CN106284796A - A kind of assembled roof system - Google Patents
A kind of assembled roof system Download PDFInfo
- Publication number
- CN106284796A CN106284796A CN201610859769.8A CN201610859769A CN106284796A CN 106284796 A CN106284796 A CN 106284796A CN 201610859769 A CN201610859769 A CN 201610859769A CN 106284796 A CN106284796 A CN 106284796A
- Authority
- CN
- China
- Prior art keywords
- roof boarding
- roof
- sides
- plate
- boarding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B7/00—Roofs; Roof construction with regard to insulation
- E04B7/02—Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B7/00—Roofs; Roof construction with regard to insulation
- E04B7/02—Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs
- E04B7/06—Constructions of roof intersections or hipped ends
Abstract
The invention belongs to building structure field, disclose a kind of assembled roof system, including roof boarding and beam, roof system stands on wallboard, roof boarding is predetermined slope the both sides being arranged at described beam, and the bottom on the upside of roof boarding is provided with groove, and the both sides, top of beam are provided with flange, the upside of the roof boarding of beam both sides is overlapped on beam, and the flange of both sides, back portion is the most chimeric with the groove of the roof boarding of beam both sides respectively;It is connected by being connected support with wallboard on the downside of roof boarding.The assembled roof structure of the present invention, strengthens the globality of roof structure, the beneficially conduction of power between roofing and beam and wallboard, the shock resistance of the most reinforced roof structure system, the present invention without using roof truss, easy for installation, safe and reliable, good integrity, and low cost.
Description
Technical field
The invention belongs to building structure field, be specifically related to a kind of assembled roof system.
Background technology
Traditional roof structure is vertical roof truss on wallboard or beam, then lays tile on roof truss, along with modern architecture
Rise, the variation that the structure of roofing becomes, roofing collection is heat insulation, water-proof function one, is generally divided into cast-in-place and roof boarding and lays
Two ways.Cast-in-site roof, especially pitched roof, formwork difficulty, mold shape is many, complex process, and roofing weight is relatively big,
It is unfavorable for antidetonation.In roof boarding laying structure, mainly vertical on wallboard have steel roof truss, and roof boarding, roofing are then placed above
Plate is made up of " profiled sheet+warming plate+profiled sheet ", as patent CN204715639U discloses a kind of pressing steel plate roofing
Plate, including profiled sheet, longitudinal reinforcement, lightweight aggregate concrete layer, coil waterproof layer and protective layer, profiled sheet is positioned at roof boarding
Orlop, is disposed with longitudinal reinforcement in profiled sheet groove, profiled sheet has poured lightweight aggregate concrete layer, lightweight aggregate coagulation
Whole to profiled sheet and longitudinal reinforcement watering is integrated by soil layer.But this roof boarding is placed up, not only needs roof truss, Er Qiexu
Wanting to arrange on roof truss purlin, not only take material, cost is high, and whole roofing construction technique is more complicated.
In sum, for cost-effective, improve efficiency of construction, offer a kind of easy construction, the roof system of material economy are provided badly
Structure.
Summary of the invention
It is an object of the invention to carry the novel assembled roof system of a kind of easy construction, material economy.
Above-mentioned purpose is to be achieved through the following technical solutions: a kind of assembled roof system, including roof boarding and beam, described roof system
Standing on wallboard, described roof boarding is predetermined slope the both sides being arranged at described beam, and the bottom on the upside of described roof boarding is provided with
Groove, the both sides, top of described beam are provided with flange, and the upside of the roof boarding of described beam both sides is overlapped on beam, described back portion two
The flange of side is the most chimeric with the groove of the roof boarding of beam both sides respectively;Prop up by being connected with described wallboard on the downside of described roof boarding
Frame is connected.In the technical program, laggard it is about to roof boarding lifting when the wallboard of the following structure of roofing, floor etc. have all been constructed,
After roof boarding dropping place, the flange of both sides, back portion is the most chimeric with the groove of the roof boarding of beam both sides respectively, logical on the downside of roof boarding
Cross connection support to be connected with wallboard.
Further, described beam is provided with stirrup, and described stirrup portion extend out to the top of described beam, the roofing of described beam both sides
Being filled with in-situ layer in the region that plate and beam are enclosed, described stirrup stretches out the position of described beam and is anchored in in-situ layer.?
The top of beam carries out pouring of in-situ layer, time cast-in-place, the roof boarding of beam and its both sides separately constitutes bed die and side form, described
Stirrup stretches out the position of described beam and is anchored in in-situ layer, after in-situ layer molding, has the roof boarding of beam Yu its both sides necessarily
Cohesive force, on the upside of roof boarding, beam and in-situ layer form overall common stress, be configured to roof structure.
Further, described roof boarding is provided with the second built-in fitting, described second built-in fitting stretch out along the side of roof boarding and to
Roof panel outer side extends, and the position that described second built-in fitting stretches out roof boarding is anchored in in-situ layer.
The assembled roof structure of the present invention, can be used for assembly concrete roof structure system, and said structure feature is not
Only strengthening the globality of roof structure, the beneficially conduction of power between roofing and beam and wallboard, the most reinforced roofing is tied
The shock resistance of structure system, the present invention without using roof truss, easy for installation, safe and reliable, good integrity, and low cost.
Further, described connection support includes base plate, gripper shoe, connecting plate and anchoring piece, and wherein, described gripper shoe is arranged
Fixing on base plate and with base plate and be connected, the end face of described gripper shoe is the predetermined gradient, and described connecting plate is fixed on described
On the end face of fagging, described anchoring piece is fixing with connecting plate to be connected, and described base plate stands on wallboard, and described anchoring piece is anchored at room
In panel.Connect support to be used for connecting roof boarding and wallboard, make roof boarding stand on wallboard, so without using roof truss, it is only necessary to
Roof boarding is winched on wallboard, use connection support to connect.During use, anchoring piece is anchored in roof boarding, and base plate stands on
On wallboard, when, after roof boarding dropping place, anchoring piece being fixed with connecting plate and is connected the connection being to realize roof boarding and wallboard, or even
Connecing support integral with roof boarding, during dropping place, base plate dropping place is at wallboard end face.So, the peace of roof boarding is considerably increased
Dress efficiency, and has saved cost, connects the own simple in construction of support, easy to use, and connects reliable.Should be appreciated that and prop up herein
Described in the end face of fagging specifically refer in the predetermined gradient with roof boarding in the gradient consistent, be so easy to connect support even
Connect roof boarding and wallboard.Preferably, described roof boarding uses concrete prefabricated forming.
Further, described anchoring piece includes fixed plate and anchoring supporting leg, and described anchoring supporting leg is anchored at inside roof boarding, institute
State fixed plate at least partly to expose to roof boarding bottom surface.Being arranged such, not only anchoring property is good, fixed plate at least partly expose to
Roof boarding bottom surface is easy to it and is welded with connecting plate.Preferably, fixed plate only joint face exposes.Due to the restriction of roof structure, fixing
Plate uses the mode welded more suitable with connecting plate, not only connects reliable, and it is more convenient to construct.
Further, described base plate bottom is provided with elastic base.Owing to roof boarding has certain weight, especially concrete
Roof boarding, the setting of elastic base, during roof boarding dropping place, play certain cushioning effect, meanwhile, elastic base can
There is elastic deformation, it is easy to adjust the flatness of roof boarding.It should be noted that described elastic base can fixing with base plate connect
Connect, it is possible to do not fix with base plate and be connected.
Further, described elastic base is bolted with base plate.
Further, described elastic base is board-like rubber blanket.Board-like rubber blanket is the most wear-resisting but also load performance good, prolonged
Durable.
Further, described elastic base bottom is provided with locating part.Wallboard is snapped in it by described locating part, so can ensure that
Connect support during roof boarding dropping place to move relative to wallboard;Described locating part is preferably U-shaped steel, and U-shaped steel is with elastic
Pedestal and the fixing connection of base plate, wallboard snaps in the U-type groove of U-shaped steel;The most described panel tops is embedded with I-steel, U-shaped steel
Welding with pre-buried I-steel, so connection support is fixing with wallboard is connected, and connects the most reliable.
Further, described gripper shoe at least includes that two pieces of vertically arranged floors, two pieces of described floors are arranged on base plate
Both sides.
Further, described floor is provided with screw, and described screw extends from the bottom surface of described floor to end face, described elastic base
Seat and base plate are provided with through hole, and described floor, elastic base and base plate are connected by screw rod, through hole and spiral shell described in described screw rod cross-under
Hole.It is arranged such, by screw rod floor, elastic base and base plate can connect into entirety, simple in construction, easy for installation.
Further, it is provided with reinforcing plate between described connecting plate and base plate.The setting of reinforcing plate, shares what gripper shoe was born
Load, can effectively prevent gripper shoe from deforming, extend the service life of this bracing frame.
Further, described in-situ layer top is provided with cover plate, the roof boarding of tie-beam both sides respectively, the both sides of described cover plate.Excellent
Choosing, cover plate is connected by nailing or self threading pin with roof boarding, so, can be strengthened even by cover plate between the roof boarding of beam both sides
Connecing, roof structure is the most firm.
Further, described cover plate is bending plate, and described roof boarding forms ridge with cover plate.
Further, described roof boarding is provided with heat-insulation layer.Being arranged such, roof boarding has good heat-insulating property, strengthens
The integral heat insulation effect of building.
Further, being provided with elongated muscle in described in-situ layer, described elongated muscle passes described stirrup.It is arranged such, not only may be used
It is effectively increased the intensity of in-situ layer, the globality of beam and in-situ layer can be increased simultaneously.
Further, the both sides of described beam are equipped with polylith roof boarding, and described roof boarding is assembled into entirety.When roofing area relatively
Time big, due to lifting problem, the roofing of the both sides of described beam will be assembled into entirety by polylith roof boarding.
Further, the Mosaic face of described roof boarding is embedded with elastic water-proof body.In the manufacturing process of roof boarding, elasticity is prevented
Water body is embedded in its Mosaic face, when, after the same side roof boarding assembly of beam, the roof boarding of adjacent assembly is the most crowded by water-proof elastomer
It is pressed in the Mosaic face of the two, so, water can be prevented along the Mosaic face seepage of roof boarding.Preferably, can be at roof boarding and elastic water-proof
The contact surface of body arranges groove, and elastic water-proof body side embeds the Mosaic face of roof boarding, and opposite side is squeezed into another room corresponding
In the groove in panel splicing face, the most both can play waterproof effect, nor affect on the assembled effect of roof boarding.
Further, the Mosaic face of described roof boarding arranges slip casting groove, is perfused with waterproofing slurry in described slip casting groove.At beam
After the roof boarding splicing of the same side, it is perfused with waterproofing slurry in described slip casting groove, carries out waterproof sealing, when waterproofing slurry hardens
After, form waterproof layer at Mosaic face, can effectively prevent water along Mosaic face seepage.
Further, the Mosaic face of described roof boarding is provided with waterproof steel plate, and adjacent waterproof steel plate is welded into entirety.Waterproof steel
Plate is preferably located at the periphery of Mosaic face, and after the roof boarding splicing in the same side of beam, adjacent waterproof steel plate is welded into entirety, this
Time waterproof steel plate play and close or block the effect of Mosaic face, can effectively prevent water along Mosaic face seepage.
Accompanying drawing explanation
The accompanying drawing of the part constituting the present invention is used for providing a further understanding of the present invention, and the present invention's is schematic real
Execute example and illustrate for explaining the present invention, being not intended that inappropriate limitation of the present invention.
Fig. 1 is the structural representation of the assembled roof system involved by one embodiment of the present invention;
Fig. 2 is the schematic diagram connecting node of roof boarding involved in Fig. 1 and beam;
Fig. 3 is the structural representation connecting support involved by one embodiment of the present invention;
Fig. 4 is the disassemblying structure schematic diagram connecting support involved in Fig. 3;
Fig. 5 is the front schematic view connecting support involved by another embodiment of the present invention;
Fig. 6 is the structural representation of the anchoring piece involved by one embodiment of the present invention;
Fig. 7 is the front schematic view of anchoring piece involved in Fig. 6;
Fig. 8 is the connection node schematic diagram of the roof boarding involved by one embodiment of the present invention and wallboard.
In figure:
1 roof boarding 2 beam 3 wallboard 4 groove
5 flange 6 stirrup 7 in-situ layer 8 cover plates
18 fixed plates 19 anchor the elongated muscle of supporting leg 22 heat-insulation layer 23
24 base plate 25 gripper shoe 26 connecting plate 27 anchoring pieces
28 elastic base 29 screw 30 screw rod 31 locating parts
32 I-steel 33 connect support
Detailed description of the invention
Describing the present invention below in conjunction with the accompanying drawings, the description of this part is only exemplary and explanatory, should not
Protection scope of the present invention is had any restriction effect.Additionally, those skilled in the art are according to the description of presents, can be right
In presents, the feature in embodiment and in different embodiment carries out respective combination.
The embodiment of the present invention is as follows, sees figures.1.and.2, and a kind of assembled roof system, including roof boarding 1 and beam 2, described room
Lid stands on wallboard 3, and described roof boarding 1 is in predetermined slope and is arranged at the both sides of described beam 2, and described roof boarding 1 is by concrete
Prefabricated forming, the bottom on the upside of described roof boarding 1 is provided with groove 4, and the both sides, top of described beam 2 are provided with flange 5,2 liang of described beam
The upside of the roof boarding 1 of side is overlapped on beam 2, the flange 5 of both sides, described beam 2 top recessed with the roof boarding 1 of beam 2 both sides respectively
Groove 4 is the most chimeric;It is connected by being connected support 33 with described wallboard 3 on the downside of described roof boarding 1.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 1, described beam 2 is provided with stirrup 6, described hoop
Muscle 6 part extend out to the top of described beam 2, is filled with cast-in-place in the region that roof boarding 1 in beam 2 both sides and beam 2 are enclosed
Layer 7, described stirrup 6 stretches out the position of described beam 2 and is anchored in in-situ layer 7
In the technical program, when the laggard roof boardings 1 of being about to of all having constructed such as the wallboard 3 of the following structure of roofing, floor hang
Dress, after roof boarding 1 dropping place, the flange 5 of both sides, beam 2 top is the most chimeric with the groove 4 of the roof boarding 1 of beam 2 both sides respectively, roofing
On the downside of plate 1 by connect support 33 be connected with wallboard 3, carry out pouring of in-situ layer 7 on the top of beam 2, time cast-in-place, by beam 2 with
And the roof boarding 1 of both sides separately constitutes bed die and side form, described stirrup 6 stretches out the position of described beam 2 and is anchored at in-situ layer 7
In, after in-situ layer 7 molding, the roof boarding 1 of beam 2 with its both sides is had certain cohesive force, on the upside of roof boarding 1, beam 2 and cast-in-place
Layer 7 also forms overall common stress, is configured to roof structure.
On the basis of above-described embodiment, in another embodiment of the present invention, described roof boarding 1 is provided with the second built-in fitting, institute
Stating the second built-in fitting stretch out along the side of roof boarding 1 and extend outside roof boarding 1, described second built-in fitting stretches out roof boarding 1
Position be anchored in in-situ layer 7.
The assembled roof structure of the present invention, can be used for assembly concrete roof structure system, and said structure feature is not
Only strengthen the conduction of power between the globality of roof structure, beneficially roofing and beam 2 and wallboard 3, the most reinforced roofing
The shock resistance of structural system, the present invention without using roof truss, easy for installation, safe and reliable, good integrity, and low cost.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 3~5, described connection support 33 includes the end
Plate 24, gripper shoe 25, connecting plate 26 and anchoring piece 27, wherein, described gripper shoe 25 is arranged on base plate 24 and solid with base plate 24
Fixed connection, the end face of described gripper shoe 25 is the predetermined gradient, and described connecting plate 26 is fixed on the end face of described gripper shoe 25,
Described anchoring piece 27 is fixing with connecting plate 26 to be connected, and described base plate 24 stands on wallboard 3, and described anchoring piece 27 is anchored at roof boarding
In 1.Connect support 33 to be used for connecting roof boarding 1 and wallboard 3, make roof boarding 1 stand on wallboard 3, so without using roof truss, only
Need to roof boarding 1 be winched on wallboard 3, use connection support 33 to connect.During use, anchoring piece 27 is anchored in roof boarding 1,
Base plate 24 stands on wallboard 3, when after roof boarding 1 dropping place, anchoring piece 27 is fixed with connecting plate 26 be connected be realize roof boarding 1 and
The connection of wallboard 3, or it is integral with roof boarding 1 to connect support 33, and during dropping place, base plate 24 dropping place is at wallboard 3 end face.As
This, considerably increase the installation effectiveness of roof boarding 1, and saved cost, connects the own simple in construction of support 33, easy to use,
And connect reliable.Should be appreciated that described in the end face of gripper shoe 25 herein specifically refer in the predetermined gradient with roof boarding 1 in
The gradient consistent, be so easy to connect support 33 and connect roof boarding 1 and wallboard 3.Preferably, described roof boarding 1 uses concrete
Prefabricated form.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 6 and Fig. 7, described anchoring piece 27 includes solid
Determining plate 18 and anchoring supporting leg 19, it is internal that described anchoring supporting leg 19 is anchored at roof boarding 1, described fixed plate 18 at least partly expose to
Roof boarding 1 bottom surface.Being arranged such, not only anchoring property is good, fixed plate 18 at least partly expose to roof boarding 1 bottom surface be easy to its with
Connecting plate 26 welds.Preferably, fixed plate 18 only joint face exposes.Due to the restriction of roof structure, fixed plate 18 and connecting plate 26
The mode using welding is more suitable, not only connects reliable, and it is more convenient to construct.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 3, described base plate 24 bottom is provided with elasticity
Pedestal 28.Owing to roof boarding 1 has certain weight, especially concrete face-board for room 1, the setting of elastic base 28, at roofing
Playing certain cushioning effect during plate 1 dropping place, meanwhile, elastic base 28 can occur elastic deformation, it is easy to adjusts roofing
The flatness of plate 1.It should be noted that described elastic base 28 can fixing with base plate 24 be connected, it is possible to do not fix with base plate 24
Connect.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 4, described elastic base 28 and base plate 24
It is bolted.
On the basis of above-described embodiment, in another embodiment of the present invention, described elastic base 28 is board-like rubber blanket.Plate
Formula rubber blanket is the most wear-resisting but also load performance good, durable in use.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 5, described elastic base 28 bottom is provided with
Locating part 31.Wallboard 3 is snapped in it by described locating part 31, connects support 33 during so can ensure that roof boarding 1 dropping place
Will not move relative to wallboard 3;Described locating part 31 is preferably U-shaped steel, and U-shaped steel is fixed be connected with elastic base 28 and base plate 24,
Wallboard 3 snaps in the U-type groove of U-shaped steel;The most described wallboard 3 top is embedded with I-steel 32, and U-shaped steel enters with pre-buried I-steel 32
Row welding, so connection support 33 are fixing with wallboard 3 to be connected, and connects the most reliable.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 4, described gripper shoe 25 at least includes two
The floor that block is vertically arranged, two pieces of described floors are arranged on base plate 24 both sides.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 4, described floor is provided with screw 29, described
Screw 29 extends from the bottom surface of described floor to end face, and described elastic base 28 is provided with through hole, described floor, elasticity with base plate 24
Pedestal 28 and base plate 24 are connected by screw rod 30, through hole and screw 29 described in the cross-under of described screw rod 30.It is arranged such, passes through screw rod
Floor, elastic base 28 and base plate 24 can be connected into entirety by 30, and simple in construction is easy for installation.
On the basis of above-described embodiment, in another embodiment of the present invention, it is provided with between described connecting plate 26 and base plate 24
Reinforcing plate.The setting of reinforcing plate, shares the load that gripper shoe 25 is born, and can effectively prevent gripper shoe 25 from deforming, extend this
The service life of support.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 2, described in-situ layer 7 top is provided with cover plate
8, the roof boarding 1 of tie-beam 2 both sides respectively, the both sides of described cover plate 8.Preferably, cover plate 8 and roof boarding 1 are by nailing or self threading pin
Connecting, so, can add strong ties by cover plate 8 between the roof boarding 1 of beam 2 both sides, roof structure is the most firm.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 2, described cover plate 8 is bending plate, described
Roof boarding 1 and cover plate 8 form ridge.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 8, described roof boarding 1 is provided with heat-insulation layer
22.Being arranged such, roof boarding 1 has good heat-insulating property, strengthens the integral heat insulation effect of building.
On the basis of above-described embodiment, in another embodiment of the present invention, such as Fig. 2, in described in-situ layer 7, it is provided with elongated muscle
23, described elongated muscle 23 is through described stirrup 6.It is arranged such, not only can be effectively increased the intensity of in-situ layer 7, can increase simultaneously
Beam 2 and the globality of in-situ layer 7.
On the basis of above-described embodiment, in another embodiment of the present invention, the both sides of described beam 2 are equipped with polylith roof boarding
1, described roof boarding 1 is assembled into entirety.When roofing area is bigger, due to lifting problem, the roofing of the both sides of described beam 2 will be by
Polylith roof boarding 1 is assembled into entirety.
On the basis of above-described embodiment, the Mosaic face of roof boarding 1 described in another embodiment of the present invention is embedded with elastic anti-
Water body.In the manufacturing process of roof boarding 1, elastic water-proof body is embedded in its Mosaic face, when the same side roof boarding 1 of beam 2 is assembled
After, water-proof elastomer is tightly squeezed in the Mosaic face of the two by the roof boarding 1 of adjacent assembly, so, water can be prevented along roof boarding 1
Mosaic face seepage.Preferably, can arrange groove 4 at the contact surface of roof boarding 1 with elastic water-proof body, elastic water-proof body side embeds
The Mosaic face of roof boarding 1, opposite side is squeezed in the groove 4 of another roof boarding 1 Mosaic face corresponding, the most both can play waterproof
Effect, nor affects on the assembled effect of roof boarding 1.
On the basis of above-described embodiment, in another embodiment of the present invention, the Mosaic face of described roof boarding 1 arranges slip casting
Groove, is perfused with waterproofing slurry in described slip casting groove.After roof boarding 1 splicing in the same side of beam 2, it is perfused with in described slip casting groove
Waterproofing slurry, carries out waterproof sealing, after waterproofing slurry hardens, forms waterproof layer at Mosaic face, can effectively prevent water along splicing
Face seepage.
On the basis of above-described embodiment, in another embodiment of the present invention, the Mosaic face of described roof boarding 1 is provided with waterproof steel
Plate, adjacent waterproof steel plate is welded into entirety.Waterproof steel plate is preferably located at the periphery of Mosaic face, at the roofing of the same side of beam 2
After plate 1 splicing, adjacent waterproof steel plate is welded into entirety, and waterproof steel plate now plays the effect closing or blocking Mosaic face,
Can effectively prevent water along Mosaic face seepage.
On the basis of above-described embodiment, in another embodiment of the present invention, the end face of described roof boarding 1 is provided with tile hanging part,
Being mounted with tile on described tile hanging part, described roof boarding 1 end face is covered by described tile.This roof boarding 1 uses concrete prefabricated,
Intensity is big, single domatic uses one piece of roof boarding 1, and installation process only needs to be winched on beam 2, is configured to roofing and ties
Structure, and tile is integrated on roof boarding 1, while roof boarding 1 has lifted, also complete executing of roof sheet tile structure
Work, it is not necessary to follow-up workman carries out secondary operation, will not affect its water resistance and heat-insulating property to causing the damage of roof boarding 1,
Aerial work can be reduced simultaneously as far as possible, improve the safety of construction.
On the basis of above-described embodiment, in another embodiment of the present invention, described tile hanging part is provided with draw-in groove, described tile
Bottom is provided with flexible snap, and described flexible snap is connected in described draw-in groove.So, tile can be effectively improved to tie with roof boarding 1
The stability of structure, during roof boarding 1 can be avoided to lift, tile comes off;Certainly, described tile can be metallic tile also
Nonmetal tile.
On the basis of above-described embodiment, in another embodiment of the present invention, described tile hanging part becomes with roof boarding 1 one-piece casting
Type.It is arranged such, strengthens tile hanging part and can ensure that roof boarding 1 structural intergrity, Bu Huiyou while the globality of roof boarding 1
In subsequent installation process, the end face of roof boarding 1 is damaged, thus affect its water resistance.
On the basis of above-described embodiment, in another embodiment of the present invention, described roof boarding 1 is formed by concrete prefabricated,
The end face of described roof boarding 1 includes tile, and described tile is by metal stamping formed, and described tile becomes with roof boarding 1 one-piece casting
Type.
On the basis of above-described embodiment, in another embodiment of the present invention, bottom described tile, it is provided with fixture, described solid
Locking member is embedded in described roof boarding 1, and concrete layer is close in the bottom surface of described tile.So, tile is difficult to take off with roof boarding 1
Fall, even if the most in use running into the situation of strong wind.
On the basis of above-described embodiment, in another embodiment of the present invention, the edge of described tile is provided with standing-seam.As
This is arranged, it is simple to the tile being disposed adjacent connects.
On the basis of above-described embodiment, in another embodiment of the present invention, tile and roof boarding 1 are by described in connector watt
Sheet is provided with buckle, and described buckle is connected on connector.Being arranged such, during roof boarding 1 can be avoided to lift, tile is de-
Fall.
On the basis of above-described embodiment, in another embodiment of the present invention, the main body of described roof boarding 1 includes that concrete is pre-
Making sheet, the end face of described concrete prefabricated board is fixing connects bracing frame, and support frame as described above is by frame and orthogonal connecting rod structure
Becoming, described frame constitutes accommodation space with connecting rod, is filled with solar panels in described accommodation space.
On the basis of above-described embodiment, in another embodiment of the present invention, support frame as described above is provided with fixture, described fixing
Part is embedded in concrete prefabricated board.It is arranged such that the fixture of bracing frame during concrete prefabricated sheet metal forming
Part is pre-buried within it, and such bracing frame is more preferable with concrete prefabricated board globality, connects the most firm.
On the basis of above-described embodiment, in another embodiment of the present invention, in described concrete prefabricated board, it is embedded with connection
Part, described connector part exposes the end face to concrete prefabricated board, and described connector exposes the position to concrete prefabricated board
Connect support frame as described above.
On the basis of above-described embodiment, in another embodiment of the present invention, described support is provided with force bearing plate, described load
Plate is arranged on bottom accommodation space, and described solar panels are arranged on force bearing plate, sets between described force bearing plate and top of concrete
Headspace, the end face of described concrete prefabricated board is had to be equipped with waterproof roll.The setting of headspace, facilitates solar panels to pacify
In process of assembling, the laying of circuit, the most attractive in appearance, and middle air layer can play the most heat insulation effect, and concrete is pre-
The end face of making sheet be equipped with waterproof roll can have play waterproof and every the effect of vapour.
When solar panels are arranged with tile simultaneously, solar panels are arranged on tile top, for supporting solar panels
Support passes tile, and the cross-under position of the two uses marine glue to carry out encapsulation process.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For Yuan, under the premise without departing from the principles of the invention, it is also possible to make some improvements and modifications, these improvements and modifications also should
It is considered as protection scope of the present invention.
Claims (10)
1. an assembled roof system, it is characterised in that include that roof boarding and beam, described roof system stand on wallboard, described roof boarding
In predetermined slope and be arranged at the both sides of described beam, the bottom on the upside of described roof boarding is provided with groove, the both sides, top of described beam
Being provided with flange, the upside of the roof boarding of described beam both sides is overlapped on beam, the flange of both sides, described back portion respectively with beam both sides
The groove of roof boarding the most chimeric;It is connected by being connected support with described wallboard on the downside of described roof boarding.
Assembled roof system the most according to claim 1, it is characterised in that described beam is provided with stirrup, described stirrup portion is stretched
Go out the top to described beam, in the region that the roof boarding of described beam both sides and beam are enclosed, be filled with in-situ layer, described stirrup
The position stretching out described beam is anchored in in-situ layer.
Assembled roof system the most according to claim 2, it is characterised in that described connection support includes base plate, gripper shoe, company
Fishplate bar and anchoring piece, wherein, described gripper shoe is arranged on base plate and fixes with base plate and is connected, and the end face of described gripper shoe is in advance
The fixed gradient, described connecting plate is fixed on the end face of described gripper shoe, and described anchoring piece is fixing with connecting plate to be connected, the described end
Plate stands on wallboard, and described anchoring piece is anchored in roof boarding.
Assembled roof system the most according to claim 3, it is characterised in that described base plate bottom is provided with elastic base.
Assembled roof system the most according to claim 4, it is characterised in that described elastic base is with base plate by bolt even
Connect.
Assembled roof system the most according to claim 5, it is characterised in that described elastic base bottom is provided with locating part.
Assembled roof system the most according to claim 6, it is characterised in that described gripper shoe at least include two pieces vertically arranged
Floor, two pieces of described floors are arranged on base plate both sides.
Assembled roof system the most according to claim 7, it is characterised in that described floor is provided with screw, and described screw is from institute
The bottom surface stating floor extends to end face, and described elastic base and base plate are provided with through hole, and described floor, elastic base and base plate pass through
Screw rod connects, through hole and screw described in described screw rod cross-under.
9. according to the assembled roof system described in claim 1~8 any one, it is characterised in that described in-situ layer top is provided with
Cover plate, the roof boarding of tie-beam both sides respectively, the both sides of described cover plate.
Assembled roof system the most according to claim 9, it is characterised in that described cover plate is bending plate, described roof boarding with
Cover plate forms ridge.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610859769.8A CN106284796A (en) | 2016-09-28 | 2016-09-28 | A kind of assembled roof system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610859769.8A CN106284796A (en) | 2016-09-28 | 2016-09-28 | A kind of assembled roof system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106284796A true CN106284796A (en) | 2017-01-04 |
Family
ID=57716394
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610859769.8A Pending CN106284796A (en) | 2016-09-28 | 2016-09-28 | A kind of assembled roof system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106284796A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4488385A (en) * | 1982-05-28 | 1984-12-18 | Nfs Industries, Inc. | Building construction |
CN101059012A (en) * | 2006-04-18 | 2007-10-24 | 邱则有 | Reinforced concrete precast plate |
CN103422672A (en) * | 2013-08-29 | 2013-12-04 | 杜新智 | Construction method for reinforced concrete prefabricated house |
CN104612241A (en) * | 2015-02-05 | 2015-05-13 | 潘树宾 | Civil building prefabricated member set and assembly method thereof |
CN105201079A (en) * | 2014-06-20 | 2015-12-30 | 任丘市永基建筑安装工程有限公司 | Floorslab and wallboard welding technique |
-
2016
- 2016-09-28 CN CN201610859769.8A patent/CN106284796A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4488385A (en) * | 1982-05-28 | 1984-12-18 | Nfs Industries, Inc. | Building construction |
CN101059012A (en) * | 2006-04-18 | 2007-10-24 | 邱则有 | Reinforced concrete precast plate |
CN103422672A (en) * | 2013-08-29 | 2013-12-04 | 杜新智 | Construction method for reinforced concrete prefabricated house |
CN105201079A (en) * | 2014-06-20 | 2015-12-30 | 任丘市永基建筑安装工程有限公司 | Floorslab and wallboard welding technique |
CN104612241A (en) * | 2015-02-05 | 2015-05-13 | 潘树宾 | Civil building prefabricated member set and assembly method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103850352B (en) | A kind of method of attachment of precast plate | |
CN106284801A (en) | A kind of assembled roof system | |
CN101839033A (en) | Closed-section profiled steel sheet-concrete combined floor and construction method thereof | |
CN106351379A (en) | Roof assembly method | |
CN106351380A (en) | Roof assembly method | |
CN106320589A (en) | Roof assembling method | |
CN106284795A (en) | A kind of assembled roof system | |
CN106481011A (en) | A kind of assembly method of roof system | |
CN211499505U (en) | High-performance autoclaved aerated concrete slab parapet structure of prefabricated building | |
CN106284798A (en) | A kind of assembled roof system | |
CN206189694U (en) | Assembled room lid | |
CN106284796A (en) | A kind of assembled roof system | |
CN106284799A (en) | A kind of assembly method of roof system | |
CN206189702U (en) | Connected node of roof boarding and wallboard | |
CN206189697U (en) | Assembled room lid | |
CN106481009A (en) | A kind of assembly method of roof system | |
CN106284800A (en) | A kind of assembly method of roof system | |
CN208347285U (en) | A kind of construction and decoration high-altitude construction supporting structure | |
CN206289837U (en) | A kind of assembly type roof system | |
CN206408805U (en) | A kind of roof boarding and its installation node | |
CN206328959U (en) | A kind of roof boarding and roof system | |
CN206815635U (en) | A kind of assembly type roof system | |
CN206189696U (en) | Roof boarding and room lid | |
CN207003840U (en) | A kind of roof boarding and roof system | |
CN206189703U (en) | Assembled room lid |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170104 |