CN105870844B - The operational method of the arc-extinction device of disconnecting operation is charged for 35kV substation equipment drainage threads - Google Patents
The operational method of the arc-extinction device of disconnecting operation is charged for 35kV substation equipment drainage threads Download PDFInfo
- Publication number
- CN105870844B CN105870844B CN201610200277.8A CN201610200277A CN105870844B CN 105870844 B CN105870844 B CN 105870844B CN 201610200277 A CN201610200277 A CN 201610200277A CN 105870844 B CN105870844 B CN 105870844B
- Authority
- CN
- China
- Prior art keywords
- arc
- conducting wire
- extinction device
- rope
- female
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/14—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for joining or terminating cables
Landscapes
- Load-Engaging Elements For Cranes (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
Description
技术领域technical field
本发明涉及变电站设备带电作业技术领域,具体涉及一种用于35kV变电站设备引流线带电断接作业的消弧装置及使用方法。The invention relates to the technical field of live operation of substation equipment, in particular to an arc suppressing device and a use method for live disconnection operation of 35kV substation equipment drainage lines.
背景技术Background technique
消弧装置是带电断接设备引流线作业时的专用工具之一,其由消弧滑车与带有一段铜导线的绝缘消弧绳组成。当对架空线路进行带电断接工作时,通常作业人员会借助绝缘软梯或绝缘斗臂车等绝缘平台以等电位方式进入到引流线附近安装消弧装置,完成此项工作后断开(或接上)引流线并远离安装地点一段距离,以确保电弧不会伤及人员。此时引流导线上的电流靠消弧绳上铜线导通,在操作消弧装置中消弧绳的2个地面工作人员的熟练配合下,其中1人快速拉动消弧绳而另1人同时放松消弧绳,依靠消弧绳上的铜线移动拉断(或接上)其所带电而产生的电弧,从而完成带电断接引流线工作。然而,当对变电站设备引流线进行带电断接工作时,上述方法已不适用。主要因为运行中的变电站设备引流线因受地面变压器、开关设备和避雷器等众多设备设施布局影响,导致绝缘斗臂车较难接近作业点,而且在挂接引流线的架空软母线导线或硬母线导线上悬挂绝缘软梯已非常困难且不安全,这时就需要作业人员根据地面设备布置方式,在构架横担上或借助如绝缘斗臂车等绝缘平台并使用相应的绝缘操作工具装拆适用于间接作业法的专用消弧装置,从而完成带电断接设备设施的引流线作业。The arc suppression device is one of the special tools for the operation of the drain line of the live disconnection equipment. It is composed of an arc suppression block and an insulated arc suppression rope with a section of copper wire. When carrying out live disconnection work on overhead lines, usually the operator will use an insulating platform such as an insulating ladder or an insulating bucket truck to enter the vicinity of the drain line to install an arc suppression device in an equipotential manner, and disconnect (or connect) after completing this work. above) drain wire and keep a certain distance away from the installation site to ensure that the arc will not hurt people. At this time, the current on the drain wire is conducted by the copper wire on the arc-suppression rope. With the skilled cooperation of the two ground workers who operate the arc-suppression rope in the arc-suppression device, one of them pulls the arc-suppression rope quickly and the other at the same time Loosen the arc-suppression rope, rely on the copper wire on the arc-suppression rope to move and break (or connect) the electric arc generated by it, so as to complete the work of disconnecting the drain wire when it is live. However, when carrying out live disconnection work on the diversion line of the substation equipment, the above method is no longer applicable. The main reason is that the running substation equipment drainage lines are affected by the layout of many equipment and facilities such as ground transformers, switchgears, and lightning arresters, which makes it difficult for the insulated bucket truck to approach the operating point, and the overhead soft bus conductors or hard busbars where the drainage lines are connected It is very difficult and unsafe to hang the insulating ladder on the wire. At this time, it is necessary for the operator to assemble and disassemble it on the cross arm of the frame or with the help of an insulating platform such as an insulating bucket truck and use corresponding insulating operating tools according to the layout of the ground equipment. The special arc suppression device of the indirect operation method can complete the operation of the drainage line of the live disconnection equipment and facilities.
发明内容Contents of the invention
本发明针对变电站设备引流线带电断接作业时安装消弧装置较为困难甚至无法完成的实际,提供一种用于35kV变电站设备引流线带电断接作业的消弧装置的作业方法。Aiming at the reality that it is difficult or even impossible to install an arc suppression device during the live disconnection operation of the diversion line of the substation equipment, the invention provides an operation method of the arc suppression device for the live disconnection operation of the diversion line of the 35kV substation equipment.
本发明提供的技术方案如下:The technical scheme provided by the invention is as follows:
用于35kV变电站设备引流线带电断接作业的消弧装置的作业方法,所述用于35kV变电站设备引流线带电断接作业的消弧装置包括通过顶端的吊环悬挂于母导线上的装置主体、固定连接于装置主体上或者与装置主体为一体式结构的用于夹紧母导线的固定夹紧板、固定连接于固定夹紧板底端的用于悬吊消弧滑车的挂耳板;在固定夹紧板上加工有贯通前后的挂孔以及从外部一侧爬升式通向挂孔的用于挂入母导线的通道,在通道入口处安装有锁销,在固定夹紧板的另一侧安装有从外部水平通向挂孔的母导线活动夹紧装置,整套消弧装置采用导电良好的金属制做;The operation method of the arc suppression device used for the live disconnection operation of the lead wire of the 35kV substation equipment, the arc suppression device used for the live disconnection operation of the lead wire of the 35kV substation equipment includes a device main body suspended on the bus conductor through the lifting ring at the top, The fixed clamping plate fixedly connected to the main body of the device or integrated with the main body of the device is used to clamp the female conductor, and the lug plate fixedly connected to the bottom end of the fixed clamping plate is used to suspend the arc-extinguishing block; The clamping plate is processed with a hanging hole through the front and rear and a channel for hanging the bus conductor from the external side to the hanging hole. A lock pin is installed at the entrance of the channel, and the other side of the fixed clamping plate There is a movable clamping device for the bus conductor leading horizontally from the outside to the hanging hole, and the whole set of arc suppression device is made of metal with good conductivity;
采用本发明消弧装置的作业方法包括断开作业和接入作业,其中,The operation method using the arc suppression device of the present invention includes disconnection operation and connection operation, wherein,
断开作业方法步骤如下:The steps to disconnect the operation method are as follows:
S0)准备好消弧装置;S0) Prepare the arc suppression device;
S1)将特制的带有由多股软铜线与绝缘绳编织的一段铜导线的绝缘消弧绳穿入消弧滑车(9)中,垂下的两端绳头分别由2个地面人员控制;S1) Put a special insulated arc-suppression rope with a section of copper wire braided by multi-strand annealed copper wire and insulating rope into the arc-suppression block (9), and the hanging rope ends at both ends are respectively controlled by two ground personnel;
S2)用绝缘操作杆将消弧装置沿通道(8)入口挑入并通过挂孔挂接在变电站设备带电引流线的母导线上;S2) Pick up the arc suppressing device along the entrance of the channel (8) with the insulating operating rod and hang it on the bus conductor of the live diversion line of the substation equipment through the hanging hole;
S3)通过绝缘操作杆端头上的工具夹持住母导线活动夹紧装置(4)的外端并转动,通过旋进母导线活动夹紧装置(4)压紧母导线;S3) Hold and rotate the outer end of the movable clamping device (4) of the female conductor through the tool on the end of the insulating operating rod, and compress the female conductor by screwing in the movable clamping device (4) of the female conductor;
S4)确认消弧装置安装牢固且消弧绳上的一段铜导线已接入消弧滑车并与之连接良好,带电作业人员利用绝缘操作工具将带电引流线与铜导线绑扎在一起,使消弧装置导通带电引流线上电流;S4) Confirm that the arc suppression device is firmly installed and that a section of copper wire on the arc suppression rope has been connected to the arc suppression tackle and is well connected with it. The device conducts the current on the live drain line;
S5)检查绝缘消弧绳上一段铜线和带电引流线均处于良好导电状态后,带电作业人员使用绝缘操作工具将带电引流线从母导线上断开;S5) After checking that the section of copper wire on the insulated arc suppression rope and the live drain wire are in a good conductive state, live workers use insulating operation tools to disconnect the live drain wire from the bus conductor;
S6)2个地面人员中的1人快速拉动绝缘消弧绳,另1人配合同时快速松开绝缘消弧绳,完成带电引流线断开作业;S6) One of the two ground personnel quickly pulls the insulating arc-suppression rope, and the other person cooperates with and simultaneously loosens the insulating arc-suppression rope to complete the disconnection operation of the live diversion line;
S7)地面人员使用绝缘操作工具拆除消弧装置后,结束带电断开引流线作业;S7) After the ground personnel use the insulating operation tool to dismantle the arc suppression device, the work of disconnecting the drain wire with power is completed;
接入作业方法步骤如下:The steps to access the operation method are as follows:
S0)准备好消弧装置;S0) Prepare the arc suppression device;
S1)将特制的绝缘消弧绳上由多股软铜线与绝缘绳编织的一段与待接入的35kV变电站设备引流线绑扎固定在一起并穿入消弧装置滑车中,垂下的两端绳头分别由2个地面人员控制;S1) Bind and fix a section of the special insulated arc-suppression rope braided by multi-strand annealed copper wire and insulating rope with the drain wire of the 35kV substation equipment to be connected, and pass it into the arc-suppression device pulley. The heads are controlled by two ground personnel respectively;
S2)带电作业人员用绝缘操作杆将消弧装置沿通道(8)挑入并通过挂孔挂接在母导线上;S2) The live working personnel use the insulating operating rod to pick the arc suppression device along the channel (8) and hang it on the bus conductor through the hanging hole;
S3)通过绝缘操作杆端头上的工具夹持住母导线活动夹紧装置(4)的外端并转动,通过旋进母导线活动夹紧装置(4)压紧母导线;S3) Hold and rotate the outer end of the movable clamping device (4) of the female conductor through the tool on the end of the insulating operating rod, and compress the female conductor by screwing in the movable clamping device (4) of the female conductor;
S4)确认消弧装置安装牢固后,2个地面人员中的1人快速拉动消弧绳,而另1人配合快速松开消弧绳,使带有软铜线的一段消弧绳快速接入带电母导线上。S4) After confirming that the arc suppression device is firmly installed, one of the two ground personnel quickly pulls the arc suppression rope, while the other cooperates with the quick release of the arc suppression rope to quickly connect a section of arc suppression rope with soft copper wire On the live bus conductor.
S5)确认绝缘消弧绳的一段铜线处于良好导电状态后,带电作业人员使用绝缘操作工具将设备引流线接入母导线上并安装牢固;之后解开设备引流线与消弧绳上铜线的绑扎连接;S5) After confirming that a section of copper wire of the insulated arc-suppression rope is in a good conductive state, live workers use insulating operation tools to connect the equipment drainage wire to the bus conductor and install it firmly; then untie the equipment drainage wire and the copper wire on the arc-suppression rope binding connection;
S6)拆除消弧装置后完成带电接入设备引流线作业。S6) After the arc suppression device is removed, the operation of the drainage line of the live connection equipment is completed.
本发明所述母导线活动夹紧装置为可向前旋进的压紧螺杆,该压紧螺杆的内端面为内凹的弧形面,外端面带有凸柄。The movable clamping device for the female conductor in the present invention is a compression screw that can be screwed forward, the inner end surface of the compression screw is a concave arc surface, and the outer end surface has a convex handle.
采用本发明消弧装置及作业方法可以实现35kV变电站设备引流线带电断接作业,本发明的消弧装置适用于间接带电作业方式,结构简单,使用方便,安全可靠。Adopting the arc suppression device and operation method of the present invention can realize the live disconnection operation of the drain line of the 35kV substation equipment. The arc suppression device of the present invention is suitable for the indirect live operation mode, and has a simple structure, is convenient to use, and is safe and reliable.
附图说明Description of drawings
图1为本发明消弧装置的结构示意图;Figure 1 is a schematic structural view of the arc suppression device of the present invention;
图2是图1的左视图。Fig. 2 is a left side view of Fig. 1 .
具体实施方式Detailed ways
如图1、图2所示的一种用于35kV变电站设备引流线带电断接作业的消弧装置,包括通过顶端的吊环1悬挂于母导线上的装置主体2、固定连接于装置主体2上或者与装置主体为一体式结构的用于夹紧母导线的固定夹紧板3、固定连接于固定夹紧板底端的用于悬吊消弧滑车9的挂耳板5;在固定夹紧板3上加工有贯通前后的挂孔7以及从外部一侧爬升式通向挂孔的用于挂入母导线的通道8,挂孔7与母导线外径匹配,通道8为进出母导线的通道。为了防止带电作业时母导线从消弧装置脱出的风险,在通道8入口处安装了由销钉或螺栓固定的锁销6,在消弧装置挂入或退出母导线时通过绝缘操作工具打开锁销,以利于母导线进出。当消弧装置挂上母导线后通过绝缘操作工具关闭入口,作为消弧装置脱出导线的后备保护措施。在固定夹紧板的另一侧安装有从外部水平通向挂孔7的母导线活动夹紧装置4,整套消弧装置采用导电良好的金属制做。所述母导线活动夹紧装置4为可向前旋进的压紧螺杆,旋进可压紧母导线,旋出可松开母导线。压紧螺杆的内端面4a为内凹的弧形面,与要压紧的母导线外形适配,以确保将母导线压紧压稳,压紧螺杆的外端面带有凸柄4b,凸柄可为Ⅰ字杆形状,也可以是正六边形结构或其它适用于带电作业用绝缘操作杆的端头形状,便于带电作业用绝缘操作杆旋紧或松开。As shown in Fig. 1 and Fig. 2, an arc suppression device used for live disconnection operation of the diversion line of 35kV substation equipment includes a device main body 2 suspended on the bus conductor through a lifting ring 1 at the top, and fixedly connected to the device main body 2 Or the fixed clamping plate 3 for clamping the female wire with an integrated structure with the main body of the device, the lug plate 5 for suspending the arc-extinguishing block 9 fixedly connected to the bottom of the fixed clamping plate; 3 is processed with a hanging hole 7 passing through the front and rear and a channel 8 for hanging the bus conductor from the outside side to the hanging hole. The hanging hole 7 matches the outer diameter of the bus conductor, and the channel 8 is the channel for entering and leaving the bus conductor . In order to prevent the risk of the bus conductor coming out of the arc suppression device during live work, a lock pin 6 fixed by a pin or bolt is installed at the entrance of the channel 8, and the lock pin is opened by an insulating operation tool when the arc suppression device is hung in or withdrawn from the bus conductor , to facilitate the entry and exit of the bus conductor. When the arc suppression device is hung on the bus conductor, the inlet is closed through the insulation operation tool, as a backup protection measure for the arc suppression device to come out of the wire. On the other side of the fixed clamping plate, a movable clamping device 4 for the bus conductor leading horizontally from the outside to the hanging hole 7 is installed, and the whole set of arc suppression device is made of metal with good conductivity. The movable clamping device 4 for the female wire is a compression screw that can be screwed forward, and the female wire can be compressed when screwed in, and the female wire can be loosened when screwed out. The inner end surface 4a of the compression screw is a concave arc surface, which is adapted to the shape of the bus conductor to be compressed, so as to ensure that the bus conductor is pressed and pressed firmly. The outer end surface of the compression screw has a convex handle 4b, and the convex handle It can be in the shape of an I-shaped rod, or it can be a regular hexagonal structure or other end shapes suitable for the insulating operating rod for live work, which is convenient for tightening or loosening the insulating operating rod for live working.
本发明的装置主体2可以制做为多种结构形式。例如,可以将装置主体制作成为一侧开放式框架结构,将固定夹紧板3安装于开放式框架中,将挂耳板5固定安装于框架底端;通道7从固定夹紧板位于装置主体开放侧的一边爬升式通向挂孔,母导线活动夹紧装置4水平穿过装置主体的封闭侧及固定夹紧板通向挂孔。还可以将装置主体制作成一个矩形块,将母导线固定夹紧板固定连接于矩形块底端,将挂耳板固定安装于固定夹紧板底端;通道7从固定夹紧板一侧爬升式通向挂孔,母导线活动夹紧装置从固定夹紧板另一侧水平穿入通向挂孔。装置主体与母导线固定夹紧板可以制作成一体,也可以制作成相互固定连接的两个部分。The device main body 2 of the present invention can be manufactured in various structural forms. For example, the main body of the device can be made into an open frame structure on one side, the fixed clamping plate 3 is installed in the open frame, and the lug plate 5 is fixedly installed on the bottom end of the frame; One side of the open side climbs and leads to the hanging hole, and the movable clamping device 4 of the female conductor passes horizontally through the closed side of the device main body and the fixed clamping plate to lead to the hanging hole. The main body of the device can also be made into a rectangular block, the fixed clamping plate of the female conductor is fixedly connected to the bottom end of the rectangular block, and the lug plate is fixedly installed on the bottom end of the fixed clamping plate; the channel 7 climbs up from the side of the fixed clamping plate lead to the hanging hole, and the movable clamping device of the female conductor penetrates horizontally from the other side of the fixed clamping plate to the hanging hole. The main body of the device and the fixed clamping plate of the female wire can be made into one body, or can be made into two parts fixedly connected with each other.
采用本发明消弧装置用于35kV变电站设备引流线带电断接作业的方法包括断开作业和接入作业,其中,断开作业方法步骤如下:The method of adopting the arc suppression device of the present invention for the live disconnection operation of the drainage line of the 35kV substation equipment includes the disconnection operation and the connection operation, wherein, the steps of the disconnection operation method are as follows:
S0)准备好消弧装置;S0) Prepare the arc suppression device;
S1)将特制的带有由多股软铜线与绝缘绳编织的一段铜导线的绝缘消弧绳穿入消弧滑车9中,垂下的两端绳头分别由2个地面人员控制;S1) Put a special insulated arc-suppression rope with a section of copper wire braided by multiple strands of annealed copper wire and an insulating rope into the arc-suppression block 9, and the hanging rope ends at both ends are respectively controlled by two ground personnel;
S2)用绝缘操作杆将消弧装置沿通道8入口挑入并通过挂孔挂接在变电站设备带电引流线的母导线上;S2) Use the insulating operating rod to pick the arc suppression device along the entrance of channel 8 and hang it on the bus conductor of the live diversion line of the substation equipment through the hanging hole;
S3)通过绝缘操作杆端头上的工具夹持住母导线活动夹紧装置4的外端并转动,通过旋进母导线活动夹紧装置4压紧母导线;S3) Hold and rotate the outer end of the movable clamping device 4 of the bus conductor through the tool on the end of the insulating operating rod, and compress the bus conductor by screwing in the movable clamping device 4 of the bus conductor;
S4)确认消弧装置安装牢固且消弧绳上的一段铜导线已接入消弧滑车并与之连接良好,带电作业人员利用绝缘操作工具将带电引流线与铜导线绑扎在一起,使消弧装置导通带电引流线上电流;S4) Confirm that the arc suppression device is firmly installed and that a section of copper wire on the arc suppression rope has been connected to the arc suppression tackle and is well connected with it. The device conducts the current on the live drain line;
S5)检查绝缘消弧绳上一段铜线和带电引流线均处于良好导电状态后,带电作业人员使用绝缘操作工具将带电引流线从母导线上断开;S5) After checking that the section of copper wire on the insulated arc suppression rope and the live drain wire are in a good conductive state, live workers use insulating operation tools to disconnect the live drain wire from the bus conductor;
S6)2个地面人员中的1人快速拉动绝缘消弧绳,另1人配合同时快速松开绝缘消弧绳,完成带电引流线断开作业;S6) One of the two ground personnel quickly pulls the insulating arc-suppression rope, and the other person cooperates with and simultaneously loosens the insulating arc-suppression rope to complete the disconnection operation of the live diversion line;
S7)地面人员使用绝缘操作工具拆除消弧装置后,结束带电断开引流线作业;S7) After the ground personnel use the insulating operation tool to dismantle the arc suppression device, the work of disconnecting the drain wire with power is completed;
接入作业方法步骤如下:The steps to access the operation method are as follows:
S0)准备好消弧装置;S0) Prepare the arc suppression device;
S1)将特制的绝缘消弧绳上由多股软铜线与绝缘绳编织的一段与待接入的35kV变电站设备引流线绑扎固定在一起并穿入消弧装置滑车中,垂下的两端绳头分别由2个地面人员控制;S1) Bind and fix a section of the special insulated arc-suppression rope braided by multi-strand annealed copper wire and insulating rope with the drain wire of the 35kV substation equipment to be connected, and pass it into the arc-suppression device pulley. The heads are controlled by two ground personnel respectively;
S2)带电作业人员用绝缘操作杆将消弧装置沿通道8挑入并通过挂孔挂接在母导线上;S2) The live working personnel use the insulating operating rod to pick the arc suppression device along the channel 8 and hang it on the bus conductor through the hanging hole;
S3)通过绝缘操作杆端头上的工具夹持住母导线活动夹紧装置4的外端并转动,通过旋进母导线活动夹紧装置4压紧母导线;S3) Hold and rotate the outer end of the movable clamping device 4 of the bus conductor through the tool on the end of the insulating operating rod, and compress the bus conductor by screwing in the movable clamping device 4 of the bus conductor;
S4)确认消弧装置安装牢固后,2个地面人员中的1人快速拉动消弧绳,而另1人配合快速松开消弧绳,使带有软铜线的一段消弧绳快速接入带电母导线上。S4) After confirming that the arc suppression device is firmly installed, one of the two ground personnel quickly pulls the arc suppression rope, while the other cooperates with the quick release of the arc suppression rope to quickly connect a section of arc suppression rope with soft copper wire On the live bus conductor.
S5)确认绝缘消弧绳的一段铜线处于良好导电状态后,带电作业人员使用绝缘操作工具将设备引流线接入母导线上并安装牢固;之后解开设备引流线与消弧绳上铜线的绑扎连接;S5) After confirming that a section of copper wire of the insulated arc-suppression rope is in a good conductive state, live workers use insulating operation tools to connect the equipment drainage wire to the bus conductor and install it firmly; then untie the equipment drainage wire and the copper wire on the arc-suppression rope binding connection;
S6)拆除消弧装置后完成带电接入设备引流线作业。S6) After the arc suppression device is removed, the operation of the drainage line of the live connection equipment is completed.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610200277.8A CN105870844B (en) | 2016-04-01 | 2016-04-01 | The operational method of the arc-extinction device of disconnecting operation is charged for 35kV substation equipment drainage threads |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610200277.8A CN105870844B (en) | 2016-04-01 | 2016-04-01 | The operational method of the arc-extinction device of disconnecting operation is charged for 35kV substation equipment drainage threads |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105870844A CN105870844A (en) | 2016-08-17 |
| CN105870844B true CN105870844B (en) | 2018-09-28 |
Family
ID=56627716
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610200277.8A Active CN105870844B (en) | 2016-04-01 | 2016-04-01 | The operational method of the arc-extinction device of disconnecting operation is charged for 35kV substation equipment drainage threads |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105870844B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109921335A (en) * | 2019-03-25 | 2019-06-21 | 云南电网有限责任公司昆明供电局 | The tower line adopts the method of breaking the ground potential of the arc suppression rope and connecting the drainage line |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202034702U (en) * | 2011-01-14 | 2011-11-09 | 北京市电力公司 | Arc extinguishing rope, wire fastener, arc extinguishing pulley and cable control lever |
| CN202534972U (en) * | 2012-03-30 | 2012-11-14 | 辽宁省电力有限公司辽阳供电公司 | Over-current clamping device |
| CN202586166U (en) * | 2012-04-28 | 2012-12-05 | 辽宁省电力有限公司锦州供电公司 | Tackle for disconnecting lead from tubular busbar and connecting lead to tubular busbar |
| CN102832567A (en) * | 2012-08-09 | 2012-12-19 | 国家电网公司 | Arc-extinguishing device for live disconnection lead wire and method for live disconnection lead wire |
| CN203645247U (en) * | 2013-12-20 | 2014-06-11 | 武汉珈铭凯尔电气科技发展有限公司 | An insulating rod with arc suppression device and arc transfer and arc suppression device |
| CN103986086A (en) * | 2014-04-14 | 2014-08-13 | 国家电网公司 | Arc suppression tackle for disconnecting and connecting drainage thread in transformer substation in charged mode |
| CN204481397U (en) * | 2015-03-25 | 2015-07-15 | 国家电网公司 | A kind of novel conductive wire charged disconnecting drainage thread arc suppression tackle |
| CN104868403A (en) * | 2015-05-08 | 2015-08-26 | 国家电网公司 | A portable 120-400mm2 steel-cored aluminum stranded wire shunt line fixture and its application method |
| CN105207123A (en) * | 2015-10-13 | 2015-12-30 | 国网辽宁省电力有限公司丹东供电公司 | Equipotential operation method of tubular bus |
| CN205509381U (en) * | 2016-04-01 | 2016-08-24 | 云南电网有限责任公司临沧供电局 | A arc extinction device that is used for 35kV substation equipment drainage tape electricity breaking of contact operation |
-
2016
- 2016-04-01 CN CN201610200277.8A patent/CN105870844B/en active Active
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202034702U (en) * | 2011-01-14 | 2011-11-09 | 北京市电力公司 | Arc extinguishing rope, wire fastener, arc extinguishing pulley and cable control lever |
| CN202534972U (en) * | 2012-03-30 | 2012-11-14 | 辽宁省电力有限公司辽阳供电公司 | Over-current clamping device |
| CN202586166U (en) * | 2012-04-28 | 2012-12-05 | 辽宁省电力有限公司锦州供电公司 | Tackle for disconnecting lead from tubular busbar and connecting lead to tubular busbar |
| CN102832567A (en) * | 2012-08-09 | 2012-12-19 | 国家电网公司 | Arc-extinguishing device for live disconnection lead wire and method for live disconnection lead wire |
| CN203645247U (en) * | 2013-12-20 | 2014-06-11 | 武汉珈铭凯尔电气科技发展有限公司 | An insulating rod with arc suppression device and arc transfer and arc suppression device |
| CN103986086A (en) * | 2014-04-14 | 2014-08-13 | 国家电网公司 | Arc suppression tackle for disconnecting and connecting drainage thread in transformer substation in charged mode |
| CN204481397U (en) * | 2015-03-25 | 2015-07-15 | 国家电网公司 | A kind of novel conductive wire charged disconnecting drainage thread arc suppression tackle |
| CN104868403A (en) * | 2015-05-08 | 2015-08-26 | 国家电网公司 | A portable 120-400mm2 steel-cored aluminum stranded wire shunt line fixture and its application method |
| CN105207123A (en) * | 2015-10-13 | 2015-12-30 | 国网辽宁省电力有限公司丹东供电公司 | Equipotential operation method of tubular bus |
| CN205509381U (en) * | 2016-04-01 | 2016-08-24 | 云南电网有限责任公司临沧供电局 | A arc extinction device that is used for 35kV substation equipment drainage tape electricity breaking of contact operation |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105870844A (en) | 2016-08-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104868403B (en) | A kind of portable 120~400mm2Steel-cored aluminium strand shunt line fixture and application method | |
| CN111541066B (en) | A retractable portable multifunctional grounding wire | |
| CN205092507U (en) | Multi -functional insulating drainage line support frame | |
| CN102842867A (en) | Method for electrically disconnecting or connecting disconnector with drainage wire between buses | |
| CN104882825B (en) | Electrification in high voltage breaking and connecting thread guide devices and lead method | |
| CN103268991A (en) | Grounding device for 10kv cable branch box, ring main unit and ring main box | |
| CN206542167U (en) | A kind of insulated cable support | |
| CN102185267B (en) | 66KV ground potential hot-line make-and-break bypassing method | |
| CN105207123A (en) | Equipotential operation method of tubular bus | |
| CN104767050B (en) | Hook type personal security line | |
| CN105870844B (en) | The operational method of the arc-extinction device of disconnecting operation is charged for 35kV substation equipment drainage threads | |
| CN103474909B (en) | Drainage thread supports the method for expansion live-line replacing multiloop strain insulator string | |
| CN205509381U (en) | A arc extinction device that is used for 35kV substation equipment drainage tape electricity breaking of contact operation | |
| CN102545091A (en) | Charged disconnecting wire lead clamp device | |
| CN106207885B (en) | The short circuit fixture and method of charged for replacement 220kV pipe bus telescoping wire clamps | |
| CN103500966B (en) | 66kv disconnecting switch is to pipe bus charged disconnecting lead-in wire method | |
| CN203014232U (en) | Transformer station tube type bus single-clamp grounding device | |
| CN106356758A (en) | Operating method for replacing pole-mounted switch live on indirect bypass of 10 KV line insulating pole | |
| CN105699713A (en) | Multifunctional telescopic high-altitude electric testing clamp and application method thereof | |
| CN207753173U (en) | A kind of powering shelf earth protective device | |
| CN213071962U (en) | Insulating operating rod for power distribution network | |
| CN201562769U (en) | UHV grounding wire device | |
| CN219576453U (en) | Electrified wire breaking and connecting tool | |
| CN204088982U (en) | A kind of ground protection pincers | |
| CN206506042U (en) | A kind of power taking operating assembly |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| OL01 | Intention to license declared | ||
| OL01 | Intention to license declared |