Technical field
The present invention relates to Impacts Evaluation of Urban Tunnel engineering field and urban operating mechanism technical field, particularly a kind of prefabricated assembled
Concrete metro station.
Background technology
Urban transportation construction at present is like a raging fire, is pushed further into pipe gallery, sponge Urban strategy, China with country
Big and medium-sized cities will start the new round climax of underground engineering construction, and due to the scarcity of the underground space, to collection, " Urban Underground is comprehensive
The demand of the Urban Underground Complex in conjunction piping lane, Urban Underground expressway, urban underground construction space " is huge.
The exploitation of Japan and the American-European underground space and construction maintain the leading position, and advocate and propose underground city and city at first
The synthesization of city's underground space and three-dimensional utility strategies, nineteen ninety proposes Tokyo Declaration:The Devoting Major Efforts To Developing underground space, starts people
Class new cave period, International Tunnelling Association in 2010 expands to tunnel and with underground space association and declares:21 century is underground
The century in space.
To mark international metropolis, become extensive style, stand large flat bread urban development pattern is intensive, solid mode, to underground
Want space;Break through urban land, air, water source, greenery patches, the per capita constraint of the resource environment total amount such as city space, the energy, environment;
Sea, greening are not enough, real estate finance makes the transition, old town is seen to traffic congestion, air dirt, noise pollution, visual pollution, city
The urban disease that vigor decline etc. causes life carries out comprehensive improvement;Change made in China is Created in China, cultivates height leading in the world
End industry cluster.
Cities of Foreign Countries underground space development is with a long history, how and to be stopped with reference to commercial facility with Large Underground transport hub
Parking lot, the multiple traffic forms of appearance present in the underground space synthesises type of one.In the world, Japan and America and Europe are empty in underground
Between exploitation and construction maintain the leading position, advocate and propose synthesization and the solid of underground city and urban underground space at first
Change utility strategies.Totally see have during the many countries of underground space synthesises including multiple transportation modes or several functions
Existing, there is not yet collection " Urban Underground pipe gallery, Urban Underground expressway, urban underground construction space " Urban Underground is comprehensive
Body type.Therefore, in the urgent need to developing underground space synthesises, national green building and the strategy of sustainable development are adapted to.
Content of the invention
For the deficiencies in the prior art, it is an object of the invention to provide a kind of prefabricated assembled concrete subway station,
In solving World Cities development problem of " traffic congestion, sponge city, pipe gallery " integration, save construction investment and beating
The green ecological ideal city making " on the ground, thing and car are in underground for people " provides technical scheme.
The technical solution used in the present invention is as follows:
Prefabricated assembled concrete subway station, main inclusion structural envelope stake, Guan Liang, waterproof layer, L-shaped base angle shell wall, two-beam type
Base plate shell wall, double pier formula base plate shell wall, bright corbel type shell wall, double-deck connection post, platform gripper shoe, in across platen, platform platen, rank
Terraced beam, in across cover plate, band civil engineering air duct cover board, hidden bracket formula shell wall, back timber, in across ladder top shell wall, end bay ladder top shell wall,
It is characterized in that:All topology layouts are preferentially symmetrical with middle vertical axis;1 piece of two-beam type base plate shell wall in the middle of bottom, at it
Both sides each 1 piece of L-shaped base angle shell wall respectively, is respectively bright corbel type shell wall and hidden bracket formula shell wall in two sides from the bottom to top,
Crown center across ladder top shell wall in being, both sides are respectively end bay ladder top shell wall, by 1 piece of two-beam type base plate shell wall, 2 block L
Shape base angle shell wall, 2 bright corbel type shell walls, 2 hidden bracket formula shell walls, across ladder top shell wall in 1 piece, 2 pieces of end bay ladder top shells
Wall constitutes the lining cutting shell wall of the complete prefabricated assembled concrete subway station of a ring;All arc is passed through by arch screw bolt in the vertical
Shape bolt hole connects;
L-shaped base angle shell wall and two-beam type base plate shell wall connect, and are all connected by arch screw bolt hole using arch screw bolt;Two-beam type bottom
The top water bar of plate shell wall is agreed with the upper recess phase of both sides L-shaped base angle shell wall;
The reinforcing bar that connects of two sides L-shaped base angle shell wall is connected with the hidden bracket formula shell wall on top, connects preferentially with bolts,
Nut is tightened at connection installing port;
Hidden bracket formula shell wall passes through to be connected bar connecting with end bay ladder top shell wall, connects reinforcing bar top and carries buckle, adopts
Nut screwing clamping;The hidden bracket of hidden bracket formula shell wall is mutually agreed with the ladder mouth of end bay ladder top shell wall;
In across ladder top shell wall and end bay ladder top shell wall connected by arch screw bolt, ladder mouth and ladder mouth mutually agree with;
It is structural envelope stake in the both sides of the lining cutting shell wall of prefabricated assembled concrete subway station, the top of structural envelope stake is hat
Beam;
It is respectively provided with waterproof layer in the surrounding of the lining cutting shell wall of prefabricated assembled concrete subway station;
The top of two drain pan piers of double pier formula base plate shell walls is all connected with double-deck connection post, and connected mode is that connection reinforcing bar insertion is double
Layer connection post, connects reinforcing bar top and carries buckle, is connecting nut screwing clamping at installing port;
Double-deck connection post all with across ladder top shell wall is connected, connected mode is across rank during the double-deck top connection reinforcing bar joining post inserts
Ladder top shell wall, and fastened using nut at top;
Stepped Beam is connected with the ladder beam-ends of double-deck connection post, and Stepped Beam beam-ends is ladder, and the ladder beam-ends rank with double-deck connection post
Ladder way phase is agreed with;
The top of double-deck connection post is all connected with back timber, back timber all with across ladder top shell wall be connected;
In overlap with Stepped Beam respectively across the two ends of cover plate, the one end with civil engineering air duct cover board and Stepped Beam overlap, the other end with
The bracket overlap joint of bright corbel type shell wall;Civil engineering air channel is located at the lower section near bracket side;
In across platen two ends overlap with the platform bottom girder of two-beam type base plate shell wall respectively;Or the drain pan pier with double pier formula base plate shell walls
Overlap joint, and in across platen top and double-deck connection post at a distance of preferentially electing 10mm as;
Platform gripper shoe lower end is connected with L-shaped base angle shell wall, and its upper end is connected with platform platen;The other end of platform platen with double
The platform bottom girder overlap joint of beam type base plate shell wall;Or the drain pan pier overlap joint with double pier formula base plate shell walls;
Described L-shaped base angle shell wall mainly includes horizontal shell wall, vertical shell wall, arch screw bolt hole, capillary groove, water bar, connection
Reinforcing bar, longitudinally connected bolt installing port, ring connecting bolt installing port, L-shaped base angle shell wall is L-shaped, horizontal shell wall, vertical shell wall
All at least provided with one layer of capillary groove and water bar in longitudinal direction and ring, preferentially layer water bar is set in outermost layer, capillary groove is preferential
Near outer layer;
It is respectively provided with multiple arcs bolt hole in horizontal shell wall longitudinal terminal surface and ring end face, in the longitudinal terminal surface setting of vertical shell wall
Multiple arcs bolt hole, arch screw bolt hole is arc, in the longitudinal direction of horizontal shell wall longitudinal terminal surface and ring end face and vertical shell wall
End, its tangent line is parallel with horizontal shell wall, vertical shell wall place plane respectively;
Arch screw bolt hole and its center of circle plane are vertical with the horizontal shell wall being located or vertical shell wall, and the center of circle is positioned at complete prefabricated
Within the lining cutting shell wall of assembly concrete subway station;
The other end in arch screw bolt hole is respectively positioned on inside the lining cutting shell wall of complete prefabricated assembled concrete subway station, apart from L
The longitudinal end of shape base angle shell wall or ring end 100 ~ 250mm, and it is respectively provided with longitudinally connected bolt installing port, ring connection
Bolt installing port, the inner surface of the lining cutting shell wall in complete prefabricated assembled concrete subway station for the ring connecting bolt installing port
It is preferably isosceles trapezoid;
Vertically shell wall sets up overhanging connection reinforcing bar in ring, and it is vertical for connecting reinforcing bar, and top is by buckle.
Described two-beam type base plate shell wall mainly includes horizontal shell wall, platform bottom girder, capillary groove, water bar, arc spiral shell
Keyhole, overall is in fall " ∏ " font, arranges two vertical platform bottom girders on horizontal shell wall top;Horizontal shell wall longitudinal direction and
Ring is respectively provided with arch screw bolt hole, and arch screw bolt hole is arc, in horizontal shell wall longitudinal terminal surface and ring end face, arch screw bolt hole
Tangent line all parallel with horizontal shell wall place plane;Arch screw bolt hole and its center of circle plane are vertical with the horizontal shell wall being located, and
Within the center of circle is located at the complete lining cutting shell wall of prefabricated assembled concrete subway station;The other end in arch screw bolt hole has been respectively positioned on
Inside the lining cutting shell wall of whole prefabricated assembled concrete subway station;
At least one water bar and capillary groove on horizontal shell wall, wherein anti-together in the preferential setting of outermost of horizontal shell wall
Water baffle plate.
Described double pier formula base plate shell walls mainly include horizontal shell wall, drain pan pier, capillary groove, water bar, arch screw bolt
Hole, connection reinforcing bar,
Overall is in fall " ∏ " font, arranges two vertical drain pan piers on horizontal shell wall top;Longitudinal direction and ring in horizontal shell wall
To being respectively provided with arch screw bolt hole, arch screw bolt hole is arc, in horizontal shell wall longitudinal terminal surface and ring end face, arch screw bolt hole
Tangent line is all parallel with horizontal shell wall place plane;Arch screw bolt hole and its center of circle plane are vertical with the horizontal shell wall being located, and circle
Within the heart is located at the complete lining cutting shell wall of prefabricated assembled concrete subway station;The other end in arch screw bolt hole is respectively positioned on completely
The lining cutting shell wall of prefabricated assembled concrete subway station inside;
At least one water bar and capillary groove on horizontal shell wall, wherein anti-together in the preferential setting of outermost of horizontal shell wall
Water baffle plate;
Arrange in drain pan pier top portion and connect reinforcing bar, it is vertical for connecting reinforcing bar, and top carries buckle.
Described bright corbel type shell wall mainly includes the vertical shell wall of lower floor, capillary groove, water bar, arch screw bolt hole, connection
Reinforcing bar, bracket, connecting bolt installing port,
At least one capillary groove, water bar on the vertical shell wall of lower floor, wherein in outermost preferentially one of setting of vertical shell wall
Water bar;
Arrange at lower floor's vertical shell wall top and connect reinforcing bar, it is vertical for connecting reinforcing bar, and top carries buckle;Vertical in lower floor
The inner side setting bracket on shell wall top, arranges some connecting bolt installing ports in bottom;
In the longitudinally disposed arch screw bolt hole of the vertical shell wall of lower floor, arch screw bolt hole is arc, in lower floor's vertical shell wall longitudinal end
Face, the tangent line in arch screw bolt hole is all parallel with lower floor's vertical shell wall place plane;Arch screw bolt hole and its center of circle plane and place
The vertical shell wall of lower floor vertical, and within the center of circle is located at the complete lining cutting shell wall of prefabricated assembled concrete subway station;Arc
The other end of bolt hole is respectively positioned on inside the lining cutting shell wall of complete prefabricated assembled concrete subway station;
Described double-deck connection post mainly includes lower floor's cylinder, upper strata cylinder, ladder beam-ends, connects installing port, connects reinforcing bar, lower floor
The two-layer post that cylinder, upper strata cylinder are integrated, longitudinally disposed ladder beam-ends between the two layers, ladder beam-ends is overhanging 200 ~
500mm, ladder beam-ends with ladder mouth, preferentially contour up and down, top half takes in 100 ~ 200mm;
Arrange in bottom and connect installing port, arrange on top and connect reinforcing bar, the top connecting reinforcing bar carries buckle.
Described band civil engineering air duct cover board mainly includes plate body, civil engineering air channel, in plate body near complete prefabricated assembled
The downside setting civil engineering air channel of the lining cutting shell wall at concrete metro station;Civil engineering air channel is rectangle, preferentially adopts xoncrete structure.
Described hidden bracket formula shell wall mainly includes upper level upright shell wall, water bar, capillary groove, arch screw bolt hole, dark cattle
Lower limb, connection reinforcing bar, connecting bolt installing port,
At least one water bar, capillary groove on upper level upright shell wall, wherein in outermost preferentially one of setting of vertical shell wall
Water bar;
Hidden bracket is set at upper level upright shell wall top, hidden bracket is ladder mouth, preferentially interior outside equal thickness, and medial wall is taken in
150-300mm;Arrange in interior side steps mouth and connect reinforcing bar, it is vertical for connecting reinforcing bar, and top carries buckle;In bottom setting
Some connecting bolt installing ports;
In the longitudinally disposed arch screw bolt hole of upper level upright shell wall, arch screw bolt hole is arc, in upper level upright shell wall longitudinal end
Face, the tangent line in arch screw bolt hole is all parallel with upper level upright shell wall place plane;Arch screw bolt hole and its center of circle plane and place
Upper level upright shell wall vertical, and within the center of circle is located at the complete lining cutting shell wall of prefabricated assembled concrete subway station;Arc
The other end of bolt hole is respectively positioned on inside the lining cutting shell wall of complete prefabricated assembled concrete subway station;
In described, across ladder top shell wall mainly includes top layer housing, water fender, capillary groove, arch screw bolt hole, ladder mouth,
At least one water fender, capillary groove on top layer housing, the wherein outermost in top layer housing preferentially arrange one dash
Plate;
It is respectively provided with ladder mouth, preferential top and the bottom equal thickness at the two ends of top layer housing, 150-300mm is taken on top;
Be respectively provided with arch screw bolt hole in the longitudinal direction of top layer housing and ring, arch screw bolt hole is arc, top layer housing longitudinally and
Ring end face, the tangent line in arch screw bolt hole is all parallel with top layer housing place plane;Arch screw bolt hole and its center of circle plane and institute
Top layer housing vertical, and within the center of circle is located at the complete lining cutting shell wall of prefabricated assembled concrete subway station;Arc spiral shell
The other end of keyhole is respectively positioned on inside the lining cutting shell wall of complete prefabricated assembled concrete subway station.
Described end bay ladder top shell wall mainly includes top layer housing, water fender, capillary groove, arch screw bolt hole, ladder mouth;
At least one water fender, capillary groove on top layer housing, the wherein outermost in top layer housing preferentially arrange one dash
Plate;
It is respectively provided with ladder mouth, preferential top and the bottom equal thickness at the two ends of top layer housing, 150-300mm is taken in bottom;In top layer
The longitudinal direction of housing and ring are respectively provided with arch screw bolt hole, and its requirement is identical with arch screw bolt hole.
Beneficial effects of the present invention:
The invention has the beneficial effects as follows production template can be saved when producing, improve industrialization degree, gain economic effect,
And avoid environmental pollution, improve execution conditions when installing, the field installation steps of simplification, accelerating construction progress, Ke Yiji
One-tenthization general assembly, raises labour productivity it is ensured that construction quality, it is achieved that generalization, standardization and industrialization, accelerates city
Synthesization and the process of three-dimensional.
Brief description
Fig. 1 is prefabricated assembled concrete subway station schematic cross-sectional view of the present invention;
Fig. 2 is the vertical sectional schematic diagram of L-shaped base angle shell wall;
Fig. 3 is L-shaped base angle shell wall floor map;
Fig. 4 is the vertical sectional schematic diagram of two-beam type base plate shell wall;
Fig. 5 is double vertical sectional schematic diagram of pier formula base plate shell wall;
Fig. 6 is the vertical sectional schematic diagram of bright corbel type shell wall;
Fig. 7 is bright corbel type shell wall elevational schematic view;
Fig. 8 is double-deck connection post elevational schematic view;
Fig. 9 is the band vertical sectional schematic diagram of civil engineering air duct cover board;
Figure 10 is the vertical sectional schematic diagram of hidden bracket formula shell wall;
Figure 11 is the vertical elevational schematic view of hidden bracket formula shell wall;
Figure 12 vertical sectional schematic diagram of across ladder top shell wall in being;
Figure 13 is the vertical sectional schematic diagram of end bay ladder top shell wall;
In figure:1 is structural envelope stake;2 is Guan Liang;3 is waterproof layer;4 is L-shaped base angle shell wall;5 is two-beam type base plate shell wall;6 are
Double pier formula base plate shell walls;7 is bright corbel type shell wall;8 is double-deck connection post;9 is platform gripper shoe;10 be in across platen;11 is station
Platform platen;12 is Stepped Beam;13 be in across cover plate;14 is band civil engineering air duct cover board;15 is hidden bracket formula shell wall;16 is back timber;
17 be in across ladder top shell wall;18 is end bay ladder top shell wall;4-1 is horizontal shell wall;4-2 is vertical shell wall;4-3 is arc spiral shell
Keyhole;4-4 is capillary groove;4-5 is water bar;4-6 is to connect reinforcing bar;4-7 is longitudinally connected bolt installing port;4-8 is ring
Connecting bolt installing port;4-9 is recess;5-1 is horizontal shell wall;5-2 is platform bottom girder;5-3 is capillary groove;5-4 keeps off for waterproof
Plate;5-5 is stepped plate;5-6 is arch screw bolt hole;6-1 is horizontal shell wall;6-2 is drain pan pier;6-3 is capillary groove;6-4 is anti-
Water baffle plate;6-5 is stepped plate;6-5 is arch screw bolt hole;6-7 is to connect reinforcing bar;7-1 is the vertical shell wall of lower floor;7-2 is waterproof
Groove;7-3 is water bar;7-4 is arch screw bolt hole;7-5 is to connect reinforcing bar;7-6 is bracket;7-7 is connecting bolt installing port;8-
1 is lower floor's cylinder;8-2 is upper strata cylinder;8-3 is ladder two ends;8-4 is to connect installing port;8-5 is to connect reinforcing bar;14-1 is
Plate body;14-2 is civil engineering air channel;15-1 is upper level upright shell wall;15-2 is water bar;15-3 is capillary groove;15-4 is arc spiral shell
Keyhole;15-5 is hidden bracket;15-6 is to connect reinforcing bar;15-7 is to connect installing port;17-1 is top layer housing;17-2 is dash
Plate;17-3 is capillary groove;17-4 is arch screw bolt hole;17-5 is ladder mouth;18-1 is top layer housing;18-2 is water fender;18-
3 is capillary groove;18-4 is arch screw bolt hole;18-5 is ladder mouth.
Specific embodiment
Below in conjunction with drawings and Examples, the present invention is further described.
The present embodiment prefabricated assembled concrete subway station, as shown in Fig. 1 ~ Figure 13, including structural envelope stake 1, Guan Liang 2, is prevented
Water layer 3, L-shaped base angle shell wall 4, two-beam type base plate shell wall 5, double pier formula base plate shell wall 6, bright corbel type shell wall 7, bilayer join post 8, stand
Platform gripper shoe 9, in across platen 10, platform platen 11, Stepped Beam 12, in across cover plate 13, band civil engineering air duct cover board 14, hidden bracket formula
Shell wall 15, back timber 16, in across ladder top shell wall 17, end bay ladder top shell wall 18 it is characterised in that:All topology layouts preferentially with
Middle vertical axis are symmetrical;The 1 piece of two-beam type base plate shell wall 5 in bottom centre, distinguishes each 1 piece of L-shaped base angle shell wall 4 in its both sides,
Two sides are respectively bright corbel type shell wall 7 and hidden bracket formula shell wall 15 from the bottom to top, crown center across ladder top shell wall in being
17, both sides are respectively end bay ladder top shell wall 18, by 1 piece of two-beam type base plate shell wall, 4,2 bright cattle of 5,2 block L-shaped base angle shell walls
In 15,1 piece of 7,2 hidden bracket formula shell walls of lower limb formula shell wall, across ladder 17,2 pieces of end bay ladder top shell walls 18 composition one rings of top shell wall are complete
The lining cutting shell wall of whole prefabricated assembled concrete subway station;All arch screw bolt hole is passed through even by arch screw bolt in the vertical
Connect;
L-shaped base angle shell wall 4 and two-beam type base plate shell wall 5 connect, and are all connected by arch screw bolt hole using arch screw bolt;Two-beam type
The top water bar 5-4 of base plate shell wall 5 is agreed with the upper recess 4-9 phase of both sides L-shaped base angle shell wall 4;
The connection reinforcing bar 7-5 of two sides L-shaped base angle shell wall 4 is connected with the hidden bracket formula shell wall 15 on top, connects and preferentially adopts spiral shell
Tether and connect, nut is tightened at connection installing port 15-7;
Hidden bracket formula shell wall 15 passes through to be connected reinforcing bar 15-6 connection with end bay ladder top shell wall 18, connects reinforcing bar 15-6 top and carries
Buckle, using nut screwing clamping;The hidden bracket 15-5 of the hidden bracket formula shell wall 15 and ladder mouth 18-5 of end bay ladder top shell wall 18
Mutually agree with;
In across ladder top shell wall 17 and end bay ladder top shell wall 18 connected by arch screw bolt, ladder mouth 17-5 and ladder mouth 18-5
Mutually agree with;
It is structural envelope stake 1 in the both sides of the lining cutting shell wall of prefabricated assembled concrete subway station, the top of structural envelope stake 1 is
Guan Liang 2;
It is respectively provided with waterproof layer 3 in the surrounding of the lining cutting shell wall of prefabricated assembled concrete subway station;
The top of two drain pan pier 6-2 of double pier formula base plate shell walls 6 is all connected with double-deck connection post 8, and connected mode is to connect reinforcing bar
6-6 insertion double-deck connection post 8, connects reinforcing bar 6-6 top and carries buckle, is connecting nut screwing clamping at installing port 8-4;
Double-deck connection post 8 all with across ladder top shell wall 17 be connected, connected mode is that the top connection reinforcing bar 8-5 of double-deck connection post 8 is slotting
Across ladder top shell wall 17 in entering, and fastened using nut at top;
Stepped Beam 12 is connected with the ladder beam-ends 8-3 of double-deck connection post 8, and Stepped Beam 12 beam-ends is ladder, and the rank with double-deck connection post 8
Terraced beam-ends 8-3 ladder mouth mutually agrees with;
The top of double-deck connection post 8 is all connected with back timber 16, back timber 16 all with across ladder top shell wall 17 be connected;
In overlap with Stepped Beam 12 respectively across the two ends of cover plate 13, the one end with civil engineering air duct cover board 14 is overlapped with Stepped Beam 12,
The other end is overlapped with the bracket 7-6 of bright corbel type shell wall 7;Civil engineering air channel 14-2 is located at the lower section near bracket 7-6 side;
In overlap with the platform bottom girder 5-2 of two-beam type base plate shell wall 5 respectively across platen 10 two ends;Or with double pier formula base plate shell walls 6
Drain pan pier 6-2 overlap joint, and in across platen 10 top and double-deck connection post 8 at a distance of preferentially electing 10mm as;
Platform gripper shoe 9 lower end is connected with L-shaped base angle shell wall 4, and its upper end is connected with platform platen 11;Platform platen 11 another
End is overlapped with the platform bottom girder 5-2 of two-beam type base plate shell wall 5;Or the drain pan pier 6-2 overlap joint with double pier formula base plate shell walls 6;
Described L-shaped base angle shell wall 4 mainly includes horizontal shell wall 4-1, vertical shell wall 4-2, arch screw bolt hole 4-3, capillary groove 4-
4th, water bar 4-5, connection reinforcing bar 4-6, longitudinally connected bolt installing port 4-7, ring connecting bolt installing port 4-8, L-shaped base angle shell
Wall 4 is L-shaped, all at least provided with one layer of capillary groove 4-4 and water bar 4- on horizontal shell wall 4-1, vertical shell wall 4-2 longitudinal direction and ring
5, preferentially layer water bar 4-5 is set in outermost layer, capillary groove 4-4 is preferentially near outer layer;
It is respectively provided with multiple arcs bolt hole 4-3 in horizontal shell wall 4-1 longitudinal terminal surface and ring end face, vertical in vertical shell wall 4-2
Multiple arcs bolt hole 4-3 is set to end face, arch screw bolt hole 4-3 is arc, at horizontal shell wall 4-1 longitudinal terminal surface and ring end
At the longitudinal terminal surface of face and vertical shell wall 4-2, its tangent line is parallel with horizontal shell wall 4-1, vertical shell wall 4-2 place plane respectively;
Arch screw bolt hole 4-3 and its center of circle plane are vertical with the horizontal shell wall 4-1 or vertical shell wall 4-2 being located, and the center of circle is located at
Within the lining cutting shell wall of complete prefabricated assembled concrete subway station;
The other end of arch screw bolt hole 4-3 is respectively positioned on inside the lining cutting shell wall of complete prefabricated assembled concrete subway station, away from
From longitudinal end or the ring end 100 ~ 250mm of L-shaped base angle shell wall 4, and be respectively provided with longitudinally connected bolt installing port 4-7,
Ring connecting bolt installing port 4-8, ring connecting bolt installing port 4-8 is in the lining of complete prefabricated assembled concrete subway station
The inner surface building shell wall is preferably isosceles trapezoid;
Vertically shell wall 4-2 sets up overhanging connection reinforcing bar 4-6 in ring, and it is vertical for connecting reinforcing bar 4-6, and top is by screw
Button.
Described two-beam type base plate shell wall 5 mainly includes horizontal shell wall 5-1, platform bottom girder 5-2, capillary groove 5-3, waterproof gear
Plate 5-4, arch screw bolt hole 5-5, overall is in fall " ∏ " font, arranges two vertical platform bottom girders on horizontal shell wall 5-1 top
5-2;It is respectively provided with arch screw bolt hole 5-5 in the longitudinal direction of horizontal shell wall 5-1 and ring, arch screw bolt hole 5-5 is arc, in horizontal shell
Wall 5-1 longitudinal terminal surface and ring end face, the tangent line of arch screw bolt hole 5-5 is all parallel with horizontal shell wall 5-1 place plane;Arc spiral shell
Keyhole 5-5 and its center of circle plane are vertical with the horizontal shell wall 5-1 being located, and the center of circle is located at complete prefabricated assembled concrete ground
Within the lining cutting shell wall at ferrum station;The other end of arch screw bolt hole 5-5 is respectively positioned on complete prefabricated assembled concrete subway station
Inside lining cutting shell wall;
At least one water bar 5-4 and capillary groove 5-3 on horizontal shell wall 5-1, wherein excellent in the outermost of horizontal shell wall 5-1
One water bar 5-4 is first set.
Described double pier formula base plate shell walls 6 mainly include horizontal shell wall 6-1, drain pan pier 6-2, capillary groove 6-3, water bar
6-4, arch screw bolt hole 6-5, connection reinforcing bar 6-6,
Overall is in fall " ∏ " font, arranges two vertical drain pan pier 6-2 on horizontal shell wall 6-1 top;Horizontal shell wall 6-1's
Longitudinally it is respectively provided with arch screw bolt hole 6-5 with ring, arch screw bolt hole 6-5 is arc, in horizontal shell wall 6-1 longitudinal terminal surface and ring
End face, the tangent line of arch screw bolt hole 6-5 is all parallel with horizontal shell wall 6-1 place plane;Arch screw bolt hole 6-5 and its center of circle plane
Vertical with the horizontal shell wall 6-1 being located, and the center of circle is within the complete lining cutting shell wall of prefabricated assembled concrete subway station;
The other end of arch screw bolt hole 6-5 is respectively positioned on inside the lining cutting shell wall of complete prefabricated assembled concrete subway station;
At least one water bar 6-4 and capillary groove 6-3 on horizontal shell wall 6-1, wherein excellent in the outermost of horizontal shell wall 6-1
One water bar 6-4 is first set;
Arrange at drain pan pier 6-2 top and connect reinforcing bar 6-6, it is vertical for connecting reinforcing bar 6-6, and top carries buckle.
Described bright corbel type shell wall 7 mainly includes lower floor vertical shell wall 7-1, capillary groove 7-2, water bar 7-3, arc spiral shell
Keyhole 7-4, connection reinforcing bar 7-5, bracket 7-6, connecting bolt installing port 7-7,
At least one capillary groove 7-2, water bar 7-3 on lower floor vertical shell wall 7-1, wherein in the outermost of vertical shell wall 7-1
One water bar 7-3 is preferentially set;
Arrange at lower floor vertical shell wall 7-1 top and connect reinforcing bar 7-5, it is vertical for connecting reinforcing bar 7-5, and top carries buckle;
Bracket 7-6 is set in the inner side on lower floor vertical shell wall 7-1 top, some connecting bolt installing port 7-7 are set in bottom;
In the longitudinally disposed arch screw bolt hole 7-4 of lower floor vertical shell wall 7-1, arch screw bolt hole 7-4 is arc, in the vertical shell of lower floor
Wall 7-1 longitudinal terminal surface, the tangent line of arch screw bolt hole 7-4 is all parallel with lower floor vertical shell wall 7-1 place plane;Arch screw bolt hole 7-
4 and its center of circle plane vertical with the lower floor vertical shell wall 7-1 being located, and the center of circle is positioned at complete prefabricated assembled concrete subway
Within the lining cutting shell wall stood;The other end of arch screw bolt hole 7-4 is respectively positioned on the lining of complete prefabricated assembled concrete subway station
Build inside shell wall;
Described double-deck connection post 8 mainly include lower floor cylinder 8-1, upper strata cylinder 8-2, ladder beam-ends 8-3, connect installing port 8-4,
Connect reinforcing bar 8-5, the two-layer post that lower floor cylinder 8-1, upper strata cylinder 8-2 are integrated, longitudinally disposed Stepped Beam between the two layers
End 8-3, the overhanging 200 ~ 500mm of ladder beam-ends 8-3, ladder beam-ends 8-3 with ladder mouth, preferentially contour up and down, top half
Take in 100 ~ 200mm;
Arrange in bottom and connect installing port 8-4, arrange on top and connect reinforcing bar 8-5, the top connecting reinforcing bar 8-5 carries screw
Button.
Described band civil engineering air duct cover board 14 mainly includes plate body 14-1, civil engineering air channel 14-2, in plate body 14-1 near complete
The downside setting civil engineering air channel 14-2 of the lining cutting shell wall of whole prefabricated assembled concrete subway station;Civil engineering air channel 14-2 is square
Shape, preferentially adopts xoncrete structure.
Described hidden bracket formula shell wall 15 mainly includes upper level upright shell wall 15-1, water bar 15-2, capillary groove 15-3, arc
Shape bolt hole 15-4, hidden bracket 15-5, connection reinforcing bar 15-6, connecting bolt installing port 15-7,
At least one water bar 15-2, capillary groove 15-3 on upper level upright shell wall 15-1, wherein in the outermost of vertical shell wall 7-1
Side preferentially arranges one water bar 15-2;
Hidden bracket 15-5 is set at upper level upright shell wall 15-1 top, hidden bracket 15-5 is ladder mouth, preferentially interior outside equal thickness,
150-300mm is taken in medial wall;Arrange in interior side steps mouth and connect reinforcing bar 15-6, it is vertical for connecting reinforcing bar 15-6, and top tape
There is buckle;In bottom, some connecting bolt installing port 15-7 are set;
In the longitudinally disposed arch screw bolt hole 15-4 of upper level upright shell wall 15-1, arch screw bolt hole 15-4 is arc, erects on upper strata
Straight shell wall 15-1 longitudinal terminal surface, the tangent line of arch screw bolt hole 15-4 is all parallel with upper level upright shell wall 15-1 place plane;Arc
Bolt hole 15-4 and its center of circle plane are vertical with the upper level upright shell wall 15-1 being located, and the center of circle is positioned at complete prefabricated assembled
Within the lining cutting shell wall at concrete metro station;The other end of arch screw bolt hole 15-4 is respectively positioned on complete prefabricated assembled concrete
Inside the lining cutting shell wall of subway station;
In described, across ladder top shell wall 17 mainly includes top layer housing 17-1, water fender 17-2, capillary groove 17-3, arch screw bolt
Hole 17-4, ladder mouth 17-5, at least one water fender 17-2, capillary groove 17-3 on top layer housing 17-1, wherein in top layer shell
The outermost of body 17-1 preferentially arranges one water fender 17-2;It is respectively provided with ladder mouth 17-5 at the two ends of top layer housing 17-1,
Preferential top and the bottom equal thickness, 150-300mm is taken on top;It is respectively provided with arch screw bolt hole in the longitudinal direction of top layer housing 17-1 and ring
17-4, arch screw bolt hole 17-4 are arc, and in top layer housing 17-1 longitudinal direction and ring end face, the tangent line of arch screw bolt hole 17-4 is equal
Parallel with top layer housing 17-1 place plane;Arch screw bolt hole 17-4 and its center of circle plane are hung down with the top layer housing 17-1 being located
Directly, and within the center of circle is located at the complete lining cutting shell wall of prefabricated assembled concrete subway station;Arch screw bolt hole 17-4's is another
End is respectively positioned on inside the lining cutting shell wall of complete prefabricated assembled concrete subway station.
Described end bay ladder top shell wall 18 mainly includes top layer housing 18-1, water fender 18-2, capillary groove 18-3, arc
Bolt hole 18-4, ladder mouth 18-5;
At least one water fender 18-2, capillary groove 18-3 on top layer housing 18-1, wherein in the outermost of top layer housing 18-1
One water fender 18-2 is preferentially set;
It is respectively provided with ladder mouth 18-5, preferential top and the bottom equal thickness at the two ends of top layer housing 18-1,150- is taken in bottom
300mm;It is respectively provided with arch screw bolt hole 18-4 in the longitudinal direction of top layer housing 18-1 and ring, it requires and arch screw bolt hole 17-4 phase
With.
The above is only the preferred embodiment of the present invention it is noted that ordinary skill people for the art
For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should
It is considered as protection scope of the present invention.