CN106368127A - Whole support landing device and method for box girder support - Google Patents

Whole support landing device and method for box girder support Download PDF

Info

Publication number
CN106368127A
CN106368127A CN201610980449.8A CN201610980449A CN106368127A CN 106368127 A CN106368127 A CN 106368127A CN 201610980449 A CN201610980449 A CN 201610980449A CN 106368127 A CN106368127 A CN 106368127A
Authority
CN
China
Prior art keywords
suspender
box girder
double
nut
boom
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610980449.8A
Other languages
Chinese (zh)
Inventor
唐璜
王健
雷进发
于长波
唐丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Engineering Co Ltd of CREC
Sixth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Original Assignee
Shanghai Civil Engineering Co Ltd of CREC
Sixth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Engineering Co Ltd of CREC, Sixth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC filed Critical Shanghai Civil Engineering Co Ltd of CREC
Priority to CN201610980449.8A priority Critical patent/CN106368127A/en
Publication of CN106368127A publication Critical patent/CN106368127A/en
Pending legal-status Critical Current

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及桥梁施工技术领域,具体是一种适用于现浇箱梁贝雷膺架施工的箱梁支架的落架装置,包括落架砂筒、底横梁、贝雷支架、上拖梁、连接面板、吊杆及分离式螺母,所述的底横梁下部设有落架砂筒,上部设有贝雷支架,所述的贝雷支架底部与底横梁之间相接并置于混凝土梁体下方,吊杆垂直贯穿于梁体预留孔内,吊杆的上端采用分离式螺母与上托梁连接,吊杆中部采用分离式螺母与双层钢垫板固定于连接面板上,吊杆的底部采用双螺母固定于底横梁上,混凝土梁体上方置有机械千斤顶所述的机械千斤顶反复升降将其上部设有的上托梁循环复位、下降来实现整体落架。本装置可降低安全风险、提高工效,具有较高的应用和推广价值。

The invention relates to the technical field of bridge construction, in particular to a drop frame device for box girder brackets suitable for the construction of cast-in-place box girder Bailey frames, including drop frame sand cylinders, bottom beams, Bailey brackets, upper drag beams, connecting panels, and suspenders and separate nuts, the lower part of the bottom beam is provided with a drop frame sand cylinder, and the upper part is provided with a Bailey bracket. In the reserved hole of the beam body, the upper end of the suspender is connected to the upper joist with a separate nut, the middle part of the suspender is fixed on the connecting panel with a separate nut and a double-layer steel backing plate, and the bottom of the suspender is fixed with double nuts On the bottom beam, a mechanical jack is placed above the concrete beam body. The mechanical jack repeatedly lifts and resets and descends the upper joist provided on the top to realize the overall fall. The device can reduce safety risks, improve work efficiency, and has high application and popularization value.

Description

一种箱梁支架整体落架装置及方法A device and method for integral drop frame of box girder support

[技术领域][technical field]

本发明涉及桥梁施工技术领域,具体来说是一种适用于现浇箱梁贝雷膺架施工的箱梁支架的落架装置及方法。The invention relates to the technical field of bridge construction, in particular to a frame drop device and method for a box girder support suitable for the construction of a cast-in-place box girder Bailey frame.

[背景技术][Background technique]

随着我国经济的发展,桥梁建设进入了全面发展阶段。国家的“十二五”规划提出了向低碳经济转型,桥梁工程的施工工法也必须紧跟脚步。现浇箱梁整体落架施工技术在国内外的桥梁施工中应用较多,目前现浇箱梁模板支架体系多采用吊车直接拆除,受周围地形环境和场地操作空间限制,该施工方法施工难度较大,且严重违反安全起重吊装规程,存在较大安全隐患,还存在安装拆除成本高、工效低的问题,而在具有一定高度的现浇箱梁或受空间限制的现浇箱梁施工中,尚无经济可靠的支架拆除方法可供借鉴。With the development of my country's economy, bridge construction has entered a stage of comprehensive development. The country's "Twelfth Five-Year Plan" proposes the transition to a low-carbon economy, and the construction methods of bridge projects must also keep pace. The cast-in-place box girder overall drop frame construction technology is widely used in bridge construction at home and abroad. At present, the cast-in-place box girder formwork support system is mostly directly dismantled by a crane. Due to the surrounding terrain environment and site operating space constraints, this construction method is difficult to construct. , and seriously violated the safe lifting and hoisting regulations, there are major safety hazards, and there are also problems of high installation and dismantling costs and low work efficiency. However, in the construction of cast-in-place box girders with a certain height or limited by space, There is no economical and reliable stent removal method for reference.

[发明内容][Content of the invention]

本发明是针对现有的现浇梁箱梁侧模的安装拆除成本高、工效低、施工难的问题,提供一种结构简单、操作灵活、适用于环保要求高的箱梁支架的落架装置及方法。The present invention aims at the problems of high installation and dismantling cost, low work efficiency and difficult construction of the existing cast-in-place girder box girder side formwork, and provides a simple structure, flexible operation, suitable for box girder support with high environmental protection requirements and a drop frame device. method.

为了实现上述目的,设计一种箱梁支架整体落架装置,所述的落架装置包括落架砂筒、底横梁、贝雷支架、上拖梁、连接面板、吊杆及分离式螺母,所述的底横梁下部设有落架砂筒,上部设有贝雷支架,所述的贝雷支架底部与底横梁之间相接并置于混凝土梁体下方,混凝土梁体上设有梁体预留孔,吊杆垂直贯穿于梁体预留孔内,吊杆的上端采用分离式螺母与上托梁连接,吊杆中部采用分离式螺母与双层钢垫板固定于连接面板上,吊杆的底部采用双螺母固定于底横梁上,所述的混凝土梁体上方置有机械千斤顶,所述的机械千斤顶反复升降将其上部设有的上托梁循环复位、下降来实现整体落架。In order to achieve the above-mentioned purpose, a kind of box girder support overall falling frame device is designed, and described falling frame device comprises falling frame sand cylinder, bottom beam, Bailey support, upper tow beam, connecting panel, suspender rod and separate type nut, and described bottom The lower part of the beam is provided with a drop frame sand drum, and the upper part is provided with a Bailey bracket. The bottom of the Bailey bracket is connected with the bottom beam and placed under the concrete beam body. The rod vertically runs through the reserved hole of the beam body. The upper end of the boom is connected to the upper joist with a separate nut, the middle part of the boom is fixed on the connecting panel with a separate nut and a double-layer steel backing plate, and the bottom of the boom is fixed with a double-layer steel backing plate. Nuts are fixed on the bottom cross beam, and a mechanical jack is placed above the concrete beam body, and the mechanical jack is repeatedly lifted and lowered to reset and lower the upper joist provided on its upper part to realize the overall falling of the frame.

所述的底横梁采用56#工字钢制作,底横梁上设有吊杆孔,所述的吊杆孔的孔位与梁体预留孔同轴同径,底横梁采用双层钢垫板及双螺母固定吊杆底部。The bottom beam is made of 56# I-beam, and the bottom beam is provided with a boom hole, and the hole position of the boom hole is coaxial and the same diameter as the reserved hole of the beam body, and the bottom beam adopts a double-layer steel backing plate And double nuts to fix the bottom of the boom.

所述的连接面板采用双层20mm厚钢板制作,所述的吊杆穿孔位于连接面板中心,与底横梁上的吊杆孔及梁体预留孔同轴同径,连接面板采用双层钢垫板、分离式螺母固定吊杆中部。The connection panel is made of double-layer 20mm thick steel plate, the suspender hole is located in the center of the connection panel, coaxial with the boom hole on the bottom beam and the reserved hole of the beam body, and the connection panel is made of double-layer steel pad The middle part of the suspender is fixed by a plate and a separate nut.

所述的上托梁采用45#双拼工字钢、加劲钢板焊接制作,双拼工字钢的间距大于吊杆的直径,以便吊杆顺利穿过,上托梁采用双层钢垫板、分离式螺母固定吊杆上端。The upper joist is made by welding 45# double I-beams and stiffened steel plates. The spacing of the double I-beams is greater than the diameter of the boom so that the boom can pass through smoothly. The upper joist adopts double-layer steel backing plates, The split nut fixes the upper end of the boom.

所述的吊杆采用32mm精轧螺纹钢制作,吊杆的直径根据箱梁支架自重选择,吊杆分别与每箱梁的四角处对称设置。Said boom adopts Made of 32mm fine-rolled rebar, the diameter of the suspenders is selected according to the weight of the box girder bracket, and the suspenders are set symmetrically with the four corners of each box girder.

所述的机械千斤顶对称设置于吊杆两侧50-60cm位置。The mechanical jacks are arranged symmetrically at 50-60 cm on both sides of the boom.

所述的分离式螺母由卡口及套环组成,卡口呈半圆形,两卡口对应相接形成围绕吊杆的环形空间,卡口两端分别设有套环,卡口固定吊杆,并通过两端的套环锁紧,松动套环用以分开螺母。The separate nut is composed of a bayonet and a collar, the bayonet is semicircular, and the two bayonets are connected correspondingly to form an annular space around the boom, and collars are respectively provided at both ends of the bayonet, and the bayonet fixes the boom , and locked by the collars at both ends, loosen the collars to separate the nuts.

上述的箱梁支架整体落架装置的安装方法具体步骤如下:The specific steps of the installation method of the above-mentioned box girder bracket overall drop frame device are as follows:

1)落架前将吊杆穿于梁体预留孔及底横梁吊杆孔,吊杆底端采用双层钢垫板、配套双螺母与底横梁固定牢固;1) Put the suspender through the reserved hole of the beam body and the suspender hole of the bottom beam before falling off the frame. The bottom of the suspender is fixed with a double-layer steel backing plate and matching double nuts to the bottom beam firmly;

2)将连接面板垂直穿于吊杆上方,落至梁面,在连接面板上安装双层钢垫板,并通过下部分离式螺母固定;2) Put the connection panel vertically above the suspender, drop it to the beam surface, install a double-layer steel backing plate on the connection panel, and fix it through the lower part of the separate nut;

3)在吊杆左右两侧50-60cm位置对称安装机械千斤顶于梁面上;3) Install mechanical jacks symmetrically on the beam surface at 50-60cm on the left and right sides of the boom;

4)最后将上托梁垂直穿于吊杆上端,落至千斤顶之上,完成全部落架设备安装并进行检查。4) Finally, put the upper joist vertically through the upper end of the suspender, drop it onto the jack, and complete the installation and inspection of all drop-off equipment.

一种采用上述的箱梁支架整体落架装置的施工方法,所述的施工方法的具体步骤如下:A kind of construction method that adopts the above-mentioned box girder support overall falling frame device, the concrete steps of described construction method are as follows:

1)用机械千斤顶将上托梁顶升至最大高度,拧紧上部的分离式螺母受力,松动下部的分离式螺母套环使其不受力;1) Use a mechanical jack to raise the upper joist to the maximum height, tighten the upper split nut to bear the force, and loosen the lower split nut collar so that it will not be stressed;

2)将落架砂筒卸砂落架,此时上部的分离式螺母受力,机械千斤顶通过上托梁将整个箱梁支架悬吊,拆除落架砂筒及支撑;2) Unload the sand barrel from the falling frame and drop the frame. At this time, the upper separate nut is stressed, and the mechanical jack suspends the entire box girder bracket through the upper joist, and the sand barrel and support of the falling frame are removed;

3)将机械千斤顶下降至最低高度,此时松开上部的分离式螺母,拧紧下部的分离式螺母使其受力;3) Lower the mechanical jack to the lowest height, loosen the upper split nut at this time, and tighten the lower split nut to make it bear the force;

4)机械千斤顶升至最大高度,将上托梁及上部分离式螺母复位,拧紧上部的分离式螺母,松开下部的分离式螺母,使上部的分离式螺母受力,机械千斤顶通过上托梁再次将整个箱梁支架悬吊;4) Lift the mechanical jack to the maximum height, reset the upper joist and the upper split nut, tighten the upper split nut, loosen the lower split nut, and force the upper split nut, and the mechanical jack passes the upper joist Suspend the entire box girder support again;

5)将机械千斤顶下降至最低高度,重复3、4、5步骤依次循环落架至墩底,人工配合机械拆除模板支架体系;5) Lower the mechanical jack to the lowest height, repeat steps 3, 4, and 5 to drop the frame to the bottom of the pier in turn, and manually cooperate with the machine to remove the formwork support system;

6)当落架高度大于单根吊杆长度,需要接长时,分离式螺母在不受力状态下分开,用于接长的接驳器通过分离式螺母,即可实现更大高度的落架。6) When the drop frame height is greater than the length of a single suspender and needs to be extended, the detachable nut is separated under the unstressed state, and the connector used for lengthening passes through the detachable nut to achieve a larger height drop frame.

本发明同现有技术相比,其优点在于:本装置采用底横梁、上拖梁、吊杆及分离式螺母组成的落架结构使得千斤顶受力时整体落架,工作原理简单,操作方便,受力清晰,通过该装置将贝雷支架与模板下落至墩底工作高度,依次循环最终达到落架的目的,拆除模板支架,施工过程安全可靠,解决了周围复杂地形环境及场地狭小施工困难的问题,并提高了工效、保证了工期,节约施工成本,具有较高的应用和推广价值。Compared with the prior art, the present invention has the advantages that: the device adopts a drop frame structure composed of bottom beam, upper drag beam, suspender and separate nut to make the jack fall off as a whole when the jack is under force. The working principle is simple, the operation is convenient, and the force Clearly, through this device, the Bailey support and formwork will be dropped to the working height of the pier bottom, and the purpose of falling will be achieved in turn, and the formwork support will be removed. The construction process is safe and reliable. The work efficiency is improved, the construction period is guaranteed, the construction cost is saved, and the utility model has high application and popularization value.

[附图说明][Description of drawings]

图1是本发明的安装后的结构立面图;Fig. 1 is the structural elevation view after the installation of the present invention;

图2是本发明中分离式螺母的轴向截面示意图;Fig. 2 is the schematic diagram of the axial section of the separable nut in the present invention;

图3是本发明中分离式螺母的侧视图;Fig. 3 is the side view of split nut among the present invention;

图4是本发明中分离式螺母的结构展开示意图;Fig. 4 is a schematic diagram of the structure expansion of the split nut in the present invention;

图5是本发明的落架砂筒卸砂落架示意图;Fig. 5 is a schematic diagram of the falling frame sand drum unloading sand falling frame of the present invention;

图6是本发明中落架时机械千斤顶的局部示意图;Fig. 6 is a partial schematic diagram of the mechanical jack when the frame falls in the present invention;

图7是本发明的上托梁复位时机械千斤顶的局部示意图;Fig. 7 is a partial schematic view of the mechanical jack when the upper joist of the present invention is reset;

图中:1.落架砂筒 2.配套双螺母 3.底横梁 4.贝雷支架 5.梁体预留孔 6.连接面板 7.下部分离式螺母 8.刚垫板 9.机械千斤顶10.上拖梁 11.吊杆 12.上部分离式螺母 13.卡口 14.套环。In the figure: 1. Falling frame sand cylinder 2. Supporting double nuts 3. Bottom beam 4. Bailey bracket 5. Beam reserved hole 6. Connection panel 7. Lower separate nut 8. Just backing plate 9. Mechanical jack 10. Upper towing beam 11. Boom 12. Upper separate nut 13. Bayonet 14. Collar.

[具体实施方式][detailed description]

下面结合附图对本发明作进一步说明,这种装置的结构和原理对本专业的人来说是非常清楚的,完全可以理解。此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。The present invention will be further described below in conjunction with accompanying drawing, and the structure and principle of this device are very clear to those skilled in the art, can understand fully. The specific embodiments described here are only used to explain the present invention, not to limit the present invention.

箱梁支架整体落架装置参见图1,包括落架砂筒1、配套双螺母2、底横梁3、贝雷支架4、梁体预留孔5、连接面板6、下部分离式螺母7、刚垫板8、机械千斤顶9、上拖梁10、吊杆11、上部分离式螺母12。底横梁下部设有落架砂筒,上部设有贝雷支架,贝雷支架底部与底横梁之间相接并置于混凝土梁体下方,混凝土梁体上设有梁体预留孔,吊杆垂直贯穿于梁体预留孔内,吊杆的上端采用分离式螺母与上托梁连接,吊杆中部采用分离式螺母与双层钢垫板固定于连接面板上,吊杆的底部采用双螺母固定于底横梁上,混凝土梁体上方置有机械千斤顶,机械千斤顶反复升降将其上部设有的上托梁循环复位、下降来实现整体落架。See Figure 1 for the overall drop frame device of the box girder bracket, including drop frame sand drum 1, matching double nuts 2, bottom beam 3, Bailey bracket 4, beam body reserved hole 5, connection panel 6, lower separate nut 7, and rigid backing plate 8. Mechanical jack 9, upper towing beam 10, boom 11, upper separate nut 12. The lower part of the bottom crossbeam is provided with a drop frame sand drum, and the upper part is provided with a Bailey support. The bottom of the Bailey support is connected to the bottom crossbeam and placed under the concrete beam body. The concrete beam body is provided with a reserved hole for the beam body. It runs through the reserved hole of the beam body. The upper end of the suspender is connected to the upper joist with a separate nut. The middle part of the suspender is fixed on the connecting panel with a separate nut and a double-layer steel backing plate. The bottom of the suspender is fixed with double nuts. On the bottom beam, a mechanical jack is placed above the concrete beam body, and the mechanical jack is repeatedly raised and lowered to reset and lower the upper joist on the upper part to realize the overall fall.

其中,底横梁采用56#工字钢制作,底横梁设置吊杆孔,孔位与梁体预留孔同轴同径,采用双层钢垫板、配套双螺母用于固定吊杆底端,用于承担模板支架体系重力;连接面板采用双层20mm厚钢板制作,目的在于增加与梁体接触面,增强刚度,防止损坏梁面混凝土;吊杆穿孔位于连接面板中心,与底横梁吊杆孔、梁体预留孔同轴同径,采用双层钢垫板、分离式螺母固定吊杆中部;上托梁采用45#双拼工字钢、加劲钢板焊接制作,双拼工字钢间距略大于吊杆直径,以便吊杆顺利穿过,采用双层钢垫板、分离式螺母固定吊杆上端;吊杆采用32mm精轧螺纹钢制作,吊杆直径根据模板支架自重选择,分别于每幅箱梁4角处对称设置;机械千斤顶对称设置于吊杆两侧50-60cm,根据模板支架自重,选择机械千斤顶型号,采用机械千斤顶目的在于便于控制起落架行程与速度。Among them, the bottom beam is made of 56# I-beam, and the bottom beam is equipped with boom holes, which are coaxial and the same diameter as the reserved holes of the beam body. Double-layer steel backing plates and matching double nuts are used to fix the bottom end of the boom. It is used to bear the gravity of the formwork support system; the connecting panel is made of double-layer 20mm thick steel plate, the purpose is to increase the contact surface with the beam body, enhance the rigidity, and prevent damage to the concrete on the beam surface; , The reserved holes in the beam body are coaxial and the same diameter, and the middle part of the suspender is fixed by double-layer steel backing plates and separate nuts; the upper joist is made of 45# double-spelled I-beams and stiffened steel plates by welding, and the distance between double-spelled I-beams is slightly It is larger than the diameter of the boom so that the boom can pass through smoothly, and the upper end of the boom is fixed with a double-layer steel backing plate and a separate nut; the boom adopts Made of 32mm fine-rolled rebar, the diameter of the suspenders is selected according to the weight of the template support, and they are symmetrically installed at the 4 corners of each box girder; the mechanical jack is symmetrically installed on both sides of the suspender 50-60cm, and the type of mechanical jack is selected according to the self-weight of the formwork support. , the purpose of using mechanical jacks is to facilitate the control of the stroke and speed of the landing gear.

分离式螺母由卡口13及套环14组成,参见图2至图4,卡口呈半圆形,两卡口对应相接形成围绕吊杆的环形空间,卡口两端分别设置套环,卡口固定吊杆,并通过两端的套环锁紧,松动套环即可将螺母分开。The split nut is composed of a bayonet 13 and a collar 14, see Figure 2 to Figure 4, the bayonet is semicircular, and the two bayonets are connected correspondingly to form an annular space around the boom. The bayonet secures the boom and locks in place with collars at both ends, loosening the collars separates the nuts.

本发明先利用落架砂筒对支架体系进行整体落架30cm左右,然后利用本装置使千斤顶受力时整体落架,不受力时抬高千斤顶依次循环最终达到落架的目的,箱梁浇筑完成具备拆模条件后,按图1中所示位置安装落架装置,本装置的安装方法为:In the present invention, the support system is firstly lowered by the sand tube for about 30 cm, and then the device is used to make the jack fall when the force is applied, and when the force is not applied, the jack is lifted up and circulated in sequence to finally achieve the purpose of falling. After the conditions are met, install the drop frame device according to the position shown in Figure 1. The installation method of this device is as follows:

1.落架前将吊杆穿于梁体预留孔、底横梁吊杆孔,底端采用双层钢垫板、配套双螺母与底横梁固定牢固;1. Before falling off the frame, put the suspender through the reserved hole of the beam body and the suspender hole of the bottom beam. The bottom end is fixed firmly with the bottom beam by double-layer steel backing plate and supporting double nuts;

2.将连接面板垂直穿于吊杆上方,落至梁面,在连接面板上安装双层钢垫板,并通过下部分离式螺母固定;2. Put the connection panel vertically above the suspender, drop it to the beam surface, install a double-layer steel backing plate on the connection panel, and fix it through the lower part of the separate nut;

3.在吊杆左右两侧50-60cm位置对称安装机械千斤顶于梁面上;3. Install mechanical jacks symmetrically on the beam surface at 50-60cm on the left and right sides of the boom;

4.最后将上托梁垂直穿于吊杆上端,落至千斤顶之上,完成全部落架设备安装并进行检查。4. Finally, put the upper joist vertically through the upper end of the boom, drop it onto the jack, and complete the installation and inspection of all drop-off equipment.

落架装置组装完成并进行安全检查后进行具体施工,其施工方法具体步骤如下:After the assembly of the drop frame device is completed and the safety inspection is carried out, the specific construction will be carried out. The specific steps of the construction method are as follows:

1)用机械千斤顶将上托梁顶升至最大高度,拧紧上部的分离式螺母受力,松动下部的分离式螺母套环使其不受力;1) Use a mechanical jack to raise the upper joist to the maximum height, tighten the upper split nut to bear the force, and loosen the lower split nut collar so that it will not be stressed;

2)将落架砂筒卸砂落架,此时上部的分离式螺母受力,机械千斤顶通过上托梁将整个箱梁支架悬吊,拆除落架砂筒及支撑,见图5;2) Unload the sand barrel from the falling frame and drop the frame. At this time, the upper separate nut is stressed, and the mechanical jack suspends the entire box girder bracket through the upper joist, and removes the sand barrel and support from the falling frame, as shown in Figure 5;

3)将机械千斤顶下降至最低高度,此时松开上部的分离式螺母,拧紧下部的分离式螺母使其受力,见图6;3) Lower the mechanical jack to the lowest height, at this time, loosen the upper separable nut, and tighten the lower separable nut to make it bear the force, see Figure 6;

4)机械千斤顶升至最大高度,将上托梁及上部分离式螺母复位,拧紧上部的分离式螺母,松开下部的分离式螺母,使上部的分离式螺母受力,机械千斤顶通过上托梁再次将整个箱梁支架悬吊,见图7;4) Lift the mechanical jack to the maximum height, reset the upper joist and the upper split nut, tighten the upper split nut, loosen the lower split nut, and force the upper split nut, and the mechanical jack passes the upper joist Suspend the entire box girder support again, see Figure 7;

5)将机械千斤顶下降至最低高度,重复3、4、5步骤依次循环落架至墩底,人工配合机械拆除模板支架体系;5) Lower the mechanical jack to the lowest height, repeat steps 3, 4, and 5 to drop the frame to the bottom of the pier in turn, and manually cooperate with the machine to remove the formwork support system;

6)当落架高度大于单根吊杆长度,需要接长时,分离式螺母在不受力状态下分开,用于接长的接驳器通过分离式螺母,即可实现更大高度的落架。6) When the drop frame height is greater than the length of a single suspender and needs to be extended, the detachable nut is separated under the unstressed state, and the connector used for lengthening passes through the detachable nut to achieve a larger height drop frame.

本装置及采用该装置的施工方法成功应用于昆明环湖南路第2合同段古城1号特大桥水域公路双幅桥梁现浇箱梁施工,不仅提高了工效、保证了工期,还保证了施工过程的安全可靠,具有较高的应用和推广价值。The device and the construction method using the device have been successfully applied to the construction of double-width bridge cast-in-place box girders in the water area of Gucheng No. 1 Super Bridge in the second contract section of Huanhu South Road in Kunming, which not only improves the work efficiency, but also ensures the construction period. It is safe and reliable, and has high application and promotion value.

Claims (9)

1.一种箱梁支架整体落架装置,其特征在于所述的落架装置包括落架砂筒、底横梁、贝雷支架、上拖梁、连接面板、吊杆及分离式螺母,所述的底横梁下部设有落架砂筒,上部设有贝雷支架,所述的贝雷支架底部与底横梁之间相接并置于混凝土梁体下方,混凝土梁体上设有梁体预留孔,吊杆垂直贯穿于梁体预留孔内,吊杆的上端采用分离式螺母与上托梁连接,吊杆中部采用分离式螺母与双层钢垫板固定于连接面板上,吊杆的底部采用双螺母固定于底横梁上,所述的混凝土梁体上方置有机械千斤顶,所述的机械千斤顶反复升降将其上部设有的上托梁循环复位、下降来实现整体落架。1. A box girder support integral falling frame device is characterized in that the falling frame device comprises a falling frame sand cylinder, a bottom crossbeam, a Bailey support, an upper drag beam, a connecting panel, a suspender and a detachable nut, and the bottom crossbeam The lower part is provided with a falling frame sand drum, and the upper part is provided with a Bailey support. The bottom of the Bailey support is connected with the bottom beam and placed under the concrete beam body. The concrete beam body is provided with a beam body reserved hole. Vertically through the reserved hole of the beam body, the upper end of the suspender is connected to the upper joist with a separate nut, the middle part of the suspender is fixed on the connecting panel with a separate nut and a double-layer steel backing plate, and the bottom of the suspender is fixed with double nuts It is fixed on the bottom beam, and a mechanical jack is placed above the concrete beam body, and the mechanical jack is repeatedly raised and lowered to reset and lower the upper joist provided on its upper part to realize the overall fall. 2.如权利要求1所述的一种箱梁支架整体落架装置,其特征在于所述的底横梁采用56#工字钢制作,底横梁上设有吊杆孔,所述的吊杆孔的孔位与梁体预留孔同轴同径,底横梁采用双层钢垫板及双螺母固定吊杆底部。2. A kind of box girder support integral falling frame device as claimed in claim 1, it is characterized in that described bottom cross beam adopts 56# I-beam to make, and bottom cross beam is provided with boom hole, and the bottom cross beam of described boom hole The hole position is coaxial and the same diameter as the reserved hole of the beam body, and the bottom beam adopts double-layer steel backing plate and double nuts to fix the bottom of the suspender. 3.如权利要求1所述的一种箱梁支架整体落架装置,其特征在于所述的连接面板采用双层20mm厚钢板制作,所述的吊杆穿孔位于连接面板中心,与底横梁上的吊杆孔及梁体预留孔同轴同径,连接面板采用双层钢垫板、分离式螺母固定吊杆中部。3. The overall falling device of a kind of box girder bracket as claimed in claim 1, wherein the connecting panel is made of double-layer 20mm thick steel plate, and the perforation of the suspender is located at the center of the connecting panel, and is connected with the bottom cross beam. The boom hole and the reserved hole of the beam body are coaxial and have the same diameter, and the connecting panel adopts double-layer steel backing plate and separate nut to fix the middle part of the boom. 4.如权利要求1所述的一种箱梁支架整体落架装置,其特征在于所述的上托梁采用45#双拼工字钢、加劲钢板焊接制作,双拼工字钢的间距大于吊杆的直径,以便吊杆顺利穿过,上托梁采用双层钢垫板、分离式螺母固定吊杆上端。4. A kind of box girder bracket overall drop frame device as claimed in claim 1, it is characterized in that described upper joist adopts 45# double-joint I-beams and stiffening steel plates to be welded, and the distance between double-part I-beams is greater than that of hanging The diameter of the rod should be adjusted so that the boom can pass through smoothly. The upper joist uses double-layer steel backing plates and separate nuts to fix the upper end of the boom. 5.如权利要求1所述的一种箱梁支架整体落架装置,其特征在于所述的吊杆采用精轧螺纹钢制作,吊杆的直径根据箱梁支架自重选择,吊杆分别与每箱梁的四角处对称设置。5. The overall falling device of a box girder support as claimed in claim 1, wherein said suspender adopts Made of fine-rolled rebar, the diameter of the suspenders is selected according to the weight of the box girder bracket, and the suspenders are respectively arranged symmetrically with the four corners of each box girder. 6.如权利要求1所述的一种箱梁支架整体落架装置,其特征在于所述的机械千斤顶对称设置于吊杆两侧50-60cm位置。6 . The overall falling device of a box girder support as claimed in claim 1 , wherein the mechanical jacks are arranged symmetrically at 50-60 cm on both sides of the boom. 7 . 7.如权利要求1所述的一种箱梁支架整体落架装置,其特征在于所述的分离式螺母由卡口及套环组成,卡口呈半圆形,两卡口对应相接形成围绕吊杆的环形空间,卡口两端分别设有套环,卡口固定吊杆,并通过两端的套环锁紧,松动套环用以分开螺母。7. The overall falling device of a box girder support as claimed in claim 1, wherein the detachable nut is composed of a bayonet and a collar, the bayonet is semicircular, and the two bayonets are connected correspondingly to form a surrounding In the annular space of the suspender, collars are provided at both ends of the bayonet, the bayonet fixes the suspender, and is locked by the collars at both ends, and the loose collars are used to separate the nuts. 8.一种采用如权利要求1所述的箱梁支架整体落架装置的安装方法,其特征在于所述的安装方法的具体步骤如下:8. An installation method adopting the overall falling frame device of the box girder support as claimed in claim 1, wherein the specific steps of the installation method are as follows: 1)落架前将吊杆穿于梁体预留孔及底横梁吊杆孔,吊杆底端采用双层钢垫板、配套双螺母与底横梁固定牢固;1) Put the suspender through the reserved hole of the beam body and the suspender hole of the bottom beam before falling off the frame. The bottom of the suspender is fixed with a double-layer steel backing plate and matching double nuts to the bottom beam firmly; 2)将连接面板垂直穿于吊杆上方,落至梁面,在连接面板上安装双层钢垫板,并通过下部分离式螺母固定;2) Put the connection panel vertically above the suspender, drop it to the beam surface, install a double-layer steel backing plate on the connection panel, and fix it through the lower part of the separate nut; 3)在吊杆左右两侧50-60cm位置对称安装机械千斤顶于梁面上;3) Install mechanical jacks symmetrically on the beam surface at 50-60cm on the left and right sides of the boom; 4)最后将上托梁垂直穿于吊杆上端,落至千斤顶之上,完成全部落架设备安装并进行检查。4) Finally, put the upper joist vertically through the upper end of the suspender, drop it onto the jack, and complete the installation and inspection of all drop-off equipment. 9.一种采用如权利要求1所述的箱梁支架整体落架装置的施工方法,其特征在于所述的施工方法的具体步骤如下:9. A construction method that adopts the overall falling frame device of the box girder support as claimed in claim 1, is characterized in that the concrete steps of the described construction method are as follows: 1)用机械千斤顶将上托梁顶升至最大高度,拧紧上部的分离式螺母受力,松动下部的分离式螺母套环使其不受力;1) Use a mechanical jack to raise the upper joist to the maximum height, tighten the upper split nut to bear the force, and loosen the lower split nut collar so that it will not be stressed; 2)将落架砂筒卸砂落架,此时上部的分离式螺母受力,机械千斤顶通过上托梁将整个箱梁支架悬吊,拆除落架砂筒及支撑;2) Unload the sand barrel from the falling frame and drop the frame. At this time, the upper separate nut is stressed, and the mechanical jack suspends the entire box girder bracket through the upper joist, and the sand barrel and support of the falling frame are removed; 3)将机械千斤顶下降至最低高度,此时松开上部的分离式螺母,拧紧下部的分离式螺母使其受力;3) Lower the mechanical jack to the lowest height, loosen the upper split nut at this time, and tighten the lower split nut to make it bear the force; 4)机械千斤顶升至最大高度,将上托梁及上部分离式螺母复位,拧紧上部的分离式螺母,松开下部的分离式螺母,使上部的分离式螺母受力,机械千斤顶通过上托梁再次将整个箱梁支架悬吊;4) Lift the mechanical jack to the maximum height, reset the upper joist and the upper split nut, tighten the upper split nut, loosen the lower split nut, and force the upper split nut, and the mechanical jack passes the upper joist Suspend the entire box girder support again; 5)将机械千斤顶下降至最低高度,重复3、4、5步骤依次循环落架至墩底,人工配合机械拆除模板支架体系;5) Lower the mechanical jack to the lowest height, repeat steps 3, 4, and 5 to drop the frame to the bottom of the pier in turn, and manually cooperate with the machine to remove the formwork support system; 6)当落架高度大于单根吊杆长度,需要接长时,分离式螺母在不受力状态下分开,用于接长的接驳器通过分离式螺母,即可实现更大高度的落架。6) When the drop frame height is greater than the length of a single suspender and needs to be extended, the detachable nut is separated under the unstressed state, and the connector used for lengthening passes through the detachable nut to achieve a larger height drop frame.
CN201610980449.8A 2016-11-08 2016-11-08 Whole support landing device and method for box girder support Pending CN106368127A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610980449.8A CN106368127A (en) 2016-11-08 2016-11-08 Whole support landing device and method for box girder support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610980449.8A CN106368127A (en) 2016-11-08 2016-11-08 Whole support landing device and method for box girder support

Publications (1)

Publication Number Publication Date
CN106368127A true CN106368127A (en) 2017-02-01

Family

ID=57893663

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610980449.8A Pending CN106368127A (en) 2016-11-08 2016-11-08 Whole support landing device and method for box girder support

Country Status (1)

Country Link
CN (1) CN106368127A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948276A (en) * 2017-05-15 2017-07-14 中国十七冶集团有限公司 A kind of method of cast-in-place box beam bracket integral demounting
CN107201727A (en) * 2017-07-25 2017-09-26 利越集团有限公司 Cross a river Continuous box girder with cast-in-place cantilever method construction environmental-protection engineering method
CN107892238A (en) * 2017-11-11 2018-04-10 中铁三局集团华东建设有限公司 A kind of lowering equipment and method for Bailey beam
CN107988920A (en) * 2018-01-25 2018-05-04 中交公局厦门工程有限公司 A kind of stent transverse direction integral translation device and its construction method
CN109468937A (en) * 2018-12-28 2019-03-15 中铁十局集团第二工程有限公司 Bridge and its method for dismounting with falsework
CN110374006A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 A kind of construction method for removing space opposite sex large-tonnage steel beam bracket
CN111749135A (en) * 2020-05-30 2020-10-09 中交路桥建设有限公司 Integral dismantling method for 0# block bracket of continuous rigid frame bridge
CN112482232A (en) * 2020-11-30 2021-03-12 中交第一航务工程局有限公司 Beam falling system for dismantling box girder Bailey beam support of urban railway and construction method
CN114934448A (en) * 2022-06-13 2022-08-23 中铁大桥局第七工程有限公司 Dismantling device and system for box girder formwork supporting system and construction method
CN118148048A (en) * 2024-03-25 2024-06-07 南京润华建设集团有限公司 Integral drop structure and construction method of cast-in-place box girder steel pipe Bailey support

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11172627A (en) * 1997-12-16 1999-06-29 Ishikawajima Harima Heavy Ind Co Ltd Method and apparatus for sending out variable section girder
CN102080357A (en) * 2011-01-06 2011-06-01 中铁二十四局集团浙江工程有限公司 Integrated beam-falling device and method for steel pipe pier bailey beam cast-in-place bracket
CN204023414U (en) * 2014-07-23 2014-12-17 中建三局集团有限公司 The few fulcrum support entirety of a kind of novel large falls rack device
CN204803765U (en) * 2015-06-26 2015-11-25 中国中铁航空港建设集团有限公司 Cast -in -place continuous case roof beam of high mound bridge whereabouts device
CN106012852A (en) * 2016-06-15 2016-10-12 江苏燕宁建设工程有限公司 Construction method for overall support removal
CN206408527U (en) * 2016-11-08 2017-08-15 中铁上海工程局集团有限公司 A kind of box beam bracket integrally falls rack device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11172627A (en) * 1997-12-16 1999-06-29 Ishikawajima Harima Heavy Ind Co Ltd Method and apparatus for sending out variable section girder
CN102080357A (en) * 2011-01-06 2011-06-01 中铁二十四局集团浙江工程有限公司 Integrated beam-falling device and method for steel pipe pier bailey beam cast-in-place bracket
CN204023414U (en) * 2014-07-23 2014-12-17 中建三局集团有限公司 The few fulcrum support entirety of a kind of novel large falls rack device
CN204803765U (en) * 2015-06-26 2015-11-25 中国中铁航空港建设集团有限公司 Cast -in -place continuous case roof beam of high mound bridge whereabouts device
CN106012852A (en) * 2016-06-15 2016-10-12 江苏燕宁建设工程有限公司 Construction method for overall support removal
CN206408527U (en) * 2016-11-08 2017-08-15 中铁上海工程局集团有限公司 A kind of box beam bracket integrally falls rack device

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948276A (en) * 2017-05-15 2017-07-14 中国十七冶集团有限公司 A kind of method of cast-in-place box beam bracket integral demounting
CN107201727A (en) * 2017-07-25 2017-09-26 利越集团有限公司 Cross a river Continuous box girder with cast-in-place cantilever method construction environmental-protection engineering method
CN107892238A (en) * 2017-11-11 2018-04-10 中铁三局集团华东建设有限公司 A kind of lowering equipment and method for Bailey beam
CN107892238B (en) * 2017-11-11 2019-10-22 中铁三局集团华东建设有限公司 A kind of lowering equipment and method for Bailey beam
CN107988920A (en) * 2018-01-25 2018-05-04 中交公局厦门工程有限公司 A kind of stent transverse direction integral translation device and its construction method
CN109468937A (en) * 2018-12-28 2019-03-15 中铁十局集团第二工程有限公司 Bridge and its method for dismounting with falsework
CN110374006A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 A kind of construction method for removing space opposite sex large-tonnage steel beam bracket
CN110374006B (en) * 2019-07-22 2021-08-10 中铁大桥局集团有限公司 Construction method for dismantling space anisotropic large-tonnage steel beam bracket
CN111749135A (en) * 2020-05-30 2020-10-09 中交路桥建设有限公司 Integral dismantling method for 0# block bracket of continuous rigid frame bridge
CN112482232A (en) * 2020-11-30 2021-03-12 中交第一航务工程局有限公司 Beam falling system for dismantling box girder Bailey beam support of urban railway and construction method
CN114934448A (en) * 2022-06-13 2022-08-23 中铁大桥局第七工程有限公司 Dismantling device and system for box girder formwork supporting system and construction method
CN118148048A (en) * 2024-03-25 2024-06-07 南京润华建设集团有限公司 Integral drop structure and construction method of cast-in-place box girder steel pipe Bailey support

Similar Documents

Publication Publication Date Title
CN105735141B (en) A kind of box beam side form slide device and its construction method
CN104746883B (en) A kind of arcuate space truss lifts construction method of installation with three machines
CN203794498U (en) Built-in self-elevating tower crane device
CN106759845B (en) A kind of construction method of Steel corridor
CN105484164B (en) Spanning type bailey beam bracket and construction method thereof
CN103711078A (en) Temporary girder-type support for bridge construction and dismantling method thereof
CN105714683A (en) Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames
CN102251483A (en) Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane
CN103669902A (en) Cast-in-place beam support truss integral dropping and dismounting tool and construction method thereof
CN116411517A (en) Concrete beam bracket-free integral lifting construction method
CN110526153B (en) A jack-assisted pile foundation steel cage lifting structure and construction method thereof
CN202658590U (en) Integral assembled drilling platform
CN102041779A (en) Erection crane and construction method thereof
CN214939311U (en) Integrated bridge erection machine for prefabricated bridge piers and beams
CN205636503U (en) Case beam side displacement device
CN206408527U (en) A kind of box beam bracket integrally falls rack device
CN210684485U (en) Steel arch frame dismantling device for deck box type arch bridge construction
CN115043330B (en) Support structure of inner climbing frame of tower crane in non-core tube area, inner climbing frame and tower crane
CN204455842U (en) Bridge prefabricated beam slab lifting frame
CN201132941Y (en) Mobile formwork self-floating lower shoulder beam
CN113802478B (en) Arch bridge deck structure demolishs device based on arch rib supports atress
CN203129025U (en) Suspension fixing device for hanging basket
CN108342984B (en) Soft foundation trestle for mudflat and installation and sedimentation method thereof
CN102877412A (en) Method of pre-assembly in integral erecting way of steel tower
CN206680994U (en) Assembled steel reinforced cage descending frame

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170201

RJ01 Rejection of invention patent application after publication