CN106429896A - Special C-shaped beam used for tower crane - Google Patents
Special C-shaped beam used for tower crane Download PDFInfo
- Publication number
- CN106429896A CN106429896A CN201610888874.4A CN201610888874A CN106429896A CN 106429896 A CN106429896 A CN 106429896A CN 201610888874 A CN201610888874 A CN 201610888874A CN 106429896 A CN106429896 A CN 106429896A
- Authority
- CN
- China
- Prior art keywords
- shaped
- girder
- structural
- receiving end
- connecting rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
Abstract
本发明提出了一种用于塔吊的异形C型梁,包括主梁、连接杆连接部、措施大梁铰接端、结构梁承接端、加劲板;其中,措施大梁铰接端、结构梁承接端分别为主梁的两端,措施大梁铰接端采用螺栓连接的方式与设计大梁相连接;结构梁承接端的尾部有加劲板,使得C型梁为伸臂式,在安装时由原来的竖向垂直摆放式改为插入式;结构梁承接端与结构梁通过加劲板焊接。本发明满足在复杂结构影响下空间对塔吊安装、爬升影响,通过将C型梁的端部支承的螺栓连接方式,改造为现场一端加劲板焊接方式、一端螺栓连接方式,满足了施工阶段结构变形工况下C型梁的顺利安装;调整原有C型梁长度,将原来支座端位置调整为伸臂形式,在狭小的空间内也能满足C型梁的伸臂端与工程结构构件有效连接。
The present invention proposes a special-shaped C-shaped beam for tower cranes, including a main girder, a connecting part of a connecting rod, a hinged end of a measure girder, a receiving end of a structural beam, and a stiffening plate; wherein, the hinged end of a measuring girder and the receiving end of a structural beam are respectively Both ends of the main girder and the hinged end of the measure girder are connected to the design girder by means of bolt connection; there is a stiffening plate at the end of the receiving end of the structural girder, so that the C-shaped girder is an outrigger type, and it is placed vertically from the original vertical position during installation. The type is changed to the plug-in type; the receiving end of the structural beam and the structural beam are welded through the stiffening plate. The invention satisfies the influence of the space on the installation and climbing of the tower crane under the influence of the complex structure, and transforms the bolt connection method of the end support of the C-shaped beam into a welding method of stiffening plate at one end and a bolt connection method at one end on site, which satisfies the structural deformation during the construction stage The smooth installation of C-shaped beams under working conditions; adjust the length of the original C-shaped beams, and adjust the position of the original support end to the outrigger form, which can also meet the effective requirements of the outrigger end of the C-shaped beams and engineering structural components in a small space. connect.
Description
技术领域technical field
本发明属于建筑施工用具技术领域,具体涉及一种用于塔吊的C型梁。The invention belongs to the technical field of building construction tools, and in particular relates to a C-shaped beam used for a tower crane.
背景技术Background technique
塔吊是建筑工地上最常用的一种起重设备,以一节一节的接长(高),用来吊施工用的钢筋、木楞、脚手管等施工原材料设备,塔吊是现在建筑施工中一种必不可少的设备。现有的塔吊常有移动式和固定式的两种形式,移动式塔吊移动方便,但不能带负荷行走、稳定性较差,目前己很少生产。固定式塔吊需要采用基础平台设置在地基上,但是长时间的使用对地基的承载能力有很高的要求。Tower crane is the most commonly used lifting equipment on construction sites. It is used to hang construction materials such as steel bars, wooden corrugated pipes, and scaffolding pipes for construction by connecting lengths (height) one by one. An essential piece of equipment. Existing tower cranes often have two forms: mobile and fixed. The mobile tower crane is easy to move, but cannot walk with a load and has poor stability. At present, it is rarely produced. The fixed tower crane needs to be set on the foundation with the foundation platform, but the long-term use has high requirements on the bearing capacity of the foundation.
塔吊C型梁一般作为塔吊设备标准件,因设备型号而不同,作为塔吊爬带悬挂点和塔吊标准节及整体塔塔吊身支承结构,并在C型梁侧面设置调节顶块,固定塔身标准节,是整体塔吊能自爬升重要的受力构件。但是,随着建筑的要求越来越高,复杂结构影响下空间对塔吊安装、爬升存在很大的影响。The C-beam of the tower crane is generally used as a standard part of the tower crane equipment, which varies depending on the type of equipment. It is used as the suspension point of the tower crane climbing belt, the standard section of the tower crane and the supporting structure of the overall tower crane body, and an adjusting top block is set on the side of the C-beam to fix the standard of the tower body. The joint is an important force-bearing component for the self-climbing of the overall tower crane. However, as the requirements of buildings become higher and higher, the space under the influence of complex structures has a great impact on the installation and climbing of tower cranes.
发明内容Contents of the invention
为解决现有技术中存在的问题,本发明提出了一种用于塔吊的异形C型梁,改进C型梁的端部支承的连接方式,同时还调整了C型梁长度,能够满足复杂结构影响下空间对塔吊安装、爬升的要求。In order to solve the problems existing in the prior art, the present invention proposes a special-shaped C-beam for tower cranes, improves the connection mode of the end support of the C-beam, and also adjusts the length of the C-beam, which can meet the requirements of complex structures. Affect the requirements of the lower space for tower crane installation and climbing.
本发明具体通过如下技术方案实现:The present invention is specifically realized through the following technical solutions:
一种用于塔吊的异形C型梁,包括C型梁主梁、连接杆连接部、措施大梁铰接端、结构梁承接端、加劲板;其中,所述措施大梁铰接端、结构梁承接端分别为所述主梁的两端,所述转措施大梁铰接端上有连接孔,所述铰接端采用螺栓连接的方式与可周转措施大梁相连接;所述结构梁承接端上有加劲板,所述加劲板位于结构梁承接端的尾部,使得所述C型梁为伸臂式C型梁,在安装时由原来的竖向垂直摆放式改为插入式;所述结构梁承接端与结构梁通过所述加劲板焊接。A special-shaped C-shaped beam for tower cranes, comprising a C-shaped girder main girder, a connecting part of a connecting rod, a hinged end of a measure girder, a receiving end of a structural beam, and a stiffening plate; wherein, the hinged end of the measuring girder and the receiving end of the structural beam are respectively It is the two ends of the main girder. There are connection holes on the hinged end of the girder with turning measures, and the hinged end is connected with the girder with turnaround measures by bolt connection; The stiffening plate is located at the tail of the structural beam receiving end, so that the C-shaped beam is an outrigger C-shaped beam, which is changed from the original vertical vertical placement type to the plug-in type during installation; the structural beam receiving end and the structural beam welded through the stiffener.
本发明的有益效果是:本发明提出的异形C型梁,除满足塔吊爬升、支承等必不可少的功能外,还满足了在复杂结构影响下空间对塔吊安装、爬升影响,通过将C型梁的端部支承的螺栓连接方式,改造为现场一端加劲板焊接方式、一端螺栓连接方式,满足了施工阶段结构变形工况下C型梁的顺利安装;本发明还调整了原有C型梁长度,由原来的支座端位置调整为伸臂形式,在狭小的空间内也能满足C型梁的伸臂端与工程结构构件有效连接。The beneficial effects of the present invention are: the special-shaped C-shaped beam proposed by the present invention not only satisfies the essential functions such as tower crane climbing and supporting, but also satisfies the influence of space on tower crane installation and climbing under the influence of complex structures. The bolt connection mode of the end support of the beam is transformed into a stiffening plate welding mode at one end and a bolt connection mode at one end on site, which satisfies the smooth installation of the C-beam under the condition of structural deformation during the construction stage; the invention also adjusts the original C-beam The length is adjusted from the position of the original support end to the outrigger form, which can also meet the effective connection between the outrigger end of the C-shaped beam and the engineering structural components in a small space.
附图说明Description of drawings
图1是采用现有技术中的C型梁组装的标准件的结构图;Fig. 1 is a structural diagram of a standard part assembled with a C-beam in the prior art;
图2是采用本发明的异形C型梁组装的标准件的结构图;Fig. 2 is the structural diagram of the standard part that adopts special-shaped C-beam assembly of the present invention;
图3是本发明的异形C型梁的横截面图。Fig. 3 is a cross-sectional view of the special-shaped C-beam of the present invention.
具体实施方式detailed description
下面结合附图说明及具体实施方式对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
如附图3所示,本发明的异形C型梁包括C型梁主梁1、连接杆连接部2、措施大梁铰接端3、结构梁承接端4、加劲板5;其中,所述措施大梁铰接端3、结构梁承接端4分别为所述主梁的两端,所述措施大梁铰接端上有连接孔6,所述措施大梁铰接端采用螺栓连接的方式与措施大梁相连接;所述结构梁承接端4上有加劲板5,所述加劲板5位于结构梁承接端4的尾部,使得所述C型梁为伸臂式C型梁,在安装时由原来的竖向垂直摆放式改为插入式;所述结构梁承接端4与结构梁通过所述加劲板5焊接。As shown in accompanying drawing 3, the special-shaped C-beam of the present invention comprises C-beam main girder 1, connecting rod connection part 2, measure girder hinged end 3, structural beam receiving end 4, stiffening plate 5; Wherein, described measure girder The hinged end 3 and the structural beam receiving end 4 are respectively the two ends of the main girder, the hinged end of the measure girder has a connection hole 6, and the hinged end of the measure girder is connected with the measure girder by bolt connection; There is a stiffening plate 5 on the receiving end 4 of the structural beam, and the stiffening plate 5 is located at the tail of the receiving end 4 of the structural beam, so that the C-shaped beam is an outrigger C-shaped beam, which is placed vertically from the original vertical position during installation. The type is changed to the plug-in type; the structural beam receiving end 4 and the structural beam are welded through the stiffening plate 5 .
附图1是现有技术中的C型梁组装的标准件的结构图,措施大梁铰接端、结构梁承接端都采用螺栓连接的方式,附图2是采用本发明的异形C型梁组装的标准件的结构图,措施大梁铰接端采用螺栓连接的方式,结构梁承接端采用加劲板焊接的方式,这样使得原有的C型梁改为伸臂式C型梁,在利用结构梁作为支承大梁时,考虑到空间影响,由原来的竖向垂直摆放式改为插入式,满足C型梁的安装和使用过程中的空间需求。Accompanying drawing 1 is the structural diagram of the standard part of C-beam assembly in the prior art, and measures girder hinged end, structural beam receiving end all adopt the mode of bolt connection, and accompanying drawing 2 adopts the special-shaped C-beam assembly of the present invention The structural diagram of the standard parts, measure the hinged end of the girder is connected by bolts, and the receiving end of the structural beam is welded by a stiffened plate, so that the original C-shaped beam is changed to an outrigger C-shaped beam, and the structural beam is used as a support For the girder, considering the impact of space, the original vertical placement type is changed to the plug-in type to meet the space requirements during the installation and use of the C-shaped beam.
两根C型梁之间通过连接杆7连接,所述连接杆7也采用螺栓连接的方式与所述连接杆连接部2固定连接。所述连接杆连接部有两个,两个连接杆连接部分别位于主梁的两端,其中,第一连接杆连接部、连接杆、所述措施大梁铰接端3在同一延长线上,第二连接杆连接部位于所述结构梁承接端4的中部,使得所述结构梁承接端4能够形成伸臂式,以便在安装时能够插入式安装。The two C-shaped beams are connected by a connecting rod 7, and the connecting rod 7 is also fixedly connected to the connecting rod connecting portion 2 by means of bolt connection. There are two connecting rod connecting parts, and the two connecting rod connecting parts are respectively located at both ends of the main girder, wherein the first connecting rod connecting part, the connecting rod, and the hinged end 3 of the measure beam are on the same extension line, and the second connecting rod connecting part is on the same extension line. The connecting parts of the two connecting rods are located in the middle of the receiving end 4 of the structural beam, so that the receiving end 4 of the structural beam can form an outrigger type, so that it can be inserted into the installation.
本发明的异形C型梁的创新点主要在于:The innovation of the special-shaped C-shaped beam of the present invention mainly lies in:
1、在带斜撑的巨型钢框架结构中,考虑到施工过程中结构变形因素,C型梁两端分别采用螺栓连接和加劲板焊接,因塔吊大梁一端刚接于结构梁,一端铰接于支承措施大梁(可周转),纯钢结构因施工变形,若结构梁上设计为螺栓连接,工厂制作,现场安装精度难以达到安装要求。同时若设计支座形式,则支座高度最小需要230mm,而对应的造成C型梁与结构斜撑体系碰撞,影响斜撑的安装,削弱整体结构体系。1. In the giant steel frame structure with diagonal braces, considering the structural deformation factors during the construction process, the two ends of the C-shaped beam are connected by bolts and welded with stiffeners, because one end of the tower crane girder is rigidly connected to the structural beam, and the other end is hinged to the support Measures The girder (turnover) and the pure steel structure are deformed due to construction. If the structural beam is designed to be bolted and manufactured by the factory, the on-site installation accuracy is difficult to meet the installation requirements. At the same time, if the support form is designed, the minimum height of the support needs to be 230mm, and the corresponding collision between the C-shaped beam and the structural brace system will affect the installation of the brace and weaken the overall structural system.
2、采用伸臂式C型梁,因C型梁结构体系中两个C型梁的连接杆件安装过程需要与结构有一定操作空间,而且塔身要求与结构边线距离至少大于500mm,满足塔吊运行过程中的摆幅。在利用结构梁作为支承大梁时,考虑到空间影响,将C型梁改为伸臂式C型梁,由原来的竖向垂直摆放式改为插入式,满足C型梁的安装和使用过程中的空间需求。通过利用原结构体系,减少三道塔吊新增支承措施大梁,同时避开结构不利空间的影响。较传统安装,减少了一道大梁的安装工作,缓解了塔吊安装精度要求高的处理难度。2. The outrigger C-beam is adopted, because the installation process of the connecting rods of the two C-beams in the C-beam structure system needs to have a certain operating space with the structure, and the distance between the tower body and the structure edge is at least 500mm, which meets the requirements of the tower crane. swing during operation. When using the structural beam as the supporting girder, considering the influence of space, the C-beam is changed to an outrigger C-beam, and the original vertical vertical placement is changed to a plug-in type, which meets the installation and use process of the C-beam space requirements in . By using the original structural system, the girders of the new supporting measures for the three tower cranes are reduced, and the influence of unfavorable space of the structure is avoided at the same time. Compared with the traditional installation, the installation work of a large beam is reduced, and the difficulty of handling the high precision installation of the tower crane is eased.
以上内容是结合具体的优选实施方式对本发明所作的进一步详细说明,不能认定本发明的具体实施只局限于这些说明。对于本发明所属技术领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干简单推演或替换,都应当视为属于本发明的保护范围。The above content is a further detailed description of the present invention in conjunction with specific preferred embodiments, and it cannot be assumed that the specific implementation of the present invention is limited to these descriptions. For those of ordinary skill in the technical field of the present invention, without departing from the concept of the present invention, some simple deduction or replacement can be made, which should be regarded as belonging to the protection scope of the present invention.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610888874.4A CN106429896B (en) | 2016-10-12 | 2016-10-12 | A special-shaped C-beam for tower crane |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610888874.4A CN106429896B (en) | 2016-10-12 | 2016-10-12 | A special-shaped C-beam for tower crane |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106429896A true CN106429896A (en) | 2017-02-22 |
| CN106429896B CN106429896B (en) | 2019-04-02 |
Family
ID=58174126
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610888874.4A Active CN106429896B (en) | 2016-10-12 | 2016-10-12 | A special-shaped C-beam for tower crane |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106429896B (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106966307A (en) * | 2017-04-28 | 2017-07-21 | 中国建筑股份有限公司 | A non-closed tower crane climbing frame device and its application method |
| CN107032241A (en) * | 2017-04-28 | 2017-08-11 | 中国建筑股份有限公司 | One kind plus drag-line tower crane climbing frame apparatus and its application method |
| CN107161884A (en) * | 2017-04-28 | 2017-09-15 | 中国建筑股份有限公司 | Mechanical device combining tower crane climbing frame and structural support beam and using method thereof |
| WO2018196452A1 (en) * | 2017-04-28 | 2018-11-01 | 中国建筑股份有限公司 | Tower crane climbing frame device with cable |
| WO2018196451A1 (en) * | 2017-04-28 | 2018-11-01 | 中国建筑股份有限公司 | Non-closed tower crane climbing frame device |
| CN109896419A (en) * | 2019-03-07 | 2019-06-18 | 江苏承天新型建材有限公司 | A kind of steel construction driving beam being easily installed |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202953748U (en) * | 2012-12-12 | 2013-05-29 | 中国建筑第二工程局有限公司 | Wall-attached structure of overhanging external hanging type self-climbing tower crane |
| CN203474309U (en) * | 2013-08-04 | 2014-03-12 | 中国建筑第四工程局有限公司 | Supporting seat of tower crane supporting beam |
| CN203497959U (en) * | 2013-08-04 | 2014-03-26 | 中国建筑第四工程局有限公司 | Support structure without inclined rod for tower crane |
| CN203794504U (en) * | 2014-03-31 | 2014-08-27 | 广东庞源工程机械有限公司 | Internal-climbing plug-in tower crane support structure |
| CN104961058A (en) * | 2015-06-08 | 2015-10-07 | 哈尔滨工业大学深圳研究生院 | Double-Z-type supporting steel girder, crane supporting component with same and use method |
| CN204752025U (en) * | 2015-06-24 | 2015-11-11 | 筑博设计股份有限公司 | A tower crane supporting beam's connection structure |
| CN206232343U (en) * | 2016-10-12 | 2017-06-09 | 中国建筑第四工程局有限公司珠海分公司 | A kind of special-shaped C-type beam for tower crane |
-
2016
- 2016-10-12 CN CN201610888874.4A patent/CN106429896B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202953748U (en) * | 2012-12-12 | 2013-05-29 | 中国建筑第二工程局有限公司 | Wall-attached structure of overhanging external hanging type self-climbing tower crane |
| CN203474309U (en) * | 2013-08-04 | 2014-03-12 | 中国建筑第四工程局有限公司 | Supporting seat of tower crane supporting beam |
| CN203497959U (en) * | 2013-08-04 | 2014-03-26 | 中国建筑第四工程局有限公司 | Support structure without inclined rod for tower crane |
| CN203794504U (en) * | 2014-03-31 | 2014-08-27 | 广东庞源工程机械有限公司 | Internal-climbing plug-in tower crane support structure |
| CN104961058A (en) * | 2015-06-08 | 2015-10-07 | 哈尔滨工业大学深圳研究生院 | Double-Z-type supporting steel girder, crane supporting component with same and use method |
| CN204752025U (en) * | 2015-06-24 | 2015-11-11 | 筑博设计股份有限公司 | A tower crane supporting beam's connection structure |
| CN206232343U (en) * | 2016-10-12 | 2017-06-09 | 中国建筑第四工程局有限公司珠海分公司 | A kind of special-shaped C-type beam for tower crane |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106966307A (en) * | 2017-04-28 | 2017-07-21 | 中国建筑股份有限公司 | A non-closed tower crane climbing frame device and its application method |
| CN107032241A (en) * | 2017-04-28 | 2017-08-11 | 中国建筑股份有限公司 | One kind plus drag-line tower crane climbing frame apparatus and its application method |
| CN107161884A (en) * | 2017-04-28 | 2017-09-15 | 中国建筑股份有限公司 | Mechanical device combining tower crane climbing frame and structural support beam and using method thereof |
| CN107032241B (en) * | 2017-04-28 | 2018-08-28 | 中国建筑股份有限公司 | One kind plus drag-line tower crane climbing frame apparatus and its application method |
| WO2018196452A1 (en) * | 2017-04-28 | 2018-11-01 | 中国建筑股份有限公司 | Tower crane climbing frame device with cable |
| WO2018196451A1 (en) * | 2017-04-28 | 2018-11-01 | 中国建筑股份有限公司 | Non-closed tower crane climbing frame device |
| WO2018196453A1 (en) * | 2017-04-28 | 2018-11-01 | 中国建筑股份有限公司 | Tower crane climbing frame and structural support beam integrated mechanical device and using method thereof |
| CN106966307B (en) * | 2017-04-28 | 2018-12-04 | 中国建筑股份有限公司 | A non-closed tower crane climbing frame device and its application method |
| CN109896419A (en) * | 2019-03-07 | 2019-06-18 | 江苏承天新型建材有限公司 | A kind of steel construction driving beam being easily installed |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106429896B (en) | 2019-04-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203188589U (en) | Rigid-frame continuous beam zero block construction bracket supporting system | |
| CN207633222U (en) | Bridge pier binder Coping Construction platform | |
| CN106429896B (en) | A special-shaped C-beam for tower crane | |
| CN207538480U (en) | A kind of lattice temporary support for curved tube component | |
| CN101503908B (en) | Construction method for spacing suspension cable structural template support platform | |
| CN212641166U (en) | Vertical-rod-free triangular truss split type steel guide beam | |
| CN209081301U (en) | A kind of special section structure | |
| CN209163043U (en) | A kind of side's Concrete-filled Double Skin Steel Tube Columns and steel beam connecting joint | |
| CN206232343U (en) | A kind of special-shaped C-type beam for tower crane | |
| CN205329549U (en) | Corbel frame device is deposited to steel case roof beam temporarily | |
| CN103601081B (en) | Support system is climbed in tower crane | |
| CN218912192U (en) | Clamp type operation platform suitable for box girder | |
| CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
| CN203474309U (en) | Supporting seat of tower crane supporting beam | |
| CN213896816U (en) | Y-shaped support frame | |
| CN216194054U (en) | Guide beam for steel box girder pushing construction | |
| CN112573341B (en) | Column top hoisting mechanism and construction method thereof | |
| CN214402141U (en) | An assembled steel beam-column connection node | |
| CN110723643B (en) | A method of changing the gauge of cranes in service | |
| CN204703310U (en) | Concrete column reinforcing joint structure | |
| CN204690594U (en) | A kind of simple and easy door frame of the Slidable for the installation of framing type steel box-girder crossbeam | |
| CN116081459A (en) | Construction adjustment method for gantry with large size Liang Guochang | |
| CN209131949U (en) | A kind of scaffold vertical stability test device for multifunctional | |
| CN209260529U (en) | A new type of composite truss beam | |
| CN202164547U (en) | Bracket system for concrete pouring of bridge contact network platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |