CN106012986A - Solar-powered intelligent gate remote measurement and control system - Google Patents

Solar-powered intelligent gate remote measurement and control system Download PDF

Info

Publication number
CN106012986A
CN106012986A CN201610601017.1A CN201610601017A CN106012986A CN 106012986 A CN106012986 A CN 106012986A CN 201610601017 A CN201610601017 A CN 201610601017A CN 106012986 A CN106012986 A CN 106012986A
Authority
CN
China
Prior art keywords
gate
powered intelligent
intelligent gate
solar
remote measurement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610601017.1A
Other languages
Chinese (zh)
Inventor
林栋�
王明合
马保和
王飞健
门广才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LIAOCHENG KECHUANG ENERGY-SAVING EQUIPMENT Co Ltd
Original Assignee
LIAOCHENG KECHUANG ENERGY-SAVING EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIAOCHENG KECHUANG ENERGY-SAVING EQUIPMENT Co Ltd filed Critical LIAOCHENG KECHUANG ENERGY-SAVING EQUIPMENT Co Ltd
Priority to CN201610601017.1A priority Critical patent/CN106012986A/en
Publication of CN106012986A publication Critical patent/CN106012986A/en
Pending legal-status Critical Current

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20—Movable barrages; Lock or dry-dock gates
    • G—PHYSICS
    • G05—CONTROLLING; REGULATING
    • G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00—Program-control systems
    • G05B19/02—Program-control systems electric
    • G05B19/04—Program control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/05—Programmable logic controllers, e.g. simulating logic interconnections of signals according to ladder diagrams or function charts
    • G05B19/054—Input/output

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Alarm Systems (AREA)

Abstract

A solar-powered intelligent gate remote measurement and control system comprises a server. The server is connected with a PLC control cabinet through a wireless communication network, and the PLC control cabinet is connected with a water level monitoring device, a gate openness detection device, a storage battery charging circuit, a storage battery pack, an inverter circuit, a water pump motor and a gate motor. A solar panel is connected with the storage battery pack through the storage battery charging circuit, and the storage battery pack is connected with the water pump motor through the inverter circuit. The system can achieve measurement and control of a gate in the flood season, and energy conservation and high efficiency are achieved.

Description

A kind of solar powered intelligent gate remote measuring and controlling system
Technical field
The present invention relates to lock gate for flood protection detection field, particularly relate to a kind of solar powered intelligence Gate remote measuring and controlling system.
Background technology
In recent years, the serious waterlogging phenomenon that China urban causes because of heavy showers happens occasionally, Bring very big inconvenience not only to the trip of people, the most also give the lives and properties peace of the people Entirely cause grave danger.To lock gate for flood protection water level detecting, warning and management aspect, at present Also the mode that being dependent on operator on duty has work to check determines, when precipitation, video heads sometimes because of Rainwater thickens, and brings the biggest inconvenience to the work of operator on duty.Suburb flood control at present Gate is primarily present problems with: 1, a lot of lock gate for flood protection are only mounted with video frequency pick-up head and general Logical scale, is fitted without Based Intelligent Control and intelligent-induction device, therefore controls at lock gate for flood protection station Also mainly manually manage with water level detecting warning aspect;2, opening and closing of gate can only be by People is to execute-in-place, and intelligent management level is relatively low.3, field type facility is supporting more backward, has Gate in city suburbs, even river course, field, power circuit is not carried out lid, is not possessed Often power supply, does not has communication line yet.
Summary of the invention
In order to solve above-mentioned technical problem, the present invention proposes a kind of solar powered intelligent gate Remote measuring and controlling system, while realizing the observing and controlling to gate within flood season, efficient energy-saving.
To achieve these goals, the scheme that the present invention uses is:
A kind of solar powered intelligent gate remote measuring and controlling system, including server, described clothes Business device connects PLC control cabinet by cordless communication network, and described PLC control cabinet connects water respectively Level detecting apparatus, lock Measuring opening device, battery charging circuit, accumulator battery, inversion electricity Road, pump motor and floodgate motor;Solar panel is connected by battery charging circuit Accumulator battery;Described accumulator battery connects pump motor by inverter circuit.
Described cordless communication network is GPRS communication network.
Described server connects LED display.
Described server is also connected with alarm device.
Beneficial effects of the present invention has: uses and solar powered makes whole system energy-conserving and environment-protective, Employing PLC control cabinet regulating gate motor simultaneously, thus the aperture of regulating gate, carry out flood control Work.
Accompanying drawing explanation
Fig. 1 is present configuration schematic diagram.
Detailed description of the invention
In order to be better understood by technical scheme, 1 couple of present invention makees below in conjunction with the accompanying drawings Further illustrate.
A kind of solar powered intelligent gate remote measuring and controlling system, including server, described clothes Business device connects PLC control cabinet by cordless communication network, and described PLC control cabinet connects water respectively Level detecting apparatus, lock Measuring opening device, battery charging circuit, accumulator battery, inversion electricity Road, pump motor and floodgate motor;Solar panel is connected by battery charging circuit Accumulator battery;Described accumulator battery connects pump motor by inverter circuit.Server is positioned at value Class is indoor, and operator on duty can pass through monitoring server gate situation.
Described cordless communication network is GPRS communication network.
Described server connects LED display.
Described server is also connected with alarm device.
Described condensate tank of dehumidifier is ultrasonic water level gauge.
PLC monitoring battery charging circuit is accumulator charging, the electricity produced by photovoltaic cell Amount stores in accumulator battery;Simultaneously by GPRS module by detection water level, the aperture of lock, The state of photovoltaic cell and the status information of accumulator are sent to Surveillance center, and accept in monitoring The switching order of the heart, controls pump motor.
From ultrasonic emitting to again being received, its time and ultrasonic water level gauge probe are to tested The distance of object is directly proportional.Electronic unit detects this time, and calculates according to known velocimeter Tested distance.Water surface place value just can be drawn by subtraction.Owing to temperature has shadow to the velocity of sound Ringing, so being provided with temperature sensor in ultrasonic water level gauge probe end, being used for measuring temperature, To revise the velocity of sound.
The waterlevel data of acquisition is transferred to server by cordless communication network, server sets Have water level detecting dedicated system software, it is capable of storing waterlevel data, analyze and Display, thus reach the automatic detection to water level.
Systems soft ware is responsible for by the personnel with operating right, it is ensured that the safety of system Property, this system can provide the user with an information-based operating platform directly perceived, simple. System is that flood control pumping station data of monitoring point is received, collects, adds up, is analyzed, to water level Carrying out detecting early warning and flood control pumping station carrying out a platform of Based Intelligent Control, this software possesses dynamic State is monitored in real time, the inquiry of historical data, alert data, login daily record and Operation Log inquiry, The multiple functions such as period statistics, tracing analysis, user's management, measuring point management.
PLC control cabinet is the control core of system, real-time monitoring field water level, as reached pre- Alert value, then automatically open up gate, performs draining flood discharge.And on-line monitoring rechargeable solar battery Circuit, the running parameter of inverter circuit, and solaode and the state etc. of accumulator, and The information such as aperture of the water level of Site Detection, gate is uploaded to Surveillance center, accepts in monitoring The opening of open and close lock order that the heart issues and pump motor, stop order, perform to control behaviour accordingly Make.
Battery charging circuit, according to the output voltage of photovoltaic array, current situation, makes charging Circuit output voltage is consistently higher than accumulator current voltage, thus improves the charging effect of accumulator Rate.When photovoltaic cell system output voltage, electric current are abnormal or break down, cut off photovoltaic Electricity generation system, carries out error protection to it.When accumulator battery is full of, start drain charge, it is ensured that Accumulator will not cross punching, to extend the service life of accumulator.
The DC voltage inversion that accumulator is exported by inverter circuit is power frequency ac voltage, for electricity Lasting alternating voltage is provided during machine emergency.
Also including pumping plant map display system, shown by pumping plant on map, client can be directly perceived Understand position and the environment around of pumping plant, be conducive to fully understanding the situation of pumping plant, Ke Yiwei Manager provides aid decision.
User may select a certain road in city or single measuring point, and system list shows to meet and imposes a condition The detailed Real-time Monitoring Data of all measuring points.
User can arbitrarily set querying condition, to measuring point historical data, measuring point alert data and be System logs in daily record, System Operation Log information is inquired about.System collects all automatically Measuring point data, warning message and System Operation Log are stored in data base.
User can arbitrarily set timing statistics section, system can by the hour, day, the moon, ten days generate prison The period consolidated statement of measuring point and period trend curve.
Alarming threshold value setting, warning message and process, warning message triggers and manages, information is looked into Ask.When the super water level of pumping plant occurring or ANOMALOUS VARIATIONS occurring, by automatic alarm, therefore Barrier data with alert needs to upload and at local record.When field condition is critical, system passes through language Sound adds the mode active warning staff such as word, it is ensured that just can send out in time before danger occurs Existing, to realize actively hedging and the purpose of reduction harm.
Although the detailed description of the invention of the present invention is described by the above-mentioned accompanying drawing that combines, but not Limiting the scope of the invention, one of ordinary skill in the art should be understood that the present invention's On the basis of technical scheme, those skilled in the art need not pay creative work and can make Various amendments or deformation still within protection scope of the present invention.

Claims (4)

1. a solar powered intelligent gate remote measuring and controlling system, it is characterised in that bag Including server, described server connects PLC control cabinet, described PLC by cordless communication network Switch board connect respectively Level monitor, lock Measuring opening device, battery charging circuit, Accumulator battery, inverter circuit, pump motor and floodgate motor;Solar panel is by storing Battery charger connects accumulator battery;Described accumulator battery connects water pump electricity by inverter circuit Machine.
A kind of solar powered intelligent gate remote measurement and control the most according to claim 1 System, it is characterised in that described cordless communication network is GPRS communication network.
A kind of solar powered intelligent gate remote measurement and control the most according to claim 1 System, it is characterised in that described server connects LED display.
A kind of solar powered intelligent gate remote measurement and control the most according to claim 1 System, it is characterised in that described server is also connected with alarm device.
CN201610601017.1A 2016-07-27 2016-07-27 Solar-powered intelligent gate remote measurement and control system Pending CN106012986A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610601017.1A CN106012986A (en) 2016-07-27 2016-07-27 Solar-powered intelligent gate remote measurement and control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610601017.1A CN106012986A (en) 2016-07-27 2016-07-27 Solar-powered intelligent gate remote measurement and control system

Publications (1)

Publication Number Publication Date
CN106012986A true CN106012986A (en) 2016-10-12

Family

ID=57114586

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610601017.1A Pending CN106012986A (en) 2016-07-27 2016-07-27 Solar-powered intelligent gate remote measurement and control system

Country Status (1)

Country Link
CN (1) CN106012986A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638450A (en) * 2016-12-28 2017-05-10 上海市城市排水有限公司机修安装分公司 Water pump start-stop and gate opening-closing true signal interlocking apparatus and method
CN109870967A (en) * 2019-02-25 2019-06-11 北京中农精准科技有限公司 A kind of water light complementation accumulation of energy remote-control lock system
CN111499116A (en) * 2020-05-12 2020-08-07 中国市政工程西北设计研究院有限公司 A side system for sewage treatment and method of using the same
CN113391607A (en) * 2021-06-22 2021-09-14 四川华能太平驿水电有限责任公司 Hydropower station gate control method and system based on deep learning
CN113934164A (en) * 2020-07-13 2022-01-14 上海硕物天成信息科技有限公司 A solar wireless controller with opening control function
CN116627055A (en) * 2023-04-13 2023-08-22 宁夏夏禹节水科技有限公司 An integrated gate controller with strong robustness of measurement and control and its control method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090128143A (en) * 2008-06-10 2009-12-15 최국현 Conductive hydro gate drive and its driving method
KR20140002254A (en) * 2012-06-28 2014-01-08 엘에스산전 주식회사 Apparatus and method for communication processing of plc
CN203701047U (en) * 2013-12-16 2014-07-09 国家电网公司 Remote monitor system for water conservation gate
CN204270083U (en) * 2014-12-23 2015-04-15 河海大学 A gate control device
CN104635571A (en) * 2014-12-09 2015-05-20 合肥三立自动化工程有限公司 Remote gate control system and remote gate control method
CN205917966U (en) * 2016-08-28 2017-02-01 聊城巾帼包装有限公司 T for building shape scute module

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090128143A (en) * 2008-06-10 2009-12-15 최국현 Conductive hydro gate drive and its driving method
KR20140002254A (en) * 2012-06-28 2014-01-08 엘에스산전 주식회사 Apparatus and method for communication processing of plc
CN203701047U (en) * 2013-12-16 2014-07-09 国家电网公司 Remote monitor system for water conservation gate
CN104635571A (en) * 2014-12-09 2015-05-20 合肥三立自动化工程有限公司 Remote gate control system and remote gate control method
CN204270083U (en) * 2014-12-23 2015-04-15 河海大学 A gate control device
CN205917966U (en) * 2016-08-28 2017-02-01 聊城巾帼包装有限公司 T for building shape scute module

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638450A (en) * 2016-12-28 2017-05-10 上海市城市排水有限公司机修安装分公司 Water pump start-stop and gate opening-closing true signal interlocking apparatus and method
CN106638450B (en) * 2016-12-28 2019-11-01 上海市城市排水有限公司机修安装分公司 The actual signal interlock and method of water pump start and stop and shutter opening and closing
CN109870967A (en) * 2019-02-25 2019-06-11 北京中农精准科技有限公司 A kind of water light complementation accumulation of energy remote-control lock system
CN111499116A (en) * 2020-05-12 2020-08-07 中国市政工程西北设计研究院有限公司 A side system for sewage treatment and method of using the same
CN113934164A (en) * 2020-07-13 2022-01-14 上海硕物天成信息科技有限公司 A solar wireless controller with opening control function
CN113391607A (en) * 2021-06-22 2021-09-14 四川华能太平驿水电有限责任公司 Hydropower station gate control method and system based on deep learning
CN116627055A (en) * 2023-04-13 2023-08-22 宁夏夏禹节水科技有限公司 An integrated gate controller with strong robustness of measurement and control and its control method

Similar Documents

Publication Publication Date Title
CN114167291B (en) Storage battery safety operation and maintenance management system for electric power internet of things of communication site
CN104635571B (en) Gate tele-control system and its long-range control method
CN108194339B (en) Water pump intelligent control system with fault self-checking function
CN104264770B (en) A kind of power distribution room ponding is reported to the police and automatic drain system and control method thereof
CN104362969B (en) A kind of domestic solar dispatch from foreign news agency origin system
CN112053536A (en) Induction type near live safety distance early warning system and method thereof
CN106990362A (en) A kind of emergency power supply Temperature/Humidity Control System
CN209676004U (en) A kind of the wireless monitor detector and system of electric line safe operation
CN109980782A (en) A kind of the wireless monitor detector and system of electric line safe operation
CN111769643A (en) A kind of intelligent distribution equipment, distribution box and distribution monitoring system based on Internet of Things
CN209198976U (en) A kind of Internet of Things intelligence Border Gateway device that the monitoring of water supply pump house uses
CN111030216A (en) Charging pile capable of preventing electricity stealing and loss detection method of charging pile
CN103217199B (en) A kind of power-saving method of the level of ground water monitoring system for field
CN204576288U (en) A kind of cable duct water level monitoring and alarm system
CN206651133U (en) Greenhouse regulation device and system
CN206848443U (en) Wisdom battery cloud management system
CN207801580U (en) An Internet intelligent power consumption data acquisition and control system
CN207182049U (en) A kind of heat exchange station intelligent measurement and control system
CN110275475A (en) A kind of electrical cabinet fault monitoring device
CN206546968U (en) A kind of important electric elements detection distribution box in real time
CN202049573U (en) Antitheft alarm device for tower door of wind-driven generator set
CN222561721U (en) Multi-parameter fusion analysis high-voltage cabinet state online monitoring system
CN205917666U (en) Intelligent gate remote control and measurement system of solar energy power supply
CN204302788U (en) Cluster observing and controlling and intelligent networking aerator system
CN219875190U (en) 5G-based solar intelligent efficient water lifting system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161012

RJ01 Rejection of invention patent application after publication