CN106485408A - A kind of engineering construction overall process intelligent management system and its application - Google Patents
A kind of engineering construction overall process intelligent management system and its application Download PDFInfo
- Publication number
- CN106485408A CN106485408A CN201610860034.7A CN201610860034A CN106485408A CN 106485408 A CN106485408 A CN 106485408A CN 201610860034 A CN201610860034 A CN 201610860034A CN 106485408 A CN106485408 A CN 106485408A
- Authority
- CN
- China
- Prior art keywords
- violation
- contractor
- unit
- workmen
- management system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Abstract
The present invention relates to a kind of engineering construction overall process intelligent management system and its application, based on mobile Internet and APP technology, realization is to contractor and workmen's supervision for described system;This system mainly includes contractor's assessment module, workmen's management module, potential safety hazard pushing module, violation operation statistical module;Can quickly and effectively solve the problems, such as that contractor and workmen's supervision are difficult, potential safety hazard management and control is delayed, work progress violation operation evidence obtaining is difficult by the present invention, it is finally reached timely exclusion potential safety hazard, significantly reduce construction risk, manage the orderly, purpose of safe construction.
Description
Technical field
The present invention relates to the intellectualizing system of engineering construction field, especially a kind of engineering construction overall process intelligent management system
System and its application, are easy to contractor and workmen carry out intelligent management.
Background technology
Derived energy chemical industry has high temperature, high pressure, inflammable, explosive, poisonous and harmful, high corrosion, the seriality of operation and answers
The features such as polygamy, once having an accident, often result in the more serious consequence of ratio, serious harm is caused to society and environment, therefore,
It is all the emphasis of national security production supervision management with its Risk Management all the time.And constantly opening up with the scope of business
Exhibition, production scale constantly expands, and derived energy chemical industry production scale maximizes, and the energy, chemical products storage, conveying are decentralized,
Requirements at the higher level and challenge are proposed to safety management.The management of contractor and workmen is as composition most important in safety management
One of part, often has that employee turnover is big, a peopleware and safety consciousness is uneven, part management personnel's management awareness
, system not high with technical ability executes the features such as tight, field surveillance is relaxed, and is a most thorny difficult problem in enterprise security manager all the time.
Seek effective contractor and workmen's control measures, during reducing safety in production, " three disobey " phenomenon sends out
Raw, promote contractor and the lifting of workmen's safety management level, reduce the generation even avoiding security incident to greatest extent,
The constantly Safety Achievements of enterprise, become the highly important work that enterprise implements " people-oriented, security developments " theory
Make.
The method that CN104636883A provides a kind of Safety skill test and appraisal of contractor, mainly solves prior art sinopec enterprise
Industry contractor Safety skill sorting technique is imperfect, lack of standardization, lack objectivity and comprehensive problem.
CN201210260496.7 provides a kind of electric operating personal security quality assessment method and system, method bag
Include:(1) collect power industry security capabilities quality data;(2) security capabilities quality evaluation metricses system and security capabilities are set up
Quality model;(3) operating personnel is evaluated and tested and specific aim training;(4) analysis, statistics and feedback evaluation result.System
Single including security capabilities quality model, security capabilities quality topic, evaluation and test test library design and maintenance unit, the evaluation and test of security capabilities quality
Unit and evaluation and test Result statisticses and analysis unit.
Prior art has certain effect to raising contractor's safety consciousness and Safety skill and prevention security incident, but
Can not be checked on from source, also cannot find in time and correct the deviation during management.The present invention is to contractor's history
Violation number of times, type and violation rate carry out statistics and have contractor's evaluation function, hold access and close it is ensured that troop of contractor is overall
The controllability of quality;The present invention implements effective, easily contractor and workmen's management, Ke Yisui by technological means simultaneously
When grasp the dynamic change of contractor and workmen, inclined during finding in time and correcting management and on cargo handling operation
Difference, rectifies and improves the problem of impact enterprise safety operation in time, greatly promotes management effect.
Content of the invention
In view of above contractor and workmen's supervision are difficult, potential safety hazard management and control is delayed, work progress violation operation evidence obtaining
Difficult existing issue, the present invention provides a kind of engineering construction overall process intelligent management system and its application, using big after this system
Facilitate greatly the regulatory requirement in construction.Concrete technical scheme is as follows:
A kind of engineering construction overall process intelligent management system, described intelligent management system include contractor's evaluation unit and/
Or workmen's administrative unit, potential safety hazard push unit, violation operation statistic unit;
Described contractor evaluation unit and described workmen's administrative unit are respectively with described violation operation statistic unit even
Connect, described violation operation statistic unit is connected with described potential safety hazard push unit;
Described contractor evaluation unit and described workmen's administrative unit record disobeying of contractor and workmen respectively
Rule information, described violation information is sent and carries out pooled classification statistics, described pooled classification to described violation operation statistic unit
The result of statistics is sent to described potential safety hazard push unit.
Described contractor evaluation unit collects following violation information:Contractor's essential information, contractor's violation operation number of times,
One or more of violation homework type, violation person-time, violation rate.
Described workmen's administrative unit collects following violation information:Workmen's essential information, violation operation type, disobey
One or more of rule number of operations, violation operation affiliated potential safety hazard rank.
Described intelligent management system is also connected with the Internet, and described potential safety hazard push unit is pacified according to belonging to violation operation
Full rank is by described the Internet by the project leader of potential safety hazard information pushing to different stage.
The information that described violation operation statistic unit counts at least includes region and counts in violation of rules and regulations and classify in violation statistics
A kind of.Region refers to the producing region of factory's division;Classification violation statistics refers to the different classes of of ARIXTRA unlawful practice and is counted.
Described contractor evaluation unit, workmen's administrative unit, potential safety hazard push unit, violation operation statistic unit
Supervision assessment is carried out by mobile terminal, and result is uploaded to supervision operation platform.
Described contractor essential information include contractor's history violation operation number of times, history violation homework type, history disobey
Rule person-time, history violation rate.
Described workmen's essential information includes the affiliated contractor of workmen, offender's transition information, and history is in violation of rules and regulations
Number of operations, violation homework type and violation rate.
The application of any of the above-described described engineering construction overall process intelligent management system, for right in engineering construction overall process
Contractor and the supervision of workmen;Described intelligent management system includes contractor's evaluation unit and/or workmen's management is single
Unit, potential safety hazard push unit, violation operation statistic unit;Described contractor evaluation unit and described workmen's administrative unit
The violation information of record contractor and workmen, described violation information is sent to enter to described violation operation statistic unit respectively
Row pooled classification counts, and the result of described pooled classification statistics is sent to described potential safety hazard push unit, described potential safety hazard
Push unit provides timely information pushing to system manager;
The method of described supervision comprises the steps:
(1) when finding the violation of contractor or workmen, carried out using described intelligent management system to take pictures, to regard
Frequently, voice or mode word carry out violation information record, described violation information pass through GPRS, 3G network, 4G network or
Wifi mode stores local or cloud server;
(2) described violation information is pushed to related director in time by push unit, and described correlation director receives and pushes away
Deliver letters after breath by the APP of networking check corresponding in violation of rules and regulations and potential safety hazard, and rectified and improved by the specified related personnel of APP.
The violation job information of described contractor evaluation unit and workmen's administrative unit, enterprise each hierarchy management personnel
According to the authority of itself, according to safety management possession, carry out result queries and browse according to operating area, work post, activity duration.
The intelligent management system of the present invention can count to contractor's history violation number of times, type and violation rate, tool
There is contractor's evaluation function, hold contractor access and close it is ensured that the controllability of troop of contractor total quality;Meanwhile, the present invention
Intelligent management system pass through to implement effectively, easily contractor and workmen's management, contractor can be grasped at any time and apply
The dynamic change of workman person, the deviation during finding in time and correcting management and on cargo handling operation, the enterprise of rectification impact in time
The problem of industry safety in production, greatly promotes management effect.
Brief description
Fig. 1 is total Organization Chart of the intelligent management system use environment of the present invention;
Fig. 2 is the hardware structure figure of the intelligent management system of the present invention;
Fig. 3 is the software function structure chart of the intelligent management system of the present invention.
Symbol description
1 mobile terminal;2 contractor's evaluation unit;3 workmen's administrative units;
4 potential safety hazard push units;5 violation operation statistic units.
Specific embodiment
Below, embodiments of the invention are described in detail, but described content is not to be regarded as limiting the present invention
Practical range.All impartial changes made according to the present patent application scope and improvement etc., the protection that all should belong to the present invention is contained
Within the scope of lid.In addition, it is necessary to explanation, in the case of not conflicting, in embodiment in the invention and embodiment
Feature can be mutually combined.
Embodiment 1
The present embodiment is related to a kind of engineering construction overall process intelligent management system, and Fig. 1 is that this intelligent management system uses ring
Total example architecture in border, Fig. 2 is the hardware structure example of this intelligent management system, and Fig. 3 is the software work(of this intelligent management system
Can topology example.
As shown in figure 1, total framework of this intelligent management system use environment, including four parts:Data base, the Internet, use
Family terminal and evaluation object.Lane database storage contractor evaluation unit, workmen's administrative unit, potential safety hazard push unit
With the relevant information of violation operation statistic unit, described intelligent management system can be with the described related letter of called data library storage
Breath.The violation information that contractor evaluation unit is collected can include the essential information of contractor, the violation number of times of contractor, in violation of rules and regulations
One or more of type, violation person-time, violation rate;The violation information that workmen's administrative unit is collected can include substantially
One or more of information, violation number of times, violation type, violation rate, Comprehensive Assessment;The letter that potential safety hazard push unit is collected
Breath can include one or more of violation number of times, violation type, violation rate, Comprehensive Assessment, and this unit is according to violation operation
Potential safety hazard information is pushed to the project leader of different stage by affiliated level of security by the Internet;Violation operation statistics is single
Unit at least includes region and counts in violation of rules and regulations and classification one of statistics in violation of rules and regulations.
The Internet define intelligent management system data transfer pattern include but is not limited to GPRS, 3G, 4G, WIFI and
Internet.User terminal can be personal computer terminal (PC) or mobile terminal (including but not limited to mobile phone and flat board electricity
Brain etc.).Evaluation object includes but is not limited to contractor and workmen.User utilizes user terminal to collect evaluation object information,
By the Internet, the information transfer collected is stored to data base corresponding region.As shown in Fig. 2 this intelligent management system
Contractor's evaluation unit can be included and/or workmen's administrative unit, potential safety hazard push unit, violation operation statistics are single
Unit;Contractor's evaluation unit, workmen's administrative unit, potential safety hazard push unit and violation operation statistic unit belong to intelligence
Four modules of energy management system, wherein, contractor's evaluation unit and workmen's administrative unit can be used alone, and safety is hidden
Suffer from push unit and violation operation statistic unit Data Source in contractor's evaluation unit and workmen's administrative unit.
As shown in figure 3, in this intelligent management system, the information that contractor's evaluation unit is collected can include the base of contractor
One or more of this information, the violation number of times of contractor, violation type, violation person-time, violation rate;Workmen's management is single
The information that unit collects can include one or more of essential information, violation number of times, violation type, violation rate, Comprehensive Assessment;
Potential safety hazard push unit collect information can include one of violation number of times, violation type, violation rate, Comprehensive Assessment or
Several, this unit is according to the affiliated level of security of violation operation by the project leader of potential safety hazard information pushing to different stage;
Violation operation statistic unit at least includes region and counts in violation of rules and regulations and classification one of statistics in violation of rules and regulations.
Contractor's evaluation unit, workmen's administrative unit, potential safety hazard push unit, violation operation statistic unit pass through
Mobile terminal carries out supervision assessment, and result is uploaded to supervision operation platform.
The essential information of contractor can include the history violation operation number of times of contractor, history violation homework type, go through
History violation person-time, history violation rate.
The essential information of workmen can include the affiliated contractor of workmen, offender's transition information, and history is disobeyed
Rule number of operations, violation homework type and violation rate.
User is carried out contractor and is applied using contractor's evaluation unit of intelligent management system and workmen's administrative unit
The violation situation record of workman person and upload, the information that described contractor evaluation unit is collected can include the basic letter of contractor
One or more of breath, the violation number of times of contractor, violation type, violation person-time, violation rate;Workmen's administrative unit is received
The information of collection can include one or more of essential information, violation number of times, violation type, violation rate, Comprehensive Assessment.Described
The project of potential safety hazard information pushing to different stage is born by potential safety hazard push unit according to the affiliated level of security of violation operation
Duty people.Described violation operation statistic unit at least includes region and counts in violation of rules and regulations and classification one of statistics in violation of rules and regulations, intelligent management
System background carries out collecting and counting of violation operation, and statistical result needs to be shown in user terminal according to user.
Embodiment 2
The present embodiment is related to the application of the engineering construction overall process intelligent management system of embodiment 1, this intelligent management system
For the supervision to contractor and workmen in engineering construction overall process.
The method of described supervision comprises the steps:
(1) when finding the violation of contractor or workmen, carried out using described intelligent management system to take pictures, to regard
Frequently, voice or mode word carry out violation information record, described violation information pass through GPRS, 3G network, 4G network or
Wifi mode stores local or cloud server;
(2) described violation information is pushed to related director in time by push unit, and described correlation director receives and pushes away
Deliver letters after breath by the APP of networking check corresponding in violation of rules and regulations and potential safety hazard, and rectified and improved by the specified related personnel of APP.
The violation job information of described contractor evaluation unit and workmen's administrative unit, enterprise each hierarchy management personnel
According to the authority of itself, according to safety management possession, carry out result queries and browse according to operating area, work post, activity duration.
This monitoring and managing method, by counting to contractor's history violation number of times, type and violation rate, has contractor and comments
Determine function, be conducive to holding contractor's access and close it is ensured that the controllability of troop of contractor total quality;Meanwhile, the present invention passes through
Technological means implement effectively, easily contractor and workmen's management, the dynamic of contractor and workmen can be grasped at any time
State changes, and the deviation during finding in time and correcting management and on cargo handling operation, the problem of impact enterprise safety operation
Rectify and improve in time, greatly promote management effect.
Claims (10)
1. a kind of engineering construction overall process intelligent management system is it is characterised in that described intelligent management system includes contractor comments
Order unit and/or workmen's administrative unit, potential safety hazard push unit, violation operation statistic unit;
Described contractor evaluation unit and described workmen's administrative unit are connected with described violation operation statistic unit respectively, institute
State violation operation statistic unit to be connected with described potential safety hazard push unit;
Described contractor evaluation unit and described workmen's administrative unit record the violation letter of contractor and workmen respectively
Breath, described violation information is sent and carries out pooled classification statistics, described pooled classification statistics to described violation operation statistic unit
Result be sent to described potential safety hazard push unit.
2. intelligent management system according to claim 1 is it is characterised in that the evaluation unit collection of described contractor is disobeyed as follows
Rule information:One of contractor's essential information, contractor's violation operation number of times, violation homework type, violation person-time, violation rate
Or it is several.
3. intelligent management system according to claim 1 is it is characterised in that the collection of described workmen's administrative unit is as follows
Violation information:Workmen's essential information, violation operation type, violation operation number of times, violation operation affiliated potential safety hazard rank
One or more of.
4. intelligent management system according to claim 1 is it is characterised in that described intelligent management system is also connected with the Internet
Connect, potential safety hazard information is pushed away by described the Internet by described potential safety hazard push unit according to the affiliated level of security of violation operation
Deliver to the project leader of different stage.
5. intelligent management system according to claim 1 it is characterised in that described violation operation statistic unit statistics letter
Breath at least includes region and counts in violation of rules and regulations and classification one of statistics in violation of rules and regulations.
6. intelligent management system according to claim 1 is it is characterised in that described contractor evaluation unit, workmen
Administrative unit, potential safety hazard push unit, violation operation statistic unit carry out supervision assessment by mobile terminal, and by result
Pass to supervision operation platform.
7. intelligent management system according to claim 2 is it is characterised in that described contractor essential information includes contractor
History violation operation number of times, history violation homework type, history violation person-time, history violation rate.
8. intelligent management system according to claim 2 is it is characterised in that described workmen's essential information includes constructing
The affiliated contractor of personnel, offender's transition information, history violation operation number of times, violation homework type and violation rate.
9. the application of the arbitrary described engineering construction overall process intelligent management system of claim 1 to 8 is it is characterised in that be used for
Supervision to contractor and workmen in engineering construction overall process;Described intelligent management system includes contractor's evaluation unit
And/or workmen's administrative unit, potential safety hazard push unit, violation operation statistic unit;Described contractor evaluation unit and
Described workmen's administrative unit records the violation information of contractor and workmen respectively, and described violation information is sent to institute
State violation operation statistic unit and carry out pooled classification statistics, the result of described pooled classification statistics is sent to described potential safety hazard and pushes away
Send unit, described potential safety hazard push unit provides timely information pushing to system manager;
The method of described supervision comprises the steps:
(1) when finding the violation of contractor or workmen, carry out to take pictures using described intelligent management system, video, language
Sound or mode word carry out violation information record, and described violation information is by GPRS, 3G network, 4G network or wifi mode
Store local or cloud server;
(2) described violation information is pushed to related director in time by push unit, and described correlation director receives push letter
After breath, corresponding violation and potential safety hazard are checked by the APP of networking, and specify related personnel to be rectified and improved by APP.
10. application according to claim 9 is it is characterised in that described contractor evaluation unit and workmen's management are single
The violation job information of unit, according to the authority of itself, foundation safety management possession, according to operation area for enterprise each hierarchy management personnel
Domain, work post, activity duration carry out result queries and browse.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610860034.7A CN106485408A (en) | 2016-09-28 | 2016-09-28 | A kind of engineering construction overall process intelligent management system and its application |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610860034.7A CN106485408A (en) | 2016-09-28 | 2016-09-28 | A kind of engineering construction overall process intelligent management system and its application |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106485408A true CN106485408A (en) | 2017-03-08 |
Family
ID=58268205
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610860034.7A Pending CN106485408A (en) | 2016-09-28 | 2016-09-28 | A kind of engineering construction overall process intelligent management system and its application |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106485408A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108171465A (en) * | 2017-12-08 | 2018-06-15 | 杭州品茗安控信息技术股份有限公司 | A kind of construction violation monitoring system and method |
CN108197801A (en) * | 2017-12-29 | 2018-06-22 | 安徽博诺思信息科技有限公司 | Site staff's management method and system and method based on visualized presence monitoring system |
CN111461372A (en) * | 2020-03-27 | 2020-07-28 | 中国平安人寿保险股份有限公司 | Conference room monitoring method and system |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040083165A1 (en) * | 2001-03-20 | 2004-04-29 | David Lawrence | Construction industry risk management clearinghouse |
CN102521709A (en) * | 2011-12-22 | 2012-06-27 | 上海建科工程咨询有限公司 | Building construction quality safety online risk management system |
CN103729712A (en) * | 2013-10-25 | 2014-04-16 | 国家电网公司 | Intelligent security control method of electric power field operating personnel |
CN105512856A (en) * | 2015-11-27 | 2016-04-20 | 清华大学 | Wechat-based potential safety hazard management method and system for large-scale civil engineering |
-
2016
- 2016-09-28 CN CN201610860034.7A patent/CN106485408A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040083165A1 (en) * | 2001-03-20 | 2004-04-29 | David Lawrence | Construction industry risk management clearinghouse |
CN102521709A (en) * | 2011-12-22 | 2012-06-27 | 上海建科工程咨询有限公司 | Building construction quality safety online risk management system |
CN103729712A (en) * | 2013-10-25 | 2014-04-16 | 国家电网公司 | Intelligent security control method of electric power field operating personnel |
CN105512856A (en) * | 2015-11-27 | 2016-04-20 | 清华大学 | Wechat-based potential safety hazard management method and system for large-scale civil engineering |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108171465A (en) * | 2017-12-08 | 2018-06-15 | 杭州品茗安控信息技术股份有限公司 | A kind of construction violation monitoring system and method |
CN108197801A (en) * | 2017-12-29 | 2018-06-22 | 安徽博诺思信息科技有限公司 | Site staff's management method and system and method based on visualized presence monitoring system |
CN111461372A (en) * | 2020-03-27 | 2020-07-28 | 中国平安人寿保险股份有限公司 | Conference room monitoring method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Verma et al. | Identifying patterns of safety related incidents in a steel plant using association rule mining of incident investigation reports | |
CN107451732A (en) | A kind of enterprise safety operation total management system and method | |
CN109144013A (en) | Capital construction and production scene managing and control system and method based on technology of Internet of things | |
CN112180854A (en) | Chemical enterprise safety production management system based on Internet of things | |
CN108010155A (en) | A kind of safety inspection and the system and method for hidden danger management | |
CN111768123A (en) | Visual management system for power distribution network construction site | |
CN106485408A (en) | A kind of engineering construction overall process intelligent management system and its application | |
CN111598411A (en) | Intelligent safety control system for operation site of transformer substation | |
CN110535895A (en) | A kind of machine room monitoring system based on technology of Internet of things | |
CN112477927A (en) | Rail transit station control information system based on mobile terminal | |
CN113449959A (en) | Mine personnel behavior governance system and platform | |
CN115410295A (en) | Intelligent integrated management platform based on cloud computing | |
CN111985776A (en) | Cloud-based labor supervision system and supervision method thereof | |
CN112800910A (en) | Communication machine room maintenance operation efficiency evaluation method and system | |
CN115130807A (en) | Intelligent supervision method for pharmaceutical production safety | |
CN113469544A (en) | Risk control method and system for safety operation | |
CN114841660A (en) | Enterprise intelligent safety management and control cloud platform based on field information | |
CN104778562B (en) | A kind of safe eye supervising platform system in job site | |
CN113869767A (en) | Method, system, electronic equipment and storage medium for supervising site police officer business assessment | |
CN107220784A (en) | A kind of engineering construction safety management system and method based on wechat | |
CN111222830A (en) | System and method for intelligently managing and monitoring pledge objects based on block chain of Internet of things | |
CN115422421A (en) | Intelligent campus data management platform system for internet-based data | |
CN112688929B (en) | Sharing system based on Internet threat information | |
CN113869758A (en) | Intelligent two-ticket management and operation site risk early warning system | |
CN110852629A (en) | System for environmental protection network supervision and using method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170308 |
|