CN106374456A - A power supply recovery method after a fault in a distribution network with distributed power - Google Patents
A power supply recovery method after a fault in a distribution network with distributed power Download PDFInfo
- Publication number
- CN106374456A CN106374456A CN201610828635.XA CN201610828635A CN106374456A CN 106374456 A CN106374456 A CN 106374456A CN 201610828635 A CN201610828635 A CN 201610828635A CN 106374456 A CN106374456 A CN 106374456A
- Authority
- CN
- China
- Prior art keywords
- load
- power supply
- distributed power
- network
- power source
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/388—Islanding, i.e. disconnection of local power supply from the network
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
Description
技术领域technical field
本发明属于配电自动化技术领域,尤其是一种含分布式电源的配电网故障后供电恢复方法。The invention belongs to the technical field of power distribution automation, in particular to a power supply recovery method after a fault in a power distribution network including a distributed power source.
背景技术Background technique
目前,含分布式电源(DG)的配电网发生故障大面积停电时,分布式电源一般先从配电网切除,然后对配电网健全区域进行供电恢复,最后分布式电源并网。但此种做法未能发挥分布式电源提高供电可靠性这一功能,因此现在配电网故障大面积停电时,具有孤岛运行能力的分布式电源带周围负荷孤岛运行,不具备孤岛运行能力的分布式电源解列,然后隔离故障区段,配电网健全区域恢复供电,最后孤岛运行部分和分布式电源并网,这样当电网大面积停电时可以保证对重要负荷的供电不中断,充分发挥分布式发电的优势。但是这种含分布式电源配电网故障后的供电恢复过程中,分布式电源只带固定负荷孤岛运行,未考虑了分布式电源以最大能力带周围负荷运行,以及对健全区域恢复供电过程中,未考虑分布式电源并网后的网损和开关动作次数问题。At present, when the distribution network containing distributed generation (DG) fails and a large-scale power outage occurs, the distributed generation is generally removed from the distribution network, and then the power supply is restored to the healthy area of the distribution network, and finally the distributed generation is connected to the grid. However, this approach fails to give full play to the function of distributed power to improve power supply reliability. Therefore, when the distribution network fails and a large-scale power outage occurs, the distributed power with island operation capability will operate in isolated islands with surrounding loads, and does not have the distribution of island operation capabilities. Then the faulty section is isolated, the power supply is restored in the healthy area of the distribution network, and finally the island operation part is connected to the distributed power supply grid, so that when the power grid fails in a large area, the power supply to important loads can be guaranteed without interruption, and the distributed power supply can be fully utilized. advantages of power generation. However, in the power supply recovery process after the fault of the distributed power distribution network, the distributed power only operates in an isolated island with fixed loads, and does not consider the operation of the distributed power with the surrounding load at its maximum capacity and the process of restoring power to healthy areas. , without considering the network loss and the number of switching operations after the distributed power generation is connected to the grid.
发明内容Contents of the invention
本发明的目的在于克服现有技术的不足,提供一种设计合理、重点负荷供电可靠性高且负荷损失以及网损小的含分布式电源的配电网故障后供电恢复方法。The purpose of the present invention is to overcome the deficiencies of the prior art, and provide a power supply recovery method after a failure of a distributed power distribution network with reasonable design, high reliability of key load power supply, and small load loss and network loss.
本发明解决其技术问题是采取以下技术方案实现的:The present invention solves its technical problem and realizes by taking the following technical solutions:
一种含分布式电源的配电网故障后供电恢复方法,包括以下步骤:A power supply recovery method after a fault in a distribution network including a distributed power supply, comprising the following steps:
步骤1、配电网故障出现大面积停电情况后,将不具备孤岛运行能力的分布式电源解列;Step 1. After a large-scale power outage occurs due to a fault in the distribution network, the distributed power generation that does not have the ability to operate in an isolated manner will be disconnected;
步骤2、基于分布式电源以最大能力带周围负荷运行的原则,采用搜索方法进行孤岛划分后,将具备孤岛运行能力的分布式电源带周围负荷孤岛运行;Step 2. Based on the principle that the distributed power supply operates with the surrounding load at its maximum capacity, after using the search method to divide the islands, the distributed power supply with the island operation capability is operated with the surrounding loads in an isolated island;
步骤3、隔离故障点,恢复剩余健全网络的供电;Step 3. Isolate the fault point and restore the power supply of the remaining sound network;
步骤4、具备并网条件的分布式电源或者孤岛并网运行,不具备并网条件的孤岛继续孤岛运行。Step 4. Distributed power sources with grid-connected conditions or isolated islands are connected to the grid, and isolated islands that do not have grid-connected conditions continue to operate in isolation.
而且,所述步骤2的孤岛划分的具体步骤包括:Moreover, the specific steps of the island division in step 2 include:
(1)以分布式电源为父节点开始,搜索与分布式电源直接相连的所有负荷子节点,将子节点代表的负荷放入待恢复负荷库W;(1) Starting with the distributed power source as the parent node, search for all load child nodes directly connected to the distributed power source, and put the load represented by the child node into the load library W to be restored;
(2)判断待恢复负荷库W是否为空;若不为空,计算待恢复负荷库W中所有负荷的Pnqn,从W中取出Pnqn中最大者对应的负荷m,将负荷m放入预选负荷库V;若为空,预选负荷库V中负荷为分布式电源孤岛运行范围内负荷,孤岛划分成功;(2) Determine whether the load library W to be restored is empty; if it is not empty, calculate the P n q n of all loads in the load library W to be restored, and take out the load m corresponding to the largest P n q n from W, and set Put the load m into the pre-selected load library V; if it is empty, the load in the pre-selected load library V is the load within the operating range of the distributed power island, and the island is divided successfully;
(3)判断分布式电源与预选负荷库V中的负荷是否满足如下式所示的约束条件;若不满足,则从预选负荷库V中去除负荷m,跳转至步骤2的第(2)步;若满足,则跳转至步骤2的第(4)步;(3) Determine whether the distributed power supply and the load in the preselected load library V meet the constraints shown in the following formula; if not, remove the load m from the preselected load library V, and jump to step (2) of step 2 Step; if satisfied, jump to step (4) of step 2;
其中,PDG、QDG分别为分布式电源带有功、无功负荷能力;Pi、Pn分别为负荷i、n的有功负荷;Qi为负荷i的无功负荷;i为V中负荷;qn为根据负荷n的重要程度,为负荷n分配的权重因子;n为W中负荷;Among them, P DG , Q DG are distributed power generation with power and reactive load capacity respectively; P i , P n are active loads of load i and n respectively; Q i is reactive load of load i; i is load in V ;q n is the weight factor assigned to load n according to the importance of load n; n is the load in W;
(4)判断分布式电源与预选负荷库V形成的网络是否满足如下式所示的约束条件;若满足,则以负荷m为父节点开始,搜索与负荷m直接相连的所有负荷子节点,将子节点代表的负荷放入待恢复负荷库W,跳转至步骤2的第(2)步;若不满足如下所示的约束条件,则从预选负荷库V中取出负荷m,跳转至步骤2的第(2)步;(4) Determine whether the network formed by the distributed power supply and the pre-selected load library V satisfies the constraints shown in the following formula; if so, start with the load m as the parent node, search for all load child nodes directly connected to the load m, and set Put the load represented by the child node into the load library W to be restored, and jump to step (2) of step 2; if the constraints shown below are not met, take the load m from the pre-selected load library V, and jump to step step (2) of 2;
其中,第一个约束式为支路电流约束,Imax_bij为线路bij的最大传输电流;第二个约束式为节点电压约束,Ui为预选负荷库V中负荷i的电压,Umax、Umin分别为预选负荷库V中负荷i的最大、最小允许电压。Among them, the first constraint is the branch current constraint, I max_bij is the maximum transmission current of the line b ij ; the second constraint is the node voltage constraint, U i is the voltage of load i in the pre-selected load library V, U max , U min are the maximum and minimum allowable voltages of load i in the pre-selected load library V, respectively.
而且,所述步骤3的具体步骤包括:And, the specific steps of described step 3 include:
(1)分别建立以恢复供电后负荷损失最少、开关动作次数最少和网损最少的多目标优化函数,该多目标优化函数如下所示:(1) Establish the multi-objective optimization function with the least load loss, the least number of switching actions and the least network loss after the power supply is restored. The multi-objective optimization function is as follows:
其中,f1、f2、f3分别代表负荷损失函数、开关动作次数函数、网损函数;PBL为断电区域内负荷大小与其对应的权系数相乘后的和;Y为除孤岛区域剩余网络负荷节点的集合;Py为负荷y的有功负荷;qy为根据负荷y的重要程度为负荷y分配的权重因子,负荷越重要其权系数越大;Ss为分段开关集合;Ts为故障前联络开关集合;Kk为开关状态,0代表断开,1代表闭合;Ploss为除孤岛部分网损;Among them, f 1 , f 2 , and f 3 respectively represent the load loss function, the switching action times function, and the network loss function; P BL is the sum of the multiplication of the load size in the power-off area and its corresponding weight coefficient; Y is the area except for isolated islands The set of remaining network load nodes; P y is the active load of load y; q y is the weight factor assigned to load y according to the importance of load y, the more important the load, the greater the weight coefficient; S s is the set of segmented switches; T s is the set of contact switches before failure; K k is the switch state, 0 means disconnected, 1 means closed; P loss is the network loss except for the isolated island;
其约束条件如下所示:Its constraints are as follows:
其中,第一个约束式为支路容量约束;Smax_b为线路b的最大传输容量;α为裕度系数;第二个约束式为电能质量之电压约束;U’y为剩余网络节点y的电压;U’max、U’min为最大、最小允许电压;第三个约束式为配电网结构约束;g为剩余网络供电恢复后的网络结构;GR为由剩余网络节点支路组成的所有可能的辐射状网络结构的集合;Among them, the first constraint is the branch capacity constraint; S max_b is the maximum transmission capacity of line b; α is the margin coefficient; the second constraint is the voltage constraint of power quality; U' y is the remaining network node y voltage; U' max and U' min are the maximum and minimum allowable voltages; the third constraint is the distribution network structure constraint; g is the network structure after the power supply of the remaining network is restored; G R is the network structure composed of the remaining network node branches The set of all possible radial network structures;
(2)根据传统的运筹学方法进行求解、可采用遗传算法或二进制粒子群算法对步骤3的第(1)步的所述多目标优化函数进行求解。(2) Solving according to traditional operations research methods, genetic algorithm or binary particle swarm algorithm can be used to solve the multi-objective optimization function in step (1) of step 3.
本发明的优点和积极效果是:Advantage and positive effect of the present invention are:
1、本发明能够在尽可能恢复负荷供电的前提下,充分发挥分布式电源作用,提高重要负荷供电可靠性,在配网大面积停电后使分布式电源带周围负荷运行,同时在供电恢复过程中尽可能少的减少开关动作次数,供电恢复后尽可能减少网损。1. The present invention can give full play to the role of distributed power supply under the premise of restoring load power supply as much as possible, improve the reliability of power supply for important loads, and make distributed power supply run with surrounding loads after a large-scale power outage in the distribution network. At the same time, during the power supply restoration process Reduce the number of switching actions as little as possible, and reduce the network loss as much as possible after the power supply is restored.
2、本发明专利充分利用了目前配电网按装的分段开关和馈线终端单元(FTU),FTU可以上传分段开关的状态并可控制其通断,在配网发生大面积停电事故后,分布式电源可以带周围负荷继续运行,保证重要负荷不停电,在配网供电恢复过程中减少了开关动作次数,提高分段开关的使用寿命,同时兼顾供电恢复后尽可能减少网损,在网络故障自愈的过程中实现减少负荷损失、减少开关动作次数、减少网损三目标的优化。2. The patent of the present invention makes full use of the subsection switch and feeder terminal unit (FTU) installed in the current distribution network. The FTU can upload the status of the subsection switch and control its on-off. , the distributed power supply can continue to run with surrounding loads, ensuring that important loads do not stop power outages, reducing the number of switching operations during the restoration of distribution network power supply, improving the service life of segmented switches, and at the same time reducing network losses as much as possible after power supply restoration. In the process of network fault self-healing, the optimization of the three goals of reducing load loss, reducing the number of switching operations, and reducing network loss is realized.
3、本发明专利充分利用了目前电网中智能电表应用及其具备运行数据自动采集功能的现实条件,在容量分摊法的基础上提出10kV电网理论线损计算的日运行等效平均负载分摊法,该方法可以很好的解决传统的容量分摊法存在的计算方法简单,计算结果不准确,故不能准确计算线路和变压器损耗量的缺点,适应了目前电网发展的新形势,充分利用了目前电网的用电信息采集系统,大大提高了计算的准确性,且计算量小,推动10kV理论线损计算系统的开发、完善,与传统的方法相比优势明显,具有较好的工程应用价值。3. The patent of the present invention makes full use of the actual conditions of the application of smart meters in the current grid and the automatic collection function of operating data, and proposes the equivalent average load sharing method of daily operation for the calculation of the theoretical line loss of 10kV power grid on the basis of the capacity sharing method. This method can well solve the shortcomings of the traditional capacity apportionment method that the calculation method is simple and the calculation result is inaccurate, so the loss of the line and transformer cannot be accurately calculated. It adapts to the new situation of the current power grid development and makes full use of the current power grid. The power consumption information collection system greatly improves the calculation accuracy, and the calculation amount is small, which promotes the development and improvement of the 10kV theoretical line loss calculation system. Compared with the traditional method, it has obvious advantages and has good engineering application value.
附图说明Description of drawings
图1是本发明实施例的配电网系统正常运行方式连接示意图。Fig. 1 is a schematic diagram of connections of a distribution network system in a normal operation mode according to an embodiment of the present invention.
具体实施方式detailed description
以下结合附图对本发明实施例作进一步详述:Embodiments of the present invention are described in further detail below in conjunction with the accompanying drawings:
在本实施例中,以图1所示的配电网系统为例进行说明,该配电网系统连接有两个分布式电源;其中,DG1、DG2为两个分布式电源;S为配网变电站;1为配网变电站出线断路器,2、3、4......14为分段开关,15、16为分布式电源侧断路器(黑色实心方形代表闭合,空心方形代表断开);一般情况下分段开关处装有FTU,可以远方控制其通断;(1)、(2)......(9)为配电变压器;·为配电变压器开关。In this embodiment, the distribution network system shown in Figure 1 is taken as an example for illustration. The distribution network system is connected with two distributed power sources; where DG1 and DG2 are two distributed power sources; S is the distribution network Substation; 1 is the outlet circuit breaker of the distribution network substation, 2, 3, 4...14 are section switches, 15, 16 are distributed power side circuit breakers (black solid squares represent closed, hollow squares represent open ); in general, FTU is installed at the section switch, which can be remotely controlled on and off; (1), (2)...(9) are distribution transformers; · are distribution transformer switches.
一种含分布式电源的配电网故障后供电恢复方法,包括以下步骤:A power supply recovery method after a fault in a distribution network including a distributed power supply, comprising the following steps:
步骤1、配电网故障出现大面积停电情况后,将不具备孤岛运行能力的分布式电源解列;Step 1. After a large-scale power outage occurs due to a fault in the distribution network, the distributed power generation that does not have the ability to operate in an isolated manner will be disconnected;
在本实施例中,以分段开关2、3、11之间线路发生永久性故障对其进行说明,断路器1断开,图1所示配电网系统全部停电。DG1不具备孤岛运行能力,断开分布式电源侧断路器15,DG1直接与配网解列。In this embodiment, a permanent fault occurs in the line between the section switches 2, 3, and 11, the circuit breaker 1 is turned off, and the power distribution network system shown in Fig. 1 is completely cut off. DG1 does not have the islanding operation capability, disconnect the circuit breaker 15 on the distributed power supply side, and DG1 is directly disconnected from the distribution network.
步骤2、基于分布式电源以最大能力带周围负荷运行的原则,采用搜索方法进行孤岛划分后,将具备孤岛运行能力的分布式电源带周围负荷孤岛运行;Step 2. Based on the principle that the distributed power supply operates with the surrounding load at its maximum capacity, after using the search method to divide the islands, the distributed power supply with the island operation capability is operated with the surrounding loads in an isolated island;
所述孤岛划分的具体步骤包括:The specific steps of the island division include:
(1)以分布式电源为父节点开始,搜索与分布式电源直接相连的所有负荷子节点,将子节点代表的负荷放入待恢复负荷库W;(1) Starting with the distributed power source as the parent node, search for all load child nodes directly connected to the distributed power source, and put the load represented by the child node into the load library W to be restored;
(2)判断待恢复负荷库W是否为空;若不为空,计算待恢复负荷库W中所有负荷的Pnqn,从W中取出Pnqn中最大者对应的负荷m,将负荷m放入预选负荷库V;若为空,预选负荷库V中负荷为分布式电源孤岛运行范围内负荷,孤岛划分成功;(2) Determine whether the load library W to be restored is empty; if it is not empty, calculate the P n q n of all loads in the load library W to be restored, and take out the load m corresponding to the largest P n q n from W, and set Put the load m into the pre-selected load library V; if it is empty, the load in the pre-selected load library V is the load within the operating range of the distributed power island, and the island is divided successfully;
(3)判断分布式电源与预选负荷库V中的负荷是否满足如式(1)所示的约束条件;若不满足,则从预选负荷库V中去除负荷m,跳转至步骤2的第(2)步;若满足,则跳转至步骤2的第(4)步;(3) Determine whether the distributed power supply and the load in the preselected load library V meet the constraint conditions shown in formula (1); if not, remove the load m from the preselected load library V, and jump to step 2. (2) step; if satisfied, then jump to step (4) of step 2;
其中,PDG、QDG分别为分布式电源带有功、无功负荷能力;Pi、Pn分别为负荷i、n的有功负荷;Qi为负荷i的无功负荷;i为V中负荷;qn为根据负荷n的重要程度,也即负荷n分配的权重因子;n为W中负荷;Among them, P DG , Q DG are distributed power generation with power and reactive load capacity respectively; P i , P n are active loads of load i and n respectively; Q i is reactive load of load i; i is load in V ;q n is the weight factor assigned according to the importance of load n, that is, load n; n is the load in W;
(4)判断分布式电源与预选负荷库V形成的网络是否满足如式(2)所示的约束条件;若满足,则以负荷m为父节点开始,搜索与负荷m直接相连的所有负荷子节点,将子节点代表的负荷放入待恢复负荷库W,跳转至步骤2的第(2)步;若不满足式(2)所示的约束条件,则从预选负荷库V中取出负荷m,跳转至步骤2的第(2)步;(4) Determine whether the network formed by the distributed power supply and the pre-selected load library V satisfies the constraints shown in formula (2); if so, start with the load m as the parent node, and search for all load sub-nodes directly connected to the load m node, put the load represented by the child node into the load library W to be restored, and jump to step (2) of step 2; if the constraint conditions shown in formula (2) are not met, take the load from the pre-selected load library V m, jump to step (2) of step 2;
其中,第一个约束式为支路电流约束,Imax_bij为线路bij的最大传输电流;第二个约束式为节点电压约束,Ui为预选负荷库V中负荷i的电压,Umax、Umin分别为预选负荷库V中负荷i的最大、最小允许电压。Among them, the first constraint is the branch current constraint, I max_bij is the maximum transmission current of the line bij; the second constraint is the node voltage constraint, U i is the voltage of load i in the pre-selected load library V, U max , U min are the maximum and minimum allowable voltages of load i in the pre-selected load library V, respectively.
在本实施例中,如图1所示,DG2具备孤岛运行能力,通过孤岛划分,DG2带负荷(6)(2)(3)(4)孤岛运行,开关8、4、7断开。In this embodiment, as shown in FIG. 1 , DG2 has the capability of island operation. Through island division, DG2 operates in an island with load (6)(2)(3)(4), and switches 8, 4, and 7 are turned off.
步骤3、隔离故障点,恢复剩余健全网络的供电;Step 3. Isolate the fault point and restore the power supply of the remaining sound network;
所述步骤3的具体步骤包括:The concrete steps of described step 3 include:
(1)分别建立以恢复供电后负荷损失最少、开关动作次数最少和网损最少的多目标优化函数,该多目标优化函数如式(3)所示,对于最后的供电恢复方案优先考虑负荷损失最少的方案,其次考虑开关动作次,最次考虑网损。(1) Establish the multi-objective optimization function with the least load loss, the least number of switching actions, and the least network loss after the restoration of power supply. The least scheme, the second is the switching action, and the last is the network loss.
其中,f1、f2、f3分别代表负荷损失函数、开关动作次数函数、网损函数;PBL为断电区域内负荷大小与其对应的权系数相乘后的和;Y为除孤岛区域剩余网络负荷节点的集合;Py为负荷y的有功负荷;qy为根据负荷y的重要程度为负荷y分配的权重因子,负荷越重要其权系数越大;Ss为分段开关集合;Ts为故障前联络开关集合;Kk为开关状态,0代表断开,1代表闭合;Ploss为除孤岛部分网损。Among them, f 1 , f 2 , and f 3 respectively represent the load loss function, the switching action times function, and the network loss function; P BL is the sum of the multiplication of the load size in the power-off area and its corresponding weight coefficient; Y is the area except for isolated islands The set of remaining network load nodes; P y is the active load of load y; q y is the weight factor assigned to load y according to the importance of load y, the more important the load, the greater the weight coefficient; S s is the set of segmented switches; T s is the set of contact switches before failure; K k is the switch state, 0 means open, 1 means closed; P loss is the network loss except for the isolated island.
其约束条件如式(4)所示:Its constraints are shown in formula (4):
其中,第一个约束式为支路容量约束;Smax_b为线路b的最大传输容量;α为裕度系数;第二个约束式为电能质量之电压约束;U’y为剩余网络节点y的电压;U’max、U’min为最大、最小允许电压;第三个约束式为配电网结构约束;g为剩余网络供电恢复后的网络结构;GR为由剩余网络节点支路组成的所有可能的辐射状网络结构的集合。Among them, the first constraint is the branch capacity constraint; S max_b is the maximum transmission capacity of line b; α is the margin coefficient; the second constraint is the voltage constraint of power quality; U' y is the remaining network node y voltage; U' max and U' min are the maximum and minimum allowable voltages; the third constraint is the distribution network structure constraint; g is the network structure after the power supply of the remaining network is restored; G R is the network structure composed of the remaining network node branches The set of all possible radial network structures.
(2)根据传统的运筹学方法进行求解、可采用遗传算法或二进制粒子群算法对步骤(1)中的所述多目标优化函数进行求解。(2) Solving according to the traditional operations research method, genetic algorithm or binary particle swarm optimization algorithm can be used to solve the multi-objective optimization function in step (1).
在本实施例中,图1中2、3、11开关断开,隔离故障点,合上断路器1。In this embodiment, switches 2, 3, and 11 in FIG. 1 are turned off to isolate the fault point, and the circuit breaker 1 is turned on.
步骤4、具备并网条件的分布式电源或者孤岛并网运行,不具备并网条件的孤岛继续孤岛运行。Step 4. Distributed power sources with grid-connected conditions or isolated islands are connected to the grid, and isolated islands that do not have grid-connected conditions continue to operate in isolation.
在本实施例中,如图1所示,孤岛具备并网运行条件,合上开关8孤岛并网运行;依次合上开关4、7、14恢复(1)(5)(7)(8)(9)负荷供电;DG1具备并网条件,合上断路器15,DG1并网运行。In this embodiment, as shown in Figure 1, the isolated island has the conditions for grid-connected operation, and switch 8 is closed for isolated island grid-connected operation; switches 4, 7, and 14 are closed sequentially to restore (1)(5)(7)(8) (9) Load power supply; DG1 has the conditions for grid connection, close the circuit breaker 15, and DG1 runs in grid connection.
需要强调的是,本发明所述的实施例是说明性的,而不是限定性的,因此本发明包括并不限于具体实施方式中所述的实施例,凡是由本领域技术人员根据本发明的技术方案得出的其他实施方式,同样属于本发明保护的范围。It should be emphasized that the embodiments described in the present invention are illustrative rather than restrictive, so the present invention includes but not limited to the embodiments described in the specific implementation manner, and those skilled in the art according to the technology of the present invention Other implementations derived from the scheme also belong to the protection scope of the present invention.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610828635.XA CN106374456A (en) | 2016-09-14 | 2016-09-14 | A power supply recovery method after a fault in a distribution network with distributed power |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610828635.XA CN106374456A (en) | 2016-09-14 | 2016-09-14 | A power supply recovery method after a fault in a distribution network with distributed power |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106374456A true CN106374456A (en) | 2017-02-01 |
Family
ID=57897643
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610828635.XA Pending CN106374456A (en) | 2016-09-14 | 2016-09-14 | A power supply recovery method after a fault in a distribution network with distributed power |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106374456A (en) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107292516A (en) * | 2017-06-21 | 2017-10-24 | 合肥工业大学 | It is a kind of to count and load rating and the load reliability estimation method of energy scheduling |
CN107492906A (en) * | 2017-08-24 | 2017-12-19 | 南京南瑞继保电气有限公司 | A kind of active distribution network isolated island division methods based on custom power service |
CN108365604A (en) * | 2018-03-02 | 2018-08-03 | 浙江大学 | A kind of two benches distribution network failure restoration methods counted and microgrid accesses |
CN108988322A (en) * | 2018-06-30 | 2018-12-11 | 南京理工大学 | The microgrid optimization of operation strategy method of consideration system time variation |
CN109120009A (en) * | 2018-09-11 | 2019-01-01 | 国网天津市电力公司电力科学研究院 | The active distribution network fault recovery method that meter and distributed generation resource power output change at random |
CN109449945A (en) * | 2018-11-22 | 2019-03-08 | 国网四川省电力公司天府新区供电公司 | Power distribution network based on the DG 10kV Alloy White Iron constraint adjusted turns for optimization method |
CN109683036A (en) * | 2018-11-29 | 2019-04-26 | 国家计算机网络与信息安全管理中心 | A kind of distribution system failure simulation method and system for data center |
CN110112778A (en) * | 2019-05-14 | 2019-08-09 | 四川大学 | A kind of Distributed Power Resource networking method of supplying power to damaged on a large scale for power grid and system |
CN110518572A (en) * | 2019-07-12 | 2019-11-29 | 国网浙江省电力有限公司杭州供电公司 | A kind of power distribution network isolated island division methods based on minimum load loss |
CN110635475A (en) * | 2019-09-29 | 2019-12-31 | 国网山东省电力公司济南市历城区供电公司 | A Distributed Power Supply Restoration System for Intelligent Distribution Network |
CN115079571A (en) * | 2022-06-27 | 2022-09-20 | 燕山大学 | Intelligent optimization control method for satellite power supply fault reconstruction based on wild goat algorithm |
CN116961104A (en) * | 2023-07-31 | 2023-10-27 | 国网上海市电力公司 | A self-healing method and system for diamond distribution network containing distributed power sources |
CN117674115A (en) * | 2023-12-05 | 2024-03-08 | 国网四川省电力公司 | Method and system for recovering power supply load after fault of power distribution network containing distributed power supply |
CN117913818A (en) * | 2024-01-24 | 2024-04-19 | 广东电网有限责任公司广州供电局 | Mutual-aid operation optimization method for feeder groups of power distribution network |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105281344A (en) * | 2015-11-20 | 2016-01-27 | 武汉大学 | Smart distribution network self-restoration optimization method considering power quality and uncertainty constraint thereof |
-
2016
- 2016-09-14 CN CN201610828635.XA patent/CN106374456A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105281344A (en) * | 2015-11-20 | 2016-01-27 | 武汉大学 | Smart distribution network self-restoration optimization method considering power quality and uncertainty constraint thereof |
Non-Patent Citations (2)
Title |
---|
崇志强: "分布式发电条件下配电网故障定位与供电恢复策略研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 * |
王旭东等: "含分布式发电配电系统的孤岛划分", 《中国科学》 * |
Cited By (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107292516B (en) * | 2017-06-21 | 2019-12-27 | 合肥工业大学 | Load reliability assessment method considering load classification and energy scheduling |
CN107292516A (en) * | 2017-06-21 | 2017-10-24 | 合肥工业大学 | It is a kind of to count and load rating and the load reliability estimation method of energy scheduling |
CN107492906A (en) * | 2017-08-24 | 2017-12-19 | 南京南瑞继保电气有限公司 | A kind of active distribution network isolated island division methods based on custom power service |
CN108365604A (en) * | 2018-03-02 | 2018-08-03 | 浙江大学 | A kind of two benches distribution network failure restoration methods counted and microgrid accesses |
CN108365604B (en) * | 2018-03-02 | 2021-09-17 | 浙江大学 | Two-stage power distribution network fault recovery method considering microgrid access |
CN108988322A (en) * | 2018-06-30 | 2018-12-11 | 南京理工大学 | The microgrid optimization of operation strategy method of consideration system time variation |
CN109120009A (en) * | 2018-09-11 | 2019-01-01 | 国网天津市电力公司电力科学研究院 | The active distribution network fault recovery method that meter and distributed generation resource power output change at random |
CN109449945A (en) * | 2018-11-22 | 2019-03-08 | 国网四川省电力公司天府新区供电公司 | Power distribution network based on the DG 10kV Alloy White Iron constraint adjusted turns for optimization method |
CN109683036A (en) * | 2018-11-29 | 2019-04-26 | 国家计算机网络与信息安全管理中心 | A kind of distribution system failure simulation method and system for data center |
CN109683036B (en) * | 2018-11-29 | 2021-06-29 | 国家计算机网络与信息安全管理中心 | Power distribution system fault simulation method and system for data center |
CN110112778A (en) * | 2019-05-14 | 2019-08-09 | 四川大学 | A kind of Distributed Power Resource networking method of supplying power to damaged on a large scale for power grid and system |
CN110112778B (en) * | 2019-05-14 | 2020-05-19 | 四川大学 | Distributed energy networking power supply method and system for large-scale destruction of power grid |
CN110518572A (en) * | 2019-07-12 | 2019-11-29 | 国网浙江省电力有限公司杭州供电公司 | A kind of power distribution network isolated island division methods based on minimum load loss |
CN110635475A (en) * | 2019-09-29 | 2019-12-31 | 国网山东省电力公司济南市历城区供电公司 | A Distributed Power Supply Restoration System for Intelligent Distribution Network |
CN115079571A (en) * | 2022-06-27 | 2022-09-20 | 燕山大学 | Intelligent optimization control method for satellite power supply fault reconstruction based on wild goat algorithm |
CN115079571B (en) * | 2022-06-27 | 2022-12-30 | 燕山大学 | Intelligent optimization control method for satellite power supply fault reconstruction based on wild goat algorithm |
CN116961104A (en) * | 2023-07-31 | 2023-10-27 | 国网上海市电力公司 | A self-healing method and system for diamond distribution network containing distributed power sources |
CN116961104B (en) * | 2023-07-31 | 2024-04-19 | 国网上海市电力公司 | A self-healing method and system for a diamond distribution network containing distributed power sources |
CN117674115A (en) * | 2023-12-05 | 2024-03-08 | 国网四川省电力公司 | Method and system for recovering power supply load after fault of power distribution network containing distributed power supply |
CN117674115B (en) * | 2023-12-05 | 2024-08-06 | 国网四川省电力公司 | Method and system for restoring power supply load after failure of distribution network containing distributed power source |
CN117913818A (en) * | 2024-01-24 | 2024-04-19 | 广东电网有限责任公司广州供电局 | Mutual-aid operation optimization method for feeder groups of power distribution network |
CN117913818B (en) * | 2024-01-24 | 2024-10-11 | 广东电网有限责任公司广州供电局 | Mutual-aid operation optimization method for feeder groups of power distribution network |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106374456A (en) | A power supply recovery method after a fault in a distribution network with distributed power | |
CN110994612B (en) | A rapid recovery method for distribution network faults based on network topology partition and layering | |
CN102088209B (en) | Self-healing control method of distribution network | |
CN108988322B (en) | Optimization method of microgrid operation strategy considering system time-varying | |
CN104037765B (en) | A Method of Selecting Power Supply Restoration Scheme of Active Distribution Network Based on Improved Genetic Algorithm | |
CN104934964B (en) | A kind of power distribution network reconfiguration and isolated island division methods containing distributed power source | |
Jian et al. | A review of control strategies for DC micro-grid | |
CN102496937A (en) | Fault recovery method applied to intelligent distribution network and based on load balance | |
CN107749620A (en) | A kind of method of service restoration containing distributed power distribution network | |
CN103812131A (en) | Multi-agent-based urban power grid isolated island black-start system and method | |
CN106532684A (en) | Active distribution network multi-fault repair method based on multi-agent system | |
CN106981875A (en) | The restoration methods of distribution network failure containing DG of meter and plan isolated island | |
CN103078391A (en) | Power distribution network power supply power restoration method based on photovoltaic power generation system | |
CN103532133B (en) | MAS-based load transfer system and method for 35kV distribution network faults | |
CN105244912A (en) | Method for active power distribution network island power supply recovery and black-start | |
CN116826725A (en) | Multi-objective fault power supply recovery method for substation-oriented medium-voltage distribution power supply area (S-SCDN) feeder line group FC | |
CN115995807A (en) | Multi-period power supply elastic improvement method for distribution network based on disaster prediction | |
CN103457345A (en) | Control device and control method for supplying power to fault region in regional power grid | |
CN115333150A (en) | A fault recovery method for distribution network with distributed power generation under anti-islanding protection | |
CN106026047A (en) | Optimized control method of high-reliability distribution automation based on multi-source coordination and cooperation | |
CN104348131B (en) | A recovery system and method based on 35kV power failure of intelligent distribution network | |
CN107294086A (en) | The service restoration method realized based on network equivalent and parallelization | |
CN117543561A (en) | A method for ensuring supply of flexible power distribution systems in collaboration with virtual power plants | |
CN103532109B (en) | A kind of for the distribution network failure restoration methods containing microgrid | |
CN115776149A (en) | A flexible intelligent battery management system, method, device and electronic equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170201 |
|
RJ01 | Rejection of invention patent application after publication |