CN106609601A - Container modularized building - Google Patents
Container modularized building Download PDFInfo
- Publication number
- CN106609601A CN106609601A CN201510691389.3A CN201510691389A CN106609601A CN 106609601 A CN106609601 A CN 106609601A CN 201510691389 A CN201510691389 A CN 201510691389A CN 106609601 A CN106609601 A CN 106609601A
- Authority
- CN
- China
- Prior art keywords
- container
- coupling bar
- bolt
- hole
- firmware
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000001808 coupling Effects 0.000 claims description 112
- 238000010168 coupling process Methods 0.000 claims description 112
- 238000005859 coupling reaction Methods 0.000 claims description 112
- 239000007787 solid Substances 0.000 claims description 103
- 238000009434 installation Methods 0.000 claims description 54
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 229910000975 Carbon steel Inorganic materials 0.000 claims description 5
- 239000010962 carbon steel Substances 0.000 claims description 5
- 230000000875 corresponding Effects 0.000 claims description 4
- 238000004806 packaging method and process Methods 0.000 claims description 4
- 238000005452 bending Methods 0.000 claims description 3
- 230000000712 assembly Effects 0.000 abstract 2
- 238000003466 welding Methods 0.000 description 4
- 238000003032 molecular docking Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000002708 enhancing Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000006011 modification reaction Methods 0.000 description 2
- 230000035939 shock Effects 0.000 description 2
- 238000004642 transportation engineering Methods 0.000 description 2
- 241001080929 Zeugopterus punctatus Species 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
Abstract
The invention discloses a container modularized building which comprises at least one container, wherein the container comprises a base frame; the base frame comprises a bottom end beam and a bottom side beam; and the bottom end beam is connected to the bottom side beam by an angular part. The base frame is characterized in that at least two side face connecting bolt-fixation assemblies are disposed on the bottom side beam; each side face connecting bolt-fixation assembly comprises a bolt fixation module, a connecting bolt fixation part and a fastening bolt; the bolt fixation module comprises a connecting bolt fixation storage part and a baseplate connected to the connecting bolt fixation storage part; and the bolt fixation module and the connecting bolt fixation part are firmly connected to the bottom side beam by fastening bolts. The container modularized building disclosed by the invention is characterized in that side faces of the containers are spliced firmly, so strength of the container bodies is enhanced, and container splicing design becomes much easier; and by the side face connecting bolt-fixation assemblies, the containers can be welded together, so the containers can be installed and fixed at a time, overall anti-seismic performance and hoisting reliability of the container modularized building are enhanced.
Description
Technical field
The present invention relates to container modular architectural technical field, more particularly to a kind of container modularity
Building.
Background technology
At present, container modular architectural is the mode for taking multiple container splicings, between container
Spelling case take fixed installation mode, which is fixedly mounted on the two ends positioned at the top and bottom of container
Angle connector at, be provided with angle connector bolt be connected contact, but in the side mesh of container
It is front also not have the solid stiffening device of systematic coupling bar.And it is also required in practical situation to packaging tank module
Change the side connection of the heap building design of multiple containers of building and reinforce and provide good solution party
Case, during so that the multi-deck container of container modular architectural running into the external force factors such as earthquake, typhoon,
Need constantly to lift integrally-built shock resistance and integrally-built stability.Accordingly, it would be desirable to a kind of
Container modular architectural, to solve the above problems.
The content of the invention
A series of concept of reduced forms is introduced in Summary, this will be in specific embodiment party
Further describe in formula part.The Summary of the present invention is not meant to attempt to limit
Go out the key feature and essential features of technical scheme required for protection, more do not mean that and attempt really
The protection domain of fixed technical scheme required for protection.
In order to solve the above problems, the invention discloses a kind of container modular architectural, the packaging
Tank moduleization building includes at least one container, and the container includes underframe, and the underframe includes
Bottom beam and bottom side beams, the bottom beam are connected with the bottom side beams by corner fittings, it is characterised in that
The solid component of at least two side coupling bars, the solid component of the side coupling bar are provided with the bottom side beams
Including bolt solid model block, coupling bar firmware and fastening bolt, the bolt solid model block includes that coupling bar is accommodated admittedly
Portion and the base plate being connected with the solid receiving portion of the coupling bar, the bolt solid model block and the coupling bar firmware
The bottom side beams are fixedly attached to by the fastening bolt.
Alternatively, it is provided with dividing plate in the solid receiving portion of the coupling bar, the dividing plate is by the coupling bar
Gu accommodating portion is divided into the first receiving portion and the second receiving portion, the base plate is accommodated in correspondence described first
The relevant position in portion is provided with the first installation through-hole, phase of the base plate in correspondence second receiving portion
Position is answered to be provided with the second installation through-hole, the base plate is soldered to the bottom side beams, and the coupling bar is solid
Part includes connecting plate, and the connecting plate is provided with the in the relevant position of correspondence first installation through-hole
One connection through hole, the connecting plate are provided with second in the relevant position of correspondence second installation through-hole
Connection through hole, the fastening bolt include the first fastening bolt and the second fastening bolt, and described first is tight
Fixing bolt passes through first installation through-hole and the first connection through hole, second fastening bolt to wear
Second installation through-hole and the second connection through hole are crossed, the bolt solid model block is solid with the coupling bar
Part is fixedly connected by the fastening bolt.
Alternatively, the container modular architectural includes container described at least two, described in two
It is fixedly connected by the solid component of the side coupling bar between container.
Alternatively, the container modular architectural includes the first container and the second container, described
It is provided with the bolt solid model block in first bottom side beams of the first container, the first of second container
The coupling bar firmware is provided with top beam of laterally, the bolt solid model block is fixed by the fastening bolt and connected
It is connected to the coupling bar firmware.
Alternatively, the container modular architectural includes the 3rd container and the 4th container, described
Coupling bar firmware includes the 3rd coupling bar firmware and the 4th coupling bar firmware, the of the 3rd container
The 3rd coupling bar firmware, the 3rd coupling bar firmware and the described 3rd are provided with three top beam of laterally
Top beam of laterally is welded, and is provided with the 4th coupling bar firmware on the 4th top beam of laterally of the 4th container,
The 4th coupling bar firmware is welded with the 4th top beam of laterally, the 3rd coupling bar firmware with it is described
4th coupling bar firmware is fixedly connected by transverse connection, and the transverse connection is fixed by screw
To the 3rd coupling bar firmware and the 4th coupling bar firmware.
Alternatively, also including the 5th container and the 6th container, the bottom side beams of the 5th container
On be provided with the bolt solid model block, be provided with the bolt solid model block in the bottom side beams of the 6th container,
5th container and the 6th container bolt solid model block respectively is by the fastening bolt
It is fixedly attached to the transverse connection.
Alternatively, the solid component of the coupling bar also includes female thread built-in fitting, the female thread built-in fitting
It is engaged with the fastening bolt.
Alternatively, the solid component of the coupling bar also includes damping damping gasket, the damping damping gasket
It is arranged between the bottom side beams and the coupling bar firmware, the damping damping gasket is by described tight
Fixing bolt is fixedly connected with the bolt solid model block, the coupling bar firmware and the bottom side beams.
Alternatively, the bolt solid model block is welded by carbon steel sheet, and the coupling bar firmware is by steel plate one
It is body formed or be welded.
Alternatively, the transverse connection is formed by steel plate bending.
According to the container modular architectural of invention, including at least one container, container include bottom
Frame, underframe include bottom beam and bottom side beams, and bottom beam is connected with bottom side beams by corner fittings, and its feature exists
In, the solid component of at least two side coupling bars is provided with bottom side beams, coupling bar solid component in side includes
Bolt solid model block, coupling bar firmware and fastening bolt, bolt solid model block include the solid receiving portion of coupling bar and with even
The base plate of the solid receiving portion connection of bolt is connect, base plate is soldered to bottom side beams, and bolt solid model block and coupling bar firmware are logical
Cross fastening bolt and be fixedly attached to bottom side beams.Container modular architectural of the invention is adopted to side
With the solid component of side coupling bar so that the side of container is assembled fixed, substitute original container with
Between container by way of corner fittings connection, the self-strength of the casing of container is enhanced, is spelling
Case design is there is provided great convenience.And coupling bar solid component in side adopts high intensity carbon steel or foundry goods system
Into with good structural strength, by the solid component of side coupling bar by container and container welding
To together so as to install fixation and settle at one go, enhance the overall shock resistance of container modular architectural
And the reliability of handling.
Description of the drawings
The drawings below of embodiment of the present invention is used to understand this in this as the part of the present invention
It is bright.Shown in the drawings of embodiments of the present invention and its description, for explaining the principle of the present invention.
In the accompanying drawings,
Fig. 1 is that the local of the container modular architectural of the first preferred implementation according to the present invention shows
It is intended to;
Fig. 2 is the structural representation of the bolt solid model block of the first preferred implementation according to the present invention;
Fig. 3 is the structural representation of the coupling bar firmware of the first preferred implementation according to the present invention;
Fig. 4 is the structural representation of the coupling bar firmware of the second preferred implementation according to the present invention;
Fig. 5 is the container of the container modular architectural of the second preferred implementation according to the present invention
Partial schematic diagram;
Fig. 6 is the top knot of the container modular architectural of the 3rd preferred implementation according to the present invention
Structure schematic diagram;And
Fig. 7 is the container of the container modular architectural of the 4th preferred implementation according to the present invention
Junction structural representation.
Description of reference numerals:
110th, 210,410, bottom side beams 120, the solid component of side coupling bar
130th, 230,430, bolt solid model block 150,250,450, fastening bolt
140th, 240,340,340 ', 440, coupling bar firmware
131st, the solid receiving portion 132,232, base plate of coupling bar
133rd, dividing plate 134, the first receiving portion
135th, the second receiving portion 136, the first installation through-hole
137th, the second installation through-hole 141,241, connecting plate
142nd, the first connection connection through hole of through hole 143, second
244th, the 344,344 ', first connecting plate side plate
245th, the 345,345 ', second connecting plate side plate
151st, 251, first the 152,252, second fastening bolt of fastening bolt
260th, female thread built-in fitting 270,470, damping damping gasket
261st, the first female thread built-in fitting 262, the second female thread built-in fitting
280th, top beam of laterally 390,490, transverse connection
381st, the 382,482, the 4th top beam of laterally of the 481, the 3rd top beam of laterally
391st, screw 392, the first transverse connection side plate
393rd, transverse connection top board 394, the second transverse connection side plate
395th, the first screw 396, the second screw
Specific embodiment
In the following description, it is more thorough to the present invention to provide to give a large amount of concrete details
Understanding.It will be apparent, however, to one skilled in the art that embodiment of the present invention
Can be carried out without the need for one or more of these details.In other examples, in order to avoid with
Embodiment of the present invention is obscured, for some technical characteristics well known in the art are not described.
In order to thoroughly understand embodiment of the present invention, detailed structure will be proposed in following description.
Obviously, what the execution of embodiment of the present invention was not limited to that those skilled in the art is familiar with is special
Details.The better embodiment of the present invention is described in detail as follows, but in addition to these detailed descriptions,
The present invention can also have other embodiment.
The container modular architectural of the present invention is after by container stack, by side coupling bar
Gu component will be connection between each container and bolt solid, container includes upper frame and underframe, upper frame and underframe
Connected by corner post, upper frame and underframe include end carriage and curb girder, and upper frame is enclosed by top beam and top beam of laterally
Into underframe is surrounded by bottom beam and bottom side beams.Now according to Fig. 1-Fig. 7 to the solid group of side coupling bar
The structure explanation of the container modular architectural of part.
First embodiment
It is provided with the solid component 120 of at least two groups side coupling bars in the bottom side beams 110 of container, two groups
The structure of the solid component 120 of side coupling bar is identical, and for simplicity, the present invention connects to arbitrary group of side
Connect the solid component be further explained explanation of bolt.As shown in figure 1, being provided with side in the bottom side beams 110 of container
The solid component 120 of face coupling bar.Coupling bar solid component 120 in side includes that bolt solid model block 130, coupling bar is solid
Part 140 and fastening bolt 150, bolt solid model block 130 is by fastening bolt 150 and coupling bar firmware 140
It is fixedly connected with bottom side beams 110, fastening bolt 150 includes the first fastening bolt 151 and the second fastening
Bolt 152.
The concrete structure of the solid component 120 of side coupling bar is as shown in Figures 2 and 3.As shown in Fig. 2
Bolt solid model block 130 includes connecting receiving portion 131 and base plate 132.Connection receiving portion 131 is by two sides
Plate and a top board connect to form hollow cavity, and the height of hollow cavity can accommodate fastening bolt
150 installation operations.The two ends of two side plates are fixedly connected with top board and base plate 132 respectively, in connection
Dividing plate 133 is provided with receiving portion 131, connection receiving portion 131 is divided into into the first receiving portion 134
With the second receiving portion 135.131 two side plates of the connection receiving portion of bolt solid model block 130 and a top
Dividing plate 133 in plate, and connection receiving portion 131 is connected by the way of carbon steel sheet welding, this
Connected mode can ensure that the overall intensity of connection receiving portion, and base plate 132 is by way of welding
It is connected in bottom side beams 110, so bolt solid model block 130 can be more firmly fixed to bottom side beams
On 110, the connected mode of two side plates and base plate 132 that connect receiving portion 131 is also adopted by what is welded
Mode, to further enhance the intensity and stability of bolt solid model block.
In bolt solid model block 130, dividing plate 133 in connection receiving portion 131, is provided with, dividing plate 133 will
Connection accommodating portion is divided into the first receiving portion 134 and the second receiving portion 135, and dividing plate 133 holds in connection
It is different and different with particular location to receive the position that arranges in portion 131.It is provided with base plate 132
Installation through-hole, is provided with the first installation in the relevant position of first receiving portion of correspondence 134 of base plate 132
Through hole 136, is provided with the second installation in the response position of second receiving portion of correspondence 135 of base plate 132
Through hole 137, the first fastening bolt 151 pass through the first installation through-hole 136, and can fix with base plate 132
Connection, the second fastening bolt 152 pass through the second installation through-hole 137, and can fix company with base plate 132
Connect.Certainly, the position of the first installation through-hole 136 and the second installation through-hole 137 is corresponded in bottom side beams 110
Put, by the first fastening bolt 151
Base plate 132 and bottom side beams 110, first in bottom side beams 110 are passed through to lead to the second fastening bolt 152
Spacing between hole and the second through hole should be between the first installation through-hole 136 and the second installation through-hole 137
Spacing it is identical.
As shown in figure 3, coupling bar firmware 140 includes connecting plate 141, connecting plate 141 is also by carbon
Steel plate is made, and the first connection through hole 142 and the second connection through hole 143 are provided with connecting plate 141,
Position first installation through-hole 136 of correspondence of the first connection through hole 142, the position of the second connection through hole 143
The second installation through-hole 137 of correspondence is put, between the first connection through hole 142 and the second connection through hole 143
Spacing should be identical with the spacing between the first installation through-hole 136 and the second installation through-hole 137, by
One connection through hole 142 and the first installation through-hole 136 coordinate, and the second connection through hole 143 and second is installed
Through hole 137 is engaged.First fastening bolt 151 is logical through the first installation through-hole 136 and the first connection
Hole 142, base plate 132 is fixedly connected with connecting plate 142, and the second fastening bolt 152 is through the
Two installation through-holes 137 and the second connection through hole 143, base plate 132 is fixedly connected with connecting plate.
Weld with base plate 132 due to connecting receiving portion 131, so bolt solid model block 130 and coupling bar firmware 140
It is fixedly connected.
Fig. 1 is gone back to, container is as follows with the connected mode of the solid component of side coupling bar:
The first through hole of the correspondence bottom side beams 110 of the first installation through-hole 136 in bolt solid model block 130, bolt
Second through hole of the correspondence bottom side beams 110 of the second installation through-hole 137 in solid model block 130, by bolt solid model
The base plate 132 of block 130 is soldered in bottom side beams 110;
Coupling bar firmware 140 is placed on ground or platform, and the bottom surface of connecting plate 141 and ground
Base or platform welding;
Container allocation and transportation are placed on into the top of coupling bar firmware 140 and are slowly declined, positioned at bolt solid model
The first installation through-hole 136 in block 130 is connected through hole 142 to the greatest extent with first in coupling bar firmware 140
Possible alignment, in the second installation through-hole 137 and coupling bar firmware 140 in bolt solid model block 130
Second connection through hole 143 aligns as far as possible;
First installation through-hole 136 is connected through hole 142 with first and docks, the second installation through-hole 137 and
Two connection through holes 143 are docked, and the first installation through-hole 136 is connected the position of the docking of through hole 142 with first
Put corresponding with the position of the first through hole of bottom side beams 110, the second installation through-hole 137 is connected with second
The position of the docking of through hole 143 is corresponding with the position of the second through hole in bottom side beams 110, the first fastening
Bolt 151 sequentially passes through the first installation through-hole 136, the first through hole of bottom side beams 110 and the first connection
Through hole 142, the second fastening bolt 152 sequentially pass through the second installation through-hole 137, the of bottom side beams 110
Two through holes and the second connection through hole 143, will be bolt solid model block 130 solid with bottom side beams 110 and coupling bar
Part 140 is fixedly connected, and the side of final container is solid with ground or platform bolt, fixed, finally reaches
To the purpose that the side bolt of the bottom of container is solid.
Second embodiment
The structure of second embodiment compares similar with the structure of first embodiment, in present embodiment
In, for simplicity purposes, the description with first embodiment same section is omitted herein.
The embodiment part different from first embodiment is, as shown in figure 4, coupling bar is solid
Part 240 includes female thread built-in fitting 260, and female thread built-in fitting 260 is coordinated with fastening bolt 250.
Specifically, coupling bar firmware 240 includes connecting plate 241, is provided with and is connected on connecting plate 241
The first connecting plate side plate 244 and the second connecting plate side plate 245 of the connection of plate 241, connecting plate 241 with
The material of the first connecting plate side plate 244 and the second connecting plate side plate 245 adopts steel plate, connecting plate 241
Can be integrally formed by steel plate or by steel with the first connecting plate side plate 244 and the second connecting plate side plate 245
Plate weld is formed.First connecting plate side plate 244 and the second connecting plate side plate 245 are along connecting plate 241
Length direction extend, between the first connecting plate side plate 244 and the second connecting plate side plate 245 arrange
There are the first female thread built-in fitting 261 and the second female thread built-in fitting 262, the first female thread built-in fitting 261
It is connected through hole (not shown) to be correspondingly arranged and be engaged with the first fastening bolt (not shown) with first,
Second female thread built-in fitting 262 is connected through hole (not shown) and is correspondingly arranged and fastens with second with second
Bolt (not shown) is engaged.
As shown in figure 5, container modular architectural includes the first container above and is located at down
Second container of side, bolt solid model block 230 are welded with the first bottom side beams 210 of the first container, even
The second top beam of laterally 280 that bolt firmware 240 is connect with the second container is welded.
The base plate 232 of bolt solid model block 230 is soldered to the first bottom side beams 210, coupling bar firmware 240
First connecting plate side plate 244 is welded with the second top beam of laterally 280, the second connecting plate side plate 245 and second
Top beam of laterally 280 is welded.First installation through-hole, first through hole, the first connection through hole and the first female thread
Built-in fitting is correspondingly arranged, so that the first fastening bolt 251 passes through the first installation through-hole, first through hole
With the first connection through hole, finally tighten with the first female thread built-in fitting 261;Second installation through-hole,
Two through holes, the second connection through hole and the second female thread built-in fitting are correspondingly arranged, so that the second fastening spiral shell
Bolt 252 connects through hole through the second installation through-hole, the second through hole and second, finally with the second female thread
Built-in fitting 262 is tightened.
The top of coupling bar firmware 240 is additionally provided with damping damping gasket 270, damping damping gasket 270
On be provided with the first damping damping gasket through hole and the second damping damping gasket through hole (not shown) so that
Obtaining the first fastening bolt 251 passes through the first damping damping gasket through hole, the second fastening bolt to pass through second
Damping damping gasket through hole.
Container is as follows with the connected mode of the solid component of side coupling bar:
First bottom side beams 210 of the first installation through-hole the first container of correspondence in bolt solid model block 230
First through hole, the first bottom side beams of the second installation through-hole the first container of correspondence in bolt solid model block 230
210 the second through hole, the base plate 232 of bolt solid model block 230 is soldered in the first bottom side beams 210;
Coupling bar firmware 240 is placed on the second top beam of laterally 280 of the second container, and first connects
Fishplate bar side plate 244 and the second connecting plate side plate 245 are welded with the second top beam of laterally 280;
Damping damping gasket 270 is placed on the top of coupling bar firmware 240, and the first damping damping mat
Piece through hole correspondence first connects through hole, and the second damping damping gasket through hole correspondence second connects through hole;
The allocation and transportation of first container are placed on into the top of coupling bar firmware 240 and damping damping gasket 270
And slowly decline, the first installation through-hole in bolt solid model block 230 and damping damping gasket 270
The first connection through hole in first damping damping gasket through hole and coupling bar firmware 240 is right as far as possible
Together, the second installation through-hole in bolt solid model block 230 is damped with the second damping of damping damping gasket 270
The second connection through hole in shim through bore and coupling bar firmware 240 aligns as far as possible;
First installation through-hole is connected through hole docking with first, and the second installation through-hole is connected through hole pair with second
Connect, the first fastening bolt 251 sequentially pass through the first installation through-hole, the first through hole of bottom side beams 210,
First damping damping gasket through hole and the first connection through hole, the first fastening bolt 251 and the first female thread
Built-in fitting 261 is tightened, and the second fastening bolt 252 sequentially passes through the second installation through-hole, bottom side beams 210
The second through hole, the second damping damping gasket through hole and second connection through hole, the second fastening bolt 251
Tighten with the second female thread built-in fitting 262, by base plate 232, damping damping gasket 270 and connecting plate
241 are fixedly connected so that bolt solid model block 230, damping damping gasket 270 and coupling bar build 240 admittedly
It is fixedly connected, the top beam of laterally 280 of the bottom side beams 210 and the second container of final first container is fixed
Connection, reaches the solid purpose of the side coupling bar of the container of two-layer up and down of container modular architectural.
3rd embodiment
The structure of the 3rd embodiment compares similar with the structure of second embodiment, in present embodiment
In, for simplicity purposes, the description with second embodiment same section is omitted herein.
The embodiment part different from second embodiment is, as shown in fig. 6, container mould
Massing building includes the 3rd container and the 4th container, the 3rd container and the 4th container by setting
The coupling bar firmware put on the top beam of laterally of casing is fixedly connected.Specifically, coupling bar firmware 340
The first connecting plate side plate 344 and the second connecting plate side plate 345 be soldered to the 3rd of the 3rd container
On top beam of laterally 381, the first connecting plate side plate 344 ' of coupling bar firmware 340 ' and the second connecting plate side
Plate 345 ' is soldered on the 4th top beam of laterally 382 of the 4th container.
Coupling bar firmware 340 and 340 ' is connected by transverse connection 390, transverse connection 390
Including transverse connection top board 393, the first transverse connection side plate 392 and the second transverse connection side
Plate 394, transverse connection top board 393, the first transverse connection side plate 392 and the second transverse connection
Side plate 394 is formed by steel plate bending, the first transverse connection side plate 392 and the first connecting plate side plate 344
It is close to, the second cross connecting plate side plate 394 is close to the first connecting plate side plate 344 ', lateral connection
Screw 391 is provided with part top board 393, screw 391 includes the first screw 395 and the second screw 396,
The connection lateral connection of first screw 395 top board 393 and coupling bar firmware 340 connect, the second screw 396
Connection lateral connection top board 393 and coupling bar firmware 340 ', so that coupling bar firmware 340 and connection
Bolt firmware 340 ' is connected to together, finally causes the 3rd top beam of laterally 381 and the 4th top beam of laterally 382 solid
It is fixed to connect, reach the side coupling bar at the top of parallel two container of container modular architectural
Solid purpose.
4th embodiment
The structure of the 4th embodiment compares similar with the structure of the 3rd embodiment, in present embodiment
In, for simplicity purposes, the description with the 3rd embodiment same section is omitted herein.
The embodiment part different from the 3rd embodiment is, as shown in fig. 7, container mould
In massing building, pass through transverse connection 490 between underlying two containers and coupling bar is solid
Part 440 is by the 3rd top beam of laterally 481 of the 3rd container positioned at lower left and is located at the bottom-right 4th
4th top beam of laterally 482 of container is fixedly connected, and the 5th of the 5th container in left side above the
Bolt solid model block 430 is installed with bottom side beams 410, fastening bolt 450 sequentially passes through bolt solid model block
430th, the 5th bottom side beams 410, damping damping gasket 470, transverse connection 490, coupling bar firmware
440, by bolt solid model block 430, the 5th bottom side beams 410, damping damping gasket 470, transverse connection
490th, coupling bar firmware 440 is fixedly connected, positioned at top-right 6th container with the 5th container
Bottom side beams 410 not close to another side the 6th bottom side beams (not shown) on also fixedly mount
There is bolt solid model block (not shown), bolt solid model block is by fastening bolt (not shown) and underlying the
Another top beam of laterally (not shown) relative to the 6th bottom side beams of four containers is fixedly connected, and so may be used
So that the 5th container above and the 6th container and underlying 3rd container and
The side coupling bar of the 4th container is solid, and the 5th container above and the 6th container
Bolt solid model block is not close to but interval setting, it is possible to use positioned at the side coupling bar of different azimuth
Gu component, in the case where ensureing that four containers can be firmly fixed connection, reasonable arrangement side
The solid component of coupling bar, reduces cost.
Unless otherwise defined, technology used herein and scientific terminology and technical field of the invention
The implication that is generally understood that of technical staff it is identical.It is specific that term used herein is intended merely to description
Implement purpose, it is not intended that limit the present invention.Terms such as herein presented " settings " both may be used
To represent that a part is attached directly to another part, it is also possible to represent that a part passes through middleware
It is attached to another part.The feature for describing in one embodiment herein can individually or with
Further feature is applied to another embodiment in combination, unless this feature is in another embodiment
In do not apply to or be otherwise noted.
The present invention is illustrated by above-mentioned embodiment, but it is to be understood that, above-mentioned reality
The mode of applying is only intended to citing and descriptive purpose, and is not intended to limit the invention to described reality
Apply in the range of mode.It will be appreciated by persons skilled in the art that teaching of the invention can be with
More kinds of variants and modifications are made, these variants and modifications all fall within model required for protection of the invention
Within enclosing.
Claims (10)
1. a kind of container modular architectural, the container modular architectural include at least one collection
Vanning, the container include underframe, and the underframe includes bottom beam and bottom side beams, the bottom beam
It is connected with the bottom side beams by corner fittings, it is characterised in that in the bottom side beams, be provided with least two
The solid component of side coupling bar, the solid component of the side coupling bar include bolt solid model block, coupling bar firmware and
Fastening bolt, the bolt solid model block are included the solid receiving portion of coupling bar and are connected with the solid receiving portion of the coupling bar
The base plate for connecing, the bolt solid model block and the coupling bar firmware are fixedly attached to by the fastening bolt
The bottom side beams.
2. container modular architectural according to claim 1, it is characterised in that
Dividing plate is provided with the solid receiving portion of the coupling bar, the coupling bar is consolidated receiving portion by the dividing plate
It is divided into the first receiving portion and the second receiving portion, the base plate is corresponding correspondence first receiving portion
Position is provided with the first installation through-hole, and the base plate is installed in the corresponding positions of correspondence second receiving portion
The second installation through-hole is equipped with, the base plate is soldered to the bottom side beams,
The coupling bar firmware includes connecting plate, and the connecting plate is in correspondence first installation through-hole
Relevant position is provided with the first connection through hole, phase of the connecting plate in correspondence second installation through-hole
Position is answered to be provided with the second connection through hole,
The fastening bolt includes the first fastening bolt and the second fastening bolt, first fastening bolt
Through first installation through-hole and the first connection through hole, second fastening bolt passes through described
Second installation through-hole and the second connection through hole, the bolt solid model block are passed through with the coupling bar firmware
The fastening bolt is fixedly connected.
3. container modular architectural according to claim 1, it is characterised in that the collection
Vanning modular architectural includes container described at least two, by described between two containers
Coupling bar solid component in side is fixedly connected.
4. container modular architectural according to claim 3, it is characterised in that the packaging
Tank moduleization building includes the first container and the second container, the first bottom side of first container
The bolt solid model block is provided with beam, on the first top beam of laterally of second container, the company is provided with
Bolt firmware is connect, the bolt solid model block is fixedly attached to the coupling bar firmware by the fastening bolt.
5. container modular architectural according to claim 3, it is characterised in that the packaging
Tank moduleization building includes the 3rd container and the 4th container, and the coupling bar firmware includes the 3rd company
Bolt firmware and the 4th coupling bar firmware are connect,
It is provided with the 3rd coupling bar firmware on 3rd top beam of laterally of the 3rd container, described
Three coupling bar firmwares are welded with the 3rd top beam of laterally,
It is provided with the 4th coupling bar firmware on 4th top beam of laterally of the 4th container, described
Four coupling bar firmwares are welded with the 4th top beam of laterally,
The 3rd coupling bar firmware is fixed by transverse connection with the 4th coupling bar firmware and is connected
Connect, the transverse connection is fixed to the 3rd coupling bar firmware and the 4th connection by screw
Bolt firmware.
6. container modular architectural according to claim 5, it is characterised in that also including
Five containers and the 6th container, are provided with the bolt solid model block in the bottom side beams of the 5th container,
It is provided with the bolt solid model block in the bottom side beams of the 6th container, the 5th container and described
The 6th container bolt solid model block respectively is fixedly attached to by the fastening bolt and described is laterally connected
Fitting.
7. the container modular architectural according to any one of claim 1 to 6, which is special
Levy and be, the solid component of the coupling bar also includes female thread built-in fitting, the female thread built-in fitting and institute
State fastening bolt to be engaged.
8. the container modular architectural according to any one of claim 1 to 6, which is special
Levy and be, the solid component of the coupling bar also includes damping damping gasket, and the damping damping gasket is arranged
Between the bottom side beams and the coupling bar firmware, the damping damping gasket is by the fastening spiral shell
Bolt is fixedly connected with the bolt solid model block, the coupling bar firmware and the bottom side beams.
9. the container modular architectural according to any one of claim 1 to 6, which is special
Levy and be, the bolt solid model block is welded by carbon steel sheet, the coupling bar firmware by steel plate one into
Type is welded.
10. container modular architectural according to claim 5, it is characterised in that the horizontal stroke
Formed to connector by steel plate bending.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510691389.3A CN106609601B (en) | 2015-10-21 | 2015-10-21 | Container modular architectural |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510691389.3A CN106609601B (en) | 2015-10-21 | 2015-10-21 | Container modular architectural |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106609601A true CN106609601A (en) | 2017-05-03 |
CN106609601B CN106609601B (en) | 2019-11-12 |
Family
ID=58610507
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510691389.3A Active CN106609601B (en) | 2015-10-21 | 2015-10-21 | Container modular architectural |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106609601B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019057149A1 (en) * | 2017-09-22 | 2019-03-28 | 中集模块化建筑投资有限公司 | Positioning system for building modules |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002350590A (en) * | 2001-05-22 | 2002-12-04 | Toshiba Corp | Lining panel, lining vessel and construction method for the lining vessel |
JP2007051419A (en) * | 2005-08-15 | 2007-03-01 | Cosmo Five:Kk | Unit for container house and connection structure of container house |
CN201096468Y (en) * | 2007-09-29 | 2008-08-06 | 黄锦明 | Adjustable bottom bracket for cooling column |
CN102619359A (en) * | 2012-04-25 | 2012-08-01 | 广东长盈重工有限公司 | Modular mobile movie theater |
CN202370100U (en) * | 2011-11-30 | 2012-08-08 | 哈尔滨工业大学深圳研究生院 | Joint connection device for container reconstructed house |
CN202575114U (en) * | 2012-04-10 | 2012-12-05 | 青岛金黄海集装箱有限公司 | Container underframe and container for loading liquid containing vessel |
CN203962652U (en) * | 2014-07-23 | 2014-11-26 | 杭州浙桥钢结构有限公司 | A kind of corrosion protection bolt assembly that is applied to Oversea bridge |
CN104712150A (en) * | 2013-12-12 | 2015-06-17 | 扬州通利冷藏集装箱有限公司 | Outdoor corridor and transportation method thereof |
CN104718330A (en) * | 2012-10-12 | 2015-06-17 | 凯驰前途科技有限公司 | Container building |
CN204475545U (en) * | 2015-01-07 | 2015-07-15 | 青岛雷悦重工股份有限公司 | A kind of container house top beam of laterally waterproof connecting device |
-
2015
- 2015-10-21 CN CN201510691389.3A patent/CN106609601B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002350590A (en) * | 2001-05-22 | 2002-12-04 | Toshiba Corp | Lining panel, lining vessel and construction method for the lining vessel |
JP2007051419A (en) * | 2005-08-15 | 2007-03-01 | Cosmo Five:Kk | Unit for container house and connection structure of container house |
CN201096468Y (en) * | 2007-09-29 | 2008-08-06 | 黄锦明 | Adjustable bottom bracket for cooling column |
CN202370100U (en) * | 2011-11-30 | 2012-08-08 | 哈尔滨工业大学深圳研究生院 | Joint connection device for container reconstructed house |
CN202575114U (en) * | 2012-04-10 | 2012-12-05 | 青岛金黄海集装箱有限公司 | Container underframe and container for loading liquid containing vessel |
CN102619359A (en) * | 2012-04-25 | 2012-08-01 | 广东长盈重工有限公司 | Modular mobile movie theater |
CN104718330A (en) * | 2012-10-12 | 2015-06-17 | 凯驰前途科技有限公司 | Container building |
CN104712150A (en) * | 2013-12-12 | 2015-06-17 | 扬州通利冷藏集装箱有限公司 | Outdoor corridor and transportation method thereof |
CN203962652U (en) * | 2014-07-23 | 2014-11-26 | 杭州浙桥钢结构有限公司 | A kind of corrosion protection bolt assembly that is applied to Oversea bridge |
CN204475545U (en) * | 2015-01-07 | 2015-07-15 | 青岛雷悦重工股份有限公司 | A kind of container house top beam of laterally waterproof connecting device |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019057149A1 (en) * | 2017-09-22 | 2019-03-28 | 中集模块化建筑投资有限公司 | Positioning system for building modules |
WO2019057162A1 (en) * | 2017-09-22 | 2019-03-28 | 中集模块化建筑投资有限公司 | Connecting method for building module |
WO2019057147A1 (en) * | 2017-09-22 | 2019-03-28 | 中集模块化建筑投资有限公司 | Positioning connection device and building module device |
GB2581288A (en) * | 2017-09-22 | 2020-08-12 | Cimc Modular Building Systems Holding Co Ltd | Positioning connection device and building module device |
Also Published As
Publication number | Publication date |
---|---|
CN106609601B (en) | 2019-11-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102970838A (en) | High and low frequency impact resistance cabinet | |
CN201023882Y (en) | Dismountable can-type tray box | |
CN106609601A (en) | Container modularized building | |
CN202206680U (en) | High-strength supporting column in frame | |
CN206886543U (en) | A kind of mounting structure of suspension crane beam orbit | |
CN102774425A (en) | Vehicle frame | |
CN106608458A (en) | A corner connecting component for containers and a container modularization building with the same | |
CN205203870U (en) | Angle coupling assembling of container and have its container modularization building | |
CN112227410A (en) | Construction method of special-shaped tower crane foundation | |
CN205100631U (en) | Container modularization building | |
RU2299393C1 (en) | Fighting compartment tray | |
CN210238285U (en) | Breast board connecting structure for rail transit bridge | |
CN216663852U (en) | Anti-falling device for construction of arch bridge steel beam structure | |
CN210213096U (en) | Auxiliary stand steel construction | |
CN214985943U (en) | Crane ship and supporting device thereof | |
CN209290162U (en) | A kind of mounting bracket and automobile of car expansion tank | |
CN215329331U (en) | Bridge beam supports for railway road construction | |
CN214738962U (en) | Air bag damping type explosion-proof wall structure for ocean platform | |
CN214194623U (en) | Special-shaped tower crane foundation | |
CN213710068U (en) | Light steel keel suspended ceiling | |
CN210064394U (en) | Assembled steel case roof beam loading device | |
CN214780118U (en) | Elevator car frame structure | |
CN214016710U (en) | Assembled goods shelf for storage environment | |
CN211556095U (en) | Multifunctional rapid freely-assembled pole for floor | |
JP3175076U (en) | Mounting bracket for mount |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |