CN106268148A - A kind of air cleaning system being applicable to painting workshop - Google Patents

A kind of air cleaning system being applicable to painting workshop Download PDF

Info

Publication number
CN106268148A
CN106268148A CN201610874224.4A CN201610874224A CN106268148A CN 106268148 A CN106268148 A CN 106268148A CN 201610874224 A CN201610874224 A CN 201610874224A CN 106268148 A CN106268148 A CN 106268148A
Authority
CN
China
Prior art keywords
drainage screen
framework
fixing
spring
lower section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610874224.4A
Other languages
Chinese (zh)
Other versions
CN106268148B (en
Inventor
徐自强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yu Yu Environmental Protection Technology Co., Ltd.
Original Assignee
Chengdu Guanyu Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Guanyu Technology Co Ltd filed Critical Chengdu Guanyu Technology Co Ltd
Priority to CN201610874224.4A priority Critical patent/CN106268148B/en
Publication of CN106268148A publication Critical patent/CN106268148A/en
Application granted granted Critical
Publication of CN106268148B publication Critical patent/CN106268148B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D50/00Combinations of methods or devices for separating particles from gases or vapours
    • B01D50/60Combinations of devices covered by groups B01D46/00 and B01D47/00

Abstract

nullA kind of air cleaning system being applicable to painting workshop,Including the first frame device (1)、Preliminary defecator (2)、Water purification installation (3)、First plumbing installation (4)、Second frame device (5)、First defecator (6)、Second defecator (7)、Retracting device (8) and the 3rd defecator (9),First frame device (1) includes the first framework (11)、First pipeline (12)、First blower fan (15)、First valve (16)、First cross bar (13)、First support (14),Preliminary defecator (2) includes the first baffle plate (21)、First spongy layer (22)、First drainage screen (23),Water purification installation includes the first transverse slat、First sponge block、First spring、3rd drainage screen and the second sponge block,The present invention can carry out the most effective filtration, purification to the dust sprayed paint,Make the pollution-free environmental protection of expellant gas,Environment can be effectively protected.

Description

A kind of air cleaning system being applicable to painting workshop
Technical field
The present invention relates to environmental technology field, particularly relate to a kind of air cleaning system being applicable to painting workshop.
Background technology
At present, during some daily spray painting operations, a fan is the most aside installed, such that it is able to will spray The coating cloud produced during paint or dust are directly discharged in the air of outdoor, the behavior severe contamination of this random discharge Environment, and bring certain impact to the health of people, and affect the quality of life of neighbouring resident.
Chinese patent literature CN204684882U discloses a kind of water rotation type paint dust Environmental-protecting treater, including purifying Device housing, circulating water pool, high-pressure axial flow fan, be provided with dust-filtering room and connect with circulating water pool in described purifier shell Filtration channel one and filtration channel two, the top of described filtration channel one and filtration channel two is connected by connecting tube, described mistake One end of filter passage one is provided with air inlet, is sequentially provided with moisture separation device, water whirlpool device, water supply line inside it from top to bottom And the deflector of inner side, it being provided with water pump in described circulating water pool, described water pump is connected with water whirlpool device by water supply line, described Dust-filtering chamber interior is provided with bag filter and activated carbon filter layer, and it is outdoor that described high-pressure axial flow fan is arranged on dust-filtering The air outlet in portion, described high-pressure axial flow fan is provided with floss hole, and it can spray paint with purified treatment spray-dust and coating cloud, minimizing The pollution of environment is destroyed and damages people by dust and coating cloud, and efficiency is higher, high treating effect.But work as spray-dust relatively Time many, it is by still remaining a part of dust after the filtration of passage one and passage two, its again through bag filter with And after the filtration of active carbon layer, it is susceptible to blocking, and then affect its filter efficiency and filter effect, even can be to it time serious Cause damage, shorten its service life;Water in circulating water pool needs to recycle simultaneously, in use for some time, and pond Interior impurity increases, and affects its effect purified;And cannot be effective when impurity is deposited on bag filter and active carbon layer Disposed so that impurity is easily accumulated on the filter.
Accordingly, it is desirable to provide a kind of new technical scheme solves above-mentioned technical problem.
Summary of the invention
The problem to be solved in the present invention is to provide a kind of air cleaning system being applicable to painting workshop, including the first framework Device, preliminary defecator, water purification installation, the first plumbing installation, the second frame device, the first defecator, the second filtration Device, retracting device and the 3rd defecator, the first frame device includes the first framework, the first pipeline, the first blower fan, the first valve Door, the first cross bar, the first support, preliminary defecator includes the first baffle plate, the first spongy layer, the first drainage screen, and Water warfare fills Putting and include the first transverse slat, the first sponge block, the first spring, the 3rd drainage screen, the second sponge block, the present invention can be to the powder sprayed paint Dirt carries out the most effective filtration, purification so that environmental protection that expellant gas is pollution-free, can be effectively protected environment.
In order to solve above-mentioned technical problem, the present invention adopts the following technical scheme that
A kind of air cleaning system being applicable to painting workshop, including the first frame device, is contained in described first framework Preliminary defecator in device, it is positioned at the water purification installation on the right side of described preliminary defecator, is positioned at described first framework dress Put first plumbing installation on right side, be positioned at the second frame device below described first plumbing installation, be contained in described second frame The first defecator in body device, it is positioned at the second defecator below described first defecator, is positioned at described second frame Retracting device on the left of body device and be positioned at the 3rd defecator below described retracting device, described first frame device includes First framework, it is positioned at the first pipeline on the left of described first framework, the first blower fan being arranged on described first pipeline, the first valve Door, it is positioned at the first cross bar on the right side of described first blower fan, is positioned at the first support below described first cross bar, is positioned at described first Second pipe above framework, the first water pump being arranged on described second pipe, the second valve and be positioned at described first framework Lower section the 3rd pipeline, described preliminary defecator include the first baffle plate, be positioned at the first spongy layer on the left of described first baffle plate, It is positioned at the first drainage screen below described first spongy layer, is positioned at the second drainage screen below described first drainage screen, is contained in The first roller in described second drainage screen and some first bristles being arranged on described first roller, described water purification installation Including the first transverse slat, it is positioned at the first sponge block below described first transverse slat, is positioned at the first bullet below described first sponge block Spring, be positioned at the 3rd drainage screen on the left of described first spring, be positioned at the second sponge block above described first transverse slat, be positioned at described The second spring on the left of second sponge block, it is positioned at the second bristle on the right side of described second sponge ring, is positioned at described second sponge block Second transverse slat of top, described first plumbing installation include the 4th pipeline, the second support being arranged on described 4th pipeline, the Four valves, first fix bar, be positioned at and described first fix the first brace below bar, be positioned at the 3rd on the left of described first brace Support, described second frame device includes the second framework, is positioned at the 4th support below described second framework, is positioned at the described 4th The second brace on the right side of support, it is positioned at the 3rd brace on the left of described 4th support, is positioned at first below described 3rd brace Montant, be positioned at the second montant above described 3rd brace, be positioned at the 5th pipeline on the left of described second framework, be arranged at described The 5th valve on 5th pipeline, described first defecator includes being contained in the second rolling of the left and right sides in described second framework Wheel, the third bristle being arranged on described second roller, the first elastic plate between described second roller, it is positioned at described the 4th drainage screen of the one elastic plate left and right sides, the second elastic plate between described 4th drainage screen, it is positioned at described second The 3rd spring above elastic plate, it is positioned at the 5th drainage screen below described second elastic plate and is positioned under described 5th drainage screen 3rd transverse slat of side, described second defecator includes the first swash plate, is positioned at the second baffle on the left of described first swash plate, is positioned at Third gear plate on the left of described second baffle, it is positioned at the 6th drainage screen on the right side of described first swash plate, is positioned at described first swash plate 7th drainage screen of lower section, it is positioned at the 4th spring on the left of described 7th drainage screen, is positioned at the on the right side of described 7th drainage screen Three rollers and be arranged at some projections of described 3rd roller, described retracting device includes the second cross bar, to be positioned at described second horizontal The 3rd cross bar on the left of bar, it is positioned at the 5th spring below described 3rd cross bar, is positioned at the 6th bullet above described 3rd cross bar Spring, being positioned at the collection box on the left of described 6th spring, described 3rd defecator includes the 3rd framework, is positioned at described 3rd framework Lower section discharge pipe, the 8th drainage screen being contained in described 3rd framework, be positioned at the bracing wire below described 8th drainage screen, position Below described 8th drainage screen the collecting board of the left and right sides, be positioned at the motor below described bracing wire, be positioned at below described motor Gripper shoe, be positioned at the 7th spring below described gripper shoe, described first framework be provided be positioned at its left surface first lead to Hole, it is positioned at the second through hole of its upper surface, is positioned at the third through-hole on its right surface and is positioned at the fourth hole of its lower surface, described Second framework is provided with the clematis stem hole being positioned at its upper surface and the 7th through hole being positioned at its left surface, and described first baffle plate sets There is the fifth hole running through surface around.
Described first framework is hollow shape, the right-hand member of described first pipeline be directed at described first through hole and with described first frame The left surface of body is fixing to be connected, and described first cross bar is horizontal, and the left end of described first cross bar is fixed with described first blower fan Connecting, the right-hand member of described first cross bar is fixing with the left surface of described first framework to be connected, and described first support is L-shaped, described One end of first support is fixing with described first cross bar to be connected, the other end of described first support and the left-handed watch of described first framework Face is fixing to be connected, and the second through hole described in the lower end aligned of described second pipe and the upper surface with described first framework are fixed even Connecing, described 3rd pipeline is vertical shape, the upper end of described 3rd pipeline be directed at described fourth hole and with described first framework Lower surface is fixing to be connected, and described 3rd pipeline is provided with the 3rd valve.
Described first baffle plate is in vertically placing, and described first baffle plate is fixing with the inner surface of described first framework to be connected, institute Stating the first baffle plate and be positioned at the left side of fourth hole, described first spongy layer is horizontal, the left surface of described first spongy layer with The inner surface of described first framework is fixing to be connected, and the left surface of the right surface of described first spongy layer and described first baffle plate is fixed Connecting, described first drainage screen is horizontal, and the left surface of the right surface of described first drainage screen and described first baffle plate is fixed Connecting, the right surface of described first drainage screen is fixing with the left surface of described first baffle plate to be connected, under described first spongy layer The upper surface of surface and described first drainage screen is fixing to be connected, and described second drainage screen is hollow round table-like, described second mistake The lower surface of filter screen is fixing with the inner surface of described first framework to be connected, and described first roller is spherical, and described first roller is received In being dissolved in described second drainage screen and turning with its axle and be connected, described first bristle is provided with several, and described first bristle uniformly divides Cloth is on described first roller and is secured to connect.
Described first transverse slat is horizontal, and the left end of described first transverse slat is fixing with the right surface of described first baffle plate to be connected Connecing, the inner surface of the right-hand member of described first transverse slat and described first framework is fixing to be connected, and the right-hand member of described first transverse slat is provided with the One groove, described first sponge block is horizontal, and the right surface of described first sponge block is solid with the inner surface of described first framework Fixed connection, the upper surface of described first sponge block is fixing with the lower surface of described first transverse slat to be connected, described first sponge block position In the lower section of described first groove, described first spring is provided with two, and described first spring is vertical shape, described first spring Lower end is fixing with the inner surface of described first framework to be connected, the upper end of described first spring and the lower surface of described first sponge block Fixing connection, the cross section of described 3rd drainage screen is semi-annular shape, and the upper surface of described 3rd drainage screen is horizontal with described first The lower surface of plate is fixing to be connected, and described 3rd drainage screen acts against on the inner surface of described first framework, described second sponge block Cross section be ellipticity, described second sponge block is between described first transverse slat and the second transverse slat and is slidably connected with it, Described second spring is provided with two, and described second spring is horizontal, the left end of described second spring and described first baffle plate Right surface is fixing to be connected, and the right-hand member of described second spring is fixing with described second sponge block to be connected, if described second bristle is provided with Dry, described second bristle is horizontal, and the left end of described second bristle is fixing with described second sponge block to be connected, and described second Transverse slat is horizontal, and the right-hand member of described second transverse slat is fixing with the inner surface of described first framework to be connected, described second transverse slat Left end is fixing with the right surface of described first baffle plate to be connected, and the left end of described second transverse slat is provided with the second groove.
The upper end of described 4th pipeline is directed at described third through-hole and fixing with the right surface of described first framework is connected, institute The lower end stating the 4th pipeline is vertical shape, and described second support is L-shaped, the lower end of described second support and described first framework Right surface is fixing to be connected, and the upper end of described second support is vertical shape, and described 4th pipeline runs through the left and right of described second support Surface and be secured to connect, described first to fix bar horizontal, and described first fixes the left end of bar and described first framework Right surface fixing connect, described 4th pipeline runs through the described first upper and lower surface fixing bar and is secured to connect, described The first inclined shape of brace, the upper end of described first brace is fixing with the lower surface of described first framework to be connected, described 3rd Frame is L-shaped, and the upper end of described 3rd support and the lower surface of described first framework are fixing to be connected, the lower end of described 3rd support in Horizontal.
Described second framework is hollow cuboid, and described second framework is vertically placed, the lower end pair of described 4th pipeline Accurate described clematis stem hole and fixing with the upper surface of described second framework being connected, the lower end of described first brace and described second frame The upper surface of body is fixing to be connected, and the lower end of described 3rd support is fixing with the left surface of described second framework to be connected, and the described 4th Support is L-shaped, and the upper end of described 4th support is fixing with the lower surface of described second framework to be connected, the lower end of described 4th support Horizontal, the described second inclined shape of brace, the upper end of described second brace is fixing with the lower surface of described second framework to be connected Connecing, the lower end of described second brace is fixing with the right surface of described 4th support to be connected, and the described 3rd inclined shape of brace is described The upper end of the 3rd brace is fixing with the lower surface of described second framework to be connected, and described first montant is vertical shape, and described first erects The upper end of bar is fixing with described 3rd brace to be connected, and the lower end of described first montant is fixing with described 4th support to be connected, described Second montant is vertical shape, and the upper end of described second montant is fixing with the lower surface of described 3rd support to be connected, and described second erects The lower end of bar is fixing with described 3rd brace to be connected, and the right-hand member of described 5th pipeline is directed at described 7th through hole and with described second The left surface of framework is fixing to be connected.
Described second roller is provided with two, and described second roller is cylinder, and described second roller is contained in described second In framework and turning with described second framework axle and be connected, described third bristle is provided with several, and described third bristle is evenly distributed on On described second roller and be secured to connect, described first elastic plate is cuboid and horizontal positioned, described first elastic plate Being positioned at the lower section in described clematis stem hole, described 4th drainage screen is provided with two, the described 4th inclined shape of drainage screen, and the described 4th The lower end of drainage screen is fixing with the inner surface of described second framework to be connected, and the upper end of described 4th drainage screen is elastic with described first The right-hand member of plate is fixing to be connected, and described second elastic plate is cuboid and horizontal positioned, and described 3rd spring is provided with two, and described the Three springs are vertical shape, and the upper end of described 3rd spring is fixing with the lower surface of described first elastic plate to be connected, described 3rd bullet The upper surface of the lower end of spring and described second elastic plate is fixing to be connected, described 5th drainage screen be cross section be the cylinder of annulus, Described 5th drainage screen is vertical shape, and the upper surface of described 5th drainage screen is fixing with the lower surface of described second elastic plate even Connecing, the lower surface of described 5th drainage screen is fixing with the upper surface of described 3rd transverse slat to be connected, and described 3rd transverse slat is cuboid And horizontal positioned, the side of described 3rd transverse slat is fixing with the inner surface of described second framework to be connected, and described 3rd transverse slat sets Having the 8th through hole running through its upper and lower surface, described 8th through hole is positioned at the lower section of described 5th drainage screen.
Described second baffle is cuboid and vertically places, under the upper surface of described second baffle and described 3rd transverse slat Surface is fixing to be connected, and the lower surface of described second baffle is fixing with the inner surface of described second framework to be connected, described second baffle Being provided with the 9th through hole running through surface around, described third gear plate is cuboid and horizontal positioned, described third gear plate Left surface is fixing with the inner surface of described second framework to be connected, the right surface of described third gear plate and the left-handed watch of described second baffle Face is fixing to be connected, and the described first inclined shape of swash plate, the upper end of described first swash plate is fixed with the right surface of described second baffle Connecting, described 6th drainage screen is wavy, and the left end of described 6th drainage screen and described first swash plate are fixed and be connected, and described the The right-hand member of six drainage screens is fixing with the inner surface of described second framework to be connected, and described 7th drainage screen is bending, and the described 7th The lower end of drainage screen is fixing with the inner surface of described second framework to be connected, the upper end of described 7th drainage screen and described first swash plate Fixing connecting, described 4th spring is provided with two, and described 4th spring is horizontal, the right-hand member of described 4th spring and described the Seven drainage screens are fixing to be connected, and the left end of described 4th drainage screen is fixing with the right surface of described second baffle to be connected, and the described 3rd Roller is cylinder, and described 3rd roller turns with described second framework axle and is connected, and described projection is provided with several, and described projection is equal Even be distributed on described 3rd roller and be secured to connect.
Described second cross bar is cuboid and horizontal positioned, the right-hand member of described second cross bar and the left-handed watch of described second framework Face is fixing to be connected, and the left end of described second cross bar is fixing with the right surface of described second montant to be connected, and described 3rd cross bar is length Cube and horizontal positioned, the right-hand member of described 3rd cross bar is fixing with the left surface of described second montant to be connected, described 5th spring In vertical shape, the upper end of described 5th spring is fixing with the lower surface of described 3rd cross bar to be connected, the lower end of described 5th spring Fixing with described 5th pipeline and be connected, described 6th spring is horizontal, the right-hand member of described 6th spring and described second montant Left surface fixing connect, the left end of described 6th spring is fixed with described collection box and is connected, and described collection box is hollow length Cube, the lower surface of described collection box is connected with the upper surface slide of described 3rd cross bar, and described collection box is positioned at the described 3rd The lower section of pipeline.
Described 3rd framework is hollow cylinder, and described 3rd framework is provided with the first circular hole and the second circular hole, described The left end of the 5th pipeline is directed at described first through hole and fixing with the outer surface of described 3rd framework is connected, described 4th support Lower end is fixing with described 3rd framework to be connected, and the lower end of described 3rd brace is fixing with described 3rd framework to be connected, described discharge Pipe is vertical shape, and the upper end of described discharge pipe is directed at described second circular hole and fixing with the outer surface of described 3rd framework is connected, Described discharge pipe is provided with the 6th valve, and the cross section of described 8th drainage screen is in the shape of the letter V, the side of described 8th drainage screen with The inner surface of described 3rd framework is slidably connected, and described collecting board is provided with two and lays respectively at the left and right in described 3rd framework Both sides, the inclined shape of described collecting board, the lower end of described collecting board is fixing with the inner surface of described 3rd framework to be connected, described receipts Collection plate is provided with the 8th spring being positioned above, and described 8th spring is vertical shape, and the lower end of described 8th spring is with described Collecting board is fixing to be connected, and the upper end of described 8th spring is fixing with the lower surface of described 8th drainage screen to be connected, described gripper shoe Horizontal and between described collecting board, the side of described gripper shoe is fixing with described collecting board to be connected, described gripper shoe Being provided with some the 3rd circular holes running through its upper and lower surface, the lower surface of described motor is fixing with the upper surface of described gripper shoe to be connected Connecing, described motor is provided with output shaft, and described output shaft is cylinder and is connected with described motor, the upper end of described bracing wire and institute Stating the fixing connection of the 8th drainage screen, the lower end of described bracing wire is fixing with described output shaft to be connected, and described 7th spring is provided with two, Described 7th spring is vertical shape, and the upper end of described 7th spring is fixing with the lower surface of described gripper shoe to be connected, and the described 7th The lower end of spring is fixing with the inner surface of described 3rd framework to be connected.
After using technique scheme, the air cleaning system being applicable to painting workshop that the present invention proposes has the most excellent Point:
The air cleaning system simple in construction being applicable to painting workshop that the present invention proposes, easy to use, it is possible to spraying paint Dust carry out thoroughly effective filtration, purification so that environmental protection that expellant gas is pollution-free, environment can be effectively protected;This The bright filtration that can first be carried out by the dust of suction substantially, then makes it sufficiently contact with purifying water, purification water now Impurity is less, can preferably purify dust, and it is longer to purify the time that water contacts with dust, and clean-up effect shows Write, then the water after purifying can be reclaimed, prevent from directly discharging environment, then dust can be carried out Fully filter, can effectively prevent dust from blocking drainage screen in the filtration filtered, and dust can be brought together, Prevent it to be deposited on drainage screen and cause blocking drainage screen, drainage screen is served preferable protective effect, extend it and use the longevity Life.
Accompanying drawing explanation
Below in conjunction with the accompanying drawings proposition of the present invention is applicable to the detailed description of the invention of the air cleaning system of painting workshop It is described further:
Fig. 1 is the structural representation of the air cleaning system being applicable to painting workshop that the present invention proposes;
In figure: 1-the first frame device;11-the first framework;111-the first through hole;112-the second through hole;113-threeway Hole;114-fourth hole;12-the first pipeline;13-the first cross bar;14-the first support;15-the first blower fan;16-the first valve; 17-second pipe;18-the first water pump;19-the second valve;10-the 3rd pipeline;101-the 3rd valve;The preliminary defecator of 2-; 21-the first baffle plate;211-fifth hole;22-the first spongy layer;23-the first drainage screen;24-the second drainage screen;25-first rolls Wheel;3-water purification installation;31-the first transverse slat;311-the first groove;32-the first sponge block;33-the first spring;34-the 3rd mistake Filter screen;35-the second sponge block;36-the second transverse slat;361-the second groove;37-the second spring;4-the first plumbing installation;41- Four pipelines;42-the second support;43-the 4th valve;44-first fixes bar;45-the first brace;46-the 3rd support;5-the second frame Body device;51-the second framework;511-clematis stem hole;512-the 7th through hole;53-the 4th support;54-the second brace;55-the 3rd Brace;56-the first montant;57-the second montant;58-the 5th pipeline;59-the 5th valve;6-the first defecator;61-second rolls Wheel;62-third bristle;63-the first elastic plate;64-the 4th drainage screen;65-the second elastic plate;66-the 3rd spring;67-the 5th Drainage screen;68-the 3rd transverse slat;681-the 8th through hole;7-the second defecator;71-the first swash plate;72-second baffle;721- Nine through holes;73-third gear plate;74-the 6th drainage screen;75-the 7th drainage screen;76-the 4th spring;77-the 3rd roller;78-is convex Block;8-retracting device;81-the second cross bar;82-the 3rd cross bar;83-the 5th spring;84-the 6th spring;85-collection box;9- Three defecators;91-the 3rd framework;911-the first circular hole;912-the second circular hole;92-discharge pipe;921-the 6th valve;93- Eight drainage screens;94-bracing wire;95-collecting board;951-the 8th spring;96-motor;961-output shaft;97-gripper shoe;971-the 3rd Circular hole;98-the 7th spring.
Detailed description of the invention
As it is shown in figure 1, the present invention propose the air cleaning system being applicable to painting workshop include the first frame device 1, It is contained in the preliminary defecator 2 in described first frame device 1, is positioned at the Water warfare dress on the right side of described preliminary defecator 2 Put 3, be positioned at the first plumbing installation 4 on the right side of described first frame device 1, be positioned at second below described first plumbing installation 4 Frame device 5, the first defecator 6 being contained in described second frame device 5, it is positioned at below described first defecator 6 The second defecator 7, be positioned at the retracting device 8 on the left of described second frame device 5 and be positioned at below described retracting device 8 3rd defecator 9.
As it is shown in figure 1, described first frame device 1 includes the first framework 11, is positioned on the left of described first framework 11 One pipeline 12, first blower fan the 15, first valve 16 being arranged on described first pipeline 12, it is positioned on the right side of described first blower fan 15 The first cross bar 13, be positioned at the first support 14 below described first cross bar 13, be positioned at second above described first framework 11 Pipeline 17, first water pump the 18, second valve 19 being arranged on described second pipe 17 and be positioned at below described first framework 11 The 3rd pipeline 10.Described first framework 11 is in hollow shape, and the cross section of described first framework 11 is isosceles trapezoid, and described first Framework 11 is provided with the first through hole 111 being positioned at its left surface, be positioned at its upper surface the second through hole 112, it is positioned at its right surface Third through-hole 113 and be positioned at the fourth hole 114 of its lower surface, described first through hole the 111, second through hole 112, third through-hole 113 and fourth hole 114 is rounded and communicates with the inside of described first framework 11.The right-hand member of described first pipeline 12 is directed at institute State the first through hole 11 and fixing with the left surface of described first framework 11 be connected so that the inside of described first pipeline 12 is with described The inside of the first framework 11 communicates.Described first blower fan 15 is electrically connected with the power supply, and described first blower fan 15 is for by the external world Air is pumped in described first pipeline 12.Described first valve 16 flow of gas in controlling described first pipeline 12. Described first cross bar 13 is horizontal, and the left end of described first cross bar 13 is fixing with described first blower fan 15 to be connected, and described first The right-hand member of cross bar 13 is fixing with the left surface of described first framework 11 to be connected.Described first support 14 is L-shaped, described first support One end of 14 is fixing with described first cross bar 13 to be connected, the other end of described first support 14 and the left-handed watch of described first framework 11 Face is fixing to be connected.Second through hole 112 described in the lower end aligned of described second pipe 17 and the upper surface with described first framework 11 Fixing connection so that the inside of described second pipe 17 communicates with the inside of described first framework 11, described second pipe 17 The other end is placed in pond.Described first water pump 18 is electrically connected with the power supply so that the water in pond can be drawn into institute State in second pipe 17.Described second valve 19 flow of water in controlling described second pipe 17.Described 3rd pipeline 10 In vertical shape, the upper end of described 3rd pipeline 10 is directed at described fourth hole 114 and the lower surface with described first framework 11 is consolidated Fixed connection so that the inside of described 3rd pipeline 10 communicates with the inside of described first framework 11, and described 3rd pipeline 10 sets Having the 3rd valve 101, it is the flow of water in controlling described 3rd pipeline 10.
As it is shown in figure 1, described preliminary defecator 2 includes the first baffle plate 21, is positioned on the left of described first baffle plate 21 One spongy layer 22, it is positioned at the first drainage screen 23 below described first spongy layer 22, is positioned at below described first drainage screen 23 If the second drainage screen 24, the first roller 25 being contained in described second drainage screen 24 and be arranged on described first roller 25 Dry first bristle.Described first baffle plate 21 is in vertically placing, and described first baffle plate 21 is solid with the inner surface of described first framework 11 Fixed connection, described first baffle plate 21 is positioned at the left side of fourth hole 114, and described first baffle plate 21 is by described first framework 11 Space is divided into left and right two parts, and described first baffle plate 21 is provided with the fifth hole 211 running through surface around, described five-way Hole 211 is square.Described first spongy layer 22 is horizontal, the left surface of described first spongy layer 22 and described first framework 11 Inner surface fixing connect, the right surface of described first spongy layer 22 is fixed with the left surface of described first baffle plate 21 and is connected.Institute Stating the first drainage screen 23 horizontal, the right surface of described first drainage screen 23 is fixing with the left surface of described first baffle plate 21 to be connected Connecing, the right surface of described first drainage screen 23 is fixing with the left surface of described first baffle plate 21 to be connected, described first spongy layer 22 The upper surface of lower surface and described first drainage screen 23 fixing be connected.Described second drainage screen 24 in hollow round table-like, institute The inner surface of the lower surface and described first framework 11 of stating the second drainage screen 24 is fixed and is connected, and described second drainage screen 24 can be right Air filters.Described first roller 25 in spherical, in described first roller 25 is contained in described second drainage screen 24 and with Its axle turns connection so that described first roller 25 can rotate in described second drainage screen 24, described first roller 25 and electricity Machine connects, and drives described first roller 25 to rotate.Described first bristle is provided with several, and described first bristle is evenly distributed on institute Stating on the first roller 25 and be secured to connect, described first bristle can contact with the inner surface of described second drainage screen 24.
As it is shown in figure 1, described water purification installation 3 includes the first transverse slat 31, is positioned at first below described first transverse slat 31 Sponge block 32, it is positioned at the first spring 33 below described first sponge block 32, is positioned at the 3rd mistake on the left of described first spring 33 Filter screen 34, it is positioned at the second sponge block 35 above described first transverse slat 31, is positioned at the second bullet on the left of described second sponge block 35 Spring 37, it is positioned at the second bristle on the right side of described second sponge ring 35, is positioned at the second transverse slat 36 above described second sponge block 35. Described first transverse slat 31 is horizontal, and the left end of described first transverse slat 31 is fixing with the right surface of described first baffle plate 21 to be connected, The right-hand member of described first transverse slat 31 is fixing with the inner surface of described first framework 11 to be connected, and the right-hand member of described first transverse slat 31 is provided with First groove 311.Described first sponge block 32 is horizontal, the right surface of described first sponge block 32 and described first framework 11 Inner surface fixing connect, the upper surface of described first sponge block 32 is fixed with the lower surface of described first transverse slat 31 and is connected, institute State the first sponge block 32 and be positioned at the lower section of described first groove 311, such that it is able to block described first groove 311.Described first Spring 33 is provided with two, described first spring 33 in vertical shape, the lower end of described first spring 33 and described first framework 11 Inner surface is fixing to be connected, and the upper end of described first spring 33 is fixing with the lower surface of described first sponge block 32 to be connected, thus right Described first sponge block 32 is played a supporting role.The cross section of described 3rd drainage screen 34 is semi-annular shape, and the described 3rd filters The upper surface of net 34 is fixing with the lower surface of described first transverse slat 31 to be connected, and described 3rd drainage screen 34 acts against described first frame On the inner surface of body 11 so that it is right that the air on the left of described 3rd drainage screen 34 needs just to enter into it after it filters Side.The cross section of described second sponge block 35 is ellipticity, and described second sponge block 35 is in described first transverse slat 31 and second It is slidably connected between transverse slat 36 and with it so that what described second sponge block 35 can be stable moves left and right.Described second spring 37 are provided with two, and described second spring 37 is horizontal, the left end of described second spring 37 and the right table of described first baffle plate 21 Face is fixing to be connected, and the right-hand member of described second spring 37 is fixing with described second sponge block 35 to be connected, thus to described second sponge Block 35 is played a supporting role.Described second bristle is provided with several, and described second bristle is horizontal, a left side for described second bristle Hold be connected fixing with described second sponge block 35.Described second transverse slat 36 is horizontal, the right-hand member of described second transverse slat 36 and institute Stating that the inner surface of the first framework 11 is fixing to be connected, the right surface of the left end of described second transverse slat 36 and described first baffle plate 21 is fixed Connecting, the left end of described second transverse slat 36 is provided with the second groove 361.
As it is shown in figure 1, described first plumbing installation 4 include the 4th pipeline 41, be arranged on described 4th pipeline 41 Two support the 42, the 4th valves 43, first fix bar 44, be positioned at and described first fix the first brace 45 below bar 44, be positioned at institute State the 3rd support 46 on the left of the first brace 45.The upper end of described 4th pipeline 41 is directed at described third through-hole 113 and with described The right surface of the first framework 11 is fixing to be connected so that the inside of described 4th pipeline 41 and the inside phase of described 4th pipeline 41 Logical, the lower end of described 4th pipeline 41 is vertical shape.Described second support 42 is L-shaped, the lower end of described second support 42 and institute Stating the fixing connection in right surface of the first framework 11, the upper end of described second support 42 is vertical shape, and described 4th pipeline 41 runs through The surface, left and right of described second support 42 and be secured to connect.Described 4th valve 43 is used for controlling in described 4th pipeline 41 The flow of gas.Described first to fix bar 44 horizontal, and described first fixes the left end of bar 44 and described first framework 11 Right surface is fixing to be connected, and described 4th pipeline 41 runs through the described first upper and lower surface fixing bar 44 and is secured to connect, from And described 4th pipeline 41 is played fixation.The described first inclined shape of brace 45, the upper end of described first brace 45 with The lower surface of described first framework 11 is fixing to be connected.Described 3rd support 46 is L-shaped, and the upper end of described 3rd support 46 is with described The lower surface of the first framework 11 is fixing to be connected, and the lower end of described 3rd support 46 is horizontal.
As it is shown in figure 1, described second frame device 5 includes the second framework 51, is positioned at below described second framework 51 Four supports 53, it is positioned at the second brace 54 on the right side of described 4th support 53, is positioned at the 3rd brace on the left of described 4th support 53 55, it is positioned at the first montant 56 below described 3rd brace 55, is positioned at the second montant 57 above described 3rd brace 55, is positioned at The 5th pipeline 58 on the left of described second framework 51, the 5th valve 59 being arranged on described 5th pipeline 58.Described second frame Body 51 is in hollow cuboid, and described second framework 51 is vertically placed, and described second framework 51 is provided with and is positioned at its upper surface Clematis stem hole 511 and be positioned at the 7th through hole 512 of its left surface, described clematis stem hole 511 and the 7th through hole 512 is rounded and with The inside of described second framework 51 communicates, clematis stem hole 511 described in the lower end aligned of described 4th pipeline 41 and with described second The upper surface of framework 51 is fixing to be connected so that the inside of described 4th pipeline 41 communicates with the inside of described second framework 51, institute The upper surface of the lower end and described second framework 51 of stating the first brace 45 is fixed and is connected, and the lower end of described 3rd support 46 is with described The left surface of the second framework 51 is fixing to be connected.Described 4th support 53 is L-shaped, the upper end and described second of described 4th support 53 The lower surface of framework 51 is fixing to be connected, and the lower end of described 4th support 53 is horizontal.The described second inclined shape of brace 54, institute The lower surface of the upper end and described second framework 51 of stating the second brace 54 is fixed and is connected, and the lower end of described second brace 54 is with described The right surface of the 4th support 53 is fixing to be connected.The described 3rd inclined shape of brace 55, the upper end of described 3rd brace 55 is with described The lower surface of the second framework 51 is fixing to be connected.Described first montant 56 is in vertical shape, and the upper end of described first montant 56 is with described 3rd brace 55 is fixing to be connected, and the lower end of described first montant 56 is fixing with described 4th support 53 to be connected.Described second montant 57 in vertical shape, and the upper end of described second montant 57 is fixing with the lower surface of described 3rd support 46 to be connected, described second montant The lower end of 57 is fixing with described 3rd brace 55 to be connected.The right-hand member of described 5th pipeline 58 be directed at described 7th through hole 512 and with The left surface of described second framework 51 is fixing to be connected so that the inside of described 5th pipeline 58 and the inside of described second framework 51 Communicate.Described 5th valve 59 flow of gas in controlling described 5th pipeline 58.
As it is shown in figure 1, described first defecator 6 includes being contained in the second rolling of the left and right sides in described second framework 51 Wheel 61, the third bristle 62 that is arranged on described second roller 61, the first elastic plate 63 between described second roller 61, The 4th drainage screen 64 of described first elastic plate 63 left and right sides, second elastic between described 4th drainage screen 64 Plate 65, it is positioned at the 3rd spring 66 above described second elastic plate 65, is positioned at the 5th filtration below described second elastic plate 65 Net 67 and be positioned at the 3rd transverse slat 68 below described 5th drainage screen 67.Described second roller 61 is provided with two, described second rolling Wheel 61, in cylinder, in described second roller 61 is contained in described second framework 51 and turns with described second framework 51 axle and is connected, Described second roller 61 can be rotated in described second framework 51, and described second roller 61 is connected with motor, drives institute State the second roller 61 to rotate.Described third bristle 62 is provided with several, and described third bristle 62 is evenly distributed on described second rolling Take turns on 61 and be secured to connect.Described first elastic plate 63 is in cuboid and horizontal positioned, before described first elastic plate 63 Rear surface is slidably connected with the inner surface of described second framework 51, and described first elastic plate 63 is positioned at described clematis stem hole 511 Lower section.Described 4th drainage screen 64 is provided with two, the described 4th inclined shape of drainage screen 64, the lower end of described 4th drainage screen 64 Fix with the inner surface of described second framework 51 and be connected, the upper end of described 4th drainage screen 64 and the right side of described first elastic plate 63 End is fixing to be connected, thus plays a supporting role described first elastic plate 63.Described second elastic plate 65 is in cuboid and level Placing, described first elastic plate 63 uses elastomeric material to make with described second elastic plate 65 and elastic deformation can occur.Institute State the 3rd spring 66 and be provided with two, described 3rd spring 66 in vertical shape, the upper end of described 3rd spring 66 and described first bullet Property plate 63 lower surface fixing connect, the lower end of described 3rd spring 66 with the upper surface of described second elastic plate 65 fixing even Connect.Described 5th drainage screen 67 is the cylinder of annulus in cross section, and described 5th drainage screen 67 is in vertical shape, and the described 5th filters The upper surface of net 67 is fixing with the lower surface of described second elastic plate 65 to be connected, and the lower surface of described 5th drainage screen 67 is with described The upper surface of the 3rd transverse slat 68 is fixing to be connected, and air can be filtered by described 5th drainage screen 67.Described 3rd transverse slat 68 In cuboid and horizontal positioned, the side of described 3rd transverse slat 68 is fixing with the inner surface of described second framework 51 to be connected, described 3rd transverse slat 68 is provided with the 8th through hole 681 running through its upper and lower surface, and described 8th through hole 681 is positioned at described 5th drainage screen The lower section of 67.
As it is shown in figure 1, described second defecator 7 includes the first swash plate 71, is positioned on the left of described first swash plate 71 Two baffle plates 72, it is positioned at the third gear plate 73 on the left of described second baffle 72, is positioned at the 6th filtration on the right side of described first swash plate 71 Net 74, it is positioned at the 7th drainage screen 75 below described first swash plate 71, is positioned at the 4th spring on the left of described 7th drainage screen 75 76, it is positioned at the 3rd roller 77 on the right side of described 7th drainage screen 75 and is arranged at the some projections 78 on described 3rd roller 77. Described second baffle 72 in cuboid and is vertically placed, the upper surface of described second baffle 72 and the following table of described 3rd transverse slat 68 Face is fixing to be connected, and the lower surface of described second baffle 72 is fixing with the inner surface of described second framework 51 to be connected, described second gear Space below described 3rd transverse slat 68 can be divided into left and right two parts by plate 72, and described second baffle 72 is provided with and runs through its left side 9th through hole 721 on right surface.Described third gear plate 73 in cuboid and horizontal positioned, the left surface of described third gear plate 73 with The inner surface of described second framework 51 is fixing to be connected, the right surface of described third gear plate 73 and the left surface of described second baffle 72 Fixing connection.The described first inclined shape of swash plate 71, the upper end of described first swash plate 71 and the right surface of described second baffle 72 Fixing connection, described first swash plate 71 is positioned at the lower section of described 8th through hole 681.Described 6th drainage screen 74 in wavy, institute State that the left end of the 6th drainage screen 74 is fixing with described first swash plate 71 to be connected, the right-hand member and described second of described 6th drainage screen 74 The inner surface of framework 51 is fixing to be connected, and described 6th drainage screen 74 uses elastomeric material to make so that described 6th drainage screen 74 Elastic deformation can occur.Described 7th drainage screen 75 in bending, the lower end of described 7th drainage screen 75 and described second frame The inner surface of body 51 is fixing to be connected, and the upper end of described 7th drainage screen 75 is fixing with described first swash plate 71 to be connected, and the described 7th Drainage screen 75 uses elastomeric material to make so that described 7th drainage screen 75 can occur elastic deformation.Described 4th spring 76 Being provided with two, described 4th spring 76 is horizontal, and the right-hand member of described 4th spring 76 is fixing even with described 7th drainage screen 75 Connecing, the left end of described 4th drainage screen 76 is fixing with the right surface of described second baffle 72 to be connected.Described 3rd roller 77 is in circle Cylinder, described 3rd roller 77 turns with described second framework 51 axle and is connected so that described 3rd roller 77 can be described second Framework 51 rotates, and described 3rd roller 77 is connected with motor, drives described 3rd roller 77 to rotate.Described projection 78 is provided with some Individual, described projection 78 is evenly distributed on described 3rd roller 77 and is secured to connect.
As it is shown in figure 1, described retracting device 8 includes the second cross bar 81, is positioned at the 3rd horizontal stroke on the left of described second cross bar 81 Bar 82, it is positioned at the 5th spring 83 below described 3rd cross bar 82, is positioned at the 6th spring 84 above described 3rd cross bar 82, position Collection box 85 on the left of described 6th spring 84.Described second cross bar 81 is in cuboid and horizontal positioned, described second cross bar The right-hand member of 81 is fixing with the left surface of described second framework 51 to be connected, the left end of described second cross bar 81 and described second montant 57 Right surface fixing connect.Described 3rd cross bar 82 is in cuboid and horizontal positioned, and the right-hand member of described 3rd cross bar 82 is with described The left surface of the second montant 57 is fixing to be connected.Described 5th spring 83 is in vertical shape, and the upper end of described 5th spring 83 is with described The lower surface of the 3rd cross bar 82 is fixing to be connected, and the lower end of described 5th spring 83 is fixing with described 5th pipeline 58 to be connected, thus Described 5th pipeline 58 is played a supporting role.Described 6th spring 84 is horizontal, the right-hand member of described 6th spring 84 and institute Stating the fixing connection in left surface of the second montant 57, the left end of described 6th spring 84 is fixing with described collection box 85 to be connected.Described Collection box 85 is in hollow cuboid, and the cross section of described collection box 85 is concave shape, the lower surface of described collection box 85 and institute The upper surface slide stating the 3rd cross bar 82 connects, and described collection box 85 is positioned at the lower section of described 3rd pipeline 10 so that discharge Liquid enters in described collection box 85.
As it is shown in figure 1, described 3rd defecator 9 includes the 3rd framework 91, is positioned at the row below described 3rd framework 91 Go out pipe 92, the 8th drainage screen 93 being contained in described 3rd framework 91, be positioned at the bracing wire 94 below described 8th drainage screen 93, It is positioned at the collecting board 95 of the left and right sides below described 8th drainage screen 93, is positioned at the motor 96 below described bracing wire 94, is positioned at institute State the gripper shoe 97 below motor 96, be positioned at the 7th spring 98 below described gripper shoe 97.Described 3rd framework 91 is in hollow Cylinder, described 3rd framework 91 is provided with the first circular hole 911 and the second circular hole 912, described first circular hole 911 and the second circle Hole 912 communicates with the inside of described 3rd framework 91, the left end of described 5th pipeline 58 be directed at described first through hole 911 and with institute State the fixing connection of outer surface of the 3rd framework 91 so that the inside of described 5th pipeline 58 and the inside phase of described 3rd framework 91 Logical, the lower end of described 4th support 53 is fixing with described 3rd framework 91 to be connected, the lower end of described 3rd brace 55 and described the Three frameworks 91 are fixing to be connected.Described discharge pipe 92 in vertical shape, the upper end of described discharge pipe 92 be directed at described second circular hole 912 and Fix with the outer surface of described 3rd framework 91 and be connected so that the inside of described discharge pipe 92 and the inside of described 3rd framework 91 Communicating, described discharge pipe 92 is provided with the 6th valve 921, and it is the flow of gas in controlling described discharge pipe 92.Described The cross section of eight drainage screens 93 is inverted V-shaped, the side of described 8th drainage screen 93 and the interior table of described 3rd framework 91 Face is slidably connected.Described collecting board 95 is provided with two and lays respectively at the left and right sides in described 3rd framework 91, described collection The inclined shape of plate 95, the lower end of described collecting board 95 is fixing with the inner surface of described 3rd framework 91 to be connected, described collecting board 95 Before and after the inner surface of surface and described 3rd framework 91 is fixing is connected, described collecting board 95 is provided with the 8th be positioned above Spring 951, described 8th spring 951 is in vertical shape, and the lower end of described 8th spring 951 is fixing with described collecting board 95 to be connected, The upper end of described 8th spring 951 is fixing with the lower surface of described 8th drainage screen 93 to be connected, thus to described 8th drainage screen 93 play a supporting role so that described 8th drainage screen 93 steadily acts against on the inner surface of described 3rd framework 91 so that Air above 8th drainage screen 93 must meet its filtration could be into its next square.Described gripper shoe 97 is horizontal and position Between described collecting board 95, the side of described gripper shoe 97 is fixing with described collecting board 95 to be connected.Set in described gripper shoe 97 There are some the 3rd circular holes 971 running through its upper and lower surface.Described motor 96 is electrically connected with the power supply, the lower surface of described motor 96 Fixing with the upper surface of described gripper shoe 97 being connected, described motor 96 is provided with output shaft 961, and described output shaft 961 is in cylinder Body and being connected with described motor 96 so that described motor 96 drives described output shaft 961 to rotate.The upper end of described bracing wire 94 and institute Stating the 8th fixing connection of drainage screen 93, the lower end of described bracing wire 94 is fixing with described output shaft 961 to be connected.Described 7th spring 98 Being provided with two, described 7th spring 98 is in vertical shape, and the upper end of described 7th spring 98 is solid with the lower surface of described gripper shoe 97 Fixed connection, the lower end of described 7th spring 98 is fixing with the inner surface of described 3rd framework 91 to be connected, thus to described gripper shoe 97 play a supporting role.
During as it is shown in figure 1, the air cleaning system being applicable to painting workshop that the present invention proposes uses, by described first pipe The left end in road 12 is directed at the position sprayed paint, and opens the first blower fan 15 and the first valve 16 so that the dust produced that sprays paint is drawn into In the first pipeline 12, being then passed through the first through hole 111 and enter in described first framework 11, its coating cloud first passes around described The filtration of one spongy layer 22, more and then filtration through described first drainage screen 23 enters into the lower section of the first drainage screen 23, Owing to air pressure when coating cloud has just enter in the first framework 11 is bigger so that the dust in gas is not easy to be deposited in described first On spongy layer 22, thus being not easy to result in blockage it, air can be entered by described first spongy layer 22 and the first drainage screen 23 The filtration that row is preliminary, disposes the impurity that wherein volume is bigger.It is entered into right after being then passed through the filtration of the second drainage screen 24 Side, is then passed through described fifth hole 211 and enters into the right side of described first baffle plate 21, start simultaneously and be connected with the first roller 25 Motor so that described first roller 25 rotates, and drives the first bristle to rotate with, such that it is able to described second drainage screen The inner surface of 24 cleans, and disposes the impurity speckled with on it, prevents it from blocking the second drainage screen 24, and can be to air Play certain filtration.Now start the first water pump 18, and open the second valve 19 so that the water in pond is drawn into In described second pipe 17, then water is in described second through hole 112 enters into described first framework 11, then focuses on institute State on the second transverse slat 36, enter into the lower section of described second transverse slat 36 through described second groove 361, the most gradually soak Two sponge blocks 35, are then passed through the first groove 311 and soak the first sponge block 32, and then water is deposited on the right side of described first baffle plate 21 And be positioned at the space below described first transverse slat 31, and soak the 3rd drainage screen 34.When deposition in the first framework 11 When water is more, open the 3rd valve 101 so that the water in the first framework 11 enters in the 3rd pipeline 10, discharges it back Receive in case 85, conveniently it is reclaimed, reduce the waste of resource.Enter into the air on the right side of described first baffle plate 21 through leaching After the filtration of the 3rd wet drainage screen 34, filtration through the first sponge block 32 enters into the top of described first transverse slat 31 again, and Can be fully contacted with water, such that it is able to sufficiently air is purified, dispose the impurity in air.Then air passes through Enter on the left of it after second bristle and the filtration of the second sponge block 35 soaked, be then passed through the second groove 361 and enter into The top of two transverse slats 36, now water constantly enters in described first framework 11 from the second through hole 112, thus water can to from The air that second groove 361 enters into above the second transverse slat 36 sufficiently filters.Enter through the abundant filtered air of water In described 4th pipeline 41, open the 4th valve 43 so that the water in the 4th pipeline 41 is drawn into described second framework 51 In.Due to the setting of the first elastic plate 63, it is directly impinging the first elastic plate 63 from the gas of clematis stem hole 511 ejection, makes Obtaining the first elastic plate 63 can occur upper and lower elastic deformation i.e. to vibrate, the most to the left and right both sides flowing, starts and the second roller 61 The motor connected so that the second roller 61 drives third bristle 62 to rotate with, such that it is able to the gas entering into the left and right sides Body filters.The vibration of the first elastic plate 63 is applied on described second elastic plate 65 by described 3rd spring 66, thus So that described second elastic plate 65 vibrates, and then described 5th drainage screen 67 is vibrated.Filter through the second bristle 62 Gas after the filtration of described 4th drainage screen 64, enter into the lower section of described first elastic plate 63 still further below, be then passed through Enter into the inside of described 5th drainage screen 67 after the filtration of described 5th drainage screen 67, then pass through described 8th through hole 681 Enter into the lower section of described 3rd transverse slat 68.Owing to the vibration of the first elastic plate 63 can also drive the 4th drainage screen 64 to vibrate, Such that it is able to prevent the impurity in air to be deposited on described 4th drainage screen 64, the vibration of the 5th drainage screen 67 can also simultaneously The impurity in air is prevented to be deposited on described 5th drainage screen 67.Enter into the air below described 3rd transverse slat 68 to bottom right Fang Liudong, moves down after being then passed through the filtration of described 6th drainage screen 74, through the lower section of the first swash plate 71 again through The left side of described 7th drainage screen 75 is entered into after the filtration of seven drainage screens 75.Start the motor being connected with the 3rd roller 77, make Obtain described 3rd roller 77 to rotate, and then described projection 78 is rotated with, revolve along with described 3rd roller 77 when projection 78 When turning, described projection 78 can touch the lower end of described first swash plate 71 so that described first swash plate 71 vibrates, and then makes institute State the 6th drainage screen 74 and the 7th drainage screen 75 vibrates, such that it is able to prevent the dust deposit in air above it so that it is can Air to be carried out normal and efficient filtration operation.Then air enters through described 9th through hole 721 and the 7th through hole 512 In described 5th pipeline 58, then open the 5th valve 59 so that the air in described 5th pipeline 58 enters into described In three frameworks 91, enter into the lower section of described 8th drainage screen 93 after being then passed through the filtration of described 8th drainage screen 93, then Enter into the lower section of described gripper shoe 97 through described 3rd circular hole 971, then in described discharge pipe 92, open the 6th Valve 921 so that the gas in discharge pipe 92 is discharged.When the impurity above described 8th drainage screen 93 is more, start motor 96 so that described output shaft 961 rotates, and then described bracing wire 94 is tightened up so that described 8th drainage screen 93 is to moving down Dynamic, owing to the 8th drainage screen 93 is in inverted V-shaped so that the impurity on described 8th drainage screen 93 filters along the described 8th The upper surface of net 93 is slipped on described collecting board 95, prevents dust deposit on the 8th drainage screen 93 so that described 8th mistake Filter screen 93 can carry out normal filtration operation to air, extends its service life.What so far the present invention proposed is applicable to spray paint The air cleaning system in workshop uses process prescription complete.
The above, the only detailed description of the invention of the present invention, but protection scope of the present invention is not limited thereto, and any Those skilled in the art, in the technical scope that the invention discloses, can readily occur in change or replace, should contain Within protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with described scope of the claims.

Claims (8)

1. it is applicable to an air cleaning system for painting workshop, including the first frame device (1), is contained in described first framework Preliminary defecator (2) in device (1), it is positioned at the water purification installation (3) on described preliminary defecator (2) right side, is positioned at institute State first plumbing installation (4) on the first frame device (1) right side, be positioned at the second framework of described first plumbing installation (4) lower section Device (5), the first defecator (6) being contained in described second frame device (5), it is positioned at described first defecator (6) Lower section the second defecator (7), be positioned at described second frame device (5) left side retracting device (8) and be positioned at described recovery Device (8) lower section the 3rd defecator (9), it is characterised in that: described first frame device (1) include the first framework (11), The first pipeline (12) being positioned at described first framework (11) left side, the first blower fan being arranged on described first pipeline (12) (15), the first valve (16), be positioned at described first blower fan (15) right side the first cross bar (13), be positioned at described first cross bar (13) Lower section the first support (14), be positioned at described first framework (11) top second pipe (17), be arranged at described second pipe (17) the first water pump (18) on, the second valve (19) and be positioned at the 3rd pipeline (10) of described first framework (11) lower section, institute State the second through hole (112) that the first framework (11) is provided with the first through hole (111) being positioned at its left surface, is positioned at its upper surface, It is positioned at the third through-hole (113) on its right surface and is positioned at the fourth hole (114) of its lower surface;Described preliminary defecator (2) Including the first baffle plate (21), be positioned at described first baffle plate (21) left side the first spongy layer (22), be positioned at described first spongy layer (22) lower section the first drainage screen (23), be positioned at described first drainage screen (23) lower section the second drainage screen (24), be contained in institute State the first roller (25) in the second drainage screen (24) and be arranged at some first bristles on described first roller (25), described First baffle plate (21) is provided with the fifth hole (211) running through surface around;Described second frame device (5) includes the second frame Body (51) and be positioned at described second framework (51) lower section the 4th support (53);Described first defecator (6) includes being contained in Second roller (61) of the interior left and right sides of described second framework (51), the third bristle being arranged on described second roller (61) (62) the first elastic plate (63) of, being positioned between described second roller (61), it is positioned at described first elastic plate (63) left and right sides The 4th drainage screen (64), the second elastic plate (65) being positioned between described 4th drainage screen (64), be positioned at described second elastic 3rd spring (66) of plate (65) top, it is positioned at the 5th drainage screen (67) of described second elastic plate (65) lower section and is positioned at described 3rd transverse slat (68) of the 5th drainage screen (67) lower section;Described second defecator (7) include the first swash plate (71), be positioned at described First swash plate (71) left side second baffle (72), be positioned at described second baffle (72) left side third gear plate (73), be positioned at institute State the first swash plate (71) right side the 6th drainage screen (74), be positioned at described first swash plate (71) lower section the 7th drainage screen (75), It is positioned at the 4th spring (76) in described 7th drainage screen (75) left side, is positioned at the 3rd roller on described 7th drainage screen (75) right side And be arranged at the some projections (78) on described 3rd roller (77) (77);Described 3rd defecator (9) includes the 3rd framework (91), it is positioned at the discharge pipe (92) of described 3rd framework (91) lower section, is contained in the 8th filtration of described 3rd framework (91) Net (93), be positioned at described 8th drainage screen (93) lower section bracing wire (94), be positioned at described 8th drainage screen (93) lower section about two The collecting board (95) of side, it is positioned at the motor (96) of described bracing wire (94) lower section, is positioned at the gripper shoe of described motor (96) lower section (97) the 7th spring (98) of described gripper shoe (97) lower section, it is positioned at.
The air cleaning system being applicable to painting workshop the most according to claim 1, it is characterised in that: the described 4th filters Net (64) is provided with two, described 4th drainage screen (64) inclined shape, the lower end and described second of described 4th drainage screen (64) The inner surface of framework (51) is fixing to be connected, and the upper end of described 4th drainage screen (64) is solid with the right-hand member of described first elastic plate (63) Fixed connecting, described second elastic plate (65) is in cuboid and horizontal positioned, and described 3rd spring (66) is provided with two, and the described 3rd Spring (66) is in vertical shape, and the upper end of described 3rd spring (66) is fixing with the lower surface of described first elastic plate (63) to be connected, The lower end of described 3rd spring (66) is fixing with the upper surface of described second elastic plate (65) to be connected.
The air cleaning system being applicable to painting workshop the most according to claim 1, it is characterised in that: the described 5th filters Net (67) is the cylinder of annulus in cross section, described 5th drainage screen (67) in vertical shape, described 5th drainage screen (67) upper Surface is fixing with the lower surface of described second elastic plate (65) to be connected, the lower surface and the described 3rd of described 5th drainage screen (67) The upper surface of transverse slat (68) is fixing to be connected, and described 3rd transverse slat (68) is in cuboid and horizontal positioned, described 3rd transverse slat (68) The inner surface of side and described second framework (51) fixing be connected, described 3rd transverse slat (68) is provided with and runs through its upper and lower surface The 8th through hole (681), described 8th through hole (681) is positioned at the lower section of described 5th drainage screen (67).
The air cleaning system being applicable to painting workshop the most according to claim 1, it is characterised in that: described second baffle (72) in cuboid and vertically placing, the lower surface of the upper surface of described second baffle (72) and described 3rd transverse slat (68) is fixed Connecting, the lower surface of described second baffle (72) is fixing with the inner surface of described second framework (51) to be connected, described second baffle (72) it is provided with and runs through the 9th through hole (721) on surface around.
The air cleaning system being applicable to painting workshop the most according to claim 1, it is characterised in that: described third gear plate (73) in cuboid and horizontal positioned, the inner surface of the left surface of described third gear plate (73) and described second framework (51) is fixed Connecting, the right surface of described third gear plate (73) is fixing with the left surface of described second baffle (72) to be connected;Described first swash plate (71) inclined shape, the upper end of described first swash plate (71) is fixing with the right surface of described second baffle (72) to be connected.
The air cleaning system being applicable to painting workshop the most according to claim 1, it is characterised in that: the described 6th filters Net (74) is in wavy, and the left end of described 6th drainage screen (74) is fixing with described first swash plate (71) to be connected, described 6th mistake The inner surface of the right-hand member of filter screen (74) and described second framework (51) is fixing to be connected, described 7th drainage screen (75) in bending, The lower end of described 7th drainage screen (75) is fixing with the inner surface of described second framework (51) to be connected, described 7th drainage screen (75) Upper end and described first swash plate (71) fixing be connected.
The air cleaning system being applicable to painting workshop the most according to claim 1, it is characterised in that: described 4th spring (76) being provided with two, described 4th spring (76) is horizontal, the right-hand member of described 4th spring (76) and described 7th drainage screen (75) fixing connection, the left end of described 4th drainage screen (76) is fixing with the right surface of described second baffle (72) to be connected, described 3rd roller (77) is in cylinder, and described 3rd roller (77) turns with described second framework (51) axle and is connected, described projection (78) Being provided with several, described projection (78) is evenly distributed on described 3rd roller (77) and above and is secured to connect.
The air cleaning system being applicable to painting workshop the most according to claim 1, it is characterised in that: described collecting board (95) it is provided with two and lays respectively at the left and right sides in described 3rd framework (91), described collecting board (95) inclined shape, institute The inner surface of the lower end and described 3rd framework (91) of stating collecting board (95) is fixed and is connected;Described collecting board (95) is provided with and is positioned at The 8th spring (951) above it, described 8th spring (951) is in vertical shape, and the lower end of described 8th spring (951) is with described Collecting board (95) is fixing to be connected, and the upper end of described 8th spring (951) is fixing with the lower surface of described 8th drainage screen (93) even Connect.
CN201610874224.4A 2016-10-03 2016-10-03 A kind of air cleaning system suitable for painting workshop Active CN106268148B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610874224.4A CN106268148B (en) 2016-10-03 2016-10-03 A kind of air cleaning system suitable for painting workshop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610874224.4A CN106268148B (en) 2016-10-03 2016-10-03 A kind of air cleaning system suitable for painting workshop

Publications (2)

Publication Number Publication Date
CN106268148A true CN106268148A (en) 2017-01-04
CN106268148B CN106268148B (en) 2018-03-27

Family

ID=57717062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610874224.4A Active CN106268148B (en) 2016-10-03 2016-10-03 A kind of air cleaning system suitable for painting workshop

Country Status (1)

Country Link
CN (1) CN106268148B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106902606A (en) * 2017-04-13 2017-06-30 深圳市玖品空气净化科技有限公司 A kind of environment-friendly type haze cleaning system for economizing on resources
CN107008091A (en) * 2017-04-18 2017-08-04 深圳市玖品空气净化科技有限公司 A kind of Air haze cleaning system of high-efficiency environment friendly

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080260574A1 (en) * 2004-08-31 2008-10-23 Kosta Kapitoures Filtration and Purification Systems
CN203123792U (en) * 2013-01-31 2013-08-14 东莞市绿羽环保净化工程有限公司 Biological waste gas treatment device
CN104998503A (en) * 2015-07-16 2015-10-28 张萍 Environmental protection type exhaust gas purification equipment high in purification efficiency
CN105749682A (en) * 2016-04-15 2016-07-13 安双志 Environment-friendly efficient dust suction device for textile spinning
CN105749678A (en) * 2016-03-09 2016-07-13 张舒维 Air purifying equipment for treating haze

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080260574A1 (en) * 2004-08-31 2008-10-23 Kosta Kapitoures Filtration and Purification Systems
CN203123792U (en) * 2013-01-31 2013-08-14 东莞市绿羽环保净化工程有限公司 Biological waste gas treatment device
CN104998503A (en) * 2015-07-16 2015-10-28 张萍 Environmental protection type exhaust gas purification equipment high in purification efficiency
CN105749678A (en) * 2016-03-09 2016-07-13 张舒维 Air purifying equipment for treating haze
CN105749682A (en) * 2016-04-15 2016-07-13 安双志 Environment-friendly efficient dust suction device for textile spinning

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106902606A (en) * 2017-04-13 2017-06-30 深圳市玖品空气净化科技有限公司 A kind of environment-friendly type haze cleaning system for economizing on resources
CN107008091A (en) * 2017-04-18 2017-08-04 深圳市玖品空气净化科技有限公司 A kind of Air haze cleaning system of high-efficiency environment friendly

Also Published As

Publication number Publication date
CN106268148B (en) 2018-03-27

Similar Documents

Publication Publication Date Title
CN105289173B (en) Gas purifier
CN208493668U (en) A kind of Automobile flywheel manufacturing shop special environment protection dust-extraction unit
CN106268148A (en) A kind of air cleaning system being applicable to painting workshop
CN106310856A (en) Indoor air purification and dust removal device
CN105854497B (en) A kind of industrial waste-gas purifier
CN108939859B (en) Medium-sized gas purification treatment equipment
CN105879554B (en) A kind of air cleaning facility
CN105854440B (en) A kind of industrial waste gas filtration purifier
CN106310857A (en) Industrial air purifying device capable of filtering paint, mist and dust
CN106731393B (en) A kind of environment friendly dedusting device
CN104722151A (en) Industrial waste gas cleaner
CN106334402A (en) Air purification system for paint spraying operation
CN106422634A (en) Improved air purification device
CN106334403A (en) Industrial dust grading filtration system for paint spraying environment
CN106731394A (en) A kind of Environmental-protecting dust-removing equipment of building engineering construction
CN208742188U (en) A kind of cleaner with decrease of noise functions
CN106268147A (en) A kind of energy filtering dust and the air purifier of fine particle
CN209801678U (en) Dust removal adsorbs uses environment-friendly air purification equipment
CN105999966A (en) Filtering and purifying system for exhaust gas generated in combustion
CN218573215U (en) Mine equipment capable of reducing dust in mining area
CN204735009U (en) Automatic cleaning apparatus
CN106178797A (en) A kind of boiler waste gas purification filtration system
CN106310854A (en) Environmental-friendly effective exhaust gas purifying treatment system
CN106268141A (en) A kind of industrial waste gas purifying processing means
CN213253443U (en) Multifunctional composite filter screen with rotatable structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Jiang Kangyi

Inventor after: Xu Shuping

Inventor before: Xu Ziqiang

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180214

Address after: Hangzhou City, Zhejiang province Yuhang District 311100 West Street Wuchang No. 998 Building 5 room 803

Applicant after: Zhejiang Yu Yu Environmental Protection Technology Co., Ltd.

Address before: Pixian Deyuan town Chengdu City, Sichuan province 611730 (Jing Rong town) Yu Road No. 66 Building 1 floor 2, No. 16 (1-2-16)

Applicant before: CHENGDU GUANYU TECHNOLOGY CO., LTD.

GR01 Patent grant
GR01 Patent grant