CN106284653A - 一种阳台构造柱顶预留空隙的施工方法 - Google Patents
一种阳台构造柱顶预留空隙的施工方法 Download PDFInfo
- Publication number
- CN106284653A CN106284653A CN201610813660.0A CN201610813660A CN106284653A CN 106284653 A CN106284653 A CN 106284653A CN 201610813660 A CN201610813660 A CN 201610813660A CN 106284653 A CN106284653 A CN 106284653A
- Authority
- CN
- China
- Prior art keywords
- extruded sheet
- space
- balcony
- steel wire
- template
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/34—Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明阳台构造柱顶预留空隙的施工方法,涉及建筑施工技术领域,包括以下步骤:(一)模板安装完成后浇注阳台构造柱混凝土,在距离上一楼层阳台梁板底面30‑50cm的高度时停止浇注混凝土,将挤塑板放满柱钢筋之间的间隙中;(二)在挤塑板上表面用铁丝固定挤塑板;(三)在挤塑板上的模板中继续浇筑上一楼层阳台梁板混凝土,阳台梁板混凝土凝结后,拆除挤塑板周围的模板,并将挤塑板全部凿掉形成空隙,再将空隙三边装塞缝模板,用比例为1:5的水泥炉渣填缝;(四)填缝两天后,将塞缝模板拆掉,洒水养护6‑8天,再用1:3水泥砂浆修补空隙表面;(五)在空隙四周挂满钢丝网,再在钢丝网外表面抹灰,使得钢丝网与空隙上下基体搭接平整。
Description
技术领域
本发明涉及建筑施工技术领域,特别涉及一种阳台构造柱顶预留空隙的施工方法。
背景技术
阳台的构造柱由于不作为承重的受力构件,其主要起到装饰作用,相邻两层楼的阳台构造柱中的混泥土是不连接在一起的,需要在相邻两层楼的阳台构造柱之间设置空隙,空隙常常设置在每一层楼层阳台构造柱靠顶部的位置。目前,工地现场常用的阳台构造柱顶预留空隙做法是用木糠或沙子填充构造柱缝隙,通常做法是在构造柱模板中浇筑完成混泥土后,再在模板的上端用木糠或沙子填充,但是该做法不但在操作过程中难以控制,施工操作不规范,且需要等木糠或沙子等填充材料凝结后才能浇注上一楼层阳台梁板,施工工期长,耗费许多的人力和时间,而且后期清理工作麻烦。
发明内容
本发明的目的是针对现有技术存在的缺陷,提供一种阳台构造柱顶预留空隙的施工方法,该方法方便快捷、定位方便,可避免后支模的麻烦,加快施工进度,省时省力。
本发明为实现上述目的采用的技术方案是:一种阳台构造柱顶预留空隙的施工方法,其特征在于,包括以下步骤:(一)在构造柱模板安装完成后浇注构造柱混凝土,在距离上一楼层阳台梁板底面30-50cm的高度时停止浇注混凝土,后用胶带绑扎好挤塑板,后将挤塑板放置到柱钢筋之间的间隙中,使挤塑板排满柱钢筋之间的所有间隙;(二)在挤塑板上表面用铁丝固定挤塑板在竖直方向的位置,相邻柱钢筋之间的铁丝交叉设置在挤塑板上表面,同时铁丝通过固定在柱钢筋上而限制挤塑板在竖直方向的位置;(三)在挤塑板上的模板中继续浇筑上一楼层阳台梁板混凝土,待浇筑好的阳台梁板混凝土凝结12-16天后,拆除挤塑板周围的模板,并将挤塑板全部凿掉形成空隙,再将构造柱空隙三边装塞缝模板,选用比例为1:5的水泥炉渣填缝;(四)填缝两天后,将塞缝模板拆掉,洒水养护6-8天,再用1:3水泥砂浆修补空隙四周表面;(五)在空隙四周挂满钢丝网,再在钢丝网外表面抹灰,使得钢丝网与空隙上下基体搭接平整。
本发明的进一步技术方案是:步骤(五)中,在空隙四周挂满钢丝网时,钢丝网上下两端分别延伸至超出空隙上下边缘10cm的位置。
本发明阳台构造柱顶预留空隙的施工方法具有如下有益效果:阳台构造柱顶预留空隙的施工方法简单,操作灵活,不需要等缝隙中的填充材料凝结后就能浇注上一楼层阳台梁板,有效缩短施工工期,预留缝隙中的挤塑板拆装方便,在缝隙中填上充材料也比较方便,可以在浇注完成所有楼层的阳台梁板后统一在缝隙中填上填缝材料,后在空隙四周挂满钢丝网后再进行抹灰,可以有效保证阳台构造柱整齐美观,在保证安全性能提升了一个档次的前提下同时实现了现场施工的标准统一化。
下面结合附图和实施例对本发明阳台构造柱顶预留空隙的施工方法作进一步的说明。
附图说明
图1是阳台构造柱中挤塑板安装在空隙中的竖向剖面示意图(图中省去模板);
图2是阳台构造柱中挤塑板安装在空隙中的横向剖面示意图;
图3是阳台构造柱中挤塑板被凿出空隙后剖面示意图;
图4是阳台构造柱中对间隙填缝后剖面示意图;
图5是阳台构造柱满挂钢丝网的示意图;
图6是阳台构造柱完成抹灰后的示意图;
附图标号说明:1-阳台梁板,2-挤塑板,3-柱钢筋,4-阳台构造柱,5-铁丝,6-模板,7-空隙,8-水泥炉渣,9-钢丝网。
具体实施方式
如图1至图6所示,本发明一种阳台构造柱顶预留空隙的施工方法,包括以下步骤:(一)在构造柱模板6安装完成后浇注阳台构造柱4混凝土,模板6采用18mm厚木胶合板,在距离上一楼层阳台梁板1底面30-50cm的高度时停止浇注混凝土,后用胶带绑扎好挤塑板2,后将挤塑板2放置到柱钢筋3之间的间隙中,使挤塑板2排满柱钢筋3之间的所有间隙,在本实施例中,挤塑板2采用50mm厚挤塑板2按柱钢筋3间距分割成一条一条的,用透明胶布封闭绑扎好,放置到柱钢筋3之间的间隙中,使得挤塑板2排满柱钢筋3之间的所有间隙即可,如图1、2所示;(二)在挤塑板2上表面用铁丝5固定挤塑板2在竖直方向的位置,相邻柱钢筋3之间的铁丝5交叉设置在挤塑板2上表面,同时铁丝5通过固定在柱钢筋3上而限制挤塑板2在竖直方向的位置,可防止浇筑阳台梁板混凝土时挤塑板2被混凝土浆挤移位,在本实施例中,铁丝5采用20~22号镀锌铁丝;(三)在挤塑板2上的模板6中继续浇筑上一楼层阳台梁板混凝土,待浇筑好的阳台梁板混凝土凝结12-16天后,拆除挤塑板2周围的模板,并将挤塑板全部凿掉形成空隙7,再将构造柱空隙三边装塞缝模板(图中未示出),选用比例为1:5的水泥炉渣8填缝;(四)填缝两天后,将塞缝模板拆掉,洒水养护6-8天,再用1:3水泥砂浆修补空隙四周表面;(五)在空隙四周挂满钢丝网9,钢丝网9通过钉子(图中未示出)满挂空隙周围,在空隙四周挂满钢丝网9时,钢丝网9上下两端分别延伸至超出空隙上下边缘10cm的位置,钢丝网9超出空隙上下边缘可有效的附着在空隙上下端的阳台构造柱外表面上,再在钢丝网9外表面抹灰,使得钢丝网9与空隙上下基体搭接平整,看不见钢丝网9即可。
Claims (2)
1.一种阳台构造柱顶预留空隙的施工方法,其特征在于,包括以下步骤:(一)在构造柱模板安装完成后浇注阳台构造柱混凝土,在距离上一楼层阳台梁板底面30-50cm的高度时停止浇注混凝土,后用胶带绑扎好挤塑板,后将挤塑板放置到柱钢筋之间的间隙中,使挤塑板排满柱钢筋之间的所有间隙;(二)在挤塑板上表面用铁丝固定挤塑板在竖直方向的位置,相邻柱钢筋之间的铁丝交叉设置在挤塑板上表面,同时铁丝通过固定在柱钢筋上而限制挤塑板在竖直方向的位置;(三)在挤塑板上的模板中继续浇筑上一楼层阳台梁板混凝土,待浇筑好的阳台梁板混凝土凝结12-16天后,拆除挤塑板周围的模板,并将挤塑板全部凿掉形成空隙,再将构造柱空隙三边装塞缝模板,选用比例为1:5的水泥炉渣填缝;(四)填缝两天后,将塞缝模板拆掉,洒水养护6-8天,再用1:3水泥砂浆修补空隙四周表面;(五)在空隙四周挂满钢丝网,再在钢丝网外表面抹灰,使得钢丝网与空隙上下基体搭接平整。
2.如权利要求1所述的阳台构造柱顶预留空隙的施工方法,其特征在于,步骤(五)中,在空隙四周挂满钢丝网时,钢丝网上下两端分别延伸至超出空隙上下边缘10cm的位置。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610813660.0A CN106284653B (zh) | 2016-09-10 | 2016-09-10 | 一种阳台构造柱顶预留空隙的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610813660.0A CN106284653B (zh) | 2016-09-10 | 2016-09-10 | 一种阳台构造柱顶预留空隙的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106284653A true CN106284653A (zh) | 2017-01-04 |
CN106284653B CN106284653B (zh) | 2018-09-21 |
Family
ID=57710395
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610813660.0A Active CN106284653B (zh) | 2016-09-10 | 2016-09-10 | 一种阳台构造柱顶预留空隙的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106284653B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106968398A (zh) * | 2017-04-25 | 2017-07-21 | 中建二局第二建筑工程有限公司 | 一种在阳台下方浇筑支撑柱的工艺方法 |
CN107035148A (zh) * | 2017-06-07 | 2017-08-11 | 甘肃第六建设集团股份有限公司 | 一种建筑物外围构造柱同主体结构同时施工的方法 |
CN107268617A (zh) * | 2017-07-28 | 2017-10-20 | 中建四局第三建筑工程有限公司 | 一种抗浮锚杆后施工工艺及装置 |
CN109881886A (zh) * | 2019-03-25 | 2019-06-14 | 中国一冶集团有限公司 | 构造柱顶部隔离缝预留施工组件及施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1078524A (zh) * | 1992-05-04 | 1993-11-17 | 范家声 | 砖混结构建筑构造柱、圈梁现浇施工方法及装置 |
JPH11190082A (ja) * | 1997-12-26 | 1999-07-13 | Taisei Corp | 快適性・個性化を考慮した集合住宅 |
CN103643798A (zh) * | 2013-12-09 | 2014-03-19 | 广州市第一建筑工程有限公司 | 一种用于构造柱顶部和大截面梁柱收口的浇筑装置 |
CN104612289A (zh) * | 2015-02-13 | 2015-05-13 | 中冶建工集团有限公司 | 一种外墙施工方法 |
CN204552085U (zh) * | 2015-02-16 | 2015-08-12 | 中国建筑第六工程局有限公司 | 一种框架梁底构造柱顶部支模浇筑混凝土构造 |
-
2016
- 2016-09-10 CN CN201610813660.0A patent/CN106284653B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1078524A (zh) * | 1992-05-04 | 1993-11-17 | 范家声 | 砖混结构建筑构造柱、圈梁现浇施工方法及装置 |
JPH11190082A (ja) * | 1997-12-26 | 1999-07-13 | Taisei Corp | 快適性・個性化を考慮した集合住宅 |
CN103643798A (zh) * | 2013-12-09 | 2014-03-19 | 广州市第一建筑工程有限公司 | 一种用于构造柱顶部和大截面梁柱收口的浇筑装置 |
CN104612289A (zh) * | 2015-02-13 | 2015-05-13 | 中冶建工集团有限公司 | 一种外墙施工方法 |
CN204552085U (zh) * | 2015-02-16 | 2015-08-12 | 中国建筑第六工程局有限公司 | 一种框架梁底构造柱顶部支模浇筑混凝土构造 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106968398A (zh) * | 2017-04-25 | 2017-07-21 | 中建二局第二建筑工程有限公司 | 一种在阳台下方浇筑支撑柱的工艺方法 |
CN107035148A (zh) * | 2017-06-07 | 2017-08-11 | 甘肃第六建设集团股份有限公司 | 一种建筑物外围构造柱同主体结构同时施工的方法 |
CN107035148B (zh) * | 2017-06-07 | 2020-04-17 | 甘肃第六建设集团股份有限公司 | 一种建筑物外围构造柱同主体结构同时施工的方法 |
CN107268617A (zh) * | 2017-07-28 | 2017-10-20 | 中建四局第三建筑工程有限公司 | 一种抗浮锚杆后施工工艺及装置 |
CN109881886A (zh) * | 2019-03-25 | 2019-06-14 | 中国一冶集团有限公司 | 构造柱顶部隔离缝预留施工组件及施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106284653B (zh) | 2018-09-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104652830B (zh) | 一种预制楼面板和预制墙板搭建的施工方法 | |
CN107542196A (zh) | 预应力混凝土双向叠合板及制作方法 | |
CN206667459U (zh) | 一种预制型钢筋混凝土剪力墙预拼结构装配式建筑 | |
CN105569355B (zh) | 一种包括预制构件模块化住宅的装配方法 | |
CN106555453A (zh) | 一种预应力预制叠合空心板及其施工方法 | |
CN107558603B (zh) | 一种装配式建筑结构体系及其施工方法 | |
CN106284653B (zh) | 一种阳台构造柱顶预留空隙的施工方法 | |
CN103790295B (zh) | 钢筋混凝土楼梯结构及其施工方法 | |
CN103556819B (zh) | 一种在梁板上预留构造柱孔洞的施工方法 | |
CN107503450A (zh) | 一种现浇中空钢筋混凝土填充墙及其施工工艺 | |
CN105507470A (zh) | 一种周边叠合整体装配式楼板及其施工方法 | |
CN112227759B (zh) | 一种古建筑清水墙体修复加固迁移方法 | |
CN104088473A (zh) | 用于托换承重墙的施工结构及施工方法 | |
CN207110214U (zh) | 一种预制内填充混凝土墙板 | |
CN103993672A (zh) | 低层装配式复合墙体房屋榫式连接节点结构 | |
CN105332386A (zh) | 一种塔吊基础兼做地下室底板的结构施工方法 | |
CN107237448A (zh) | 一种预制内填充混凝土墙板及其制造方法 | |
CN206916767U (zh) | 一种预制装配式电梯基础 | |
CN206457971U (zh) | 一种预应力预制叠合空心板 | |
CN207092299U (zh) | 一种现浇中空钢筋混凝土填充墙 | |
CN103015563B (zh) | 外砌模内砌体建筑结构体系 | |
CN207160359U (zh) | 预应力混凝土双向叠合板 | |
WO2018126950A1 (en) | Modular stairway | |
CN105386447A (zh) | 一种施工现场后浇带换撑的施工方法 | |
CN107142956A (zh) | 一种预制装配式电梯基础 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |