CN106563898A - Management system for digital welding workshop - Google Patents
Management system for digital welding workshop Download PDFInfo
- Publication number
- CN106563898A CN106563898A CN201610992042.7A CN201610992042A CN106563898A CN 106563898 A CN106563898 A CN 106563898A CN 201610992042 A CN201610992042 A CN 201610992042A CN 106563898 A CN106563898 A CN 106563898A
- Authority
- CN
- China
- Prior art keywords
- module
- task
- equipment
- workshop
- current
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K37/00—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/04—Manufacturing
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Abstract
The invention discloses a management system for a digital welding workshop. The system comprises an equipment state management module, a quality analysis module, a production scheduling module and a technology assigning module; the quality analysis module analyzes the stability of welds and monitors defects of the welds; the equipment state management module acquires and displays the current working state and the historical working state of equipment; the production scheduling module sequences existing orders and determines the time when each task is conducted; and the technology assigning module assigns manually input technological parameters to the equipment through hardware circuits. Functions and the practicability of the quality analysis module are enriched, and the sequence of workpiece assembly processes is guided by the production scheduling module, so that the process of a processed product from a raw material to the final product is more reasonable and specific; and welding technology parameters are fixed by the technology assigning module, the non-standard operation of manual adjustment is avoided, the digital degree and the production efficiency of the workshop are improved, the production process of the workshop is standard and reasonable, and an administrator manages the workshop conveniently.
Description
Technical field
The invention belongs to digital welding workshop technical field, particularly a kind of digitized is welded workshop management system.
Background technology
The advantages of digitized workshop can improve enterprise productivity, reduces cost with it becomes the heat of domestic and international research
Point.The country also has a small amount of for the research in digital welding workshop, but generally existing digitized degree is not high, and technical merit is relatively low
The shortcomings of.And for the workshop that is welded, i.e. collection welding and the workshop for being assemblied in one, then rarely have research.
First, existing quality analysis system not can for weldquality intuitively evaluated and weld seam lack
Sunken monitoring.Next, one according to certain Rulemaking reasonable production order, and can not carried out in accordance with the production sequence
The holonomic system of workpiece handling.
The content of the invention
The workshop management system it is an object of the invention to provide a kind of digitized is welded, to improve the digitized degree in workshop
And production efficiency.
The technical solution for realizing the object of the invention is:A kind of digitized is welded workshop management system, including equipment shape
State management module, quality analysiss module, scheduling module, technique assign module, wherein:
Quality analysiss module, analyzes weld joint stable, and weld defect is monitored;
Equipment state management module, obtains the current operating state and history working condition of simultaneously display device;
Scheduling module, existing order is ranked up, and determines the time that each task is carried out;
Technique assigns module, and the technological parameter being manually entered is assigned to into equipment by hardware circuit.
Further, the equipment state management module includes current device block of state and historical plant status module;
Current device block of state shows in real time the start of all welding robots of current inter-vehicular, shutdown two states, currently to whether there is
Current value represents respectively startup and shutdown, and respectively the state to current value more than 0 and equal to 0 is recorded, and counts lasting
Time;Historical plant status module daily, week, the moon statistics individual device start, shutdown two states time and shown.
Further, the quality analysiss module includes weld joint stable analysis module and weld defect monitoring modular, its
Middle weld joint stable analysis module will fixed period weldquality be assessed as it is stable, general, unstable, by the side of calculating current
Difference, analyzes the fluctuation situation of electric current, used as the foundation for evaluating weldquality;Welding occurs in weld seam in the weld defect monitoring modular
Thoroughly, provide warning when weldering leakage, the weld defect of incomplete fusion, when current/voltage value undergo mutation then think to generate more than threshold value it is scarce
Fall into, and record defective locations.
Further, the scheduling module includes that manual scheduling module, task monitors module and task assign module, its
In:
The input of the manual scheduling module is a list for manually entering, and column name is respectively from left to right component name
Title, material, blanking procedure, moulding process, packaging technology and welding procedure, output is then blanking procedure, moulding process, Welder
Concrete equipment needed for skill;
The task monitors module shows the task that currently carrying out today, has completed task and unfinished task;
The task assigns module before processed part needs to be transported to next station, manually instruction issuing
Give AGV logistics trolleys.
Compared with prior art, its remarkable advantage is the present invention:(1) weldquality estimation of stability and weld seam are realized
Defect monitors function on-line, increased the practicality of quality analysis system;(2) scheduling module enters numerous and diverse product processing
Row is disassembled, and improve enterprises production efficiency to concrete equipment according to certain regulation arrangement, it is to avoid situations such as construction delay
Occur;(3) technique assigns module and secures welding condition, it is to avoid the non-standard operation of manual adjustment, improves workshop
Digitized degree and production efficiency so that the production process in workshop more specification, more rationally, so as to manager is for the pipe in workshop
Reason is lighter.
Description of the drawings
Fig. 1 is that digitized of the present invention is welded the structural representation of workshop management system.
Fig. 2 be digitized of the present invention be welded manual scheduling module in workshop management system manually enter list figure.
Specific embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings.
The workshop management system as shown in figure 1, digitized of the present invention is welded, including equipment state management module, quality analysiss
Module, scheduling module, technique assign module, wherein:
(1) quality analysiss module, analyzes weld joint stable, and weld defect is monitored;The quality analysiss module
Including weld joint stable analysis module and weld defect monitoring modular, wherein weld joint stable analysis module will fixed period weld seam
Performance rating is stable, general, unstable, by the variance of calculating current, analyzes the fluctuation situation of electric current, used as evaluation weld seam
The foundation of quality;The weld defect monitoring modular provides report when through welding, weldering leakage, the weld defect of incomplete fusion occurs in weld seam
Alert, to undergo mutation then think more than threshold value when current/voltage value generates defect, and records defective locations.
(2) equipment state management module, obtains the current operating state and history working condition of simultaneously display device;It is described to set
Standby state management module includes current device block of state and historical plant status module;Current device block of state shows in real time
The start of all welding robots of current inter-vehicular, shutdown two states, currently to whether there is current value startup and shutdown are represented respectively,
And respectively the state to current value more than 0 and equal to 0 is recorded, duration is counted;Historical plant status module daily,
Week, moon statistics individual device start, the time of shutdown two states are simultaneously shown, for example, are shown with the formal intuition of pie chart.
(3) scheduling module, existing order is ranked up, and determines the time that each task is carried out;The scheduling module bag
Include manual scheduling module, task monitors module and task and assign module, wherein:
As shown in Fig. 2 the input of the manual scheduling module is a list for manually entering, column name is divided from left to right
Not Wei part name, material, blanking procedure, moulding process, packaging technology and welding procedure, output then be blanking procedure, molding
Concrete equipment needed for technique, welding procedure;Blanking procedure, moulding process fills in the species of equipment needed thereby under welding procedure.
In workshop, often every kind of equipment has multiple stage, and due to brand, degree of wear difference causes production efficiency different.Accordingly will be of the same race
Equipment prioritization.Additionally, equipment is had in being currently in use, failure and three kinds of states are not used.Therefore a kind of rule is formulated,
The equipment of prioritizing selection unused state, secondary priority condition be priority facility, so that it is determined that every kind of equipment choose it is concrete
Certain equipment, and the specific time is arranged into carrying out corresponding task.Blanking procedure, moulding process, welding procedure scheduling
The equipment for determining afterwards is saved in data base.
The task monitors module shows the task that currently carrying out today, has completed task and unfinished task;
The task assigns module before processed part needs to be transported to next station, manually instruction issuing
AGV logistics trolleys are given, i.e., manually sets the place of next station, instruct AGV logistics trolleys that workpiece is sent by the route for designing
To specified location.
(4) technique assigns module, and the technological parameter being manually entered is assigned to into equipment by hardware circuit.
It is an advantage of the invention that:The function and practicality of quality analysiss module are enriched, scheduling module directs workpiece dress
Order with process so that product to be processed expects that the process of final products is more rationally and clear and definite from former material.Technique assigns module
Secure welding condition, it is to avoid the non-standard operation of manual adjustment, improve the digitized degree and production effect in workshop
Rate so that the production process in workshop more specification, more rationally, so as to manager can be lighter for the management in workshop.
But, above-mentioned specific embodiment is exemplary, is to preferably enable those skilled in the art
Understand this patent, it is impossible to be not understood as including this patent the restriction of scope;As long as the institute of spirit according to disclosed in this patent
Any equivalent change made or modification, each fall within the scope that this patent includes.
Claims (4)
1. a kind of digitized is welded workshop management system, it is characterised in that including equipment state management module, quality analysiss mould
Block, scheduling module, technique assign module, wherein:
Quality analysiss module, analyzes weld joint stable, and weld defect is monitored;
Equipment state management module, obtains the current operating state and history working condition of simultaneously display device;
Scheduling module, existing order is ranked up, and determines the time that each task is carried out;
Technique assigns module, and the technological parameter being manually entered is assigned to into equipment by hardware circuit.
2. digitized according to claim 1 is welded workshop management system, it is characterised in that the equipment state manages mould
Block includes current device block of state and historical plant status module;Current device block of state shows that in real time current inter-vehicular owns
The start of welding robot, shutdown two states, currently to whether there is current value startup and shutdown are represented respectively, and respectively to electric current
Value is recorded more than 0 with the state equal to 0, counts duration;Historical plant status module daily, week, the moon statistics it is each
Platform device power-up, the time of shutdown two states are simultaneously shown.
3. digitized according to claim 1 is welded workshop management system, it is characterised in that the quality analysiss module bag
Weld joint stable analysis module and weld defect monitoring modular are included, wherein weld joint stable analysis module will fixed period weld seam matter
Amount is assessed as stable, general, unstable, by the variance of calculating current, analyzes the fluctuation situation of electric current, used as evaluating weld seam matter
The foundation of amount;The weld defect monitoring modular provides warning when through welding, weldering leakage, the weld defect of incomplete fusion occurs in weld seam,
To undergo mutation then think more than threshold value when current/voltage value and generate defect, and record defective locations.
4. digitized according to claim 1 is welded workshop management system, it is characterised in that the scheduling module includes handss
Work scheduling module, task monitors module and task assign module, wherein:
The manual scheduling module input be a list for manually entering, column name from left to right be respectively part name,
Material, blanking procedure, moulding process, packaging technology and welding procedure, output is then blanking procedure, moulding process, welding procedure
Required concrete equipment;
The task monitors module shows the task that currently carrying out today, has completed task and unfinished task;
The task assigned module before processed part needs to be transported to next station, and manually instruction issuing is given
AGV logistics trolleys.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610992042.7A CN106563898A (en) | 2016-11-11 | 2016-11-11 | Management system for digital welding workshop |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610992042.7A CN106563898A (en) | 2016-11-11 | 2016-11-11 | Management system for digital welding workshop |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106563898A true CN106563898A (en) | 2017-04-19 |
Family
ID=58541183
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610992042.7A Pending CN106563898A (en) | 2016-11-11 | 2016-11-11 | Management system for digital welding workshop |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106563898A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109894929A (en) * | 2019-02-11 | 2019-06-18 | 上海贽丰机器人技术有限公司 | A kind of modular reconfigurable flexible process and system |
CN111308964A (en) * | 2018-12-12 | 2020-06-19 | 汉能移动能源控股集团有限公司 | Automatic production line control method, device and system |
CN113909628A (en) * | 2021-11-08 | 2022-01-11 | 中车青岛四方机车车辆股份有限公司 | Intelligent welding production line system and welding method |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020193972A1 (en) * | 2001-06-14 | 2002-12-19 | Ntn Corporation | Workshop facility design and operation support system enabling verification of the entire workshop to be performed easily |
CN101984381A (en) * | 2010-09-15 | 2011-03-09 | 中国医科大学 | Instrument operating condition network real-time monitoring device and method thereof |
CN102922089A (en) * | 2012-08-13 | 2013-02-13 | 天津大学 | Welding process information acquisition and quality monitoring device and method based on Ethernet |
CN103909325A (en) * | 2014-03-26 | 2014-07-09 | 河海大学 | Welding quality monitoring system |
KR20150068512A (en) * | 2013-12-11 | 2015-06-22 | 순천대학교 산학협력단 | Integrated Management System and method for Digital welding machine |
CN104766147A (en) * | 2014-01-07 | 2015-07-08 | 青岛海尔机器人有限公司 | Intelligent device management method and management system |
CN105182940A (en) * | 2015-09-17 | 2015-12-23 | 天地科技股份有限公司 | Intelligent welding workshop information monitoring and management system for hydraulic support |
CN105717901A (en) * | 2016-04-29 | 2016-06-29 | 中船第九设计研究院工程有限公司 | Network management system of shipyard workshop production line numerical control equipment |
CN106096802A (en) * | 2015-12-16 | 2016-11-09 | 宁夏巨能机器人系统有限公司 | The information management system in a kind of Digital manufacturing workshop and management method thereof |
-
2016
- 2016-11-11 CN CN201610992042.7A patent/CN106563898A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020193972A1 (en) * | 2001-06-14 | 2002-12-19 | Ntn Corporation | Workshop facility design and operation support system enabling verification of the entire workshop to be performed easily |
CN101984381A (en) * | 2010-09-15 | 2011-03-09 | 中国医科大学 | Instrument operating condition network real-time monitoring device and method thereof |
CN102922089A (en) * | 2012-08-13 | 2013-02-13 | 天津大学 | Welding process information acquisition and quality monitoring device and method based on Ethernet |
KR20150068512A (en) * | 2013-12-11 | 2015-06-22 | 순천대학교 산학협력단 | Integrated Management System and method for Digital welding machine |
CN104766147A (en) * | 2014-01-07 | 2015-07-08 | 青岛海尔机器人有限公司 | Intelligent device management method and management system |
CN103909325A (en) * | 2014-03-26 | 2014-07-09 | 河海大学 | Welding quality monitoring system |
CN105182940A (en) * | 2015-09-17 | 2015-12-23 | 天地科技股份有限公司 | Intelligent welding workshop information monitoring and management system for hydraulic support |
CN106096802A (en) * | 2015-12-16 | 2016-11-09 | 宁夏巨能机器人系统有限公司 | The information management system in a kind of Digital manufacturing workshop and management method thereof |
CN105717901A (en) * | 2016-04-29 | 2016-06-29 | 中船第九设计研究院工程有限公司 | Network management system of shipyard workshop production line numerical control equipment |
Non-Patent Citations (1)
Title |
---|
苏贺: "《基于模式技术的数字化车间管理系统研究》", 《中国硕士学位论文全文数据库》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111308964A (en) * | 2018-12-12 | 2020-06-19 | 汉能移动能源控股集团有限公司 | Automatic production line control method, device and system |
CN109894929A (en) * | 2019-02-11 | 2019-06-18 | 上海贽丰机器人技术有限公司 | A kind of modular reconfigurable flexible process and system |
CN113909628A (en) * | 2021-11-08 | 2022-01-11 | 中车青岛四方机车车辆股份有限公司 | Intelligent welding production line system and welding method |
CN113909628B (en) * | 2021-11-08 | 2023-01-20 | 中车青岛四方机车车辆股份有限公司 | Intelligent welding production line system and welding method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107767015A (en) | A kind of production system based on MES | |
CN106563898A (en) | Management system for digital welding workshop | |
WO2019148053A1 (en) | Distributed automation control | |
US10558953B2 (en) | Welding system parameter comparison system and method | |
CN103056659B (en) | Automatic production device for cabinets | |
CN108829048A (en) | A kind of information analysis system and method based on liquid crystal glass base production and processing | |
Naranje et al. | Optimization of factory layout design using simulation tool | |
Sunadi et al. | Overall Equipment Effectiveness to Increase Productivity of Injection Molding Machine: A Case Study in Plastic Manufacturing Industry | |
CN115049326A (en) | Production management system and management method | |
CN107016456A (en) | A kind of discreteness based on state-driven produces the prediction analysis method of trace platform | |
US8809738B2 (en) | Method for providing real-time monitoring of contact tip performance | |
CN106271260A (en) | Intelligent control method in a kind of Robot Spot Welding | |
Malik et al. | Drive the cobots aright: Guidelines for industrial application of cobots | |
Wazed et al. | Theory driven real time empirical investigation on joint implementation of PDCA and 5S for performance improvement in plastic moulding industry | |
Prombanpong et al. | A buffer design for mitigation downtime effect in an automated transfer line | |
CN211589134U (en) | Motor train unit framework manufacturing system | |
CN114298612A (en) | Method for providing optimal production path equipment selection | |
Modrák | Case on manufacturing cell formation using production flow analysis | |
Sulistiyowati et al. | Product quality control based on lean manufacturing and root cause analysis methods | |
Reik et al. | A formal design for changeover methodology. Part 2: methodology and case study | |
Pandian et al. | Investigation of maintenance assumptions for an automotive production line using simulation modeling | |
Chen et al. | Design of SCADA System for Stainless Steel Pipe Production Line | |
Villarreal et al. | A TOC-OEE Based Scheme to Improve Productivity | |
Gohane et al. | Improvement of productivity using value stream mapping | |
Piedade et al. | IN2Dig–Implementation of a Digital Manufacturing System in a Production Cell of the Metal Mold Industry: From Planning to Action |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170419 |