Highly preferred embodiment of the present invention is:
Described bin mechanism of putting is possibly together with base plate I, bottom girder the Ith, crossbeam, column, horizontal pillow, by adjusting between base plate I and bottom girder I
Screw I is connected, and adjusts screw I and is provided with adjusting nut I, is connected by column between bottom girder I and crossbeam, and tiltedly pillow, horizontal pillow are arranged
Above crossbeam, and supported by pillar, adjusted the angle of oblique pillow by adjusting screw I, make workpiece automatically can roll along oblique pillow
Move on automatic feed mechanism material rotating plate assembly.
Described bin mechanism possibly together with base plate the IIth, lower shoe, adjustment screw the IIth, bottom girder the IIth, fixed plate the Ith, front column, under
Support beam, upper beam, upper beam the Ith, rear column, oil cylinder seat, gusset I, seat board the Ith, gusset the IIth, underbeam I, base plate II is connected with fixed plate I
Connecing, seat board I is connected with gusset II, and seat board I is fixed on upper beam I with the connector of gusset II, and block is fixed on seat board I and muscle
On the connector of plate II, base plate II is separately fixed on front column and rear column with the connector of fixed plate I, base plate II and bottom girder
Be connected by adjusting screw II between II, adjust screw II and be provided with adjusting nut II, front column, rear column and lower support beam, on
Beam the Ith, upper beam, underbeam I are connected, and lower shoe is fixed on lower support beam, and oil cylinder seat is arranged on rear column.
Described feed mechanism is possibly together with cylinder right support, cylinder left socle, base plate the IIIth, upper plate, footstock, leading screw, silk seat, set
Ring seat, bearing pin, bar portion free bearing, rolling linear guide I is fixed on the lower shoe of bin mechanism, right of cylinder left socle, cylinder
Frame is fixed on the lower support beam of bin mechanism, and cylinder assembly II is fixed on cylinder left socle, on cylinder right support, left of pulley
Frame, pulley right support are separately fixed on the slide block of rolling linear guide I, and cylinder assembly about II two ends are separately fixed at pulley
On left socle, pulley right support, big pulley the Vth, the truckle III in assembly pulley I passes through big pulley spindle the Vth, truckle axle III respectively
Being fixed on pulley left socle, the VIth, the truckle IV of the big pulley in assembly pulley II passes through big pulley spindle the VIth, truckle axle IV respectively
It is fixed on pulley right support;Upper plate is fixed on the upper beam I of bin mechanism, and rolling linear guide II is fixed on upper plate
On, left supported plate, right supported plate are separately fixed at the two ends, left and right of upper plate, the IIIth, big pulley the IVth, the little cunning of the big pulley in assembly pulley III
Wheel II is fixed on left supported plate and upper plate, the Ith, big pulley the IIth, the truckle I of the big pulley in assembly pulley IV be fixed on right supported plate and
On upper plate, support plate is fixed on the slide block of rolling linear guide II, and pressing plate is fixed on support plate, and adjustment plate I is fixed on support plate
On, hitting plate and be fixed in adjustment plate I, footstock, leading screw, silk seat are fixed on upper plate, and material rotating plate assembly is fixed on bin mechanism
Upper beam on, material rotating plate bracket component is fixed on material rotating plate assembly, and cylinder assembly I left end is fixed on cylinder block, cylinder
Assembly I right-hand member is connected with bar portion free bearing, and bar portion free bearing is connected fastening with material rotating plate bracket component, and pneumatic triplet is fixed on bin
On the front column of mechanism, pneumatic reversing solenoid valve I is fixed on the lower support beam of bin mechanism, magnetic sensor I, magnetic sensor
II fixes with cylinder assembly II two ends respectively, and pneumatic reversing solenoid valve II is fixed on the rear column of bin mechanism, magnetic transducing
Device the IIIth, magnetic sensor IV is fixed on the two ends of cylinder assembly I;Front material assembly and after-poppet assembly are all fixed on bin mechanism
Upper beam I on, steel wire rope links together around assembly pulley the Ith, assembly pulley II and assembly pulley the IIIth, assembly pulley IV, and is fastened on a left side
In the set ring seat at right two ends.
When ventilation is to the gentle dynamic reversing solenoid valve II of pneumatic triplet, the piston rod of cylinder assembly I moves left and right, band
Dynamic material rotating plate assembly rises and falls, and by material rotating plate assembly workpiece is slided into a material assembly before adjusting along material rotating plate assembly inclined-plane
With on after-poppet assembly, then transmitting information by magnetic sensor the IIIth, magnetic sensor IV, cylinder assembly II starts, cylinder
The piston rod band movable pulley left socle of assembly II, pulley right support, assembly pulley the Ith, assembly pulley II move on rolling linear guide I
Dynamic, steel wire rope moves band running block the IIIth, IV rotation, and then the slide block movement with dynamic pressure plate, support plate and rolling linear guide II,
The slide block of rolling linear guide II drives adjustment plate the Ith, to hit plate and does linear reciprocating motion on rolling linear guide II, hits plate and promotes
Workpiece is transported in guiding mechanism by after-poppet assembly, front the material assembly adjusted, thus is realized being transported to lead by workpiece
In mechanism.
Described guiding mechanism contains splicing sleeve assembly, support, and described splicing sleeve assembly contains bearing holder (housing, cover), feeding connects
Body, bearing bonnet, round nut, bonnet, spacer, bearing III, bearing III is arranged on bearing holder (housing, cover) and feeding connector, bearing bonnet
Being fixed on feeding connector, round nut is connected with bearing holder (housing, cover), and spacer is arranged in bearing holder (housing, cover) endoporus, after bonnet is fixed on bearing
Covering, splicing sleeve assembly is fixed on support by bearing support.
Described support contains seat board the IIth, T-slot nut, upper beam the IIth, column the IIth, crossbeam the IIth, fixed plate and the IIth, adjusts screw
IIIth, bottom girder the IIIth, base plate the IVth, underbeam II, adjusts screw III and is provided with adjusting nut III, upper beam II and column the IIth, crossbeam the IIth, underbeam
IIth, bottom girder III is connected, and base plate IV is connected with bottom girder III by adjusting screw III, and base plate IV is fixed in fixed plate II, fixing
Plate II is fixed on column II, and seat board II is fixed on upper beam II, and T-slot nut is arranged on seat board II and connects with bearing support
Connect.Adjusting center height, the centre-to-centre spacing of support set assembly, workpiece is sent in lathe by guided bearing assembly endoporus, thus is realized
Feeding.
Described after-poppet assembly contains fixed plate the IIIth, adjustment plate the IIth, right bearing bearing the Ith, left bearing bearing the Ith, sliding panel
Ith, locating shaft, bearing outside the Ith, protective cover and bearing IV, bearing IV is arranged on locating shaft and bearing outside I, and protective cover is installed
In bearing outside I hole, two, left and right locating shaft is separately mounted on left bearing bearing the IIth, right bearing bearing I, left bearing bearing
Ith, right bearing bearing I is all fixed in adjustment plate II, and adjustment plate II is fixed on sliding panel I, and sliding panel I is fixed on fixed plate III
On.
Before described, a material assembly contains fixed plate the IVth, adjustment plate the IIIth, right bearing bearing the IIth, left bearing bearing the IIth, sliding panel
IIth, axle, spacer, bearing outside II and two, left and right bearing V, two, left and right bearing V is arranged on axle and bearing outside II and a left side
On bearing spider the IIth, right bearing bearing II, spacer is mounted on an axle, and left bearing bearing the IIth, right bearing bearing II is all fixed on tune
On whole plate III, adjustment plate III is fixed on sliding panel II, and sliding panel II is fixed in fixed plate IV.
The operation principle of the present invention is:
The present invention by putting bin mechanism, automatic feed mechanism (including bin mechanism, feed mechanism), guiding mechanism form, pass through
Adjust screw, adjust put bin, automatic feed mechanism, guiding mechanism center is high, centre-to-centre spacing and between distance;Workpiece
Being contained in put and adjusting angle on bin and put well, workpiece is automatically scrolling to automatic feed mechanism material rotating plate assembly by deadweight along oblique pillow
Go up and in block;Magnetic sensor on cylinder assembly I the IIIth, magnetic sensor IV communicates information to pneumatic reversing solenoid valve II,
Pneumatic triplet starts supply, and cylinder assembly I starts to start, and drives material rotating plate assembly that workpiece is translated into after-poppet assembly and front
On material assembly, the Ith, the magnetic sensor II of the magnetic sensor on cylinder assembly II obtains information, starts pneumatic reversing solenoid valve I,
Pneumatic triplet supply, cylinder assembly II starts, the left and right support of cylinder assembly II piston rod band movable pulley, assembly pulley the Ith, II
Moving on rolling linear guide I, steel wire rope moves band running block the IIIth, assembly pulley IV rotation, and band dynamic pressure plate, support plate, rolling are straight
The slide block movement of line guide rail II, and then drive adjustment plate the Ith, to hit plate and move along a straight line on rolling linear guide II, hit plate and promote
Workpiece is transported in guiding mechanism by after-poppet assembly, front material assembly, then by guiding mechanism, workpiece is delivered to lathe and add
Territory, work area, to collision block, completes the automatic charging to machine tooling region.After on lathe, magnetic sensor V obtains information, numerical control system
System realizes gripper chuck clamping of workpieces, thus realizes the purpose of self-feeding.
The numerical control roller car automatic charging equipment made according to technical scheme, can the extremely processing of accurate conveying workpieces
In region, not only increase operating efficiency, mitigate the labour intensity of operator especially, be substantially reduced manufacturing cost, improve life
Produce efficiency.1. the present invention utilizes cylinder assembly, rolling linear guide, assembly pulley, front and back support assembly and splicing sleeve assembly to do past
Multiple motion, it is achieved feeding disposably completes, thus substantially increases production efficiency, alleviates the labour intensity of operator.2. adopt
With regulation screw regulation center is high, centre-to-centre spacing is convenient and simple, and can put many bars 3 meters long, a bar can process 60
Part, the workpiece for processing provides guarantee.
The present invention have good rigidly, be quick on the draw, reliable operation, the spy such as labour intensity is low, production efficiency is high, compact conformation
Point, its low cost of manufacture, is the ideal equipment of numerical control roller car automatic charging.
Detailed description of the invention
Below in conjunction with the accompanying drawings and the present invention is done further detailed description by the example that is embodied as:
From Fig. 2-1 to 2-2, Fig. 3-1 to 3-3, Fig. 4-1 to 4-11, Fig. 5-1 to 5-3 and Fig. 6-1 to 6-2 can, the present invention
Automatic charging equipment, containing putting bin mechanism G, automatic feed mechanism S(includes bin mechanism, feed mechanism), guiding mechanism
D, described puts the adjustment screw I 2 that bin mechanism G contains the tiltedly pillow 6 holding workpiece and adjustable tiltedly pillow 6 angles, by adjusting
Screw I 2 adjusts the angle of tiltedly pillow 6, makes the deadweight of workpiece be automatically scrolling to relevant position i.e. automatic feed mechanism along oblique pillow 6
Material rotating plate assembly 58 on, by automatic feed mechanism feeding;Described automatic feed mechanism S contains bin mechanism and feeder
Structure, feed mechanism is arranged in bin mechanism, and described bin mechanism is provided with block 27, and described feed mechanism contains stirring
Magnetic sensor III 71 on board component the 58th, cylinder assembly I 63, cylinder assembly I 63 and magnetic sensor IV 72, pneumatic commutation electricity
Magnet valve II 68, pneumatic triplet the 66th, after-poppet assembly 60 and front material assembly the 59th, cylinder assembly II 64, on cylinder assembly II 64
Magnetic sensor I 69 and magnetic sensor II 70, pneumatic reversing solenoid valve I 67, pulley left socle 34-1, pulley right support
34-2, assembly pulley I a, assembly pulley II b, assembly pulley III c, assembly pulley IV d, rolling linear guide I 61, rolling linear guide II 62,
Steel wire rope the 35th, pressing plate the 39th, support plate the 40th, left supported plate the 41st, right supported plate the 42nd, adjustment plate I 56, hitting plate 57, workpiece rolls automatically along oblique pillow 6
Move on the material rotating plate assembly 58 of automatic feed mechanism and in block 15, the magnetic sensor III 71 on cylinder assembly I 63, magnetic
Sensor IV 72 communicates information to pneumatic reversing solenoid valve II 68, and pneumatic triplet 66 starts supply, and cylinder assembly I 63 starts to open
Dynamic, drive 58 workpiece of material rotating plate assembly to translate on after-poppet assembly 60 and front material assembly 59, the magnetic on cylinder assembly II 64
Property sensor I 69, magnetic sensor II 70 obtain information, start pneumatic reversing solenoid valve I 67, and pneumatic triplet 66 supplies, gas
Cylinder component II 64 start, cylinder assembly II 64 piston rod band movable pulley left socle 34-1, pulley right support 34-2 and assembly pulley I a,
Assembly pulley II b moves on rolling linear guide I 61, steel wire rope 35 around be entangled in be connected with cylinder assembly II 64 assembly pulley I a,
Assembly pulley II b and being fixed on assembly pulley III c, assembly pulley IV d on left supported plate the 41st, right supported plate 42, steel wire rope 35 motion drives
Assembly pulley III c, assembly pulley IV d rotate, with the slide block 62-1 motion on dynamic pressure plate the 39th, support plate 40 and rolling linear guide II 62,
And then drive adjustment plate I 56, hit plate 57 and move on rolling linear guide II 62, hit after plate 57 promotes workpiece by adjusting
Bracket component the 60th, front material assembly 59 is transported in guiding mechanism D, then by guiding mechanism D, workpiece is delivered to machine tooling district
Territory, completes the automatic charging to machine tooling region.
After by guiding mechanism workpiece being delivered to the collision block IV in machine tooling region, magnetic sensor V 73 on lathe
To information, digital control system realizes that chuck III clamps workpiece, completes self-feeding.
Described bin mechanism of putting is as shown in Fig. 2-1,2-2, and it contains base plate I1, adjusts screw I 2, bottom girder II 3, column
4th, crossbeam the 5th, tiltedly pillow the 6th, pillar the 7th, horizontal pillow the 8th, left longeron the 9th, right vertical beam the 10th, mullion the 11st, striker plate the 12nd, long bent plate the 13rd, bearing diagonal is the 14th,
Baffle plate 15, base plate I1, bottom girder II 3, column the 4th, crossbeam the 5th, tiltedly pillow the 6th, pillar the 7th, horizontal pillow the 8th, left longeron the 9th, right vertical beam the 10th, mullion is the 11st,
Striker plate the 12nd, bearing diagonal the 14th, each part of baffle plate 15 puts bin by being welded to form.Adjust screw I 2 to connect with base plate I 1 and bottom girder I 3
Connecing, screwing in M20 nut 2-1, fasten after adjusting height and angle by adjusting nut 2-1, long bent plate 13 is solid with M10 bolt 13-1
It is scheduled on and puts on bin, and striker plate 12 is fixed on long bent plate 13 by M10 screw 12-1.Adjust angle by adjusting screw I 2,
The deadweight making workpiece is automatically scrolling on relevant position i.e. automatic feed mechanism material rotating plate assembly 58 along oblique pillow 6.
Described automatic feed mechanism is made up of with feed mechanism bin mechanism.Such as Fig. 3-1,3-2,3-3 institute of bin mechanism
Showing, it contains base plate II 16, lower shoe and the 31st, adjusts screw II 17, bottom girder II 18, fixed plate I 19, front column the 20th, lower support beam the 21st,
Upper beam the 22nd, upper beam I 23, rear column the 24th, oil cylinder seat the 25th, gusset I26, block the 27th, seat board I 28, gusset II 29, underbeam I 30;?
Front column 20 and lower support beam the 21st, upper beam I 23, upper beam the 22nd, rear column the 24th, underbeam I 30, bottom girder II 18, oil cylinder seat the 25th, gusset I
26 are respectively welded into frame, base plate II 16 and fixed plate I 19 welding, seat board I 28 and gusset II 29 welding, seat board I 28 and gusset II
The weldment of 29 is fixed on upper beam I 23 by M12 screw 29-1, and block 27 is fixed on seat board I 28 and gusset by M8 screw 27-1
On the weldment of II 29, base plate II 16 is fixed on front column 20 and rear column with the weldment of fixed plate I 19 by M16 screw 19-1
On 24, on the lower support beam 21 of lower shoe 31 welding, adjust screw II 17 and be connected with base plate II 16, bottom girder II 18, screw in nut 17-1,
The 20th, front column is reinforced by securing plate 50 between rear column 24 and underbeam I 30, thus, forms whole bin mechanism.
Feed mechanism is installed in bin mechanism, and described feed mechanism is if Fig. 4-1 is to shown in Fig. 4-11, right containing cylinder
The 39th, support the 32nd, cylinder left socle the 33rd, pulley left socle 34-1, pulley right support 34-2, base plate III 37, upper plate the 38th, pressing plate prop up
The 46th, plate the 40th, left supported plate the 41st, right supported plate the 42nd, footstock the 43rd, leading screw the 45th, silk seat overlaps ring seat the 47th, bearing pin the 48th, assembly pulley I a, assembly pulley II
B, assembly pulley III c, assembly pulley IV d, adjustment plate I 56, hit plate the 57th, material rotating plate assembly the 58th, front material assembly the 59th, after-poppet assembly
60th, rolling linear guide I 61, rolling linear guide II 62, cylinder assembly I 63, cylinder assembly II 64, pneumatic triplet the 66th, gas
Magnetic sensor I 69 on dynamic reversing solenoid valve I 67, pneumatic reversing solenoid valve II 68, cylinder assembly II 64 and magnetic sensor
II 70, the magnetic sensor III 71 on cylinder assembly I 63 and magnetic sensor IV 72, material rotating plate bracket component the 74th, bar portion free bearing
75th, support shaft the 76th, material rotating plate fixes axle the 77th, support shaft 78, contains truckle III 55-3, truckle axle III 54-in assembly pulley I a
3rd, bearing 65-6, big pulley V 52-5, big pulley spindle V 51-5, bearing 65-5, in assembly pulley II b containing big pulley VI 52-6,
Big pulley spindle VI 51-6, bearing 65-3, truckle IV 55-4, truckle axle IV 54-4, bearing 65-4, contain in assembly pulley III c
Big pulley IV 52-4, big pulley spindle IV 51-4, truckle II 55-2, truckle axle II 54-2, bearing 65-8, big pulley III 52-
3rd, big pulley spindle III 51-3, bearing 65-7, contains big pulley I 52-1, big pulley spindle I 51-1, bearing 65-1 in assembly pulley IV d,
Truckle I 55-1, truckle axle I 54-1, bearing 65-2, big pulley spindle II 51-2, big pulley II 52-2, rolling linear guide I
61 are fixed on lower shoe 31, and cylinder left socle the 33rd, cylinder right support 32 is welded on the lower support beam of the bin mechanism shown in Fig. 3-2
On 21, cylinder assembly II 64 is fixed on cylinder left socle the 33rd, cylinder right support 32, pulley left socle 34-1, pulley right support
34-2 is fixed on rolling linear guide I 61, and cylinder assembly about II 64 two ends are separately fixed at left of pulley by nut 36
On frame 34-1, pulley right support 34-2, big pulley spindle V 51-5, truckle axle III 54-3 in assembly pulley I a pass through bearing 65-
6th, 65-5 is separately mounted on big pulley V 52-5, truckle III 55-3, and big pulley spindle V 51-5, truckle axle III 54-3 fix
On pulley left socle 34-1, big pulley spindle VI 51-6, truckle axle IV 54-4 in assembly pulley II b pass through bearing 65-3,65-
4 are separately mounted on big pulley VI 52-6, truckle IV 55-4, and big pulley spindle VI 51-6, truckle axle IV 54-4 are fixed on cunning
On wheel right support 34-2, upper plate 38 screw 38-1, nut 38-2 are fixed on the upper beam I 23 of the bin mechanism shown in Fig. 3-2
On, rolling linear guide II 62 is fixed on upper plate 38, and left supported plate the 41st, right supported plate 42 is welded on the left and right two of upper plate 38
End, and big pulley IV 52-4 in assembly pulley III c, big pulley spindle IV 51-4, big pulley III 52-3, big pulley spindle III 51-3, little
Pulley II 55-2, truckle axle II 54-2 are fixed on left supported plate 41 and upper plate 38 by bearing 65-7,65-8, assembly pulley IV
Big pulley I 52-1 in d, big pulley spindle I 51-1, big pulley spindle II 51-2, big pulley II 52-2, truckle I 55-1, truckle
Axle I 54-1 is fixed on right supported plate 42 and upper plate 38 by bearing 65-1,65-2.Support plate 40 is fixed on rolling linear guide
On II 62, pressing plate 39 is fixed on support plate 40, and adjustment plate I 56 is fixed on support plate 40, hits plate 57 and is fixed in adjustment plate I 56,
Footstock the 43rd, nut the 44th, leading screw the 45th, silk seat 46 is fixed on upper plate 38 by silk seat 46 after assembling, and is used for adjusting big pulley III
52-3 and the degree of tightness of steel wire rope 35, material rotating plate assembly 58 is fixed axle 77 by material rotating plate and is fixed on the bin mechanism shown in Fig. 3-2
Upper beam 22 on, material rotating plate bracket component 74 is fixed on material rotating plate assembly 58 by support shaft 78, and cylinder assembly I63 left end is solid
Being scheduled on the cylinder block 25 of the bin mechanism shown in Fig. 3-2, cylinder assembly I63 right-hand member is connected with bar portion free bearing 75, bar portion free bearing
75 are connected fastening by free bearing axle 76 with material rotating plate bracket component 74, and pneumatic triplet 66 is fixed on front column 20, pneumatic commutation
Electromagnetic valve I 67 be fixed on lower support beam 21 on, magnetic sensor I69, magnetic sensor II 70 respectively with cylinder assembly II 64 two ends
Fixing, pneumatic reversing solenoid valve II 68 is fixed on the rear column 24 of the bin mechanism shown in Fig. 3-2, magnetic sensor III 71,
Magnetic sensor IV72 is fixed on the two ends of cylinder assembly I63;Front material assembly 59 and after-poppet assembly 60 are all fixed on bin
On the upper beam 22 of mechanism, steel wire rope 35 is connected to one around assembly pulley I a, assembly pulley II b, assembly pulley III c, assembly pulley IV d
Rise, and be fastened on set ring seat 47-1 at left and right two ends, on 47-2, set ring seat 47-1, set ring seat 47-2 and left supported plate the 41st, right
Plate 42 connects fixing respectively, and the length adjusting steel wire rope 35 is fastened by rope cramp, is fixed steel wire rope 35 by pressing plate 39, uses pipe
Connecting the gas outlet 48 of pneumatic triplet 66 and the air inlet 48-2 of pneumatic reversing solenoid valve I 67, pneumatic reversing solenoid valve I 67 is left
Bring out gas port 48-5 and cylinder assembly II 64 left end air inlet 48-3, cylinder assembly II 64 right-hand member gas outlet 48-6 and cylinder assembly
II 64 right-hand member air inlet 48-1.Air enters pneumatic triplet 66 from air inlet 48-4, by the gas outlet of pneumatic triplet 66
The 48 air inlet 48-2 entering pneumatic reversing solenoid valve I 67, enter gas by pneumatic reversing solenoid valve I 67 left end gas outlet 48-5
Cylinder component II 64 left end air inlet 48-3, right-hand member gas outlet 48-6 enter cylinder assembly II 64 right-hand member air inlet 48-1, thus real
Existing cylinder assembly II 64 moves left and right.
When ventilation is to gentle dynamic reversing solenoid valve II 68 of pneumatic triplet 66, the piston rod of cylinder assembly I 63 is to the left and right
Mobile, drive material rotating plate bracket component 74 to swing, material rotating plate support 74 drives material rotating plate assembly 58 to rise and fall, by material rotating plate assembly 58
Workpiece is slided into before adjusting on a material assembly 59 and after-poppet assembly 60 along material rotating plate bracket component 74 inclined-plane, then
Transmitting information by magnetic sensor III 71, magnetic sensor IV 72, cylinder assembly II 64 starts, the piston of cylinder assembly II 64
Bar band movable pulley left socle 34-1, pulley right support 34-2, assembly pulley I a, assembly pulley II b are reciprocal on rolling linear guide I 61
Mobile, drive steel wire rope 35 to move simultaneously, steel wire rope 35 carries again running block III c, assembly pulley IV d to rotate, and then band dynamic pressure plate
39th, the slide block 62-1 motion of support plate 40 and rolling linear guide II 62, the slide block 62-1 of rolling linear guide II 62 drives and adjusts
Plate I 56, hit plate 57 and do linear reciprocating motion on rolling linear guide II 62, hit plate 57 and promote workpiece by adjust rear
Frame assembly the 60th, front material assembly 59 moves to guiding mechanism direction, thus realizes being transported to workpiece in guiding mechanism.
Described after-poppet assembly 60 props up containing fixed plate III 106, adjustment plate II 107, right bearing bearing I 108, left bearing
Seat I 109, sliding panel I 110, locating shaft the 111st, bearing outside I 112, pad the 113rd, protective cover 114 and bearing IV 120, bearing IV 120
It is arranged on locating shaft 111 and bearing outside I 112, then pad 113 is installed and is screwed on locating shaft 111, protective cover
114 are arranged in bearing outside I 112 hole, and two, left and right locating shaft 111 is separately mounted to left bearing bearing II 109, right bearing props up
On seat I 108, and right bearing bearing I 108, left bearing bearing I 109 are all fixed in adjustment plate II 107 by screw 121, adjust
Plate II 107 is fixed on again on sliding panel I 110 by screw 122, and sliding panel I 110 is fixed on fixed plate III 106 by screw 123
On, fixed plate III 106 is welded on the upper beam I 23 of the bin mechanism shown in Fig. 3-3, and the center that adjusts is high, centre-to-centre spacing, makes after-poppet
Assembly is all on the same line.
Before described, a material assembly 59 props up containing fixed plate IV 125, adjustment plate III 126, right bearing bearing II 115, left bearing
Seat II 116, sliding panel II 127, axle the 117th, spacer the 118th, bearing outside II 119 and two, left and right bearing V 124, bearing V 124
Be arranged on axle the 117th, bearing outside II 119 and left bearing bearing II 116, on right bearing bearing II 115, spacer 118 is arranged on axle
On 117, compress bearing inner race, then fixed by hole back-up ring 128 and shaft block ring 129 respectively, and left and right bearing spider II
116th, 115 being separately fixed at again in adjustment plate III 126 by screw 130, adjustment plate III 126 is fixed on again cunning by screw 131
On dynamic plate 127, sliding panel II 127 is fixed in fixed plate IV 125 by screw 132, and fixed plate IV 125 is welded on Fig. 3-3 institute
On the upper beam I 23 of the bin mechanism showing, the center that adjusts is high, centre-to-centre spacing, and before making, a material assembly 59 and after-poppet assembly 60 are same
On straight line.
Described guiding mechanism contains splicing sleeve assembly the 97th, support 98, and described splicing sleeve assembly 97 is containing bearing holder (housing, cover) the 79th,
Feeding connector the 80th, bearing bonnet the 81st, round nut the 82nd, bonnet the 83rd, spacer the 84th, bearing III 96, bearing III 96 is arranged on bearing holder (housing, cover)
And on feeding connector 80, bearing bonnet 81 is fixed on feeding connector 80 by hex bolts 102, round nut 82 and bearing
Set 79 connection, spacer 84 is arranged in bearing holder (housing, cover) 79 endoporus, and bonnet 83 is fixed on bearing bonnet 81 by hex bolts 103,
Splicing sleeve assembly 97 is fixed on support 98 by bearing support 85.
Described support 98 contains seat board II 86, T-slot nut the 87th, upper beam II 88, column II 89, crossbeam II 90, fixes
Plate II 91, adjustment screw III 92, bottom girder III 93, base plate IV 94, underbeam II 95, adjust screw III 92 and be provided with adjusting nut III
92-1, upper beam II 88 is connected with column II 89, crossbeam II 90, underbeam II 95, bottom girder III 93, and T-slot nut 87 is installed present
On plate II 86, bearing support 85 is connected by hex bolts 99 with seat board II 86, and seat board II 86 is fixed on by hex bolts 100
On upper beam II 88, base plate IV 94 is connected with bottom girder III 93 by adjusting screw III 92, base plate IV 94 and fixed plate II 91 welding, Gu
Determining plate II 91 to be fixed on column II 89 by hex bolts 104, the center adjusting 4 support set assemblies 97 is high, after centre-to-centre spacing,
Trip bolt 100, workpiece is delivered in lathe by 4 guided bearing assembly endoporus 101.
Fig. 6-1, Fig. 6-2 illustrate the use state diagram when present invention uses on lathe, it can be seen that put material
Frame mechanism G, automatic feed mechanism S, guiding mechanism D group constitute the automatic feeder equipment of the present invention, and workpiece W is placed on and puts on bin,
Adjust putting bin to suitable angle, utilize the inclination gravity of workpiece W to automatic feed mechanism material rotating plate assembly 58, by keeping off
Block 27 positions, it is achieved feeding;Transmitting signal by magnetic sensor III 71, IV 72, pneumatic triplet 66 supplies, pneumatic commutation electricity
Magnet valve II 68 starts, and cylinder assembly I 63 drives material rotating plate bracket component 74 to move along a straight line, and drives material rotating plate assembly the 58th, workpiece W
Rising together, workpiece props up before rolling into through material rotating plate assembly 58 inclined-plane on material assembly the 59th, after-poppet assembly 60, magnetic sensor I
69th, II 70 transmission signal, pneumatic reversing solenoid valve I 67 starts, and cylinder assembly II 64 band running block I a, assembly pulley II b are in rolling
Moving back and forth on dynamic line slideway I 61, rolling linear guide I 61 moves back and forth and drives steel wire rope 35 to move, and then above drive
Assembly pulley III c, assembly pulley IV d rotate, drive simultaneously and hit plate 57 and move, hit plate 57 and move promotion workpiece W and move, workpiece W quilt
Deliver in guiding mechanism, by the endoporus 101 of 4 groups of bearing sleeve assemblies 97 as guiding, workpiece W is delivered to lathe by main shaft II and adds
Territory, work area, completes automatic charging.When workpiece W is transported to bump against with collision block IV, magnetic sensor V 73 transmits signal, air cylinder group
Part II 64 stop motion, digital control system starts, and chuck III Automatic-clamping workpiece W completes once to circulate, and self-feeding completes.
Concrete operations are as follows:
Adjust front material assembly the 59th, the after-poppet assembly 60 putting bin mechanism, bin mechanism, feed mechanism, in guiding mechanism
The heart is high, centre-to-centre spacing, with lathe center always, makes workpiece W to pass through.
Lifting workpiece W fills on bin putting, and activation system, workpiece W slips on material rotating plate assembly 58 automatically, cylinder assembly
I 63 pneumatic drive material rotating plate assemblies 58 prop up on material assembly 59 and after-poppet assembly 60 before delivering to workpiece W, cylinder assembly II 64 gas
Dynamic band running block I a, assembly pulley II b move back and forth on rolling linear guide I 61, and then drive above steel wire rope 35 drive
Assembly pulley III c, assembly pulley IV d move along a straight line along rolling linear guide II 62, promote workpiece W through guiding mechanism send into machine
Bed main shaft II to collision block IV positions, thus reaches self-feeding purpose.
Cylinder assembly of the present invention, pneumatic triplet, pneumatic reversing solenoid valve, magnetic sensor are directly buy
Parts, are not described in detail.