CN106052916A - Earth pressure box burying device and method for fill engineering - Google Patents
Earth pressure box burying device and method for fill engineering Download PDFInfo
- Publication number
- CN106052916A CN106052916A CN201610640739.8A CN201610640739A CN106052916A CN 106052916 A CN106052916 A CN 106052916A CN 201610640739 A CN201610640739 A CN 201610640739A CN 106052916 A CN106052916 A CN 106052916A
- Authority
- CN
- China
- Prior art keywords
- pressure cell
- connecting rod
- soil pressure
- box
- earth pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01L—MEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
- G01L1/00—Measuring force or stress, in general
- G01L1/26—Auxiliary measures taken, or devices used, in connection with the measurement of force, e.g. for preventing influence of transverse components of force, for preventing overload
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种用于填方工程的土压力盒埋设装置及方法,其包括连接杆、置盒盘、套管和密封盖。连接杆为中空螺纹杆,可以通过套管组合不同长度的连接杆至设计长度;置盒盘可通过定位螺母调节土压力盒的测量位置;密封盖用于密封连接杆的顶端和底端。该方法首先通过定位螺母将置盘盒固定在第一节连接杆上,并调整至设计测量位置;然后采用焊接的方式将土压力盒固定在置盒盘的置盒区;随着填土高度的增加,通过套管将第二节连接杆与第一节连接杆连接固定,并安装土压力盒;以此类推,最后达到设计填筑高度后,将所有导线从总线孔引出,并安装顶盖进行密封。本发明整体结构简单,操作方便,使用效果良好,有效地保证了土压力盒埋设的精度要求。
The invention discloses an earth pressure box embedding device and method for filling engineering, which comprises a connecting rod, a box setting plate, a casing and a sealing cover. The connecting rod is a hollow threaded rod, which can be combined with connecting rods of different lengths to the designed length through the casing; the box setting plate can adjust the measurement position of the earth pressure cell through the positioning nut; the sealing cover is used to seal the top and bottom ends of the connecting rod. In this method, firstly, the disc box is fixed on the first connecting rod through the positioning nut, and adjusted to the designed measurement position; then, the earth pressure box is fixed in the box area of the box tray by welding; with the filling height increase, connect and fix the second connecting rod with the first connecting rod through the bushing, and install the earth pressure cell; The cover is sealed. The present invention has the advantages of simple overall structure, convenient operation and good use effect, and effectively guarantees the precision requirement for embedding the earth pressure box.
Description
技术领域technical field
本发明涉及一种用于填方工程的土压力盒埋设装置及方法,属于现场施工监测技术领域。The invention relates to an earth pressure box embedding device and method for filling engineering, and belongs to the technical field of on-site construction monitoring.
背景技术Background technique
随着我国铁路、公路、土石坝等基础设施工程建设的不断推进,填方工程中的应力、变形等的长期监测成为设计优化、施工控制以及养护维修的主要数据来源。其中,应力的监测通常依赖于埋设于土体中的土压力盒。现有技术中,填方工程土压力盒的埋设一般采用直接将土压力盒埋入填土中的方法,而该方法存在土压力盒随填土沉降而沉降,以至于土压力盒的受力方式及其所在位置发生变化,导致监测数据出现误差大、失效等问题。因此,迫切需要一种测量数据准确、埋设便捷的土压力盒埋设装置及方法来解决上述问题。With the continuous advancement of infrastructure projects such as railways, highways, and earth-rock dams in my country, long-term monitoring of stress and deformation in fill engineering has become the main data source for design optimization, construction control, and maintenance. Among them, the monitoring of stress usually depends on the earth pressure cell buried in the soil. In the prior art, the burial of earth pressure cells in fill engineering generally adopts the method of directly burying the earth pressure cells in the fill, but in this method, the earth pressure cells will settle with the settlement of the fill, so that the force of the earth pressure cells Changes in the way and location of the monitoring data lead to problems such as large errors and failures in the monitoring data. Therefore, there is an urgent need for an earth pressure cell embedding device and method with accurate measurement data and convenient embedding to solve the above problems.
发明内容Contents of the invention
本发明要解决的技术问题是为填方工程提供一种结构简单、易于连接和埋设并且可以为土压力盒底面提供固定端,从而保证其位置精度的土压力盒装置及方法。The technical problem to be solved by the present invention is to provide an earth pressure cell device and method with a simple structure, easy to connect and embed, and provide a fixed end for the bottom surface of the earth pressure cell for filling engineering, thereby ensuring its position accuracy.
为解决上述技术问题,本装置所采取的技术方案是:一种用于填方工程的土压力盒埋设装置,其关键技术在于:其包括至少两根连接杆、用于承托土压力盒并调整其位置的置盒盘、用于连接两相邻连接杆的套管以及用于密封连接杆的密封盖;置盒盘设于连接杆上;In order to solve the above technical problems, the technical solution adopted by this device is: an earth pressure cell embedding device for filling engineering, the key technology of which is: it includes at least two connecting rods for supporting the earth pressure cell and A box setting tray for adjusting its position, a sleeve for connecting two adjacent connecting rods and a sealing cover for sealing the connecting rods; the box setting tray is arranged on the connecting rods;
所述连接杆为一中空螺纹杆,所述中空螺纹杆中部设有分线孔,顶端设有总线孔;The connecting rod is a hollow threaded rod, the middle part of the hollow threaded rod is provided with a branch hole, and the top is provided with a bus hole;
所述置盒盘为一矩形盘,所述矩形盘上设有定位孔以及用于承托土压力盒的置盒区,所述矩形盘上、下方分别设有用于定位和调位土压力盒位置的定位螺母;The box setting plate is a rectangular plate, and the rectangular plate is provided with a positioning hole and a box setting area for supporting the earth pressure box, and the upper and lower sides of the rectangular plate are respectively equipped with location of the positioning nut;
所述密封盖包括位于连接杆顶端的顶盖、底端的底盖。The sealing cover includes a top cover at the top of the connecting rod and a bottom cover at the bottom.
优选的,所述中空螺纹杆、矩形盘、定位螺母和套管均为不锈钢材质。Preferably, the hollow threaded rod, the rectangular disc, the positioning nut and the sleeve are all made of stainless steel.
优选的,所述连接杆为内径45mm、壁厚5mm、螺距4.5mm的标准配件,有0.3m、0.5m和1.0m三种标准长度。Preferably, the connecting rod is a standard fitting with an inner diameter of 45mm, a wall thickness of 5mm, and a pitch of 4.5mm, and has three standard lengths of 0.3m, 0.5m and 1.0m.
优选的,所述分线孔长10cm~20cm,宽为1cm。Preferably, the line-dividing hole is 10cm-20cm long and 1cm wide.
优选的,所述土压力盒的导线分别通过分线孔和总线孔穿引至本装置的顶端。Preferably, the wires of the earth pressure cell are led to the top of the device through the distribution hole and the bus hole respectively.
优选的,所述套管为内螺纹不锈钢管,其高度为10cm。Preferably, the casing is an internally threaded stainless steel pipe with a height of 10 cm.
优选的,所述置盒盘上的定位孔和定位螺母与中空螺纹杆匹配;所述置盒盘上的置盒区用于放置土压力盒的盒体。Preferably, the positioning holes and positioning nuts on the cassette-setting tray are matched with the hollow threaded rods; the cassette-setting area on the cassette-setting tray is used to place the box body of the earth pressure cell.
优选的,所述土压力盒的盒体采用焊接的方式固定在置盒盘上的置盒区。Preferably, the box body of the earth pressure box is fixed to the box-setting area on the box-setting tray by welding.
优选的,所述密封盖为薄壁空心单端封闭的橡胶管,其外径与中空螺纹杆的内径相同。Preferably, the sealing cap is a thin-walled hollow rubber tube closed at one end, the outer diameter of which is the same as the inner diameter of the hollow threaded rod.
本发明土压力盒埋设方法为:Earth pressure cell embedding method of the present invention is:
1)填方工程进行时,首先取一段连接杆,用密封盖对中空螺纹杆底部进行密封,将已焊接至置盒盘置盒区的土压力盒整体通过的矩形盘上的定位孔与连接杆相连,然后用定位螺母调节至测量深度并固定好,将土压力盒上的导线通过连接杆中部分线孔从连接杆内部引出,并埋入土中;1) When the filling project is in progress, first take a section of connecting rod, seal the bottom of the hollow threaded rod with a sealing cover, and connect the positioning hole on the rectangular plate through which the earth pressure box that has been welded to the box-setting area of the box-setting area passes through. The rods are connected, and then adjusted to the measurement depth with the positioning nut and fixed, and the wires on the earth pressure box are led out from the inside of the connecting rod through some wire holes in the connecting rod, and buried in the soil;
2)该层填方完成后,用套管连接下一节连接杆,并安装下一个已焊接至置盒盘的土压力盒,随着填土高度的升高,增加连接杆并固定和埋设土压力盒,达到设计填筑高度后,将所有的土压力盒导线通过顶端连接杆顶部的总线孔引出,并安装密封盖对连接杆顶部进行密封;2) After the filling of this layer is completed, connect the next connecting rod with a sleeve, and install the next earth pressure cell that has been welded to the box-setting plate. As the filling height increases, the connecting rod is added and fixed and buried After the earth pressure box reaches the designed filling height, lead all the wires of the earth pressure box through the bus hole at the top of the top connecting rod, and install the sealing cover to seal the top of the connecting rod;
本发明的土压力盒埋设过程随填土高度增加逐步完成,要保证埋设精度需保证置盒盘用定位螺母紧密固定。The embedding process of the earth pressure cell of the present invention is completed step by step with the increase of the height of the filling. To ensure the embedding accuracy, it is necessary to ensure that the casket is tightly fixed with the positioning nut.
采用上述技术方案所产生的有益效果在于:The beneficial effects produced by adopting the above-mentioned technical scheme are:
1、本发明设置了连接杆、套管、置盒盘、以及密封盖,其中,连接杆为中空螺纹杆,有3种长度可供选择,可以通过套管组合不同长度的连接杆至设计长度;置盒盘用于承托土压力盒,可通过定位螺母调节土压力盒的测量位置;密封盖用于密封连接杆的顶端和底端,以防止施工过程的破坏。其整体结构简单,操作方便,使用效果良好,有效地保证了土压力盒埋设的精度要求。1. The present invention is provided with a connecting rod, a sleeve, a box tray, and a sealing cover, wherein the connecting rod is a hollow threaded rod with three lengths to choose from, and the connecting rods of different lengths can be combined through the sleeve to reach the designed length The box set plate is used to support the earth pressure box, and the measurement position of the earth pressure box can be adjusted through the positioning nut; the sealing cover is used to seal the top and bottom ends of the connecting rod to prevent damage during the construction process. The overall structure is simple, the operation is convenient, and the use effect is good, which effectively guarantees the accuracy requirement for the embedding of the earth pressure box.
2、本装置为土压力盒底面提供了固定端,从而防止了由于填土沉降等因素导致的土压力盒位置下移、倾斜等问题的出现,保证了上覆土压力的精确测量,减少了误差。2. This device provides a fixed end for the bottom surface of the earth pressure box, thereby preventing the earth pressure box from moving down and tilting due to factors such as filling settlement and other factors, ensuring accurate measurement of the overlying soil pressure and reducing errors .
3、本装置连接杆采用0.3m、0.5m和1.0m三种长度标准,易于批量生产,且可适应现场填土高度的变化,有效的节约了试验时间。3. The connecting rod of this device adopts three length standards of 0.3m, 0.5m and 1.0m, which are easy to mass produce, and can adapt to the change of filling height on site, effectively saving the test time.
附图说明Description of drawings
图1为本发明的结构示意图;Fig. 1 is a structural representation of the present invention;
图2为连接杆的示意图;Fig. 2 is the schematic diagram of connecting rod;
图3为置盒盘的示意图;Fig. 3 is the schematic diagram of setting box tray;
图4为使用本装置前土压力盒的受力情况示意图;Fig. 4 is a schematic diagram of the force situation of the earth pressure cell before using the device;
图5为使用本装置后土压力盒的受力情况示意图;Fig. 5 is a schematic diagram of the force situation of the earth pressure cell after using the device;
图6是三种位置的土压力盒测试同一高度处粉土在分级堆载条件下的土压力值试验示意图;Fig. 6 is a schematic diagram of the earth pressure value test of the silt at the same height in the three positions of the earth pressure cell test under the condition of graded heaping;
图7是图6的测试结果示意图;Fig. 7 is the test result schematic diagram of Fig. 6;
其中,1、连接杆,1-1、中空螺纹杆,1-2、分线孔,1-3总线孔;2、置盒盘,2-1、矩形盘,2-2、定位孔,2-3、置盒区,2-4、定位螺母;3、套管;4-1、顶盖,4-2、底盖;5、土压力盒,5-1盒体,5-2、导线。Among them, 1. connecting rod, 1-1, hollow threaded rod, 1-2, branch line hole, 1-3 bus hole; 2, box setting plate, 2-1, rectangular plate, 2-2, positioning hole, 2 -3, box setting area, 2-4, positioning nut; 3, bushing; 4-1, top cover, 4-2, bottom cover; 5, earth pressure box, 5-1 box body, 5-2, wire .
具体实施方式detailed description
下面结合附图和具体实施方式对本发明作进一步详细的说明。The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
参见附图1-附图3,本实施例包括至少两根连接杆1、用于承托土压力盒5并调整其位置的置盒盘2、用于连接两相邻连接杆1的套管3以及用于密封连接杆1的密封盖;置盒盘2设于连接杆1上;所述套管3为内螺纹不锈钢管,用于组合连接不同长度的连接杆1,其高度为10cm。Referring to accompanying drawings 1 to 3, this embodiment includes at least two connecting rods 1, a box setting plate 2 for supporting the earth pressure cell 5 and adjusting its position, and a sleeve for connecting two adjacent connecting rods 1 3 and a sealing cover for sealing the connecting rod 1; the box tray 2 is located on the connecting rod 1; the sleeve 3 is an internally threaded stainless steel tube, which is used to connect connecting rods 1 of different lengths in combination, and its height is 10cm.
所述连接杆1为一中空螺纹杆1-1,所述中空螺纹杆1-1中部设有分线孔1-2,中空螺纹杆1-1杆身的顶部设有总线孔1-3。The connecting rod 1 is a hollow threaded rod 1-1, and the middle part of the hollow threaded rod 1-1 is provided with a branching hole 1-2, and the top of the shaft of the hollow threaded rod 1-1 is provided with a bus hole 1-3.
所述置盒盘2为一矩形盘2-1,所述矩形盘2-1上设有定位孔2-2以及用于承托土压力盒5的置盒区2-3,所述矩形盘2-1上、下方分别设有用于定位和调位土压力盒5位置的定位螺母2-4;The box-setting disk 2 is a rectangular disk 2-1, and the rectangular disk 2-1 is provided with a positioning hole 2-2 and a box-setting area 2-3 for supporting the earth pressure box 5. 2-1 There are positioning nuts 2-4 for positioning and adjusting the position of the earth pressure box 5 on the upper and lower parts respectively;
所述密封盖包括位于连接杆1顶端的顶盖4-1、底端的底盖4-2。所述密封盖为薄壁空心单端封闭的橡胶管,其外径与连接杆1的内径相同。The sealing cover includes a top cover 4-1 at the top of the connecting rod 1 and a bottom cover 4-2 at the bottom. The sealing cover is a thin-walled hollow rubber tube closed at one end, and its outer diameter is the same as the inner diameter of the connecting rod 1 .
所述置盒盘2上的定位孔2-2和定位螺母2-4与中空螺纹杆1-1匹配,用于固定置盒盘2并调整位置。所述置盒盘2上的置盒区2-3用于放置土压力盒5的盒体5-1。所述土压力盒5的盒体5-1采用焊接的方式固定在置盒盘2上的置盒区2-3。The positioning hole 2-2 and the positioning nut 2-4 on the cassette setting tray 2 are matched with the hollow threaded rod 1-1, and are used to fix the cassette positioning tray 2 and adjust the position. The box-setting area 2-3 on the box-setting tray 2 is used for placing the box body 5-1 of the earth pressure box 5. The box body 5-1 of the earth pressure box 5 is fixed on the box-setting area 2-3 on the box-setting tray 2 by welding.
参见附图4和附图5,传统土压力传感器的工作原理是以牛顿第三定律为理论依据,即土压力传感器反应的是土压力的反作用力。目前土压力传感器的埋设方法是直接将土压力传感器放置于土层中,当上部土压力发生变化产生土压力N,上部土层土压力作用于土压力传感器上,土压力传感器同时将应力传递给其下部土层,导致下部土层沉降,其作用力为F,那么土压力盒所反映的反作用力N`为N`=N-F,即土压力传感器反应的土压力要小于实际土压力,原理如图4所示。因此,我们将土压力传感器一端固定,使得土压力传感器完全反应出上部土压力N的变化,即N=N`,原理如图5所示。Referring to accompanying drawings 4 and 5, the working principle of the traditional earth pressure sensor is based on Newton's third law, that is, the earth pressure sensor responds to the reaction force of the earth pressure. At present, the method of embedding the earth pressure sensor is to place the earth pressure sensor directly in the soil layer. When the upper earth pressure changes, the earth pressure N is generated, and the earth pressure of the upper soil layer acts on the earth pressure sensor, and the earth pressure sensor transmits the stress to the The lower soil layer causes the lower soil layer to settle, and its action force is F, then the reaction force N` reflected by the earth pressure box is N`=N-F, that is, the earth pressure reflected by the earth pressure sensor is smaller than the actual earth pressure, the principle is as follows Figure 4 shows. Therefore, we fix one end of the earth pressure sensor so that the earth pressure sensor can fully reflect the change of the upper earth pressure N, that is, N=N`, the principle is shown in Figure 5.
实施例1Example 1
新建路基土压力盒埋设装置土压力盒埋设方法过程为:The earth pressure box embedding method process of the newly built subgrade earth pressure box embedding device is as follows:
填方工程进行时,首先取一段连接杆1,用密封盖4-2对中空螺纹杆1-1底部进行密封,将封闭好的连接杆1埋入土中一定深度后,将已焊接至置盒盘2置盒区2-3的土压力盒5整体通过矩形盘2-1上的定位孔2-2与连接杆1相连,然后用定位螺母2-4调节至测量深度固定好,将土压力盒5上的导线通过连接杆1中部分线孔1-2从连接杆1内部引出,该层填方完成后,用套管3连接下一节连接杆1,并安装下一个已焊接至置盒盘2的土压力盒5,随着填土高度的升高,增加连接杆1并固定和埋设土压力盒5,达到设计填筑高度后,将所有的土压力盒导线5-2通过顶端连接杆顶部的总线孔1-3引出,并安装顶盖4-1对连接杆1顶部进行密封。When the filling project is carried out, first take a section of connecting rod 1, seal the bottom of the hollow threaded rod 1-1 with a sealing cover 4-2, bury the sealed connecting rod 1 in the soil to a certain depth, and weld it to the box. The earth pressure box 5 in the box setting area 2-3 of the disk 2 is connected with the connecting rod 1 through the positioning hole 2-2 on the rectangular disk 2-1 as a whole, and then adjusted to the measurement depth with the positioning nut 2-4 and fixed, and the earth pressure The wires on the box 5 are drawn from the inside of the connecting rod 1 through the part of the wire hole 1-2 in the connecting rod 1. After the filling of this layer is completed, connect the next connecting rod 1 with the sleeve 3, and install the next one that has been welded to the place. For the earth pressure box 5 of the box plate 2, as the fill height increases, add the connecting rod 1 and fix and bury the earth pressure box 5. After reaching the designed filling height, pass all the earth pressure box wires 5-2 through the top The bus hole 1-3 at the top of the connecting rod is drawn out, and the top cover 4-1 is installed to seal the top of the connecting rod 1.
为了验证整个测试装置的可行性,进行了室内试验模拟,如图6所示,试验采用三种位置的土压力盒测试同一高度处粉土在分级堆载条件下的土压力值。其中,土压力盒A直接埋设于土中,土压力盒B采用本装置埋设,土压力盒C置于支撑台座上(用于验证本装置的可行性),试验结果见图7,通过图7可知,通过本装置测量的准确性更高。In order to verify the feasibility of the whole test device, an indoor test simulation was carried out, as shown in Figure 6, the test used three positions of the earth pressure cell to test the earth pressure value of the silt at the same height under the condition of graded stacking. Among them, the earth pressure cell A is directly buried in the soil, the earth pressure cell B is buried by this device, and the earth pressure cell C is placed on the supporting platform (for verifying the feasibility of this device). The test results are shown in Fig. 7. It can be seen that the accuracy of measurement by this device is higher.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610640739.8A CN106052916B (en) | 2016-08-08 | 2016-08-08 | Soil pressure box burying device and method for filling engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610640739.8A CN106052916B (en) | 2016-08-08 | 2016-08-08 | Soil pressure box burying device and method for filling engineering |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106052916A true CN106052916A (en) | 2016-10-26 |
CN106052916B CN106052916B (en) | 2022-06-24 |
Family
ID=57480140
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610640739.8A Active CN106052916B (en) | 2016-08-08 | 2016-08-08 | Soil pressure box burying device and method for filling engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106052916B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106768499A (en) * | 2016-11-16 | 2017-05-31 | 中北大学 | Fluid pressure type soil pressure sensor |
CN107574808A (en) * | 2017-10-30 | 2018-01-12 | 上海市城市建设设计研究总院(集团)有限公司 | Soil pressure sensor embedded device and its method for embedding |
CN107761786A (en) * | 2017-10-16 | 2018-03-06 | 浙江煤炭测绘院有限公司 | A kind of mounting process for deep embeded type soil pressure cell |
CN107816039A (en) * | 2017-10-31 | 2018-03-20 | 西南石油大学 | Soil pressure cell fixing device and application method after a kind of bored concrete pile |
CN107859019A (en) * | 2017-12-26 | 2018-03-30 | 天津城建大学 | The complete application apparatus of three-dimensional soil pressure cell and its implementation |
CN108760096A (en) * | 2018-06-11 | 2018-11-06 | 浙江工业大学 | A threaded seal |
CN110579586A (en) * | 2019-10-16 | 2019-12-17 | 长安大学 | Experimental apparatus and method for water-air two-phase flow migration in unsaturated soil under loading and unloading disturbance |
CN115387411A (en) * | 2022-09-30 | 2022-11-25 | 吉林建筑大学 | A spliceable embedding device suitable for fixing earth pressure cells |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201267533Y (en) * | 2008-09-17 | 2009-07-08 | 姚延丽 | Mobile three-dimensional operation area device for anaesthesia |
CN101487249A (en) * | 2008-12-30 | 2009-07-22 | 中国科学院武汉岩土力学研究所 | Embedding apparatus and method for earth pressure box |
CN201721171U (en) * | 2010-05-28 | 2011-01-26 | 湖州市善琏含山湖笔厂 | Three-section brush pen |
CN103115339A (en) * | 2011-11-16 | 2013-05-22 | 王凤华 | Telescopic lamp pole |
CN203310562U (en) * | 2013-06-27 | 2013-11-27 | 南京工业大学 | Device for directly measuring lateral pressure of concrete |
CN103528718A (en) * | 2013-10-21 | 2014-01-22 | 武汉大学 | Soft rock multi-measuring-point ground stress testing method by using connecting rod |
CN104060598A (en) * | 2014-06-27 | 2014-09-24 | 西南交通大学 | Fixing device of vertically arranged soil pressure cell |
CN204690723U (en) * | 2015-03-23 | 2015-10-07 | 山西省交通科学研究院 | A kind of earth pressure cell side direction fastening devices |
CN204855242U (en) * | 2015-06-16 | 2015-12-09 | 兰州交通大学 | Bury fixing device of soil pressure cell underground |
CN105222947A (en) * | 2015-10-16 | 2016-01-06 | 中国海洋大学 | Spliced type sea bed with range protective device surpasses hole pressure and measures feeler lever |
CN105319123A (en) * | 2015-03-16 | 2016-02-10 | 河南工业大学 | A multifunctional model test pile |
CN105586865A (en) * | 2016-03-09 | 2016-05-18 | 湖北省电力勘测设计院 | Earth pressure cell drilling embedding method and device |
CN205301066U (en) * | 2016-01-15 | 2016-06-08 | 中国科学院武汉岩土力学研究所 | Multi -functional model stake |
CN105784218A (en) * | 2016-04-28 | 2016-07-20 | 山西海源阳光科技有限公司 | Mining anchor pole dynamometer |
CN205909958U (en) * | 2016-08-08 | 2017-01-25 | 石家庄铁道大学 | A soil pressure cell buries device underground for filling engineering |
-
2016
- 2016-08-08 CN CN201610640739.8A patent/CN106052916B/en active Active
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201267533Y (en) * | 2008-09-17 | 2009-07-08 | 姚延丽 | Mobile three-dimensional operation area device for anaesthesia |
CN101487249A (en) * | 2008-12-30 | 2009-07-22 | 中国科学院武汉岩土力学研究所 | Embedding apparatus and method for earth pressure box |
CN201721171U (en) * | 2010-05-28 | 2011-01-26 | 湖州市善琏含山湖笔厂 | Three-section brush pen |
CN103115339A (en) * | 2011-11-16 | 2013-05-22 | 王凤华 | Telescopic lamp pole |
CN203310562U (en) * | 2013-06-27 | 2013-11-27 | 南京工业大学 | Device for directly measuring lateral pressure of concrete |
CN103528718A (en) * | 2013-10-21 | 2014-01-22 | 武汉大学 | Soft rock multi-measuring-point ground stress testing method by using connecting rod |
CN104060598A (en) * | 2014-06-27 | 2014-09-24 | 西南交通大学 | Fixing device of vertically arranged soil pressure cell |
CN105319123A (en) * | 2015-03-16 | 2016-02-10 | 河南工业大学 | A multifunctional model test pile |
CN204690723U (en) * | 2015-03-23 | 2015-10-07 | 山西省交通科学研究院 | A kind of earth pressure cell side direction fastening devices |
CN204855242U (en) * | 2015-06-16 | 2015-12-09 | 兰州交通大学 | Bury fixing device of soil pressure cell underground |
CN105222947A (en) * | 2015-10-16 | 2016-01-06 | 中国海洋大学 | Spliced type sea bed with range protective device surpasses hole pressure and measures feeler lever |
CN205301066U (en) * | 2016-01-15 | 2016-06-08 | 中国科学院武汉岩土力学研究所 | Multi -functional model stake |
CN105586865A (en) * | 2016-03-09 | 2016-05-18 | 湖北省电力勘测设计院 | Earth pressure cell drilling embedding method and device |
CN105784218A (en) * | 2016-04-28 | 2016-07-20 | 山西海源阳光科技有限公司 | Mining anchor pole dynamometer |
CN205909958U (en) * | 2016-08-08 | 2017-01-25 | 石家庄铁道大学 | A soil pressure cell buries device underground for filling engineering |
Non-Patent Citations (1)
Title |
---|
李彦坤等: "不同埋设状态下土压力盒砂标试验研究", 《岩土工程界》 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106768499A (en) * | 2016-11-16 | 2017-05-31 | 中北大学 | Fluid pressure type soil pressure sensor |
CN106768499B (en) * | 2016-11-16 | 2023-08-08 | 中北大学 | Hydraulic soil pressure sensor |
CN107761786A (en) * | 2017-10-16 | 2018-03-06 | 浙江煤炭测绘院有限公司 | A kind of mounting process for deep embeded type soil pressure cell |
CN107574808A (en) * | 2017-10-30 | 2018-01-12 | 上海市城市建设设计研究总院(集团)有限公司 | Soil pressure sensor embedded device and its method for embedding |
CN107816039A (en) * | 2017-10-31 | 2018-03-20 | 西南石油大学 | Soil pressure cell fixing device and application method after a kind of bored concrete pile |
CN107859019A (en) * | 2017-12-26 | 2018-03-30 | 天津城建大学 | The complete application apparatus of three-dimensional soil pressure cell and its implementation |
CN107859019B (en) * | 2017-12-26 | 2023-09-22 | 天津城建大学 | Three-dimensional soil pressure box complete application device and implementation method thereof |
CN108760096A (en) * | 2018-06-11 | 2018-11-06 | 浙江工业大学 | A threaded seal |
CN110579586A (en) * | 2019-10-16 | 2019-12-17 | 长安大学 | Experimental apparatus and method for water-air two-phase flow migration in unsaturated soil under loading and unloading disturbance |
CN115387411A (en) * | 2022-09-30 | 2022-11-25 | 吉林建筑大学 | A spliceable embedding device suitable for fixing earth pressure cells |
Also Published As
Publication number | Publication date |
---|---|
CN106052916B (en) | 2022-06-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106052916A (en) | Earth pressure box burying device and method for fill engineering | |
CN103996348B (en) | The cross-over tunnel construction indoor model test device on operation tunnel impact up and down | |
CN104569341B (en) | The method of vacuum pre-pressed joint electric osmose test | |
CN102720476B (en) | O-shaped well physical simulation experiment device | |
CN102435541A (en) | Time domain reflection technology-based moisture transport measuring device | |
CN107860528B (en) | Block detection method and device for isolation membrane leakage in landfill | |
CN108643247B (en) | Testing device and testing method for soil body reinforcement model at bottom of rectangular foundation pit in soft soil area | |
CN107060814B (en) | A kind of prefabricated shield duct piece earth pressure gauge method for embedding | |
CN105862652A (en) | Physical model test device for studying piping failure process and test method | |
CN105258669B (en) | Rain pipe sedimentation post processing simulation test device and method in a kind of sea silt soil | |
CN106771076B (en) | High-speed railway ballastless track roadbed slurry dumping mud pumping test system and test method thereof | |
CN110700794A (en) | A Physical Simulation Experiment System for Multilateral Horizontal Well Coal Seam Gas Drainage | |
CN205909958U (en) | A soil pressure cell buries device underground for filling engineering | |
CN104947645A (en) | Outer side wall earth pressure cell precession type embedding device and embedding method | |
CN202974148U (en) | Tool for detecting burial depth of chuck of chassis of power transmission pole | |
CN104697496B (en) | Split type static hydraulic pressure difference settlement monitoring system and installation method thereof | |
CN206722845U (en) | A kind of prefabricated shield duct piece earth pressure gauge embedding device | |
CN204461411U (en) | The little settlement measuring device of a kind of simple liquid ground | |
CN107179391A (en) | A kind of experimental rig that Under-cross tunnel shallow layer grouting is buried for an ultra shallow | |
CN106013267B (en) | A kind of vertical anti-pulling concrete model stake and its method of construction and application | |
CN111255439B (en) | Self-heating optical fiber device and method for judging sealing quality of clay ball on side wall of pressure reduction well | |
CN104215425B (en) | A kind of re-fill method of packed type karst passage system | |
CN106324222A (en) | Model testing device for simulating underground tunnel construction and use method of model testing device | |
CN103105308B (en) | In-situ test method for cross-fault buried pipeline | |
CN106053762A (en) | Lakeside embankment seepage and deformation characteristics testing apparatus and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |