CN106014390A - Hydraulic pressure-induced plug drilling and water pressure test method - Google Patents

Hydraulic pressure-induced plug drilling and water pressure test method Download PDF

Info

Publication number
CN106014390A
CN106014390A CN201610485424.0A CN201610485424A CN106014390A CN 106014390 A CN106014390 A CN 106014390A CN 201610485424 A CN201610485424 A CN 201610485424A CN 106014390 A CN106014390 A CN 106014390A
Authority
CN
China
Prior art keywords
pressure
test
water
probe
ejector pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610485424.0A
Other languages
Chinese (zh)
Other versions
CN106014390B (en
Inventor
王波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201610485424.0A priority Critical patent/CN106014390B/en
Publication of CN106014390A publication Critical patent/CN106014390A/en
Application granted granted Critical
Publication of CN106014390B publication Critical patent/CN106014390B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/10Locating fluid leaks, intrusions or movements
    • E21B47/117Detecting leaks, e.g. from tubing, by pressure testing

Landscapes

  • Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Geophysics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention provides a hydraulic pressure-induced plug drilling water pressure test method, which comprises the following steps: firstly, pore forming; secondly, mounting; placing; fourthly, causing the blockage; fifthly, injecting water; sixthly, a water pressing test; seventhly, closing and relieving pressure; and (8) completing the test. The invention improves the detection work efficiency, and the invention continuously tests one hole at a time after completing the drilling of one hole, and the test time of each hole section is less than 1 hour; the survey precision is improved, the plugging pressure is sufficient, the pressure maintaining effect is good, and the testing precision is 2 times higher than that of a water-pressing test of a drilling machine; the hole clamping accident rate is low, the whole probe only adopts one set of water pipe without oil pipe, the number of accessories of the probe is small, the field operation is convenient, and the hole clamping accident is reduced.

Description

A kind of hydraulic pressure causes plug water pressure test in borehole method
Technical field
The present invention relates to a kind of hydraulic pressure and cause plug water pressure test in borehole method, belong to engineering construction detection Technical field.
Background technology
Water pressure test in borehole is geological prospecting and the conventional method of underground engineering construction detection, work Method is the most artificially to install two stoppers in certain depth segment of holing, and then carries out height to therebetween Pressure injection water, after reaching pressure balance, injects flow, pressure and voltage stabling control at ground table record, Finally these record data are substituted into corresponding water pressure test in borehole computing formula, calculate test The leak factor of section.
Water-pressurizing test method mainly divides multiple because causing plug mode difference, conventional fields water injection examination Test probe and be split into one with rig, have single plug and double stifled first two, be all installation on drilling rod Blocking, by the cavity in drilling rod to plug intracavity water filling, this method is typically in drilling construction mistake Journey is carried out, owing to interrupt construction, carries out substantial amounts of drilling rod dismounting and installation, waste time and energy; Simultaneously as between drilling rod, sealing is poor, chock plug sealing is poor, test accuracy is low.
The double plugs having use oil pressure mode to cause plug, cause plug owing to employing oil pressure, and system is many A set of hydraulic oil pipe, substantial amounts of oil pipe brings much inconvenience to on-the-spot test, operating efficiency is low, Hole clipping accident easily occurs.
Summary of the invention
For solving above-mentioned technical problem, the invention provides a kind of hydraulic pressure and cause plug water pressure test in borehole Method, this hydraulic pressure causes plug water pressure test in borehole method and uses double plug hydraulic pressure to cause plug mode, can have Effect improves detection work efficiency.
The present invention is achieved by the following technical programs.
A kind of hydraulic pressure that the present invention provides causes plug water pressure test in borehole method, comprises the steps:
1. pore-creating: complete the probing pore-creating in a hole;
2. install: successively by connecting with spring end between lower push rod and upper ejector pin, connect column sleeve It is contained in outside spring, and seals at the end O RunddichtringO connecting post, lower push rod and upper ejector pin In exposing the part suit watertight rubber ball connected outside post, the end cover dress top cap of upper ejector pin, pressure Water test instrument pipeline connects aqueduct, thus lower push rod, upper ejector pin, spring, connection post, only The mounted probe of the whole composition of water ball, top cap;
3. place: by mounted probe placement anticipated degree of depth in probing pore-creating, connect probe Power control line, make the three-way electrovalve in probe be energized;
4. plug is caused: control three-way electrovalve for causing plug-like state;
5. water filling: open packer permeability test instrument and water pump, carries out high pressure water injection, reaches the pressure of regulation After force value, keep high pressure water injection state, control three-way electrovalve simultaneously and switch to setting-out state;
6. packer permeability test: carry out packer permeability test, until having tested;
7. closing pressure release: close packer permeability test instrument and water pump, control three-way electrovalve switches to lets out Pressure condition;
8. test is completed: repeat step 3. to 7., when repeating, make depth of probe relative to front every time The deepest 4~10 meters, until completing the Sectional Test of whole probing pore-creating.
Described three-way electrovalve is threeway mutual-locking electric-controlled valve.
Described connection column sleeve is contained in outside spring, is specially connection post and lower push rod internal and external threads connects Connect, upper ejector pin and connection post internal and external threads connect.
The beneficial effects of the present invention is: 1. improving detection work efficiency, the present invention is to complete Disposably being carried out continuously the test in a hole after the probing in one hole, each hole section testing time is little In 1 hour;2. improving exploration precision, cause plug pressure foot, pressurize is effective, and measuring accuracy is relatively Rig packer permeability test is high 2 times;3. hole clipping accident rate is low, whole probe only with a set of water pipe, Not having oil pipe, probe appurtenance is few, it is simple to execute-in-place, reduces hole clipping accident.
Accompanying drawing explanation
Fig. 1 is the schematic flow sheet of the present invention;
Fig. 2 is the structural representation installed in Fig. 1;
Fig. 3 is the internal structure schematic diagram of upper ejector pin part in Fig. 2;
In figure: 1-top cap, 2-upper ejector pin, the 21-body of rod, 22-rubber bulb supporting plate, 23-tri-is energized Sub-valve, 24-aqueduct, 25-outlet, 3-connects post, 4-lower push rod, 5-spring, 6-sealing Ball.
Detailed description of the invention
Technical scheme is described further below, but claimed scope is not limited to In described.
A kind of hydraulic pressure as shown in Figure 1 causes plug water pressure test in borehole method, comprises the steps:
1. pore-creating: complete the probing pore-creating in a hole;
2. install: will connect with spring 5 end between lower push rod 4 and upper ejector pin 2 the most successively Connect, connect post 3 and be sleeved on outside spring 5, and seal at the end O RunddichtringO connecting post 3, Lower push rod 4 and upper ejector pin 2 are in exposing the part suit watertight rubber ball 6 connected outside post 3, upper ejector pin 2 end cover dress top cap 1, packer permeability test instrument pipeline connect aqueduct 24, thus lower push rod 4, Upper ejector pin 2, spring 5, connection post 3, watertight rubber ball 6, the whole composition of top cap 1 are mounted Probe;
3. place: by mounted probe placement anticipated degree of depth in probing pore-creating, connect probe Power control line, make the three-way electrovalve 23 in probe be energized;
4. plug is caused: control three-way electrovalve 23 for causing plug-like state;
5. water filling: open packer permeability test instrument and water pump, carries out high pressure water injection, and current are from aqueduct 24 enter, and strengthen the intrinsic pressure of probe, due to rubber bulb supporting plate 22 and sealing in entering the body of rod 21 It is mobile that the effect of ball 6, upper ejector pin 2 and lower push rod 4 will not produce excess because of intrinsic pressure increase, After reaching the force value of regulation, keep high pressure water injection state, control three-way electrovalve 23 simultaneously Switch to setting-out state, make current flow out in boring from outlet 25;
6. packer permeability test: carry out packer permeability test, until having tested;
7. close pressure release: close packer permeability test instrument and water pump, control three-way electrovalve 23 and switch to Pressure release state, makes current be discharged by aqueduct 24;
8. test is completed: repeat step 3. to 7., when repeating, make depth of probe relative to front every time The deepest 4~10 meters, until completing the Sectional Test of whole probing pore-creating.
As it is shown on figure 3, described three-way electrovalve 23 is threeway mutual-locking electric-controlled valve.
Described connection post 3 is sleeved on outside spring 5, is specially and connects post 3 and lower push rod 4 internal and external threads Connection, upper ejector pin 2 and connection post 3 internal and external threads connect.

Claims (3)

1. a hydraulic pressure causes plug water pressure test in borehole method, it is characterised in that: include walking as follows Rapid:
1. pore-creating: complete the probing pore-creating in a hole;
2. install: will hold with spring (5) between lower push rod (4) and upper ejector pin (2) successively Portion connects, and connects post (3) and is sleeved on spring (5) outward, and is connecting the end of post (3) Sealing with O RunddichtringO, lower push rod (4) and upper ejector pin (2) are in exposing connection post (3) Outer part suit watertight rubber ball (6), end cover dress top cap (1) of upper ejector pin (2), Packer permeability test instrument pipeline connect aqueduct (24), thus lower push rod (4), upper ejector pin (2), Spring (5), connection post (3), watertight rubber ball (6), the whole composition of top cap (1) are installed Good probe;
3. place: by mounted probe placement anticipated degree of depth in probing pore-creating, connect probe Power control line, make the three-way electrovalve (23) in probe be energized;
4. plug is caused: control three-way electrovalve (23) for causing plug-like state;
5. water filling: open packer permeability test instrument and water pump, carries out high pressure water injection, reaches the pressure of regulation After force value, keep high pressure water injection state, control three-way electrovalve (23) simultaneously and switch to setting-out State;
6. packer permeability test: carry out packer permeability test, until having tested;
7. close pressure release: close packer permeability test instrument and water pump, control three-way electrovalve (23) and cut It is changed to pressure release state;
8. test is completed: repeat step 3. to 7., when repeating, make depth of probe relative to front every time The deepest 4~10 meters, until completing the Sectional Test of whole probing pore-creating.
2. hydraulic pressure as claimed in claim 1 causes plug water pressure test in borehole method, it is characterised in that: Described three-way electrovalve (23) is threeway mutual-locking electric-controlled valve.
3. hydraulic pressure as claimed in claim 1 causes plug water pressure test in borehole method, it is characterised in that: Described connection post (3) is sleeved on spring (5) outward, specially connects post (3) and lower push rod (4) internal and external threads connection, upper ejector pin (2) and connection post (3) internal and external threads connect.
CN201610485424.0A 2016-06-28 2016-06-28 Hydraulic pressure-induced plug drilling and water pressure test method Active CN106014390B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610485424.0A CN106014390B (en) 2016-06-28 2016-06-28 Hydraulic pressure-induced plug drilling and water pressure test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610485424.0A CN106014390B (en) 2016-06-28 2016-06-28 Hydraulic pressure-induced plug drilling and water pressure test method

Publications (2)

Publication Number Publication Date
CN106014390A true CN106014390A (en) 2016-10-12
CN106014390B CN106014390B (en) 2019-03-05

Family

ID=57083950

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610485424.0A Active CN106014390B (en) 2016-06-28 2016-06-28 Hydraulic pressure-induced plug drilling and water pressure test method

Country Status (1)

Country Link
CN (1) CN106014390B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110018103A (en) * 2019-04-25 2019-07-16 江西理工大学 A kind of building lot field seepage test device and its test method
CN115876402A (en) * 2021-09-30 2023-03-31 中国石油化工股份有限公司 Vertical pressure testing device and method for underwater releasing rubber plug

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201671622U (en) * 2010-05-07 2010-12-15 西安科技大学 Coal mine overlying strata water-conducting crack belt upward hole observer
CN201965246U (en) * 2011-03-17 2011-09-07 黄河勘测规划设计有限公司 Special hydraulic water test plug for rope coring drilling without hoisting
CN202039837U (en) * 2011-04-07 2011-11-16 中国水电顾问集团华东勘测设计研究院 Device for water pressure test in wire line coring borehole under condition of no drilling
US20120175133A1 (en) * 2011-01-10 2012-07-12 Tesco Corporation Dampered drop plug
CN103939077A (en) * 2014-05-04 2014-07-23 山东科技大学 Perforation and fracturing method for high-stress and low-porosity coal seams
CN105003224A (en) * 2015-07-23 2015-10-28 江苏中煤矿山设备有限公司 Two-section type hole packer and core drilling process of two-section type hole packer
CN105675470A (en) * 2016-03-01 2016-06-15 长江岩土工程总公司(武汉) Method for performing pump-in test by adopting sliding hydraulic rubber plug water plugging device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201671622U (en) * 2010-05-07 2010-12-15 西安科技大学 Coal mine overlying strata water-conducting crack belt upward hole observer
US20120175133A1 (en) * 2011-01-10 2012-07-12 Tesco Corporation Dampered drop plug
CN201965246U (en) * 2011-03-17 2011-09-07 黄河勘测规划设计有限公司 Special hydraulic water test plug for rope coring drilling without hoisting
CN202039837U (en) * 2011-04-07 2011-11-16 中国水电顾问集团华东勘测设计研究院 Device for water pressure test in wire line coring borehole under condition of no drilling
CN103939077A (en) * 2014-05-04 2014-07-23 山东科技大学 Perforation and fracturing method for high-stress and low-porosity coal seams
CN105003224A (en) * 2015-07-23 2015-10-28 江苏中煤矿山设备有限公司 Two-section type hole packer and core drilling process of two-section type hole packer
CN105675470A (en) * 2016-03-01 2016-06-15 长江岩土工程总公司(武汉) Method for performing pump-in test by adopting sliding hydraulic rubber plug water plugging device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
裴熊伟: "钻孔压水试验水压式栓塞排水泄压问题研究", 《探矿工程(岩土钻掘工程)》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110018103A (en) * 2019-04-25 2019-07-16 江西理工大学 A kind of building lot field seepage test device and its test method
CN110018103B (en) * 2019-04-25 2021-08-03 江西理工大学 A kind of building foundation field penetration test device and test method thereof
CN115876402A (en) * 2021-09-30 2023-03-31 中国石油化工股份有限公司 Vertical pressure testing device and method for underwater releasing rubber plug

Also Published As

Publication number Publication date
CN106014390B (en) 2019-03-05

Similar Documents

Publication Publication Date Title
CN110984960B (en) Top pressure type layered water pumping and injecting test system and method for same-diameter drilling holes
CN111456721B (en) Multistage airbag rapid hole sealing gas pressure measuring device and measuring method
CN104265281A (en) Method for predicting well yield of sealed, unsaturated oil reservoirs through elastic driving water-flooding extraction
CN207647494U (en) A kind of twin packer layering water plug
CN206497010U (en) Geology Drilling multi-aquifer is layered bailing test device
CN109060073A (en) Single hole observes Karst Mountain bilayer level of ground water device and method
CN106525637A (en) Shale gas-content testing device and testing method
CN111622706A (en) Separation water-stopping device and method capable of transforming strong-sealing single-well double-layer hydrological monitoring well
CN204344115U (en) A kind of tubing and casing looks for the omission of examination to seal system
CN106014390A (en) Hydraulic pressure-induced plug drilling and water pressure test method
CN104018824A (en) Zonation testing method used for downhole intelligent well shutdown
CN209485935U (en) A kind of multistage gradient pressure stabilizing water pressure test in borehole device
CN104420836A (en) Horizontal Well Segmented Setting Wellhead Flow Method for Finding Water String and Its Water Finding Method
CN202228038U (en) Shallow casing leakage water injection well plugging pipe column
CN209115072U (en) A kind of water pressure test in borehole multichannel conversion quick pressure releasing device
CN208847278U (en) Single-hole observation device for double-layer groundwater level in karst mountainous area
CN215830491U (en) High-pressure airtight simulation device of underground packing system
CN207516005U (en) packer simulation test device
CN103089247B (en) Gas pressure testing device and method of coal measure strata rich in water
CN200971780Y (en) Measuring instrument for packer of water injection well
CN116577091B (en) Pressure testing device for underground testing tool of oil field
CN202937264U (en) Electronically controlled single-loop water plugging and overburden rock fracture detector
CN203022679U (en) Multi-plug hole packer for water-pressure test in drilled hole
CN111502589A (en) Packer for measuring ground stress by hydraulic fracturing method
CN201778786U (en) Hydraulic control isolation valve for downhole operations

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant