CN106192701A - The construction method of repaving asphalt coat after the punishment of concrete road surface under high and cold heavy duty - Google Patents

The construction method of repaving asphalt coat after the punishment of concrete road surface under high and cold heavy duty Download PDF

Info

Publication number
CN106192701A
CN106192701A CN201610700564.5A CN201610700564A CN106192701A CN 106192701 A CN106192701 A CN 106192701A CN 201610700564 A CN201610700564 A CN 201610700564A CN 106192701 A CN106192701 A CN 106192701A
Authority
CN
China
Prior art keywords
plate
construction method
deflection value
colophonium
micro
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610700564.5A
Other languages
Chinese (zh)
Other versions
CN106192701B (en
Inventor
田明有
李强
朱磊
王永维
凌晨
刘伟
张生贵
杨志鹏
白卿
李桂琴
花红桂
党生成
熊文涛
卢健
汪珍昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinghai Toll Road Management Office
JSTI Group Co Ltd
Original Assignee
Qinghai Toll Road Management Office
JSTI Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qinghai Toll Road Management Office, JSTI Group Co Ltd filed Critical Qinghai Toll Road Management Office
Priority to CN201610700564.5A priority Critical patent/CN106192701B/en
Publication of CN106192701A publication Critical patent/CN106192701A/en
Application granted granted Critical
Publication of CN106192701B publication Critical patent/CN106192701B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/06Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses the construction method of repaving asphalt coat after concrete road surface is punished under high and cold heavy duty, including: step S1, the detection of old pavement performance and repairing: the deflection value crack casting glue less than 20 (0.01mm) is repaired, the crack of deflection value 20 45 (0.01mm) cement mud-jack is repaired, and the deflection value plate more than 45 (0.01mm) carries out changing plate;Step S2, rechecks after repairing: deflection value is qualified less than 20 (0.01mm) side;Step S3, road surface is cleared up;Step S4, seam is strengthened;Seam crossing both sides overlap joint glass fiber grid;Step S5, overlays bituminous macadam: use Colophonium synchronous breakstone technology to overlay bituminous macadam;Step S6, voltage stabilizing: until bituminous macadam temperature be reduced to steel roller do not glue rubble time, utilize steel roller to carry out voltage stabilizing;Step S7, health preserving: bituminous macadam making completes to carry out afterwards health preserving;Step S8, surface construction: making surface layer asphalt after health preserving.

Description

The construction method of repaving asphalt coat after the punishment of concrete road surface under high and cold heavy duty
Technical field
The invention belongs to building field, relate to the construction method of a kind of cement concrete repaving asphalt coat, be specifically related to The construction method of repaving asphalt coat after cover it is applicable under the heavy duty of High aititude mountain area at cement concrete pavement table to a kind of.
Background technology
On cement concrete pavement, Laying Asphalt Surface Course is commonly called as white changing black, and the pavement structure of this form can absorb two kinds of materials The advantage of material, the most original cement concrete pavement can provide stablizes solid basic unit, and asphaltum concrete cover-layer can provide and rub Resistance coefficient is high, and the surface layer that flatness is good substantially improves the serviceability on road surface.But from the point of view of actual using effect, instead The passage ratio penetrating crack and corner is more serious.Research shows: between original road surface and bitumen layer have effective adhesive be white change black Transformation is successfully crucial, change the most in vain black road surface produce the reason of disease be mostly the tensile strength at the bottom of due to layer and anti-shearing by force Spend low cause.
Some regions, northwest such as Qinghai, Tibet, owing to height above sea level is higher, climatic environment is complicated, and especially mountain road is more, Bend and zig zag are more, in order to avoid the erosion of Moisture Damage, are more cement concrete pavement in early days during Pavement Design, Along with the volume of traffic and heavy-duty vehicle get more and more, road surface running vehicle comfortableness is increasingly paid close attention to, it is contemplated that cost reason, uses relatively Many modes are cement concrete pavement to carry out the Colophonium micro-surface area of 1cm control and recover road surface comfortableness function, but investigation is sent out Existing, thin overlay micro-surface area contains higher bitumen aggregate ratio, although thin overlay can improve original road surface serviceability and Road-ability, but be not particularly suited for the location that High aititude mountain area loaded vehicle is more, practice result shows, uses this kind of mode can only Delay the time of origin of disease, the durability wretched insufficiency on road surface, shortly there occurs early disease, especially bend after being open to traffic The passage at place and reflection crack etc., bring great economic loss not only to owner's unit, and have impact on normal road surface Serviceability.
Summary of the invention
In order to overcome the deficiencies in the prior art, it is an object of the invention to provide a kind of water under the heavy duty of High aititude mountain area The construction method of repaving asphalt coat after cover at the table of cement concrete road surface, it is adaptable at the coagulating cement that Colophonium micro-surface area is controlled Bitumen layer is laid, to reduce passage and the reflection crack disease of corner on soil surface.
The above-mentioned purpose of the present invention is achieved by techniques below scheme:
A kind of it is applicable under high and cold heavy duty at cement concrete pavement table the construction method of repaving asphalt coat after cover, including Following operating procedure:
Step S1, the detection of old pavement performance is with repairing: the old pavement carrying out Colophonium micro-surface area is carried out deflection value detection, And according to deflection value size, old pavement carried out crack repairing and plate is changed;The pit light to disease and ravelled spot carry out Colophonium Micro-surface area changes and is compacted after filling out;
Step S2, rechecks after repairing: the deflection value of all slits and plate is qualified less than 20 (0.01mm) side;
Step S3, road surface is cleared up: the granule repaired on qualified old pavement, earth, foreign material are cleaned up;
Step S4, seam is strengthened;Seam crossing both sides overlap joint glass fiber grid;
Step S5, overlays bituminous macadam: use Colophonium synchronous breakstone technology to overlay bituminous macadam;
Step S6, voltage stabilizing: until bituminous macadam temperature be reduced to steel roller do not glue rubble time, utilize steel wheel press road Machine carries out one or more bout of voltage stabilizing, makes rubble go deep into the micro-surface area layer of old pavement;
Step S7, health preserving: bituminous macadam making completes to carry out afterwards health preserving, centre must not open to traffic;
Step S8, surface construction: making surface layer asphalt after health preserving.
Preferably, described crack repairing and plate are changed and are included: the crack that deflection value is less than 20 (0.01mm) uses filling Sealing is repaired, and uses cement mud-jack to repair in the crack of 20-45 (0.01mm) deflection value;To deflection value more than 45 (0.01mm) plate carries out changing plate.
Preferably, the plate that step S1 is more than 45 (0.01mm) to deflection value changes plate method particularly includes: before changing plate Relief of traffic, changes plate after cement concrete slab intensity is formed, as other plate faces, and cover Colophonium micro-surface area layer.
Preferably, the thickness of cover Colophonium micro-surface area layer is 1cm.
Preferably, step S4 seam both sides respectively overlap 1m glass fiber grid.
Preferably, step S5 Colophonium selects 90# bi tumenf orr oad.
Preferably, the spread quantity of Colophonium is 0.6-1.5kg/m2
Preferably, step S5 rubble selects that quality is hard, clean, granule without air slaking, and particle diameter is 4.75mm-9.5mm The full paving rate of rubble is not less than 70%.
Preferably, step S1 casting glue is cold mixing water-base epoxy Colophonium.
Preferably, step S1 cement mud-jack material comprises early strength agent, extender and flyash.
Advantages of the present invention:
1, the construction method that the present invention provides does not carries out milling to the Colophonium micro-surface area layer on old pavement, but first basis Different diseases is processed by deflection value size respectively, then carries out regeneration, and (asphalt content reduces to not only save cost 5%), and it is provided that higher shearing force, thus effectively solves passage and the reflection crack disease of corner.
2, the construction method that the present invention provides is first each about seam crossing before overlaying bituminous macadam overlaps about 1m Glass fiber grid, it is possible to effectively prevent reflection crack from occurring;In addition select Colophonium synchronous breakstone technique, utilize rubble by former road surface Colophonium micro-surface area layer combines with new black top layer strength with having, and is firmly bonded, and anti-passage performance is more preferable, road surface overall structure More durable.
Detailed description of the invention
Further illustrate the essentiality content of the present invention below in conjunction with embodiment, but do not limit the present invention with this and protect model Enclose.Although the present invention being explained in detail with reference to preferred embodiment, it will be understood by those within the art that, can be right Technical scheme is modified or equivalent, without deviating from the spirit and scope of technical solution of the present invention.
Embodiment 1: a kind of be applicable to the construction of repaving asphalt coat after cover at cement concrete pavement table under high and cold heavy duty Method
Including following operating procedure:
Step S1, the detection of old pavement performance is with repairing: utilize FWD (or backman beam method) to carrying out The old pavement of Colophonium micro-surface area carries out deflection value detection, and the disease come out for emphasis around should survey some more, weight Joint slab ability and deflection value at some abutment joint detect, and the deflection value crack less than 20 (0.01mm) is utilized embedding Glue is repaired, and utilizes cement mud-jack to repair in the crack of 20-45 (0.01mm) deflection value, to deflection value more than 45 (0.01mm) plate carries out changing plate (utilizing C35 plain concrete to carry out changing plate), after needing to pay close attention to change plate between each seam Effective connection, it is ensured that the transmission of load;Pit that disease is light and ravelled spot carry out Colophonium micro-surface area and change and fill out, and use small-sized pressure road Machine or plate compactor compacting;Wherein it is desired to health preserving measure and traffic dredging organization work are carried out in the road surface changing plate health preserving, treat that cement mixes After concrete board intensity is formed, as other plate faces, the micro-surface area layer of cover 1cm, and ensure the effective connection between each seam, Ensure the transmission of load;Wherein, casting glue is cold mixing water-base epoxy Colophonium, and the mass ratio of aqueous epoxy resins and emulsified asphalt is 1:10, the solid content of emulsified asphalt otherwise less than 50%;Wherein, cement mud-jack material comprises early strength agent, extender and fine coal Ash, the ratio of mud is 0.5, and quality is than cement: early strength agent: extender: flyash=1:0.006:0.15:1;
Step S2, rechecks after repairing: Disease Processing completes to carry out afterwards deflection value reinspection, it is necessary to assure deflection value is in technology Within requirement, the deflection value of all slits and plate is qualified less than 20 (0.01mm) side, carries out weight for underproof plate New repairing, requires to reach qualified until meeting technology;
Step S3, road surface is cleared up: the granule repaired on qualified old pavement, earth, foreign material are cleaned up;
Step S4, seam is strengthened;Seam crossing both sides overlap joint glass fiber grid;
Step S5, overlays bituminous macadam: utilize the high bitumen aggregate ratio of original thin layer micro-surface area layer, carrying out interlaminar bonding layer Colophonium synchronous breakstone technology is used to overlay bituminous macadam during process;Rubble selects that quality is hard, clean, without air slaking Grain, specification is 4.75mm-9.5mm, and completely paving rate is not less than 75%;Colophonium selects 90# bi tumenf orr oad, and spread quantity parameter is 1.0kg/m2
Step S6, voltage stabilizing: until bituminous macadam temperature be reduced to steel roller do not glue rubble time, utilize steel wheel press road Machine carries out voltage stabilizing one bout, makes rubble go deep into the micro-surface area layer of old pavement;
Step S7, health preserving: bituminous macadam making completes to carry out afterwards health preserving, centre must not open to traffic;
Step S8, surface construction: waiting until after the assay was approved, making surface layer asphalt, in strict accordance with bituminous concrete Making technique complete each Paving Techniques, it is ensured that the flatness on road surface and compactness;When pavement temperature is reduced to below 50 DEG C Ability open to traffic, and require coring according to coring, test its shearing strength between layers, check whether to meet technology requirement.
Embodiment 2: a kind of be applicable to the construction of repaving asphalt coat after cover at cement concrete pavement table under high and cold heavy duty Method
Including following operating procedure:
Step S1, the detection of old pavement performance is with repairing: utilize FWD (or backman beam method) to carrying out The old pavement of Colophonium micro-surface area carries out deflection value detection, and the disease come out for emphasis around should survey some more, weight Joint slab ability and deflection value at some abutment joint detect, and the deflection value crack less than 20 (0.01mm) is utilized embedding Glue is repaired, and utilizes cement mud-jack to repair in the crack of 20-45 (0.01mm) deflection value, to deflection value more than 45 (0.01mm) plate carries out changing plate (utilizing C35 plain concrete to carry out changing plate), after needing to pay close attention to change plate between each seam Effective connection, it is ensured that the transmission of load;Pit that disease is light and ravelled spot carry out Colophonium micro-surface area and change and fill out, and use small-sized pressure road Machine or plate compactor compacting;Wherein it is desired to health preserving measure and traffic dredging organization work are carried out in the road surface changing plate health preserving, treat that cement mixes After concrete board intensity is formed, as other plate faces, the micro-surface area layer of cover 1cm, and ensure the effective connection between each seam, Ensure the transmission of load;Wherein, casting glue is cold mixing water-base epoxy Colophonium, and the mass ratio of aqueous epoxy resins and emulsified asphalt is 1:7.5, the solid content of emulsified asphalt otherwise less than 50%;Wherein, cement mud-jack material comprises early strength agent, extender and fine coal Ash, the ratio of mud is 0.5, and quality is than cement: early strength agent: extender: flyash=1:0.007:0.16:1;
Step S2, rechecks after repairing: Disease Processing completes to carry out afterwards deflection value reinspection, it is necessary to assure deflection value is in technology Within requirement, the deflection value of all slits and plate is qualified less than 20 (0.01mm) side, carries out weight for underproof plate New repairing, requires to reach qualified until meeting technology;
Step S3, road surface is cleared up: the granule repaired on qualified old pavement, earth, foreign material are cleaned up;
Step S4, seam is strengthened;Seam crossing both sides overlap joint glass fiber grid;
Step S5, overlays bituminous macadam: utilize the high bitumen aggregate ratio of original thin layer micro-surface area layer, carrying out interlaminar bonding layer Colophonium synchronous breakstone technology is used to overlay bituminous macadam during process;Rubble selects that quality is hard, clean, without air slaking Grain, specification is 4.75mm-9.5mm, and completely paving rate is not less than 70%;Colophonium selects 90# bi tumenf orr oad, and spread quantity parameter is 1.5kg/m2
Step S6, voltage stabilizing: until bituminous macadam temperature be reduced to steel roller do not glue rubble time, utilize steel wheel press road Machine carries out voltage stabilizing one bout, makes rubble go deep into the micro-surface area layer of old pavement;
Step S7, health preserving: bituminous macadam making completes to carry out afterwards health preserving, centre must not open to traffic;
Step S8, surface construction: waiting until after the assay was approved, making surface layer asphalt, in strict accordance with bituminous concrete Making technique complete each Paving Techniques, it is ensured that the flatness on road surface and compactness;When pavement temperature is reduced to below 50 DEG C Ability open to traffic, and require coring according to coring, test its shearing strength between layers, check whether to meet technology requirement.
Embodiment 3: a kind of be applicable to the construction of repaving asphalt coat after cover at cement concrete pavement table under high and cold heavy duty Method
Including following operating procedure:
Step S1, the detection of old pavement performance is with repairing: utilize FWD (or backman beam method) to carrying out The old pavement of Colophonium micro-surface area carries out deflection value detection, and the disease come out for emphasis around should survey some more, weight Joint slab ability and deflection value at some abutment joint detect, and the deflection value crack less than 20 (0.01mm) is utilized embedding Glue is repaired, and utilizes cement mud-jack to repair in the crack of 20-45 (0.01mm) deflection value, to deflection value more than 45 (0.01mm) plate carries out changing plate (utilizing C35 plain concrete to carry out changing plate), after needing to pay close attention to change plate between each seam Effective connection, it is ensured that the transmission of load;Pit that disease is light and ravelled spot carry out Colophonium micro-surface area and change and fill out, and use small-sized pressure road Machine or plate compactor compacting;Wherein it is desired to health preserving measure and traffic dredging organization work are carried out in the road surface changing plate health preserving, treat that cement mixes After concrete board intensity is formed, as other plate faces, the micro-surface area layer of cover 1cm, and ensure the effective connection between each seam, Ensure the transmission of load;Wherein, casting glue is cold mixing water-base epoxy Colophonium, and the mass ratio of aqueous epoxy resins and emulsified asphalt is 1:12.5, the solid content of emulsified asphalt otherwise less than 50%;Wherein, cement mud-jack material comprises early strength agent, extender and powder Coal ash, the ratio of mud is 0.5, and quality is than cement: early strength agent: extender: flyash=1:0.008:0.17:1;
Step S2, rechecks after repairing: Disease Processing completes to carry out afterwards deflection value reinspection, it is necessary to assure deflection value is in technology Within requirement, the deflection value of all slits and plate is qualified less than 20 (0.01mm) side, carries out weight for underproof plate New repairing, requires to reach qualified until meeting technology;
Step S3, road surface is cleared up: the granule repaired on qualified old pavement, earth, foreign material are cleaned up;
Step S4, seam is strengthened;Seam crossing both sides overlap joint glass fiber grid;
Step S5, overlays bituminous macadam: utilize the high bitumen aggregate ratio of original thin layer micro-surface area layer, carrying out interlaminar bonding layer Colophonium synchronous breakstone technology is used to overlay bituminous macadam during process;Rubble selects that quality is hard, clean, without air slaking Grain, specification is 4.75mm-9.5mm, and completely paving rate is not less than 80%;Colophonium selects 90# bi tumenf orr oad, and spread quantity parameter is 1.2kg/m2
Step S6, voltage stabilizing: until bituminous macadam temperature be reduced to steel roller do not glue rubble time, utilize steel wheel press road Machine carries out voltage stabilizing one bout, makes rubble go deep into the micro-surface area layer of old pavement;
Step S7, health preserving: bituminous macadam making completes to carry out afterwards health preserving, centre must not open to traffic;
Step S8, surface construction: waiting until after the assay was approved, making surface layer asphalt, in strict accordance with bituminous concrete Making technique complete each Paving Techniques, it is ensured that the flatness on road surface and compactness;When pavement temperature is reduced to below 50 DEG C Ability open to traffic, and require coring according to coring, test its shearing strength between layers, check whether to meet technology requirement.
Embodiment 4: comparative example, contrasts with embodiment 1, and old pavement micro-surface area layer carries out milling:
Step S1, the detection of old pavement performance is with repairing: first carry out the micro-surface area cover of cement concrete pavement completely Milling processes, and then utilizes FWD (or backman beam method) that the old pavement after milling is carried out deflection value detection, The disease come out for emphasis around should survey some more, and joint slab ability and deflection value at emphasis abutment joint enter Row detection, utilizes casting glue to repair, to deflection value at 20-45 (0.01mm) in the deflection value crack less than 20 (0.01mm) Crack utilize cement mud-jack to repair, deflection value is changed plate more than the plate of 45 (0.01mm) and (utilizes C35 element coagulation Soil carries out changing plate), effectively connecting between each seam after needing to pay close attention to change plate, it is ensured that the transmission of load;Wherein it is desired to change Health preserving measure and traffic dredging organization work are carried out in the road surface of plate health preserving, and ensure the effective connection between each seam, it is ensured that carry The transmission of lotus;Wherein, casting glue is cold mixing water-base epoxy Colophonium, and the mass ratio of aqueous epoxy resins and emulsified asphalt is 1:10, The solid content of emulsified asphalt however less than 50%;Wherein, cement mud-jack material comprises early strength agent, extender and flyash, water Gray scale is 0.5, and quality is than cement: early strength agent: extender: flyash=1:0.006:0.15:1;
Step S2, rechecks after repairing: Disease Processing completes to carry out afterwards deflection value reinspection, it is necessary to assure deflection value is in technology Within requirement, the deflection value of all slits and plate is qualified less than 20 (0.01mm) side, carries out weight for underproof plate New repairing, requires to reach qualified until meeting technology;
Step S3, road surface is cleared up: the granule repaired on qualified old pavement, earth, foreign material are cleaned up;
Step S4, seam is strengthened;Seam crossing both sides overlap joint glass fiber grid;
Step S5, overlays bituminous macadam: use Colophonium synchronous breakstone technology to overlay bituminous macadam;Rubble selects quality Hard, clean, granule without air slaking, specification is 4.75mm-9.5mm, and completely paving rate is not less than 75%;Colophonium selects 90# road Asphalt, spread quantity parameter is 1.0kg/m2
Step S6, voltage stabilizing: until bituminous macadam temperature be reduced to steel roller do not glue rubble time, utilize steel wheel press road Machine carries out voltage stabilizing one bout, makes rubble go deep into old pavement;
Step S7, health preserving: bituminous macadam making completes to carry out afterwards health preserving, centre must not open to traffic;
Step S8, surface construction: waiting until after the assay was approved, making surface layer asphalt, in strict accordance with bituminous concrete Making technique complete each Paving Techniques, it is ensured that the flatness on road surface and compactness;When pavement temperature is reduced to below 50 DEG C Ability open to traffic, and require coring according to coring, test its shearing strength between layers, check whether to meet technology requirement.
Embodiment 5: effect example
Require coring according to coring, test its shearing strength between layers, check whether to meet technology requirement.Result of the test such as following table Shown in.
Embodiment 1 Embodiment 2 Embodiment 3 Embodiment 4
Shearing strength (MPa) 2.4 2.2 2.3 1.5
The contrast of embodiment 1 and embodiment 4 is it can be seen that construction method of the present invention is not required to table micro-to the Colophonium on old pavement Place's layer carries out milling, but first processes different diseases respectively according to deflection value size, then carries out regeneration, not only saves Save cost (asphalt content reduces by 5%), and be provided that higher shearing force compared with the method for milling, thus effectively solved The passage of corner and reflection crack disease.
The effect of above-described embodiment indicates that the essentiality content of the present invention, but does not limit the protection of the present invention with this Scope.It will be understood by those within the art that, technical scheme can be modified or equivalent, Essence and protection domain without deviating from technical solution of the present invention.

Claims (10)

1. it is applicable under high and cold heavy duty at cement concrete pavement table a construction method for repaving asphalt coat, its feature after cover It is, including following operating procedure:
Step S1, the detection of old pavement performance is with repairing: the old pavement carrying out Colophonium micro-surface area is carried out deflection value detection, and root According to deflection value size, old pavement carried out crack repairing and plate is changed;The pit light to disease and ravelled spot carry out the micro-table of Colophonium Place changes and is compacted after filling out;
Step S2, rechecks after repairing: the deflection value of all slits and plate is qualified less than 20 (0.01mm) side;
Step S3, road surface is cleared up: the granule repaired on qualified old pavement, earth, foreign material are cleaned up;
Step S4, seam is strengthened;Seam crossing both sides overlap joint glass fiber grid;
Step S5, overlays bituminous macadam: use Colophonium synchronous breakstone technology to overlay bituminous macadam;
Step S6, voltage stabilizing: until bituminous macadam temperature be reduced to steel roller do not glue rubble time, utilize steel roller to enter One or more bout of row voltage stabilizing, makes rubble go deep into the micro-surface area layer of old pavement;
Step S7, health preserving: bituminous macadam making completes to carry out afterwards health preserving, centre must not open to traffic;
Step S8, surface construction: making surface layer asphalt after health preserving.
Construction method the most according to claim 1, it is characterised in that described crack repairing and plate are changed and included: to curved The heavy value crack less than 20 (0.01mm) uses casting glue to repair, and uses deflection value in the crack of 20-45 (0.01mm) Cement mud-jack is repaired;The deflection value plate more than 45 (0.01mm) is changed plate.
Construction method the most according to claim 2, it is characterised in that the plate that deflection value is more than 45 (0.01mm) is carried out Change plate method particularly includes: change relief of traffic before plate, change plate after cement concrete slab intensity is formed, as other plate faces, Cover Colophonium micro-surface area layer.
Construction method the most according to claim 3, it is characterised in that: the thickness of cover Colophonium micro-surface area layer is 1cm.
Construction method the most according to claim 1, it is characterised in that step S4 seam both sides respectively overlap 1m glass fiber grid.
Construction method the most according to claim 1, it is characterised in that step S5 Colophonium selects 90# bi tumenf orr oad.
Construction method the most according to claim 6, it is characterised in that the spread quantity of Colophonium is 0.6-1.5kg/m2
Construction method the most according to claim 1, it is characterised in that step S5 rubble selects that quality is hard, clean, do not contain The granule of air slaking, particle diameter is 4.75mm-9.5mm;The full paving rate of rubble is not less than 70%.
Construction method the most according to claim 1, it is characterised in that: step S1 casting glue is cold mixing water-base epoxy Colophonium.
Construction method the most according to claim 1, it is characterised in that: step S1 cement mud-jack material comprises early strength agent, Extender and flyash.
CN201610700564.5A 2016-08-22 2016-08-22 Construction method for repaving asphalt coat after the lower concrete road surface punishment of high and cold heavy duty Expired - Fee Related CN106192701B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610700564.5A CN106192701B (en) 2016-08-22 2016-08-22 Construction method for repaving asphalt coat after the lower concrete road surface punishment of high and cold heavy duty

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610700564.5A CN106192701B (en) 2016-08-22 2016-08-22 Construction method for repaving asphalt coat after the lower concrete road surface punishment of high and cold heavy duty

Publications (2)

Publication Number Publication Date
CN106192701A true CN106192701A (en) 2016-12-07
CN106192701B CN106192701B (en) 2018-07-24

Family

ID=57523720

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610700564.5A Expired - Fee Related CN106192701B (en) 2016-08-22 2016-08-22 Construction method for repaving asphalt coat after the lower concrete road surface punishment of high and cold heavy duty

Country Status (1)

Country Link
CN (1) CN106192701B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288003A (en) * 2017-07-19 2017-10-24 广东金长成桥梁隧道科技有限公司 A kind of road surface or preventive maintenance of deck structure and its construction method
CN115450086A (en) * 2022-09-08 2022-12-09 广西北投交通养护科技集团有限公司 Old cement concrete pavement reconstruction structure suitable for non-heavy traffic grade and design method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030086762A1 (en) * 1999-12-17 2003-05-08 Atsushi Oka Road reinforcement street, structure of asphalt reinforced pavement and method for paving road
CN101603286A (en) * 2009-07-03 2009-12-16 江西赣粤高速公路股份有限公司 Old road asphalt stabilized macadam overlay reforming method and structure thereof
CN101691736A (en) * 2009-09-23 2010-04-07 中交二公局第六工程有限公司 Construction method for reconstructing old concrete pavement by paving asphalt-concrete surface layer
CN105256686A (en) * 2015-10-10 2016-01-20 青海正平公路养护工程有限公司 High-grade highway high and cold road surface micro-surfacing preventive maintenance construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030086762A1 (en) * 1999-12-17 2003-05-08 Atsushi Oka Road reinforcement street, structure of asphalt reinforced pavement and method for paving road
CN101603286A (en) * 2009-07-03 2009-12-16 江西赣粤高速公路股份有限公司 Old road asphalt stabilized macadam overlay reforming method and structure thereof
CN101691736A (en) * 2009-09-23 2010-04-07 中交二公局第六工程有限公司 Construction method for reconstructing old concrete pavement by paving asphalt-concrete surface layer
CN105256686A (en) * 2015-10-10 2016-01-20 青海正平公路养护工程有限公司 High-grade highway high and cold road surface micro-surfacing preventive maintenance construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288003A (en) * 2017-07-19 2017-10-24 广东金长成桥梁隧道科技有限公司 A kind of road surface or preventive maintenance of deck structure and its construction method
CN115450086A (en) * 2022-09-08 2022-12-09 广西北投交通养护科技集团有限公司 Old cement concrete pavement reconstruction structure suitable for non-heavy traffic grade and design method
CN115450086B (en) * 2022-09-08 2023-10-13 广西北投交通养护科技集团有限公司 Old cement concrete pavement reconstruction structure suitable for non-extra-heavy traffic grade and design method

Also Published As

Publication number Publication date
CN106192701B (en) 2018-07-24

Similar Documents

Publication Publication Date Title
US20100316445A1 (en) Method for continuous on-site repaving of an asphalt mixture layer of paved road pavement and a motor-driven vehicle system therefor
CN104762863A (en) Bituminous mixture used for thin layer overlay of cement concrete pavement and preparation and construction methods of bituminous mixture
Kumar et al. Case studies on failure of bituminous pavements
CN203546553U (en) Stable cement concrete road surface pavement structure
CN106320129A (en) Method for designing mix proportion of bituminous mixture for ultra-thin wearing course
Maggenti et al. Initial and replacement riding surface for the orthotropic San Mateo/Hayward Bridge
CN106192701A (en) The construction method of repaving asphalt coat after the punishment of concrete road surface under high and cold heavy duty
Ali et al. Asphalt surface treatment practice in southeastern United States.
Hanson Construction and performance of an ultrathin bonded hot-mix asphalt wearing course
CN101220574A (en) Method for paving track resistant road surface and product improving track resistant capability of road surface
CN103225264B (en) A kind of composite rubber asphalt concrete steel bridge surface pavement structure
CN204491343U (en) A kind of compound cold mixing cold-application ultrathin overlay paving structure
Zumrawi Investigating causes of pavement deterioration in Khartoum state, Sudan
CN114319000B (en) Thin asphalt pavement bonding layer capable of absorbing stress and construction method thereof
CN108914757A (en) A kind of technique that cement concrete pavement solves reflective crack
Davidson et al. Best practices in cold in-place recycling
CN103321123A (en) Highway, pavement structure and construction method of highway pavement
CN107022954A (en) A kind of bridge deck water-proof tack coat, its preparation method and application
CN207210958U (en) A kind of bridge deck water-proof tack coat and a kind of bridge floor
CN215668926U (en) Pavement repairing structure
CN210086044U (en) Bridge deck pavement structure for assembled bridge
CN113152311B (en) Steel bridge deck pavement maintenance method and performance evaluation method after maintenance
CN204491346U (en) A kind of composite type heat mixes heat paving ultrathin overlay paving structure
Brotman et al. Roller compacted concrete pavement: Properties, design, and construction
KR102236636B1 (en) Manhole cover set for sidewalk

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180724