CN106120656A - A kind of constructing device changing waterstop under water and using method thereof - Google Patents

A kind of constructing device changing waterstop under water and using method thereof Download PDF

Info

Publication number
CN106120656A
CN106120656A CN201610664116.4A CN201610664116A CN106120656A CN 106120656 A CN106120656 A CN 106120656A CN 201610664116 A CN201610664116 A CN 201610664116A CN 106120656 A CN106120656 A CN 106120656A
Authority
CN
China
Prior art keywords
aqueduct
access path
water
waterstop
section steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610664116.4A
Other languages
Chinese (zh)
Other versions
CN106120656B (en
Inventor
周剑波
高作平
张畅
谭星舟
周志勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Jucheng Structure Group Co ltd
Original Assignee
WUDA JUCHENG STRUCTURE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUDA JUCHENG STRUCTURE Co Ltd filed Critical WUDA JUCHENG STRUCTURE Co Ltd
Priority to CN201610664116.4A priority Critical patent/CN106120656B/en
Publication of CN106120656A publication Critical patent/CN106120656A/en
Application granted granted Critical
Publication of CN106120656B publication Critical patent/CN106120656B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Barrages (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Revetment (AREA)

Abstract

A kind of constructing device changing waterstop under water and using method thereof, constructing device therein is that interior the covering along aqueduct expansion joints of aqueduct is provided with access path (2), and it is provided with pressurization channel-section steel (5) between access path (2) bottom and aqueduct sidewall (3) and aqueduct base plate (4), the groove face of pressurization channel-section steel (5), towards aqueduct sidewall (3) and aqueduct base plate (4), is provided with pressurised airbag (6) in pressurization channel-section steel (5);Using method therein include make sense channel (2), installation construction device, the water taken away in access path (2) cavity and by pressurised airbag (6) inflating pressure, change original waterstop (1) and this constructing device entirety hung out step.Effectively seal and prevent external water stream from entering in access path (2), create the space of a construction for underwater construction.

Description

一种水下更换止水带的施工装置及其使用方法A construction device for underwater waterstop replacement and its application method

技术领域technical field

本发明涉及一种水下更换止水带的施工装置,更具体的说涉及一种水下更换止水带的施工装置及其使用方法,属于渡槽止水带更换技术领域。The invention relates to a construction device for underwater replacement of a water stop, more specifically to a construction device for underwater replacement of a water stop and a method for using the same, and belongs to the technical field of aqueduct water stop replacement.

背景技术Background technique

渡槽是输送水流跨越河渠、道路、山沟等的架空输水建筑结构,是渠系建筑结构中应用最广泛的交叉建筑结构之一。渡槽除了用于输送渠水进行农田灌溉、城镇生活用水、工业用水跨流域输水外,其还可提供排水和导流的作用。An aqueduct is an overhead water delivery structure that transports water across river canals, roads, ravines, etc. It is one of the most widely used intersecting building structures in canal building structures. In addition to being used to transport canal water for farmland irrigation, urban domestic water, and industrial water transport across river basins, the aqueduct can also provide drainage and diversion.

随着渡槽采用壳槽、薄壁结构日益增多,渡槽构件间的接头、伸缩缝处的防渗问题也随之增加。为了防止渡槽的渗漏,目前通常在渡槽伸缩缝处安装两道止水带,一个是内嵌式止水带即浇筑在混凝土里面的;另一个是面贴式止水带,是安装在渡槽伸缩缝表面,以方便日后维修更换。但是,对于有些重要的渡槽来说,一旦通水后就很难停止供水给你检修的空间和时间,因此其面临着在有水流的情况下解决伸缩缝止水带的维修和更换问题。As aqueducts adopt more and more shell tanks and thin-walled structures, the problems of anti-seepage at joints and expansion joints between aqueduct components also increase. In order to prevent the leakage of the aqueduct, two waterstops are usually installed at the expansion joints of the aqueduct, one is an embedded waterstop that is poured into the concrete; the other is a surface-mounted waterstop that is installed on the aqueduct The surface of the expansion joint is convenient for future maintenance and replacement. However, for some important aqueducts, it is difficult to stop the water supply to give you space and time for maintenance once the water is passed through, so it is faced with the problem of repairing and replacing the expansion joint waterstop when there is water flow.

发明内容Contents of the invention

本发明的目的在于针对现有的在有水流的情况下伸缩缝止水带的维修和更换较难的等问题,提供一种水下更换止水带的施工装置及其使用方法。The object of the present invention is to provide a construction device for underwater replacement of waterstops and a method of use thereof for existing problems such as difficult maintenance and replacement of expansion joint waterstops in the presence of water flow.

本发明为实现上述目的,所采用技术解决方案是:一种水下更换止水带的施工装置,所述的渡槽内沿着渡槽伸缩缝覆盖安装有检修通道。In order to achieve the above purpose, the technical solution adopted by the present invention is: a construction device for underwater replacement of waterstops, wherein the aqueduct is covered with maintenance channels along the expansion joints of the aqueduct.

所述的检修通道底部与渡槽侧壁和渡槽底板之间设置有加压槽钢,所述加压槽钢的槽面朝向渡槽侧壁和渡槽底板,加压槽钢内设置有加压气囊。A pressurized channel steel is arranged between the bottom of the maintenance passage, the side wall of the aqueduct and the bottom plate of the aqueduct, the groove surface of the pressurized channel steel faces the side wall of the aqueduct and the bottom plate of the aqueduct, and a pressurized air bag is arranged in the pressurized channel steel.

所述的加压气囊与渡槽侧壁和渡槽底板之间填充有柔性防水材料。A flexible waterproof material is filled between the pressurized air bag, the side wall of the aqueduct and the bottom plate of the aqueduct.

一种水下更换止水带的施工装置的使用方法,包括以下步骤:A method for using a construction device for underwater replacement of a waterstop, comprising the following steps:

步骤一,按要求下料、制作好检修通道各构件的尺寸,再制作好检测通道;Step 1: Cut the material according to the requirements, make the size of each component of the inspection channel, and then make the detection channel;

步骤二,将安装好的检修通道沉入过水渡槽中,安装于伸缩缝止水带的位置;Step 2, sink the installed maintenance channel into the aqueduct and install it at the position of the expansion joint water stop;

步骤三,将检修通道空腔内的水抽出,同时将加压气囊充气加压,利用检修通道外部水压力作用将加压槽钢与渡槽侧壁和渡槽底板之间压紧,柔性防水材料将加压气囊与渡槽侧壁和渡槽底板之间缝隙完全填充,从而实现检修通道与外侧水体之间的隔水作用;Step 3: Pump out the water in the cavity of the maintenance channel, and at the same time, inflate the pressurized air bag to pressurize the pressurized channel steel, the side wall of the aqueduct and the bottom plate of the aqueduct by using the external water pressure of the maintenance channel, and the flexible waterproof material will The gap between the pressurized air bag and the side wall of the aqueduct and the bottom plate of the aqueduct is completely filled, so as to realize the water isolation function between the maintenance channel and the outer water body;

步骤四,待检修通道内水抽完后,更换原有止水带;Step 4, after the water in the maintenance channel is pumped out, replace the original water stop belt;

步骤五,止水带安装后验收合格后将本施工装置整体吊出。Step 5: After the installation of the waterstop is checked and accepted, the construction device will be hoisted out as a whole.

所述的步骤一中包括下面的步骤:Described step one comprises the following steps:

步骤一,制作好检修通道的钢结构骨架;Step 1, making the steel structure skeleton of the maintenance channel;

步骤二,将加压槽钢与检修通道的钢结构骨架焊接成整体;Step 2, welding the pressurized channel steel and the steel structure skeleton of the maintenance channel into a whole;

步骤三,将未充气的加压气囊置于加压槽钢中;Step 3, placing the uninflated pressurized air bag in the pressurized channel steel;

步骤四,将柔性防水材料与加压槽钢和加压气囊固定为整体。Step 4, fixing the flexible waterproof material, the pressurized channel steel and the pressurized air bag as a whole.

与现有技术相比较,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:

本发明在渡槽内沿着渡槽伸缩缝止水带覆盖安装有检修通道,然后抽走检修通道空腔内的水,同时将加压气囊充气加压;利用检修通道外部水压力作用将加压槽钢与渡槽侧壁和渡槽底板之间压紧,从而可以有效密封防止外部水流进入检修通道内,为水下施工创造了一个施工的空间。In the present invention, an inspection passage is covered and installed in the aqueduct along the waterstop of the expansion joint of the aqueduct, and then the water in the inspection passage cavity is pumped away, and the pressurized air bag is inflated and pressurized at the same time; The steel is pressed tightly between the side wall of the aqueduct and the bottom plate of the aqueduct, so that it can be effectively sealed to prevent external water flow from entering the maintenance channel, creating a construction space for underwater construction.

附图说明Description of drawings

图1是本发明结构示意图。Fig. 1 is a schematic diagram of the structure of the present invention.

图2是本发明立面图。Fig. 2 is the elevation view of the present invention.

图中,止水带1,检修通道2,渡槽侧壁3,渡槽底板4,加压槽钢5,加压气囊6,柔性防水材料7。In the figure, a waterstop 1, an inspection channel 2, an aqueduct side wall 3, an aqueduct bottom plate 4, a pressurized channel steel 5, a pressurized air bag 6, and a flexible waterproof material 7.

具体实施方式detailed description

以下结合附图说明和具体实施方式对本发明作进一步的详细描述。The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

参见图1至图2,一种水下更换止水带的施工装置,为水下检修和更换伸缩缝止水带1创造一个施工空间,具体适用于渡槽或其他水工结构的面贴式止水带维修或更换;所述的渡槽内沿着渡槽伸缩缝覆盖安装有检修通道2。该检修通道2为钢结构通道。Referring to Figure 1 to Figure 2, a construction device for underwater replacement of waterstops creates a construction space for underwater maintenance and replacement of expansion joint waterstops 1, and is specifically suitable for surface-mounted waterstops of aqueducts or other hydraulic structures. The hose is repaired or replaced; the aqueduct is covered with an inspection channel 2 along the expansion joint of the aqueduct. The maintenance channel 2 is a steel structure channel.

参见图2,所述的检修通道2底部与渡槽侧壁3和渡槽底板4之间设置有加压槽钢5;所述加压槽钢5的槽面朝向渡槽侧壁3和渡槽底板4,加压槽钢5内设置有加压气囊6。Referring to Fig. 2, a pressurized channel steel 5 is arranged between the bottom of the maintenance channel 2 and the aqueduct side wall 3 and the aqueduct bottom plate 4; the groove surface of the pressurized channel steel 5 faces the aqueduct side wall 3 and the aqueduct bottom plate 4, A pressurized air bag 6 is arranged in the pressurized channel steel 5 .

参见图2,所述的加压气囊6与渡槽侧壁3和渡槽底板4之间填充有柔性防水材料7。Referring to FIG. 2 , a flexible waterproof material 7 is filled between the pressurized air bag 6 , the aqueduct side wall 3 and the aqueduct bottom plate 4 .

参见图1至图2,一种水下更换渡槽止水带的施工装置的使用方法,包括以下步骤:Referring to Fig. 1 to Fig. 2, a method for using a construction device for underwater replacement of an aqueduct waterstop comprises the following steps:

步骤一,按要求下料、制作好检修通道2各构件的尺寸,再制作好检测通道2。Step 1: Cutting the material according to the requirements, making the dimensions of the components of the inspection channel 2, and then making the detection channel 2.

步骤二,将安装好的检修通道2沉入过水渡槽中,安装于伸缩缝止水带1的位置。Step 2, sink the installed maintenance channel 2 into the aqueduct, and install it at the position of the expansion joint waterstop 1.

步骤三,将检修通道2空腔内的水抽出,同时将加压气囊7充气加压,利用检修通道2外部水压力作用将加压槽钢5与渡槽侧壁3和渡槽底板4之间压紧;柔性防水材料7将加压气囊6与渡槽侧壁3和渡槽底板4之间缝隙完全填充,从而实现检修通道2与外侧水体之间的隔水作用。Step 3: pump out the water in the cavity of the maintenance channel 2, and at the same time inflate the pressurized air bag 7 to pressurize the pressure between the pressurized channel steel 5 and the aqueduct side wall 3 and the aqueduct bottom plate 4 by using the external water pressure of the maintenance channel 2. Tight; the flexible waterproof material 7 completely fills the gap between the pressurized airbag 6 and the aqueduct side wall 3 and the aqueduct bottom plate 4, thereby realizing the water-proof effect between the maintenance channel 2 and the outer water body.

步骤四,待检修通道2内水抽完后,更换原有止水带1。Step 4: After the water in the maintenance channel 2 is pumped out, the original water stop 1 is replaced.

步骤五,止水带1安装后验收合格后将本施工装置整体吊出。Step five, after the installation of the waterstop 1 is checked and accepted, the construction device is hoisted out as a whole.

具体的,所述的步骤一中包括下面的步骤:Specifically, the step one includes the following steps:

步骤一,制作好检修通道2的钢结构骨架。Step 1, make the steel structure skeleton of the maintenance channel 2.

步骤二,将加压槽钢5与检修通道2的钢结构骨架焊接成整体。Step 2, welding the pressurized channel steel 5 and the steel structure skeleton of the maintenance channel 2 into a whole.

步骤三,将未充气的加压气囊6置于加压槽钢5中。Step 3, placing the uninflated pressurized air bag 6 in the pressurized channel steel 5 .

步骤四,将柔性防水材料7与加压槽钢5和加压气囊6固定为整体。Step 4, fixing the flexible waterproof material 7, the pressurized channel steel 5 and the pressurized airbag 6 as a whole.

参见图1至图2,本发明在渡槽内沿着渡槽伸缩缝止水带1覆盖安装有检修通道2,然后抽走检修通道2空腔内的水,同时将加压气囊6充气加压;利用检修通道2外部水压力作用将加压槽钢5与渡槽侧壁3和渡槽底板4之间压紧,从而可以有效密封防止外部水流进入检修通道2内,为水下施工创造了一个施工的空间,解决了在有水流的情况下伸缩缝止水带的维修和更换问题。Referring to Fig. 1 to Fig. 2, the present invention covers and installs an inspection passage 2 along the aqueduct expansion joint waterstop 1 in the aqueduct, then pumps away the water in the inspection passage 2 cavity, and inflates the pressurized air bag 6 at the same time; Utilize the external water pressure of the maintenance channel 2 to compress the pressurized channel steel 5, the side wall 3 of the aqueduct and the bottom plate 4 of the aqueduct, so as to effectively seal and prevent the external water flow from entering the maintenance channel 2, creating a construction environment for underwater construction It solves the problem of maintenance and replacement of expansion joint waterstops under the condition of water flow.

以上内容是结合具体的优选实施方式对本发明所作的进一步详细说明,不能认定本发明的具体实施只局限于这些说明。对于本发明所属技术领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干简单推演或替换,上述结构都应当视为属于本发明的保护范围。The above content is a further detailed description of the present invention in conjunction with specific preferred embodiments, and it cannot be assumed that the specific implementation of the present invention is limited to these descriptions. For those of ordinary skill in the technical field to which the present invention belongs, some simple deduction or replacement can also be made without departing from the concept of the present invention, and the above structures should be regarded as belonging to the protection scope of the present invention.

Claims (5)

1. the constructing device changing waterstop under water, it is characterised in that: cover along aqueduct expansion joints in described aqueduct Access path (2) is installed.
A kind of constructing device changing aqueduct waterstop under water the most according to claim 1, it is characterised in that: described inspection Repair and be provided with pressurization channel-section steel (5), described pressurization channel-section steel (5) between passage (2) bottom and aqueduct sidewall (3) and aqueduct base plate (4) Groove face towards aqueduct sidewall (3) and aqueduct base plate (4), be provided with pressurised airbag (6) in pressurization channel-section steel (5).
A kind of constructing device changing aqueduct waterstop under water the most according to claim 2, it is characterised in that: described adds Flexible waterproof material (7) it is filled with between pressuring gasbag (6) and aqueduct sidewall (3) and aqueduct base plate (4).
4. the using method of the constructing device changing waterstop under water, it is characterised in that comprise the following steps:
Step one, blanking on request, makes the size of access path (2) each component, then makes sense channel (2);
Step 2, sank to, in water aqueduct, be installed on the position of expansion joint water stop (1) by mounted access path (2);
Step 3, extracts out the water in access path (2) cavity, simultaneously by pressurised airbag (7) inflating pressure, utilizes access path (2) effect of external water pressure power will compress between pressurization channel-section steel (5) and aqueduct sidewall (3) and aqueduct base plate (4), flexible waterproof material (7) gap between pressurised airbag (6) and aqueduct sidewall (3) and aqueduct base plate (4) is filled up completely with, thus realizes access path (2) impermeable role and between the water body of outside;
Step 4, after Awaiting Overhaul passage (2) interior water exhausts, changes original waterstop (1);
Step 5, hangs out this constructing device entirety after acceptance(check) after waterstop (1) installation.
The using method of a kind of constructing device changing waterstop under water the most according to claim 4, it is characterised in that institute The step one stated includes below step:
Step one, makes the steel structure framework of access path (2);
Step 2, is welded into entirety by the steel structure framework of pressurization channel-section steel (5) with access path (2);
Step 3, is placed in the pressurised airbag (6) of unaerated in pressurization channel-section steel (5);
Step 4, is fixed as entirety by flexible waterproof material (7) with pressurization channel-section steel (5) and pressurised airbag (6).
CN201610664116.4A 2016-08-12 2016-08-12 A kind of application method of the underwater constructing device for changing waterstop Active CN106120656B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610664116.4A CN106120656B (en) 2016-08-12 2016-08-12 A kind of application method of the underwater constructing device for changing waterstop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610664116.4A CN106120656B (en) 2016-08-12 2016-08-12 A kind of application method of the underwater constructing device for changing waterstop

Publications (2)

Publication Number Publication Date
CN106120656A true CN106120656A (en) 2016-11-16
CN106120656B CN106120656B (en) 2018-03-30

Family

ID=57258672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610664116.4A Active CN106120656B (en) 2016-08-12 2016-08-12 A kind of application method of the underwater constructing device for changing waterstop

Country Status (1)

Country Link
CN (1) CN106120656B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727142A (en) * 2021-01-05 2021-04-30 三峡大学 Device and method for repairing underwater crack by using superfine magnetic cement mortar
CN112832147A (en) * 2021-01-26 2021-05-25 武大巨成结构股份有限公司 Sidewall maintenance device and maintenance method for aqueduct under continuous water condition
CN113512991A (en) * 2021-06-22 2021-10-19 长江勘测规划设计研究有限责任公司 Aqueduct structure and waterstop maintenance construction device and using method thereof
CN119221428A (en) * 2024-12-02 2024-12-31 浙江元兴工程顾问有限公司 A water-stopping device for the joints between aqueducts used in water conservancy projects

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005023514A (en) * 2003-06-30 2005-01-27 Sumitomo Metal Ind Ltd Waterproof joint structure and its construction method
CN101781885A (en) * 2010-03-12 2010-07-21 中国水电顾问集团中南勘测设计研究院 Composite rubber water stop tape and slope sticking type water stop structure
CN203821313U (en) * 2014-05-09 2014-09-10 河北省水利水电第二勘测设计研究院 Water stop device with replaceable aqueduct expansion joints
CN104314048A (en) * 2014-11-10 2015-01-28 张朝利 Manufacture and Construction Method of Airbag Concrete Engineering Deformation Joint Waterproof Cavity Form
CN205444121U (en) * 2016-01-07 2016-08-10 中国电建集团华东勘测设计研究院有限公司 That can not cut off water supply maintenance aqueduct wall goes along with sb. to guard him facility temporarily
CN205975505U (en) * 2016-08-12 2017-02-22 武大巨成结构股份有限公司 Change construction equipment of waterstop under water

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005023514A (en) * 2003-06-30 2005-01-27 Sumitomo Metal Ind Ltd Waterproof joint structure and its construction method
CN101781885A (en) * 2010-03-12 2010-07-21 中国水电顾问集团中南勘测设计研究院 Composite rubber water stop tape and slope sticking type water stop structure
CN203821313U (en) * 2014-05-09 2014-09-10 河北省水利水电第二勘测设计研究院 Water stop device with replaceable aqueduct expansion joints
CN104314048A (en) * 2014-11-10 2015-01-28 张朝利 Manufacture and Construction Method of Airbag Concrete Engineering Deformation Joint Waterproof Cavity Form
CN205444121U (en) * 2016-01-07 2016-08-10 中国电建集团华东勘测设计研究院有限公司 That can not cut off water supply maintenance aqueduct wall goes along with sb. to guard him facility temporarily
CN205975505U (en) * 2016-08-12 2017-02-22 武大巨成结构股份有限公司 Change construction equipment of waterstop under water

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727142A (en) * 2021-01-05 2021-04-30 三峡大学 Device and method for repairing underwater crack by using superfine magnetic cement mortar
CN112832147A (en) * 2021-01-26 2021-05-25 武大巨成结构股份有限公司 Sidewall maintenance device and maintenance method for aqueduct under continuous water condition
CN113512991A (en) * 2021-06-22 2021-10-19 长江勘测规划设计研究有限责任公司 Aqueduct structure and waterstop maintenance construction device and using method thereof
CN119221428A (en) * 2024-12-02 2024-12-31 浙江元兴工程顾问有限公司 A water-stopping device for the joints between aqueducts used in water conservancy projects

Also Published As

Publication number Publication date
CN106120656B (en) 2018-03-30

Similar Documents

Publication Publication Date Title
CN102900848B (en) A kind of shield machine belt pressure warehouse entry airbag sealing unit and method
CN106120656B (en) A kind of application method of the underwater constructing device for changing waterstop
CN107489435B (en) Replaceable inflatable water stop for mine tunnel
CN204530780U (en) The water proof structure of underground-structure deformation joint
CN104344152B (en) Pipeline non-excavation rehabilitation device and trenchless repairing method
CN108316347A (en) Partition waterproof assembly type underground comprehensive pipe gallery and waterproof method thereof
CN110565585A (en) A folding portable water that fills encloses well for piping is speedily carried out rescue work
CN203393678U (en) Permanent expansion joint water stop structure
CN107576574B (en) A test method for the ultimate water pressure resistance of the same size of the waterstop buried in the deformation joint
CN207261914U (en) Pipeline non-excavation rehabilitation device
CN205975505U (en) Change construction equipment of waterstop under water
CN203514482U (en) Novel sealing plastic inspection well
CN107130620B (en) Channel steel cofferdam method for arranging with the flow-compensated function of section
CN104964121B (en) A kind of sleeve water leakage plugging method
CN104110014A (en) Floating body flap valve
CN208152086U (en) Partition waterproof assembled underground comprehensive pipe gallery
CN219220508U (en) Emergent drainage water retaining device of tunnel construction
CN103175664B (en) Non-return valve connecting portion sealing property model test apparatus and test method
CN111692454A (en) Seepage-proofing reinforcing device for pipeline and repairing method thereof
CN106655068A (en) Flexible pipeline clogging device
CN205035830U (en) Drainage structure is prevented with basement bottom plate movement joint department that escape canal combined together to movement joint
CN212251495U (en) Concrete pond underwater equipment installation device
CN104154369B (en) Lined Prestressed concrete cylinder pipe boring device and boring method
CN203628052U (en) Large-diameter pipeline wall penetrating sealing flexible connection structure
CN114351846B (en) Flexible cut-off device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Zhou Jianbo

Inventor after: Gao Zuoping

Inventor after: Zhou Zhou

Inventor after: Zhang Chang

Inventor after: Tan Xingzhou

Inventor after: Zhou Zhiyong

Inventor before: Zhou Jianbo

Inventor before: Gao Zuoping

Inventor before: Zhang Chang

Inventor before: Tan Xingzhou

Inventor before: Zhou Zhiyong

CB03 Change of inventor or designer information
CP01 Change in the name or title of a patent holder

Address after: No. 4, Wuda Science and Technology Park Road, Donghu Development Zone, Wuhan City, Hubei Province, 430223

Patentee after: Wuhan Jucheng Structure Group Co.,Ltd.

Address before: No. 4, Wuda Science and Technology Park Road, Donghu Development Zone, Wuhan City, Hubei Province, 430223

Patentee before: WUDA JUCHENG STRUCTURE Co.,Ltd.

CP01 Change in the name or title of a patent holder