CN106522567A - Assembled folded discharging platform and construction mode thereof - Google Patents
Assembled folded discharging platform and construction mode thereof Download PDFInfo
- Publication number
- CN106522567A CN106522567A CN201611151230.3A CN201611151230A CN106522567A CN 106522567 A CN106522567 A CN 106522567A CN 201611151230 A CN201611151230 A CN 201611151230A CN 106522567 A CN106522567 A CN 106522567A
- Authority
- CN
- China
- Prior art keywords
- steel
- channel
- support body
- assembled
- discharging platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007599 discharging Methods 0.000 title claims abstract description 20
- 238000010276 construction Methods 0.000 title claims description 10
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 100
- 239000010959 steel Substances 0.000 claims abstract description 100
- 210000000481 breast Anatomy 0.000 claims description 12
- 239000000725 suspension Substances 0.000 claims description 10
- 229910003460 diamond Inorganic materials 0.000 claims description 6
- 239000010432 diamond Substances 0.000 claims description 6
- 210000003205 muscle Anatomy 0.000 claims 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/166—Landings, receiving platforms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention relates to an assembled folded discharging platform which comprises I-shaped steel, a platform plate assembly is detachably arranged in the I-shaped steel and comprises a plurality of channel steel frame bodies arranged in parallel, pattern plates are arranged in the channel steel frame bodies, and a plurality of lifting rings are arranged at the position where the pattern plates and the channel steel frame bodies are connected. The single assembled folded discharging platform is small in volume, and convenient to transport, convenient and fast to assemble and disassemble, scientific, firm and safe in structure, and low in cost.
Description
Technical field
The present invention relates to a kind of assembled folds discharging platform and its form of construction work, it is adaptable to which the material of building floor is removed
Fortune and transfer.
Background technology
At present, it is in engineering to adopt monoblock type discharging platform, monoblock type discharging platform to there is transport inconvenience, somewhat expensive more
The shortcomings of.It is therefore proposed that of the invention.
The content of the invention
For the above-mentioned technical problem of prior art, the invention provides a kind of assembled folds discharging platform and its construction
Method, which adopts fabricated construction, and cost of transportation and piece weight are reduced significantly, convenient to transport, and saves freight charges.
To reach above-mentioned purpose, the present invention is achieved by the following technical solutions:
A kind of assembled folds discharging platform, including I-steel, and platform board component, institute are removably provided with the I-steel
The platform board component stated includes several channel-section steel support bodys arranged side by side, is provided with diamond plate in the U-steel frame body, and diamond plate and
The junction of channel-section steel support body is provided with several suspension ring.
The afterbody of the I-steel is connected with gear pin.
The left and right sides of the I-steel is provided with other plate, and described side includes square tube frame, the square tube frame and work
The junction of word steel is provided with angle steel.
Closure door is embedded with described angle steel.
It is equipped with described channel-section steel support body and I-steel for installing the screw of nut, and two adjacent screws does not exist
On same straight line.
The side of the channel-section steel support body is provided with steel bar end.
A kind of assembled folds the construction method of discharging platform, comprises the following steps:
(1)Two I-steel are placed, size of the size between I-steel more than channel-section steel support body;
(2)By channel-section steel support body while being shelved on I-steel bottom flap, and to good screw;Respectively by the spiral shell on channel-section steel support body both sides
Silk and pad through after screw are connected with the nut of channel-section steel support body, and are tightened;
(3)The other plate of the left and right sides is attached by assembly hinge pin, and breast board two ends bottom and I-steel are carried out into screw thread company
Connect;
(4)End breast board is inserted in the U-type groove of both sides breast board end, and bolt is inserted in screw, by breast board and I-steel
It is fixed;
(5)Four suspension ring of channel-section steel support body are put on steel wire rope, and the specified location of floor is suspended to tower crane;
(6)I-steel later half position is put in pre-buried good anchor ear, and is fixed with panel nut;
(7)The suspension ring of I-steel both sides are packaged into steel wire rope, and is tensed in having hung the pre-buried ring in upper strata.
Beneficial effects of the present invention are as follows:
The assembled of the present invention folds discharging platform and its construction method, single-piece small volume, is readily transported;It is convenient to mount and dismount, quickly,
Scientific structure, firm, safety, and it is with low cost.
Description of the drawings
Fig. 1 is the structural representation of the present invention;
A-A direction cross section structure diagrams of the Fig. 2 for Fig. 1;
Fig. 3 is the structural representation of the other plate in the present invention;
Fig. 4 is the structural representation of the closure door in the present invention;
Fig. 5 is the structural representation of the platform board component in the present invention;
Fig. 6 is the screwed hole position view of the channel-section steel support body in the present invention;
Fig. 7 is the screwed hole position view of the I-steel in the present invention;
Wherein, 1 be I-steel, 2 be channel-section steel support body, 3 be diamond plate, 4 be suspension ring, 5 for gear pin, 6 be square tube frame, 7 be angle steel,
8 to seal up a door, 9 is screwed hole, 10 is nut, 11 is steel bar end.
Specific embodiment
With reference to specific embodiment, the present invention is further illustrated, but protection scope of the present invention is not limited to
This.
As shown in figs. 1-7, assembled of the invention folds discharging platform, including I-steel 1, dismountable in I-steel 1
Platform board component is installed, and platform board component includes several channel-section steel support bodys 2 arranged side by side, diamond plate is provided with channel-section steel support body 2
3, and the junction of diamond plate 3 and channel-section steel support body 2 is provided with several suspension ring 4.The afterbody of I-steel 1 is connected with gear pin 5.I-steel
1 left and right sides is provided with other plate, and side includes square tube frame 6, and square tube frame 6 is provided with angle steel 7, angle with the junction of I-steel 1
Closure door 8 is embedded with steel 7.It is equipped with channel-section steel support body 2 and I-steel 1 for installing the screw 9 of nut 10, and two adjacent spiral shells
Hole 9 is not on the same line.
Further arrange, to make platform high plate avoid device to hole, the present invention to be provided with the side of channel-section steel support body 2 when advancing channel-section steel
Steel bar end 11, the left side and right side of channel-section steel support body 2 are respectively equipped with two steel bar ends 11, and two steel bar ends 11 are located at U-steel frame respectively
The upper and lower of body 2.
Assembled of the present invention folds the construction method of discharging platform, comprises the following steps:
(1)Two I-steel 1 are placed, size of the size between I-steel 1 more than channel-section steel support body 2;
(2)2 one side of channel-section steel support body is shelved on 1 bottom flap of I-steel, and to good screw 9;Respectively by 2 both sides of channel-section steel support body
Screw and pad through after screw 9, be connected with the nut of channel-section steel support body 2, and tighten;
(3)The other plate of the left and right sides is attached by assembly hinge pin, and breast board two ends bottom and I-steel 1 are carried out into screw thread company
Connect;
(4)End breast board is inserted in the U-type groove of both sides breast board end, and bolt is inserted in screw 9, by breast board and I-steel
1 fixes;
(5)Four suspension ring 4 of channel-section steel support body 2 are put on steel wire rope, and the specified location of floor is suspended to tower crane;
(6)1 later half position of I-steel is put in pre-buried good anchor ear, and is fixed with panel nut 10;
(7)The suspension ring 4 of 1 both sides of I-steel are packaged into steel wire rope, and is tensed in having hung the pre-buried ring in upper strata.
The present invention adopts fabricated construction, and cost of transportation and piece weight are reduced significantly, convenient to transport, and saves freight charges.
Above-described embodiment is only used for the inventive concept for illustrating the present invention, rather than the restriction to rights protection of the present invention,
All changes for carrying out unsubstantiality using this design to the present invention, all should fall into protection scope of the present invention.
Claims (7)
1. a kind of assembled folds discharging platform, it is characterised in that:Including I-steel, removably it is provided with the I-steel
Platform board component, described platform board component include several channel-section steel support bodys arranged side by side, are provided with decorative pattern in the U-steel frame body
Plate, and the junction of diamond plate and channel-section steel support body is provided with several suspension ring.
2. assembled as claimed in claim 1 folds discharging platform, it is characterised in that:The afterbody of the I-steel is connected with gear
Pin.
3. assembled as claimed in claim 1 folds discharging platform, it is characterised in that:The left and right sides of the I-steel is provided with
Other plate, described side include square tube frame, and the square tube frame is provided with angle steel with the junction of I-steel.
4. assembled as claimed in claim 3 folds discharging platform, it is characterised in that:Closure door is embedded with described angle steel.
5. assembled as claimed in claim 1 folds discharging platform, it is characterised in that:On described channel-section steel support body and I-steel
It is equipped with for installing the screw of nut, and two adjacent screws is not on the same line.
6. assembled as claimed in claim 1 folds discharging platform, it is characterised in that:The side of the channel-section steel support body is provided with steel
Muscle head.
7. a kind of assembled folds the construction method of discharging platform, it is characterised in that comprise the following steps:
(1)Two I-steel are placed, size of the size between I-steel more than channel-section steel support body;
(2)By channel-section steel support body while being shelved on I-steel bottom flap, and to good screw;Respectively by the spiral shell on channel-section steel support body both sides
Silk and pad through after screw hole are connected with the nut of channel-section steel support body, and are tightened;
(3)The other plate of the left and right sides is attached by assembly hinge pin, and breast board two ends bottom and I-steel are carried out into screw thread company
Connect;
(4)End breast board is inserted in the U-type groove of both sides breast board end, and bolt is inserted in screw, by breast board and I-steel
It is fixed;
(5)Four suspension ring of channel-section steel support body are put on steel wire rope, and the specified location of floor is suspended to tower crane;
(6)I-steel later half position is put in pre-buried good anchor ear, and is fixed with panel nut;
(7)The suspension ring of I-steel both sides are packaged into steel wire rope, and is tensed in having hung the pre-buried ring in upper strata.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611151230.3A CN106522567A (en) | 2016-12-14 | 2016-12-14 | Assembled folded discharging platform and construction mode thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611151230.3A CN106522567A (en) | 2016-12-14 | 2016-12-14 | Assembled folded discharging platform and construction mode thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106522567A true CN106522567A (en) | 2017-03-22 |
Family
ID=58339357
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611151230.3A Pending CN106522567A (en) | 2016-12-14 | 2016-12-14 | Assembled folded discharging platform and construction mode thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106522567A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587708A (en) * | 2017-09-22 | 2018-01-16 | 宁夏桥多美路桥钢模板科技有限公司 | Foldable high-altitude construction platform and high-altitude construction method |
CN110499916A (en) * | 2019-08-31 | 2019-11-26 | 杭州昂创科技有限公司 | Exempt from the construction method through walls for increasing anchorage support pull folding discharging platform |
CN113503045A (en) * | 2021-08-25 | 2021-10-15 | 浙江鸿翔建设集团股份有限公司 | Lift assembled business turn over material platform in construction |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09125690A (en) * | 1995-11-02 | 1997-05-13 | Japan Steels Internatl Kk | Assembled temporary passage |
CN201297036Y (en) * | 2008-11-19 | 2009-08-26 | 常州第一建筑工程有限公司 | Discharging platform |
CN202031310U (en) * | 2011-04-27 | 2011-11-09 | 天津天一建设集团有限公司 | Detachable structural steel unloading platform |
CN204691264U (en) * | 2015-06-19 | 2015-10-07 | 中国科学院重庆绿色智能技术研究院 | A kind of detachable folding discharging platform |
CN105239765A (en) * | 2015-10-26 | 2016-01-13 | 中国建筑股份有限公司 | Foldable multifunctional overhanging unloading platform |
CN206360381U (en) * | 2016-12-14 | 2017-07-28 | 绍兴明煌建材科技有限公司 | A kind of assembled folds discharging platform |
-
2016
- 2016-12-14 CN CN201611151230.3A patent/CN106522567A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09125690A (en) * | 1995-11-02 | 1997-05-13 | Japan Steels Internatl Kk | Assembled temporary passage |
CN201297036Y (en) * | 2008-11-19 | 2009-08-26 | 常州第一建筑工程有限公司 | Discharging platform |
CN202031310U (en) * | 2011-04-27 | 2011-11-09 | 天津天一建设集团有限公司 | Detachable structural steel unloading platform |
CN204691264U (en) * | 2015-06-19 | 2015-10-07 | 中国科学院重庆绿色智能技术研究院 | A kind of detachable folding discharging platform |
CN105239765A (en) * | 2015-10-26 | 2016-01-13 | 中国建筑股份有限公司 | Foldable multifunctional overhanging unloading platform |
CN206360381U (en) * | 2016-12-14 | 2017-07-28 | 绍兴明煌建材科技有限公司 | A kind of assembled folds discharging platform |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587708A (en) * | 2017-09-22 | 2018-01-16 | 宁夏桥多美路桥钢模板科技有限公司 | Foldable high-altitude construction platform and high-altitude construction method |
CN107587708B (en) * | 2017-09-22 | 2023-12-22 | 昌吉城建市政工程建设有限公司 | Foldable high-altitude construction platform and high-altitude construction method |
CN110499916A (en) * | 2019-08-31 | 2019-11-26 | 杭州昂创科技有限公司 | Exempt from the construction method through walls for increasing anchorage support pull folding discharging platform |
CN110499916B (en) * | 2019-08-31 | 2021-08-13 | 杭州昂创科技有限公司 | Construction method of wall-penetration-free heightening, anchoring, supporting, pulling and folding type unloading platform |
CN113503045A (en) * | 2021-08-25 | 2021-10-15 | 浙江鸿翔建设集团股份有限公司 | Lift assembled business turn over material platform in construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203638954U (en) | Hanger for vertically hoisting fairing | |
CN106522567A (en) | Assembled folded discharging platform and construction mode thereof | |
CN103630416B (en) | Test platform of hoisting mechanism | |
CN103072893A (en) | Tool and device for overturning vertical equipment in nuclear power plant | |
CN106120571B (en) | Arch bridge suspender tensioning equipment | |
CN207245138U (en) | Boat scaffold adjustable in pitch | |
CN206244301U (en) | A kind of architectural engineering tower crane anti-sway control device | |
CN206360381U (en) | A kind of assembled folds discharging platform | |
CN207918257U (en) | Prefabricated post hanger structure | |
CN204849595U (en) | Frame bridge crane landing leg suitable for set up precast beam under heavy grade circumstances | |
CN207853369U (en) | A kind of cable bearer | |
CN207346997U (en) | One kind hangs vehicle safety protection device | |
CN207554968U (en) | A kind of lifting pipeline stent | |
US9169067B2 (en) | System and method to assist in lifting a vessel | |
CN203474249U (en) | Aircraft rudder lifting appliance | |
CN203865929U (en) | Portable crane | |
CN206437774U (en) | The steel transport support in construction site | |
CN105905793A (en) | Automatic unhooking lifting tool | |
CN107176537B (en) | A kind of hanging device and its hanging method | |
CN206111235U (en) | Car is transferred to anchor rope | |
CN205417233U (en) | Turn to fixed bolster with adjustable inner ratchet compensation in tunnel is casted anchor | |
CN109537921A (en) | Anti-falling support for building construction | |
CN204342259U (en) | A kind of large quality Initiator Safety hangs rotary device | |
CN102747833A (en) | Suspending steel tube fastener | |
CN208791078U (en) | The portable anti-down fixed device fixed for winch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170322 |
|
RJ01 | Rejection of invention patent application after publication |