CN106089234B - A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range - Google Patents

A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range Download PDF

Info

Publication number
CN106089234B
CN106089234B CN201610557466.0A CN201610557466A CN106089234B CN 106089234 B CN106089234 B CN 106089234B CN 201610557466 A CN201610557466 A CN 201610557466A CN 106089234 B CN106089234 B CN 106089234B
Authority
CN
China
Prior art keywords
line
haulage drift
stopping
connection roadway
mechanized mining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610557466.0A
Other languages
Chinese (zh)
Other versions
CN106089234A (en
Inventor
姜福兴
舒凑先
朱斯陶
李东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of Science and Technology Beijing USTB
Original Assignee
University of Science and Technology Beijing USTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of Science and Technology Beijing USTB filed Critical University of Science and Technology Beijing USTB
Priority to CN201610557466.0A priority Critical patent/CN106089234B/en
Publication of CN106089234A publication Critical patent/CN106089234A/en
Application granted granted Critical
Publication of CN106089234B publication Critical patent/CN106089234B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/06Transport of mined material at or adjacent to the working face
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Abstract

The present invention provides a kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range, belongs to mining technique field.Before this method predominantly stops adopting line first advance, haulage drift is dug along coal wall stopping adopting on the outside of line;Connection roadway is excavated between haulage drift and stopping adopts line, in connection roadway and haulage drift construction major diameter pressure relief vent;At connection roadway and haulage drift arrangement stress monitoring station;In working face close to danger of burst when stopping adopting line, is found, release processing is carried out in time;Treat that working face extraction to the position of terminal mining line carries out round-off work.It this approach reduce adit and bump danger occur, and bull parallel operations are realized by connection roadway, improve and withdraw speed.It has been essentially ensures that safe, the stopping surface of quickly moving of deep thump fully-mechanized mining working.

Description

A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range
Technical field
The present invention relates to mining technique fields, particularly relate to a kind of auxiliary lane multichannel Quick-return fully-mechanized mining working of long range Method.
Background technology
The removal of home stopping surface of fully-mechanized mining working is the important production preparation of fully mechanized mining production mine, it is not only mine realization The important step of safety in production, and directly restrict the raising of fully-mechanized mining working unit yield.With coal mine machinery journey The raising of degree, high-power, large-tonnage mechanical equipment application, removal of home stopping surface work seriously constrain fully-mechanized mining working unit yield Raising.Quick removal of home stopping surface mainly has following two Quick-return methods at present:(1) CN1482344A discloses working face Mian Fu lanes multichannel moving process, in working face the position of terminal mining line, minimum two substantially parallel, phases are dug out along coal wall first for it Adit at a certain distance;Then several connection roadways are excavated between at least two adits, so as to fulfill Quick-return.(2) a kind of methods of single channel railless plastic core-rubber-tire vehicle back withdrawing fully-mechanized mining working face of CN101349159A, it is first in fully mechanized mining Working face, which stops adopting, tunnels a return channel and supporting at line;Then oblique adjusting is carried out during advanced 38~42m, during ending, in hydraulic pressure Metal mesh and half round timber are laid on set cap, finally after working face and return channel perforation, withdraws working face equipment.It is above-mentioned Two kinds of fully-mechanized mining working Quick-return methods are largely promoted and applied in superficial part mine, and obtain good result, but with It and adopts deep increasing, the concentrated stress and coverage that working face surface bearing pressure generates apparent become occur compared with superficial part Change, when causing return channel with working face perforation, phenomena such as gradually appearing roof fall, deformation and impact, seriously affected fully mechanized mining work Make safe, the stopping surface of quickly moving in face.Therefore, it is badly in need of research deep thump fully-mechanized mining working safety, quick removal of home stopping surface side Method.
The content of the invention
The technical problem to be solved by the present invention is to overcome deep thump fully-mechanized mining working safety, the difficulties of quick removal of home stopping surface Point, the method that a kind of auxiliary lane multichannel Quick-return fully-mechanized mining working of long range is provided.
This method comprises the following steps:
(1) before stopping to adopt line first advance 300m, away from the position for stopping adopting 60~80m on the outside of line, one is dug along coal wall The item haulage drift substantially parallel with stopping adopting line;
(2) two or more connection roadways are excavated between haulage drift and stopping adopts line, realizes rack restoring bull concurrent job;
(3) supporting is carried out to connection roadway and haulage drift;
(4) it is 110~250mm in connection roadway and haulage drift construction aperture, pitch-row 2m, hole depth is the major diameter of 15m Pressure relief vent;
(5) three or more stress monitoring stations are arranged in connection roadway and haulage drift, each stress monitoring station arranges that two are answered Power monitoring point, strain gauge are embedded in stress monitoring point, and the depth of two stress monitoring points is respectively 15m, 7m;
(6) connection roadway and haulage drift stress monitoring station stress variation shape are paid close attention to close to when stopping adopting line in working face Condition finds danger of burst, carries out release processing in time;
(7) treat that working face extraction to the position of terminal mining line carries out round-off work.
Wherein, connection roadway uses bolt-mesh-anchor support, while is equipped with hydraulic prop, mining I-beam and pile formula hydraulic pressure branch Frame;Connection roadway and haulage drift cure floor using concrete, and haulage drift carries out supporting using anchor rete cord.
Compared to superficial part fully-mechanized mining working, the tunnel of the supported pressure influence in deep is easier that rock blast hazard occurs.This By stopping adopting line 60~80m location arrangements haulage drifts, favourable avoids supporting pressure influence, adds stabilization for invention Property;By strengthening supporting, the impact resistance of connection roadway is improved.
Large diameter borehole shifts to an earlier date release, reduces the stress concentration degree of auxiliary lane peripheral rock, ensures the low stress of country rock Environment;It arranges stress monitoring hole, monitors the surrouding rock stress environment in auxiliary lane closely, it is found that the rock burst fatalness area is carried out at release in time Reason, so as to ensure the stabilization in the auxiliary lane of working face.
The above-mentioned technical proposal of the present invention has the beneficial effect that:
The present invention proposes a kind of auxiliary lane multichannel fully-mechanized mining working safety of long range, the method for quick removal of home stopping surface, from And reduce adit and bump danger occurs, and bull parallel operations are realized by connection roadway, it improves and withdraws speed. It has been essentially ensures that safe, the stopping surface of quickly moving of deep thump fully-mechanized mining working.
The present invention is avoided the influence of the supported pressure of haulage drift, is reduced connection roadway using long range roadway layout scheme Supported pressure influence scope.So as to improve the ambient stress in headentry road and connection roadway, roadway support warp is reduced Take, be conducive to stent withdraws operation.
The formation of " multichannel " realizes working face and removes the bull operation of frame, the superiority of sectional management top plate, in fully mechanized mining Working face is widely applied.Extra exit of the connection roadway as working face, the safety for creating to withdraw to operating personnel Passage is conducive to improve work efficiency.Bull operation removes frame speed to improve, shorten remove the creation of frame time condition be even more it is aobvious and It is clear to.
The use of lane multichannel new process auxiliary over long distances makes deep thump fully-mechanized mining working ensure the situation of safety Under, realize the quick removal of home stopping surface of working face.Its main efficacy results is:
1) avoid branch bearing capacity influences on a large scale, so as to ensure that the stabilization in most of tunnel;
2) the driving expense of passage and supporting expense are effectively reduced, shortens the formation time of removal of home system;
3) escape way is more, keeps away that calamity circuit is more, so as to add the sense of security of worker;
4) face roof is easily managed, and is realized and is withdrawn stent bull parallel operations, is segmented caving, so as to greatest extent Ground reduces the generation of working face concentrated stress and the intensity shown, makes the remaining stent of working face should from significantly concentrating Power improves the load situation of stent, and very good operating environment is created for quick removal of home stopping surface.
Description of the drawings
Fig. 1 is the schematic diagram one that the embodiment of the present invention is related to;
Fig. 2 is the schematic diagram two that the embodiment of the present invention is related to;
Fig. 3 is the schematic diagram three that the embodiment of the present invention is related to.
Wherein:1-haulage drift;2-connection roadway;3-stop adopting line;4-hydraulic support;5-air return way;6-work Face;7-major diameter pressure relief vent;8-strain gauge.
Specific embodiment
To make the technical problem to be solved in the present invention, technical solution and advantage clearer, below in conjunction with attached drawing and tool Body embodiment is described in detail.
The present invention provides a kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range.
As shown in Figure 1, Figure 2 and Figure 3, it is schematic diagram of this method in implementation process, specific implementation step is as follows:
(1) before stopping to adopt 3 first advance of line, 6 distance 300m, away from the position for stopping adopting 3 60~80m of distance of line, along coal wall One haulage drift 1 substantially parallel with stopping adopting line 3 of digging;The tunnel 4.5~5.0m of clear span, 3.6~3.8m of clear height, bottom plate are adopted Cured with concrete, supporting is carried out using anchor rete cord, supporting parameter is as follows:
Net:45 × 45mm, 8# iron wire weave;
Anchor pole:φ18×1600mm;
Rope:φ 15.3 × 7500mm steel strand wires.
(2) according to coal seam geological condition, the technical equipment and economic condition of removal of home, between haulage drift 1 and stopping adopts line 3 Several connection roadways 2 are excavated, constitute " lane multichannel auxiliary over long distances " system.
(3) 2 tunnel 4.5~5.0m of clear span of connection roadway, 3.6~3.8m of clear height, bottom plate are cured using concrete, except using anchor rete cord Outside supporting, hydraulic prop, mining I-beam and brettis are also equipped with, is on the one hand to strengthen, to roof timbering, reducing work Make influence of the rock pressure to tunnel;Shield support when on the other hand being withdrawn as working face.Supporting parameter is as follows:
Net:40 × 40mm, 8# diamond shape iron wire weave;
Anchor pole:φ18×1600mm;
Rope:φ 15.3 × 7500mm steel strand wires;
I-steel:11#;
Individual prop:3.6~3.8;
Brettis:DZ10000-2.5/3.9.
(4) aperture is constructed as 110~250mm in connection roadway 2 and haulage drift 1, pitch-row 2m, hole depth is the big straight of 15m Footpath pressure relief vent 7.
(5) several stress monitoring stations, each stress monitoring station arrangement depth, shallow two are arranged in connection roadway 2 and haulage drift 1 A measuring point, strain gauge 8 are embedded in stress monitoring point, and two 8 buried depths of strain gauge are respectively 15m, 7m.
(6) in working face 6 close to when stopping adopting line 3, paying close attention to connection roadway 2 and 1 stress monitoring station stress of haulage drift becomes Change situation finds danger of burst, carries out release processing in time.
(7) working face 6 is treated to push to adopt to stopping adopting 3 distance 12m positions of line and carries out round-off work, subsequent hydraulic support 4 is from return air Crossheading 5 and connection roadway 2 carry out bull and withdraw from.
The above is the preferred embodiment of the present invention, it is noted that for those skilled in the art For, without departing from the principles of the present invention, several improvements and modifications can also be made, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (1)

  1. A kind of 1. method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range, it is characterised in that:Comprise the following steps:
    (1) before stopping to adopt line first advance 300m, away from the position for stopping adopting 60~80m on the outside of line, along coal wall dig one with Stop adopting the parallel haulage drift of line;
    (2) two or more connection roadways are excavated between haulage drift and stopping adopts line, realizes rack restoring bull concurrent job;
    (3) supporting is carried out to connection roadway and haulage drift;
    (4) it is 110~250mm in connection roadway and haulage drift construction aperture, pitch-row 2m, hole depth is the major diameter release of 15m Hole;
    (5) three or more stress monitoring stations are arranged in connection roadway and haulage drift, two stress prisons are arranged at each stress monitoring station Measuring point, strain gauge are embedded in stress monitoring point, and the depth of two stress monitoring points is respectively 15m, 7m;
    (6) connection roadway and haulage drift stress monitoring station stress variation situation are paid close attention to close to when stopping adopting line in working face, sent out Existing danger of burst, carries out release processing in time;
    (7) treat that working face extraction to the position of terminal mining line carries out round-off work;
    The connection roadway uses bolt-mesh-anchor support, while is equipped with hydraulic prop, mining I-beam and hydraulic chock;Connection Network lane and haulage drift cure floor using concrete, and haulage drift carries out supporting using anchor rete cord.
CN201610557466.0A 2016-07-15 2016-07-15 A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range Active CN106089234B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610557466.0A CN106089234B (en) 2016-07-15 2016-07-15 A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610557466.0A CN106089234B (en) 2016-07-15 2016-07-15 A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range

Publications (2)

Publication Number Publication Date
CN106089234A CN106089234A (en) 2016-11-09
CN106089234B true CN106089234B (en) 2018-05-25

Family

ID=57220619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610557466.0A Active CN106089234B (en) 2016-07-15 2016-07-15 A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range

Country Status (1)

Country Link
CN (1) CN106089234B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108361034B (en) * 2017-11-24 2019-08-30 枣庄矿业(集团)付村煤业有限公司 A kind of order mining large-mining-height working surface is quickly moved technique
CN107956475A (en) * 2017-12-13 2018-04-24 陕西煤业化工技术研究院有限责任公司 A kind of structure and construction method for protecting development work surrounding rock stability
CN109268049A (en) * 2018-08-08 2019-01-25 中国神华能源股份有限公司 Fully-mechanized mining working withdraws method
CN112065395A (en) * 2020-09-16 2020-12-11 刘雪 Method for quickly withdrawing fully-mechanized coal mining face

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4174135A (en) * 1978-04-10 1979-11-13 Bechtel International Corporation Underground formed wall single-entry mining method
CN1482344A (en) * 2002-09-09 2004-03-17 神华集团有限责任公司 Fully-mechanized mining working plane supplementary laneway multiple passage quick-speed moving process
CN101349159A (en) * 2008-08-23 2009-01-21 山西焦煤集团有限责任公司 Method of single channel railless plastic core-rubber-tire vehicle back withdrawing fully-mechanized mining working face
CN203257456U (en) * 2013-05-08 2013-10-30 中国神华能源股份有限公司 Shift change train lane with inclined communication tunnel
CN103939135A (en) * 2014-05-07 2014-07-23 中国矿业大学 Rapid construction method for support dismantling channel of fully mechanized coal mining face
CN104234749A (en) * 2014-07-10 2014-12-24 中泰德恒(北京)矿业科技有限公司 Surrounding rock control method for large-section dismantling tunnel of fully-mechanized mining face
CN204572003U (en) * 2015-04-14 2015-08-19 六盘水师范学院 Angular region Surrounding Rock Control system is smeared during a kind of comprehensive coal face ending
CN105179002A (en) * 2015-09-08 2015-12-23 南京梅山冶金发展有限公司 Construction method for dynamic ventilation channels of underground mining of thick ore body
CN105736044A (en) * 2013-03-15 2016-07-06 中国矿业大学 Method for rapidly withdrawing fully mechanized coal mining face device of steep seam

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4174135A (en) * 1978-04-10 1979-11-13 Bechtel International Corporation Underground formed wall single-entry mining method
CN1482344A (en) * 2002-09-09 2004-03-17 神华集团有限责任公司 Fully-mechanized mining working plane supplementary laneway multiple passage quick-speed moving process
CN101349159A (en) * 2008-08-23 2009-01-21 山西焦煤集团有限责任公司 Method of single channel railless plastic core-rubber-tire vehicle back withdrawing fully-mechanized mining working face
CN105736044A (en) * 2013-03-15 2016-07-06 中国矿业大学 Method for rapidly withdrawing fully mechanized coal mining face device of steep seam
CN203257456U (en) * 2013-05-08 2013-10-30 中国神华能源股份有限公司 Shift change train lane with inclined communication tunnel
CN103939135A (en) * 2014-05-07 2014-07-23 中国矿业大学 Rapid construction method for support dismantling channel of fully mechanized coal mining face
CN104234749A (en) * 2014-07-10 2014-12-24 中泰德恒(北京)矿业科技有限公司 Surrounding rock control method for large-section dismantling tunnel of fully-mechanized mining face
CN204572003U (en) * 2015-04-14 2015-08-19 六盘水师范学院 Angular region Surrounding Rock Control system is smeared during a kind of comprehensive coal face ending
CN105179002A (en) * 2015-09-08 2015-12-23 南京梅山冶金发展有限公司 Construction method for dynamic ventilation channels of underground mining of thick ore body

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
煤柱过渡区的应力迁移与冲击矿压显现特征;张少杰等;《中国矿业》;20130531;第22卷(第5期);第73-78页 *

Also Published As

Publication number Publication date
CN106089234A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
CN101372891B (en) Strip filling integral backstopping coal mining method
CN103161480B (en) Initiatively support the method for roadside packing gob side entry retaining
CN106089234B (en) A kind of method of the auxiliary lane multichannel Quick-return fully-mechanized mining working of long range
Tu et al. Present situation of fully mechanized mining technology for steeply inclined coal seams in China
CN104775819B (en) Deep inclined coal seam mining roadway mine pressure control mining method
CN104234749B (en) A kind of fully-mechanized mining working big cross section return channel surrounding rock control method
CN109209495B (en) Roof cutting and pressure relief protection method on stoping surface of fully mechanized coal mining face
CN104481578B (en) A kind of high gas layer large-mining-height working surface mash gas harnessing method
CN105240013A (en) Longwall mining N00 construction method
CN102966354A (en) Non-pillar mining method for hard roof coal wall of thick coal seam
CN105134216B (en) Anti- slump structure by the engineering method lane of breaking roof 110
CN104989272B (en) Upward inverse well drilling process
CN106968691A (en) Improve CD method construction methods in a kind of extremely frigid zones silty clay tunnel
CN108868833A (en) A method of it carries out cutting gob side entry retaining in the relieving roadway of top in U-shaped steel supported laneway
CN102418525B (en) Soft coal seam long-wall high-mining-height comprehensive mechanized coal mining end mining method
CN104632220A (en) Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope
CN105736044A (en) Method for rapidly withdrawing fully mechanized coal mining face device of steep seam
CN103089267A (en) Thin-ore-body shallow hole shrinkage method without sill pillar
CN109630112A (en) A kind of N00 mining codes for cutting top filling
CN104405392A (en) Three-soft thick coal seam roadway top-support bottom-retaining anchor-net cable active supporting fully-mechanized caving mining method
CN105134212B (en) A kind of method that three soft high seam tunnel ensures the rate of extraction along top driving longwall top coal caving
CN109577981A (en) A kind of high seam pillar recovery method
CN111472781A (en) Arrangement and construction method of special roadway for coal mining area working face retraction
CN104863599B (en) Fully-mechanized mining working synchronously expands side installation method and support system
CN112780276A (en) Fully-closed blasting pressure relief structure for grouting reconstruction of composite roof and self-retained roadway method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant