CN106284363B - High-efficiency dangerous rock mass artificial excavation method - Google Patents

High-efficiency dangerous rock mass artificial excavation method Download PDF

Info

Publication number
CN106284363B
CN106284363B CN201610784006.1A CN201610784006A CN106284363B CN 106284363 B CN106284363 B CN 106284363B CN 201610784006 A CN201610784006 A CN 201610784006A CN 106284363 B CN106284363 B CN 106284363B
Authority
CN
China
Prior art keywords
dangerous rock
rock body
slag
subregion
explosion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610784006.1A
Other languages
Chinese (zh)
Other versions
CN106284363A (en
Inventor
刘淑芳
彭继乐
赵继勇
俞灵光
秦晓亮
张涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201610784006.1A priority Critical patent/CN106284363B/en
Publication of CN106284363A publication Critical patent/CN106284363A/en
Application granted granted Critical
Publication of CN106284363B publication Critical patent/CN106284363B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a high-efficiency dangerous rock mass manual excavation method which comprises the steps of constructing a pedestrian path, carrying construction equipment, arranging a slag collecting platform, carrying out partition sequence blasting construction, collecting slag, discharging slag and the like. The method promotes most of the excavation slag to directly roll to the slag collecting platform, effectively reduces the slag collection of the excavation area, greatly reduces the workload of manual slag removal, and further shortens the construction period.

Description

A kind of high efficiency Dangerous Rock Body hand excavation's method
Technical field
The present invention relates to hydraulic and hydroelectric engineering Dangerous Rock Body Treatment process fields, and in particular to a kind of high efficiency Dangerous Rock Body is artificial Excavation method.
Background technique
Currently, Dangerous Rock Body adverse geological condition is very common, almost during the development & construction of hydraulic and hydroelectric engineering Each project more or less can be related to the improvement of Dangerous Rock Body.Currently, the improvement about Dangerous Rock Body, resolution is more, But macroscopic destruction is still a kind of very common resolution.For excavation, current Mechanization Level is higher, rock excavation Mechanized construction technique also comparative maturity, but Dangerous Rock Body a kind of so is also encountered in engineering, they have following feature: High, steep, processing project amount and work surface less, can not build Transportation Highway to excavate region, mechanical equipment is difficult to be transported to construction Work surface.Such Dangerous Rock Body is although small, but since work surface is little, traffic difficult arrangement, mechanical equipment is difficult to transport To operation side, and in operation side it is difficult to keep away quick-fried, and do mechanization operation is caused to be difficult to carry out, in such cases, adopted Manually operation be have to using method, however, traditional artificial construction method general work efficiency is lower, consumption of manually slagging tap Time-consuming more, the construction period is longer, encounters geographical location locating for Dangerous Rock Body to the influential situation of major project construction, then endangers The processing duration of rock mass will directly influence the time of completion of engineering.
Summary of the invention
The present invention is intended to provide a kind of high efficiency Dangerous Rock Body hand excavation's method, with solve that work surface is small and mechanical equipment without Method working efficiency existing when being transported to the small-sized Dangerous Rock Body of operation side using hand excavation's operation is low, consumption of manually slagging tap The problems such as duration, long construction period.
The present invention is achieved by following technical solution:
A kind of high efficiency Dangerous Rock Body hand excavation's method, this approach includes the following steps:
(1) compare the upstream side of Dangerous Rock Body and the topographic and geologic situation in downstream side, in the side that topographic and geologic condition is excellent To excavating at the top of work surface, scaffold is built when can not build sidewalk in local sharp regions for sidewalk;
(2) quick-fried and slag-tapping device will be bored using sidewalk be carried to operation side;
(3) slag charge collection slag platform is set in the lower part shoulder of Dangerous Rock Body;
(4) Dangerous Rock Body is divided into several layers subregion, includes several piecemeals in each subregion, according to sequence from top to bottom The blast working of subregion is carried out, the slag charge generated after explosion falls into slag charge collection slag platform, and collection slag platform discontinuity is slagged tap;
(5) supporting is carried out after excavating one layer of subregion, using riding track as foot after the completion of the work surface for being equipped with riding track is excavated The supporting of hand cradle set up basis and excavate region;
(6) collection slag is carried out to the slag charge hoarded in Dangerous Rock Body lower part slope surface pocket;
(7) after the completion of excavating, Dangerous Rock Body lower part slope surface is thoroughly cleared up.
The step (4) is divided into following steps:
Dangerous Rock Body is divided into the piecemeal of several quadrangles according to horizontal direction and upper left inclined direction by (4-1), towards bottom right All piecemeals in the same plane of side are divided into a subregion;
Piecemeal in (4-2) same layer subregion buries explosion filler, with subregion explosion order from the bottom to top;
(4-3) same layer by stages drops down onto region of slagging tap along natural grade every blast working, slag charge, and same layer subregion explosion is complete At rear collection slag and slag tap;
(4-4) repeats step (4-2)-(4-3) until all subregions are fully completed construction.
Dangerous Rock Body construction period carries out the concussion of blasting safety monitoring and slope stability safety monitoring of construction period.
The height and the width of every layer of piecemeal in the step (4) are 2-8m.
The width for the sidewalk being arranged in the step (1) is 1-2m.
Interval blasting time in the step (4-3) is 1-5s.
The beneficial effects of the invention are as follows:
Compared with prior art, high efficiency Dangerous Rock Body hand excavation's method provided by the invention, for " high, steep, processing work Journey amount and work surface less, without traffic, mechanical equipment are difficult to be transported to operation side " Dangerous Rock Body, dexterously according to " from outer It is interior, from outward appearance to inner essence, successively remove " principle, carry out subregion and sequence explosion divided to plan, with batch blast area, and reasonable arrangement is quick-fried Broken interval time and explosion order, explosion order consider successively explosion from the bottom to top, are conducive to excavated material after explosion It is tumbled naturally along natural grade to region of slagging tap, it is flat to collection slag that this method promotes most excavation slag charge directly to tumble Platform is effectively reduced the collection slag for excavating region, greatly reduces workload of manually skimming, and then shorten the duration.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention of the invention;
In figure:Serial number 1-18 is the excavation in zones and sequence of excavation of Dangerous Rock Body.
Specific embodiment
Technical solution of the present invention is described further with reference to the accompanying drawings and embodiments, but required protection scope It is not limited to described;
Embodiment 1:
Compare the upstream side of Dangerous Rock Body and the topographic and geologic situation in downstream side first before excavating, it is excellent in topographic and geologic condition Side build the sidewalk of wide 2m to excavating at the top of work surface, foot is built when can not build sidewalk in local sharp regions Hand cradle;Quick-fried and slag-tapping device, which will be bored, using sidewalk is carried to operation side;It is arranged in the lower part shoulder of Dangerous Rock Body Slag charge collection slag platform;Dangerous Rock Body is divided into several layers subregion, includes several piecemeals in each subregion, is in shape body as shown in Figure 1, The height and the width of piecemeal are 8m, are constructed according to the principle of " from outer to inner, from outward appearance to inner essence, successively remove ", by up to Under sequence carry out the blast working of subregion, the slag charge generated after explosion falls into slag charge collection slag platform, and collection slag platform discontinuity goes out Slag, specially:Dangerous Rock Body is divided into the piecemeal of several quadrangles according to horizontal direction and upper left inclined direction, towards bottom right side Same plane in all piecemeals be divided into a subregion, Dangerous Rock Body is divided into subregion 1- subregion 18 as shown in Figure 1;Together Layer subregion in piecemeal bury explosion filler, with subregion explosion order from the bottom to top;Same layer by stages is every blast working, interval Blasting time is 5s, and slag charge drops down onto region of slagging tap along natural grade, and slag is collected after the completion of the explosion of same layer subregion and is slagged tap;Weight Multiple construction is until all subregions are fully completed construction;Supporting is carried out after excavating one layer of subregion, when the work surface for being equipped with riding track is excavated The supporting set up basis and excavate region using riding track as scaffold after the completion;It is low in Dangerous Rock Body lower part slope surface to hoarding The slag charge of recess carries out collection slag;After the completion of excavation, Dangerous Rock Body lower part slope surface is thoroughly cleared up.
Embodiment 2:
Compare the upstream side of Dangerous Rock Body and the topographic and geologic situation in downstream side first before excavating, it is excellent in topographic and geologic condition Side build the sidewalk of wide 1m to excavating at the top of work surface, foot is built when can not build sidewalk in local sharp regions Hand cradle;Quick-fried and slag-tapping device, which will be bored, using sidewalk is carried to operation side;It is arranged in the lower part shoulder of Dangerous Rock Body Slag charge collection slag platform;Dangerous Rock Body is divided into several layers subregion, includes several piecemeals in each subregion, is in shape body as shown in Figure 1, The height and the width of piecemeal are 2m, are constructed according to the principle of " from outer to inner, from outward appearance to inner essence, successively remove ", by up to Under sequence carry out the blast working of subregion, the slag charge generated after explosion falls into slag charge collection slag platform, and collection slag platform discontinuity goes out Slag, specially:Dangerous Rock Body is divided into the piecemeal of several quadrangles according to horizontal direction and upper left inclined direction, towards bottom right side Same plane in all piecemeals be divided into a subregion, Dangerous Rock Body is divided into subregion 1- subregion 18 as shown in Figure 1;Together Layer subregion in piecemeal bury explosion filler, with subregion explosion order from the bottom to top;Same layer by stages is every blast working, interval Blasting time is 1s, and slag charge drops down onto region of slagging tap along natural grade, and slag is collected after the completion of the explosion of same layer subregion and is slagged tap;Weight Multiple construction is until all subregions are fully completed construction;Supporting is carried out after excavating one layer of subregion, when the work surface for being equipped with riding track is excavated The supporting set up basis and excavate region using riding track as scaffold after the completion;It is low in Dangerous Rock Body lower part slope surface to hoarding The slag charge of recess carries out collection slag;After the completion of excavation, Dangerous Rock Body lower part slope surface is thoroughly cleared up.
Embodiment 3:
Compare the upstream side of Dangerous Rock Body and the topographic and geologic situation in downstream side first before excavating, it is excellent in topographic and geologic condition Side build the sidewalk of wide 1.5m to excavating at the top of work surface, local sharp regions are built when can not build sidewalk Scaffold;Quick-fried and slag-tapping device, which will be bored, using sidewalk is carried to operation side;It is set in the lower part shoulder of Dangerous Rock Body Set slag charge collection slag platform;Dangerous Rock Body is divided into several layers subregion, includes several piecemeals in each subregion, is in shape as shown in Figure 1 Body, the height and the width of piecemeal are 5m, it constructs according to the principle of " from outer to inner, from outward appearance to inner essence, successively removing ", by Sequence under carries out the blast working of subregion, and the slag charge generated after explosion falls into slag charge collection slag platform, collection slag platform interruption Property is slagged tap, specially:Dangerous Rock Body is divided into the piecemeal of several quadrangles according to horizontal direction and upper left inclined direction, towards bottom right All piecemeals in the same plane of side are divided into a subregion, and Dangerous Rock Body is divided into subregion 1- subregion as shown in Figure 1 18;Piecemeal in same layer subregion buries explosion filler, with subregion explosion order from the bottom to top;Same layer by stages flame proof is broken to be applied Work, interval blasting time are 3.5s, and slag charge drops down onto region of slagging tap along natural grade, collects slag after the completion of the explosion of same layer subregion and go forward side by side Row is slagged tap;Construction is repeated until all subregions are fully completed construction;Supporting is carried out after excavating one layer of subregion, when the work for being equipped with riding track The supporting set up basis and excavate region after the completion of the excavation of industry face using riding track as scaffold;To hoarding under Dangerous Rock Body The slag charge of portion's slope surface pocket carries out collection slag;After the completion of excavation, Dangerous Rock Body lower part slope surface is thoroughly cleared up.

Claims (5)

1. a kind of high efficiency Dangerous Rock Body hand excavation's method, it is characterised in that:This approach includes the following steps:
(1) compare the upstream side of Dangerous Rock Body and the topographic and geologic situation in downstream side, built in the excellent side of topographic and geologic condition To excavating at the top of work surface, scaffold is built when can not build sidewalk in local sharp regions for sidewalk;
(2) quick-fried and slag-tapping device will be bored using sidewalk be carried to operation side;
(3) slag charge collection slag platform is set in the lower part shoulder of Dangerous Rock Body;
(4) Dangerous Rock Body is divided into several layers subregion, includes several piecemeals in each subregion, is carried out according to sequence from top to bottom The blast working of subregion, the slag charge generated after explosion fall into slag charge collection slag platform, and collection slag platform discontinuity is slagged tap;
(5) supporting is carried out after excavating one layer of subregion, using riding track as scaffold after the completion of the work surface for being equipped with riding track is excavated Set up basis carry out excavate region supporting;
(6) collection slag is carried out to the slag charge hoarded in Dangerous Rock Body lower part slope surface pocket;
(7) after the completion of excavating, Dangerous Rock Body lower part slope surface is thoroughly cleared up;
The step (4) is divided into following steps:
(4-1) is incited somebody to action according to the principle from outer to inner, from outward appearance to inner essence, successively removed, and according to horizontal direction and upper left inclined direction Dangerous Rock Body is divided into the piecemeal of several quadrangles, and from left top, bottom end direction will be in the division of all piecemeals in same plane to the right For a subregion;
Piecemeal in (4-2) same layer subregion buries explosion filler, with subregion explosion order from the bottom to top;
(4-3) same layer by stages is every blast working, and slag charge drops down onto region of slagging tap along natural grade, after the completion of same layer subregion explosion Collection slag is simultaneously slagged tap;
(4-4) repeats step (4-2)-(4-3) until all subregions are fully completed construction.
2. high efficiency Dangerous Rock Body hand excavation's method according to claim 1, it is characterised in that:Dangerous Rock Body construction period does The concussion of blasting safety monitoring and slope stability safety monitoring of good construction period.
3. high efficiency Dangerous Rock Body hand excavation's method according to claim 1, it is characterised in that:In the step (4) The height and the width of every layer of piecemeal are 2-8m.
4. high efficiency Dangerous Rock Body hand excavation's method according to claim 1, it is characterised in that:It is set in the step (1) The width for the sidewalk set is 1-2m.
5. high efficiency Dangerous Rock Body hand excavation's method according to claim 1, it is characterised in that:In the step (4-3) Interval blasting time be 1-5s.
CN201610784006.1A 2016-08-31 2016-08-31 High-efficiency dangerous rock mass artificial excavation method Active CN106284363B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610784006.1A CN106284363B (en) 2016-08-31 2016-08-31 High-efficiency dangerous rock mass artificial excavation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610784006.1A CN106284363B (en) 2016-08-31 2016-08-31 High-efficiency dangerous rock mass artificial excavation method

Publications (2)

Publication Number Publication Date
CN106284363A CN106284363A (en) 2017-01-04
CN106284363B true CN106284363B (en) 2018-11-27

Family

ID=57673232

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610784006.1A Active CN106284363B (en) 2016-08-31 2016-08-31 High-efficiency dangerous rock mass artificial excavation method

Country Status (1)

Country Link
CN (1) CN106284363B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842781A (en) * 2018-08-06 2018-11-20 中国电建集团华东勘测设计研究院有限公司 A kind of Excavation of High And Steep Slopes tap cinder construction method
CN111981922A (en) * 2020-08-24 2020-11-24 中国葛洲坝集团第一工程有限公司 Construction method for converting dangerous rock control blasting material into dam filling grade ingredient
CN112459076A (en) * 2020-11-17 2021-03-09 中铁二局集团有限公司 Excavation method for arranging slag discharge access roads in steep cliff arch support slope area

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148882A (en) * 2007-10-29 2008-03-26 中铁二院工程集团有限责任公司 Stable excavating method for cracked weak rock road cutting high slope
JP2009150084A (en) * 2007-12-19 2009-07-09 Nishimatsu Constr Co Ltd Method of reinforcing slope and method of building frame
JP5619659B2 (en) * 2011-03-24 2014-11-05 株式会社熊谷組 How to excavate the ground slope
CN102979103A (en) * 2012-12-13 2013-03-20 中国水电顾问集团成都勘测设计研究院 Step type excavating method for large unloading loose rocky side slope
CN103850257B (en) * 2014-03-21 2015-12-30 中国电建集团成都勘测设计研究院有限公司 For excavation slope body structure and the excavation construction method thereof of rock side slope
CN105089058A (en) * 2015-06-18 2015-11-25 中国电建集团贵阳勘测设计研究院有限公司 Method and device for quickly forming slag collecting platform on high and steep slope

Also Published As

Publication number Publication date
CN106284363A (en) 2017-01-04

Similar Documents

Publication Publication Date Title
CN103216238B (en) A kind of Opencut coal mine mining technique
CN106284363B (en) High-efficiency dangerous rock mass artificial excavation method
CN109931065B (en) Open pit coal mine throwing blasting-loosening blasting partition mining method
CN103726848B (en) Be applicable to the mining methods of recovery of gentle-inclined/inclthin thin ore body
CN109630121B (en) Steering, developing and transporting system for strip mining area
CN103527196A (en) Method for recovery of room-type coal pillar through loess filling
CN109931064B (en) An independent dumping operation method of a dragline in an open-pit coal mine
JP6653493B2 (en) Rapid tunnel construction method
CN103388478B (en) Forming method for transportation road of bucket shovel applied to open pit coal mine
CN104541650A (en) Dynamic reclamation method for open pit mine stope
CN104143284A (en) A mining model system for deep concave open-pit mines
CN105626068B (en) Help the method for dismounting of bridge in open coal mine end
RU2011149407A (en) METHOD FOR OPEN DEVELOPMENT OF MINERAL DEPOSITS DEPOSITS WITH CREATION OF DUMP OF LARGE CAPACITY AND HEIGHT IN DIFFICULT CONDITIONS
CN106089220A (en) In a kind of water, shield machine arrives and receives structure and method of reseptance
DK2761088T3 (en) PROCEDURE FOR REMOVAL OF A BALLAST BEARING ON A TRACK
CN118640013B (en) Multi-directional coordinated ore-dropping mining method for thin ore vein segmented medium-deep holes
JP2020506309A (en) Clean and efficient coal mining
CN113187502A (en) Slag discharging method for tunnel construction by drilling and blasting method
CN216342165U (en) Drilling and blasting method tunnel construction slag device
RU2278261C1 (en) Method of combined open-cut and underground steeply pitching deposit development
CN108343438B (en) A mining method for inclined ore body with variable angle cutting trench
RU2118456C1 (en) Quarry development method
RU2597237C1 (en) Method of sludge dump location on the territory of future salt dumps
CN107676131A (en) A kind of solid waste packs filling coal mining method
SU685752A1 (en) Method of forming dumps

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant