CN106556738A - Electricity consumption monitoring system - Google Patents

Electricity consumption monitoring system Download PDF

Info

Publication number
CN106556738A
CN106556738A CN201611069418.3A CN201611069418A CN106556738A CN 106556738 A CN106556738 A CN 106556738A CN 201611069418 A CN201611069418 A CN 201611069418A CN 106556738 A CN106556738 A CN 106556738A
Authority
CN
China
Prior art keywords
intelligent electric
electric meter
data
service
intelligent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611069418.3A
Other languages
Chinese (zh)
Inventor
范先慎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201611069418.3A priority Critical patent/CN106556738A/en
Publication of CN106556738A publication Critical patent/CN106556738A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R22/00Arrangements for measuring time integral of electric power or current, e.g. electricity meters

Abstract

A kind of electricity consumption monitoring system is embodiments provided, is related to electric power monitoring field.Electricity consumption monitoring system includes service end, the first gateway and multiple first intelligent electric meters;Multiple first intelligent electric meters are used for the first current power amount data for detecting multiple load branch;First gateway is for being uploaded to service end by the identification code of each the first current power amount data and each the first intelligent electric meter;Service end is for calculating power consumption data of each first intelligent electric meter in predetermined time period according to each first current power amount data and treats electricity payment data, and the power consumption data by each first intelligent electric meter in predetermined time period and treats that electricity payment data is activation gives the corresponding intelligent terminal of identification code of each the first intelligent electric meter.The waste of the reduced human resources that the present invention is provided, can remind to user's electricity payment, and the situation for preventing from due to seasonal electricity consumption or leading to not the problems such as being had a holiday or vacation with electric unit making a copy of in time ammeter occurs.

Description

Electricity consumption monitoring system
Technical field
The present invention relates to electric power monitoring field, in particular to a kind of electricity consumption monitoring system.
Background technology
At present, for the data acquisition of ammeter is mostly by the way of manually making a copy of, the mode of traditional manual metering exists There is many unfavorable factors in actual operation.Substantial amounts of human resources can be expended when carrying out manual metering, and the cycle of checking meter is long. Meanwhile, manual metering easily malfunctions, and causes the electricity charge to calculate error, the experience of degrading user.Secondly, it is also possible to due to seasonal use Electricity and lead to not make a copy of in time the situation of ammeter the problems such as had a holiday or vacation with electric unit and occur.In addition, the mode of manual metering cannot Early warning, prompting are carried out to abnormal electricity consumption situation.
The content of the invention
In view of this, the purpose of the embodiment of the present invention is to provide a kind of electricity consumption monitoring system to improve the problems referred to above.
To achieve the above object, the technical scheme that the present invention is provided is as described below:
In a first aspect, the invention provides a kind of electricity consumption monitoring system, the electricity consumption monitoring system includes:Service end, One gateway and multiple first intelligent electric meters, each described first intelligent electric meter include a unique identification code;
The service end is communicated to connect with multiple first intelligent electric meters respectively by first gateway, multiple described First intelligent electric meter is electrically connected at multiple load branch respectively one by one, and first for detecting multiple load branch is current Power consumption data;
First gateway is for the first current power amount data for detecting each described first intelligent electric meter And the identification code of each first intelligent electric meter is uploaded to the service end;
The service end for communicating to connect with multiple intelligent terminals, the plurality of intelligent terminal and the plurality of first intelligence The identification code of energy ammeter is corresponded, and the service end is additionally operable to detect described first according to each first intelligent electric meter Current power amount data calculate each the power consumption data of first intelligent electric meter in predetermined time period and wait to pay Electricity charge data, and the power consumption data by each described first intelligent electric meter in predetermined time period and treat electricity payment Data are sent respectively to the intelligent terminal corresponding with the identification code of the first intelligent electric meter each described;
The service end is additionally operable to the first stage when arbitrary first intelligent electric meter in the predetermined time period Power consumption data exceed setting first threshold when, to the corresponding intelligent terminal of identification code of first intelligent electric meter Send the first information, and the use of the second stage when arbitrary first intelligent electric meter in the predetermined time period When the ratio of electric quantity data and the power consumption data of the first stage exceedes the Second Threshold for setting, to first intelligent electric meter The corresponding intelligent terminal of identification code send the second information.
Second aspect, the invention provides another kind of electricity consumption monitoring system, the electricity consumption monitoring system includes:Service end, First gateway, multiple first intelligent electric meters and multiple intelligent terminals, each described first intelligent electric meter include a unique identification Code;
The service end is communicated to connect with multiple first intelligent electric meters respectively by first gateway, multiple described First intelligent electric meter is electrically connected at multiple load branch respectively one by one, and first for detecting multiple load branch is current Power consumption data;
First gateway is for the first current power amount data for detecting each described first intelligent electric meter And the identification code of each first intelligent electric meter is uploaded to the service end;
The service end is communicated to connect with the plurality of intelligent terminal, the plurality of intelligent terminal and the plurality of first intelligence The identification code of energy ammeter is corresponded, and the service end is additionally operable to detect described first according to each first intelligent electric meter Current power amount data calculate each the power consumption data of first intelligent electric meter in predetermined time period and wait to pay Electricity charge data, and the power consumption data by each described first intelligent electric meter in predetermined time period and treat electricity payment Data are sent respectively to the intelligent terminal corresponding with the identification code of the first intelligent electric meter each described;
The service end is additionally operable to the first stage when arbitrary first intelligent electric meter in the predetermined time period Power consumption data exceed setting first threshold when, to the corresponding intelligent terminal of identification code of first intelligent electric meter Send the first information, and the use of the second stage when arbitrary first intelligent electric meter in the predetermined time period When the ratio of electric quantity data and the power consumption data of the first stage exceedes the Second Threshold for setting, to first intelligent electric meter The corresponding intelligent terminal of identification code send the second information.
Compared with prior art, electricity consumption monitoring system of the invention has the advantages that:
The electricity consumption monitoring system that the present invention is provided is capable of achieving by the first intelligent electric meter to each load branch predetermined Power consumption data in time period and treat that electricity payment data are calculated, and by the power consumption data for obtaining and treat electricity payment Data is activation extremely intelligent terminal corresponding with each first intelligent electric meter, meanwhile, when the first intelligent electric meter is in predetermined time period Information can be sent to the corresponding intelligent terminal of the first intelligent electric meter when interior first stage and excessive second stage power consumption. Thus, being capable of achieving the prompting of making a copy of automatically and pay the fees to power consumption data, more traditional mode for manually making a copy of ammeter is compared, can The waste of human resources is effectively reduced, and power consumption data statistics is accurately, it is not error-prone, lift Consumer's Experience.Meanwhile, can to Family electricity payment is reminded, and is easy to the user can electricity payment in time.Secondly, in time power consumption data can be counted, is prevented The situation for only being led to not make a copy of due to seasonal electricity consumption or the problems such as being had a holiday or vacation with electric unit in time ammeter is occurred.In addition, can be by Abnormal electricity consumption situation feeds back to user, reaches the effect for reminding user's using electricity wisely, and when load branch leaks electricity or big User is reminded in time can during amount power stealing.
To enable the above objects, features and advantages of the present invention to become apparent, preferred embodiment cited below particularly, and coordinate Appended accompanying drawing, is described in detail below.
Description of the drawings
In order to be illustrated more clearly that the technical scheme of the embodiment of the present invention, below by to be used attached needed for embodiment Figure is briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, thus be not construed as it is right The restriction of scope, for those of ordinary skill in the art, on the premise of not paying creative work, can be with according to this A little accompanying drawings obtain other related accompanying drawings.
The electricity consumption monitoring system block diagram schematic diagram that Fig. 1 is provided for first embodiment of the invention.
The electricity consumption monitoring system block diagram schematic diagram that Fig. 2 is provided for second embodiment of the invention.
The electricity consumption monitoring system block diagram schematic diagram that Fig. 3 is provided for third embodiment of the invention.
The electricity consumption monitoring system block diagram schematic diagram that Fig. 4 is provided for fourth embodiment of the invention.
Icon:100- service ends;The first gateways of 200-;The first intelligent electric meters of 300-;The first video cameras of 400-;500- second Gateway;The second intelligent electric meters of 600-;The second video cameras of 700-;800- alarms;900- intelligent terminals.
Specific embodiment
To make purpose, technical scheme and the advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is The a part of embodiment of the present invention, rather than the embodiment of whole.Present invention enforcement generally described and illustrated in accompanying drawing herein The component of example can be arranged and be designed with a variety of configurations.
Therefore, the detailed description of embodiments of the invention below to providing in the accompanying drawings is not intended to limit claimed The scope of the present invention, but be merely representative of the present invention selected embodiment.Based on the embodiment in the present invention, this area is common The every other embodiment obtained under the premise of creative work is not made by technical staff, belongs to the model of present invention protection Enclose.
It should be noted that:Similar label and letter represent similar terms in following accompanying drawing, therefore, once a certain Xiang Yi It is defined in individual accompanying drawing, then in subsequent accompanying drawing which further need not be defined and is explained.
In describing the invention, it should be noted that term " " center ", " on ", D score, "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " interior ", " outward " be based on orientation shown in the drawings or position relationship, or should Invention product using when the orientation usually put or position relationship, be for only for ease of the description present invention and simplify description, and not Be indicate or imply the device or element of indication must have specific orientation, with specific azimuth configuration and operation, therefore not It is understood that as limitation of the present invention.Additionally, term " first ", " second ", " the 3rd " etc. are only used for distinguishing description, and can not manage Solve to indicate or implying relative importance.
Additionally, the term such as term " level ", " vertical ", " pendency " is not offered as requiring part abswolute level or pendency, and Can be to be slightly tilted.As " level " only refers to for its direction relative " vertical " more level, it is not the expression structure Must be fully horizontal, and can be to be slightly tilted.
In describing the invention, in addition it is also necessary to explanation, unless otherwise clearly defined and limited, term " setting ", " installation ", " being connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected, or be detachably connected, or one The connection of body ground;Can be mechanically connected, or electrically connect;Can be joined directly together, it is also possible to indirect by intermediary It is connected, can is the connection of two element internals.For the ordinary skill in the art, can be with concrete condition understanding State term concrete meaning in the present invention.
First embodiment
Fig. 1 is referred to, is the block diagram representation of electricity consumption monitoring system provided in an embodiment of the present invention.As shown in figure 1, described Electricity consumption monitoring system includes service end 100, the first gateway 200 and multiple first intelligent electric meters 300.
Wherein, each first intelligent electric meter 300 includes a unique identification code, and service end 100 passes through 200 points of the first gateway Do not communicate to connect with the plurality of first intelligent electric meter 300, the plurality of first intelligent electric meter 300 is electrically connected at respectively one by one Multiple load branch, for detecting the first current power amount data of multiple load branch respectively.In the present embodiment, load branch May refer to the power supply branch road powered for the electrical equipment of same user or unit.
First gateway 200 is then for the first current power amount data for detecting each first intelligent electric meter 300 and every The identification code of individual first intelligent electric meter 300 is uploaded to service end 100.
Service end 100 for communicating to connect with multiple intelligent terminals, multiple intelligent terminals and multiple first intelligent electric meters 300 Identification code set up have one-to-one relationship, service end 100 is additionally operable to first detected according to each the first intelligent electric meter 300 Current power amount data calculate each the power consumption data of the first intelligent electric meter 300 in predetermined time period, and according to every What power consumption data of individual first intelligent electric meter 300 in predetermined time period calculated each intelligent electric meter treats electricity payment number According to while by each the power consumption data of the first intelligent electric meter 300 in predetermined time period and treating electricity payment data is activation To intelligent terminal corresponding with the identification code of each the first intelligent electric meter 300.
For example, service end 100 can be detected according to each the first intelligent electric meter 300 and be started every month and at the end of this month The front power consumption data of (such as from 0 o'clock sharp of on January 1st, 2016 to 24 o'clock sharps of on January 31st, 2016) calculate the first intelligent electric meter The power consumption data in 300 this month, and electricity payment number is treated according to what of that month power consumption data and electricity Unit Price calculated this month According to (electricity charge that i.e. this month need to pay).Then by the power consumption data in each 300 this month of the first intelligent electric meter and treat electricity payment Data is activation is to intelligent terminal corresponding with the identification code of the first intelligent electric meter 300 (if service end 100 is by the first intelligent electric meter A Of that month power consumption data and treat that electricity payment data is activation gives the corresponding intelligent terminal of identification code of the first intelligent electric meter A A1, the first intelligent electric meter B of that month power consumption data and treat that electricity payment data are then sent to the identification with the first intelligent electric meter B The corresponding intelligent terminal B1 of code).
Service end 100 is additionally operable to the first stage when arbitrary one the first intelligent electric meter 300 in predetermined time period When power consumption data exceed the first threshold of setting, send to the corresponding intelligent terminal of identification code of first intelligent electric meter 300 First information, and the power consumption data of the second stage when arbitrary first intelligent electric meter 300 in predetermined time period When exceeding the Second Threshold for setting with the ratio of the power consumption data of first stage, to the identification code correspondence of the first intelligent electric meter 300 Intelligent terminal send the second information.Each one first threshold of correspondence of the first intelligent electric meter 300, each first intelligence electricity The first threshold of table 300 can be true according to the power consumption data of first intelligent electric meter 300 in front several predetermined time periods It is fixed.Second Threshold is the power consumption data of second stage of first intelligent electric meter 300 within the time period ordered and first stage The ratio of power consumption data.
For example, the predetermined time period for every month the first arrival the end of month moon, service end 100 can by the predetermined amount of time according to The first tenday period of a month of every month, the middle ten days and the last ten-days period are divided into first stage, second stage and phase III.Each first intelligent electric meter 300 pairs The first threshold answered is the same first intelligent electric meter average power consumption data of 300 front 3 months, and Second Threshold is set as 2.When certain One first intelligent electric meter 300 is when the average power consumption data of first 3 months are 50 degree, if first intelligent electric meter 300 is being worked as Month the power consumption data of first stage exceeded 50 degree, then service end 100 to the 300 corresponding intelligence of the first intelligent electric meter Terminal sends the first information and points out user's this month power consumption higher, to reach the effect for reminding user's using electricity wisely.If First intelligent electric meter 300 is exceeded with the ratio of the power consumption data of first stage in the power consumption data of of that month second stage When 2 (the power consumption data of second stage are more than 2 times of the power consumption data of first stage), then service end 100 to this First intelligent electric meter, 300 corresponding intelligent terminal sends the second information, to remind user power utilization situation exception, if user Roughly the same using the situation of electricity with the first stage in the situation using electricity of second stage, then there is electric leakage or a large amount of in explanation The situation of power stealing occurs, so as to realize that user's exception electricity consumption is reminded.
In the present embodiment, intelligent terminal can be smart mobile phone, PC, panel computer or personal digital assistant etc., this Limit in embodiment.
To sum up, the electricity consumption monitoring system for applying example offer of the invention is capable of achieving very easily to every road load branch predetermined The power consumption data of (such as every month) and the electricity charge paid of needs in time period are counted, and by the power consumption data of statistics and The electricity charge paid of needs are sent to corresponding intelligent terminal, to remind user's electricity payment at the intelligent terminal and need to pay The amount of money of the electricity charge.Meanwhile, when first stage of first intelligent electric meter in predetermined time period and second stage power consumption it is excessive The corresponding intelligent terminal of identification code of the first intelligent electric meters of Shi Kexiang 300 sends information.The electricity consumption monitoring that the present invention is provided The more traditional mode for manually making a copy of ammeter of system is compared, and can effectively reduce the waste of human resources, and power consumption data statistics Accurately, it is not error-prone, lift Consumer's Experience.Meanwhile, user's electricity payment can be reminded, be easy to user pay electricity in time Take.Secondly, in time power consumption data can be counted, prevents due to seasonal electricity consumption or cause the problems such as being had a holiday or vacation with electric unit The situation that ammeter cannot be made a copy of in time occurs.In addition, abnormal electricity consumption situation can be fed back to user, reach prompting user and save The effect of electricity consumption, and user can be reminded in time when load branch leaks electricity or is sneaked current in a large number.
Second embodiment
Fig. 2 is referred to, electricity consumption monitoring system provided in an embodiment of the present invention is carried out in the basic unit of first embodiment Further improve, from unlike first embodiment, electricity consumption monitoring system provided in an embodiment of the present invention is also included and first Multiple first video cameras 400 of 300 quantity identical of intelligent electric meter, multiple first video cameras 400 and multiple first intelligent electric meters 300 Correspond, and multiple first video cameras 400 are communicated to connect with service end 100 by the first gateway 200.
First video camera 400 is installed at corresponding first intelligent electric meter 300, for carrying out to the first intelligent electric meter 300 Shooting obtains the picture signal of the first current power amount data of the first intelligent electric meter 300.Service end 100 is additionally operable to calculating every During power consumption data of individual first intelligent electric meter 300 in predetermined time period, control letter is sent to each first video camera 400 Number, corresponding first intelligent electric meter 300 is shot with controlling each first video camera 400, obtain each first intelligence electricity The picture signal of the first current power amount data of table 300.
First gateway 200 is additionally operable to the picture signal of the first current power amount data of each the first intelligent electric meter 300 It is uploaded to service end 100.
Service end 100 is additionally operable to send out the picture signal of the first current power amount data of each the first intelligent electric meter 300 Give intelligent terminal corresponding with the identification code of each the first intelligent electric meter 300.
Thus, when service end 100 is by each the power consumption data of the first intelligent electric meter 300 in predetermined time period and treats Electricity payment data is activation to the identification code of each the first intelligent electric meter 300 during corresponding intelligent terminal, can also by each the The picture signal of the first current power amount data of one intelligent electric meter 300 is sent to corresponding intelligent terminal, to show to user The foundation of charge, lifts Consumer's Experience.
To sum up, the electricity consumption monitoring system for applying example offer of the invention is capable of achieving very easily to every road load branch predetermined The power consumption data of (such as every month) and the electricity charge paid of needs in time period are counted, and by the power consumption data of statistics and The electricity charge paid of needs are sent to corresponding intelligent terminal, to remind user's electricity payment at intelligent terminal and need to pay electricity The amount of money for taking.Meanwhile, it is right can be also sent to the picture signal of the first current power amount data of each the first intelligent electric meter 300 The intelligent terminal answered, to show the foundation of charge to user, lifts Consumer's Experience.In addition, can be anti-by abnormal electricity consumption situation Feed user, reaches the effect for reminding user's using electricity wisely, and can carry in time when load branch leaks electricity or is sneaked current in a large number Awake user.
3rd embodiment
Fig. 3 is referred to, electricity consumption monitoring system provided in an embodiment of the present invention is carried out in the basic unit of second embodiment Further improve, from unlike second embodiment, electricity consumption monitoring system provided in an embodiment of the present invention also includes the second net The 500, second intelligent electric meter 600 and alarm 800 are closed, the second intelligent electric meter 600 is led to by the second gateway 500 and service end 100 Letter connection.
Second intelligent electric meter 600 is electrically connected at the power-supply system for powering for multiple load branch, for detecting Second current power amount data of the plurality of load branch.Service end 100 is additionally operable to judge all first intelligence in the same time period Whether the power consumption data sum of energy ammeter 300 is with the ratio of the power consumption data of the second intelligent electric meter 600 beyond the threshold for setting Value scope.
Alarm 800 is electrically connected with service end 100, and service end 100 is additionally operable to when all first intelligence in the same time period The power consumption data sum of energy ammeter 300 is with the ratio of the power consumption data of the second intelligent electric meter 600 less than the threshold value model for setting When enclosing, alarm control signal is sent to alarm 800 so that alarm 800 sends alarm signal.
Second intelligent electric meter 600 is electrically connected at the power-supply system for powering for multiple load branch, due to power supply Part power consumption on main line, it is dry that the power consumption sum within the same time period of multiple load branch can be slightly less than power supply Power consumption on road, and both ratio is maintained at certain threshold range, if occurring more taking privately in power-supply system During the power stealing behavior connected wires, both ratio can be less than this scope.Therefore, service end 100 is preset with a threshold value model (such as 95%-98%) is enclosed, when the power consumption data sum of all first intelligent electric meters 300 in the same time period and the second intelligence electricity When the ratio of the power consumption data of table 600 is less than the threshold range of the setting, then illustrate to be likely to occur more private in power-supply system From the power stealing behavior of overlap joint electric wire, now, service end 100 sends alarm control signal to alarm 800, and alarm 800 is received Send alarm signal after alarm control signal, be likely to occur in the staff's power-supply system for pointing out service end 100 it is more privately The power stealing behavior of overlap joint electric wire.
In the present embodiment, alarm 800 can be adopted but be not limited to buzzer or loudspeaker, not do concrete in the present embodiment Limit.
Further, Fig. 3 is referred to, the electricity consumption monitoring system that the present embodiment is provided also includes the second video camera 700, the Two video cameras 700 are communicated to connect with service end 100 by the second gateway 500.
Second video camera 700 is installed at the second intelligent electric meter 600, for carrying out shooting to the second intelligent electric meter 600 To the picture signal of the second current power amount data of the second intelligent electric meter 600.Second gateway 500 is additionally operable to for getting The picture signal of two current power amount data is uploaded to service end 100.Thus, what the second gateway 500 can be uploaded by service end 100 The picture signal of the second current power amount data is stored as historical record, so as to follow-up access, verification.
To sum up, the electricity consumption monitoring system for applying example offer of the invention is capable of achieving very easily to every road load branch predetermined The power consumption data of (such as every month) and the electricity charge paid of needs in time period are counted, and by the power consumption data of statistics and The electricity charge that needs are paid are sent to corresponding intelligent terminal, to remind user's electricity payment and needs at the intelligent terminal to pay Receive the amount of money of the electricity charge.Meanwhile, also the picture signal of the first current power amount data of each the first intelligent electric meter 300 can be sent To corresponding intelligent terminal, to show the foundation of charge to user, Consumer's Experience is lifted.Secondly, can also be in power-supply system The power stealing behavior for overlapping privately electric wire being likely to occur is monitored warning, and current to the second of the second intelligent electric meter 600 The picture signal of power consumption data is stored, so as to follow-up access, verification.In addition, abnormal electricity consumption situation can be fed back To user, the effect for reminding user's using electricity wisely is reached, and can be reminded in time when load branch leaks electricity or is sneaked current in a large number User.
Fourth embodiment
Refer to Fig. 4, present example provides another kind of electricity consumption monitoring system, and unlike first embodiment, this The electricity consumption monitoring system that inventive embodiments are provided also is included and the multiple intelligent terminals of 300 quantity identical of the first intelligent electric meter 900, multiple intelligent terminals 900 are communicated to connect with service end 100, and multiple intelligent terminals 900 and multiple first intelligent electric meters 300 Identification code correspond.
The preferred embodiments of the present invention are the foregoing is only, the present invention is not limited to, for the skill of this area For art personnel, the present invention can have various modifications and variations.It is all within the spirit and principles in the present invention, made any repair Change, equivalent, improvement etc., should be included within the scope of the present invention.It should be noted that:Similar label and letter exist Similar terms is represented in figure below, therefore, once being defined in a certain Xiang Yi accompanying drawing, then it is not required in subsequent accompanying drawing Which is further defined and is explained.
The above, the only specific embodiment of the present invention, but protection scope of the present invention is not limited thereto, any Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all be contained Cover within protection scope of the present invention.Therefore, protection scope of the present invention described should be defined by scope of the claims.

Claims (10)

1. a kind of electricity consumption monitoring system, it is characterised in that include:Service end, the first gateway and multiple first intelligent electric meters, each First intelligent electric meter includes a unique identification code;
The service end is communicated to connect with multiple first intelligent electric meters respectively by first gateway, and multiple described first Intelligent electric meter is electrically connected at multiple load branch respectively one by one, for detecting the first current power of multiple load branch Amount data;
First gateway for the first current power amount data for detecting each described first intelligent electric meter and The identification code of each first intelligent electric meter is uploaded to the service end;
, for communicating to connect with multiple intelligent terminals, the plurality of intelligent terminal and the plurality of first intelligence are electric for the service end The identification code of table is corresponded, and the service end is additionally operable to detect described first according to each first intelligent electric meter current Power consumption data calculate each the power consumption data of first intelligent electric meter in predetermined time period and treat electricity payment Data, and the power consumption data by each described first intelligent electric meter in predetermined time period and treat electricity payment data It is sent respectively to the intelligent terminal corresponding with the identification code of the first intelligent electric meter each described;
The service end is additionally operable to the use of the first stage when arbitrary first intelligent electric meter in the predetermined time period When electric quantity data exceedes the first threshold of setting, send to the corresponding intelligent terminal of identification code of first intelligent electric meter First information, and the power consumption of the second stage when arbitrary first intelligent electric meter in the predetermined time period When the ratio of data and the power consumption data of the first stage exceedes the Second Threshold for setting, to the knowledge of first intelligent electric meter The second information of the other corresponding intelligent terminal transmission of code.
2. electricity consumption monitoring system according to claim 1, it is characterised in that also including multiple first video cameras, Duo Gesuo State the first video camera to correspond with multiple first intelligent electric meters respectively, for obtaining each first intelligent electric meter The picture signal of the first current power amount data, first gateway are additionally operable to work as the first of each first intelligent electric meter The picture signal of front power consumption data is uploaded to the service end.
3. electricity consumption monitoring system according to claim 2, it is characterised in that the service end be additionally operable to by each described The picture signal of the first current power amount data of one intelligent electric meter is sent to the knowledge with the first intelligent electric meter each described respectively The corresponding intelligent terminal of other code.
4. electricity consumption monitoring system according to claim 1, it is characterised in that also including the second gateway and the second intelligence electricity Table, second intelligent electric meter are communicated to connect by second gateway and the service end;
Second intelligent electric meter is electrically connected at the plurality of load branch, for detecting the second of the plurality of load branch Current power amount data;
The service end is additionally operable to judge the power consumption data sum of all first intelligent electric meters and institute in the same time period The ratio of power consumption data of the second intelligent electric meter is stated whether beyond the threshold range for setting.
5. electricity consumption monitoring system according to claim 4, it is characterised in that also including the second video camera, described second takes the photograph Camera is communicated to connect by second gateway and the service end, and second video camera is used to obtain the described second current use The picture signal of electric quantity data, second gateway are additionally operable to the image letter of the second current power amount data that will be got Number it is uploaded to the service end.
6. electricity consumption monitoring system according to claim 4, it is characterised in that also including alarm, the alarm and institute Service end electric connection is stated, the service end is additionally operable to when the power consumption number of all first intelligent electric meters in the same time period According to sum and the power consumption data of second intelligent electric meter ratio less than the setting threshold range when, to the warning Device sends alarm control signal so that the alarm sends alarm signal.
7. electricity consumption monitoring system according to claim 6, it is characterised in that the alarm is buzzer.
8. electricity consumption monitoring system according to claim 1, it is characterised in that the alarm is loudspeaker.
9. electricity consumption monitoring system according to claim 1, it is characterised in that the intelligent terminal is smart mobile phone.
10. a kind of electricity consumption monitoring system, it is characterised in that include:Service end, the first gateway, multiple first intelligent electric meters and many Individual intelligent terminal, each described first intelligent electric meter include a unique identification code;
The service end is communicated to connect with multiple first intelligent electric meters respectively by first gateway, and multiple described first Intelligent electric meter is electrically connected at multiple load branch respectively one by one, for detecting the first current power of multiple load branch Amount data;
First gateway for the first current power amount data for detecting each described first intelligent electric meter and The identification code of each first intelligent electric meter is uploaded to the service end;
The service end is communicated to connect with the plurality of intelligent terminal, and the plurality of intelligent terminal and the plurality of first intelligence are electric The identification code of table is corresponded, and the service end is additionally operable to detect described first according to each first intelligent electric meter current Power consumption data calculate each the power consumption data of first intelligent electric meter in predetermined time period and treat electricity payment Data, and the power consumption data by each described first intelligent electric meter in predetermined time period and treat electricity payment data It is sent respectively to the intelligent terminal corresponding with the identification code of the first intelligent electric meter each described;
The service end is additionally operable to the use of the first stage when arbitrary first intelligent electric meter in the predetermined time period When electric quantity data exceedes the first threshold of setting, send to the corresponding intelligent terminal of identification code of first intelligent electric meter First information, and the power consumption of the second stage when arbitrary first intelligent electric meter in the predetermined time period When the ratio of data and the power consumption data of the first stage exceedes the Second Threshold for setting, to the knowledge of first intelligent electric meter The second information of the other corresponding intelligent terminal transmission of code.
CN201611069418.3A 2016-11-28 2016-11-28 Electricity consumption monitoring system Pending CN106556738A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611069418.3A CN106556738A (en) 2016-11-28 2016-11-28 Electricity consumption monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611069418.3A CN106556738A (en) 2016-11-28 2016-11-28 Electricity consumption monitoring system

Publications (1)

Publication Number Publication Date
CN106556738A true CN106556738A (en) 2017-04-05

Family

ID=58445347

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611069418.3A Pending CN106556738A (en) 2016-11-28 2016-11-28 Electricity consumption monitoring system

Country Status (1)

Country Link
CN (1) CN106556738A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107015038A (en) * 2017-04-21 2017-08-04 武汉理工大学 A kind of power consumption reminding method, device and ammeter based on intelligent electric meter
CN107478882A (en) * 2017-09-06 2017-12-15 上海斐讯数据通信技术有限公司 Intelligent electric meter long-distance monitorng device
CN107623975A (en) * 2017-09-30 2018-01-23 深圳市鑫汇达机械设计有限公司 A kind of Intelligent lighting power-saving TT&C system
CN108401007A (en) * 2018-01-12 2018-08-14 上海大学 A kind of meter register method based on intelligent gateway
CN109374964A (en) * 2018-10-30 2019-02-22 四川洪诚电气科技有限公司 Use electric detection method and Internet of things system based on Internet of Things
CN110646664A (en) * 2019-09-18 2020-01-03 珠海格力电器股份有限公司 Method and device for monitoring power consumption of multi-split system and multi-split system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101179206A (en) * 2007-09-12 2008-05-14 刘爱民 Low-voltage electric network remote monitoring and service network
CN202759542U (en) * 2012-07-30 2013-02-27 浙江新能量科技有限公司 Remote electric energy information collection system based on image identification
CN103150888A (en) * 2013-03-05 2013-06-12 康宇星科技(北京)有限公司 Method for realizing automatic electricity meter reading based on Ethernet passive optical network
US20140330955A1 (en) * 2013-05-03 2014-11-06 Landis+Gyr Innovations, Inc. Monitoring the Health of a Home Area Network
CN105528877A (en) * 2014-09-29 2016-04-27 镇江石鼓文智能化系统开发有限公司 Remote ammeter system
CN205428177U (en) * 2016-02-25 2016-08-03 贵州大学 Automatic data logging system based on zigBee
CN205583848U (en) * 2016-04-13 2016-09-14 安徽征圣智能科技有限公司 Intelligent ammeter cabinet

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101179206A (en) * 2007-09-12 2008-05-14 刘爱民 Low-voltage electric network remote monitoring and service network
CN202759542U (en) * 2012-07-30 2013-02-27 浙江新能量科技有限公司 Remote electric energy information collection system based on image identification
CN103150888A (en) * 2013-03-05 2013-06-12 康宇星科技(北京)有限公司 Method for realizing automatic electricity meter reading based on Ethernet passive optical network
US20140330955A1 (en) * 2013-05-03 2014-11-06 Landis+Gyr Innovations, Inc. Monitoring the Health of a Home Area Network
CN105528877A (en) * 2014-09-29 2016-04-27 镇江石鼓文智能化系统开发有限公司 Remote ammeter system
CN205428177U (en) * 2016-02-25 2016-08-03 贵州大学 Automatic data logging system based on zigBee
CN205583848U (en) * 2016-04-13 2016-09-14 安徽征圣智能科技有限公司 Intelligent ammeter cabinet

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107015038A (en) * 2017-04-21 2017-08-04 武汉理工大学 A kind of power consumption reminding method, device and ammeter based on intelligent electric meter
CN107478882A (en) * 2017-09-06 2017-12-15 上海斐讯数据通信技术有限公司 Intelligent electric meter long-distance monitorng device
CN107623975A (en) * 2017-09-30 2018-01-23 深圳市鑫汇达机械设计有限公司 A kind of Intelligent lighting power-saving TT&C system
CN108401007A (en) * 2018-01-12 2018-08-14 上海大学 A kind of meter register method based on intelligent gateway
CN108401007B (en) * 2018-01-12 2021-06-04 上海大学 Meter reading method based on intelligent gateway
CN109374964A (en) * 2018-10-30 2019-02-22 四川洪诚电气科技有限公司 Use electric detection method and Internet of things system based on Internet of Things
CN110646664A (en) * 2019-09-18 2020-01-03 珠海格力电器股份有限公司 Method and device for monitoring power consumption of multi-split system and multi-split system

Similar Documents

Publication Publication Date Title
CN106556738A (en) Electricity consumption monitoring system
CN201796423U (en) Single-phase remote cost-control smart electricity meter
CN205318534U (en) Gas table of mutual transmission of IC -card, NFC and bluetooth
US20130066773A1 (en) Intelligent administration system for paying electric bill
CN201210322Y (en) Pre-payment electrical energy meter
EP2881911A1 (en) Energy management device and energy management method
CN106093507A (en) A kind of monitoring method and system
CN103543309B (en) Method and apparatus to user reminding power consumption
CN104966355A (en) Intelligent water meter control system achieving self service
CN106066416A (en) A kind of intelligent electric meter based on mobile Internet
CN205880051U (en) Smart electric meter based on mobile internet
CN106023456B (en) Self-power generation type Intelligent watermeter based on radio-frequency technique
CN101520919A (en) Public electricity utilization management system
CN205066845U (en) Water gauge based on wifi wireless transmission network
Kate et al. ZIGBEE based monitoring theft detection and automatic electricity meter reading
CN205193130U (en) Take voice broadcast's smart electric meter
CN107231276A (en) Multi-purpose intelligent Internet of Things communication means and system
CN101026660A (en) Mobile phone prepaid fee power management terminal
KR101904831B1 (en) Intellgent building management system and method for controlling thereof
CN108983679A (en) A kind of intelligent remote controlling terminal and system
CN201904653U (en) Service terminal equipment in electricity utilization fields
JPH10111326A (en) Automatic measurement of electric power and its control method
US20170325301A1 (en) Methods And Systems Of Proactive Monitoring And Metering Of Lighting Devices
US20170287259A1 (en) Electricity Smart Meters And Electricity Distribution Systems
CN108648436A (en) A kind of multiple-in-one collector and collecting method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Fan Xianshen

Inventor after: Cheng Zhaoliang

Inventor after: Liu Sixian

Inventor before: Fan Xianshen

CB03 Change of inventor or designer information
RJ01 Rejection of invention patent application after publication

Application publication date: 20170405

RJ01 Rejection of invention patent application after publication