CN106836035B - A kind of cofferdam dam filling construction being applicable in existing culvert under spoil embankment - Google Patents
A kind of cofferdam dam filling construction being applicable in existing culvert under spoil embankment Download PDFInfo
- Publication number
- CN106836035B CN106836035B CN201710224274.2A CN201710224274A CN106836035B CN 106836035 B CN106836035 B CN 106836035B CN 201710224274 A CN201710224274 A CN 201710224274A CN 106836035 B CN106836035 B CN 106836035B
- Authority
- CN
- China
- Prior art keywords
- embankment
- cofferdam
- culvert
- seepage
- spoil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01F—ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
- E01F5/00—Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
- E01F5/005—Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/02—Restraining of open water
- E02D19/04—Restraining of open water by coffer-dams, e.g. made of sheet piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Architecture (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本发明公开了一种适用矸石路堤下既有涵洞的围堰填筑方法,首先在涵洞两侧的路堤坡面上铺设防渗膜,然后设置围堰,围堰由圆弧段以及连接圆弧段两端的直线段组成,防渗膜被围堰的直线段压住,从而使得水无法从设有防渗膜覆盖段的路堤渗透进路堤,也就无法再通过涵洞洞身的沉降缝进入涵洞内部,从而能够尽快排空涵洞内部积水,降低涵洞内部的排水费用,降低工程造价。
The invention discloses a cofferdam filling method suitable for existing culverts under gangue embankments. Firstly, an anti-seepage film is laid on the embankment slopes on both sides of the culvert, and then a cofferdam is arranged. The cofferdam consists of circular arc sections and connecting circular arcs. The anti-seepage membrane is pressed by the straight section of the cofferdam, so that water cannot penetrate into the embankment from the embankment with the section covered by the anti-seepage membrane, and can no longer enter the culvert through the settlement joint of the culvert body The inside of the culvert can be drained as quickly as possible, the drainage cost inside the culvert can be reduced, and the project cost can be reduced.
Description
技术领域technical field
本发明涉及一种透水路堤下涵洞围堰填筑方法,适用于透水路堤下既有涵洞的维修加固工程,可减少涵洞维修加固时的排水费用,降低工程造价。The invention relates to a method for filling a culvert cofferdam under a permeable embankment, which is suitable for the maintenance and reinforcement project of the existing culvert under the permeable embankment, and can reduce drainage costs during the maintenance and reinforcement of the culvert and reduce the engineering cost.
背景技术Background technique
透水路堤通常用大石块、卵石或其他孔隙率高、透水性好的材料堆筑的具有透水能力的路堤。在采煤沉陷区大量使用的矸石路堤由矸石材料填筑而成。矸石本身为颗粒材料,加之施工碾压不充分,填料的透水性往往较高。因此,矸石路堤也可以认为是透水路堤。透水路堤下的涵洞由于各种原因,如年久失修、涵洞上覆填料厚度增加等,需要对其结构进行加固和维修。传统方法是在涵洞的两端洞口位置填筑围堰,将涵洞内部与外侧水系隔绝,然后将涵洞内的积水排空,获得施工作业空间。由于路堤本身为透水材料,在排水过程中,水可以透过路堤,然后通过涵洞洞身的沉降缝进入涵洞内部。尽管洞口位置由于围堰的存在,水无法进入涵洞,但路堤-洞身这一渗透路径,排水过程中水源源不断的进入到涵洞内部。为了使涵洞内部积水尽快排空,为涵洞维修加固创造良好作业空间,只能增大排水能力,造成排水费用迅速增加。这类问题已在淮南矿区的几个既有涵洞维修工程中凸显出来,排水费用有的个别工程高达上百万,占到工程总投资的20%。Permeable embankments are usually embankments with water permeability built with large stones, pebbles or other materials with high porosity and good water permeability. The gangue embankment widely used in the coal mining subsidence area is filled with gangue materials. Gangue itself is a granular material, combined with insufficient construction and rolling, the water permeability of the filler is often high. Therefore, gangue embankment can also be considered as permeable embankment. The culvert under the permeable embankment needs to be strengthened and repaired due to various reasons, such as disrepair for a long time, increase in the thickness of the filler over the culvert, etc. The traditional method is to fill cofferdams at both ends of the culvert to isolate the interior of the culvert from the outside water system, and then drain the accumulated water in the culvert to obtain construction work space. Since the embankment itself is a permeable material, water can pass through the embankment during the drainage process, and then enter the culvert through the settlement joints of the culvert body. Although water cannot enter the culvert due to the existence of the cofferdam at the entrance, the seepage path of the embankment-cave body allows water to continuously enter the culvert during the drainage process. In order to drain the accumulated water inside the culvert as soon as possible and create a good working space for the maintenance and reinforcement of the culvert, we can only increase the drainage capacity, resulting in a rapid increase in drainage costs. This kind of problem has been highlighted in several existing culvert maintenance projects in Huainan mining area. Some individual projects have drainage costs as high as millions, accounting for 20% of the total project investment.
发明内容Contents of the invention
发明目的:针对上述现有技术,提出一种适用矸石路堤下既有涵洞的围堰填筑方法,可以降低涵洞内部的排水费用。Purpose of the invention: Aiming at the above-mentioned prior art, a cofferdam filling method suitable for the existing culvert under the gangue embankment is proposed, which can reduce the drainage cost inside the culvert.
技术方案:一种适用于矸石路堤下既有涵洞围堰的防渗方法,包括如下步骤:Technical solution: an anti-seepage method suitable for existing culvert cofferdams under gangue embankments, including the following steps:
步骤a:在涵洞两侧的路堤坡面上铺设防渗膜;Step a: laying anti-seepage membrane on the embankment slope on both sides of the culvert;
步骤b:设置围堰,所述围堰由圆弧段以及连接圆弧段两端的直线段组成,所述防渗膜被围堰的直线段压住。Step b: setting a cofferdam, the cofferdam is composed of a circular arc segment and a straight line segment connecting two ends of the circular arc segment, and the anti-seepage membrane is pressed by the straight line segment of the cofferdam.
进一步的,所述防渗膜外伸至路堤坡脚线外侧2-3m处。Further, the anti-seepage membrane is extended to 2-3m outside the toe line of the embankment.
进一步的,所述防渗膜沿路堤方向的长度L根据路堤填料渗透系数以及围堰内外的水头差确定,具体计算方法为:Further, the length L of the anti-seepage membrane along the direction of the embankment is determined according to the permeability coefficient of the embankment filler and the water head difference inside and outside the cofferdam, and the specific calculation method is:
L=KΔ/vL=KΔ/v
式中,L为防渗膜长度,Δ为围堰内外水头差,K为路堤渗透系数,v为渗透速度。In the formula, L is the length of the anti-seepage membrane, Δ is the head difference inside and outside the cofferdam, K is the permeability coefficient of the embankment, and v is the seepage velocity.
进一步的,所述防渗膜的顶端露出水位线。Further, the top of the anti-seepage membrane exposes the water level.
进一步的,所述围堰由木桩及黏土填料组成。Further, the cofferdam is composed of wooden piles and clay filler.
进一步的,所述围堰直线段沿路堤方向外伸长度与防渗膜长度一致。Further, the extension length of the straight section of the cofferdam along the direction of the embankment is consistent with the length of the anti-seepage membrane.
有益效果:本发明的一种适用矸石路堤下既有涵洞的围堰填筑方法,其所适用的路堤由煤矸石填筑而成,透水性强。由于地下采矿活动,地表会发生沉降,为了维持路堤顶面标高不变,需要对路堤进行加高处理,导致涵洞顶面上覆填料厚度增加。因此,需要对涵洞结构进行加固,加固的方法通常有加厚涵洞侧墙以及顶板,或者在涵洞中设置矩形钢框架,与原有结构紧密接触,形成共同受力的复合结构。不管那一种加固方法,都需要在两段洞口填筑围堰,形成封闭区域,然后将该区域积水排空,人员、设备才能进入该区域,进行施工作业。本发明的围堰共由三段组成,弧线段需将涵洞洞口包围,两侧直线段沿路堤方向外伸。在路堤边坡坡面上铺设防渗膜,防渗膜需被直线段围堰压住,从而使得水无法从设有防渗膜覆盖段的路堤渗透进路堤,也就无法再通过涵洞洞身的沉降缝进入涵洞内部,从而能够尽快排空涵洞内部积水,降低涵洞内部的排水费用,降低工程造价。Beneficial effects: the present invention is a cofferdam filling method suitable for existing culverts under gangue embankments. The applicable embankment is filled with coal gangue and has strong water permeability. Due to underground mining activities, the ground surface will subside. In order to maintain the same elevation of the top of the embankment, it is necessary to heighten the embankment, resulting in an increase in the thickness of the filling on the top of the culvert. Therefore, it is necessary to strengthen the culvert structure. The reinforcement methods usually include thickening the side wall and roof of the culvert, or setting a rectangular steel frame in the culvert, which is in close contact with the original structure to form a composite structure under common stress. Regardless of the reinforcement method, it is necessary to fill in cofferdams at the entrances of the two sections to form a closed area, and then drain the accumulated water in the area so that personnel and equipment can enter the area and carry out construction operations. The cofferdam of the present invention is composed of three sections, the arc section needs to surround the culvert opening, and the straight sections on both sides extend outward along the direction of the embankment. The anti-seepage membrane is laid on the side slope of the embankment, and the anti-seepage membrane needs to be suppressed by the cofferdam of the straight section, so that water cannot penetrate into the embankment from the embankment with the section covered by the anti-seepage membrane, and can no longer pass through the culvert body The settlement joints in the culvert enter the interior of the culvert, so that the accumulated water inside the culvert can be drained as soon as possible, the drainage cost inside the culvert can be reduced, and the project cost can be reduced.
附图说明Description of drawings
图1是本发明的围堰立面图;Fig. 1 is a cofferdam elevation view of the present invention;
图2是本发明的围堰平面图;Fig. 2 is a cofferdam plan view of the present invention;
图3是本发明的路堤横断面图;Fig. 3 is an embankment cross-sectional view of the present invention;
附图中,1为涵洞,2为路堤坡面,3为防渗膜,4为路堤坡脚线,5为围堰,6为路肩边线,7为路堤中心线。In the accompanying drawings, 1 is a culvert, 2 is an embankment slope, 3 is an anti-seepage film, 4 is an embankment slope footline, 5 is a cofferdam, 6 is a shoulder line, and 7 is an embankment centerline.
具体实施方式Detailed ways
下面结合附图对本发明做更进一步的解释。The present invention will be further explained below in conjunction with the accompanying drawings.
一种适用于矸石路堤下既有涵洞围堰的防渗方法,包括如下步骤:An anti-seepage method applicable to existing culvert cofferdams under gangue embankments, comprising the following steps:
步骤a:在涵洞1两侧的路堤坡面2上铺设防渗膜3,防渗膜3外伸至路堤坡脚线4外侧2-3m处,防渗膜3的顶端露出水位线,如图3所示。防渗膜3沿路堤方向的单侧长度L根据路堤填料渗透系数以及围堰5内外的水头差确定,具体计算方法为:Step a: Lay the anti-seepage membrane 3 on the embankment slope 2 on both sides of the culvert 1. The anti-seepage membrane 3 extends to 2-3m outside the foot line 4 of the embankment, and the top of the anti-seepage membrane 3 exposes the water level line, as shown in the figure 3 shown. The length L of one side of the anti-seepage membrane 3 along the direction of the embankment is determined according to the permeability coefficient of the embankment filler and the water head difference inside and outside the cofferdam 5, and the specific calculation method is:
L=KΔ/vL=KΔ/v
式中,L为防渗膜长度,m;Δ为围堰内外水头差,m;K为路堤渗透系数,m/s;v为渗透速度,m/s。In the formula, L is the length of the anti-seepage membrane, m; Δ is the head difference inside and outside the cofferdam, m; K is the embankment permeability coefficient, m/s; v is the seepage velocity, m/s.
步骤b:设置围堰5,围堰5由圆弧段以及连接圆弧段两端的直线段组成,围堰5由木桩及黏土填料组成,外伸至路堤坡脚线4外侧以及路堤坡面2上的防渗膜3被围堰5的直线段压住,围堰5直线段沿路堤方向外伸长度与防渗膜长度一致,如图2所示。Step b: Set up the cofferdam 5. The cofferdam 5 is composed of a circular arc segment and a straight line connecting the two ends of the circular arc segment. The cofferdam 5 is composed of wooden piles and clay fillers, and extends to the outside of the embankment footline 4 and the embankment slope The anti-seepage membrane 3 on the 2 is pressed by the straight section of the cofferdam 5, and the extension length of the straight section of the cofferdam 5 along the direction of the embankment is consistent with the length of the anti-seepage membrane, as shown in Figure 2.
理论上,单位时间内渗入围堰范围内的水量为Sv,而围堰内部单位时间内排水能力为Q,如果有:Theoretically, the amount of water infiltrated into the cofferdam within a unit time is Sv, and the internal drainage capacity of the cofferdam is Q within a unit time, if:
Q≥SvQ≥Sv
则围堰内部不会有积水;式中,Q为水泵排水能力,m3/s;S为路堤在水位线以下部分横断面面积,m2。Then there will be no accumulated water inside the cofferdam; where, Q is the drainage capacity of the pump, m 3 /s; S is the cross-sectional area of the part of the embankment below the water level, m 2 .
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710224274.2A CN106836035B (en) | 2017-04-07 | 2017-04-07 | A kind of cofferdam dam filling construction being applicable in existing culvert under spoil embankment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710224274.2A CN106836035B (en) | 2017-04-07 | 2017-04-07 | A kind of cofferdam dam filling construction being applicable in existing culvert under spoil embankment |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106836035A CN106836035A (en) | 2017-06-13 |
| CN106836035B true CN106836035B (en) | 2018-11-27 |
Family
ID=59147463
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710224274.2A Expired - Fee Related CN106836035B (en) | 2017-04-07 | 2017-04-07 | A kind of cofferdam dam filling construction being applicable in existing culvert under spoil embankment |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106836035B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110004843A (en) * | 2019-05-06 | 2019-07-12 | 中国建设基础设施有限公司 | Coombe location antiseepage embankment structure and its construction method |
| CN111305095B (en) * | 2020-03-30 | 2024-08-20 | 中铁第五勘察设计院集团有限公司 | Pushing frame culvert of existing line of underpass railway |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101838995A (en) * | 2010-05-20 | 2010-09-22 | 中铁六局集团有限公司 | Simple water sealing method of steel sheet pile cofferdam for shoal affected by tidal water level |
| CN203113359U (en) * | 2013-03-18 | 2013-08-07 | 中国水电顾问集团成都勘测设计研究院 | Earth rock cofferdam structure |
| CN203429606U (en) * | 2013-07-23 | 2014-02-12 | 中国水电顾问集团华东勘测设计研究院 | Sediment retaining bank reconstructed from temporary cofferdam |
-
2017
- 2017-04-07 CN CN201710224274.2A patent/CN106836035B/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| CN106836035A (en) | 2017-06-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105696427B (en) | The construction method and its road structure of a kind of consolidation process newly built railway karst foundation | |
| CN106638669B (en) | Existing subway station building enclosure hardened system and method are worn under a kind of shield | |
| CN103758123B (en) | The construction method of manually digging hole filling pile retaining wall lining | |
| CN105179011B (en) | A kind of tunnel closure facility and its method for blocking | |
| CN107762535A (en) | Cut-and-cover tunnel secretly does construction technology under complicated geological environment | |
| CN103741714A (en) | Full-cover excavation top-down construction method for underground engineering | |
| CN104131575A (en) | Plugging and drainage method for dam foundation on karst highly developed stratum | |
| CN105200881B (en) | The construction method of High-cold regions roadbed freeze-harm Comprehensive Treatment structure | |
| CN103883328A (en) | Semi-covering semi-darkened construction method for separated tunnels downwards penetrating through high and steep V-shaped gully eccentric compression section | |
| CN106049196B (en) | Flexible pile combines ballastless track roadbed construction method with stake raft with section | |
| CN203684242U (en) | Mud flat area geotechnical bag mud composite cofferdam type underwater construction platform | |
| CN102787236A (en) | Ion-absorbing type rare earth in-situ mineral leaching mother liquor recovery process | |
| CN108517881A (en) | Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages and construction method | |
| CN206467684U (en) | Existing subway station building enclosure hardened system is worn under a kind of shield | |
| CN103670448A (en) | Underground pipeline protection device and support method applying underground pipeline protection device | |
| CN104895121B (en) | Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction | |
| CN108487331B (en) | An underground structure anti-floating system integrating corridor drainage and fertilizer tank anti-seepage | |
| CN106836035B (en) | A kind of cofferdam dam filling construction being applicable in existing culvert under spoil embankment | |
| CN104989410A (en) | Ground-settlement-resisting and collapse-preventing construction method for shallowly buried and darkly excavated tunnel | |
| CN208293588U (en) | A kind of Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages | |
| CN107100099A (en) | A kind of reinforcement means for railway culvert | |
| CN108277815B (en) | Cofferdam structure for construction of water taking head structure in river and construction method thereof | |
| CN106498967A (en) | A kind of open caisson with water sealing structure | |
| CN111636447B (en) | A ballast structure for slope of phosphogypsum storage yard | |
| CN105386505B (en) | The closely knit construction method of circular arc under sand substrate drainpipe |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181127 Termination date: 20200407 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |