CN106081735A CN201610645866.7A CN201610645866A CN106081735A CN 106081735 A CN106081735 A CN 106081735A CN 201610645866 A CN201610645866 A CN 201610645866A CN 106081735 A CN106081735 A CN 106081735A
Authority
CN
China
Prior art keywords
wire
drop
coaster
bracket
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610645866.7A
Other languages
Chinese (zh)
Inventor
张书豪
田璐
董四清
熊织明
陈海波
王艳
张甲雷
梁会永
罗本壁
李峰
况月明
刘波
张尔乐
宋学强
郑晓龙
刘晓
田冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Power Transmission and Transformation Co Ltd
State Grid Corp of China SGCC
AC Construction Branch of State Grid Corp of China
Original Assignee
Hebei Power Transmission and Transformation Co Ltd
State Grid Corp of China SGCC
AC Construction Branch of State Grid Corp of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Power Transmission and Transformation Co Ltd, State Grid Corp of China SGCC, AC Construction Branch of State Grid Corp of China filed Critical Hebei Power Transmission and Transformation Co Ltd
Priority to CN201610645866.7A priority Critical patent/CN106081735A/en
Publication of CN106081735A publication Critical patent/CN106081735A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H57/00Guides for filamentary materials; Supports therefor
    • B65H57/14Pulleys, rollers, or rotary bars
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H57/00Guides for filamentary materials; Supports therefor
    • B65H57/04Guiding surfaces within slots or grooves
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H59/00Adjusting or controlling tension in filamentary material, e.g. for preventing snarling; Applications of tension indicators
    • B65H59/10Adjusting or controlling tension in filamentary material, e.g. for preventing snarling; Applications of tension indicators by devices acting on running material and not associated with supply or take-up devices
    • B65H59/18Driven rotary elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H2701/00Handled material; Storage means
    • B65H2701/30Handled filamentary material
    • B65H2701/34Handled filamentary material electric cords or electric power cables

Landscapes

  • Table Equipment (AREA)

Abstract

本发明公开一种导线拖放滑车,涉及输电线路施工专用设备技术领域,用于降低导线放线张力,提高导线展放的施工安全。所述导线拖放滑车包括:固定装置,所述固定装置包括:用于安装在跨越架架体上的固定架,以及与所述固定架固定连接的托架;所述托架上承载有滑轮轴,所述滑轮轴上套设有多个可转动的滑轮,所述滑轮的表面设有用于盛放导线的滑槽。本发明提供的导线拖放滑车用于输电线路架线施工的导线展放。

The invention discloses a wire dragging and dropping tackle, which relates to the technical field of special equipment for transmission line construction, and is used for reducing the tension of wire unwinding and improving the construction safety of wire unwinding. The wire dragging and dropping trolley includes: a fixing device, and the fixing device includes: a fixing frame used to be installed on the frame body of the spanning frame, and a bracket fixedly connected with the fixing frame; the bracket carries a sliding A wheel shaft, a plurality of rotatable pulleys are sheathed on the pulley shaft, and the surfaces of the pulleys are provided with chutes for accommodating wires. The wire drag-and-drop tackle provided by the invention is used for wire laying and laying in power transmission line stringing construction.

Description

一种导线拖放滑车A wire drag and drop tackle

技术领域technical field

本发明涉及输电线路施工专用设备技术领域,具体涉及一种导线拖放滑车。The invention relates to the technical field of special equipment for transmission line construction, in particular to a wire dragging and dropping tackle.

背景技术Background technique

现有技术中的输电线路架线施工包括基础施工、组塔和挂线等,当跨越高速公路、高速铁路等障碍时,一般需要搭设跨越架,之后再进行导线的展放和挂线等。The wiring construction of transmission lines in the prior art includes foundation construction, tower assembly and wire hanging, etc. When crossing obstacles such as expressways and high-speed railways, it is generally necessary to build spanning frames, and then carry out wire spreading and wire hanging.

目前在输电线路架线施工的导线展放过程中,当导线通过跨越架横担时,为了保证导线不被磨损并保证跨越架架体的稳定性,不能使导线与跨越架横担摩擦接触,也就是要求导线与跨越架横担之间保持一定的距离,因此,需要很大的导线放线张力。At present, in the process of laying out the wires in the construction of transmission lines, when the wires pass through the cross-arm of the spanning frame, in order to ensure that the wires are not worn and the stability of the spanning frame body is ensured, the wires cannot be frictionally contacted with the cross-arm of the spanning frame. That is to say, it is required to keep a certain distance between the conductor and the cross arm of the spanning frame, therefore, a large conductor tension is required.

然而,导线放线张力过大,容易使得导线断线,而导线断线的冲击力又会影响到输电线路的架线施工安全。However, if the tension of the wire is too high, it is easy to cause the wire to break, and the impact force of the wire break will affect the safety of the wire construction of the transmission line.

发明内容Contents of the invention

本发明的目的在于提供一种导线拖放滑车,用于降低导线放线张力,提高导线展放的施工安全。The object of the present invention is to provide a wire dragging and dropping block, which is used to reduce the tension of wire unwinding and improve the construction safety of wire unwinding.

为了实现上述目的,本发明提供如下技术方案:In order to achieve the above object, the present invention provides the following technical solutions:

一种导线拖放滑车,包括:固定装置;固定装置包括:用于安装在跨越架架体上的固定架,以及与固定架固定连接的托架;托架上承载有滑轮轴,滑轮轴上套设有多个可转动的滑轮,滑轮的表面设有用于盛放导线的滑槽。A wire dragging and dropping tackle, comprising: a fixing device; the fixing device includes: a fixing frame used to be installed on the frame body of the spanning frame, and a bracket fixedly connected with the fixing frame; a pulley shaft is carried on the bracket, and the pulley shaft A plurality of rotatable pulleys are sheathed, and the surface of the pulleys is provided with a chute for accommodating wires.

本发明提供的导线拖放滑车,通过固定架可以安装在各种钢结构的跨越架架体上,而带有滑槽的滑轮,可以使展放的导线落于滑槽中,这样滑槽不仅能够避免导线与跨越架横担等直接接触,以有效防止导线卡伤或磨损;而且,滑槽还能够对导线起到一定的支撑作用,且由于滑槽对导线支撑力的作用方向,与导线重力的作用方向相反,使得滑槽对导线的支撑力能够抵消导线的部分重力,这就相当于减小了导线的重力,而导线的重力减小,因导线重力作用而产生的导线的放线张力也就随之减小。因此,本发明提供的导线拖放滑车,可以减小导线的放线张力,从而降低导线的断线概率,提高输电线路架线施工的安全性。The wire dragging and dropping block provided by the present invention can be installed on various steel structure spanning frame bodies through the fixing frame, and the pulley with the chute can make the deployed wire fall in the chute, so that the chute not only It can avoid direct contact between the wire and the cross arm of the spanning frame, so as to effectively prevent the wire from being stuck or worn; moreover, the chute can also play a certain supporting role on the wire, and because the direction of the chute’s supporting force on the wire is different from that of the wire The gravity acts in the opposite direction, so that the support force of the chute to the conductor can offset part of the gravity of the conductor, which is equivalent to reducing the gravity of the conductor, while the gravity of the conductor is reduced, and the pay-off of the conductor due to the gravity of the conductor Tension also decreases accordingly. Therefore, the wire dragging and dropping tackle provided by the present invention can reduce the tension of the wires, thereby reducing the probability of wire breakage and improving the safety of the wire construction of the transmission line.

附图说明Description of drawings

此处所说明的附图用来提供对本发明的进一步理解,构成本发明的一部分,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:The accompanying drawings described here are used to provide a further understanding of the present invention, and constitute a part of the present invention. The schematic embodiments of the present invention and their descriptions are used to explain the present invention, and do not constitute improper limitations to the present invention. In the attached picture:

图1为本发明实施例提供的导线拖放滑车的结构主视示意图;Fig. 1 is a schematic front view of the structure of the wire drag and drop tackle provided by the embodiment of the present invention;

图2为本发明实施例提供的导线拖放滑车的结构侧视示意图;Fig. 2 is the schematic side view of the structure of the wire drag and drop tackle provided by the embodiment of the present invention;

图3为本发明实施例提供的固定架的结构示意图。Fig. 3 is a schematic structural diagram of a fixing frame provided by an embodiment of the present invention.

附图标记:Reference signs:

1-固定架, 2-托架,1-Fixer, 2-Bracket,

3-滑轮轴, 4-滑轮,3- pulley shaft, 4- pulley,

10-固定安装孔, 11-底板,10-fixed mounting holes, 11-bottom plate,

12-侧板。12 - Side panels.

具体实施方式detailed description

为便于理解,下面结合说明书附图,对本发明实施例提供的导线拖放滑车进行详细描述。For ease of understanding, the wire dragging and dropping tackle provided by the embodiment of the present invention will be described in detail below in conjunction with the accompanying drawings.

请参阅图1和图2,本发明实施例提供的导线拖放滑车,包括固定装置,固定装置包括:用于安装在跨越架架体上的固定架1,以及与固定架1固定连接的托架2;托架2上承载有滑轮轴3,滑轮轴3上套设有多个可转动的滑轮4,滑轮4的表面设有用于盛放导线的滑槽。Referring to Fig. 1 and Fig. 2, the wire dragging and dropping tackle provided by the embodiment of the present invention includes a fixing device, and the fixing device includes: a fixing frame 1 for being installed on the frame body of the spanning frame, and a bracket fixedly connected with the fixing frame 1 Frame 2; the pulley shaft 3 is carried on the bracket 2, and a plurality of rotatable pulleys 4 are sleeved on the pulley shaft 3, and the surface of the pulley 4 is provided with a chute for accommodating wires.

具体实施时,本发明实施例提供的导线拖放滑车,通过固定架1可以安装在各种钢结构的跨越架架体上,而带有滑槽的滑轮4,可以使展放的导线落于滑槽中,随着导线的展放,盛放导线的滑轮4会绕滑轮轴3发生转动。During specific implementation, the wire dragging and dropping block provided by the embodiment of the present invention can be installed on various steel structures spanning the frame body through the fixed frame 1, and the pulley 4 with the chute can make the wires laid out fall on the In the chute, along with the unfolding of the wires, the pulley 4 accommodating the wires will rotate around the pulley shaft 3 .

当采用上述导线拖放滑车进行导线展放时,通过将导线落于滑槽中,使得滑槽不仅能够避免导线与跨越架横担等直接接触,以有效防止导线卡伤或磨损;而且,滑槽还能够对导线起到一定的支撑作用,且由于滑槽对导线支撑力的作用方向,与导线重力的作用方向相反,使得滑槽对导线的支撑力能够抵消导线的部分重力,这就相当于减小了导线的重力,而导线的重力减小,因导线重力作用而产生的导线的放线张力也就随之减小。因此,本发明实施例提供的导线拖放滑车,可以减小导线的放线张力,从而降低导线的断线概率,提高输电线路架线施工的安全性。When the above-mentioned wire dragging and dropping tackle is used to spread the wires, by dropping the wires into the chute, the chute can not only avoid direct contact between the wires and the cross-arm of the spanning frame, so as to effectively prevent the wires from being stuck or worn out; The groove can also support the wire to a certain extent, and because the direction of the chute’s supporting force on the wire is opposite to the direction of the gravity of the wire, the supporting force of the chute on the wire can offset part of the gravity of the wire, which is quite Because the gravity of the wire is reduced, and the gravity of the wire is reduced, the pay-off tension of the wire due to the gravity of the wire is also reduced. Therefore, the wire dragging and dropping tackle provided by the embodiment of the present invention can reduce the wire tension of the wire, thereby reducing the probability of wire breakage and improving the safety of the wire construction of the transmission line.

另外,随着对导线的牵引和拉伸,导线还可以通过滑槽将导线的放线张力传递给滑轮4,使得滑轮4绕滑轮轴3转动,即导线的放线张力所带来的导线与滑轮4之间的摩擦力转化为滑轮4转动的动力,而滑轮4绕滑轮轴3转动,可以缓冲滑轮4对滑轮轴3的作用力,这也从另一方面减小了导线的放线张力对导线拖放滑车中托架2及固定架1的作用,因而可以减小导线放线张力对跨越架架体的影响。In addition, along with the traction and stretching of the wire, the wire can also pass the pay-off tension of the wire to the pulley 4 through the chute, so that the pulley 4 rotates around the pulley shaft 3, that is, the wire and wire caused by the pay-off tension of the wire and The friction between the pulleys 4 is converted into the power of the pulley 4 rotation, and the pulley 4 rotates around the pulley shaft 3, which can buffer the force of the pulley 4 on the pulley shaft 3, which also reduces the tension of the wire on the other hand. The role of the bracket 2 and the fixed frame 1 in the wire dragging and dropping tackle can reduce the influence of the wire pay-off tension on the spanning frame body.

而且,滑轮4随导线的展放而转动,将导线与滑轮4之间的摩擦力用为滑轮4转动的动力,减弱了导线与滑轮4之间的摩擦力对导线的作用,能够有效避免因该摩擦力作用而造成的导线摩损;而将导线落于滑槽中,还可以通过滑槽两侧面对导线的导向和分隔作用,有效防止多条导线同时展放时出现扭弯、缠绕等情况。And the pulley 4 rotates with the unfolding of the wire, and the friction between the wire and the pulley 4 is used as the power for the rotation of the pulley 4, which weakens the effect of the friction between the wire and the pulley 4 on the wire, and can effectively avoid the friction caused by the wire. The frictional force causes the wires to wear; and the wires fall into the chute, and the two sides of the chute can also guide and separate the wires, effectively preventing twisting and winding when multiple wires are deployed at the same time. Condition.

可选的,滑轮4表面用于盛放导线的滑槽为环形滑槽,所述滑槽的表面应光滑、无尖角毛刺等;当对导线进行牵引和拉伸时,以避免滑槽对导线造成一定的卡伤或磨损。Optionally, the chute on the surface of the pulley 4 for holding the wire is an annular chute, and the surface of the chute should be smooth without sharp burrs; Some damage or wear to the wires.

而为了进一步减缓导线张力对跨越架架体的影响,在滑槽内可设有弹性套;弹性套通过自身的弹性,能够在一定程度上缓冲导线展放过程中的导线张力,减弱导线张力对滑轮4的作用,达到减小导线拖放滑车对跨越架架体的作用力的目的,从而避免对输电线路的架线施工安全产生影响,提高输电线路架线施工的安全性。在本实施例中,弹性套采用橡胶套。And in order to further slow down the influence of the wire tension on the spanning frame body, an elastic sleeve can be provided in the chute; the elastic sleeve can buffer the wire tension in the process of wire deployment to a certain extent through its own elasticity, and weaken the impact of the wire tension on the frame body. The function of the pulley 4 is to reduce the force of the wire dragging and dropping the pulley on the spanning frame body, thereby avoiding the impact on the safety of the wiring construction of the transmission line and improving the safety of the wiring construction of the transmission line. In this embodiment, the elastic sleeve is a rubber sleeve.

需要说明的是,上述实施例中的固定架1和托架2的材质可有多种选择,比如铸铁、铸钢、锻钢等,而为了确保固定架1和托架2具有良好的力学性能,优选用锻钢。It should be noted that the materials of the fixed frame 1 and the bracket 2 in the above-mentioned embodiments can be selected from various materials, such as cast iron, cast steel, forged steel, etc., and in order to ensure that the fixed frame 1 and the bracket 2 have good mechanical properties , preferably forged steel.

具体的,上述实施例中的固定架1的结构可以配合各种跨越架架体的结构进行具体设计,存在有多种选择,只要能够完成导线拖放滑车与跨越架架体的安装固定即可。在本发明实施例提供的导线拖放滑车中,配合最常见的跨越架架体结构,优选一种简单稳固的固定架结构,具体参阅图3,固定架1包括底板11,以及设在底板上表面的两个侧板12;托架2固定连接在底板11下表面;两个侧板12相对设置,且每个侧板12上设有至少两个用于与跨越架架体固定的固定安装孔10。Specifically, the structure of the fixing frame 1 in the above embodiment can be specifically designed in conjunction with various structures spanning the frame body. . In the wire drag and drop tackle provided in the embodiment of the present invention, a simple and stable fixed frame structure is preferred in conjunction with the most common spanning frame structure. Referring to Fig. 3 for details, the fixed frame 1 includes a bottom plate 11, and The two side plates 12 on the surface; the bracket 2 is fixedly connected to the lower surface of the bottom plate 11; the two side plates 12 are arranged oppositely, and each side plate 12 is provided with at least two fixed mounting brackets for fixing with the spanning frame body. hole 10.

本发明实施例中,固定架1由底板11和相对的两个侧板12围成长方体盒状结构,两个侧板12可位于底板11的任意一组对边处。In the embodiment of the present invention, the fixing frame 1 is surrounded by a bottom plate 11 and two opposite side plates 12 to form a cuboid box-like structure, and the two side plates 12 can be located at any pair of opposite sides of the bottom plate 11 .

当配合跨越架架体使用时,将固定架1扣在跨越架架体上,即固定架1的底板11与跨越架架体的顶面面接触,而两个侧板12位于跨越架架体的两侧,通过两个侧板12上的固定安装孔10,能够将导线拖放滑车固定在跨越架的架体上。When used in conjunction with the spanning frame body, the fixed frame 1 is buckled on the spanning frame body, that is, the bottom plate 11 of the fixing frame 1 is in contact with the top surface of the spanning frame body, and the two side plates 12 are located on the spanning frame body. Both sides, through the fixed mounting holes 10 on the two side plates 12, the wire drag and drop tackle can be fixed on the frame body of the spanning frame.

通过上述固定架配合跨越架架体使用的过程可以看出,本固定架1的结构虽然简单,但固定架1通过的底板11与跨越架架体的大面积接触,以及两个侧板12从跨越架架体侧面的固定,能够使导线拖放滑车稳固的安装在跨越架架体上,不会因导线展放时导线张力的作用而受到影响。Through the process of using the above-mentioned fixed frame with the straddling frame body, it can be seen that although the structure of the fixed frame 1 is simple, the base plate 11 passed by the fixed frame 1 is in contact with the large area of the straddling frame body, and the two side plates 12 from the The fixing on the side of the spanning frame body can make the wire dragging and dropping tackle stably installed on the spanning frame body, and will not be affected by the tension of the wires when the wires are deployed.

而为了方便导线拖放滑车的随用随装,固定架1的两个侧板12与跨越架架体之间的固定方式,优选用螺栓固定,这样侧板12上的固定安装孔10应为固定螺纹孔;或者,可以在每个侧板12上设有与固定安装孔10对应且可拆卸的连接套,而在每个连接套上设有固定螺纹孔,具体的,固定安装孔10可为光孔,连接套可为圆柱状套筒,连接套的外圆表面与固定安装孔10的内孔表面过盈配合,在连接套的中心设有固定螺纹孔,用于固定架1与跨越架架体的螺栓固定,通过连接套的拆卸更换,能够延长导线拖放滑车的使用寿命。And in order to facilitate the use of the wire drag and drop tackle, the fixing method between the two side plates 12 of the fixed mount 1 and the spanning frame body is preferably fixed with bolts, so that the fixed mounting hole 10 on the side plate 12 should be fixed threaded holes; or, each side plate 12 can be provided with a detachable connecting sleeve corresponding to the fixed mounting hole 10, and each connecting sleeve is provided with a fixed threaded hole, specifically, the fixed mounting hole 10 can be It is a light hole, and the connecting sleeve can be a cylindrical sleeve. The outer surface of the connecting sleeve is in interference fit with the surface of the inner hole of the fixed installation hole 10. A fixed threaded hole is provided in the center of the connecting sleeve for the fixing frame 1 and the spanning The bolts of the frame body are fixed, and the service life of the wire dragging and dropping tackle can be extended by disassembling and replacing the connecting sleeve.

为了确保固定架1具备足够的强度,底板11和两个侧板12可以为一体式结构,即通过一体冲压成型方式或一体铸造成型方式制作固定架1,使得固定架1具有上述结构特征。而当底板11和两个侧板12为分体式结构时,则通过焊接的方式,将两个侧板12分别焊接在底板11的两个边缘处。In order to ensure that the fixing frame 1 has sufficient strength, the bottom plate 11 and the two side plates 12 can be of an integrated structure, that is, the fixing frame 1 is made by integral stamping or integral casting, so that the fixing frame 1 has the above-mentioned structural features. And when the bottom plate 11 and the two side plates 12 are of split structure, the two side plates 12 are respectively welded to the two edges of the bottom plate 11 by means of welding.

另外,还可以在两个侧板12相对的一面设有垫片,使得固定架1安装在跨越架架体上时,够通过垫片的缓冲填补固定架1与跨越架架体之间的间隙,以保证固定架1和跨越架架体的紧固强度,而且,还可以避免固定架1与跨越架架体直接接触,防止在导线张力的作用下,固定架1对跨越架架体的表面所造成的损伤,从而影响到跨越架的施工质量。In addition, gaskets can also be provided on the opposite sides of the two side plates 12, so that when the fixed frame 1 is installed on the spanning frame body, the gap between the fixed frame 1 and the spanning frame body can be filled by the cushioning of the gasket. , to ensure the fastening strength of the fixed frame 1 and the spanning frame body, and also avoid the direct contact between the fixed frame 1 and the spanning frame body, and prevent the surface of the fixed frame 1 from spanning the frame body under the action of wire tension. The damage caused will affect the construction quality of the spanning frame.

需要说明的是,垫片的材质可以有多种,比如垫纸、橡胶、硅橡胶、软木等,在本实施例中,垫片优选用橡胶材质;并且为了方便使用,可使垫片与侧板胶粘,在垫片磨损时,亦可更换维护。It should be noted that the gasket can be made of various materials, such as pad paper, rubber, silicon rubber, cork, etc. In this embodiment, the gasket is preferably made of rubber; The board is glued, and when the gasket is worn, it can also be replaced and maintained.

此外,上述实施例中的固定架1与托架2也可以为一体式结构或分体式结构;而为了确保导线拖放滑车自身的结构强度,固定架1可和托架2一体形成,比如一体冲压成型、一体铸造成型等;若固定架1与托架2为分体式结构时,固定架1和托架2应通过焊接的方式固定连接。In addition, the fixed frame 1 and the bracket 2 in the above-mentioned embodiments can also be an integral structure or a split structure; and in order to ensure the structural strength of the wire dragging and dropping tackle itself, the fixed frame 1 can be integrally formed with the bracket 2, such as an integrated Stamping molding, integrated casting molding, etc.; if the fixed frame 1 and the bracket 2 are of a split structure, the fixed frame 1 and the bracket 2 should be fixedly connected by welding.

为了减缓导线展放过程中,导线张力对跨越架架体的影响,固定架1还可通过弹性连接件与托架2固定连接。弹性连接件对托架2的承载力具有缓冲作用,能够在导线展放时,减弱因导线张力等带给固定架1的作用力,达到减小导线拖放滑车对跨越架架体的作用力的目的,从而避免对输电线路的架线施工安全产生影响,提高输电线路架线施工的安全性。In order to slow down the influence of the wire tension on the spanning frame during the deployment of the wires, the fixing frame 1 can also be fixedly connected to the bracket 2 through elastic connectors. The elastic connector has a buffering effect on the bearing capacity of the bracket 2, and can weaken the force brought to the fixed frame 1 due to the tension of the wire when the wire is unfolded, so as to reduce the force of the dragging and dropping block of the wire on the spanning frame body The purpose of this is to avoid the impact on the safety of the wiring construction of the transmission line and improve the safety of the wiring construction of the transmission line.

至于弹性连接件的结构可有多种,在本实施例中,弹性连接件具体采用弹簧;弹簧的内径尺寸、外径尺寸及有效圈数等的技术参数,应由本领域技术人员根据实际的载荷强度要求具体确定。As for the structure of the elastic connector, there can be many kinds. In the present embodiment, the elastic connector specifically adopts a spring; Strength requirements are specified.

为了提高托架2的承载强度,可在托架2上分散设置多个辅助支撑部,以分散滑轮轴3带给托架2的作用力。In order to improve the load-bearing strength of the bracket 2 , a plurality of auxiliary supporting parts can be distributed on the bracket 2 to disperse the force brought by the pulley shaft 3 to the bracket 2 .

具体的,参阅图1和图2,滑轮轴3的两端通过位于托架2两边缘处的主支撑结构进行固定支撑,而在托架2中部对应滑轮轴3的区域,等距间隔设置多个辅助支撑肋板,分别与对应的滑轮轴3中部不套设滑轮4的表面进行活动连接或固定连接,实现托架2对滑轮轴3的分散承重。此外,为了减轻导线拖放滑车的重量,方便安装,还可在托架2上设置多个减重孔。Specifically, referring to Fig. 1 and Fig. 2, the two ends of the pulley shaft 3 are fixedly supported by the main support structure located at the two edges of the bracket 2, and in the area corresponding to the pulley shaft 3 in the middle of the bracket 2, there are more equidistant intervals. Auxiliary support ribs are respectively movably connected or fixedly connected to the surface of the corresponding pulley shaft 3 that is not sleeved with pulley 4, so as to realize the distributed load bearing of bracket 2 to pulley shaft 3. In addition, in order to reduce the weight of the wire dragging and dropping tackle and facilitate installation, multiple weight-reducing holes can also be provided on the bracket 2 .

可选的,滑轮轴3的轴线方向与固定架1的侧板12平面为同一方向或互相垂直均可,具体应由导线拖放滑车在跨越架架体上的安装位置确定。例如:当导线拖放滑车安装在跨越架的横担上,用于使导线沿垂直跨越架横担的方向跨过跨越架的横担时,滑轮轴3的轴线方向与固定架1的侧板12平面为同一方向。Optionally, the axial direction of the pulley shaft 3 and the plane of the side plate 12 of the fixed frame 1 can be in the same direction or be perpendicular to each other, which should be determined by the installation position of the wire dragging and dropping block on the spanning frame body. For example: when the wire drag and drop block is installed on the cross arm of the spanning frame, and is used to make the wire cross the cross arm of the spanning frame along the direction perpendicular to the cross arm of the spanning frame, the axial direction of the pulley shaft 3 and the side plate of the fixed frame 1 12 planes are in the same direction.

需要说明的是,上述实施例中的滑轮4可以为尼龙轮,在滑轮4的轮体内孔设有与滑轮轴3配合的轴承,以实现滑轮4的可转动连接,具体的,轴承可选用滚动轴承,滚动轴承具有较高的承载能力,且使用维护方便。而且为了延长滑轮4的使用寿命,在滑轮4的轮体内孔与轴承之间还可设置耐磨套。It should be noted that the pulley 4 in the above embodiment can be a nylon wheel, and a bearing that cooperates with the pulley shaft 3 is provided in the inner hole of the pulley 4 to realize the rotatable connection of the pulley 4. Specifically, the bearing can be a rolling bearing , Rolling bearings have high load carrying capacity and are easy to use and maintain. And in order to prolong the service life of pulley 4, wear-resistant sleeve can also be set between the wheel inner hole of pulley 4 and the bearing.

另外,滑轮4的个数,应由本领域技术人员根据输电线路的架线施工的实际需要具体确定,本实施例中,选用8个滑轮:8个滑轮沿滑轮轴3的轴向无间隔设置,使导线拖放滑车的结构较为紧凑;也可沿滑轮轴3的轴向等距间隔的套设在滑轮轴3上,使多条导线保持一定的间隔距离,防止多条导线同时展放时出现扭弯、缠绕等情况。In addition, the number of pulleys 4 should be specifically determined by those skilled in the art according to the actual needs of the wire construction of the transmission line. In this embodiment, 8 pulleys are selected: 8 pulleys are arranged without intervals along the axial direction of the pulley shaft 3, Make the structure of the wire dragging and dropping tackle more compact; it can also be sleeved on the pulley shaft 3 at equidistant intervals along the axial direction of the pulley shaft 3, so that multiple wires can be kept at a certain distance to prevent multiple wires from appearing when they are deployed at the same time. Twisting, winding, etc.

在导线的展放过程中,为了减弱沿滑轮轴3的轴线方向上滑轮4对托架2的作用力,不论8个滑轮是沿滑轮轴3的轴向依次无间隔的套设在滑轮轴3上,还是沿滑轮轴3的轴向等距间隔的套设在滑轮轴3上,均可在相邻的两个滑轮4之间设有弹性缓冲件,且在弹性缓冲件上设有可与滑轮轴3相配合的卡接件;弹性缓冲件具体可选用橡胶垫片或伸缩软管等,卡接件具体可选用能与滑轮轴3进行卡接的限位挡圈。In the process of wire deployment, in order to weaken the force of the pulley 4 on the bracket 2 along the axial direction of the pulley shaft 3, regardless of whether the 8 pulleys are sleeved on the pulley shaft 3 in sequence without intervals along the axial direction of the pulley shaft 3 On the pulley shaft 3, it is also sleeved on the pulley shaft 3 at equidistant intervals along the axial direction of the pulley shaft 3. An elastic buffer can be provided between two adjacent pulleys 4, and an elastic buffer can be provided on the elastic buffer. The clamping piece matched with the pulley shaft 3; the elastic buffer can be specifically selected from rubber gaskets or telescopic hoses, etc., and the clamping piece can be specifically selected from a limit retaining ring that can be clamped with the pulley shaft 3.

当8个滑轮沿滑轮轴3的轴向依次无间隔的套设在滑轮轴3上时,位于最外端的两个滑轮的外侧面,可贴合设有橡胶垫片和限位挡圈,橡胶垫片位于滑轮的外侧面与限位挡圈之间,而限位挡圈与滑轮轴3卡接,用以承担8个滑轮彼此之间沿滑轮轴3的轴线方向的作用力,防止各滑轮沿滑轮轴3的轴线方向发生大幅度窜动;而其他的滑轮之间可以不必设置限位挡圈,视情况选择使用橡胶垫片。When the 8 pulleys are sleeved on the pulley shaft 3 without intervals along the axial direction of the pulley shaft 3, the outer surfaces of the two pulleys at the outermost ends can be fitted with rubber gaskets and stop rings. The gasket is located between the outer surface of the pulley and the limit stop ring, and the limit stop ring is clamped with the pulley shaft 3 to bear the force between the 8 pulleys along the axis of the pulley shaft 3 and prevent each pulley from A large amount of movement occurs along the axial direction of the pulley shaft 3; while other pulleys do not need to be provided with stop rings, and rubber gaskets are selected according to the situation.

当然,若托架2的主支撑结构与位于最外端的两个滑轮的外侧面相贴合时,托架2的主支撑结构就能够承担8个滑轮彼此之间沿滑轮轴3的轴线方向的作用力,也无需再设置限位挡圈,用于防止各滑轮沿滑轮轴3的轴线方向发生大幅度窜动。Of course, if the main support structure of the bracket 2 fits with the outer surfaces of the two pulleys located at the outermost ends, the main support structure of the bracket 2 can bear the role of the eight pulleys along the axial direction of the pulley shaft 3 force, and there is no need to set a limit retaining ring, which is used to prevent the pulleys from significantly moving along the axial direction of the pulley shaft 3.

当8个滑轮沿滑轮轴3的轴向依次等距间隔的套设在滑轮轴3上时,在每个滑轮的两侧均可对应设有伸缩软管和限位挡圈,伸缩软管位于相邻两个滑轮的侧面之间,而限位挡圈可设于相邻两个滑轮之间的间隔中部并与滑轮轴3卡接,用以承担8个滑轮彼此之间沿滑轮轴3的轴线方向的作用力,防止各滑轮沿滑轮轴3的轴线方向发生大幅度窜动。When the 8 pulleys are sleeved on the pulley shaft 3 at equidistant intervals along the axial direction of the pulley shaft 3, a telescopic hose and a stop ring can be correspondingly provided on both sides of each pulley, and the telescopic hose is located on the Between the sides of two adjacent pulleys, the stop ring can be set in the middle of the interval between two adjacent pulleys and snapped with the pulley shaft 3 to bear the distance between the 8 pulleys along the pulley shaft 3 The active force in the axial direction prevents each pulley from significantly moving along the axial direction of the pulley shaft 3 .

在上述实施方式的描述中,具体特征、结构、材料或者特点可以在任何的一个或多个实施例或示例中以合适的方式结合。In the description of the above embodiments, specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in an appropriate manner.

以上所述,仅为本发明的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到变化或替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应以所述权利要求的保护范围为准。The above is only a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Anyone skilled in the art can easily think of changes or substitutions within the technical scope disclosed in the present invention. Should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be determined by the protection scope of the claims.

Claims (10)

1. a wire drag and drop coaster, it is characterised in that including: fixing device;Described fixing device includes: be used for being arranged on across The more fixed mount on frame support body, and fix, with described fixed mount, the bracket being connected;Pulley spindle is carried on described bracket, described Being arranged with multiple rotating pulley on pulley spindle, the surface of described pulley is provided with the chute for holding wire.
Wire drag and drop coaster the most according to claim 1, it is characterised in that described fixed mount includes base plate, and is located at Two side plates of plate upper surface;Described bracket is fixedly connected on base plate lower surface;
Two described side plates are oppositely arranged, and each described side plate is provided with at least two and consolidates for fixing with crossing frame support body Determine installing hole.
Wire drag and drop coaster the most according to claim 2, it is characterised in that each described side plate is provided with fixing with described Installing hole is corresponding and dismountable adapter sleeve, and each described adapter sleeve is provided with fixing screwed hole;Or, described fixed installation hole is Fixing screwed hole.
Wire drag and drop coaster the most according to claim 2, it is characterised in that described base plate and two described side plates are integrated Formula structure;Or, two described side plates are respectively welded at the Liang Ge edge of described base plate.
Wire drag and drop coaster the most according to claim 2, it is characterised in that the one side that two described side plates are relative is equipped with Pad;Described pad is gluing with described side plate.
Wire drag and drop coaster the most according to claim 1, it is characterised in that described fixed mount and described bracket one bodily form Become;Or, described fixed mount and described bracket are fixing by the way of welding to be connected.
Wire drag and drop coaster the most according to claim 1, it is characterised in that described fixed mount passes through Flexible Connector and institute State the fixing connection of bracket;And/or, it is provided with resilient sleeve in described chute.
8. according to the arbitrary described wire drag and drop coaster of claim 1-7, it is characterised in that described fixed mount and described bracket are Steelframe.
Wire drag and drop coaster the most according to claim 8, it is characterised in that be provided with bullet between two adjacent described pulleys Property bolster, described resilient snubber is provided with the shackle member that can match with described pulley spindle.
Wire drag and drop coaster the most according to claim 9, it is characterised in that described pulley is set in by rolling bearing On described pulley spindle.
CN201610645866.7A 2016-08-08 2016-08-08 A kind of wire drag and drop coaster Pending CN106081735A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610645866.7A CN106081735A (en) 2016-08-08 2016-08-08 A kind of wire drag and drop coaster

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610645866.7A CN106081735A (en) 2016-08-08 2016-08-08 A kind of wire drag and drop coaster

Publications (1)

Publication Number Publication Date
CN106081735A true CN106081735A (en) 2016-11-09

Family

ID=57457109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610645866.7A Pending CN106081735A (en) 2016-08-08 2016-08-08 A kind of wire drag and drop coaster

Country Status (1)

Country Link
CN (1) CN106081735A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107149262A (en) * 2017-05-25 2017-09-12 平湖市乾业进出口有限公司 A kind of hair-dryer device
CN113277421A (en) * 2021-06-09 2021-08-20 安徽送变电工程有限公司 Line turning crossing device based on crane

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11215632A (en) * 1998-01-29 1999-08-06 Yutaka Consultant:Kk Metal wheel
CN201813104U (en) * 2010-09-21 2011-04-27 河南省电力公司三门峡供电公司 Uncoiling tackle
CN102868118A (en) * 2012-09-05 2013-01-09 中国电力科学研究院 Assembled paying-off pulley and paying-off tackle
CN202840366U (en) * 2012-09-18 2013-03-27 辽宁省送变电工程公司 Double door wire uncoiling tackle for stringing of a power transmission line
CN204809755U (en) * 2015-06-24 2015-11-25 天津市迈威电力器材科技有限公司 Unwrapping wire coaster that can install fast and dismantle
CN105811316A (en) * 2016-03-23 2016-07-27 国家电网公司 Crossing line-passing apparatus for overhead conductor
CN205873502U (en) * 2016-08-08 2017-01-11 国家电网公司 Wire drag and drop coaster

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11215632A (en) * 1998-01-29 1999-08-06 Yutaka Consultant:Kk Metal wheel
CN201813104U (en) * 2010-09-21 2011-04-27 河南省电力公司三门峡供电公司 Uncoiling tackle
CN102868118A (en) * 2012-09-05 2013-01-09 中国电力科学研究院 Assembled paying-off pulley and paying-off tackle
CN202840366U (en) * 2012-09-18 2013-03-27 辽宁省送变电工程公司 Double door wire uncoiling tackle for stringing of a power transmission line
CN204809755U (en) * 2015-06-24 2015-11-25 天津市迈威电力器材科技有限公司 Unwrapping wire coaster that can install fast and dismantle
CN105811316A (en) * 2016-03-23 2016-07-27 国家电网公司 Crossing line-passing apparatus for overhead conductor
CN205873502U (en) * 2016-08-08 2017-01-11 国家电网公司 Wire drag and drop coaster

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋平海: "《张力架线机械设备和应用》", 30 April 1992, 水利电力出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107149262A (en) * 2017-05-25 2017-09-12 平湖市乾业进出口有限公司 A kind of hair-dryer device
CN113277421A (en) * 2021-06-09 2021-08-20 安徽送变电工程有限公司 Line turning crossing device based on crane

Similar Documents

Publication Publication Date Title
CN104617521A (en) Cable laying device
CN102811936A (en) Arrangement for damping lateral sways of a rope-like means fixed to an elevator car
CN204198145U (en) Cable drum device
CN205873502U (en) Wire drag and drop coaster
CN209823279U (en) Fast assembly's unwrapping wire coaster
CN106081735A (en) A kind of wire drag and drop coaster
CN104229545A (en) Paying-off device
CA1065773A (en) Suspended cable apparatus
CN102303824A (en) Ward-off rope device and engineering machinery with same
CN202321803U (en) Steel wire rope guiding device
CN103663171A (en) Cranes and their poles
CN105439006B (en) A kind of hoist cable stabilising arrangement for crane
CN204002494U (en) The groove separation preventing device of flexible gate lifting wire rope
CN203612860U (en) Steel wire rope winding device of large portal crane
CN102602794A (en) Special tool for lifting bushing
CN204138016U (en) Cable spreader for cable-stayed bridges
CN202829379U (en) Tower crane with automatic balancing device
JP2004189441A (en) Main cable detachment preventer of sheave for elevator
RU2309109C1 (en) Device for winding fiber-optic cablke on carrying wire
CN202594599U (en) Tool special for hoisting casing
CN215934293U (en) High tension transmission line alternately stridees across unwrapping wire construction abrasionproof and decreases device
CN207173595U (en) Mining overhead man-riding main shaft off-axis protection device and its main shaft device of application
CN112736763A (en) Elasticity unwrapping wire coaster device with adjustable rigidity
CN201758255U (en) Vertical horizontal cable guide
CN207596314U (en) a crane hook

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109