CN106088476A - The ultra-high performance concrete cylinder permanent template of self-locking connection and construction method thereof - Google Patents
The ultra-high performance concrete cylinder permanent template of self-locking connection and construction method thereof Download PDFInfo
- Publication number
- CN106088476A CN106088476A CN201610614541.2A CN201610614541A CN106088476A CN 106088476 A CN106088476 A CN 106088476A CN 201610614541 A CN201610614541 A CN 201610614541A CN 106088476 A CN106088476 A CN 106088476A
- Authority
- CN
- China
- Prior art keywords
- high performance
- ultra
- performance concrete
- permanent template
- self
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/34—Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
Abstract
The invention discloses the ultra-high performance concrete cylinder permanent template that a kind of self-locking connects, it is included in the ultra-high performance concrete surrounding layer of prefabrication, is provided with the steel pipe of self-locking attachment structure at two ends, described ultra-high performance concrete surrounding layer is positioned at outer wall of steel pipe, adjacent ultra-high performance concrete cylinder permanent template pass through fastener for connection, adjacent ultra-high performance concrete surrounding layer in junction cast-in-place ultra-high performance concrete to form entirety.Present invention simultaneously provides its construction method.The present invention achieves the axial connection of cylinder permanent template by self-locking structure, enhances the gmatjpdumamics of cylinder permanent template junction, possesses precision high, and speed of application is fast, and the feature that durability is high can meet the needs of various engineering.
Description
Technical field
Patent of the present invention belongs to building materials construction applications, the ultra-high performance concrete circle that a kind of self-locking connects
Post permanent template and construction method thereof.
Background technology
Comparing traditional building form, it is fast that permanent template has speed of application, easy construction, it is not necessary to formwork and dismounting,
Reduce the advantages such as human cost.When the scantling of institute's molding is less, can be solved by monoblock permanent template.But work as structure
When part size is bigger, due to transport, the restriction of lifting cannot directly use monoblock permanent template to solve, it is necessary to by pin-connected panel
Permanent template, and traditional pin-connected panel component generally requires a large amount of cross-brace, support system, sets up complex, expends big
Amount manpower and materials.
Summary of the invention
The problem that it is an object of the invention to overcome prior art to exist, it is provided that the very-high performance that a kind of self-locking connects mixes
Solidifying soil steel pipe column-form and construction method thereof.This cylinder permanent template is prefabricated in the factory, and mould material uses steel pipe and surpasses
High performance concrete.
The present invention adopts the following technical scheme that and realizes:
The ultra-high performance concrete cylinder permanent template that a kind of self-locking connects, is included in the ultra-high performance concrete of prefabrication
Surrounding layer, being provided with the steel pipe of self-locking attachment structure at two ends, described ultra-high performance concrete surrounding layer is positioned at outer wall of steel pipe, phase
Adjacent ultra-high performance concrete cylinder permanent template is by fastener for connection, and described adjacent ultra-high performance concrete surrounding layer is in junction
Cast-in-place ultra-high performance concrete is to form entirety.
Further, described ultra-high performance concrete surrounding layer flushes with outer wall of steel pipe upper end, and the lower end of steel pipe is stretched out super
High performance concrete surrounding layer 200 ~ 300mm, described ultra-high performance concrete surrounding layer two ends are all reserved cast-in-place very-high performance and are mixed
The inclined-plane of solidifying soil.
Further, described steel pipe upper end inwall arranges cross section is trapezoidal helical form inner slope rib.
Further, outside the pipe of described steel pipe lower end connect tubular ribbed steel, described ribbed steel outer wall be provided with
The cross section that described helical form inner slope rib matches is trapezoidal helical form outer slope rib.
Further, described inner slope rib and rib surface, outer slope painting lubricating oil, slope angle θ of rib and skin-friction coefficient μ should
Meet relation: tan θ > μ.
Present invention also offers the construction of the ultra-high performance concrete cylinder permanent template that a kind of described self-locking connects
Method, including step: when locating template, arranges a small amount of diagonal brace to keep the stability of permanent template;Outside described concrete
Covering is cast-in-place ultra-high performance concrete at reserved inclined-plane, and carries out vibration compacting with vibrating spear, and complete before concrete hardens
Become splicing;Described cylinder permanent template crane is directed at, to ensure that the trapezoidal finned surface at the two ends of docking is at same vertical
On line, the most slowly place;Under gravity, superposed cylinder permanent template will screw in lower cylindrical permanent template,
Check that docking is the most accurate;After concrete surface hardens, answer wetted surface and enclose with plastic foil, to prevent water from dividing evaporation mixed
Solidifying soil shrinks excessive, causes the ultra-high performance concrete of junction to ftracture.
Compared to currently used permanent template and common templates, it has the advantage that
Cross-brace greatly reduces, and speed of application is fast, and easy construction uses manpower and material resources sparingly.
Intensity is high, and crack resistance is strong, effectively protects inner concrete.
Being prefabricated in the factory, industrialization degree is high, and quality is guaranteed.
Corrosion resistance and impermeability are superior, have good durability.
Template is lighter, and size is less simultaneously, convenient transport, can carry out the splicing of length direction, good integrity.
Enhance anti-seismic performance and the impact flexibility of structure, reduce the accidental load damage to structure, improve structure reliable
Degree.
Protective layer heat-proof quality is good, and refractory ability is strong.
Due to the constraint of ultra-high performance concrete permanent template and share, structural-load-carrying capacity improves, simultaneously
Integrally-built ductility increases, and fragility reduces.
Accompanying drawing explanation
Fig. 1 is the permanent template top partial enlarged drawing of the embodiment of the present invention.
Fig. 2 is partial enlarged drawing bottom the permanent template of the embodiment of the present invention.
Fig. 3 is the permanent template top view of the embodiment of the present invention.
Fig. 4 is the permanent template upward view of the embodiment of the present invention.
Fig. 5 is the permanent template link position detail drawing of the embodiment of the present invention.
Fig. 6 is the permanent template axonometric chart of the embodiment of the present invention.
Fig. 7 is the another axonometric chart of permanent template of the embodiment of the present invention.
Shown in figure: 1-ultra-high performance concrete surrounding layer;2-steel pipe;3-inner slope rib;4-ribbed steel;5-outer slope rib;
6-junction;7-inclined-plane.
Detailed description of the invention
Being described in further detail the purpose of the present invention with specific embodiment below in conjunction with the accompanying drawings, embodiment can not be
This repeats one by one, but the most therefore embodiments of the present invention are defined in following example.
Embodiment:
As shown in Figure 1 to Figure 4, shown in Fig. 6, Fig. 7, the ultra-high performance concrete cylinder permanent template that a kind of self-locking connects, a diameter of
600mm, long 1500mm, the thickness being included in prefabrication is 30mm ultra-high performance concrete surrounding layer 1, is provided with self-locking at two ends
The steel pipe 2 of tight attachment structure, described steel pipe 2 thickness is 30mm, a length of 1m, and described ultra-high performance concrete surrounding layer is positioned at steel
Pipe 2 outer wall, adjacent ultra-high performance concrete cylinder permanent template is connected by steel pipe 2, described ultra-high performance concrete surrounding layer 1
At the cast-in-place ultra-high performance concrete in junction 6 to form entirety with adjacent surrounding layer.
Described ultra-high performance concrete surrounding layer 1 flushes with steel pipe 2 outer wall upper end, and very-high performance is stretched out in the lower end of steel pipe 2
Concrete surrounding layer 200 ~ 300mm, cast-in-place ultra-high performance concrete is all reserved at described ultra-high performance concrete surrounding layer 1 two ends
Inclined-plane 7.
It is trapezoidal helical form inner slope rib 3 that described steel pipe 2 upper end inwall arranges cross section.Connect outside the pipe of described steel pipe 2 lower end
Connecing tubular ribbed steel 4, it is trapezoidal that described ribbed steel 4 outer wall is provided with the cross section matched with described helical form inner slope rib 3
Helical form outer slope rib 5.
Described inner slope rib 3 and rib 5 surface, outer slope are coated with lubricating oil, and slope angle θ and the skin-friction coefficient μ of rib should meet pass
System: tan θ > μ.
As it is shown in figure 5, the permanent template connecing steel plate in being placed on the nothing of bottom is disposed vertically appointment position, arrange a small amount of oblique
Support to keep the stability of permanent template;Described concrete surrounding layer 6 cast-in-place ultra-high performance concrete at reserved inclined-plane, and use
Vibrating spear carries out vibration compacting, and completes splicing before concrete hardens.By Upper cylindrical permanent template crane pair
Accurate, it is ensured that the trapezoidal finned surface 5 and 3 at the two ends of docking, on same plumb line, is the most slowly placed, and superposed cylinder is permanent
Template will screw in lower cylindrical permanent template, check that docking is accurately;After concrete surface scleroma, wetted surface also encloses with plastic foil
Closing, maintenance reaches intensity to junction concrete.
After above-mentioned two cylinder permanent templates are assembled into entirety, in the space that this cylinder permanent template is surrounded, pour one
Change construction concrete, when the concrete poured is after maintenance reaching design strength, cylinder permanent template with pour mixed
Solidifying soil is solidified into one.This template is without dismounting or wipes one's face, and forms concrete steel pipe and surpass after construction completes
High performance concrete compound system, through experiment test, its axial compression strength is 84.1Mpa, showing compared with same size
Water sea work C50 high-strength concrete cylinder and exceed 72.4%;Cracking load is 57.8Mpa, compared with the cast-in-place sea work of same size
C50 high-strength concrete cylinder exceeds 67.8%.And can effective guarantee normal service of cylinder within structure cycle projected life
Use.After using this template, speed of application is greatly improved simultaneously, need not overlap a large amount of lateral shuttering supporting, need only set up a small amount of dimension
Steady support and workman construct, and improve the economic benefit of engineering.
The above, preferred embodiment the most of the present invention, but protection scope of the present invention is not limited thereto.Any ripe
Know those skilled in the art in scope disclosed in this invention, according to technical scheme and inventive concept thereof
Equivalent or change in addition, broadly falls into protection scope of the present invention.
Claims (6)
1. the ultra-high performance concrete cylinder permanent template that a self-locking connects, it is characterised in that: it is included in prefabrication
Ultra-high performance concrete surrounding layer (1), it is provided with the steel pipe (2) of self-locking attachment structure at two ends, described ultra-high performance concrete
Surrounding layer is positioned at steel pipe (2) outer wall, and adjacent ultra-high performance concrete cylinder permanent template is connected by steel pipe (2), described superelevation
Performance concrete surrounding layer (1) at junction (6) cast-in-place ultra-high performance concrete to form entirety.
The ultra-high performance concrete cylinder permanent template that self-locking the most according to claim 1 connects, it is characterised in that: institute
Stating ultra-high performance concrete surrounding layer (1) to flush with steel pipe (2) outer wall upper end, very-high performance coagulation is stretched out in the lower end of steel pipe (2)
Soil surrounding layer (1) 200 ~ 300mm, cast-in-place ultra-high performance concrete is all reserved at described ultra-high performance concrete surrounding layer (1) two ends
Inclined-plane (7).
The ultra-high performance concrete cylinder permanent template that self-locking the most according to claim 3 connects, it is characterised in that: institute
Stating steel pipe (2) upper end inwall and arranging cross section is trapezoidal helical form inner slope rib (3).
The ultra-high performance concrete cylinder permanent template that self-locking the most according to claim 3 connects, it is characterised in that: institute
Stating and connect tubular ribbed steel (4) outside the pipe of steel pipe (2) lower end, described ribbed steel (4) outer wall is provided with and described helical form
The cross section that inner slope rib (3) matches is outer slope rib (5) of trapezoidal helical form.
5. the ultra-high performance concrete cylinder permanent template connected according to the self-locking described in claim 3 and 4, its feature exists
Being coated with lubricating oil in: described inner slope rib (3) and rib (5) surface, outer slope, slope angle θ of rib and skin-friction coefficient μ should meet relation:
tanθ>μ。
6. the construction method of the ultra-high performance concrete cylinder permanent template connected according to the self-locking described in claim 1 to 5,
It is characterized in that, including step: when locating template, a small amount of diagonal brace is set to keep the stability of permanent template;Described mixed
Solidifying soil surrounding layer cast-in-place ultra-high performance concrete at reserved inclined-plane, and before ultra-high performance concrete initial set, complete splicing;Institute
State cylinder permanent template crane alignment, with ensure the trapezoidal finned surface at two ends of docking on same plumb line, then
Slowly place;Under gravity, superposed cylinder permanent template will screw in lower cylindrical permanent template, check that docking is
No accurately;After having docked, in time cast-in-place ultra-high performance concrete plastic foil is closed, to prevent water from dividing evaporation to cause connecting
The ultra-high performance concrete cracking at place.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610614541.2A CN106088476A (en) | 2016-07-29 | 2016-07-29 | The ultra-high performance concrete cylinder permanent template of self-locking connection and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610614541.2A CN106088476A (en) | 2016-07-29 | 2016-07-29 | The ultra-high performance concrete cylinder permanent template of self-locking connection and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106088476A true CN106088476A (en) | 2016-11-09 |
Family
ID=57478513
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610614541.2A Pending CN106088476A (en) | 2016-07-29 | 2016-07-29 | The ultra-high performance concrete cylinder permanent template of self-locking connection and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106088476A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112376408A (en) * | 2020-11-18 | 2021-02-19 | 福州大学 | UHPC hollow column pier and construction method thereof |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201096233Y (en) * | 2007-10-10 | 2008-08-06 | 天津万联管道工程有限公司 | Longitudinal rib prestressing force steel cylinder concrete pipe |
CN102102423A (en) * | 2011-03-09 | 2011-06-22 | 湖南大学 | Sleeve reinforced concrete column |
CN102373803A (en) * | 2011-11-15 | 2012-03-14 | 天津大学 | Novel precast concrete pipe die and construction method thereof |
CN202580338U (en) * | 2011-12-31 | 2012-12-05 | 北京韩建河山管业股份有限公司 | Prestressed concrete cylinder pipe for jacking construction method |
CN203213401U (en) * | 2013-04-10 | 2013-09-25 | 中建六局第三建筑工程有限公司 | Concrete steel pipe column lining reinforced connecting pipe |
CN103994285A (en) * | 2014-06-09 | 2014-08-20 | 宁夏青龙管业股份有限公司 | Concrete tube |
CN105275095A (en) * | 2015-11-19 | 2016-01-27 | 山东大学 | Circular steel tube column in threaded connection and construction method |
CN206091074U (en) * | 2016-07-29 | 2017-04-12 | 华南理工大学 | From permanent template of locking joint's ultra high performance concrete cylinder |
-
2016
- 2016-07-29 CN CN201610614541.2A patent/CN106088476A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201096233Y (en) * | 2007-10-10 | 2008-08-06 | 天津万联管道工程有限公司 | Longitudinal rib prestressing force steel cylinder concrete pipe |
CN102102423A (en) * | 2011-03-09 | 2011-06-22 | 湖南大学 | Sleeve reinforced concrete column |
CN102373803A (en) * | 2011-11-15 | 2012-03-14 | 天津大学 | Novel precast concrete pipe die and construction method thereof |
CN202580338U (en) * | 2011-12-31 | 2012-12-05 | 北京韩建河山管业股份有限公司 | Prestressed concrete cylinder pipe for jacking construction method |
CN203213401U (en) * | 2013-04-10 | 2013-09-25 | 中建六局第三建筑工程有限公司 | Concrete steel pipe column lining reinforced connecting pipe |
CN103994285A (en) * | 2014-06-09 | 2014-08-20 | 宁夏青龙管业股份有限公司 | Concrete tube |
CN105275095A (en) * | 2015-11-19 | 2016-01-27 | 山东大学 | Circular steel tube column in threaded connection and construction method |
CN206091074U (en) * | 2016-07-29 | 2017-04-12 | 华南理工大学 | From permanent template of locking joint's ultra high performance concrete cylinder |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112376408A (en) * | 2020-11-18 | 2021-02-19 | 福州大学 | UHPC hollow column pier and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104746422B (en) | A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method | |
CN108360370B (en) | A kind of prefabricated steel tube confinement reinforced concrete bridge pier and cushion cap connecting node | |
CN107700361B (en) | A kind of dumb-bell shape grout sleeve and the method for carrying out assembly construction with the grout sleeve | |
CN108505433B (en) | Pier structure and construction method thereof | |
CN205206033U (en) | Frame post connected node suitable for prefabricated assembly building | |
CN106438213B (en) | Tower drum for wind driven generator | |
CN111042185B (en) | Construction method of basement raft foundation with tower crane foundation | |
CN108360712A (en) | A kind of assembled steel reinforced concrete shear force wall and its construction method | |
CN106884502A (en) | A kind of reinforced concrete combination rod structure and same period pouring construction method | |
CN104594193B (en) | A kind of Hollow Slab Beam Bridge superstructure and construction method thereof | |
CN206127746U (en) | Isolation bearing handles accurate location structure of pre -buried steel sheet in back | |
CN105970803B (en) | The shearing resistance energy-dissipating device and construction method of assembled bridge pier | |
CN208251372U (en) | A kind of assembled steel reinforced concrete shear force wall | |
CN105350641B (en) | Suitable for the framework column connected node and its construction technology of prefabrication and assembly construction building | |
CN205662838U (en) | Prestressing force joint construction of pier is assembled to prefabricated segment | |
CN106193644A (en) | Basement reconstruction structure with raft foundation building | |
CN106088476A (en) | The ultra-high performance concrete cylinder permanent template of self-locking connection and construction method thereof | |
CN105951987B (en) | Node and construction method are poured after the secondary external permanent aluminium sheet external mold of frame | |
CN108797321A (en) | A kind of the ECC pipes-concrete prefabricated assembling combination bridge pier and its construction method of spigot-and-socket joint | |
CN206091074U (en) | From permanent template of locking joint's ultra high performance concrete cylinder | |
CN104675138B (en) | A kind of slab balcony reinforcement means for sound insulation and noise reducing transformation | |
CN111926860B (en) | Basement steel column water stop treatment method | |
CN208169729U (en) | A kind of low pressure Prestressed concrete cylinder pipe and defeated drainage pipeline | |
CN108103925A (en) | A kind of assembled hollow steel pipe constrains reinforced column squat pier | |
CN108086136A (en) | A kind of assembled solid steel tube constrains reinforced column squat pier |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161109 |