CN105862598A - 定点起吊导梁式架桥机首跨24米过孔作业施工方法 - Google Patents

定点起吊导梁式架桥机首跨24米过孔作业施工方法 Download PDF

Info

Publication number
CN105862598A
CN105862598A CN201610234709.7A CN201610234709A CN105862598A CN 105862598 A CN105862598 A CN 105862598A CN 201610234709 A CN201610234709 A CN 201610234709A CN 105862598 A CN105862598 A CN 105862598A
Authority
CN
China
Prior art keywords
bridge
meters
bridge erector
nose girder
meter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610234709.7A
Other languages
English (en)
Inventor
曾文
张菲
刘太富
谭俊
杨青斌
李翔宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority to CN201610234709.7A priority Critical patent/CN105862598A/zh
Publication of CN105862598A publication Critical patent/CN105862598A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

本发明公开了一种定点起吊导梁式架桥机首跨24米过孔作业施工方法,将架桥机调整至32米状态,并使导梁搭设在连续梁端头与24米桥墩上;对导梁的尾部施加向下的锚固力,将架桥机向前移动,使架桥机搭设在24米桥墩与连续梁上;将导梁继续向前移动,提至下一跨;将架桥机向前移动;将架桥机调整为24米状态,并使架桥机的前支腿垂直搭设在24米桥墩上;利用运梁车喂梁模式锚固架桥机,将导梁提回至待架跨度,使架桥机处于架梁状态;本发明所述定点起吊导梁式架桥机首跨24米过孔作业施工方法利用设备自身结构特点及稳定性完成过孔作业;避免额外修筑钢构支墩,节省了大量的人机料,大大减少了工作量,减少成本投入。

Description

定点起吊导梁式架桥机首跨24米过孔作业施工方法
技术领域
本发明涉及一种铁路施工方法,尤其涉及一种定点起吊导梁式架桥机首跨24米过孔作业施工方法。
背景技术
随着全国各地推进市域铁路的建设,市域铁路是中心城区与周边区市县连接的快速轨道交通线,通常以高架桥形式跨越城区,受城市道路影响,设计利用连续梁和跨度变换来适应城市道路,这样就出现了以往施工中未出现的首跨为24米的特殊工况。
因市域铁路设计时速通常低于高铁高于普铁,其梁型比高铁外形小、重量轻、所能承受的施工荷载小,设计采用900吨级定点起吊式架桥机进行施工。
因设备在设计时未考虑首跨24米施工工况,目前施工单位在遇到此类工况时采取在导梁前支腿32米位置搭设临时钢结构支墩来满足架桥机过孔要求。搭设钢构支墩法需用大量的材料、设备和人工,且随着高度的增加支墩稳定性也存在考验,在架桥机过孔完成后刚支墩的拆除也很麻烦,成本花费大,此方法在安全、经济、时效上非常不合理。
发明内容
本发明的目的就在于为了解决上述问题而提供一种定点起吊导梁式架桥机首跨24米过孔作业施工方法。
本发明通过以下技术方案来实现上述目的:
一种定点起吊导梁式架桥机首跨24米过孔作业施工方法,包括以下步骤:
(1)将架桥机调整至32米状态,并将其移动至连续梁端头,并调整导梁,使导梁的尾部支腿垂直搭设在连续梁端头的桥墩上,导梁的前支腿垂直搭设在24米桥墩上;
(2)对导梁的尾部施加20t向下的锚固力,将架桥机向前移动24.7米,使架桥机的前支腿垂直搭设在24米桥墩上,架桥机的后支腿垂直搭设在连续梁上;
(3)固定架桥机的位置,并在此状态下将导梁继续向前移动,提至下一跨,即使导梁的尾部支腿垂直搭设在24米桥墩上,使导梁的前支腿垂直搭设在下一跨的桥墩上;
(4)将架桥机转换为整机过孔模式,拆除架桥机的前支腿与导梁的连接螺栓,将架桥机向前移动8米;
(5)将架桥机的前支腿向后移动8米,即使架桥机处于24米状态,并使架桥机的前支腿垂直搭设在24米桥墩上;
(6)利用运梁车喂梁模式锚固架桥机,将导梁提回至待架跨度,使架桥机处于架梁状态。
本发明的有益效果在于:
本发明所述定点起吊导梁式架桥机首跨24米过孔作业施工方法利用设备自身结构特点及稳定性完成过孔作业;避免额外修筑钢构支墩,节省了大量的人机料,大大减少了工作量,减少成本投入。
附图说明
图1是本发明所述定点起吊导梁式架桥机首跨24米过孔作业施工方法的步骤(1)的示意图;
图2是本发明所述步骤(2)的示意图;
图3是本发明所述步骤(3)的示意图;
图4是本发明所述步骤(4)的示意图;
图5是本发明所述步骤(5)的示意图;
图6是本发明所述步骤(6)的示意图;
图7是本发明所述步骤(2)的导梁稳定性计算示意图。
具体实施方式
下面结合附图对本发明作进一步说明:
如图1所示,架桥机调整至32米状态,并将其移动至连续梁端头,并调整导梁,使导梁的尾部支腿垂直搭设在连续梁端头的桥墩上,导梁的前支腿垂直搭设在24米桥墩上;
如图2所示,对导梁的尾部施加20t向下的锚固力,将架桥机向前移动24.7米,使架桥机的前支腿垂直搭设在24米桥墩上,架桥机的后支腿垂直搭设在连续梁上;
如图3所示,固定架桥机的位置,并在此状态下将导梁继续向前移动,提至下一跨,即使导梁的尾部支腿垂直搭设在24米桥墩上,使导梁的前支腿垂直搭设在下一跨的桥墩上;
如图4所示,将架桥机转换为整机过孔模式,拆除架桥机的前支腿与导梁的连接螺栓,将架桥机向前移动8米;
如图5所示,将架桥机的前支腿向后移动8米,即使架桥机处于24米状态,并使架桥机的前支腿垂直搭设在24米桥墩上;
如图6所示,利用运梁车喂梁模式锚固架桥机,将导梁提回至待架跨度,使架桥机处于架梁状态。
如图7所示,对图2所示的导梁的状态进行稳定性分析:
图中O为导梁前支腿支点,G为导梁重心点(重力为109t),P1对导梁尾部施加的锚固力与导梁后支腿、吊翅、钢丝绳的锚固力等总作用力(总作用力为28t),P3为架桥机前支腿行走时为导梁施加的倾覆力223t;
倾覆力矩:M1=P3×3=669t·m,其中3为P3的作用点到O点的距离;
稳定力矩:M2=P1×23.2+G×5.288=1226t·m,其中23.2为P1的作用点到O点的距离,5.288为G的作用点到O点的距离;
稳定系数:n=M2/M1=1226/(669×1.1)=1.67>1.5,即满足过孔的稳定需求。
本发明的技术方案不限于上述具体实施例的限制,凡是根据本发明的技术方案做出的技术变形,均落入本发明的保护范围之内。

Claims (1)

1.一种定点起吊导梁式架桥机首跨24米过孔作业施工方法,其特征在于:包括以下步骤:
(1)将架桥机调整至32米状态,并将其移动至连续梁端头,并调整导梁,使导梁的尾部支腿垂直搭设在连续梁端头的桥墩上,导梁的前支腿垂直搭设在24米桥墩上;
(2)对导梁的尾部施加20t向下的锚固力,将架桥机向前移动24.7米,使架桥机的前支腿垂直搭设在24米桥墩上,架桥机的后支腿垂直搭设在连续梁上;
(3)固定架桥机的位置,并在此状态下将导梁继续向前移动,提至下一跨,即使导梁的尾部支腿垂直搭设在24米桥墩上,使导梁的前支腿垂直搭设在下一跨的桥墩上;
(4)将架桥机转换为整机过孔模式,拆除架桥机的前支腿与导梁的连接螺栓,将架桥机向前移动8米;
(5)将架桥机的前支腿向后移动8米,即使架桥机处于24米状态,并使架桥机的前支腿垂直搭设在24米桥墩上;
(6)利用运梁车喂梁模式锚固架桥机,将导梁提回至待架跨度,使架桥机处于架梁状态。
CN201610234709.7A 2016-04-14 2016-04-14 定点起吊导梁式架桥机首跨24米过孔作业施工方法 Pending CN105862598A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610234709.7A CN105862598A (zh) 2016-04-14 2016-04-14 定点起吊导梁式架桥机首跨24米过孔作业施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610234709.7A CN105862598A (zh) 2016-04-14 2016-04-14 定点起吊导梁式架桥机首跨24米过孔作业施工方法

Publications (1)

Publication Number Publication Date
CN105862598A true CN105862598A (zh) 2016-08-17

Family

ID=56637787

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610234709.7A Pending CN105862598A (zh) 2016-04-14 2016-04-14 定点起吊导梁式架桥机首跨24米过孔作业施工方法

Country Status (1)

Country Link
CN (1) CN105862598A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107653783A (zh) * 2017-09-29 2018-02-02 中交第二航务工程局有限公司 双幅桥尾部喂梁吊装方法
CN111910531A (zh) * 2020-09-22 2020-11-10 河南省中原奥起实业有限公司 一种桥梁的架设方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060118066A (ko) * 2005-05-16 2006-11-23 에이앤텍건설 주식회사 이동식비계의 비계보
CN202194077U (zh) * 2011-08-29 2012-04-18 中铁科工集团有限公司 一种适应小曲线过孔的架桥机走行装置
CN102561200A (zh) * 2012-01-20 2012-07-11 中铁一局集团有限公司 架桥机过路基用推行装置及架桥机过路基方法
CN102704407A (zh) * 2012-07-03 2012-10-03 中铁一局集团有限公司 一种下导梁式架桥机过隧道施工方法
CN103485282A (zh) * 2013-09-22 2014-01-01 中铁六局集团有限公司 运架一体机进出隧道口架设箱梁的施工方法
CN103938547A (zh) * 2014-04-16 2014-07-23 河北工业大学 一种定点起吊式架桥机及架桥方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060118066A (ko) * 2005-05-16 2006-11-23 에이앤텍건설 주식회사 이동식비계의 비계보
CN202194077U (zh) * 2011-08-29 2012-04-18 中铁科工集团有限公司 一种适应小曲线过孔的架桥机走行装置
CN102561200A (zh) * 2012-01-20 2012-07-11 中铁一局集团有限公司 架桥机过路基用推行装置及架桥机过路基方法
CN102704407A (zh) * 2012-07-03 2012-10-03 中铁一局集团有限公司 一种下导梁式架桥机过隧道施工方法
CN103485282A (zh) * 2013-09-22 2014-01-01 中铁六局集团有限公司 运架一体机进出隧道口架设箱梁的施工方法
CN103938547A (zh) * 2014-04-16 2014-07-23 河北工业大学 一种定点起吊式架桥机及架桥方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
冯燕: "900吨级导梁式定点起吊架桥机研究", 《中国学位论文全文数据库》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107653783A (zh) * 2017-09-29 2018-02-02 中交第二航务工程局有限公司 双幅桥尾部喂梁吊装方法
CN111910531A (zh) * 2020-09-22 2020-11-10 河南省中原奥起实业有限公司 一种桥梁的架设方法

Similar Documents

Publication Publication Date Title
CN202936736U (zh) 一种斜拉桥组合梁施工桥面吊机
CN102373671B (zh) 钢桁梁柔性拱桥带拱顶推施工方法
CN100543235C (zh) 斜拉索辅助全悬臂架设钢桁梁的方法及系统
CN103572708B (zh) 大跨度混凝土连续梁桥边跨合拢装置及方法
CN104727227B (zh) 一种中承式钢箱系杆拱桥敞口格构式钢梁整节段架设方法
CN103669224A (zh) 斜置拱塔双索面预应力混凝土斜拉桥中拱塔施工方法及钢管支架
CN201106155Y (zh) 斜拉索辅助全悬臂架设钢桁梁装置
CN102535348B (zh) 一种铰塔斜拉桥斜拉索的张拉方法
CN201506952U (zh) 无支架临时索配合挂篮建筑混凝土斜拉桥
CN101158146A (zh) 斜拉桥主梁滑动模架系统及施工方法
CN103882812A (zh) 斜拉索桥中跨主梁的施工方法
CN109736206A (zh) 波形钢腹板连续梁桥边跨合拢现浇支架结构及施工方法
CN202482776U (zh) 一种大风及高空条件下桥梁施工用腹板式造桥机
CN101481903B (zh) 跨缆吊机倒退拼装架设山区悬索桥主桁方法
CN104532749A (zh) 一种用于悬索桥主塔上横梁施工的支架
CN110093863A (zh) 一种不设置前支腿的双工作面一体化架桥机
CN105862598A (zh) 定点起吊导梁式架桥机首跨24米过孔作业施工方法
CN106758872A (zh) 波形钢腹板scc工法随车回旋吊移动挂篮及利用其施工的方法
CN201746780U (zh) 能通过隧道且实现隧道口架梁的架桥机
CN203613467U (zh) 斜置拱塔双索面预应力混凝土斜拉桥中拱塔施工中的钢管支架
CN102134832A (zh) 活动支架辅助不变幅架梁吊机架设钢箱梁方法及活动支架
CN106906750A (zh) 一种多功能跨铁路线平转桥梁合龙施工模架及其施工方法
CN207032062U (zh) 可用于大跨度钢箱梁施工的吊索塔架
CN102535351B (zh) 大风及高空条件下桥梁施工用腹板式造桥机及施工工艺
CN210315233U (zh) 一种不设置前支腿的双工作面一体化架桥机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zeng Wen

Inventor after: Yang Qingbin

Inventor after: Wang Hui

Inventor after: Chen Jiangyi

Inventor after: Li Xiangyu

Inventor after: Dong Guilin

Inventor after: Wu Zhangjun

Inventor before: Zeng Wen

Inventor before: Zhang Fei

Inventor before: Liu Taifu

Inventor before: Tan Jun

Inventor before: Yang Qingbin

Inventor before: Li Xiangyu

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160817