CN106223329A - 一种全套管旋喷桩的施工方法 - Google Patents

一种全套管旋喷桩的施工方法 Download PDF

Info

Publication number
CN106223329A
CN106223329A CN201610643527.5A CN201610643527A CN106223329A CN 106223329 A CN106223329 A CN 106223329A CN 201610643527 A CN201610643527 A CN 201610643527A CN 106223329 A CN106223329 A CN 106223329A
Authority
CN
China
Prior art keywords
pile
drill bit
center
churning
rotary churning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610643527.5A
Other languages
English (en)
Inventor
郑添寿
邱维衍
张强
孔秋平
许万强
江景云
钟志明
陈万琴
李丽琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN YONGQIANG GEOTECHNICAL Co Ltd
Original Assignee
FUJIAN YONGQIANG GEOTECHNICAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN YONGQIANG GEOTECHNICAL Co Ltd filed Critical FUJIAN YONGQIANG GEOTECHNICAL Co Ltd
Priority to CN201610643527.5A priority Critical patent/CN106223329A/zh
Publication of CN106223329A publication Critical patent/CN106223329A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Abstract

本发明涉及一种全套管旋喷桩的施工方法,其特征在于:通过定孔位中心、钻机定位、制备水泥浆、启动旋喷钻头等步骤进行旋喷桩作业,具有安装和操作简易,可以减少注浆时水泥浆液向四周土层渗透,造成浪费,而且由于增加了套管,使得桩体的整体性更好,成桩可靠。

Description

一种全套管旋喷桩的施工方法
技术领域
本发明涉及土木工程领域,一种特殊水泥土桩的施工方法,具体说是一种全套管旋喷桩的施工方法。
背景技术
高压旋喷桩施工技术是70年代日本首先提出,它是在静压灌浆的基础上,引进水力采煤技术而发展起来的,是利用射流作用切割掺搅地层,改变原地层的结构和组成,同时灌入水泥浆或复合浆形成凝结体,借以达到加固地基和防渗止水的目的。
目前,高压喷射注浆法处理地基在我国已有了广泛的应用,并制定了相应的施工设计规范;在高速公路软弱地基加固、水利工程防渗、矿山井巷加固与防渗等方面得到越来越多的应用;在一些大城市,随着地铁建设和高层建筑的崛起,不少深基坑工程亦都采用了高压喷射注浆技术来进行深基坑的止水防渗。高压喷射注浆按注浆管类型可分为单管、二重管和三重管三种方法;单管以单纯喷射水泥浆液;二重管在水泥浆液射流外面包裹一层高压空气同时喷射,来破坏土层结构,同时完成置换、填充;而三重管则是以包裹了高压空气的高压水流来破坏土层结构,再以水泥浆液进行置换、填充;但在打桩灌浆时混凝土的浆液向四周渗透,造成浪费。
发明内容
本发明是针对以上问题,提供一种全套管旋喷桩的施工方法,具有安装和操作简易,可以避免注浆时水泥浆液向桩周以外的四周土层渗透,造成浪费,而且由于增加了套管,使得桩体的整体性更好,成桩可靠。
本发明解决上述技术问题采用的以下技术方案:
一种全套管旋喷桩的施工方法,其特征在于:施工步骤如下:
第一步:以孔位中心为圆心,将预制好的直径比设计桩体稍大一点的钢结构套管,插入地下,直至设计标高以下500mm;
第二步:钻机定位。移动旋喷桩机到指定桩位(套管中心),将钻头对准孔位中心,同时整平钻机,放置平稳、水平,钻杆的垂直度偏差不大于1%~1.5%。就位后,首先进行低压(0.5MPa)射水试验,用以检查喷嘴是否畅通,压力是否正常;
第三步:制备水泥浆。桩机移位时,即开始按设计确定的配合比拌制水泥浆。首先将水加入桶中,再将水泥和外掺剂倒入,开动搅拌机搅拌10~20分钟,而后拧开搅拌桶底部阀门,放入第一道筛网(孔径为0.8mm),过滤后流入浆液池,然后通过泥浆泵抽进第二道过滤网(孔径为0.8mm),第二次过滤后流入浆液桶中,待压浆时备用;
第四步:启动旋喷钻头,钻入孔位中心,钻至设计标高后同时开启高压泥浆泵低压输送水泥浆液,使钻杆沿导向架边旋转边上拔喷射切割土体;直到桩顶设计标高以上500mm,即使得旋喷钻头在预制好的套管内作业。
第五步:补浆,喷射注浆作业完成后,由于浆液的析水作用,一般均有不同程度的收缩,使固结体顶部出现凹穴,要及时用水灰比为1.0的水泥浆补灌;
第六步:喷射注浆作业完成后,拔出旋喷钻头及钢套管,都可多次使用。
本发明的有益效果是:具有安装和操作简易,可以减少注浆时水泥浆液向四周土层渗透,造成浪费,而且由于增加了套管,使得桩体的整体性更好,成桩可靠。
附图说明
下面结合附图和实施方式对本发明做进一步的说明
图1是本发明的一种全套管旋喷桩的施工方法的施工流程图。
具体实施方式
下面结合附图和具体实施例对本发明的一种全套管旋喷桩的施工方法作进一步的描述。
如图所示,一种全套管旋喷桩的施工方法,其特征在于:施工步骤如下:
第一步:以孔位中心为圆心,将预制好的直径比设计桩体稍大一点的钢结构套管,插入地下,直至设计标高以下500mm;
第二步:钻机定位。移动旋喷桩机到指定桩位(套管中心),将钻头对准孔位中心,同时整平钻机,放置平稳、水平,钻杆的垂直度偏差不大于1%~1.5%。就位后,首先进行低压(0.5MPa)射水试验,用以检查喷嘴是否畅通,压力是否正常;
第三步:制备水泥浆。桩机移位时,即开始按设计确定的配合比拌制水泥浆。首先将水加入桶中,再将水泥和外掺剂倒入,开动搅拌机搅拌10~20分钟,而后拧开搅拌桶底部阀门,放入第一道筛网(孔径为0.8mm),过滤后流入浆液池,然后通过泥浆泵抽进第二道过滤网(孔径为0.8mm),第二次过滤后流入浆液桶中,待压浆时备用;
第四步:启动旋喷钻头,钻入孔位中心,钻至设计标高后同时开启高压泥浆泵低压输送水泥浆液,使钻杆沿导向架边旋转边上拔喷射切割土体;直到桩顶设计标高以上500mm,即使得旋喷钻头在预制好的套管内作业。
第五步:补浆,喷射注浆作业完成后,由于浆液的析水作用,一般均有不同程度的收缩,使固结体顶部出现凹穴,要及时用水灰比为1.0的水泥浆补灌;
第六步:喷射注浆作业完成后,拔出旋喷钻头及钢套管,都可多次使用。
以上所述的实施例,只是本发明较优选的具体实施方式的一种,本领域的技术人员在本发明技术方案范围内进行的通常变化和替换都应包含在本发明的保护范围内。

Claims (1)

1.一种全套管旋喷桩的施工方法,其特征在于:施工步骤如下:
第一步:以孔位中心为圆心,将预制好的直径比设计桩体稍大一点的钢结构套管,插入地下,直至设计标高以下500mm;
第二步:钻机定位。移动旋喷桩机到指定桩位(套管中心),将钻头对准孔位中心,同时整平钻机,放置平稳、水平,钻杆的垂直度偏差不大于1%~1.5%。就位后,首先进行低压(0.5MPa)射水试验,用以检查喷嘴是否畅通,压力是否正常;
第三步:制备水泥浆。桩机移位时,即开始按设计确定的配合比拌制水泥浆。首先将水加入桶中,再将水泥和外掺剂倒入,开动搅拌机搅拌10~20分钟,而后拧开搅拌桶底部阀门,放入第一道筛网(孔径为0.8mm),过滤后流入浆液池,然后通过泥浆泵抽进第二道过滤网(孔径为0.8mm),第二次过滤后流入浆液桶中,待压浆时备用;
第四步:启动旋喷钻头,钻入孔位中心,钻至设计标高后同时开启高压泥浆泵低压输送水泥浆液,使钻杆沿导向架边旋转边上拔喷射切割土体;直到桩顶设计标高以上500mm,即使得旋喷钻头在预制好的套管内作业;
第五步:补浆,喷射注浆作业完成后,由于浆液的析水作用,一般均有不同程度的收缩,使固结体顶部出现凹穴,要及时用水灰比为1.0的水泥浆补灌;
第六步:喷射注浆作业完成后,拔出旋喷钻头及钢套管,都可多次使用。
CN201610643527.5A 2016-08-08 2016-08-08 一种全套管旋喷桩的施工方法 Pending CN106223329A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610643527.5A CN106223329A (zh) 2016-08-08 2016-08-08 一种全套管旋喷桩的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610643527.5A CN106223329A (zh) 2016-08-08 2016-08-08 一种全套管旋喷桩的施工方法

Publications (1)

Publication Number Publication Date
CN106223329A true CN106223329A (zh) 2016-12-14

Family

ID=57548265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610643527.5A Pending CN106223329A (zh) 2016-08-08 2016-08-08 一种全套管旋喷桩的施工方法

Country Status (1)

Country Link
CN (1) CN106223329A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453678A (zh) * 2019-07-30 2019-11-15 甘肃恒捷路桥养护科技有限公司 一种高压旋喷桩二重管法治理黄土公路路基沉降的方法
CN110725305A (zh) * 2019-10-31 2020-01-24 上海长凯岩土工程有限公司 一种提高斜向钢管桩承载力的施工方法
CN110924385A (zh) * 2019-12-02 2020-03-27 韶关市第一建筑工程有限公司 高压旋喷桩施工工艺
WO2021103210A1 (zh) * 2019-11-29 2021-06-03 裴晓峰 一种全套管复合扩盘桩施工方法及设备

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101314945A (zh) * 2008-07-02 2008-12-03 江伟 高压旋喷扩大头预应力管桩及其组合方法
CN201288325Y (zh) * 2008-07-02 2009-08-12 江伟 高压旋喷扩大头预应力管桩
CN101603311A (zh) * 2009-07-02 2009-12-16 北京建材地质工程公司 重锤夯扩挤密土预成孔旋喷桩施工方法
CN102011399A (zh) * 2010-11-05 2011-04-13 河南理工大学 一种基于phc桩的多重高喷扩底桩施工方法
CN104153357A (zh) * 2014-08-26 2014-11-19 骆嘉成 复合桩的施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101314945A (zh) * 2008-07-02 2008-12-03 江伟 高压旋喷扩大头预应力管桩及其组合方法
CN201288325Y (zh) * 2008-07-02 2009-08-12 江伟 高压旋喷扩大头预应力管桩
CN101603311A (zh) * 2009-07-02 2009-12-16 北京建材地质工程公司 重锤夯扩挤密土预成孔旋喷桩施工方法
CN102011399A (zh) * 2010-11-05 2011-04-13 河南理工大学 一种基于phc桩的多重高喷扩底桩施工方法
CN104153357A (zh) * 2014-08-26 2014-11-19 骆嘉成 复合桩的施工方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453678A (zh) * 2019-07-30 2019-11-15 甘肃恒捷路桥养护科技有限公司 一种高压旋喷桩二重管法治理黄土公路路基沉降的方法
CN110725305A (zh) * 2019-10-31 2020-01-24 上海长凯岩土工程有限公司 一种提高斜向钢管桩承载力的施工方法
CN110725305B (zh) * 2019-10-31 2021-06-18 上海长凯岩土工程有限公司 一种提高斜向钢管桩承载力的施工方法
WO2021103210A1 (zh) * 2019-11-29 2021-06-03 裴晓峰 一种全套管复合扩盘桩施工方法及设备
CN110924385A (zh) * 2019-12-02 2020-03-27 韶关市第一建筑工程有限公司 高压旋喷桩施工工艺

Similar Documents

Publication Publication Date Title
CN100591866C (zh) 流砂层及砂砾层动水双液高压注浆堵水施工方法
CN103277120B (zh) 一种非全深冻结立井解冻后的涌水防治方法
CN112030964B (zh) 一种适用于工程渗透破坏防治的定位注浆锚杆及其施工方法
CN104929114A (zh) 一种高压旋喷桩止水帷幕施工装置及其方法
CN104631480B (zh) 采用高压旋喷桩机进行深基坑止水帷幕施工的方法
CN102691296A (zh) 一种桩侧静压注浆桩底旋喷注浆的管桩基础及其施工方法
CN106759297A (zh) 一种支护桩与三管高压旋喷桩深基坑的施工方法
CN106223329A (zh) 一种全套管旋喷桩的施工方法
CN106836214A (zh) 旋挖灌注桩桩身塌孔或桩底沉渣质量缺陷处理的施工方法
CN103388338B (zh) 一种新型快速止水及土体改良的方法
CN101560764B (zh) 间隔式高压旋喷注浆封堵勘察孔的方法
CN204753574U (zh) 一种高压旋喷桩止水帷幕施工装置
CN203361143U (zh) 高压旋喷桩与预应力管桩组合结构
CN114808990A (zh) 一种高压预填充溶洞桩基施工方法
CN204418184U (zh) 高压旋喷桩双套管成孔施工装置
CN107366282A (zh) 一种隧道拱脚局部高压旋喷桩加固技术
CN104988914A (zh) 一种水域环境下的钻孔灌注桩断桩处理方法
CN206220101U (zh) 一种深基坑的支护加固结构
CN105113492A (zh) 一种适用于粘性土、砂土、粉土地基的组合桩施工方法
CN107653889A (zh) 一种型钢压灌水泥土帷幕支护桩的施工方法
CN107338790A (zh) 旋喷搅拌复合桩施工方法
CN105586978A (zh) 基于砾石的换土搅拌止水帷幕施工方法
CN205314093U (zh) 一种桩的基坑支护构造
KR100463104B1 (ko) 시멘트밀크 중ㆍ고압분사를 통한 주상형 고결체 형성장치및 형성방법
CN204728318U (zh) 长螺旋钻孔水泥浆护壁式植入管桩的施工装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161214