CN106368426B - A kind of auxiliary shoring system of super high-rise building climbing equipment - Google Patents

A kind of auxiliary shoring system of super high-rise building climbing equipment Download PDF

Info

Publication number
CN106368426B
CN106368426B CN201610890917.2A CN201610890917A CN106368426B CN 106368426 B CN106368426 B CN 106368426B CN 201610890917 A CN201610890917 A CN 201610890917A CN 106368426 B CN106368426 B CN 106368426B
Authority
CN
China
Prior art keywords
temporary structure
structure beam
column
steel
rise building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610890917.2A
Other languages
Chinese (zh)
Other versions
CN106368426A (en
Inventor
龚震
陆秋平
赵晗
孙宇杰
龚寅
赵征
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201610890917.2A priority Critical patent/CN106368426B/en
Publication of CN106368426A publication Critical patent/CN106368426A/en
Application granted granted Critical
Publication of CN106368426B publication Critical patent/CN106368426B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of auxiliary shoring systems of super high-rise building climbing equipment, set on shear wall absent region, including and each floor is corresponding and both ends are erected on respectively on two heel post of shear wall absent region temporary structure beam, on the temporary structure beam and upper end and the corresponding lattice column of support bracket, be embedded in the temporary structure beam and steel corresponding with the column that climbs is pedaled.The column that climbs is supported by the way that temporary structure beam corresponding with each floor is arranged, the setting lattice column corresponding with support bracket on temporary structure beam, effectively bear the load of support bracket, steel corresponding with the column that climbs is buried in temporary structure beam to pedal, when temporary structure beam is not up to specified intensity, play the role of dispersion to climb the load of column, supporting & stablizing of the present invention, later period dismounting amount is small, material after dismounting is reusable, engineering cost is low, ensure that being normally carried out for whole work of climbing.

Description

A kind of auxiliary shoring system of super high-rise building climbing equipment
Technical field
The present invention relates to super high-rise building temporary support fields, and in particular to a kind of auxiliary of super high-rise building climbing equipment Support system.
Background technique
Currently, the continuous renewal of construction techniques, new material largely makes with the rapid development of modern architecture industry With more and more executive information systems are just many to rise sheer from level ground.And in the construction of super high-rise building, it is whole to be promoted Steel platform construction technology is just more and more being applied in core wall structure construction, its working principle is that climbing by top Column carries out whole work of climbing, and the lotus of the entire steel platform of structural shear wall inner support is then put in by the support bracket of lower part It carries.But the diversity using function of super high-rise building, upper layer are generally used as luxurious hotel, the pattern of structure has one Fixed variation --- structural andlysis missing.Resulting problem be exactly shear wall deleted areas it is original climb column and under Portion's bracket does not support reliably, and the column position that climbs differs larger with the position absolute altitude of lower support bracket, influences Whole work of climbing is normally carried out.
Summary of the invention
The present invention provides a kind of auxiliary shoring systems of super high-rise building climbing equipment, to solve to exist in the prior art Shear wall deleted areas original climb column and lower part bracket does not have the problem of secure support.
In order to solve the above-mentioned technical problem, the technical scheme is that a kind of auxiliary of super high-rise building climbing equipment Support system is set to shear wall absent region, including corresponding and both ends are erected on the shear wall missing respectively with each floor Temporary structure beam on two heel post of region, be set on the temporary structure beam and upper end lattice column corresponding with bracket is supported, It is embedded in the temporary structure beam and steel corresponding with the column that climbs is pedaled.
Further, the lower end of the lattice column is fixed on the temporary structure beam by built-in fitting, and upper end is equipped with water Flat support plate.
Further, the built-in fitting include the dowel being embedded in the temporary structure beam and be set to the dowel top Connecting plate.
Further, the lattice column includes angle steel and batten plate, and the angle steel and the connecting plate of the lattice column lower end weld Connect fixation.
Further, the steel is pedaled including upper and lower two pieces of iron plates and the I-steel between two pieces of iron plates, described The iron plate of I-steel and lower section is embedded in the temporary structure beam, and the iron plate of top and the upper surface of the temporary structure beam are neat It is flat.
Further, there are two the I-steel is set, the upper and lower ends of each I-steel and iron plate welding are solid It is fixed.
It further, further include the framed bent system being set between the temporary structure beam of two neighboring floor, the framed bent body System includes several framed bents disposed in parallel.
Further, framed bent density of the framed bent system at the column that climbs is greater than far from the column that climbs The framed bent density at place.
Further, each framed bent includes steel pipe and the jacking above the steel pipe.
Further, the temporary structure beam is formed using concreting.
The auxiliary shoring system of super high-rise building climbing equipment provided by the invention is set to shear wall absent region, including Corresponding and both ends are erected on temporary structure beam on two heel post of shear wall absent region respectively, are set to institute with each floor State on temporary structure beam and upper end and the corresponding lattice column of support bracket, be embedded in the temporary structure beam and with the column that climbs Corresponding steel is pedaled.The column that climbs is supported by the way that temporary structure beam corresponding with each floor is arranged, in temporary structure beam Upper setting lattice column corresponding with bracket is supported, effectively bears the load of support bracket, buries and climb in temporary structure beam It rises the corresponding steel of column to pedal, when temporary structure beam is not up to specified intensity, plays the role of dispersion and climb the load of column, this Invention supporting & stablizing, later period dismounting amount is small, and the material after dismounting is reusable, and engineering cost is low, ensure that whole work of climbing That makees is normally carried out.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the auxiliary shoring system of super high-rise building climbing equipment of the present invention;
Fig. 2 is the support schematic diagram of framed bent system of the present invention;
Fig. 3 is the support concept figure of the auxiliary shoring system of super high-rise building climbing equipment of the present invention;
Fig. 4 is the connection schematic diagram of lattice column and built-in fitting of the present invention;
Fig. 5 is the structural schematic diagram that steel of the present invention is pedaled.
It is as shown in the figure: 1, column;2, temporary structure beam;3, lattice column;31, angle steel;32, batten plate;4, steel is pedaled;41, iron plate; 42, I-steel;5, built-in fitting;51, dowel;52, connecting plate;6, horizontal supporting plate;7, framed bent;71, steel pipe;72, jacking;8, it climbs Rise column;9, bracket is supported.
Specific embodiment
The present invention is described in detail with reference to the accompanying drawing:
As shown in Figure 1-3, being set to shearing the present invention provides a kind of auxiliary shoring system of super high-rise building climbing equipment Wall absent region is erected on two heel post 1 of shear wall absent region respectively including the corresponding and both ends with each floor Temporary structure beam 2 on the temporary structure beam 2 and upper end and the corresponding lattice column 3 of support bracket 9, is embedded in described face When structural beams 2 in and steel corresponding with the column 8 that climbs pedal 4.Preferably, the temporary structure beam is formed using concreting. Specifically, each floor in shear wall absent region is respectively provided with the temporary structure beam 2, to climbing, column 8 is effectively supported, Since the position for the column 8 that climbs differs larger with the position of support bracket 9, setting and branch on temporary structure beam 2 The corresponding lattice column 3 of bracket 9 is supportted, the height of lattice column 3 is designed according to the position of action point of support bracket 9, for bearing The load of bracket 9 is supported, in addition, burying steel corresponding with the column 8 that climbs in temporary structure beam 2 pedals 4, when temporary structure beam 2 Not up to specified intensity when, play the role of dispersion and climb the load of column 8, further ensure stability of strutting system.
As shown in figure 4, the lower end of the lattice column 3 is fixed on the temporary structure beam 2 by built-in fitting 5, upper end is set There is horizontal supporting plate 6, which can be iron plate, play raising forced area, preferably bear support 9 lotus of bracket The effect of load.
Please continue to refer to Fig. 3-4, the built-in fitting 5 includes the dowel 51 being embedded in the temporary structure beam 2 and is set to The connecting plate 52 on 51 top of dowel, the connecting plate 52 are iron plate, and built-in fitting 5 is fixed on temporary structure beam 2 by dowel 51 In, top passes through the fixed lattice column 3 of connecting plate 52.Preferably, the lattice column 3 includes angle steel 31 and batten plate 32, wherein angle steel 31 are primarily subjected to axial force, the main lateral force resisting of batten plate 32, wherein the angle steel 31 of 2 lower end of the lattice column and the connecting plate 52 are welded and fixed, specifically, angle steel 31 is fixed with connecting plate 52 by fillet welding.
As shown in figure 5, it includes upper and lower two pieces of iron plates 41 and the I-steel between two pieces of iron plates 41 that the steel, which pedals 4, 42, the iron plate 41 of the I-steel 42 and lower section is embedded in the temporary structure beam 2, the iron plate 41 of top and the interim knot The upper surface of structure beam 2 flushes.Preferably, there are two the I-steel 42 is set, the upper and lower ends of each I-steel 42 and institute It states iron plate 41 to be welded and fixed, specifically, fixing between I-steel 42 and iron plate 41 by fillet welding.
Please continue to refer to Fig. 2, which further includes between the temporary structure beam of two neighboring floor Framed bent system, the framed bent system include several framed bents disposed in parallel 7.Preferably, the framed bent system is climbed close to described Framed bent density at column 8 is greater than far from the framed bent density at the column 8 that climbs, for column 8 and the support bracket 9 of climbing Load be successively transferred to lower section permanent structure.Preferably, each framed bent 7 including steel pipe 71 and is set to the steel pipe 71 The jacking 72 of top, the bottom end of steel pipe 72 are vertical on the temporary structure beam 2 of lower layer, and the bottom end of top and jacking 72 is fixed to be connected It connects, the top of jacking 72 and the temporary structure beam 2 on upper layer are in close contact.
In conclusion the auxiliary shoring system of super high-rise building climbing equipment provided by the invention, is set to shear wall and lacks Region is erected on the interim knot on two heel post 1 of shear wall absent region including the corresponding and both ends with each floor respectively Structure beam 2 on the temporary structure beam 2 and upper end and the corresponding lattice column 3 of support bracket 9, is embedded in the temporary structure In beam 2 and steel corresponding with the column 8 that climbs pedals 4.By the way that corresponding with each floor temporary structure beam 2 is arranged to the column 8 that climbs It is supported, setting lattice column 3 corresponding with support bracket 9, effectively bears the load of support bracket 9 on temporary structure beam 2 Lotus buries steel corresponding with the column 8 that climbs in temporary structure beam 2 and pedals 4, when temporary structure beam 2 is not up to specified intensity, rises It climbs the effect of the load of column 8 to dispersion, supporting & stablizing of the present invention, later period dismounting amount is small, the repeatable benefit of the material after dismounting With engineering cost is low, ensure that being normally carried out for whole work of climbing.
Although embodiments of the present invention are illustrated in specification, these embodiments are intended only as prompting, It should not limit protection scope of the present invention.It is equal that various omission, substitution, and alteration are carried out without departing from the spirit and scope of the present invention It should be included within the scope of the present invention.

Claims (9)

1. a kind of auxiliary shoring system of super high-rise building climbing equipment is set to shear wall absent region, which is characterized in that including With each floor corresponding and both ends be erected on respectively temporary structure beam (2) on two heel post of shear wall absent region (1), On the temporary structure beam (2) and upper end and support bracket (9) corresponding lattice column (3), it is embedded in the temporary structure In beam (2) and steel corresponding with the column that climbs (8) pedals (4), further includes between the temporary structure beam (2) of two neighboring floor Framed bent system, the framed bent system includes several framed bents disposed in parallel (7).
2. the auxiliary shoring system of super high-rise building climbing equipment according to claim 1, which is characterized in that the lattice The lower end of column (3) is fixed on the temporary structure beam (2) by built-in fitting (5), and upper end is equipped with horizontal supporting plate (6).
3. the auxiliary shoring system of super high-rise building climbing equipment according to claim 2, which is characterized in that described pre-buried Part (5) includes the dowel (51) being embedded in the temporary structure beam (2) and the connecting plate for being set to the dowel (51) top (52)。
4. the auxiliary shoring system of super high-rise building climbing equipment according to claim 3, which is characterized in that the lattice Column (3) includes angle steel (31) and batten plate (32), and the angle steel (31) of lattice column (3) lower end and the connecting plate (52) welding are solid It is fixed.
5. the auxiliary shoring system of super high-rise building climbing equipment according to claim 1, which is characterized in that the steel is pedaled (4) I-steel (42) for including upper and lower two pieces of iron plates (41) and being set between two pieces of iron plates (41), the I-steel (42) It is embedded in the temporary structure beam (2) with the iron plate (41) of lower section, the iron plate (41) of top and the temporary structure beam (2) Upper surface flushes.
6. the auxiliary shoring system of super high-rise building climbing equipment according to claim 5, which is characterized in that the I-shaped There are two steel (42) is set, the upper and lower ends of each I-steel (42) are welded and fixed with the iron plate (41).
7. the auxiliary shoring system of super high-rise building climbing equipment according to claim 1, which is characterized in that the framed bent System is greater than close to the framed bent density climbed at column (8) far from the framed bent density climbed at column (8).
8. the auxiliary shoring system of super high-rise building climbing equipment according to claim 1, which is characterized in that each described Framed bent (7) includes steel pipe (71) and the jacking (72) above the steel pipe (71).
9. the auxiliary shoring system of super high-rise building climbing equipment according to claim 1, which is characterized in that described interim Structural beams (2) are formed using concreting.
CN201610890917.2A 2016-10-12 2016-10-12 A kind of auxiliary shoring system of super high-rise building climbing equipment Active CN106368426B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610890917.2A CN106368426B (en) 2016-10-12 2016-10-12 A kind of auxiliary shoring system of super high-rise building climbing equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610890917.2A CN106368426B (en) 2016-10-12 2016-10-12 A kind of auxiliary shoring system of super high-rise building climbing equipment

Publications (2)

Publication Number Publication Date
CN106368426A CN106368426A (en) 2017-02-01
CN106368426B true CN106368426B (en) 2018-12-18

Family

ID=57896569

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610890917.2A Active CN106368426B (en) 2016-10-12 2016-10-12 A kind of auxiliary shoring system of super high-rise building climbing equipment

Country Status (1)

Country Link
CN (1) CN106368426B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112789486B (en) * 2019-07-05 2024-03-08 林振宇 Force and inclination monitoring system with self-locating identification
CN113216591B (en) * 2021-05-13 2022-09-30 中建一局集团建设发展有限公司 Climbing formwork climbing auxiliary steel structure and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101967880A (en) * 2010-10-29 2011-02-09 中建三局第三建设工程有限责任公司 Standardized lattice column for low jack-up formwork system
CN102677889A (en) * 2012-05-11 2012-09-19 上海建工集团股份有限公司 System for alternatively supporting whole lifting steel platform formwork by steel column casing rack and construction method
CN103979433A (en) * 2014-05-26 2014-08-13 上海市机械施工集团有限公司 Method for climbing of tower crane in construction process
CN105672694A (en) * 2016-04-06 2016-06-15 中国建筑第八工程局有限公司 Lifting platform box girder support structure for super high-rise buildings and construction method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110016660A (en) * 2009-08-12 2011-02-18 상진건설(주) Temporary frame for both frame and exterior finishing construction and frame and exterior finishing method using it

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101967880A (en) * 2010-10-29 2011-02-09 中建三局第三建设工程有限责任公司 Standardized lattice column for low jack-up formwork system
CN102677889A (en) * 2012-05-11 2012-09-19 上海建工集团股份有限公司 System for alternatively supporting whole lifting steel platform formwork by steel column casing rack and construction method
CN103979433A (en) * 2014-05-26 2014-08-13 上海市机械施工集团有限公司 Method for climbing of tower crane in construction process
CN105672694A (en) * 2016-04-06 2016-06-15 中国建筑第八工程局有限公司 Lifting platform box girder support structure for super high-rise buildings and construction method thereof

Also Published As

Publication number Publication date
CN106368426A (en) 2017-02-01

Similar Documents

Publication Publication Date Title
CN104389419B (en) Encorbelment and prop up mould structure for mounting platform and a constructional method
CN103437300A (en) Construction method for erecting double cantilevers for pier top steel beam without pier-side bracket
CN104480922B (en) Space truss formwork system and construction method thereof
US20120047822A1 (en) Earthquake force absorption system
CN101240550A (en) Construction method for lattice type steel column tower crane pedestal
CN105544398A (en) Horizontal force self-balancing type splayed heavy type upper air support system and installation method thereof
KR101026012B1 (en) Bridge deck dismantling method using lifting jack integrated with bridge
CN103866693A (en) Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN107245953B (en) A kind of crossed construction method of multilayer bridge structure
CN106368426B (en) A kind of auxiliary shoring system of super high-rise building climbing equipment
CN107227814A (en) Sectional construction method for large cantilever concrete structure
CN212507296U (en) High formwork system
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN103132640B (en) Detachable steel-concrete composite floor
CN109653517A (en) A kind of multidirectional Load Relief System and the construction method with the system assembly steel vestibule
CN104831928B (en) High-altitude long-span concrete conjoined structure shuttering supporting steel platform construction method
CN103485350B (en) The method of attachment of the steel supporting system raised and the collar tie beam that bears down on one
CN106121238A (en) High-altitude concrete conveying device
CN213805443U (en) Steel construction, frame beam structure, side slope reinforced structure and reinforcement and support structure
CN105155867B (en) A kind of underpinning device of the existing large diameter pile building of Tunnel Passing
CN204940916U (en) A kind of Super High Core Walls Structure emergency escape passage
JP6334970B2 (en) Temporary support method for foundation
JP6368570B2 (en) Existing building reinforcement structure
CN208717939U (en) A kind of efficiently molding building hoist foundation structure
CN108104136B (en) Foundation pit supporting structure and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant