CN106968252A - Pile pulling recharge method and pile pulling recharge system - Google Patents

Pile pulling recharge method and pile pulling recharge system Download PDF

Info

Publication number
CN106968252A
CN106968252A CN201710213872.XA CN201710213872A CN106968252A CN 106968252 A CN106968252 A CN 106968252A CN 201710213872 A CN201710213872 A CN 201710213872A CN 106968252 A CN106968252 A CN 106968252A
Authority
CN
China
Prior art keywords
pile
hole
anchor
pulled out
pulling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710213872.XA
Other languages
Chinese (zh)
Other versions
CN106968252B (en
Inventor
刘海祥
陈亮
柯敏勇
唐云清
鲁文妍
龙志勇
陈西宁
王凌骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing R & D Tech Group Co Ltd
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Original Assignee
Nanjing R & D Tech Group Co Ltd
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing R & D Tech Group Co Ltd, Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources filed Critical Nanjing R & D Tech Group Co Ltd
Priority to CN201710213872.XA priority Critical patent/CN106968252B/en
Publication of CN106968252A publication Critical patent/CN106968252A/en
Application granted granted Critical
Publication of CN106968252B publication Critical patent/CN106968252B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a kind of pile pulling recharge method and pile pulling recharge system, belong to stake in the engineerings such as water conservancy, highway, railway, municipal administration, bridge removes technical field.The pile pulling recharge method comprises the following steps:1)First make the top exposed for treating pile pulling through pre-treatment;2)Treating to drill anchor hole and pile body grout hole at the top of pile pulling;3)One end of anchorage cable materials is transferred to anchor hole bottom, its other end, which exposes, to be treated at the top of pile pulling;4)The first slurry is irrigated to anchor hole, anchorage cable materials are fixed on and treat to form anchor pole in pile pulling;5) pile pulling is treated to pull up by the other end of lifting appliance lifting anchorage cable materials, during pile pulling, passes through pile body grout hole the second slurry of recharge so that the second slurry penetrates into the pile peripheral earth for treating pile pulling bottom, and by the soil body and treats that pile pulling is linked as entirety.The pile pulling recharge method and pile pulling recharge system can fast and safely extract stake, play reduction lifting force, prevent landslide, improve success rate, and the stable effect of protection surrounding building underground structure.

Description

拔桩回灌方法及拔桩回灌系统Pulling pile recharging method and pulling pile recharging system

技术领域technical field

本发明涉及一种拔桩回灌方法及拔桩回灌系统,属于水利、公路、铁路、市政、桥梁等工程中桩的撤去技术领域。The invention relates to a pile pulling recharging method and a pile pulling recharging system, belonging to the technical field of removing piles in water conservancy, highway, railway, municipal, bridge and other projects.

背景技术Background technique

现有地铁隧洞盾构施工中,需要将影响隧洞施工的整桩提至安全高度,即将影响隧洞施工的整桩完全拔出或者部分拔出。In the shield construction of existing subway tunnels, it is necessary to raise the entire piles that affect the tunnel construction to a safe height, that is, to completely or partially pull out the entire piles that affect the tunnel construction.

但是,据申请人了解,现有国内外的拔桩技术,主要采用以下几种方式:However, as far as the applicant knows, the existing domestic and foreign pile extraction technologies mainly adopt the following methods:

1)冲击碎桩法与全套管减磨拔除法;这两种拔桩技术主要依赖全套管钻机及大型起重机,故对施工场地要求较高,施工场地面积很大且场地上部无净高限制,但是,实际施工环境是难以达到的。1) Impact pile breaking method and full-casing wear-reducing extraction method; these two pile-extraction technologies mainly rely on full-casing drilling rigs and large cranes, so the requirements for the construction site are relatively high. The construction site has a large area and there is no clear height limit on the upper part of the site. However, the actual construction environment is difficult to achieve.

2)全套管静压拔桩的方法,这种方法采用钢套管以及结合喷射高压水及高压膨润土浆对桩的周圈土体进行清除,然后进行拔桩,但是工艺较复杂,实际较长,特别是对于彼此紧邻的多根桩的拔除不能适用。2) The method of static pressure pile extraction with full casing. This method uses steel casing and combined with spraying high-pressure water and high-pressure bentonite slurry to remove the surrounding soil of the pile, and then pulls the pile. However, the process is more complicated and the actual time is longer. , especially for the extraction of multiple piles next to each other cannot be applied.

3)直接将灌注桩中的桩头钢筋与拔桩设置连接,逐渐施力直至将桩拔出,但是,现有灌注桩中的钢筋强度低、焊接不可靠、受力不均,容易将灌注桩拔断,这是拔桩施工中所不允许的。3) Directly connect the pile head steel bar in the cast-in-place pile with the pulling pile, and apply force gradually until the pile is pulled out. However, the steel bar in the existing cast-in-place pile has low strength, unreliable welding, and uneven force, and it is easy to pull out the cast-in-place pile. The pile is pulled out, which is not allowed in the pile pulling construction.

同时,据申请人了解,在拔桩过程中,桩的底部将形成由水体代替的空腔,空腔周边松散土体极易坍塌,破坏桩的功能,容易对周边建筑物产生不利影响,现有桩的回灌都是在拔桩后进行的。At the same time, according to the applicant's knowledge, during the process of pulling out the pile, a cavity will be formed at the bottom of the pile replaced by a water body, and the loose soil around the cavity will easily collapse, destroying the function of the pile, and easily adversely affecting the surrounding buildings. The recharge of piles is carried out after the piles are pulled out.

可见,现有拔桩技术中,设备要求高、占地大、启用大型吊机风险大,快速安全拔桩仍然是一个难题,尤其是在小空间中的大直径桩快速安全拔出。同时,现有桩的回灌不能保证原有桩的功能,不能保护周边建筑物地下结构稳定。It can be seen that in the existing pile pulling technology, the equipment requirements are high, the area is large, and the risk of using a large crane is high. Quick and safe pile pulling is still a problem, especially for large-diameter piles in a small space. At the same time, the recharge of the existing piles cannot guarantee the function of the original piles, and cannot protect the stability of the underground structure of the surrounding buildings.

发明内容Contents of the invention

本发明要解决的技术问题是针对现有技术不足,提出一种快速安全拔出不同直径桩并同时保证桩的功能的拔桩回灌方法及拔桩回灌系统。The technical problem to be solved by the present invention is to propose a pile pulling refilling method and a pile pulling refilling system that can quickly and safely pull out piles of different diameters while ensuring the function of the piles.

本发明为解决上述技术问题提出的技术方案之一是:一种拔桩回灌方法,包括以下步骤:One of the technical solutions proposed by the present invention to solve the above technical problems is: a method for pulling out piles and recharging, comprising the following steps:

1)经前处理先使待拔桩的顶部曝露,同时备设多根高强度锚索材料以及起吊设备;1) After pretreatment, the top of the pile to be pulled is first exposed, and multiple high-strength anchor cable materials and lifting equipment are equipped at the same time;

2)在待拔桩的顶部钻制向待拔桩内的底部延伸的锚孔,在待拔桩上钻制贯通其顶面和底面的桩体灌浆孔;2) drilling an anchor hole extending to the bottom of the pile to be pulled out at the top of the pile to be pulled out, and drilling a pile body grouting hole through the top surface and the bottom surface of the pile to be pulled out;

3)将所述锚索材料的一端下放至所述锚孔底部,其另一端露出待拔桩顶部;3) lowering one end of the anchor cable material to the bottom of the anchor hole, the other end of which is exposed to the top of the pile to be pulled out;

4)向所述锚孔灌注第一浆体,待所述第一浆体固化并达到设定强度后,将所述锚索材料固定于所述待拔桩内形成锚杆;4) pouring the first slurry into the anchor hole, and after the first slurry solidifies and reaches a set strength, the anchor cable material is fixed in the pile to be pulled out to form an anchor rod;

5)通过起吊设备提升所述锚索材料的另一端以拔起待拔桩,在拔起待拔桩的过程中,通过桩体灌浆孔回灌第二浆体,使得第二浆体渗入待拔桩底部的桩周土体,并将土体与待拔桩连为整体。5) lifting the other end of the anchor cable material by lifting equipment to pull up the pile to be pulled out, and during the process of pulling up the pile to be pulled out, refill the second slurry through the grouting hole of the pile body, so that the second slurry penetrates into the pile to be pulled out. Pull out the soil around the pile at the bottom of the pile, and connect the soil with the pile to be pulled out as a whole.

本发明为解决上述技术问题提出的技术方案之二是:一种拔桩回灌系统,用于上述的拔桩回灌方法中,该拔桩回灌系统设置于固定在土体中并顶部曝露的待拔桩附近,包括多根高强度锚索材料和起吊设备,其特征在于:所述待拔桩的顶部制有向待拔桩内的底部延伸的锚孔,所述待拔桩上制有贯通其顶面和底面的桩体灌浆孔,所述锚索材料的一端设于所述锚孔底部,所述锚索材料的另一端露出待拔桩顶部;所述锚孔内灌注有固化后用于将锚索材料固定于待拔桩内以形成锚杆的第一浆体,所述起吊设备用于提升所述锚索材料的另一端以拔起待拔桩,所述桩体灌浆孔用于在拔桩过程中回灌第二浆体。The second technical solution proposed by the present invention to solve the above technical problems is: a pile pulling recharge system, used in the above pile pulling refilling method, the pile pulling refilling system is set in the soil and the top is exposed Near the piles to be pulled out, comprising a plurality of high-strength anchor cable materials and lifting equipment, it is characterized in that: the top of the piles to be pulled out is formed with anchor holes extending toward the bottom of the piles to be pulled out, and the top of the piles to be pulled out is formed with There is a pile body grouting hole that runs through its top and bottom surfaces, one end of the anchor cable material is arranged at the bottom of the anchor hole, and the other end of the anchor cable material exposes the top of the pile to be pulled out; the anchor hole is filled with solidified Afterwards, it is used to fix the anchor cable material in the pile to be pulled out to form the first slurry of the anchor rod, the lifting device is used to lift the other end of the anchor cable material to pull up the pile to be pulled out, and the pile body is grouted The holes are used to refill the second slurry during pile extraction.

本发明直接在待拔桩的顶部钻制向待拔桩内的底部延伸的锚孔,在待拔桩上钻制贯通其其顶面和底面的桩体灌浆孔,然后将锚索材料的一端下放至所述锚孔底部,其另一端露出待拔桩顶部,再向锚孔灌注第一浆体,将锚索材料固定于待拔桩内形成锚杆,最后通过起吊设备提升所述锚索材料的另一端以拔起待拔桩,在拔起待拔桩的过程中,通过桩体灌浆孔回灌第二浆体,这样具有如下效果:The present invention directly drills the anchor hole extending to the bottom of the pile to be pulled out on the top of the pile to be pulled out, and drills the pile body grouting hole through the top surface and the bottom surface of the pile to be pulled out, and then puts one end of the anchor cable material Lower to the bottom of the anchor hole, the other end of which exposes the top of the pile to be pulled out, then pour the first slurry into the anchor hole, fix the anchor cable material in the pile to be pulled out to form an anchor rod, and finally lift the anchor cable by lifting equipment The other end of the material is used to pull up the pile to be pulled out. During the process of pulling up the pile to be pulled out, the second slurry is refilled through the grouting hole of the pile body, which has the following effects:

1)巧妙的将现有岩土锚固技术中的锚杆移用到拔桩中,相比于传统拔桩的思维定势是一味在桩的外表固定后进行吊拔,本发明突破了这一思维定势,对待拔桩先钻孔进行锚固再拔除,形成先锚后拔,因此十分出人意料。1) Cleverly transfer the anchor rods in the existing geotechnical anchoring technology to pile pulling. Compared with the traditional thinking of pulling piles, which is to blindly pull the piles after their appearance is fixed, the present invention breaks through this The mindset is that the piles to be pulled out should be drilled first and then anchored and then pulled out, forming an anchor first and then pulling out, so it is very unexpected.

本发明既可以对于不同直径(大、中、小)待拔桩进行锚固提升,同时又对拔桩进行加固,可以有效防止拔桩中的断桩并将大直径桩快速安全拔出,特别是对于小空间中彼此紧邻的多根桩的拔除十分适用,整体非常可靠稳固、安全性大大提高的同时节省大量成本,且提高效率。The present invention can anchor and lift piles of different diameters (large, medium and small) to be pulled out, and at the same time reinforce the piles pulled out, which can effectively prevent piles from being pulled out and pull out large-diameter piles quickly and safely, especially It is very suitable for pulling out multiple piles that are adjacent to each other in a small space, and the whole is very reliable and stable, greatly improving safety, saving a lot of cost, and improving efficiency.

2)通过在待拔桩上钻制贯通其顶面和底面的桩体灌浆孔,在拔起待拔桩的过程中,通过桩体灌浆孔回灌第二浆体,可以确保桩的结构安全,保护周边建筑物地下结构稳定,防止塌方,同时,可以使大气压内外平衡,降低提升力,提高成功率。特别重要的是,在只需要将桩部分拔出的施工要求时,在拔桩过程中,通过桩体灌浆孔回灌第二浆体,使得第二浆体渗入待拔桩底部的桩周土体,并将土体与待拔桩连为整体,这样,未完全拔出的余下的桩还可以进行利用。2) By drilling the pile body grouting holes through the top and bottom surfaces of the piles to be pulled out, during the process of pulling up the piles to be pulled out, refilling the second slurry through the pile body grouting holes can ensure the structural safety of the piles , to protect the stability of the underground structure of surrounding buildings and prevent landslides. At the same time, it can balance the atmospheric pressure inside and outside, reduce the lifting force, and increase the success rate. It is particularly important that when only part of the pile needs to be pulled out, during the pile pulling process, the second slurry is refilled through the grouting hole of the pile body, so that the second slurry penetrates into the soil around the pile at the bottom of the pile to be pulled out body, and connect the soil body and the pile to be pulled out as a whole, so that the remaining piles that have not been fully pulled out can also be utilized.

上述技术方案之一的改进是:在所述步骤2)中,在所述待拔桩的顶部钻制向其底部延伸的静态爆破孔;在所述步骤5)中,在通过起吊设备提升所述锚索材料的另一端以拔起桩后,先在静态爆破孔中倒入破碎剂并用快硬性水泥堵住静态爆破孔的孔口12-18小时,然后通过破碎设备进行桩体破碎。The improvement of one of the above technical solutions is: in the step 2), a static blast hole extending to the bottom of the pile to be extracted is drilled on the top of the pile; After pulling up the pile from the other end of the anchor cable material, first pour the breaking agent into the static blasting hole and block the opening of the static blasting hole with rapid hardening cement for 12-18 hours, and then the pile body is broken by the crushing equipment.

本发明采用上述技术方案的效果是:通过在待拔桩的顶部钻制向其底部延伸的静态爆破孔,这样在通过起吊设备提升锚索材料的另一端以拔起桩后,先在静态爆破孔中倒入破碎剂并用快硬性水泥堵住静态爆破孔的孔口12-18小时,然后通过破碎设备进行桩体破碎,结合混凝切割以及气割钢筋等办法,可以快速分解混凝土,实现桩的上部拆除,将拔桩工程顺利转向下一工序、下一根桩。The present invention adopts the effect of the above-mentioned technical scheme: by drilling a static blast hole extending toward the bottom of the pile to be pulled out, after the other end of the anchor cable material is lifted by the hoisting device to pull up the pile, the static blast hole is firstly blasted. Pour the breaking agent into the hole and block the opening of the static blasting hole with quick-hardening cement for 12-18 hours, and then crush the pile body through the crushing equipment. Combined with concrete cutting and gas cutting steel bars, the concrete can be quickly decomposed to realize the pile The upper part is removed, and the pile pulling project is smoothly transferred to the next process and the next pile.

上述技术方案之一的完善之一是:在所述步骤1)中,在所述待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台;在所述步骤5)中,所述起吊设备是设于工作平台上的穿心千斤顶、吊机或卷扬机,所述穿心千斤顶、吊机或卷扬机持续张拉锚索材料的另一端以连续拔起所述待拔桩。One of the improvement of one of the above-mentioned technical solutions is: in the step 1), a working platform is provided on other piles near the pile to be pulled out or on the soil around the pile to be pulled out; in the step 5) Among them, the lifting equipment is a through-hole jack, crane or hoist arranged on the working platform, and the other end of the anchor cable material is continuously stretched by the through-hole jack, crane or hoist to continuously pull up the pile to be pulled out. .

本发明采用上述技术方案的效果是:本发明通过在待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台,起吊设备采用设于工作平台上的穿心千斤顶、吊机或卷扬机,这样可以通过穿心千斤顶、吊机或卷扬机持续张拉锚索材料的另一端,对桩连续拔起,整体结构简单可靠。The present invention adopts the effect of the technical scheme as follows: the present invention is provided with a working platform on other piles near the piles to be pulled out or on the soil around the piles to be pulled out, and the hoisting equipment adopts a through-hole jack, a crane, etc. that are arranged on the working platform. Machine or hoist, so that the other end of the anchor cable material can be continuously stretched by a through-hole jack, crane or hoist, and the pile can be pulled up continuously. The overall structure is simple and reliable.

上述技术方案之一的完善之一的改进是:所述工作平台是钢筋混凝土平台、钢结构框架平台或组合结构平台;所述穿心千斤顶通过反力架安装固定在钢筋混凝土平台、钢结构框架平台或组合结构平台上;所述吊机或卷扬机设于钢筋混凝土平台、钢结构框架平台或组合结构平台上。The improvement of one of the above-mentioned technical solutions is: the working platform is a reinforced concrete platform, a steel structure frame platform or a composite structure platform; On a platform or a combined structure platform; the crane or winch is set on a reinforced concrete platform, a steel structure frame platform or a combined structure platform.

本发明采用上述技术方案的效果是:本发明通过设置钢筋混凝土平台、钢结构框架平台或组合结构平台,可以对头部位于地表以上或整体位于地表以下的桩,进行连续拔起,整体结构简单可靠。The effect of adopting the above-mentioned technical solution in the present invention is that the present invention can continuously pull up the pile whose head is above the ground surface or the whole is below the ground surface by setting a reinforced concrete platform, a steel structure frame platform or a combined structure platform, and the overall structure is simple reliable.

上述技术方案之一的完善之一的改进是:所述工作平台是沉井平台,所述穿心千斤顶固定在沉井平台上。The improvement of one of the perfections of one of the above technical solutions is: the working platform is a caisson platform, and the through-hole jack is fixed on the caisson platform.

本发明采用上述技术方案的效果是:本发明通过设置沉井平台,特别适用于整体位于地表以下的桩,进行连续拔起,整体结构简单可靠。The effect of adopting the above-mentioned technical solution in the present invention is that the present invention is particularly suitable for continuous pulling up of piles located below the ground surface by setting the caisson platform, and the overall structure is simple and reliable.

上述技术方案之一的完善之二是:所述锚孔的深度和锚杆的长度小于所述待拔桩的长度并大于所述锚杆的最小锚固长度,所述锚杆的最小锚固长度L按下式计算:The second improvement of one of the above technical solutions is: the depth of the anchor hole and the length of the anchor rod are less than the length of the pile to be pulled and greater than the minimum anchor length of the anchor rod, the minimum anchor length L of the anchor rod Calculate according to the formula:

式中,a为安全系数;σ为锚索材料强度;A为锚索材料截面面积;d为锚孔直径;τ为锚杆与孔壁抗剪强度。In the formula, a is the safety factor; σ is the strength of the anchor cable material; A is the cross-sectional area of the anchor cable material; d is the diameter of the anchor hole; τ is the shear strength of the anchor rod and the hole wall.

上述技术方案之一的完善之三是:所述锚索材料上设有出口分别位于锚孔底部、中部和上部处的三根灌浆管;采用压力灌浆向锚孔内灌注第一浆体,所述第一浆体是由PO52.5水泥、水泥浆孔道压浆剂和水混合而成的浆体,所述第一浆体的水胶比为0.35~0.45;采用砂浆搅拌机和注浆泵进行压力灌浆。The third improvement of one of the above technical solutions is: the anchor cable material is provided with three grouting pipes whose outlets are respectively located at the bottom, middle and upper part of the anchor hole; pressure grouting is used to pour the first slurry into the anchor hole, and the The first slurry is a slurry formed by mixing PO52.5 cement, cement slurry channel grouting agent and water. The water-binder ratio of the first slurry is 0.35-0.45; the pressure is carried out by using a mortar mixer and a grouting pump. grouting.

上述技术方案之二的改进是:所述待拔桩的顶部制有向待拔桩内的底部延伸的静态爆破孔;所述静态爆破孔中倒入有破碎剂并封堵有快硬性水泥块。The improvement of the second technical solution is: the top of the pile to be pulled out is formed with a static blast hole extending toward the bottom of the pile to be pulled out; the static blast hole is poured with breaking agent and blocked with rapid hardening cement block .

上述技术方案之二的改进是:所述待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台。The improvement of the second technical solution is: a working platform is provided on other piles near the pile to be pulled out or on the soil around the pile to be pulled out.

附图说明Description of drawings

下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with accompanying drawing:

图1是本发明实施例一的拔桩回灌方法以及拔桩回灌系统采用的拔桩装置示意图。Fig. 1 is a schematic diagram of the pile pulling and recharging method and the pile pulling device used in the pile pulling and recharging system according to Embodiment 1 of the present invention.

图2是图1的左视图。Fig. 2 is a left side view of Fig. 1 .

图3是图1待拔桩上钻制的锚孔、桩体灌浆孔和静态爆破孔的示意图。Fig. 3 is a schematic diagram of anchor holes, pile body grouting holes and static blast holes drilled on the pile to be pulled out in Fig. 1 .

具体实施方式detailed description

实施例一Embodiment one

本实施例的拔桩回灌方法,如图1、图2和图3所示,包括以下步骤:The method for pulling piles of the present embodiment, as shown in Fig. 1, Fig. 2 and Fig. 3, comprises the following steps:

1)经前处理先使待拔桩1的顶部曝露,同时备设多根高强度锚索材料2以及起吊设备。1) After pretreatment, the top of the pile 1 to be pulled out is first exposed, and a plurality of high-strength anchor cable materials 2 and lifting equipment are equipped at the same time.

本实施例的待拔桩1是埋在在土体中摩擦桩、部分嵌岩的端承桩或是埋于地表以下一定深度的咬合桩、承台桩和打入桩,摩擦桩或端承桩的头部曝露在地表。The pile 1 to be pulled out in this embodiment is a friction pile buried in the soil, a partially rock-socketed end-bearing pile, or an occlusal pile buried at a certain depth below the surface, a cap pile and a driven pile, a friction pile or an end-bearing pile. The head of the pile is exposed to the surface.

本实施例的锚索材料2可以是金属硬质或软质材料制成。金属硬质制成,例如:粘结钢绞束、预应力钢绞线、预应力钢绞束、高强钢丝、高强钢丝绳或高强钢筋,等等;也可以是非金属硬质或软质材料制成,例如:纤维、塑料或尼龙,等等。The anchor cable material 2 of this embodiment can be made of metal hard or soft material. Made of metal hard, such as: bonded steel strands, prestressed steel strands, prestressed steel strands, high-strength steel wires, high-strength steel wire ropes or high-strength steel bars, etc.; can also be made of non-metallic hard or soft materials , such as: fiber, plastic or nylon, etc.

2)在待拔桩1的顶部钻制向待拔桩内的底部延伸的锚孔1-1,在待拔桩1上钻制贯通其顶面和底面的桩体灌浆孔1-2。本实施例的锚孔1-1是位于待拔桩1横截面中心的一个锚孔或沿待拔桩1横截面中心周圈均布的至少两个锚孔。2) An anchor hole 1-1 extending to the bottom of the pile to be pulled is drilled on the top of the pile to be pulled out, and a pile body grouting hole 1-2 is drilled on the pile to be pulled out through its top surface and bottom surface. The anchor hole 1-1 in this embodiment is one anchor hole located at the center of the cross section of the pile to be pulled 1 or at least two anchor holes uniformly distributed along the center circumference of the cross section of the pile to be pulled 1 .

本实施例的锚孔1-1钻孔采用履带式钻机D150,单台功率75kW;同时配15m3,1.3MPa空压机,空压机功率135kW。工作效率为60m/8hr。钻完孔后,运用清水清洗干浆,并抽干其中自由水,下锚索材料2之前,运用塞子堵住孔口,防止异物进入孔内。若待拔桩仍作为工程桩,为避免履带式钻机对桩的损伤,可以采用地质钻机钻孔。如果待拔桩1的顶面在地表以下,可以通过勘察明确桩中心及直径的桩,锚孔1-1和桩体灌浆孔1-2通过套管法钻制。Anchor hole 1-1 of this embodiment is drilled using a crawler drill rig D150 with a single power of 75kW; it is also equipped with a 15m3, 1.3MPa air compressor with a power of 135kW. The working efficiency is 60m/8hr. After the hole is drilled, use clear water to clean the dry slurry, and drain the free water therein. Before lowering the anchor cable material 2, use a plug to block the hole to prevent foreign matter from entering the hole. If the piles to be pulled are still used as engineering piles, in order to avoid damage to the piles by crawler drilling rigs, geological drilling rigs can be used to drill holes. If the top surface of the pile to be pulled 1 is below the surface, the pile center and diameter of the pile can be determined through investigation, and the anchor hole 1-1 and the pile body grouting hole 1-2 are drilled by the casing method.

3)将锚索材料2的一端下放至锚孔1-1底部,其另一端露出待拔桩1顶部,或者下放至咬合桩、承台桩或打入桩等等桩中的锚孔的锚索材料2的另一端露出地表。3) One end of the anchor cable material 2 is lowered to the bottom of the anchor hole 1-1, and the other end is exposed to the top of the pile 1 to be pulled out, or the anchor is lowered to the anchor hole in the occlusal pile, cap pile or driven pile, etc. The other end of cable material 2 exposes the ground surface.

4)向锚孔1-1灌注第一浆体,待第一浆体固化并达到设定强度后,将锚索材料2固定于待拔桩1内形成锚杆;4) Pour the first slurry into the anchor hole 1-1, and after the first slurry solidifies and reaches the set strength, fix the anchor cable material 2 in the pile to be pulled out 1 to form an anchor rod;

本实施例的锚孔1-1的深度和锚杆的长度小于待拔桩1的长度并大于锚杆的最小锚固长度,锚杆的最小锚固长度L按下式计算:The depth of the anchor hole 1-1 of the present embodiment and the length of the anchor rod are less than the length of the pile 1 to be pulled and greater than the minimum anchor length of the anchor rod, and the minimum anchor length L of the anchor rod is calculated as follows:

式中,a为安全系数;σ为锚索材料强度;A为锚索材料截面面积;d为锚孔直径;τ为锚杆与孔壁抗剪强度。In the formula, a is the safety factor; σ is the strength of the anchor cable material; A is the cross-sectional area of the anchor cable material; d is the diameter of the anchor hole; τ is the shear strength of the anchor rod and the hole wall.

5)在起拔之前,可以灌注大量的水体,对拔桩1的桩底进行软化、平衡内外大气压等,然后通过起吊设备提升锚索材料2的另一端以拔起待拔桩1,在拔起待拔桩1的过程中(本实施例从拔起产生明显竖向位移后,可定为10cm,当然也可以定为其它尺寸),通过桩体灌浆孔1-2回灌第二浆体,使得第二浆体渗入待拔桩1底部的桩周土体,并将土体与待拔桩1连为整体。5) Before pulling out, a large amount of water can be injected to soften the pile bottom of the pulling pile 1, balance the internal and external atmospheric pressure, etc., and then lift the other end of the anchor cable material 2 by lifting equipment to pull up the pile 1 to be pulled out. During the process of raising the pile 1 to be pulled out (in this embodiment, after the obvious vertical displacement is generated from the pulling up, it can be set to 10cm, and of course it can also be set to other sizes), the second grout is refilled through the pile body grouting hole 1-2 , so that the second slurry penetrates into the soil around the pile at the bottom of the pile to be pulled 1, and connects the soil with the pile to be pulled 1 as a whole.

可以将帷幕灌浆方法运用于桩的回灌,提高回灌质量;针对待拔桩1的桩周土体稳定性差的,与周边建筑物近的情况,可以采用边拔边灌,甚至双浆液固结灌浆。The curtain grouting method can be applied to the recharging of piles to improve the quality of recharging; for the poor stability of the soil around the pile 1 to be pulled out, and the situation that it is close to the surrounding buildings, side pulling and side grouting, or even double grout liquid solidification can be used. Knot grouting.

针对待拔桩1相邻的多根桩,为避免灌浆过程中,将体将相邻桩连接起来,影响下一根桩的起拔,需要同桩同桩灌注。For the multiple piles adjacent to pile 1 to be pulled out, in order to avoid connecting the adjacent piles during the grouting process and affecting the pulling out of the next pile, it is necessary to grout the same pile with the same pile.

为了避免回灌对周边桩的起拔,可以回灌抗拉、剪强度极低的胶凝材料,仅起到填充作用。In order to avoid the uplifting of the surrounding piles by recharging, the cementitious material with extremely low tensile and shear strength can be refilled, which only plays a filling role.

采用商品砂浆,泵车进行回灌,针对灌浆孔,可以放置一根出气、出水管至桩底,桩顶通过漏斗进行快速灌浆,灌浆时桩底水、气通过通气、水孔排出桩顶,实现桩底快速、可靠灌浆。Commercial mortar is used for recharging by pump truck. For the grouting hole, an air outlet and water outlet pipe can be placed to the bottom of the pile, and the top of the pile can be quickly grouted through the funnel. When grouting, the water and air at the bottom of the pile are discharged from the top of the pile through the ventilation and water holes. Realize rapid and reliable grouting at the bottom of the pile.

本实施例的在步骤1)中,在待拔桩1附近的其它桩上或待拔桩周边的土体上设有工作平台3;工作平台3可以是钢筋混凝土平台、钢结构框架平台或组合结构平台,也可以是沉井平台,等等。In step 1) of the present embodiment, a working platform 3 is provided on other piles near the pile to be pulled out 1 or on the soil around the pile to be pulled out; the working platform 3 can be a reinforced concrete platform, a steel structure frame platform or a combination Structural platform, also can be caisson platform, etc.

为了快速分解混凝土,实现待拔桩1的上部桩体拆除,将拔桩工程顺利转向下一工序、下一根桩:In order to quickly decompose the concrete and realize the removal of the upper pile body of the pile to be pulled 1, the pile pulling project will be smoothly transferred to the next process and the next pile:

本实施例在步骤2)中,在待拔桩1的顶部钻制向其底部延伸的静态爆破孔1-3。In step 2) of this embodiment, a static blast hole 1-3 extending to the bottom of the pile 1 to be extracted is drilled at the top.

本实施例在步骤5)中,在通过起吊设备提升锚索材料2的另一端以拔起桩后,先在静态爆破孔1-3中倒入破碎剂并用快硬性水泥堵住静态爆破孔1-3的孔口12-18小时,然后通过破碎设备进行桩体破碎。In step 5) of this embodiment, after the other end of the anchor cable material 2 is lifted by the hoisting equipment to pull up the pile, the breaker is first poured into the static blast hole 1-3 and the static blast hole 1 is blocked with rapid hardening cement. -3 orifice for 12-18 hours, and then the pile body is crushed by crushing equipment.

静态爆破孔1-3是在需破除部位提前钻制出,呈“十”字型分布。破碎剂采用SCA-2型(无声破碎剂),适用于10-25℃环境,按每袋5公斤破碎剂与1.5升水调配,搅拌后,保证破碎剂完全溶解到水中成了浆体。浆体必须在搅拌后10-15分钟内倒入静态爆破孔1-3内,装填到离孔口15mm处,将浆体倒入孔中并在孔中搅动,以确保钻孔中没有气孔;填完后用快硬性水泥堵住孔口;12-18小时后可以达到效果。Static blast holes 1-3 are drilled in advance at the site to be demolished, and are distributed in a "ten" shape. The crushing agent adopts SCA-2 type (silent crushing agent), which is suitable for the environment of 10-25°C. Each bag is prepared with 5 kg of crushing agent and 1.5 liters of water. After stirring, ensure that the crushing agent is completely dissolved in water to form a slurry. The slurry must be poured into the static blast hole 1-3 within 10-15 minutes after stirring, filled to a distance of 15mm from the hole, pour the slurry into the hole and stir in the hole to ensure that there are no air holes in the drilled hole; After filling, plug the hole with rapid hardening cement; the effect can be achieved after 12-18 hours.

为了简单可靠对待拔桩1连续拔起,本实施例在在步骤5)中,起吊设备是设于工作平台3上的穿心千斤顶5,穿心千斤顶5通过反力架4安装固定在钢筋混凝土平台、钢结构框架平台或组合结构平台上;当需要对整体位于地表以下的桩进行拔出时,穿心千斤顶5固定在沉井平台上,等等。穿心千斤顶5持续张拉锚索材料2的另一端以连续拔起待拔桩1。In order to be simple and reliable for the continuous pulling up of the pile 1, in step 5) of the present embodiment, the hoisting device is a through-hole jack 5 arranged on the working platform 3, and the through-hole jack 5 is installed and fixed on the reinforced concrete by the reaction force frame 4 platform, a steel structure frame platform or a combined structure platform; when it is necessary to pull out the piles located below the surface as a whole, the through-hole jack 5 is fixed on the caisson platform, and so on. The core-through jack 5 continuously tensions the other end of the anchor cable material 2 to continuously pull up the pile 1 to be pulled out.

为了确保灌浆密实,本实施例的锚索材料2上设有出口分别位于锚孔1-1底部、中部和上部处的三根灌浆管;采用压力灌浆向锚孔1-1内灌注第一浆体,第一浆体是由PO52.5水泥、水泥浆孔道压浆剂和水混合而成的浆体,第一浆体的水胶比为0.35~0.45;采用砂浆搅拌机和注浆泵进行压力灌浆。压浆前可以进行砂浆块制作试验,确保试块3d强度达到25MPa,10d强度达到30MPa。当然也可以采用常态灌浆管,第一浆体还可以是砂浆或砂,等等。In order to ensure that the grouting is dense, the anchor cable material 2 of this embodiment is provided with three grouting pipes whose outlets are respectively located at the bottom, middle and upper part of the anchor hole 1-1; the first grout is poured into the anchor hole 1-1 by pressure grouting , the first slurry is a slurry made by mixing PO52.5 cement, cement slurry channel grouting agent and water. The water-binder ratio of the first slurry is 0.35-0.45; the mortar mixer and grouting pump are used for pressure grouting . Before grouting, the mortar block production test can be carried out to ensure that the 3d strength of the test block reaches 25MPa, and the 10d strength reaches 30MPa. Of course, normal grouting pipes can also be used, and the first slurry can also be mortar or sand, and so on.

采用砂浆搅拌机和注浆泵进行压力灌浆(灌注第一浆体)。灌注第一浆体由底部向上灌浆,当灌至上一个个灌浆管时,开启上一灌浆管,直至灌至设计位置。每次灌浆制作3组水泥浆试块,采用砂浆块,待3d、7d压制试块,待强度达到后可以进行提升。Pressure grouting (injection of the first slurry) is carried out using a mortar mixer and a grouting pump. The first grout is poured upwards from the bottom, and when it reaches the previous grouting pipe, open the previous grouting pipe until it reaches the designed position. Make 3 sets of cement slurry test blocks for each grouting, use mortar blocks, press the test blocks after 3 days and 7 days, and lift them after the strength is reached.

如图1、图2和图3所示,本实施例的拔桩回灌系统,用于上述的拔桩回灌方法中,该拔桩回灌系统设置于固定在土体中并顶部曝露的待拔桩1附近,包括多根高强度锚索材料2和起吊设备。As shown in Fig. 1, Fig. 2 and Fig. 3, the pile pulling refilling system of this embodiment is used in the above-mentioned pile pulling refilling method. The vicinity of the pile 1 to be pulled includes a plurality of high-strength anchor cable materials 2 and lifting equipment.

本实施例的拔桩回灌系统的待拔桩1也是埋在在土体中摩擦桩、部分嵌岩的端承桩或是埋于地表以下一定深度的咬合桩、承台桩和打入桩,摩擦桩或端承桩的头部曝露在地表。The piles 1 to be pulled out of the pile pulling recharge system in this embodiment are also friction piles buried in the soil, end-bearing piles partially embedded in rocks, or occlusal piles, cap piles and driven piles buried at a certain depth below the surface , the heads of friction piles or end-bearing piles are exposed to the surface.

本实施例的拔桩回灌系统的锚索材料2也可以是金属硬质或软质材料制成,例如:粘结钢绞束、预应力钢绞线、预应力钢绞束、高强钢丝、高强钢丝绳或高强钢筋,等等;也可以是非金属硬质或软质材料制成,例如:纤维、塑料或尼龙,等等。The anchor cable material 2 of the pile pulling recharge system of the present embodiment can also be made of metal hard or soft materials, such as: bonded steel strands, prestressed steel strands, prestressed steel strands, high-strength steel wires, High-strength steel wire rope or high-strength steel bar, etc.; also can be made of non-metal hard or soft material, such as: fiber, plastic or nylon, etc.

待拔桩1的顶部制有向待拔桩内的底部延伸的锚孔1-1,待拔桩1上制有贯通其其顶面和底面的桩体灌浆孔1-2,锚索材料2的一端设于锚孔1-1底部,锚索材料2的另一端露出待拔桩1顶部;本实施例的锚孔1-1是位于待拔桩1横截面中心的一个锚孔或沿待拔桩1横截面中心周圈均布的至少两个锚孔。The top of the pile to be pulled 1 is formed with an anchor hole 1-1 extending to the bottom of the pile to be pulled, and the pile to be pulled 1 is formed with a pile body grouting hole 1-2 passing through its top surface and bottom surface, and the anchor cable material 2 One end of the anchor hole 1-1 is located at the bottom of the anchor cable material 2, and the other end of the anchor cable material 2 is exposed at the top of the pile to be pulled out; At least two anchor holes uniformly distributed around the center of the cross-section of the pulled pile 1 .

锚孔1-1内灌注有固化后用于将锚索材料2固定于待拔桩1内以形成锚杆的第一浆体,起吊设备用于提升锚索材料2的另一端以拔起待拔桩1,桩体灌浆孔1-2用于在拔桩过程中回灌第二浆体。The anchor hole 1-1 is poured with the first slurry that is solidified and used to fix the anchor cable material 2 in the pile 1 to form the anchor rod, and the lifting device is used to lift the other end of the anchor cable material 2 to pull out the pile to be pulled out. Pulling out the pile 1, the pile body grouting holes 1-2 are used for refilling the second slurry during the pile pulling out process.

本实施例的拔桩回灌系统的锚孔1-1的深度和锚杆的长度也小于待拔桩1的长度并大于锚杆的最小锚固长度,锚杆的最小锚固长度L按下式计算:The depth of the anchor hole 1-1 and the length of the anchor rod of the pile pulling recharge system of this embodiment are also smaller than the length of the pile to be pulled 1 and greater than the minimum anchor length of the anchor rod. The minimum anchor length L of the anchor rod is calculated by the following formula :

式中,a为安全系数;σ为锚索材料强度;A为锚索材料截面面积;d为锚孔直径;τ为锚杆与孔壁抗剪强度。In the formula, a is the safety factor; σ is the strength of the anchor cable material; A is the cross-sectional area of the anchor cable material; d is the diameter of the anchor hole; τ is the shear strength of the anchor rod and the hole wall.

本实施例的待拔桩1的顶部制有向待拔桩内的底部延伸的静态爆破孔1-3;静态爆破孔1-3中倒入有破碎剂并封堵有快硬性水泥块。The top of the pile 1 to be pulled out of the present embodiment is formed with a static blast hole 1-3 extending toward the bottom of the pile to be pulled out; the static blast hole 1-3 is poured with breaking agent and blocked with rapid hardening cement block.

本实施例的待拔桩1附近的其它桩上或待拔桩1周边的土体上设有工作平台3。起吊设备是设于工作平台3上的穿心千斤顶5,工作平台3是钢筋混凝土平台、钢结构框架平台、组合结构平台或沉井平台,等等。In this embodiment, a working platform 3 is provided on other piles near the pile to be pulled out 1 or on the soil around the pile to be pulled out 1 . The hoisting device is a center-through jack 5 located on the working platform 3, and the working platform 3 is a reinforced concrete platform, a steel structure frame platform, a composite structure platform or a caisson platform, or the like.

穿心千斤顶5通过反力架4安装固定在钢筋混凝土平台、钢结构框架平台或组合结构平台上。当需要对整体位于地表以下的桩进行拔出时,穿心千斤顶5固定在沉井平台上,等等。穿心千斤顶5用于持续张拉锚索材料2的另一端以连续拔起待拔桩1。The through-hole jack 5 is installed and fixed on the reinforced concrete platform, the steel structure frame platform or the combined structure platform through the reaction force frame 4 . When it is necessary to pull out the pile that is located below the ground surface as a whole, the through-hole jack 5 is fixed on the caisson platform, and the like. The core-through jack 5 is used for continuously tensioning the other end of the anchor cable material 2 to continuously pull up the pile 1 to be pulled out.

本实施例的拔桩回灌系统的锚索材料2上也设有出口分别位于锚孔1-1底部、中部和上部处的三根灌浆管。The anchor cable material 2 of the pile pulling refilling system of this embodiment is also provided with three grouting pipes whose outlets are respectively located at the bottom, middle and upper part of the anchor hole 1-1.

实施例二Embodiment two

本实施例的拔桩回灌方法,是在实施例一基础上的改进,与实施例一的不同之处在于:The pile pulling method of the present embodiment is an improvement on the basis of the first embodiment, and the difference from the first embodiment is:

本实施例需要提升的待拔桩1总长24m,桩径1500mm,该桩需提升高度达7-8m,占该待拔桩1的总长24m的30%。经过计算,拔桩力设计荷载为8000kN,校核荷载为10000kN。The total length of the pile 1 to be pulled out that needs to be promoted in this embodiment is 24m, and the pile diameter is 1500mm. After calculation, the design load of the pile pulling force is 8000kN, and the check load is 10000kN.

这样,锚索材料2采用选用4束CPS15A-12型剪力分散型锚索。每束CPS15A-14型剪力分散型锚索采用14-φ15.24高强度、低松弛钢绞线,抗拉强度为1860MPa。In this way, the anchor cable material 2 adopts 4 bundles of CPS15A-12 type shear dispersion anchor cables. Each bundle of CPS15A-14 shear dispersion type anchor cable adopts 14-φ15.24 high-strength, low-relaxation steel strands with a tensile strength of 1860MPa.

本实施例的起吊设备还是采用穿心千斤顶5,选用4台4000kN穿心千斤顶5作为提升动力设备,按0.8效率考虑,总提升能力达12800kN。The hoisting equipment of this embodiment still adopts the core-through jack 5, and selects four 4000kN core-through jacks 5 as the lifting power equipment. Considering the efficiency of 0.8, the total lifting capacity reaches 12800kN.

放线之前,首先将反力架4位置编制于地坪上,然后根据反力架4可布设位置确定锚孔1-1位置。本实施例的锚孔1-1是中心分布在边长为60cm的正方形四个角点的四个锚孔,锚孔1-1孔径150mm,正方形的边长分别与反力架大梁平行与垂直。Before laying out the line, first compile the position of the reaction force frame 4 on the floor, and then determine the position of the anchor hole 1-1 according to the laying position of the reaction force frame 4. The anchor holes 1-1 of this embodiment are four anchor holes centered at the four corners of a square with a side length of 60 cm. The anchor holes 1-1 have a diameter of 150 mm, and the side lengths of the square are respectively parallel and perpendicular to the reaction force frame girder. .

由于桩周受挡墙、渠壁等连接影响,可以采用履带式钻机D150,将该连接通过钻孔消除。消除该连接时,钻孔范围适当加大、加深,防止强连接以下范围存在较大的扩孔与塌孔。强连接消除选择与锚孔1-1同期进行。Since the pile circumference is affected by connections such as retaining walls and canal walls, the crawler drilling rig D150 can be used to eliminate the connections through drilling. When this connection is eliminated, the drilling range should be appropriately increased and deepened to prevent large reaming and collapse of holes below the strong connection. Strong connection elimination selection was carried out at the same time as anchor hole 1-1.

桩周与土层间的摩阻部分消除,是通过在桩周钻制一定数量的孔、适当冲水实现消除桩周磨阻。孔内下直径50PVC花管,一方面防止塌孔,另一方面用于通过桩体灌浆孔1-2回灌第二浆体时,桩体灌浆孔底的水体通过桩体灌浆孔底从桩顶孔口溢出;第二浆体渗入待拔桩1底部的桩周土体,将土体与待拔桩1连为整体,加固桩周土体,恢复待拔桩1的作用。The friction between the pile and the soil layer is partially eliminated by drilling a certain number of holes around the pile and flushing water properly to eliminate the friction around the pile. The lower diameter of the hole is 50PVC flower tube, on the one hand, to prevent the hole from collapsing, and on the other hand, when the second slurry is refilled through the grouting hole 1-2 of the pile body, the water at the bottom of the grouting hole of the pile body passes through the bottom of the grouting hole of the pile body from the pile. The top hole overflows; the second slurry penetrates into the soil around the pile at the bottom of the pile to be pulled out, connects the soil with the pile to be pulled out as a whole, strengthens the soil around the pile, and restores the function of the pile to be pulled out.

可以在建筑物沉降观测的基础上,确定回灌时机、回灌压力。对于建筑物安全,回灌宜早不宜迟,对于相邻桩提升具有挤密效果,宜迟不宜早。回灌压力过大,易造成周边建筑物上升,本次消阻范围相对较小,采用不超过1MPa的低压回灌。On the basis of building settlement observation, the recharge timing and recharge pressure can be determined. For building safety, recharging should be performed sooner rather than later, and for the lifting of adjacent piles to have a compacting effect, it should be later rather than earlier. If the recharge pressure is too high, it will easily cause the surrounding buildings to rise. This time, the resistance reduction range is relatively small, and a low pressure recharge of no more than 1MPa is used.

拔桩分为以下几个阶段,将预估提升力分为10级,每级观察10钟,每分钟测一次数据,分析桩顶位移随时间变化与随荷载变化关系。同时监测地表沉降位移、结构应力与变形。预估提升力为8000kN,具体荷载分级为800kN、1600kN,2400kN,直至启动荷载。实施例三Pile pulling is divided into the following stages. The estimated lifting force is divided into 10 levels, each level is observed for 10 minutes, and the data is measured every minute to analyze the relationship between the displacement of the pile top with time and the change with load. Simultaneously monitor surface settlement displacement, structural stress and deformation. The estimated lifting force is 8000kN, and the specific load is graded as 800kN, 1600kN, 2400kN until the starting load. Embodiment three

本实施例的拔桩回灌方法,是在实施例一和实施例二基础上的改进,与上述实施例的不同之处在于:本实施例在在步骤5)中,起吊设备采用设于工作平台3上的吊机或卷扬机,吊机或卷扬机持续张拉锚索材料2的另一端以连续拔起待拔桩1。吊机或卷扬机设于钢筋混凝土平台、钢结构框架平台或组合结构平台上。The pile extraction method of this embodiment is an improvement on the basis of Embodiment 1 and Embodiment 2. The difference from the above embodiment is that in this embodiment, in step 5), the lifting device adopts a The crane or winch on the platform 3 continuously pulls the other end of the anchor cable material 2 to continuously pull up the pile 1 to be pulled out. The crane or winch is set on the reinforced concrete platform, the steel structure frame platform or the combined structure platform.

本发明不局限于上述实施例。凡采用等同替换形成的技术方案,均落在本发明要求的保护范围。The present invention is not limited to the above-described embodiments. All technical solutions formed by equivalent replacements fall within the scope of protection required by the present invention.

Claims (10)

1.一种拔桩回灌方法,其特征在于包括以下步骤:1. A pile pulling method for recharging is characterized in that it may further comprise the steps: 1)经前处理先使待拔桩的顶部曝露,同时备设多根高强度锚索材料以及起吊设备;1) After pretreatment, the top of the pile to be pulled is first exposed, and multiple high-strength anchor cable materials and lifting equipment are equipped at the same time; 2)在待拔桩的顶部钻制向待拔桩内的底部延伸的锚孔,在待拔桩上钻制贯通其顶面和底面的桩体灌浆孔;2) drilling an anchor hole extending to the bottom of the pile to be pulled out at the top of the pile to be pulled out, and drilling a pile body grouting hole through the top surface and the bottom surface of the pile to be pulled out; 3)将所述锚索材料的一端下放至所述锚孔底部,其另一端露出待拔桩顶部;3) lowering one end of the anchor cable material to the bottom of the anchor hole, the other end of which is exposed to the top of the pile to be pulled out; 4)向所述锚孔灌注第一浆体,待所述第一浆体固化并达到设定强度后,将所述锚索材料固定于所述待拔桩内形成锚杆;4) pouring the first slurry into the anchor hole, and after the first slurry solidifies and reaches a set strength, the anchor cable material is fixed in the pile to be pulled out to form an anchor rod; 5)通过起吊设备提升所述锚索材料的另一端以拔起待拔桩,在拔起待拔桩的过程中,通过桩体灌浆孔回灌第二浆体,使得第二浆体渗入待拔桩底部的桩周土体,并将土体与待拔桩连为整体。5) lifting the other end of the anchor cable material by lifting equipment to pull up the pile to be pulled out, and during the process of pulling up the pile to be pulled out, refill the second slurry through the grouting hole of the pile body, so that the second slurry penetrates into the pile to be pulled out. Pull out the soil around the pile at the bottom of the pile, and connect the soil with the pile to be pulled out as a whole. 2.如权利要求1所述的拔桩回灌方法,其特征在于:在所述步骤2)中,在所述待拔桩的顶部钻制向其底部延伸的静态爆破孔;在所述步骤5)中,在通过起吊设备提升所述锚索材料的另一端以拔起桩后,先在静态爆破孔中倒入破碎剂并用快硬性水泥堵住静态爆破孔的孔口12-18小时,然后通过破碎设备进行桩体破碎。2. pile pulling method for recharging as claimed in claim 1, is characterized in that: in described step 2), at the top of described pile to be pulled out, drill the static blast hole that extends toward its bottom; 5), after the other end of the anchor cable material is lifted by lifting equipment to pull up the pile, the breaker is first poured into the static blast hole and the opening of the static blast hole is blocked with rapid hardening cement for 12-18 hours, Then the pile body is crushed by crushing equipment. 3.如权利要求1或2所述的拔桩回灌方法,其特征在于:在所述步骤1)中,在所述待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台;在所述步骤5)中,所述起吊设备是设于工作平台上的穿心千斤顶、吊机或卷扬机,所述穿心千斤顶、吊机或卷扬机持续张拉锚索材料的另一端以连续拔起所述待拔桩。3. The pile pulling recharge method according to claim 1 or 2, characterized in that: in the step 1), on other piles near the pile to be pulled or on the soil around the pile to be pulled There is a working platform; in the step 5), the hoisting device is a through-hole jack, a crane or a winch located on the working platform, and the other part of the continuous tensioning anchor cable material is provided by the through-hole jack, a crane or a winch. One end is to continuously pull up the pile to be pulled out. 4.如权利要求3所述的拔桩回灌方法,其特征在于:所述工作平台是钢筋混凝土平台、钢结构框架平台或组合结构平台;所述穿心千斤顶通过反力架安装固定在钢筋混凝土平台、钢结构框架平台或组合结构平台上;所述吊机或卷扬机设于钢筋混凝土平台、钢结构框架平台或组合结构平台上。4. The pile pulling recharge method according to claim 3, characterized in that: the working platform is a reinforced concrete platform, a steel structure frame platform or a combined structure platform; On a concrete platform, a steel structure frame platform or a combined structure platform; the crane or winch is arranged on a reinforced concrete platform, a steel structure frame platform or a combined structure platform. 5.如权利要求3所述的拔桩回灌方法,其特征在于:所述工作平台是沉井平台,所述穿心千斤顶固定在沉井平台上。5. The pile pulling method according to claim 3, characterized in that: the working platform is a caisson platform, and the piercing jack is fixed on the caisson platform. 6.如权利要求1或2所述的拔桩回灌方法,其特征在于:所述锚孔的深度和锚杆的长度小于所述待拔桩的长度并大于所述锚杆的最小锚固长度,所述锚杆的最小锚固长度L按下式计算:6. The pile pulling recharge method according to claim 1 or 2, characterized in that: the depth of the anchor hole and the length of the anchor rod are less than the length of the pile to be pulled and greater than the minimum anchoring length of the anchor rod , the minimum anchorage length L of the anchor rod is calculated as follows: LL ≥&Greater Equal; aa σσ ** AA ππ dd ττ 式中,a为安全系数;σ为锚索材料强度;A为锚索材料截面面积;d为锚孔直径;τ为锚杆与孔壁抗剪强度。In the formula, a is the safety factor; σ is the strength of the anchor cable material; A is the cross-sectional area of the anchor cable material; d is the diameter of the anchor hole; τ is the shear strength of the anchor rod and the hole wall. 7.如权利要求1或2所述的拔桩回灌方法,其特征在于:所述锚索材料上设有出口分别位于锚孔底部、中部和上部处的三根灌浆管;采用压力灌浆向锚孔内灌注第一浆体,所述第一浆体是由PO52.5水泥、水泥浆孔道压浆剂和水混合而成的浆体,所述第一浆体的水胶比为0.35~0.45;采用砂浆搅拌机和注浆泵进行压力灌浆。7. The pile pulling method according to claim 1 or 2, wherein: the anchor cable material is provided with three grouting pipes whose outlets are located at the bottom, middle and upper part of the anchor hole; The first slurry is poured into the hole, the first slurry is a slurry formed by mixing PO52.5 cement, cement slurry hole grouting agent and water, and the water-binder ratio of the first slurry is 0.35-0.45 ; Use mortar mixer and grouting pump for pressure grouting. 8.一种拔桩回灌系统,用于权利要求1所述的拔桩回灌方法中,该拔桩回灌系统设置于固定在土体中并顶部曝露的待拔桩附近,包括多根高强度锚索材料和起吊设备,其特征在于:所述待拔桩的顶部制有向待拔桩内的底部延伸的锚孔,所述待拔桩上制有贯通其顶面和底面的桩体灌浆孔,所述锚索材料的一端设于所述锚孔底部,所述锚索材料的另一端露出待拔桩顶部;所述锚孔内灌注有固化后用于将锚索材料固定于待拔桩内以形成锚杆的第一浆体,所述起吊设备用于提升所述锚索材料的另一端以拔起待拔桩,所述桩体灌浆孔用于在拔桩过程中回灌第二浆体。8. A pile pulling refilling system, used in the pile pulling refilling method described in claim 1, the pile pulling refilling system is arranged near the piles to be pulled out that are fixed in the soil and exposed at the top, including a plurality of High-strength anchor cable material and lifting equipment, it is characterized in that: the top of described pile to be pulled out is shaped on the anchor hole that extends to the bottom in the pile to be pulled out, and the pile that runs through its top surface and bottom surface is shaped on described pile to be pulled out body grouting hole, one end of the anchor cable material is arranged at the bottom of the anchor hole, and the other end of the anchor cable material is exposed at the top of the pile to be pulled; The first slurry of the anchor rod is formed in the pile to be pulled out. The lifting device is used to lift the other end of the anchor cable material to pull up the pile to be pulled out. Fill the second slurry. 9.如权利要求8所述的拔桩回灌系统,其特征在于:所述待拔桩的顶部制有向待拔桩内的底部延伸的静态爆破孔;所述静态爆破孔中倒入有破碎剂并封堵有快硬性水泥块。9. The pile pulling recharge system as claimed in claim 8, characterized in that: the top of the pile to be pulled is shaped on a static blast hole extending toward the bottom of the pile to be pulled; Breaking agent and blocked with rapid hardening cement blocks. 10.如权利要求8所述的拔桩回灌系统,其特征在于:所述待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台。10. The pile pulling recharge system according to claim 8, characterized in that: a working platform is provided on other piles near the pile to be pulled or on the soil around the pile to be pulled.
CN201710213872.XA 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system Active CN106968252B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710213872.XA CN106968252B (en) 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710213872.XA CN106968252B (en) 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system

Publications (2)

Publication Number Publication Date
CN106968252A true CN106968252A (en) 2017-07-21
CN106968252B CN106968252B (en) 2022-08-09

Family

ID=59336156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710213872.XA Active CN106968252B (en) 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system

Country Status (1)

Country Link
CN (1) CN106968252B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107421816A (en) * 2017-08-10 2017-12-01 北京林业大学 A kind of stratum splitting drag Rapid measuring and its assay method
CN108894224A (en) * 2018-08-03 2018-11-27 中冶沈勘工程技术有限公司 A kind of method for pulling out of static pressure pipe pile
CN113737796A (en) * 2021-09-07 2021-12-03 江苏兴宇建设集团有限公司 Construction method for high-pressure water flushing assisted pile driving and pile pulling synchronous grouting of steel plate pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1482309A (en) * 2003-06-12 2004-03-17 上海隧道工程股份有限公司 A drill hole grout pile drag reduction extraction process
CN101886390A (en) * 2010-06-12 2010-11-17 中铁十六局集团有限公司 All casing static pressure pile pulling technology in narrow space
CN204475338U (en) * 2015-02-05 2015-07-15 温州荣强海洋科技有限公司 A kind of single sleeve pipe is without the pile pulling device of water burst no swell mud
CN204662442U (en) * 2015-03-27 2015-09-23 江苏高速公路工程养护有限公司 Highway barrier hydraulic pressure inner bearing type gets an equipment
CN105442605A (en) * 2015-11-20 2016-03-30 常州第一建筑集团有限公司 Construction method for drawing out prestress high concrete (PHC) pile and reusing PHC pile for retaining in deep excavation
CN206902712U (en) * 2017-04-01 2018-01-19 南京瑞迪建设科技有限公司 Pile pulling recharge system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1482309A (en) * 2003-06-12 2004-03-17 上海隧道工程股份有限公司 A drill hole grout pile drag reduction extraction process
CN101886390A (en) * 2010-06-12 2010-11-17 中铁十六局集团有限公司 All casing static pressure pile pulling technology in narrow space
CN204475338U (en) * 2015-02-05 2015-07-15 温州荣强海洋科技有限公司 A kind of single sleeve pipe is without the pile pulling device of water burst no swell mud
CN204662442U (en) * 2015-03-27 2015-09-23 江苏高速公路工程养护有限公司 Highway barrier hydraulic pressure inner bearing type gets an equipment
CN105442605A (en) * 2015-11-20 2016-03-30 常州第一建筑集团有限公司 Construction method for drawing out prestress high concrete (PHC) pile and reusing PHC pile for retaining in deep excavation
CN206902712U (en) * 2017-04-01 2018-01-19 南京瑞迪建设科技有限公司 Pile pulling recharge system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107421816A (en) * 2017-08-10 2017-12-01 北京林业大学 A kind of stratum splitting drag Rapid measuring and its assay method
CN108894224A (en) * 2018-08-03 2018-11-27 中冶沈勘工程技术有限公司 A kind of method for pulling out of static pressure pipe pile
CN113737796A (en) * 2021-09-07 2021-12-03 江苏兴宇建设集团有限公司 Construction method for high-pressure water flushing assisted pile driving and pile pulling synchronous grouting of steel plate pile

Also Published As

Publication number Publication date
CN106968252B (en) 2022-08-09

Similar Documents

Publication Publication Date Title
CN102678134B (en) Collapse and sink intrusion limit construction method for treating wind accumulated sand loess tunnel through stride shed pipe
CN106638673B (en) A kind of construction method of compound retaining structure
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN104389628B (en) Landslide location tunnel reinforcement device and reinforced construction method
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN101761237B (en) Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN105178979A (en) Supporting structure of tunnel in bias salt cavity environment and construction method of supporting structure
CN101906780A (en) A steel pipe pile anchor cable protection and reinforcement method
CN110106889A (en) A kind of deep basal pit perfusion slope protection pile adds cable bolting construction
CN106907157B (en) A kind of shield machine normal pressure opens the cabin operation construction method
CN106948347A (en) Pile extracting method and pile pulling system
CN115596453A (en) "Micro brush slope" entry method for long-distance side of tunnel passing through accumulation
CN206570811U (en) Existing bridge pile pulling device is passed through in weak soil shield driving area
CN105862862B (en) A kind of large diameter pile buries hammer Refloatation method
CN106968252A (en) Pile pulling recharge method and pile pulling recharge system
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN105951874A (en) Retaining wall reinforcing structure and construction method thereof
CN218175851U (en) Supporting construction of prestressed anchorage cable for soft soil stratum
CN206902712U (en) Pile pulling recharge system
CN108842792A (en) A kind of layering is interior to draw anchor pole and construction method with being lifted discharging type
CN206902710U (en) Retaining wall and counter-force open caisson platform pile pulling system
CN206928296U (en) Pile pulling system
CN107059872B (en) Inclined cable pile pulling method and inclined cable pile pulling system
CN205712171U (en) A kind of retaining wall reinforcement structure

Legal Events

Date Code Title Description
PB01 Publication
CB03 Change of inventor or designer information

Inventor after: Liu Haixiang

Inventor after: Chen Liang

Inventor after: Ke Minyong

Inventor after: Tang Yunqing

Inventor after: Zhang Min

Inventor after: Lu Wenyan

Inventor after: Long Zhiyong

Inventor after: Chen Xining

Inventor after: Wang Lingjun

Inventor before: Liu Haixiang

Inventor before: Chen Liang

Inventor before: Ke Minyong

Inventor before: Tang Yunqing

Inventor before: Lu Wenyan

Inventor before: Long Zhiyong

Inventor before: Chen Xining

Inventor before: Wang Lingjun

CB03 Change of inventor or designer information
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant