华冶科工集团有限公司 | 构造柱的施工方法及装置 |
CN105155669A (zh) * | 2015-09-15 | 2015-12-16 | 成都市第四建筑工程公司 | 暗梁楼板构造柱结构以及施工方法 |
CN106567543A (zh) * | 2016-10-26 | 2017-04-19 | 上海中锦建设集团股份有限公司 | 一种板底构造柱预留洞施工法 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113565263A (zh) * | 2021-07-23 | 2021-10-29 | 华北冶建工程建设有限公司 | 构造柱施工方法 |
CN114856033A (zh) * | 2022-04-25 | 2022-08-05 | 北京崇建工程有限公司 | 一种二次结构构造柱免植筋施工工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013530B (zh) | 基于3d打印的混凝土剪力墙的配筋结构 | |
CN104775553B (zh) | 一种新型l型叠合板式剪力墙边缘构件及其连接方法 | |
CN106894587A (zh) | 预制楼梯连接方法 | |
CN109723140A (zh) | 一种预制楼梯间的施工方法 | |
CN204899204U (zh) | 逆作法中取土口处构建混凝土结构的模板系统 | |
CN106368365A (zh) | 通筋式混凝土叠合楼板结构及其制作和装配方法 | |
CN105839784B (zh) | 拼装顶升式建筑施工方法 | |
CN106968334A (zh) | 一种现浇混凝土框架二次结构构造柱的施工方法 | |
CN105019645B (zh) | 逆作法中取土口处构建混凝土结构的模板系统及施工方法 | |
CN206220297U (zh) | 预制剪力墙 | |
CN103321153A (zh) | 一种中小跨径槽形梁桥的施工方法 | |
CN206233566U (zh) | 一种早拆法用后浇带模板支撑结构 | |
CN107675838A (zh) | 装配式建筑便道砖式预制梁预埋套筒插筋施工方法 | |
CN206554428U (zh) | 一种预制楼梯连接节点 | |
CN204551824U (zh) | 一种新型l型叠合板式剪力墙边缘构件 | |
CN209261310U (zh) | 连体式混凝土预制装配组合仓 | |
CN106567543A (zh) | 一种板底构造柱预留洞施工法 | |
CN208347063U (zh) | 一种预制双板墙单元、剪力墙单元及装配式混凝土剪力墙 | |
CN206337643U (zh) | 预制框架结构 | |
CN107237436B (zh) | 一种空腔楼板施工时的临时固定方法 | |
CN103628684B (zh) | 一种同时浇筑楼板和剪力墙的施工方法 | |
CN211773695U (zh) | 新老结构多层地下室换撑传力构造 | |
CN107574934A (zh) | 装配式剪力墙预埋套筒插筋施工方法 | |
CN206693476U (zh) | 一种斜屋面结构的边缘结构构造 | |
CN206070550U (zh) | 一种装配式建筑预制基础 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170721 |