CN106926989A - A kind of combined simple ocean platform and its construction method - Google Patents
A kind of combined simple ocean platform and its construction method Download PDFInfo
- Publication number
- CN106926989A CN106926989A CN201710258165.2A CN201710258165A CN106926989A CN 106926989 A CN106926989 A CN 106926989A CN 201710258165 A CN201710258165 A CN 201710258165A CN 106926989 A CN106926989 A CN 106926989A
- Authority
- CN
- China
- Prior art keywords
- square steel
- platform
- piling
- steel
- square
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 33
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 241
- 239000010959 steel Substances 0.000 claims abstract description 241
- 239000013535 sea water Substances 0.000 claims abstract description 15
- 238000002156 mixing Methods 0.000 claims abstract 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 45
- 239000002689 soil Substances 0.000 claims description 26
- 238000013461 design Methods 0.000 claims description 17
- 238000003466 welding Methods 0.000 claims description 6
- 230000005484 gravity Effects 0.000 claims description 3
- 238000012795 verification Methods 0.000 claims description 3
- 238000001514 detection method Methods 0.000 claims 1
- 239000000203 mixture Substances 0.000 claims 1
- 230000000994 depressogenic effect Effects 0.000 abstract 1
- 238000005476 soldering Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 11
- 238000010586 diagram Methods 0.000 description 9
- 230000006835 compression Effects 0.000 description 4
- 238000007906 compression Methods 0.000 description 4
- 238000006073 displacement reaction Methods 0.000 description 3
- 238000011161 development Methods 0.000 description 2
- 238000009792 diffusion process Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000035515 penetration Effects 0.000 description 2
- 238000005086 pumping Methods 0.000 description 2
- 238000000926 separation method Methods 0.000 description 2
- 238000012271 agricultural production Methods 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 238000009360 aquaculture Methods 0.000 description 1
- 244000144974 aquaculture Species 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000036316 preload Effects 0.000 description 1
- 230000000452 restraining effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/44—Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/02—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
- E02B17/027—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto steel structures
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Ocean & Marine Engineering (AREA)
- Revetment (AREA)
Abstract
Description
技术领域:Technical field:
本发明涉及海洋平台结构,具体涉及一种组合式简易海洋平台及其施工方法。The invention relates to an offshore platform structure, in particular to a combined simple offshore platform and a construction method thereof.
背景技术:Background technique:
我国海洋滩涂、潮间带土地资源丰富,具有面积大、分布集中、区位条件好、农牧渔业综合开发潜力大的特点。潮间带是水产养殖和发展农业生产的重要基地,是开发海洋、发展海洋产业的一笔宝贵财富。my country's marine tidal flats and intertidal zone are rich in land resources, which are characterized by large area, concentrated distribution, good location conditions, and great potential for comprehensive development of agriculture, animal husbandry and fishery. The intertidal zone is an important base for aquaculture and the development of agricultural production, and a valuable asset for developing the ocean and marine industry.
通常,需要在滩涂、潮间带地区建造简易海洋平台供海洋作业使用。滩涂、潮间带地区土层松软,承载力较低,且潮间带受潮水涨落起伏的影响,一天中高水位持续时间较短,且水位高度有限,施工环境较差。Generally, simple offshore platforms need to be built in tidal flats and intertidal zones for marine operations. The soil layer in tidal flats and intertidal zones is soft and the bearing capacity is low, and the intertidal zone is affected by tidal fluctuations, the duration of high water levels in a day is short, and the water level height is limited, so the construction environment is poor.
一般地,可采用桩基础或桶形基础作为潮间带简易海洋平台的基础型式。但如果桩基础的长度与重量较大,需要大型起重及打桩设备,但潮间带水位无法供大型施工船进入;如果采用桶形基础,由于潮间带高水位有限,在较小的水压差作用下桶形基础难以贯入海床至设计深度。可见,设计一种适应滩涂、潮间带施工环境的基础型式是淤泥地区简易海洋平台的关键技术之一。Generally, pile foundation or barrel foundation can be used as the foundation type of the simple offshore platform in the intertidal zone. However, if the length and weight of the pile foundation are large, large-scale lifting and piling equipment are required, but the water level in the intertidal zone cannot be used by large construction ships; Under the action of pressure difference, it is difficult for the barrel foundation to penetrate the seabed to the design depth. It can be seen that designing a foundation type suitable for the construction environment in tidal flats and intertidal zones is one of the key technologies for simple offshore platforms in silt areas.
虽然滩涂、潮间带地区多为淤泥、淤泥质土,承载力较低,但若基础的面积足够大,甚至用多块钢板拼装组成基础,并对基底淤泥进行一定的预压固结,也可使海洋平台满足变形与稳定要求。可见,有必要探讨适应淤泥地区的简易海洋平台结构型式及其施工方法,促进现有技术的革新与进步。Although tidal flats and intertidal zones are mostly silt and silty soils with low bearing capacity, if the area of the foundation is large enough, it is even possible to assemble the foundation with multiple steel plates and pre-compress the silt to a certain extent. It can make the offshore platform meet the deformation and stability requirements. It can be seen that it is necessary to explore the structure type and construction method of simple offshore platforms suitable for silt areas, and promote the innovation and progress of existing technologies.
发明内容:Invention content:
为了弥补现有技术问题的不足,本发明的目的是提供一种组合式简易海洋平台及其施工方法,采用桩与钢板组合的基础形式,并利用海水重量进行预压沉降,施工简便。In order to make up for the deficiencies of the existing technical problems, the object of the present invention is to provide a combined simple offshore platform and its construction method, which adopts the foundation form of a combination of piles and steel plates, and uses the weight of seawater for pre-compression settlement, and the construction is simple.
本发明的技术方案如下:Technical scheme of the present invention is as follows:
组合式简易海洋平台,其特征在于,包括两个方钢框架、钢板、钢桩与上部作业平台及在设计指定的海域竖直的打入四根钢桩,四根钢桩上依次套入第一个方钢框架、钢板、第二个方钢框架,四根钢桩上端伸出第二个方钢框架并安装有上部作业平台。The combined simple offshore platform is characterized in that it includes two square steel frames, steel plates, steel piles and the upper working platform, and four steel piles are driven vertically in the sea area specified in the design, and the four steel piles are sequentially inserted into the first A square steel frame, steel plates, a second square steel frame, the upper ends of four steel piles protrude from the second square steel frame and an upper working platform is installed.
所述的组合式简易海洋平台,其特征在于,所述的方钢框架由相互垂直的多根方钢纵横交错焊接而成网格状,整体呈正方形形状,在其内部对称、均匀的焊接四个套筒,四个套筒连线也呈正方形形状,两个对角位置的套筒之间还用方钢进行斜向焊接连接。The combined simple offshore platform is characterized in that the square steel frame is welded in a grid shape by a plurality of vertical square steels criss-crossed, and the whole is in a square shape, and four sides are welded symmetrically and uniformly inside it. There are two sleeves, and the connecting lines of the four sleeves are also in a square shape, and the two diagonally positioned sleeves are also connected by oblique welding with square steel.
所述的组合式简易海洋平台,其特征在于,所述的上部作业平台由四根立柱与平台板焊接构成,四根立柱分布于正方形四个拐点纵向竖立,四根立柱中相邻两根之间焊接有横向、斜向撑杆构成空间网架体系,四根立柱的底部焊接有口字型的扩展板,各立柱底部侧面通过钢管对称焊接有套管,套管侧壁与扩展板焊接固定。The combined simple offshore platform is characterized in that the upper working platform is composed of four uprights welded to the platform plate, and the four uprights are distributed at four inflection points of a square and vertically erected, and the adjacent two of the four uprights are Horizontal and oblique struts are welded between them to form a space grid system. The bottom of the four columns is welded with a mouth-shaped expansion plate. The bottom side of each column is symmetrically welded with a sleeve through steel pipes. The side wall of the sleeve is welded and fixed to the expansion plate. .
所述的组合式简易海洋平台,其特征在于,所述的上部作业平台上四个套管中心距与方钢框架上四个套筒中心距相等,套管内径与套筒的内径相等,套管内径大于钢桩外径1~2cm。The combined simple offshore platform is characterized in that the center distance of the four casings on the upper working platform is equal to the center distance of the four casings on the square steel frame, and the inner diameter of the casing is equal to the inner diameter of the casing. The inner diameter of the pipe is 1~2cm larger than the outer diameter of the steel pile.
所述的组合式简易海洋平台,其特征在于,所述的钢板有两块,两块相对设置铺设在第一个方钢框架与第二个方钢框架之间,钢板上条形孔宽度略大于钢桩外径,条形孔长度大于钢桩外径的三倍以上,每块钢板上两个条形孔中心距与方钢框架上相邻两个套筒中心距相等。The combined simple offshore platform is characterized in that there are two steel plates, and the two plates are relatively arranged between the first square steel frame and the second square steel frame, and the width of the strip hole on the steel plate is slightly Greater than the outer diameter of the steel pile, the length of the strip hole is more than three times the outer diameter of the steel pile, and the center distance between the two strip holes on each steel plate is equal to the center distance between two adjacent sleeves on the square steel frame.
一种组合式简易海洋平台的施工方法,其特征在于,包括如下步骤:A construction method for a combined simple offshore platform is characterized in that it comprises the following steps:
1)、打入四根钢桩:1) Drive in four steel piles:
根据设计参数,在设计指定的海域竖直的打入四根钢桩,最终使四根钢桩的中心距、铅垂度、入土深度等参数满足设计要求;According to the design parameters, drive four steel piles vertically in the sea area specified by the design, and finally make the parameters such as the center distance, plumbness, and soil penetration depth of the four steel piles meet the design requirements;
2)、平整海床:2) Leveling the seabed:
对四根钢桩周边大于方钢框架外轮廓范围内的海床进行平整,使平整范围内的海床土体最大高差小于10cm;Level the seabed around the four steel piles that is larger than the outer contour of the square steel frame, so that the maximum height difference of the seabed soil within the leveling range is less than 10cm;
3)、第一个方钢框架套住钢桩:3) The first square steel frame covers the steel pile:
起吊第一个方钢框架,使方钢框架上的四个套筒套住相应的四根钢桩并下沉直至接触海床;Lift the first square steel frame so that the four sleeves on the square steel frame cover the corresponding four steel piles and sink until it touches the seabed;
4)、钢板套住钢桩:4), the steel plate covers the steel pile:
依次逐个起吊两块钢板,使钢板上的两个条形孔套住相邻的两根钢桩下沉并压在第一个方钢框架上;Lift the two steel plates one by one, so that the two strip holes on the steel plates cover the two adjacent steel piles to sink and press on the first square steel frame;
5)、第二个方钢框架套住钢桩:5) The second square steel frame covers the steel pile:
起吊第二个方钢框架,使方钢框架上的四个套筒套住相应的四根钢桩下沉并压在钢板上;Lift the second square steel frame so that the four sleeves on the square steel frame cover the corresponding four steel piles to sink and press on the steel plate;
6)、连接上部作业平台:6) Connect the upper working platform:
起吊上部作业平台并下沉至桩基础位置处,使上部作业平台的四个套管套住四根钢桩下沉并压在第二个方钢框架上,并用螺栓固定钢桩上的螺栓孔,实现上部作业平台与钢桩之间的相互连接;Lift the upper working platform and sink it to the position of the pile foundation, make the four casings of the upper working platform cover the four steel piles, sink and press on the second square steel frame, and fix the bolt holes on the steel piles with bolts , to realize the interconnection between the upper working platform and the steel pile;
7)、水箱预压海洋平台:7) Water tank preloaded offshore platform:
在上部作业平台的平台板上均匀、对称的放置水箱,用水泵抽取海水逐步对称的填满各水箱,使海洋平台在水箱重力作用下沿着钢桩压缩海床至稳定状态;The water tanks are evenly and symmetrically placed on the platform of the upper working platform, and the water tanks are gradually and symmetrically filled with seawater pumped by water pumps, so that the offshore platform compresses the seabed along the steel piles to a stable state under the gravity of the water tanks;
8)、移除水箱,完成施工:8) Remove the water tank and complete the construction:
海洋平台底部的海床土体预压满足设计要求且海洋平台达到稳定状态后,逐步对称的移除水箱,并对简易海洋平台进行必要的检测与校验,最终完成简易海洋平台的施工。After the preloading of the seabed soil at the bottom of the offshore platform meets the design requirements and the offshore platform reaches a stable state, the water tank is gradually and symmetrically removed, and the simple offshore platform is subjected to necessary inspection and verification, and the construction of the simple offshore platform is finally completed.
本发明的有益效果是:The beneficial effects of the present invention are:
1、本发明各构件是相互独立的,这种化整为零的做法使得各单独构件的重量较小,降低了对海上作业的运输与起吊及其它施工设备的要求,适应淤泥、潮间带的施工环境;1. The components of the present invention are independent of each other. This method of breaking them into parts makes the weight of each individual component smaller, reduces the requirements for transportation, lifting and other construction equipment for offshore operations, and is suitable for mud, intertidal zones construction environment;
2、本发明各构件之间的连接方式简单,无复杂的连接方法及施工要求,今后若需拆卸,按照安装方法相反的步骤即可完成移除作用,操作简单,施工方便;2. The connection method between the components of the present invention is simple, without complicated connection methods and construction requirements. If it needs to be disassembled in the future, the removal can be completed according to the opposite steps of the installation method. The operation is simple and the construction is convenient;
3、本发明由方钢框架与钢板组合而成,其与海床土体接触面积非常大,可达到平台板面积的两倍以上,能适应淤泥质海床地质条件,且制作简单,施工方便,是一种简便、实用、经济的设计方案;3. The invention is composed of a square steel frame and a steel plate. Its contact area with the seabed soil is very large, which can reach more than twice the area of the platform plate. It can adapt to the geological conditions of the muddy seabed, and is simple to manufacture and convenient to construct. , is a simple, practical and economical design;
4、本发明施工过程中,在平台板上放置系列水箱并抽取海水填充,利用海水重量对海洋平台的地基土体进行预压固结,使地基土体的强度与工后沉降满足使用要求,利用海洋平台结构本身进行海床地基处理,具有经济性、实用性与合理性。4. During the construction process of the present invention, a series of water tanks are placed on the platform plate and filled with seawater, and the foundation soil of the offshore platform is pre-compressed and consolidated by using the weight of seawater, so that the strength and post-construction settlement of the foundation soil meet the use requirements. It is economical, practical and rational to use the offshore platform structure itself for seabed foundation treatment.
附图说明:Description of drawings:
图1为本发明的方钢框架结构示意图。Fig. 1 is a schematic diagram of the square steel frame structure of the present invention.
图2为本发明的受力钢板结构示意图。Fig. 2 is a structural schematic diagram of the stressed steel plate of the present invention.
图3为本发明的上部作业平台俯视图。Fig. 3 is a top view of the upper working platform of the present invention.
图4为本发明的上部作业平台仰视图。Fig. 4 is a bottom view of the upper working platform of the present invention.
图5为本发明的四根钢桩施工完毕示意图。Fig. 5 is a schematic diagram of four steel piles of the present invention after construction.
图6为本发明的第一个方钢框架套入钢桩示意图。Fig. 6 is a schematic diagram of the first square steel frame inserted into steel piles according to the present invention.
图7为本发明的受力钢板套入钢桩示意图。Fig. 7 is a schematic diagram of a steel pile inserted into a stressed steel sheet according to the present invention.
图8为本发明的第二个方钢框架套入钢桩示意图。Fig. 8 is a schematic diagram of a second square steel frame inserted into a steel pile according to the present invention.
图9为本发明的上部作业平台套入钢桩示意图。Fig. 9 is a schematic diagram of the upper working platform inserted into the steel pile according to the present invention.
图10为本发明的水箱辅助海洋平台压入海床示意图。Fig. 10 is a schematic diagram of the water tank auxiliary ocean platform pressed into the seabed according to the present invention.
图11为本发明的海洋平台施工完毕三维结构示意图。Fig. 11 is a three-dimensional schematic diagram of the constructed offshore platform of the present invention.
图12为本发明的海洋平台施工完毕主视图。Fig. 12 is a front view of the offshore platform of the present invention after construction.
附图标记说明:1、方钢框架;2、套筒;3、钢板;4、条形孔;5、立柱;6、平台板;7、套管;8、扩展板;9、钢桩;10、锥状桩尖;11、螺栓孔;12、螺栓;13、水箱; A、海平面;B、海床面;C、压缩沉降量。Explanation of reference signs: 1. Square steel frame; 2. Sleeve; 3. Steel plate; 4. Strip hole; 5. Column; 6. Platform plate; 7. Sleeve; 10. Conical pile tip; 11. Bolt hole; 12. Bolt; 13. Water tank; A, sea level; B, seabed surface; C, compression settlement.
具体实施方式:detailed description:
参见附图:See attached picture:
一种组合式简易海洋平台,包括方钢框架1、钢板3、钢桩9与上部作业平台,上部作业平台由四根中空立柱5与平台板6焊接而成,四根立柱5之间焊接有横向、斜向的撑杆形成空间网架体系,四根立柱5的底部侧面通过钢管对称的焊接套管7,施工时先打设四根钢桩9,基于套筒2把第一个方钢框架1套在四根钢桩9上,然后基于条形孔4把钢板3套住四根钢桩9并压在第一个方钢框架1上,再基于套筒2把第二个方钢框架1套在四根钢桩9并压在钢板3上,然后起吊上部作业平台基于四个套管7套住四根钢桩9压在第二个方钢框架1上并用螺栓固定,利用海水重量把海床地基压至稳定状态,由此构成简易海洋平台。A combined simple offshore platform, including a square steel frame 1, steel plates 3, steel piles 9 and an upper operating platform, the upper operating platform is welded by four hollow columns 5 and a platform plate 6, and the four columns 5 are welded with Horizontal and oblique struts form a space grid system. The bottom sides of the four columns 5 pass through the symmetrical welded sleeves 7 of steel pipes. During construction, four steel piles 9 are first laid, and the first square steel The frame 1 is set on the four steel piles 9, and then the steel plate 3 is put on the four steel piles 9 based on the strip hole 4 and pressed on the first square steel frame 1, and then the second square steel is put on the second square steel frame based on the sleeve 2 The frame 1 is set on four steel piles 9 and pressed on the steel plate 3, and then the upper work platform is lifted based on the four casings 7 to cover the four steel piles 9, pressed on the second square steel frame 1 and fixed with bolts, using seawater The weight presses the seabed foundation to a stable state, thereby forming a simple ocean platform.
方钢框架1由相互垂直的多根方钢焊接而成,整体呈正方形形状,在其内部对称、均匀的焊接四个套筒2,四个套筒2的连线也呈正方形形状,两个对角位置的套筒2之间还用方钢进行斜向焊接连接,如图1所示。The square steel frame 1 is welded by multiple square steels perpendicular to each other, and has a square shape as a whole. Four sleeves 2 are welded symmetrically and evenly inside it. Square steel is also used for oblique welding connection between the sleeves 2 at the diagonal positions, as shown in FIG. 1 .
方钢框架1的上下表面均为平面,能与钢板3紧密接触。所提简易海洋平台中共使用两个方钢框架1,钢板3加在两个方钢框架1之间形成基础底板,海洋平台荷载通过钢板3传递给海床。方钢框架1对钢板3起到约束、控制的作用,上部荷载通过方钢框架1均匀的传递给钢板3,方钢框架1使钢板3各处受力基本均匀,起到荷载扩散的作用。The upper and lower surfaces of the square steel frame 1 are planes, which can be in close contact with the steel plate 3 . The proposed simple offshore platform uses two square steel frames 1 in total, and a steel plate 3 is added between the two square steel frames 1 to form a foundation floor, and the load of the offshore platform is transmitted to the seabed through the steel plates 3 . The square steel frame 1 plays the role of restraint and control on the steel plate 3. The upper load is evenly transmitted to the steel plate 3 through the square steel frame 1. The square steel frame 1 makes the stress on the steel plate 3 basically uniform everywhere, and plays the role of load diffusion.
由于淤泥、淤泥质土的承载力较低,故可增大方钢框架1与钢板3尺寸,达到增加基底面积的目的。一般地,方钢框架1的面积可达到平台板6面积的两倍以上。方钢框架1与钢板3组合形成的基础形式与海床土体接触面积非常大,能适应淤泥质海床地质条件,且制作简单,施工方便,是一种简便、实用的设计方案。Because the bearing capacity of silt and silty soil is low, the size of the square steel frame 1 and the steel plate 3 can be increased to achieve the purpose of increasing the base area. Generally, the area of the square steel frame 1 can reach more than twice the area of the platform plate 6 . The foundation form formed by the combination of the square steel frame 1 and the steel plate 3 has a very large contact area with the seabed soil, can adapt to the geological conditions of the muddy seabed, and is simple to manufacture and convenient to construct. It is a simple and practical design scheme.
上部作业平台由四根立柱5与平台板6焊接而成,四根立柱5组成正方形形状,四根立柱5之间焊接有横向、斜向的撑杆形成空间网架体系,四根立柱5的底部焊接有封闭的口字型扩展板8,各立柱5的底部侧面通过钢管对称的焊接套管7,如图3与图4所示。The upper working platform is welded by four uprights 5 and platform plate 6, the four uprights 5 form a square shape, the four uprights 5 are welded with horizontal and oblique struts to form a space grid system, the four uprights 5 The bottom is welded with a closed mouth-shaped expansion plate 8, and the bottom side of each column 5 passes through a steel pipe symmetrical welding sleeve 7, as shown in Figures 3 and 4.
上部作业平台上设置一圈扩展板8,是为了增加上部作业平台与方钢框架1的接触面积,使上部荷载能通过方钢框架1有效扩散至钢板3上,避免应力集中而产生过大变形。A circle of expansion plates 8 is set on the upper work platform to increase the contact area between the upper work platform and the square steel frame 1, so that the upper load can be effectively spread to the steel plate 3 through the square steel frame 1, and avoid excessive deformation due to stress concentration .
上部作业平台上四个套管7的中心轴线之间的距离与方钢框架1上四个套筒2中心轴线之间的距离相等,套管7的中空内径与套筒2的中空内径相等。最终,四个套管7与四个套筒2均套在钢桩9上,故套管7与套筒2位置关系需一致。The distance between the central axes of the four sleeves 7 on the upper working platform is equal to the distance between the central axes of the four sleeves 2 on the square steel frame 1, and the hollow inner diameter of the sleeves 7 is equal to the hollow inner diameter of the sleeve 2. Finally, the four sleeves 7 and the four sleeves 2 are all sleeved on the steel pile 9, so the positional relationship between the sleeves 7 and the sleeves 2 must be consistent.
套管7的内径大于钢桩9外径1~2cm,钢板3上条形孔4的宽度略大于钢桩9的外径、条形孔4的长度大于钢桩9外径的三倍以上,钢板3上两个条形孔4中心点之间的距离与方钢框架1上相邻两个套筒2中心轴线之间的距离相等。The inner diameter of the casing 7 is 1-2 cm greater than the outer diameter of the steel pile 9, the width of the strip hole 4 on the steel plate 3 is slightly greater than the outer diameter of the steel pile 9, and the length of the strip hole 4 is more than three times greater than the outer diameter of the steel pile 9, The distance between the center points of two bar-shaped holes 4 on the steel plate 3 is equal to the distance between the central axes of two adjacent sleeves 2 on the square steel frame 1 .
一块钢板3上共设置两个条形孔4,两块钢板3拼装起来即可布满方钢框架1,如图7所示。条形孔4的长度大于钢桩9外径的三倍以上,是为了方便钢板3套在钢桩9上。A steel plate 3 is provided with two strip holes 4, and the two steel plates 3 can be assembled to cover the square steel frame 1, as shown in FIG. 7 . The length of the strip hole 4 is more than three times greater than the outer diameter of the steel pile 9, so that the steel plate 3 is sleeved on the steel pile 9 for convenience.
在四根钢桩9的垂直度满足要求情况下,方钢框架1与钢板3套在钢桩9后,其只能沿着钢桩9发生竖直向下的沉降,而不会发生水平方向位移。即钢桩9对方钢框架1与钢板3起到定位、约束与控制的作用,钢桩9本身并不承担海洋平台的竖向荷载。故钢桩9的截面尺寸不需要太大,只要其能打入密实土层中在外荷载作用下保持稳定性即可。When the verticality of the four steel piles 9 meets the requirements, the square steel frame 1 and the steel plate 3 are set behind the steel piles 9, and they can only settle vertically downward along the steel piles 9, but not in the horizontal direction. displacement. That is, the steel pile 9 plays the role of positioning, restraint and control on the other steel frame 1 and the steel plate 3, and the steel pile 9 itself does not bear the vertical load of the offshore platform. Therefore, the cross-sectional size of the steel pile 9 does not need to be too large, as long as it can be driven into a compact soil layer and maintain stability under external loads.
海洋平台受到的水平荷载由四根钢桩9、方钢框架1与钢板3组成的结构体系共同承担,故钢桩9需有足够的入土深度,在较大水平荷载作用下能维持其铅垂度与稳定性。The horizontal load on the offshore platform is jointly borne by the structural system composed of four steel piles 9, square steel frame 1 and steel plate 3, so the steel pile 9 must have sufficient depth to maintain its vertical degree and stability.
钢桩9、方钢框架1、上部作业平台均由钢材焊接而成,各构件、焊缝及整体结构的强度应满足复杂工况下组合荷载的作用需求而不发生屈服,各构件应满足应力集中需要而不发生超过规范允许的过大变形。The steel pile 9, the square steel frame 1, and the upper working platform are all welded by steel. The strength of each component, weld and the overall structure should meet the combined load requirements under complex working conditions without yielding, and each component should meet the stress Concentration is required without excessive deformation beyond that permitted by the specification.
一种组合式简易海洋平台的施工方法,其特征在于,包括如下步骤:A construction method for a combined simple offshore platform is characterized in that it comprises the following steps:
1)、打入四根钢桩:1) Drive in four steel piles:
根据设计参数,在设计指定的海域竖直的打入四根钢桩9,最终使四根钢桩9的中心距、铅垂度、入土深度等参数满足设计要求,如图5所示。According to the design parameters, four steel piles 9 are driven vertically in the sea area specified by the design, and finally the parameters such as the center distance, plumbness, and soil penetration depth of the four steel piles 9 meet the design requirements, as shown in Fig. 5 .
四根钢桩9中心轴线之间的距离、四个套管7的中心轴线之间的距离与方钢框架1上四个套筒2中心轴线之间的距离均相等,即方钢框架1基于四个套筒2可套在四根钢桩9上滑入海床,上部作业平台可基于套管7套在四根钢桩9上滑入海床。The distance between the central axes of the four steel piles 9, the distance between the central axes of the four casings 7, and the distance between the central axes of the four sleeves 2 on the square steel frame 1 are all equal, that is, the square steel frame 1 is based on The four sleeves 2 can be sleeved on the four steel piles 9 and slide into the seabed, and the upper working platform can be sleeved on the four steel piles 9 and slide into the seabed based on the sleeves 7 .
2)、平整海床:2) Leveling the seabed:
对四根钢桩9周边大于方钢框架1外轮廓范围内的海床进行平整,使平整范围内的海床土体最大高差小于10cm。Leveling the seabed around the four steel piles 9 that is larger than the outer contour of the square steel frame 1, so that the maximum height difference of the seabed soil within the leveling range is less than 10cm.
后续方钢框架1、钢板3均套在四根钢桩9上接触海床,若海床表面不平整、高差过大,会导致钢板3的下沉产生倾斜与扭力。故对海床进行平整,有利于提高海洋平台的稳定性。Subsequent square steel frame 1 and steel plate 3 are set on the four steel piles 9 to contact the seabed. If the surface of the seabed is uneven and the height difference is too large, the sinking of the steel plate 3 will cause inclination and torsion. Therefore, leveling the seabed is conducive to improving the stability of the offshore platform.
3)、第一个方钢框架套住钢桩:3) The first square steel frame covers the steel pile:
起吊第一个方钢框架1,使方钢框架1上的四个套筒2套住相应的四根钢桩9并下沉直至接触海床,如图6所示。The first square steel frame 1 is hoisted so that the four sleeves 2 on the square steel frame 1 cover the corresponding four steel piles 9 and sink until they touch the seabed, as shown in Figure 6 .
由于套筒2具有一定长度,其沿着钢桩9下沉,在钢桩9的铅垂度满足要求情况下,其只能发生竖向沉降,而不产生水平位移。Since the sleeve 2 has a certain length, it sinks along the steel pile 9. When the plumbness of the steel pile 9 meets the requirements, it can only settle vertically without horizontal displacement.
第一个方钢框架1的作用是:约束与控制其上方钢板3向下发生均匀的沉降,维持钢板3受到荷载作用后仍呈水平状态。The function of the first square steel frame 1 is to restrain and control the uniform settlement of the steel plate 3 above it, and maintain the steel plate 3 in a horizontal state after being loaded.
4)、钢板套住钢桩:4), the steel plate covers the steel pile:
依次逐个起吊两块钢板3,使钢板3上的两个条形孔4套住相邻的两根钢桩9下沉并压在第一个方钢框架1上,如图7所示。Lift the two steel plates 3 one by one, so that the two strip holes 4 on the steel plates 3 cover the two adjacent steel piles 9 to sink and press on the first square steel frame 1, as shown in Figure 7 .
两块钢板3合并起来的面积即为方钢框架1的外轮廓面积。钢板3作用是把海洋平台的上部荷载传至较大面积的海床土体上去。由于钢板3的面积可取较大值,使得钢板3底部海床土体的基底压力较小,适应淤泥、淤泥质土等海床土体强度较低、压缩性较大的特性。The combined area of the two steel plates 3 is the outer contour area of the square steel frame 1 . The role of the steel plate 3 is to transmit the upper load of the offshore platform to the larger area of seabed soil. Since the area of the steel plate 3 can take a larger value, the base pressure of the seabed soil at the bottom of the steel plate 3 is relatively small, which is suitable for the characteristics of low strength and high compressibility of the seabed soil such as silt and silty soil.
5)、第二个方钢框架套住钢桩:5) The second square steel frame covers the steel pile:
起吊第二个方钢框架1,使方钢框架1上的四个套筒2套住相应的四根钢桩9下沉并压在钢板3上,如图8所示。Lift the second square steel frame 1 so that the four sleeves 2 on the square steel frame 1 cover the corresponding four steel piles 9 to sink and press on the steel plate 3, as shown in FIG. 8 .
第二个方钢框架1的作用是:把海洋平台受到的荷载有效、均匀的传递给钢板3,避免钢板3局部受力过大而发生不均匀变形。The function of the second square steel frame 1 is to effectively and evenly transmit the load on the offshore platform to the steel plate 3, so as to avoid uneven deformation of the steel plate 3 due to excessive local stress.
6)、连接上部作业平台:6) Connect the upper working platform:
起吊上部作业平台并下沉至桩基础位置处,使上部作业平台的四个套管7套住四根钢桩9下沉并压在第二个方钢框架1上,并用螺栓固定钢桩9上的螺栓孔,实现上部作业平台与钢桩之间的相互连接,如图9所示。Lift the upper working platform and sink it to the position of the pile foundation, make the four casings 7 of the upper working platform cover the four steel piles 9, sink and press on the second square steel frame 1, and fix the steel piles 9 with bolts Bolt holes on the upper part realize the mutual connection between the upper working platform and the steel piles, as shown in Figure 9.
上部作业平台的扩展板8与其正下方的方钢框架1是紧密接触的,由于方钢框架1具有足够的强度与刚度,其能把扩展板8传递过来的荷载有效、均匀的传递给下方的钢板3,实现应力的有效扩散。The expansion plate 8 of the upper working platform is in close contact with the square steel frame 1 directly below. Since the square steel frame 1 has sufficient strength and rigidity, it can effectively and evenly transfer the load transmitted by the expansion plate 8 to the lower one. The steel plate 3 realizes the effective diffusion of stress.
在后续使用荷载作用下,上部作业平台压在方钢框架上,故钢桩9上的螺栓孔中螺栓仅起到栓固作用,防止特殊情况下上部作业平台与钢桩9之间的分离与脱落。上部作业平台受到的水平荷载,将通过套管7传递给钢桩9,故套管7应具有足够的强度与刚度,能承受复杂工况下组合荷载的作用而不发生屈曲与变形。Under the subsequent use load, the upper work platform is pressed on the square steel frame, so the bolts in the bolt holes on the steel pile 9 only play a role of bolting, preventing the separation and separation between the upper work platform and the steel pile 9 under special circumstances. fall off. The horizontal load on the upper working platform will be transmitted to the steel pile 9 through the casing 7, so the casing 7 should have sufficient strength and stiffness to withstand the combined load under complex working conditions without buckling and deformation.
在四根钢桩9垂直度满足要求的情况下,方钢框架1、钢板3与上部作业平台沿着四根钢桩9竖向的压迫海床土体,使得方钢框架1、钢板3与上部作业平台只能发生竖向沉降而不发生水平位移,钢桩9起到引导、约束、控制方钢框架1、钢板3与上部作业平台作用。竖向荷载均由钢板3传递给海床,钢桩9本身并不承担竖向荷载。When the verticality of the four steel piles 9 meets the requirements, the square steel frame 1, the steel plate 3 and the upper working platform vertically compress the seabed soil along the four steel piles 9, so that the square steel frame 1, the steel plate 3 and the The upper work platform can only undergo vertical settlement without horizontal displacement, and the steel pile 9 plays the role of guiding, restraining and controlling the square steel frame 1, the steel plate 3 and the upper work platform. The vertical load is transmitted to the seabed by the steel plate 3, and the steel pile 9 itself does not bear the vertical load.
7)、水箱预压海洋平台:7) Water tank preloaded offshore platform:
在上部作业平台的平台板6上均匀、对称的放置水箱13,用水泵抽取海水逐步对称的填满各水箱13,使海洋平台在水箱重力作用下沿着钢桩9压缩海床至稳定状态。Place water tanks 13 evenly and symmetrically on the platform plate 6 of the upper working platform, and pump seawater to fill each water tank 13 gradually and symmetrically, so that the offshore platform compresses the seabed along the steel pile 9 to a stable state under the gravity of the water tank.
海水的密度一般为1.025g/cm3,即1m3的海水重1t左右。若数量较多的水箱累计充水后达到10m3,则可给海床土体施加10t的竖向荷载;若水箱累计充水15m3,则可给海床土体施加15t的竖向荷载;若水箱累计充水20m3,则可给海床土体施加20t的竖向荷载。水箱一般由塑料制成,其费用较低,可以反复利用。可见,因地制宜的抽取海水给海床土体进行预压固结,是一种廉价、高效的施工方法。特别地,加载过程中可使水箱总重量超过后续使用荷载,使后续海洋平台使用过程中不再产生竖向沉降,提高海洋平台的整体稳定性。The density of seawater is generally 1.025g/cm 3 , that is, 1m 3 of seawater weighs about 1 ton. If a large number of water tanks are accumulatively filled to 10m 3 , a vertical load of 10t can be applied to the seabed soil; if the accumulative water tanks are filled with water of 15m 3 , a vertical load of 15t can be applied to the seabed soil; If the water tank is accumulatively filled with 20m 3 of water, a vertical load of 20t can be applied to the seabed soil. The water tank is generally made of plastic, its cost is low, and it can be used repeatedly. It can be seen that pumping seawater according to local conditions to preload and consolidate seabed soil is a cheap and efficient construction method. In particular, during the loading process, the total weight of the water tank can exceed the subsequent use load, so that vertical settlement will no longer occur during the subsequent use of the offshore platform, and the overall stability of the offshore platform will be improved.
水箱充水应沿平台板6的中轴线处对称、均匀的开展,避免产生不均匀荷载。且水箱本身应具有足够的强度,多层水箱层叠时,最下方的水箱应能承受上部荷载而不发生破损。The filling of the water tank should be carried out symmetrically and evenly along the central axis of the platform plate 6 to avoid uneven loads. And the water tank itself should have sufficient strength. When multi-layer water tanks are stacked, the bottom water tank should be able to bear the upper load without damage.
应循序渐进、缓慢的增加水箱的总体重量,合理设计各级加载荷载与加载时间,使待海床土体在由小变大的缓慢加载过程中逐渐压缩固结。应时刻观察、校对上部作业平台下沉的姿态,确保上部作业平台下沉的垂直度。若上部作业平台发生一定的倾斜,可在其倾斜相反方向多施加一些水箱,通过不均匀加载形成的弯矩可对倾斜海洋平台进行纠偏,从而确保海洋平台的垂直度满足要求。The overall weight of the water tank should be gradually and slowly increased, and the loading and loading time of each level should be reasonably designed so that the seabed soil is gradually compressed and consolidated during the slow loading process from small to large. The sinking attitude of the upper working platform should be observed and checked at all times to ensure the verticality of the sinking of the upper working platform. If the upper working platform is tilted to a certain extent, more water tanks can be added in the opposite direction of the tilt, and the bending moment formed by uneven loading can correct the tilted offshore platform, so as to ensure that the verticality of the offshore platform meets the requirements.
施工过程中,应避免最底层的水箱浸泡于海水中。若水箱浸泡于海水中,其受到向上浮力,抵消了水箱的重量,显然对预压固结不利。During the construction process, the water tank at the bottom should be prevented from being soaked in seawater. If the water tank is immersed in seawater, it will be subjected to upward buoyancy, which offsets the weight of the water tank, which is obviously unfavorable for pre-compression consolidation.
最终的加载荷载即水箱总重量可超过该海洋平台的后续使用荷载,使海洋平台产生较大的压缩沉降量C,如图12所示,可使海洋平台使用过程中不再产生竖向沉降,提高海洋平台的整体稳定性。可见,因地制宜的抽取海水给海洋平台施加竖向荷载,是一种廉价、高效的施工方法。The final loading load, that is, the total weight of the water tank can exceed the subsequent use load of the offshore platform, causing the offshore platform to generate a large compression settlement C, as shown in Figure 12, which can prevent the vertical settlement of the offshore platform from occurring during use. Improve the overall stability of the offshore platform. It can be seen that pumping seawater according to local conditions to apply vertical loads to offshore platforms is a cheap and efficient construction method.
8)、移除水箱,完成施工:8) Remove the water tank and complete the construction:
海洋平台底部的海床土体预压满足设计要求且海洋平台达到稳定状态后,逐步对称的移除水箱13,并对简易海洋平台进行必要的检测与校验,最终完成简易海洋平台的施工。After the preloading of the seabed soil at the bottom of the offshore platform meets the design requirements and the offshore platform reaches a stable state, the water tank 13 is gradually and symmetrically removed, and necessary inspections and verifications are carried out on the simple offshore platform, and the construction of the simple offshore platform is finally completed.
移除水箱过程中,应保持剩余水箱荷载的均匀性与对称性,不可产生不均匀荷载,不可使海洋平台产生倾斜与偏移。In the process of removing the water tank, the uniformity and symmetry of the load on the remaining water tank should be maintained, and uneven load should not be generated, and the offshore platform should not be tilted and shifted.
本发明不局限于上述具体实施方式,根据上述内容,按照本领域的普通技术知识和惯用手段,在不脱离本发明上述基本技术思想前提下,本发明还可以做出其它多种形式的等效修改、替换或变更,均落在本发明的保护范围之内。The present invention is not limited to the above-mentioned specific implementation methods. According to the above-mentioned content, according to the common technical knowledge and conventional means in this field, without departing from the above-mentioned basic technical idea of the present invention, the present invention can also make other equivalents in various forms. Modifications, substitutions or alterations all fall within the protection scope of the present invention.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710258165.2A CN106926989B (en) | 2017-04-19 | 2017-04-19 | A kind of combined simple ocean platform and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710258165.2A CN106926989B (en) | 2017-04-19 | 2017-04-19 | A kind of combined simple ocean platform and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106926989A true CN106926989A (en) | 2017-07-07 |
CN106926989B CN106926989B (en) | 2018-10-16 |
Family
ID=59437748
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710258165.2A Active CN106926989B (en) | 2017-04-19 | 2017-04-19 | A kind of combined simple ocean platform and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106926989B (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109368794A (en) * | 2018-09-30 | 2019-02-22 | 杭州江润科技有限公司 | The construction method of water plant combined type ecological floating island |
CN109631845A (en) * | 2018-11-16 | 2019-04-16 | 浙江海洋大学 | Ocean platform oblique view equipment |
CN111114711A (en) * | 2019-12-30 | 2020-05-08 | 江苏省水文地质工程地质勘察院 | Offshore exploration platform capable of walking and moving by oneself |
CN112144562A (en) * | 2020-04-22 | 2020-12-29 | 中国海洋大学 | Pile foundation monitoring device for offshore operation platform |
CN113638386A (en) * | 2021-08-19 | 2021-11-12 | 中交第三航务工程局有限公司 | Offshore wind power single pile socketed foundation construction is with assembled platform |
CN114348192A (en) * | 2022-01-13 | 2022-04-15 | 东北石油大学 | Assembled FRP concrete cable tower shock absorption platform and its construction method |
CN114517470A (en) * | 2022-03-09 | 2022-05-20 | 中国建筑工程(香港)有限公司 | Construction method of overwater construction platform |
CN115059838A (en) * | 2022-06-10 | 2022-09-16 | 自然资源部第三海洋研究所 | Support for coast photography and hydrological observation |
CN115402470A (en) * | 2022-09-30 | 2022-11-29 | 中国能源建设集团江苏省电力建设第一工程有限公司 | Floating photovoltaic mooring system adaptive to high water level change |
CN115772884A (en) * | 2022-12-23 | 2023-03-10 | 大连理工大学 | A hinged fixed photovoltaic platform |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2473128Y (en) * | 2001-02-23 | 2002-01-23 | 胜利石油管理局钻井工艺研究院 | One pile single well oil production platform with seat cushion under water conduct frame |
RU2347866C2 (en) * | 2007-02-19 | 2009-02-27 | Виктор Ильич Мищевич | Method of constructing process platforms |
CN201546211U (en) * | 2009-09-28 | 2010-08-11 | 中交第二航务工程勘察设计院有限公司 | Static pressure fixed drilling platform assembled at sea |
CN102616344A (en) * | 2012-03-22 | 2012-08-01 | 中国海洋石油总公司 | Heavy draught truss type floating platform |
KR20130075594A (en) * | 2011-12-27 | 2013-07-05 | 현대중공업 주식회사 | Offshore fixed platform using solar energy |
CN204199261U (en) * | 2014-11-11 | 2015-03-11 | 江苏海王星海洋油气装备有限公司 | Settling type mobile platform |
CN105059489A (en) * | 2015-07-15 | 2015-11-18 | 中国海洋石油总公司 | Constantly stable offshore nuclear power platform |
CN205475167U (en) * | 2016-03-23 | 2016-08-17 | 中交第三航务工程勘察设计院有限公司 | Shallow sea territory in situ test survey platform |
CN206664888U (en) * | 2017-04-19 | 2017-11-24 | 合肥学院 | A kind of combined simple ocean platform |
-
2017
- 2017-04-19 CN CN201710258165.2A patent/CN106926989B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2473128Y (en) * | 2001-02-23 | 2002-01-23 | 胜利石油管理局钻井工艺研究院 | One pile single well oil production platform with seat cushion under water conduct frame |
RU2347866C2 (en) * | 2007-02-19 | 2009-02-27 | Виктор Ильич Мищевич | Method of constructing process platforms |
CN201546211U (en) * | 2009-09-28 | 2010-08-11 | 中交第二航务工程勘察设计院有限公司 | Static pressure fixed drilling platform assembled at sea |
KR20130075594A (en) * | 2011-12-27 | 2013-07-05 | 현대중공업 주식회사 | Offshore fixed platform using solar energy |
CN102616344A (en) * | 2012-03-22 | 2012-08-01 | 中国海洋石油总公司 | Heavy draught truss type floating platform |
CN204199261U (en) * | 2014-11-11 | 2015-03-11 | 江苏海王星海洋油气装备有限公司 | Settling type mobile platform |
CN105059489A (en) * | 2015-07-15 | 2015-11-18 | 中国海洋石油总公司 | Constantly stable offshore nuclear power platform |
CN205475167U (en) * | 2016-03-23 | 2016-08-17 | 中交第三航务工程勘察设计院有限公司 | Shallow sea territory in situ test survey platform |
CN206664888U (en) * | 2017-04-19 | 2017-11-24 | 合肥学院 | A kind of combined simple ocean platform |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109368794B (en) * | 2018-09-30 | 2021-10-26 | 杭州江润科技有限公司 | Construction method of aquatic plant composite ecological floating island |
CN109368794A (en) * | 2018-09-30 | 2019-02-22 | 杭州江润科技有限公司 | The construction method of water plant combined type ecological floating island |
CN109631845A (en) * | 2018-11-16 | 2019-04-16 | 浙江海洋大学 | Ocean platform oblique view equipment |
CN109631845B (en) * | 2018-11-16 | 2023-12-19 | 浙江海洋大学 | Ocean platform inclination observation equipment |
CN111114711A (en) * | 2019-12-30 | 2020-05-08 | 江苏省水文地质工程地质勘察院 | Offshore exploration platform capable of walking and moving by oneself |
CN112144562A (en) * | 2020-04-22 | 2020-12-29 | 中国海洋大学 | Pile foundation monitoring device for offshore operation platform |
WO2023020381A1 (en) * | 2021-08-19 | 2023-02-23 | 中交第三航务工程局有限公司 | Fabricated platform for offshore wind power monopile rock-socketed foundation construction |
CN113638386A (en) * | 2021-08-19 | 2021-11-12 | 中交第三航务工程局有限公司 | Offshore wind power single pile socketed foundation construction is with assembled platform |
CN113638386B (en) * | 2021-08-19 | 2022-09-09 | 中交第三航务工程局有限公司 | Offshore wind power single pile socketed foundation construction is with assembled platform |
CN114348192A (en) * | 2022-01-13 | 2022-04-15 | 东北石油大学 | Assembled FRP concrete cable tower shock absorption platform and its construction method |
CN114348192B (en) * | 2022-01-13 | 2024-04-26 | 东北石油大学 | Assembled FRP concrete guy cable tower type damping platform and construction method thereof |
CN114517470A (en) * | 2022-03-09 | 2022-05-20 | 中国建筑工程(香港)有限公司 | Construction method of overwater construction platform |
CN115059838A (en) * | 2022-06-10 | 2022-09-16 | 自然资源部第三海洋研究所 | Support for coast photography and hydrological observation |
CN115402470A (en) * | 2022-09-30 | 2022-11-29 | 中国能源建设集团江苏省电力建设第一工程有限公司 | Floating photovoltaic mooring system adaptive to high water level change |
CN115772884A (en) * | 2022-12-23 | 2023-03-10 | 大连理工大学 | A hinged fixed photovoltaic platform |
Also Published As
Publication number | Publication date |
---|---|
CN106926989B (en) | 2018-10-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106926989B (en) | A kind of combined simple ocean platform and its construction method | |
CN106930261B (en) | A simple ocean platform in the intertidal zone and its construction method | |
CN102191777B (en) | Steel sheet pile coefferdam structure and topdown construction method thereof | |
CN206664888U (en) | A kind of combined simple ocean platform | |
DE202020106244U1 (en) | Single pile composite foundation structure for offshore wind power | |
CN103669385A (en) | Method for improving pile group bearing capacity by means of reticular pile foundations | |
CN105350561B (en) | A kind of miniature well foundation of assembled for soft clay area power transmission tower | |
CN110820793A (en) | Composite foundation for collapsible loess area and construction method | |
CN211340800U (en) | Super dark foundation ditch earthwork excavation platform structure | |
CN109518711A (en) | A kind of jacket basis of conduit leg column bifurcated and its construction method | |
CN104264703A (en) | Miniature vertical and inclined combined pile for power transmission tower | |
CN103215965A (en) | Laminate type high-rise platform pile tower crane foundation and construction method | |
CN202969333U (en) | Steel truss rock-socketed wharf structure | |
CN205205853U (en) | Ecological green graticule mesh retaining wall structure | |
CN212052780U (en) | Oblique supporting type deep foundation pit supporting structure | |
CN219327097U (en) | Gravity caisson photovoltaic unit supporting structure | |
CN214574082U (en) | Foundation structure | |
CN207109842U (en) | A kind of rock foundation pole and tower foundation structure | |
CN202131602U (en) | Steel sheet pile cofferdam structure | |
CN206157758U (en) | But towage's truss marine wind turbine foundation structure of gravity type combination | |
CN104452798A (en) | Offshore wind turbine foundation structure and equipment and construction method of offshore wind turbine foundation equipment | |
CN213390202U (en) | Combined type polygonal tubular structure fan foundation | |
CN106368222B (en) | A kind of mound, suspension device and method of backfill for engineering construction | |
CN203213140U (en) | Laminate-type high pile cap tower crane foundation structure | |
CN103266624B (en) | Method for supporting oil and gas pipeline penetrating through karst active zone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |