CN106940411B - A kind of single-phase ground fault line selecting method of small-electric current grounding system - Google Patents

A kind of single-phase ground fault line selecting method of small-electric current grounding system Download PDF

Info

Publication number
CN106940411B
CN106940411B CN201710263991.6A CN201710263991A CN106940411B CN 106940411 B CN106940411 B CN 106940411B CN 201710263991 A CN201710263991 A CN 201710263991A CN 106940411 B CN106940411 B CN 106940411B
Authority
CN
China
Prior art keywords
route
ground
historical failure
ground path
history
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710263991.6A
Other languages
Chinese (zh)
Other versions
CN106940411A (en
Inventor
周福举
康冬波
孙元
房雪涛
王磊
高燕
王秀茹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suqian Electric Power Design Institute Co Ltd
Suqian Power Supply Co Of State Grid Jiangsu Electric Power Co
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Suqian Electric Power Design Institute Co Ltd
Suqian Power Supply Co Of State Grid Jiangsu Electric Power Co
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suqian Electric Power Design Institute Co Ltd, Suqian Power Supply Co Of State Grid Jiangsu Electric Power Co, State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd filed Critical Suqian Electric Power Design Institute Co Ltd
Priority to CN201710263991.6A priority Critical patent/CN106940411B/en
Publication of CN106940411A publication Critical patent/CN106940411A/en
Application granted granted Critical
Publication of CN106940411B publication Critical patent/CN106940411B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/08Locating faults in cables, transmission lines, or networks
    • G01R31/081Locating faults in cables, transmission lines, or networks according to type of conductors
    • G01R31/086Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution networks, i.e. with interconnected conductors
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/08Locating faults in cables, transmission lines, or networks
    • G01R31/088Aspects of digital computing

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Mathematical Physics (AREA)
  • Theoretical Computer Science (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)
  • Locating Faults (AREA)

Abstract

The invention belongs to Single-phase Earth Fault of Power System processing technology fields, and what is involved is a kind of single-phase ground fault line selecting method of small-electric current grounding system.Including 1) counting same bus historical failure data;2) same bus history ground path collection is extracted;3) determine that ground path historical failure is estimated under different time scales;4) ground path historical failure is estimated into Weighted Fusion;5) it is carried out drawing road route selection according to integrated ground probability;6) same bus historical failure data updates.Electrical quantity is by the disadvantage that the factors such as grid operation mode, device parameter are influenced and cause the rate of falsely dropping high when the present invention overcomes traditional selection method due to failure, improve accuracy rate and efficiency that single-phase earthing draws road route selection, it reduces and draws road route selection number, ensure distribution to user security reliable power supply.

Description

A kind of single-phase ground fault line selecting method of small-electric current grounding system
Technical field
The invention belongs to Single-phase Earth Fault of Power System processing technology fields, and what is involved is a kind of small current neutral grounding systems Fault line selection method for single-phase-to-ground fault.
Background technique
Small current neutral grounding system is widely used in China's power distribution network at present, and when single-phase earthing occurs, fault current is smaller, and three Phase voltage keeps symmetrical, still is able to continue to power to load, but non-faulting phase voltage rises to line voltage, not to the class of insulation High user equipment easily causes phase fault, when grounding point capacitance current is more than limit value, can generate arc overvoltage, Seriously threaten power grid and equipment safety.Therefore, when single-phase earthing occurs for small current neutral grounding system, dispatcher need to judge to connect as quickly as possible Ground route, and then isolated fault.Traditional fault line selection method for single-phase-to-ground fault mainly has zero sequence drying method, zero sequence power method, bears The intelligent algorithms such as sequence current method, signal injection method and neural network, fuzzy control, evidence theory method, these methods are equal The variation of electrical quantity when dependent on failure by grid operation mode, load condition, line construction, current transformer precision, connects The factors such as place transition resistance influence, and falsely drop rate height, it is difficult to obtain ideal effect.Single-phase earth fault line selection is still at present So mainly by the artificial route selection of dispatcher, for there is the substation bus bar of a large amount of outlets, draw that road number is excessive, accident treatment time mistake Long problem is not able to satisfy requirement of the user to power supply reliability more and more.
Summary of the invention
To overcome the shortcomings of the above selection method, the present invention provides a kind of single-phase grounded malfunction in grounded system of low current route selection Method can fast and accurately find out faulty line when single-phase earthing occurs for small current neutral grounding system.
The present invention adopts the following technical solutions to achieve, a kind of single-phase grounded malfunction in grounded system of low current route selection side Method, comprising the following steps:
1) same bus historical failure data is counted;
2) same bus history ground path collection is extracted;
3) determine that ground path historical failure is estimated under different time scales;
4) ground path historical failure is estimated into Weighted Fusion;
5) it is carried out drawing road route selection according to integrated ground probability;
6) same bus historical failure data updates.
The method specific steps are as follows:
1) as unit of a bus, the historical failure data of every route on the bus is divided into single-phase earthing, route Tripping, defect processing three classes count the respectivelyxThe number of three classes permanent fault occurs for route, shape At historical failure data library, whereinIndicate single-phase earthing number,Indicate line tripping number,Indicate fault location Number is managed,x=0,1 ...,M,MGo out number of lines for the bus, and according to the actual motion of each outlet of the bus in current electric grid Situation, the line tripping of corresponding line in real-time update historical failure data libraryAnd defect processingTwo class data;
2) all routes that singlephase earth fault occurred on bus described in step 1) are extracted, history of forming Ground path collection, the number of element is denoted as in the sets of linesN
3) according to the periodic law and distribution character of fault data in step 1) historical data base, the history of step 2 is determined Ground path concentrates historical failure of the every route under long and short two different time scales to estimate, it is assumed that theiRoute exists Historical failure under long and short two time scales estimate for,i=0,1 ...,N, from the historical failure data in step 1) Is intercepted in libraryiThe statistical data of route under corresponding time scale,j=0,1,2, the calculating that historical failure is estimated Formula is
4) is determinediThe route ground connection weight that ground path historical failure is estimated under long and short two time scales,
Historical failure of the every route under different time scales is concentrated to estimate the history ground path of step 2 It is weighted fusion, predicts integrated ground probability of the every ground path under current state,
5) the integrated ground probability size predicted according to step 4) is ranked up history ground path, is formed and draws Lu Xuan Line sequence list, dispatcher carry out drawing road route selection according to the route for drawing route selection sequence list in road preferentially to concentrate history ground path, if It is unsuccessful, draw road route selection according to a conventional method in remaining route;
6) road route selection is drawn as a result, if ground path is the of history ground path collection according to step 5)iRoute, then its Corresponding singlephase earth fault dataAdd 1, if ground path is new line, more new historical ground path collection, element numberNAdd 1.
Electrical quantity is influenced to change by factors such as power grid, equipment when the present invention overcomes conventional method due to failure does not know and leads The high disadvantage of rate is falsely dropped in cause, is analysis object with the historical data that same bus breaks down, by historical failure number Analysis, Weighted Fusion according to statistics predict the integrated ground probability of history ground path, are formed and the guidance of road route selection sequence list is drawn to connect Ground route selection reduces ground connection and draws road number, shorten the earthing wire-selecting time, has good route selection effect and accuracy rate, strong guarantor Barrier distribution is securely and reliably powered.
Detailed description of the invention
Below with reference to attached drawing, the invention will be further described:
Fig. 1 is the flow chart of single-phase ground fault line selecting method of small-electric current grounding system of the present invention.
Specific embodiment
Further details of elaboration made to the present invention in the following with reference to the drawings and specific embodiments, but the invention is not limited to Following implementation.
As shown in Figure 1, single-phase ground fault line selecting method of small-electric current grounding system of the present invention the following steps are included:
Step 1, the same bus historical failure data of statistics.A large amount of production practices show that event occurs for same bus The route of barrier repeatability with higher, the type of each line failure are mainly shown as: single-phase earthing, route are jumped Lock, defect three types, three kinds of fault types are connected each other, are mutually converted, and the same failure cause may start to behave as scarce It falls into or ground connection, just develops into line tripping after a period of time, or specifically show as line tripping, it is next then show as single-phase connect Ground, therefore the historical data that three classes failure occurs for same route is all included in sample, consideration joint uses, short-term instantaneity The factors such as failure carry out data screening, reject invalid data, guarantee the accuracy and integrality of fault data.
The historical failure data of every route can be obtained from dispatch automated system D5000 or management and running log It takes, is known to those skilled in the art, details are not described herein again.As unit of a bus, by every route on the bus Historical failure data is divided into single-phase earthing, line tripping, defect processing three classes, counts respectivelyxThree classes occur for route forever The number of long property failure, history of forming Mishap Database,Indicate single-phase earthing number,Indicate line Road tripping times,Indicate defect processing number, whereinx=0,1 ...,M,MGo out number of lines for the bus.According to current electric grid In each outlet of the bus practical operation situation, the line tripping of corresponding line in real-time update historical failure data library And defect processingTwo class data.
Step 2 extracts all routes that singlephase earth fault occurred for a bus, history of forming ground path Collect, element number is denoted as in the sets of linesN
Step 3, according to the periodic law and distribution character of fault data in step 1) historical data base, determine that history is grounded Historical failure of the every route under long and short two different time scales is estimated in sets of lines.The selection of long time scale should be The periodicity of fault data is held, the ground line number under the time scale should concentrate all elements comprising history ground path, with Characterize the chronicity rule of ground path.The selection of short-term time scale should hold the distribution character of fault data, mainly for connecing The ground line failure rate higher period, to characterize the short-term rule of ground path.The generally optional 3-5 of long time scale is short The optional 0.5-1 of time scale can be determined according to power grid practical operation situation.
TheiHistorical failure of the route under long and short two time scales estimate for,i=0,1 ...,N, from going through Is intercepted in history Mishap DatabaseiThe statistical data of route under corresponding time scale,j=0,1,2, history event Hindering the calculation formula estimated is
Step 4 determines the ground connection weight that ground path historical failure is estimated under long and short two time scales,
It concentrates historical failure of the every route under different time scales to estimate history ground path and is weighted fusion, Predict integrated ground probability of the every ground path under current state,
Step 5 is ranked up history ground path according to the integrated ground probability size predicted, is formed and draws road route selection Sequence list, dispatcher carries out drawing road route selection according to the route for drawing route selection sequence list in road preferentially to concentrate history ground path, if not It is successful then draw road route selection according to a conventional method in remaining route.
Step 6, according to drawing road route selection as a result, if ground path is the of history ground path collectioniRoute, then it is corresponded to Singlephase earth fault dataAdd 1, if ground path is new line, more new historical ground path collection, element numberNAdd 1.
Embodiment of above is the preferred embodiment of the present invention, is not to impose any restrictions to the present invention, it is any not It is detached from made by essence of the present invention and simply modifies or convert, within the scope of protection of the patent of the invention.

Claims (1)

1. a kind of single-phase ground fault line selecting method of small-electric current grounding system, which comprises the following steps:
1) same bus historical failure data is counted,
As unit of a bus, the historical failure data of every route on the bus is divided into single-phase earthing, line tripping, is lacked Processing three classes are fallen into, count the respectivelyxThe number of three classes permanent fault occurs for route, history of forming Mishap Database, whereinIndicate single-phase earthing number,Indicate line tripping number,Indicate defect processing time Number,x=0,1 ...,M,MGo out number of lines for the bus, and according to the practical operation situation of each outlet of the bus in current electric grid, The line tripping of corresponding line in real-time update historical failure data libraryAnd defect processingTwo class data;
2) same bus history ground path collection is extracted,
All routes that singlephase earth fault occurred on bus described in step 1) are extracted, history of forming ground line Road collection, the number of element is denoted as in the sets of linesN
3) determine that ground path historical failure is estimated under different time scales,
According to the periodic law and distribution character of fault data in step 1) historical data base, the history ground line of step 2 is determined Historical failure of the every route under long and short two different time scales is concentrated to estimate in road, it is assumed that theiRoute is long and short two Historical failure under a time scale estimate for,i=0,1 ...,N, cut from the historical failure data library in step 1) TakeiThe statistical data of route under corresponding time scale,j=0,1,2, the calculation formula that historical failure is estimated For
4) ground path historical failure is estimated into Weighted Fusion,
DetermineiThe route ground connection weight that ground path historical failure is estimated under long and short two time scales,
5) it is carried out drawing road route selection according to integrated ground probability,
The integrated ground probability size predicted according to step 4) is ranked up history ground path, is formed and draws road route selection sequence Table, dispatcher carries out drawing road route selection according to the route for drawing route selection sequence list in road preferentially to concentrate history ground path, if unsuccessful Then draw road route selection according to a conventional method in remaining route;
6) same bus historical failure data updates,
Road route selection is drawn as a result, if ground path is the of history ground path collection according to step 5)iRoute, then its is corresponding Singlephase earth fault dataAdd 1, if ground path is new line, more new historical ground path collection, element numberNAdd 1.
CN201710263991.6A 2017-04-21 2017-04-21 A kind of single-phase ground fault line selecting method of small-electric current grounding system Active CN106940411B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710263991.6A CN106940411B (en) 2017-04-21 2017-04-21 A kind of single-phase ground fault line selecting method of small-electric current grounding system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710263991.6A CN106940411B (en) 2017-04-21 2017-04-21 A kind of single-phase ground fault line selecting method of small-electric current grounding system

Publications (2)

Publication Number Publication Date
CN106940411A CN106940411A (en) 2017-07-11
CN106940411B true CN106940411B (en) 2019-05-31

Family

ID=59463830

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710263991.6A Active CN106940411B (en) 2017-04-21 2017-04-21 A kind of single-phase ground fault line selecting method of small-electric current grounding system

Country Status (1)

Country Link
CN (1) CN106940411B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108845226A (en) * 2018-04-25 2018-11-20 国网甘肃省电力公司 A kind of Distribution Network Failure intelligent locating method based on angle analysis weighting algorithm
CN109001590B (en) * 2018-05-04 2021-12-07 国网安徽省电力有限公司芜湖供电公司 Single-phase grounding line selection method of grounding system
CN108919046B (en) * 2018-05-15 2020-11-06 国网山东省电力公司济南供电公司 Power distribution network ground fault trial stop line sequence decision method and system
CN109164339B (en) * 2018-07-27 2020-09-25 国电南瑞科技股份有限公司 Method for counting and displaying accuracy of bus low-current grounding pull-out sequence
CN110488154B (en) * 2019-08-28 2021-06-22 国网四川省电力公司成都供电公司 Low-current grounding line selection method for dispatching master station end
CN112180205B (en) * 2020-08-28 2024-05-28 南京国电南自软件工程有限公司 Intelligent distributed single-phase grounding line selection method and system for power distribution network
CN112736869B (en) * 2020-12-23 2023-05-23 贵州电网有限责任公司 Fault round cutting method of low-current grounding line selection device
CN113640621B (en) * 2021-08-27 2023-09-15 国网四川省电力公司成都供电公司 Full-automatic detection method and detection system for low-current ground fault line
CN113884817B (en) * 2021-10-27 2023-09-01 国网江苏省电力有限公司镇江供电分公司 Single-phase grounding fault grounding searching method for small-current grounding system
CN116008733A (en) * 2023-03-21 2023-04-25 成都信息工程大学 Single-phase grounding fault diagnosis method based on integrated deep neural network

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101162838A (en) * 2007-11-29 2008-04-16 昆明理工大学 Low current neutral grounding system fault route selecting method by wavelet package decompose and correlation analysis
CN101923137A (en) * 2010-06-30 2010-12-22 湖南湘能电气自动化有限公司 Single-phase ground fault line selecting method of small-electric current grounding system
CN102788933A (en) * 2012-09-25 2012-11-21 河北省电力公司 Method for utilizing automatic switch-out controller to search power grid low-current single-phase ground fault
CN103592571A (en) * 2013-11-08 2014-02-19 珠海威瀚科技发展有限公司 Method for achieving single-phase earth fault line selection of small current grounding system
CN104849614A (en) * 2015-05-11 2015-08-19 国家电网公司 Judgment method of small current single-phase grounding fault line selection
CN104977499A (en) * 2015-07-23 2015-10-14 中国电力科学研究院 Small current grounding system single-phase grounding fault line selection method
EP2985613A1 (en) * 2013-03-29 2016-02-17 Beijing Inhand Networks Technology Co., Ltd. Method and system for detecting and locating single-phase ground fault on low current grounded power-distribution network
CN105629128A (en) * 2016-01-15 2016-06-01 国网河北省电力公司电力科学研究院 Device and searching method for searching power grid undercurrent single-phase earth fault

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101162838A (en) * 2007-11-29 2008-04-16 昆明理工大学 Low current neutral grounding system fault route selecting method by wavelet package decompose and correlation analysis
CN101923137A (en) * 2010-06-30 2010-12-22 湖南湘能电气自动化有限公司 Single-phase ground fault line selecting method of small-electric current grounding system
CN102788933A (en) * 2012-09-25 2012-11-21 河北省电力公司 Method for utilizing automatic switch-out controller to search power grid low-current single-phase ground fault
EP2985613A1 (en) * 2013-03-29 2016-02-17 Beijing Inhand Networks Technology Co., Ltd. Method and system for detecting and locating single-phase ground fault on low current grounded power-distribution network
CN103592571A (en) * 2013-11-08 2014-02-19 珠海威瀚科技发展有限公司 Method for achieving single-phase earth fault line selection of small current grounding system
CN104849614A (en) * 2015-05-11 2015-08-19 国家电网公司 Judgment method of small current single-phase grounding fault line selection
CN104977499A (en) * 2015-07-23 2015-10-14 中国电力科学研究院 Small current grounding system single-phase grounding fault line selection method
CN105629128A (en) * 2016-01-15 2016-06-01 国网河北省电力公司电力科学研究院 Device and searching method for searching power grid undercurrent single-phase earth fault

Also Published As

Publication number Publication date
CN106940411A (en) 2017-07-11

Similar Documents

Publication Publication Date Title
CN106940411B (en) A kind of single-phase ground fault line selecting method of small-electric current grounding system
CN106124935B (en) Middle and low voltage network Fault Locating Method
CN104218676B (en) The intelligent warning system of power dispatching automation main website and method
CN106021596B (en) A kind of analysis method of electric network fault rush of current topological diagram
CN101789626B (en) Protected object-oriented automatic modeling and real-time information joint processing method
CN104103019B (en) Operation risk assessment method and assessment system of power distribution network containing distributed power supply
CN106408438B (en) Security and stability control strategy automatic Check method based on full dynamic simulation
CN110210701A (en) A kind of grid equipment risk perceptions method
CN106990325B (en) Distribution small current grounding fault determination method based on mutation logic array
CN103679554B (en) Power grid accident separating brake aided analysis method
CN103489138B (en) The Controlling UEP method of a kind of power transmission network failure message and the out-of-limit information of circuit
CN105467276B (en) A kind of line fault monitoring method and system
CN104617677A (en) Method for determining POWER GRID OUTAGE AND FAULT CONDITION, device thereof, and power grid management system
CN110286300A (en) A kind of multi branch electric power lines road Fault Locating Method, device, equipment and system
CN105158647B (en) Dan Zhanduan electric network failure diagnosis and aid decision-making method based on grid monitoring system
CN104950216B (en) A kind of distribution line failure localization method based on waveform comparison
CN110380514A (en) A kind of intelligent substation relay protection secondary circuit method for diagnosing faults
CN106646130B (en) A kind of active distribution network Fault Locating Method compared based on current polarity and system
CN103259333B (en) Intelligent alarm and comprehensive analysis of fault system
CN107317313B (en) A kind of protection starting householder method of current comparison pilot protection
CN102624097A (en) Fault point positioning method for intelligent distribution lines
CN105093063A (en) Online power grid fault diagnosis method based on multisource data characteristic unit combination judgment
CN103632311A (en) Fault examining system and method for power grid operation
CN108061841A (en) A kind of method of electric network fault event class automatic identification
CN103227450A (en) On-line failure recovery method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant