CN106703068A - 一种混凝土塔筒与基础的连接方式 - Google Patents
一种混凝土塔筒与基础的连接方式 Download PDFInfo
- Publication number
- CN106703068A CN106703068A CN201710119642.7A CN201710119642A CN106703068A CN 106703068 A CN106703068 A CN 106703068A CN 201710119642 A CN201710119642 A CN 201710119642A CN 106703068 A CN106703068 A CN 106703068A
- Authority
- CN
- China
- Prior art keywords
- concrete tower
- foundation ring
- anchor bar
- circular connector
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
- E02D27/425—Foundations for poles, masts or chimneys specially adapted for wind motors masts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/12—Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Chemical & Material Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
Abstract
本发明公开了一种混凝土塔筒与基础的连接方式,包括混凝土塔筒、环形连接件和基础环,所述混凝土塔筒上开设的钢筋孔内锚固钢筋,混凝土塔筒内沿锚固钢筋呈环状设置约束钢筋用于对锚固钢筋加以固定,混凝土塔筒的下端设有环形连接件,环形连接件上设有与锚固钢筋对应的钢筋孔,环形连接件的下侧设有基础环,基础环的顶部设有与锚固钢筋对应的法兰,锚固钢筋依次穿过环形连接件上的钢筋孔和基础环顶部法兰上的螺栓孔,基础环的顶部法兰下设有用于对锚固钢筋固定的螺母。本发明施工更为简便,锚固钢筋、连接件和法兰盘等构件易统一尺寸和标准,便于大量生产与检验和控制连接质量。
Description
技术领域
本发明涉及风力发电领域,具体是一种混凝土塔筒与基础的连接方式。
背景技术
风力发电机组简称风机,风机中主要包括叶轮、发电机、塔架等部件,其中塔架用于支撑叶轮和发电机。随着风力发电技术的发展,出现了钢-混凝土混合的塔架,塔架各部分之间的连接方式也得到了越来越多的关注。
现有技术中提出了使用锚固头连接混凝土塔筒与基础环的方案。在基础环顶部设置有顶部法兰,混凝土塔底部设置有底部法兰。顶部法兰与底部法兰的重叠部分开设有通孔,在通孔中穿设有锚固头。锚固头包括锚板与穿设于锚板中的预应力钢筋。但施加预应力易使混凝土筒产生裂缝,影响风电塔架质量。除此之外,这种技术方案还存在步骤较为复杂,施工难度大,不便于检验连接质量的缺点。
发明内容
本发明的目的在于提供一种混凝土塔筒与基础的连接方式,以解决上述背景技术中提出的问题。
为实现上述目的,本发明提供如下技术方案:
一种混凝土塔筒与基础的连接方式,包括混凝土塔筒、环形连接件和基础环,所述混凝土塔筒上开设的钢筋孔内锚固钢筋,且锚固钢筋从混凝土塔筒的下端面伸出一定长度,所述混凝土塔筒内沿锚固钢筋呈环状设置约束钢筋用于对锚固钢筋加以固定,所述混凝土塔筒的下端设有环形连接件,环形连接件上设有与锚固钢筋对应的钢筋孔,所述环形连接件的下侧设有基础环,基础环的顶部设有与锚固钢筋对应的法兰,所述锚固钢筋依次穿过环形连接件上的钢筋孔和基础环顶部法兰上的螺栓孔,所述基础环的顶部法兰下设有用于对锚固钢筋固定的螺母。
作为本发明进一步的方案:所述锚固钢筋直径小于钢筋孔直径。
作为本发明进一步的方案:所述钢筋孔在混凝土塔筒环形边缘与环形连接件上均匀分布,螺栓孔在基础环顶部法兰上均匀分布。
作为本发明进一步的方案:所述环形连接件为钢板、钢管或圆钢。
作为本发明进一步的方案:所述混凝土塔筒内的约束钢筋成环状布置。
与现有技术相比,本发明的有益效果是:该装置施工更为简便,锚固钢筋、连接件和法兰盘等构件易统一尺寸和标准,便于大量生产与检验和控制连接质量。
附图说明
图1是本连接方式所提供的混凝土塔筒与基础环连接处立体示意图。
图2是本连接方式所提供的混凝土塔筒与基础环连接处的剖面图。
图3是环形连接件的立体示意图。
图中:1-混凝土塔筒,2-环形连接件,3-基础环,4-螺母,5-锚固钢筋,6-约束钢筋。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
请参阅图1~3,本发明实施例中,一种混凝土塔筒与基础的连接方式,包括混凝土塔筒1、环形连接件2和基础环3,所述混凝土塔筒1上开设的钢筋孔内锚固钢筋5,且锚固钢筋5从混凝土塔筒1的下端面伸出一定长度,所述混凝土塔筒1内沿锚固钢筋5呈环状设置约束钢筋6用于对锚固钢筋5加以固定,所述混凝土塔筒1的下端设有环形连接件2,环形连接件2上设有与锚固钢筋5对应的钢筋孔,所述环形连接件2的下侧设有基础环3,基础环3的顶部设有与锚固钢筋5对应的法兰,所述锚固钢筋5依次穿过环形连接件2上的钢筋孔和基础环3顶部法兰上的螺栓孔,所述基础环3的顶部法兰下设有用于对锚固钢筋5固定的螺母4。
进一步的:所述锚固钢筋5直径小于钢筋孔直径。
进一步的:所述钢筋孔在混凝土塔筒1环形边缘与环形连接件2上均匀分布,螺栓孔在基础环3顶部法兰上均匀分布。
进一步的:所述环形连接件2为钢板、钢管或圆钢。
进一步的:所述混凝土塔筒1内的约束钢筋6成环状布置。
本发明的工作原理:在连接混凝土塔筒1与基础环3时,首先在开有钢筋孔的混凝土塔筒1内锚固钢筋5,并使锚固钢筋5穿过钢筋孔,伸出足够长度;在混凝土内沿锚固钢筋5呈环状设置约束钢筋6对锚固钢筋5加以固定;将环形连接件2吊装至基础环3之上,并使基础环3顶部法兰的螺栓孔与环形连接件2的钢筋孔对齐;将混凝土塔筒1吊装于环形连接件2之上,使锚固钢筋5穿过环形连接件2的钢筋孔与基础环3顶部法兰的螺栓孔;最后在基础环3顶部法兰下使用螺母4对锚固钢筋5加以固定。
以上的仅是本发明的优选实施方式,应当指出,对于本领域的技术人员来说,在不脱离本发明构思的前提下,还可以作出若干变形和改进,这些也应该视为本发明的保护范围,这些都不会影响本发明实施的效果和专利的实用性。
Claims (5)
1.一种混凝土塔筒与基础的连接方式,包括混凝土塔筒、环形连接件和基础环,其特征在于,所述混凝土塔筒上开设的钢筋孔内锚固钢筋,且锚固钢筋从混凝土塔筒的下端面伸出一定长度,所述混凝土塔筒内沿锚固钢筋呈环状设置约束钢筋用于对锚固钢筋加以固定,所述混凝土塔筒的下端设有环形连接件,环形连接件上设有与锚固钢筋对应的钢筋孔,所述环形连接件的下侧设有基础环,基础环的顶部设有与锚固钢筋对应的法兰,所述锚固钢筋依次穿过环形连接件上的钢筋孔和基础环顶部法兰上的螺栓孔,所述基础环的顶部法兰下设有用于对锚固钢筋固定的螺母。
2.根据权利要求1所述的混凝土塔筒与基础的连接方式,其特征在于,所述锚固钢筋直径小于钢筋孔直径。
3.根据权利要求1或2所述的混凝土塔筒与基础的连接方式,其特征在于,所述钢筋孔在混凝土塔筒环形边缘与环形连接件上均匀分布,螺栓孔在基础环顶部法兰上均匀分布。
4.根据权利要求1所述的混凝土塔筒与基础的连接方式,其特征在于,所述环形连接件为钢板、钢管或圆钢。
5.根据权利要求1所述的混凝土塔筒与基础的连接方式,其特征在于,所述混凝土塔筒内的约束钢筋成环状布置。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710119642.7A CN106703068A (zh) | 2017-03-01 | 2017-03-01 | 一种混凝土塔筒与基础的连接方式 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710119642.7A CN106703068A (zh) | 2017-03-01 | 2017-03-01 | 一种混凝土塔筒与基础的连接方式 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106703068A true CN106703068A (zh) | 2017-05-24 |
Family
ID=58917282
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710119642.7A Pending CN106703068A (zh) | 2017-03-01 | 2017-03-01 | 一种混凝土塔筒与基础的连接方式 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106703068A (zh) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4575061B2 (ja) * | 2004-07-23 | 2010-11-04 | 第一建設機工株式会社 | 洋上風力発電施設の施工方法 |
CN103821677A (zh) * | 2014-03-20 | 2014-05-28 | 哈尔滨工业大学(威海) | 装配式预应力活性粉末混凝土风电塔架 |
CN203755778U (zh) * | 2014-03-27 | 2014-08-06 | 哈尔滨工业大学(威海) | 装配式体外预应力活性粉末混凝土风电塔架 |
CN104278690A (zh) * | 2014-10-11 | 2015-01-14 | 国家电网公司 | 一种新型高压输电线路铁塔桩基础 |
CN204282394U (zh) * | 2014-12-04 | 2015-04-22 | 瑞风能源(武汉)工程技术有限公司 | 一种风机基础及用于风机基础的预应力组件 |
CN204510987U (zh) * | 2015-03-04 | 2015-07-29 | 陈宝民 | 风机混凝土塔筒与基础的一体化结构 |
CN104929148A (zh) * | 2015-07-06 | 2015-09-23 | 同济大学建筑设计研究院(集团)有限公司 | 风力发电塔基础环基础的倒装加固系统及其加固方法 |
CN106436735A (zh) * | 2016-07-27 | 2017-02-22 | 中国能源建设集团安徽电力建设第工程有限公司 | 一种风机基础环的安装方法 |
CN206941633U (zh) * | 2017-03-01 | 2018-01-30 | 北京建筑大学 | 一种混凝土塔筒与基础的连接结构 |
-
2017
- 2017-03-01 CN CN201710119642.7A patent/CN106703068A/zh active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4575061B2 (ja) * | 2004-07-23 | 2010-11-04 | 第一建設機工株式会社 | 洋上風力発電施設の施工方法 |
CN103821677A (zh) * | 2014-03-20 | 2014-05-28 | 哈尔滨工业大学(威海) | 装配式预应力活性粉末混凝土风电塔架 |
CN203755778U (zh) * | 2014-03-27 | 2014-08-06 | 哈尔滨工业大学(威海) | 装配式体外预应力活性粉末混凝土风电塔架 |
CN104278690A (zh) * | 2014-10-11 | 2015-01-14 | 国家电网公司 | 一种新型高压输电线路铁塔桩基础 |
CN204282394U (zh) * | 2014-12-04 | 2015-04-22 | 瑞风能源(武汉)工程技术有限公司 | 一种风机基础及用于风机基础的预应力组件 |
CN204510987U (zh) * | 2015-03-04 | 2015-07-29 | 陈宝民 | 风机混凝土塔筒与基础的一体化结构 |
CN104929148A (zh) * | 2015-07-06 | 2015-09-23 | 同济大学建筑设计研究院(集团)有限公司 | 风力发电塔基础环基础的倒装加固系统及其加固方法 |
CN106436735A (zh) * | 2016-07-27 | 2017-02-22 | 中国能源建设集团安徽电力建设第工程有限公司 | 一种风机基础环的安装方法 |
CN206941633U (zh) * | 2017-03-01 | 2018-01-30 | 北京建筑大学 | 一种混凝土塔筒与基础的连接结构 |
Non-Patent Citations (1)
Title |
---|
赵显忠等: "《风力发电工程技术丛书风电场施工与安装》", 31 August 2015 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106223368B (zh) | 玻璃纤维预应力锚杆锚固结构、其加载装置及加载方法 | |
CN101812842B (zh) | 无张力灌注桩结构 | |
CN106988483A (zh) | 一种装配式钢筋混凝土u形框架梁及其施工方法 | |
CN108699796A (zh) | 用于风力机的基座 | |
CN101936170B (zh) | 一种洞室顶拱模喷混凝土施工结构及工艺 | |
WO2012019505A1 (zh) | 桩锚杆基础结构 | |
CN206396816U (zh) | 一种风机基础多维度加固结构 | |
CN105179183A (zh) | 一种预应力混凝土风电塔架体系及其施工方法 | |
CN102505636A (zh) | 一种双薄壁墩连续刚构桥0号块施工方法 | |
CN106545472A (zh) | 全向预应力抗疲劳组合钢结构风塔及其安装方法 | |
CN203625918U (zh) | 锚索式风力发电机基础结构 | |
WO2024007618A1 (zh) | 一种用于海上风电单桩基础加固、纠偏的装置及方法 | |
CN215057908U (zh) | 一种已建风电混塔基础和钢管塔筒的转换结构 | |
CN112195957B (zh) | 一种风机塔筒与基础的加强型连接结构及施工方法 | |
CN206190458U (zh) | 全向预应力抗疲劳组合钢结构风塔 | |
CN206941633U (zh) | 一种混凝土塔筒与基础的连接结构 | |
CN201649071U (zh) | 无张力灌注桩结构 | |
CN106703068A (zh) | 一种混凝土塔筒与基础的连接方式 | |
CN108532625A (zh) | 一种风力发电机组基础 | |
CN106704108A (zh) | 一种混凝土塔筒与钢塔筒的连接方式 | |
CN207079809U (zh) | 一种装配式钢筋混凝土u形框架梁及制作模具和连接钢架 | |
CN211006741U (zh) | 一种p&h型岩石锚杆风机基础的加固结构 | |
CN205742249U (zh) | 一种预应力混凝土封底型承台模板 | |
CN206770117U (zh) | 一种混凝土塔筒与钢塔筒的连接结构 | |
CN206800195U (zh) | 一种斜拉桥混凝土索塔用锚拉板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170524 |