CN106013193A - Geomembrane cofferdam top structure and cofferdam heightening method - Google Patents

Geomembrane cofferdam top structure and cofferdam heightening method Download PDF

Info

Publication number
CN106013193A
CN106013193A CN201610547613.6A CN201610547613A CN106013193A CN 106013193 A CN106013193 A CN 106013193A CN 201610547613 A CN201610547613 A CN 201610547613A CN 106013193 A CN106013193 A CN 106013193A
Authority
CN
China
Prior art keywords
cofferdam
geomembrane
groove
standby
spare
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610547613.6A
Other languages
Chinese (zh)
Inventor
梁娟
雷运华
付峥
张有山
程保根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201610547613.6A priority Critical patent/CN106013193A/en
Publication of CN106013193A publication Critical patent/CN106013193A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Abstract

The invention discloses a geomembrane cofferdam top structure used for resisting over-level flood and a cofferdam heightening method in the field of hydraulic and hydroelectric engineering. The geomembrane cofferdam top structure comprises a cofferdam body and a concrete anchoring structure arranged at the top of the cofferdam body. A groove penetrating the length direction of the whole cofferdam body is formed in the top of the anchoring concrete structure. A long enough spare geomembrane is arranged in the groove. One end of the spare geomembrane is fixed in the anchoring concrete structure and stored in the groove in a folded manner. Before flood comes, the spare geomembrane can be taken out, and then seepage-proofing bodies are adopted on the two sides of the spare geomembrane for fast heightening and pressing. Due to the fact that one end of the spare geomembrane is fixed in the original anchoring concrete structure, the seepage-proofing bodies and the spare geomembrane are fixed well after heightening. The geomembrane cofferdam top structure has the same seepage-proofing effect as that of an original cofferdam, and therefore the water retaining capacity of the whole cofferdam is increased, and the situation that when over-level flood happens, economic losses are caused due to the fact that the height of the cofferdam is not enough is avoided.

Description

Method is increased in geomembrane cofferdam top structure and cofferdam
Technical field
The present invention relates to Hydraulic and Hydro-Power Engineering field, particularly relate to a kind of geomembrane cofferdam top structure for resisting over-level flood and utilize this top Portion's structure increases the method in cofferdam.
Background technology
When building Hydraulic and Hydro-Power Engineering, in order to make water conservancy project permanent construction dam can be maintained at dry construction on the ground, often through using cofferdam once Blocking disconnected whole riverbed, downstream guided into by the water conservancy diversion outlet structure escape works outside allowing river by riverbed.Owing to earth rock cofferdam can make full use of local material, over the ground Base strong adaptability, construction technology is simple, so the most preferentially selecting earth rock cofferdam in Practical Project, earth rock cofferdam is fine due to water penetration, needs Carrying out Anti-seeping technology, in the seepage control measure of earth rock cofferdam, composite geo-membrane is cheap with it, and easy construction is widely used in seepage prevention of cofferdam, its Form of construction work is to be laid on by geomembrane on Yu Shui inclined-plane, cofferdam, thus blocks river, prevents river from permeating cofferdam.But it is 3 grades or mistake for rank 4 grades of earth rock cofferdams that fruit is more serious afterwards, except strengthening inherently safe detection, outside automatic Hydrological Telemetry System is set up in reservoir area, also answer incorporation engineering special Point does technology and economic analysis, and research uses to increase superelevation or arrange emergency spillway etc. resists the safety measure of over-level flood.
Summary of the invention
For the deficiencies such as seepage control measure difference after overcoming existing geomembrane cofferdam structure cannot resist over-level flood or increase cofferdam, skill to be solved by this invention Art problem is: provide one can be easy to cofferdam and quickly increase, and the perfect geomembrane cofferdam top structure of seepage control measure and increase the side in cofferdam Method.
The technical solution adopted for the present invention to solve the technical problems is: geomembrane cofferdam top structure, including weir, cofferdam body and be arranged on weir, cofferdam body The concrete anchor fixing structure at top, the top of described anchoring xoncrete structure is provided with the groove running through body length direction, weir, whole cofferdam, in described groove Being provided with the standby geomembrane of sufficient length, described standby geomembrane one end is fixed in anchoring xoncrete structure and stored collapsed is in described groove.
Further, it is provided with backfill fine sand in described groove and protects standby geomembrane for filling groove.
Further, the top open part of described groove is provided with cover plate.
The method utilizing this geomembrane cofferdam top structure to increase cofferdam, comprises the following steps, and first pulls out standby geomembrane from groove, And it is at vertical or oblique tensioned state, and then stack impervious body in the both sides of standby geomembrane, finally impervious body is carried out compacting fixing, complete In pairs cofferdam add high disposal.
The invention has the beneficial effects as follows: by the standby geomembrane of the top pre-plugged certain length at weir, cofferdam body, before flood arrives, desirable Go out standby geomembrane, then use impervious body quickly cofferdam to be increased, owing to standby geomembrane one end is fixed on original anchoring xoncrete structure In, so impervious body and geomembrane after increasing are fixed well, there is the anti-seepage effect identical with original cofferdam, thus add the gear in whole cofferdam Outlet capacity, it is to avoid cause economic loss due to cofferdam insufficient height when there is over-level flood.
Accompanying drawing explanation
Fig. 1 is present configuration schematic diagram.
Being labeled as in figure, weir, 1-cofferdam body, 2-anchors xoncrete structure, 3-groove, the standby geomembrane of 4-, and 5-backfills fine sand, 6-cover plate.
Detailed description of the invention
The present invention is further described below in conjunction with the accompanying drawings.
As it is shown in figure 1, the present invention includes weir, cofferdam body 1 and is arranged on the concrete anchor fixing structure 2 at body 1 top, weir, cofferdam, described anchoring concrete The top of structure 2 is provided with the groove 3 running through weir, whole cofferdam body 1 length direction, is provided with the standby geomembrane 4 of sufficient length in described groove 3, Described standby geomembrane 4 one end is fixed in anchoring xoncrete structure 2 and stored collapsed is in described groove 3.The geomembrane in common cofferdam is only on weir Lay on the Yu Shui inclined-plane of body, be then fixed by the anchoring concrete at upper and lower two ends, if running into dangerous situation when needing cofferdam is increased, The geomembrane at body top, weir cannot be carried out the most fixing, so good anti-seepage effect can not be accomplished, is seriously also possible to cause and increases collapsing of cofferdam. The present invention thes improvement is that, the standby geomembrane 4 of pre-plugged one section in the anchoring xoncrete structure 2 at body 1 top, weir, original cofferdam, and it is long Spend and choose according to local hydrologic regime, a certain degree of over-level flood can be resisted.
Owing to standby geomembrane 4 has certain thickness and elasticity, stored collapsed easily ejects in groove 3, it is possible to can be damaged, so Be provided with in described groove 3 backfill fine sand 5 for filling groove 3, standby geomembrane 4 is embedded in groove 3, thus to its play protection make With.
After a period of time that cofferdam constructs, owing to exposing to the sun and rain for a long time, the backfill fine sand 5 being easily caused in groove 3 hardens or by rain Water washes away loss, and fine sand can increase certain difficulty to the engineering taking out geomembrane after hardening, it is possible at the top of the groove 3 of xoncrete structure 2 Opening part arranges cover plate 6, it is possible to standby geomembrane 4 is played more preferable protective effect.
When utilizing this geomembrane cofferdam top structure that cofferdam is increased, need to carry out according to the following steps, from groove 31, first pull out standby soil Work film 4, and make standby geomembrane 4 be in vertical or oblique tensioned state, then the both sides heap at the standby geomembrane 4 of pull-out sets impervious body and presses Fasten, thus effectively improve the height in cofferdam, owing to the lower end of standby geomembrane 4 is fixed in anchoring xoncrete structure 3, so after increasing Cofferdam geomembrane stable, good seepage-proof property, and standby geomembrane 4 serves the protective effect to the impervious body after increasing the most to a certain extent, Stabilizing it property is more preferable, improves the water-retaining capacity in whole cofferdam.
Present configuration is relatively simple, but is skillfully constructed, and improves and sets up the efficiency increasing cofferdam, and prevent by the way of pre-buried standby geomembrane Ooze effective, Stability Analysis of Structures, increase the water-retaining capacity in cofferdam, it is to avoid the economic damage caused when there is over-level flood due to cofferdam insufficient height Lose.

Claims (4)

1. geomembrane cofferdam top structure, including weir, cofferdam body (1) and the concrete anchor fixing structure (2) that is arranged on body (1) top, weir, cofferdam, It is characterized in that: the top of described anchoring xoncrete structure (2) is provided with the groove (3) running through weir, whole cofferdam body (1) length direction, described groove (3) being provided with the standby geomembrane (4) of sufficient length in, described standby geomembrane (4) one end is fixed in anchoring xoncrete structure (2) and rolls over Fold and leave in described groove (3).
2. geomembrane cofferdam as claimed in claim 1 top structure, is characterized in that: is provided with backfill fine sand (5) in described groove (3) and is used for Fill groove (3) and protect standby geomembrane (4).
3. geomembrane cofferdam as claimed in claim 2 top structure, is characterized in that: the top open part of described groove (3) is provided with cover plate (6).
4. the method utilizing the geomembrane cofferdam top structure described in claim 1,2 or 3 to increase cofferdam, is characterized in that, including following Step: first pull out standby geomembrane (4) from groove (3), and be at vertical or oblique tensioned state, then in standby geomembrane (4) Both sides stack impervious body, finally impervious body is carried out compacting fixing, completes cofferdam is added high disposal.
CN201610547613.6A 2016-07-12 2016-07-12 Geomembrane cofferdam top structure and cofferdam heightening method Pending CN106013193A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610547613.6A CN106013193A (en) 2016-07-12 2016-07-12 Geomembrane cofferdam top structure and cofferdam heightening method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610547613.6A CN106013193A (en) 2016-07-12 2016-07-12 Geomembrane cofferdam top structure and cofferdam heightening method

Publications (1)

Publication Number Publication Date
CN106013193A true CN106013193A (en) 2016-10-12

Family

ID=57109323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610547613.6A Pending CN106013193A (en) 2016-07-12 2016-07-12 Geomembrane cofferdam top structure and cofferdam heightening method

Country Status (1)

Country Link
CN (1) CN106013193A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677980A (en) * 2018-07-12 2018-10-19 中国电建集团贵阳勘测设计研究院有限公司 A kind of upstream cofferdam that taking into account communication function increases method and structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1701792A1 (en) * 1990-02-09 1991-12-30 Научно-Исследовательский Институт Строительного Производства Method for building embankment with film diaphragm
CN2533155Y (en) * 2002-02-08 2003-01-29 杨学海 Plate dam type secondary dyke
RU2309219C1 (en) * 2006-03-10 2007-10-27 Общество с ограниченной ответственностью "Русская инжиниринговая компания" Earth-fill dam of frozen type
RU2377363C1 (en) * 2008-07-22 2009-12-27 Василий Петрович Ягин Soil non-homogenuous fill dam
CN102011506A (en) * 2010-11-23 2011-04-13 昆明理工大学 Flood control buoyancy device for building
CN102966072A (en) * 2012-11-14 2013-03-13 河海大学 Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN205917708U (en) * 2016-07-12 2017-02-01 中国电建集团成都勘测设计研究院有限公司 A geomembrane cofferdam top structure for resisting flood that exceeds standard

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1701792A1 (en) * 1990-02-09 1991-12-30 Научно-Исследовательский Институт Строительного Производства Method for building embankment with film diaphragm
CN2533155Y (en) * 2002-02-08 2003-01-29 杨学海 Plate dam type secondary dyke
RU2309219C1 (en) * 2006-03-10 2007-10-27 Общество с ограниченной ответственностью "Русская инжиниринговая компания" Earth-fill dam of frozen type
RU2377363C1 (en) * 2008-07-22 2009-12-27 Василий Петрович Ягин Soil non-homogenuous fill dam
CN102011506A (en) * 2010-11-23 2011-04-13 昆明理工大学 Flood control buoyancy device for building
CN102966072A (en) * 2012-11-14 2013-03-13 河海大学 Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN205917708U (en) * 2016-07-12 2017-02-01 中国电建集团成都勘测设计研究院有限公司 A geomembrane cofferdam top structure for resisting flood that exceeds standard

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
顾淦臣: "我国土石坝应用土工膜技术的新进展(续)", 《河海科技进展》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677980A (en) * 2018-07-12 2018-10-19 中国电建集团贵阳勘测设计研究院有限公司 A kind of upstream cofferdam that taking into account communication function increases method and structure
CN108677980B (en) * 2018-07-12 2023-10-31 中国电建集团贵阳勘测设计研究院有限公司 Upstream cofferdam heightening method and structure taking traffic function into consideration

Similar Documents

Publication Publication Date Title
CN205077453U (en) Dam structure that panel rock -fill dam and upstream cofferdam combine
CN103526724B (en) The anchoring leakage preventing structure that a kind of reservoir bottom geomembrane is connected with storehouse week collector drain periphery fissure
CN101761051B (en) Assembled water pocket dam body
CN102979061B (en) Oblique membrane core wall earth and rockfill dam and anti-seepage body construction method thereof
CN203429606U (en) Sediment retaining bank reconstructed from temporary cofferdam
CN204703179U (en) A kind of composite geo-membrane sloping core cofferdam
CN106368176B (en) The high dam structure being built on earth material scarcity area deeply covered layer
CN106149626A (en) A kind of automatic river levee controlled flood with flood
CN104314089A (en) Method for composite geo-membrane sloping core cofferdam
CN106013193A (en) Geomembrane cofferdam top structure and cofferdam heightening method
CN205917708U (en) A geomembrane cofferdam top structure for resisting flood that exceeds standard
CN105970882A (en) Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN103938585A (en) Arrangement structure of mixed dam composed of earth dams and gravity dam
CN203080480U (en) Upstream blanket structure of concrete face rockfill dam
CN203096696U (en) High and low composite backwater weir
CN210636421U (en) Underwater hollowing defect repairing device for navigation wall pile foundation of ship lock on gravel layer foundation
CN105256763A (en) Diking method based on bamboo raft frame structure
CN205329632U (en) Utilize geotechnique to fill provisional manger plate dykes and dams of irritating bag and construction of steelframe support system
CN103938590A (en) Tide sand protection dike
CN207452923U (en) Gather the seepage prevention of cofferdam structure of cut-pff wall and composite geo-membrane
CN104947630A (en) Over-current slag collecting weir for water conservancy and hydropower engineering and construction method thereof
CN206667186U (en) A kind of impervious watertight structure in Hydraulic and Hydro-Power Engineering
CN205894016U (en) Automatic river levee with flood flood control
CN204849791U (en) Structure of earth rock cofferdam prevention of seepage system
CN206157755U (en) Carry on anti - seepage prevention of dam foundation system of straining structure of double -deck level in deep overburden high dam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161012