CN106759399B - A kind of side slope vegetation ecological recovery system and method - Google Patents

A kind of side slope vegetation ecological recovery system and method Download PDF

Info

Publication number
CN106759399B
CN106759399B CN201710030075.8A CN201710030075A CN106759399B CN 106759399 B CN106759399 B CN 106759399B CN 201710030075 A CN201710030075 A CN 201710030075A CN 106759399 B CN106759399 B CN 106759399B
Authority
CN
China
Prior art keywords
slope
platform
fixed
planting soil
centimetres
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710030075.8A
Other languages
Chinese (zh)
Other versions
CN106759399A (en
Inventor
张明
张�杰
闫伟峰
李晶晶
李长军
袁敏
樊金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Science and Technology
Original Assignee
Henan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Science and Technology filed Critical Henan University of Science and Technology
Priority to CN201710030075.8A priority Critical patent/CN106759399B/en
Publication of CN106759399A publication Critical patent/CN106759399A/en
Application granted granted Critical
Publication of CN106759399B publication Critical patent/CN106759399B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/202Securing of slopes or inclines with flexible securing means
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G22/00Cultivation of specific crops or plants not otherwise provided for
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G9/00Cultivation in receptacles, forcing-frames or greenhouses; Edging for beds, lawn or the like
    • A01G9/02Receptacles, e.g. flower-pots or boxes; Glasses for cultivating flowers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Botany (AREA)
  • Cultivation Of Plants (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本发明公开了一种边坡植被生态恢复系统及其方法,涉及地质工程技术领域。在边坡底部开挖排水沟,边坡底部靠近排水沟的位置砌筑挡土墙,边坡位于挡土墙上方的坡面分台阶削方,形成多个斜坡和平台,斜坡上放置多个固定笼,并填埋种植土,平台上开挖凹槽,在凹槽中填埋砂土垫层和种植土,斜坡和平台上的种植土中开挖排水槽,最后在平台和斜坡上铺设三维土工格网,并在三维土工格网间隙的种植土中喷播苜蓿草种,为边坡植物制造有利的生长环境,同时对雨水也有很好的保持作用,具有广阔的应用价值。

The invention discloses a slope vegetation ecological restoration system and a method thereof, and relates to the technical field of geological engineering. Drainage ditches are excavated at the bottom of the slope, and a retaining wall is built near the bottom of the slope. The slope above the retaining wall is cut into squares to form multiple slopes and platforms. Fix the cage and fill the planting soil, excavate the groove on the platform, fill the sand cushion and planting soil in the groove, excavate the drainage groove in the planting soil on the slope and platform, and finally lay it on the platform and slope Three-dimensional geogrid, and spray alfalfa seeds in the planting soil in the gap of three-dimensional geogrid to create a favorable growth environment for slope plants, and at the same time, it also has a good effect on rainwater retention, and has broad application value.

Description

A kind of side slope vegetation ecological recovery system and method
Technical field
The present invention relates to Geological Engineering technical field, in particular to a kind of side slope vegetation ecological recovery system and method.
Background technique
With the economic development in China and the quickening of Development of China's Urbanization, the exploitation such as corresponding traffic, electric power, mine, water conservancy Construction project increasing number, China's area is larger and with a varied topography at the same time, because the factors such as artificial and natural produce largely Easy erosion side slope and channel.These side slopes and channel can not only cause serious soil erosion, or landslide, mud-rock flow, collapse It collapses, the root of flood and the environmental problems such as climatic deterioration and ecological disruption.Traditional side slope and RBS in channel direction mode such as grouts One systems such as that there is costs is high for the modes such as stone barricade, concrete revetment, Landscape Ecological is uncoordinated, revegetation is difficult Column problem.
Artificial ecology repairs side slope, and generally at restoration of the ecosystem initial stage, plant growth is vigorous, and soil and water conservation effect is good, so And over time, phytobiocoenose just will appear decay, and multiple green vegetation tends to unification, finally be difficult to form stabilization Phytobiocoenose.One of the main reasons for this is that stressing short-term recovery effects, single draft is often directly sowed, phytobiocoenose lacks Weary diversity;Another main cause is that side slope soil thickness is relatively thin, and shrub or dungarunga root growth are difficult, how to guarantee side The problem that plant root growth space is current urgent need to resolve is improved under the premise of stablizing in slope.
Summary of the invention
The embodiment of the invention provides a kind of side slope vegetation ecological recovery system and method, to solve in the prior art There are the problem of.
A kind of side slope vegetation ecological recovery system, the side slope including being set as multiple slopes and platform, the top of the side slope Portion and bottom all have the platform, intermediate to be connected by multiple alternate slopes with platform;On each slope Multiple fixed holes are offered, place a fixed cage in each fixed hole, the fixed cage is to be worked out by degradation material At hollow cube structure;Planting soil, the surface of planting soil and institute are filled on the slope between multiple fixed cages It states fixed cage upper surface to flush, fills crushed stone inside the fixed cage;A groove is opened up on each platform, it is described recessed Sand bed course is filled in slot, sand bed course upper berth sets planting soil;Have at least one wide along the platform on each platform The platform rhone that direction extends is spent, with the batter drainage slot that at least one extends along line of slope on each slope, The platform rhone is identical as the quantity of the batter drainage slot, and each platform rhone and a slope are arranged Sink connection;The slope and platform upper berth set three V dimensional grid, are followed closely using U-shaped steel by the both ends of the three V dimensional grid On the platform of the platform and bottom that are fixed at the top of the side slope;It is empty to be located at the three V dimensional grid on the platform and slope Sowing grass seeds by duster in planting soil in gap has clover grass seeds;The side slope bottom is the retaining wall being piled by multilayer fly ash hollow brick, The retaining wall bottom has gutter.
Preferably, the vertical height on each slope is 3 meters or 6 meters, and the gradient is 1:0.35 to 1:0.75, Mei Gesuo The width for stating platform is 1.5 to 2 meters.
Preferably, the depth in each fixed hole is 40 centimetres, and length and width is 80 centimetres to 1 meter, described solid The length, width and height for determining cage are 80 centimetres to 1 meter.
Preferably, the fixed hole is at least two rows, often come it is horizontally extending on the slope, in adjacent two rows The fixed hole be staggered, the distance between two neighboring described fixed hole is 1 meter in same row, and adjacent two rows are described solid Distance of the fixed hole on the slope line of slope is also 1 meter, and the fixed cage is made of bamboo cane or starch plastics.
Preferably, the depth of the groove is 40 centimetres, and the sand cushion thickness filled in the groove is 10 centimetres, institute Planting soil that sand bed course upper berth is set is stated with a thickness of 30 centimetres.
Preferably, the width of the platform rhone and batter drainage slot is 10 centimetres, 20 centimetres deep, bottom surface and side wall It is built using M10 mortar.
Preferably, the U-shaped steel nail length for being fixed on three V dimensional grid both ends is 1.2 meters, while the three-dimensional soil Work grid is fixed on the slope between the platform at the top of the side slope and the platform of bottom using 0.5 meter long of U-shaped steel nail On platform.
Preferably, the vertical height of the retaining wall is 3 meters, gradient 1:0.35.
Preferably, the depth of drainage ditch is 50 centimetres, and width is 30 centimetres, and bottom surface and side wall are built using M10 mortar It builds.
The present invention also provides a kind of side slope vegetation ecological recovery methods, which comprises
Gutter is excavated in side slope bottom;
The gear being piled by multilayer fly ash hollow brick is built in the slope surface in the gutter in the side slope bottom Cob wall;
The side slope is located in the slope surface above the retaining wall and divides the step side of cutting, forms multiple slopes and platform, institute It states and all has the platform at the top and bottom of side slope, it is intermediate to be connected by multiple alternate slopes with platform;
Multiple fixed holes are opened up on each slope, place a fixed cage in each fixed hole, it is described solid Determining cage is the hollow cube structure being compiled by degradation material;
Planting soil, table on the surface of planting soil and the fixed cage are filled between multiple fixed cages on the slope Face flushes, and fills crushed stone inside the fixed cage;
A groove is opened up on each platform, sand bed course is first filled in the groove, and sand bed course upper berth is set Planting soil;
At least one platform row extended along the berm width direction is excavated in the planting soil on each platform Sink, while at least one is excavated along the oblique of line of slope extension in the planting soil and/or fixed cage on each slope Slope rhone, the platform rhone is identical as the quantity of the batter drainage slot, and each platform rhone and one The batter drainage slot connection;
Three V dimensional grid is set on the slope and platform upper berth, is followed closely using U-shaped steel by the two of the three V dimensional grid End is fixed on the platform at the top of the side slope and the platform of bottom;
It sows grass seeds by duster clover grass seeds in the planting soil being located in three V dimensional grid gap on the platform and slope.
A kind of side slope vegetation ecological recovery system and method in the embodiment of the present invention excavate gutter in side slope bottom, Side slope bottom builds retaining wall close to the position in gutter, and the slope surface that side slope is located above retaining wall divides the step side of cutting, and is formed more A slope and platform place multiple fixed cages on slope, and fill planting soil, and groove is excavated on platform, fills sand in a groove Soil padding and planting soil excavate rhone in the planting soil on slope and platform, three-dimensional soil are finally laid on platform and slope Work grid, and clover grass seeds of sowing grass seeds by duster in the planting soil in three V dimensional grid gap are side slope while keeping stability of slope Plant manufactures advantageous growing environment, while also having good holding to act on to rainwater, has wide application value.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is a kind of side slope vegetation ecological recovery system structure diagram provided in an embodiment of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig.1, the present invention provides a kind of side slope vegetation ecological recovery systems, including are set as multiple 300 Hes of slope The side slope of platform 400 all has the platform 400 at the top and bottom of the side slope, intermediate by multiple alternate described Slope 300 and platform 400 connect.The vertical height on each slope 300 is 3 meters or 6 meters, and the gradient is 1:0.35 to 1: 0.75, the width of each platform 400 is 1.5 to 2 meters.
Multiple fixed holes are offered on each slope 300, the depth in each fixed hole is 40 centimetres, length and Width is 80 centimetres to 1 meter, places a fixed cage 310 in each fixed hole, the fixed cage 310 is by degradable The hollow cube structure that material is compiled into, length, width and height are 80 centimetres to 1 meter.In the present embodiment, the fixation is cheated extremely Few often to come horizontally extending on the slope 300 for two rows, the fixed hole in adjacent two rows is staggered.Together The distance between two neighboring described fixed hole is 1 meter in one row, and the adjacent two rows fixed hole is along the 300 slope surface side of slope Upward distance is also 1 meter, and the fixed cage 310 is made of degradable materials such as bamboo cane, starch plastics.
Planting soil, the surface of planting soil and the fixation are filled on the slope 300 between multiple fixed cages 310 310 upper surface of cage flushes, and fills crushed stone inside the fixed cage 310.
A groove 410 is opened up on each platform 400, the depth of the groove 410 is 40 centimetres, the groove The sand bed course of 10 cm thicks is first filled in 410, sand bed course upper berth sets the planting soil of 30 cm thicks.
With the platform rhone that at least one extends along 400 width direction of platform on each platform 400, often On a slope 300 also at least one along line of slope extend batter drainage slot, the platform rhone with it is described The quantity of batter drainage slot is identical, and each platform rhone is connected to a batter drainage slot.The platform row The width of sink and batter drainage slot is 10 centimetres, and 20 centimetres deep, bottom surface and side wall are built using M10 mortar.
Three V dimensional grid 500 is laid on the slope 300 and platform 400, the three V dimensional grid 500 is high intensity Earth-fixing mat is moulded, is stereoscopic graticule made of being bonded after heating as multilayer polyethylene material plastic stereo net and High Strength Plane net Structure.In the present embodiment, the three V dimensional grid 500 extends to the platform of bottom from the platform 400 at the top of the side slope 400, while the both ends of the three V dimensional grid 500 being fixed at the top of the side slope using 1.2 meters long of U-shaped steel nail 510 Platform 400 and bottom platform 400 on, it is intermediate to be followed closely with 0.5 meter long of U-shaped steel by the three V dimensional grid 500 It is fixed on the slope 300 and platform 400 between the platform 400 of the platform 400 and bottom that are located at the top of the side slope.
Sowing grass seeds by duster in the planting soil being located in 500 gap of three V dimensional grid on the platform 400 and slope 300 has lucerne Mu grass seeds.
The side slope bottom is the retaining wall 200 being piled by multilayer fly ash hollow brick, the retaining wall 200 it is vertical Height is 3 meters, gradient 1:0.35.
200 bottom of retaining wall has gutter 100, and 100 depth of gutter is 50 centimetres, and width is 30 lis Rice, bottom surface and side wall are built using M10 mortar.
Based on identical inventive concept, the present invention also provides a kind of side slope vegetation ecological recovery method, the realities of this method Apply the implementation that can refer to above system, which comprises
It is 50 centimetres in side slope bottom cutting depth, the gutter 100 that width is 30 centimetres, 100 bottom surface of gutter It is built with side wall using M10 mortar;
Retaining wall 200 is built in the slope surface in the gutter 100 in the side slope bottom, the retaining wall 200 Vertical height is 3 meters, gradient 1:0.35, is piled by multilayer fly ash hollow brick;
The side slope is located in the slope surface of 200 top of retaining wall and divides the step side of cutting, forms multiple 300 peace of slope Platform 400 all has the platform 400 at the top and bottom of the side slope, intermediate by multiple alternate 300 Hes of slope Platform 400 connects, and the vertical height on each slope 300 is 3 meters or 6 meters, and the gradient is 1:0.35 to 1:0.75, Mei Gesuo The width for stating platform 400 is 1.5 to 2 meters;
Multiple fixed holes are opened up on each slope 300, the depth in each fixed hole is 40 centimetres, length and Width is 80 centimetres to 1 meter, places a fixed cage 310 in each fixed hole, the fixed cage 310 is by degradable The hollow cube structure that material is compiled into, length, width and height are 80 centimetres to 1 meter.In the present embodiment, the fixation is cheated extremely Few often to come horizontally extending on the slope 300 for two rows, the fixed hole in adjacent two rows is staggered.Together The distance between two neighboring described fixed hole is 1 meter in one row, and the adjacent two rows fixed hole is along the 300 slope surface side of slope Upward distance is also 1 meter, and the fixed cage 310 is made of degradable materials such as bamboo cane, starch plastics;
Planting soil, the surface of planting soil and the fixation are filled between multiple fixed cages 310 on the slope 300 310 upper surface of cage flushes, and fills crushed stone inside the fixed cage 310;
A groove 410 is opened up on each platform 400, the depth of the groove 410 is 40 centimetres, the groove The sand bed course of 10 cm thicks is first filled in 410, sand bed course upper berth sets the planting soil of 30 cm thicks;
Excavate what at least one extended along 400 width direction of platform in the planting soil on each platform 400 Platform rhone, while at least one is excavated along slope surface in the planting soil and/or fixed cage 310 on each slope 300 The batter drainage slot that direction extends, the platform rhone is identical as the quantity of the batter drainage slot, and each platform Rhone is connected to a batter drainage slot.The width of the platform rhone and batter drainage slot is 10 centimetres, deeply 20 Centimetre, bottom surface and side wall are built using M10 mortar;
Three V dimensional grid 500 is laid on the slope 300 and platform 400, the three V dimensional grid 500 is high-strength Degree modeling earth-fixing mat, is solid made of being bonded after heating as multilayer polyethylene material plastic stereo net and High Strength Plane net Web frame.In the present embodiment, the three V dimensional grid 500 extends to the flat of bottom from the platform 400 at the top of the side slope Platform 400, while the both ends of the three V dimensional grid 500 are fixed on the side slope top using 1.2 meters long of U-shaped steel nail 510 It is intermediate to be followed closely with 0.5 meter long of U-shaped steel by the three V dimensional grid on the platform 400 in portion and the platform 400 of bottom 500 are fixed on slope 300 and platform 400 between the platform 400 at the top of the side slope and the platform 400 of bottom;
It sows grass seeds by duster lucerne in the planting soil being located in 500 gap of three V dimensional grid on the platform 400 and slope 300 Mu grass seeds.
Although preferred embodiments of the present invention have been described, it is created once a person skilled in the art knows basic Property concept, then additional changes and modifications may be made to these embodiments.So it includes excellent that the following claims are intended to be interpreted as It selects embodiment and falls into all change and modification of the scope of the invention.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art Mind and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.

Claims (10)

1. a kind of side slope vegetation ecological recovery system, which is characterized in that the side slope including being set as multiple slopes and platform, it is described The platform is all had at the top and bottom of side slope, it is intermediate to be connected by multiple alternate slopes with platform;Each institute It states and offers multiple fixed holes on slope, place a fixed cage in each fixed hole, the fixed cage is by degradable The hollow cube structure that material is compiled into;Planting soil is filled between multiple fixed cages on the slope, planting soil Surface is flushed with the fixed cage upper surface, fills crushed stone inside the fixed cage;Opened up on each platform one it is recessed Slot fills sand bed course in the groove, and sand bed course upper berth sets planting soil;Have at least one along institute on each platform The platform rhone of berm width direction extension is stated, has at least one along the slope that line of slope extends on each slope Rhone, the platform rhone is identical as the quantity of the batter drainage slot, and each platform rhone and an institute State the connection of batter drainage slot;The slope and platform upper berth set three V dimensional grid, are followed closely using U-shaped steel by the three V dimensional lattice The both ends of net are fixed on the platform at the top of the side slope and the platform of bottom;It is located at the three-dimensional soil on the platform and slope Sowing grass seeds by duster in planting soil in work grid gap has clover grass seeds;The side slope bottom is piled by multilayer fly ash hollow brick Retaining wall, the retaining wall bottom have gutter.
2. the system as claimed in claim 1, which is characterized in that the vertical height on each slope is 3 meters or 6 meters, slope Degree is 1:0.35 to 1:0.75, and the width of each platform is 1.5 to 2 meters.
3. the system as claimed in claim 1, which is characterized in that the depth in each fixed hole is 40 centimetres, length and width Degree is 80 centimetres to 1 meter, and the length, width and height of the fixed cage are 80 centimetres to 1 meter.
4. system as claimed in claim 3, which is characterized in that the fixed hole is at least two rows, often comes on the slope Horizontally extending, the fixed hole in adjacent two rows is staggered, in same row between the two neighboring fixed hole Distance be 1 meter, the adjacent two rows fixed distance cheated on the slope line of slope is also 1 meter, the fixed cage by Bamboo cane or starch plastics are made.
5. the system as claimed in claim 1, which is characterized in that the depth of the groove is 40 centimetres, is filled in the groove Sand cushion thickness be 10 centimetres, the planting soil that sand bed course upper berth is set is with a thickness of 30 centimetres.
6. the system as claimed in claim 1, which is characterized in that the width of the platform rhone and batter drainage slot is 10 lis Rice, 20 centimetres deep, bottom surface and side wall are built using M10 mortar.
7. the system as claimed in claim 1, which is characterized in that be fixed on the U-shaped steel nail length at three V dimensional grid both ends Degree is 1.2 meters, while the three V dimensional grid is fixed on putting down at the top of the side slope using 0.5 meter long of U-shaped steel nail On slope and platform between platform and the platform of bottom.
8. the system as claimed in claim 1, which is characterized in that the vertical height of the retaining wall is 3 meters, the gradient 1: 0.35。
9. the system as claimed in claim 1, which is characterized in that the depth of drainage ditch is 50 centimetres, and width is 30 centimetres, Bottom surface and side wall are built using M10 mortar.
10. a kind of side slope vegetation ecological recovery method, which is characterized in that the described method includes:
Gutter is excavated in side slope bottom;
The retaining wall being piled by multilayer fly ash hollow brick is built in the slope surface in the gutter in the side slope bottom;
The side slope is located in the slope surface above the retaining wall and divides the step side of cutting, forms multiple slopes and platform, the side The platform is all had at the top and bottom of slope, it is intermediate to be connected by multiple alternate slopes with platform;
Multiple fixed holes are opened up on each slope, place a fixed cage, the fixed cage in each fixed hole For the hollow cube structure being compiled by degradation material;
Planting soil is filled between multiple fixed cages on the slope, the surface of planting soil and the fixed cage upper surface are neat It is flat, crushed stone is filled inside the fixed cage;
A groove is opened up on each platform, sand bed course is first filled in the groove, and sand bed course upper berth sets plantation Soil;
At least one platform rhone extended along the berm width direction is excavated in the planting soil on each platform, At least one batter drainage extended along line of slope is excavated in the planting soil and/or fixed cage on each slope simultaneously Slot, the platform rhone is identical as the quantity of the batter drainage slot, and each platform rhone and one it is described tiltedly The connection of slope rhone;
Three V dimensional grid is set on the slope and platform upper berth, is followed closely using U-shaped steel and consolidates the both ends of the three V dimensional grid On the platform of the platform and bottom that are scheduled at the top of the side slope;
It sows grass seeds by duster clover grass seeds in the planting soil being located in three V dimensional grid gap on the platform and slope.
CN201710030075.8A 2017-01-16 2017-01-16 A kind of side slope vegetation ecological recovery system and method Expired - Fee Related CN106759399B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710030075.8A CN106759399B (en) 2017-01-16 2017-01-16 A kind of side slope vegetation ecological recovery system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710030075.8A CN106759399B (en) 2017-01-16 2017-01-16 A kind of side slope vegetation ecological recovery system and method

Publications (2)

Publication Number Publication Date
CN106759399A CN106759399A (en) 2017-05-31
CN106759399B true CN106759399B (en) 2018-12-21

Family

ID=58945924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710030075.8A Expired - Fee Related CN106759399B (en) 2017-01-16 2017-01-16 A kind of side slope vegetation ecological recovery system and method

Country Status (1)

Country Link
CN (1) CN106759399B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107912182A (en) * 2017-11-16 2018-04-17 安徽金联地矿科技有限公司 A kind of useless slope is with degradable growth belt and its plants method of taking off
CN108374393A (en) * 2018-04-27 2018-08-07 中国水利水电科学研究院 The hard slope formula shore protection and remodeling method in situ for planting raw formula ecology transformation
CN109505291B (en) * 2018-06-06 2021-04-27 湖北文理学院 Soil slope surface drainage method
CN109763497A (en) * 2018-12-28 2019-05-17 北京顺景园林有限公司 A flexible slope ecological protection system and its construction method
CN109729935A (en) * 2019-03-05 2019-05-10 湖北红杏生态环境科技有限公司 A kind of method of exposed geology slopes reparation greening
CN109997592A (en) * 2019-04-28 2019-07-12 浙江原野建设有限公司 A kind of side slope vegetation ecological recovery method
CN111255045B (en) * 2020-01-17 2021-06-04 兖矿东华建设有限公司地矿建设分公司 Method for monitoring and ecologically treating water resource pollution in mining area
CN115288165A (en) * 2022-08-17 2022-11-04 国网福建省电力有限公司电力科学研究院 A graded slope protection method for slope protection

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04118427A (en) * 1990-09-06 1992-04-20 Yamatomi Sangyo Kk Block for construction
CN102257945A (en) * 2010-10-30 2011-11-30 鞍钢集团矿业公司 Wicker basket hole fixing planting method for mine side slope
CN203530994U (en) * 2013-10-30 2014-04-09 中国水电顾问集团成都勘测设计研究院有限公司 Stone slag field side slope ecological protection structure
CN205387710U (en) * 2016-02-29 2016-07-20 西安科技大学 Loess area slope vegetation plants guarantee masonry structure system
CN106168030A (en) * 2016-07-27 2016-11-30 西北大学 A kind of Loess Landslide countermeasure system based on restoration of the ecosystem
CN106284378A (en) * 2016-08-30 2017-01-04 西北大学 A kind of Canal in Loess Area side slope soil and water conservation method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04118427A (en) * 1990-09-06 1992-04-20 Yamatomi Sangyo Kk Block for construction
CN102257945A (en) * 2010-10-30 2011-11-30 鞍钢集团矿业公司 Wicker basket hole fixing planting method for mine side slope
CN203530994U (en) * 2013-10-30 2014-04-09 中国水电顾问集团成都勘测设计研究院有限公司 Stone slag field side slope ecological protection structure
CN205387710U (en) * 2016-02-29 2016-07-20 西安科技大学 Loess area slope vegetation plants guarantee masonry structure system
CN106168030A (en) * 2016-07-27 2016-11-30 西北大学 A kind of Loess Landslide countermeasure system based on restoration of the ecosystem
CN106284378A (en) * 2016-08-30 2017-01-04 西北大学 A kind of Canal in Loess Area side slope soil and water conservation method

Also Published As

Publication number Publication date
CN106759399A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN106759399B (en) A kind of side slope vegetation ecological recovery system and method
CN108221861A (en) A kind of ecological slope protection structure to prevent erosion and its construction method
CN103603316A (en) Ecological cement and geocell combination slope protection technology
CN207392127U (en) A kind of bank protection barricade applied to hydraulic engineering
CN104294829A (en) Rock slope combined type protective structure and method
CN206693140U (en) A kind of protection slope
CN211395577U (en) Ecological interlocking grass planting brick slope protection structure
CN216973293U (en) Ecological retaining brick with novel structure
CN102134842B (en) Method for building fishpond slope protection
CN211006526U (en) Road soil slope green ecological protection structure suitable for ecological sensitive area
CN222313917U (en) A flexible honeycomb grid protection structure for preventing erosion gully bank expansion
CN209741762U (en) combined ecological bank protection structure
CN217710769U (en) Anchor pile type geocell structure for excavation slope ecological protection
CN206418460U (en) Ecological slope protection structure
CN105200998A (en) Planting structure and ecological slope protection structure
CN105386449B (en) Gully ecological slope protection structure and construction method thereof
CN204940307U (en) Pattern of farming and ecological slope protection structure
CN114086507A (en) An ecological revetment process with high soil and water conservation
CN109338988B (en) Single-side wing wall type ecological type spur dike
CN208379542U (en) A low water level bank protection block construction structure
CN206538735U (en) A kind of environmental compound shore structure
CN201865114U (en) Protective structure for vegetation concrete side slope
CN207686047U (en) A kind of ecological block wall
CN206467631U (en) The domatic beam attachment structure of ecological slope protection
CN205804371U (en) A kind of structure protecting swell-shrink characteristic ground cut slope

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181221

Termination date: 20210116