CN105846418B CN201610327926.0A CN201610327926A CN105846418B CN 105846418 B CN105846418 B CN 105846418B CN 201610327926 A CN201610327926 A CN 201610327926A CN 105846418 B CN105846418 B CN 105846418B
Authority
CN
China
Prior art keywords
unit
power
data
energy management
capacitance sensor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610327926.0A
Other languages
Chinese (zh)
Other versions
CN105846418A (en
Inventor
檀庭方
付豪
李靖霞
王涛
吴世伟
张哲�
王紫东
刘文彪
纪陵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing SAC Automation Co Ltd
Original Assignee
Nanjing SAC Automation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing SAC Automation Co Ltd filed Critical Nanjing SAC Automation Co Ltd
Priority to CN201610327926.0A priority Critical patent/CN105846418B/en
Publication of CN105846418A publication Critical patent/CN105846418A/en
Application granted granted Critical
Publication of CN105846418B publication Critical patent/CN105846418B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J1/00Circuit arrangements for dc mains or dc distribution networks
    • H02J1/10Parallel operation of dc sources
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J1/00Circuit arrangements for dc mains or dc distribution networks
    • H02J1/14Balancing the load in a network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J3/32Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • H02J3/385
    • H02J3/386
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
    • H02J7/34Parallel operation in networks using both storage and other dc sources, e.g. providing buffering
    • H02J7/35Parallel operation in networks using both storage and other dc sources, e.g. providing buffering with light sensitive cells
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/003Load forecast, e.g. methods or systems for forecasting future load demand
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/388Islanding, i.e. disconnection of local power supply from the network
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/50Energy storage in industry with an added climate change mitigation effect

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

The present invention discloses a kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System, including energy management unit, real-time monitoring unit, PREDICTIVE CONTROL unit and distributed unit breaker;Micro-capacitance sensor includes the generator unit, accumulator and the load that connect power bus-bar by energy converter respectively;Real-time monitoring unit obtains the operating status of each generator unit and accumulator, PREDICTIVE CONTROL unit is according to current weather information data and historical load data, predict the output power and loading demand of generator unit, energy management unit is according to receiving micro-capacitance sensor operation data and prediction result data, with the minimum object function of system operation expense, using system safety operation as constraints, the operating status and output power of each generator unit of subsequent time are calculated, and is transmitted accordingly by each generator unit of distributed unit breaker control to the electric energy of electric power network.The present invention can reduce the influence that the uncertain factors such as weather conditions, the fluctuation of load bring system operation, promote micro-capacitance sensor reliability of operation.

Description

A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System
Technical field
The present invention relates to isolated island type micro-capacitance sensor management and running technical field, particularly a kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System.
Background technology
With the energetically support that uses of the country to regenerative resource, more and more micro-capacitance sensor projects have been built up, special It is not that the isolated island type micro-capacitance sensor used for remote districts, industry park, school, hospital receives more and more attention.
With building up for a large amount of isolated island type micro-capacitance sensors, it is following the problem of, such as the interval of regenerative resource output power Property with randomness to system power balance influence problem, how regenerative resource effectively uses problem, systematic economy in systems Operation problem, system operation how each distributed generation unit output power problem of Real-Time Scheduling, how effective accumulator is Prolong the service life problem etc..The EMS system of micro-capacitance sensor is namely based on the above problem and carries out relevant research, makes micro-capacitance sensor system System is capable of the operation of economic and reliable.
And current EMS researchs are mostly focused on and dispatch a few days ago, the operation result of second day are calculated according to predictive information, so It is run afterwards according to this scheduling result.Due to the intermittence of renewable sources of energy output power, randomness and load-side demand not Certainty, regenerative resource often has the prediction result for being worse than the previous day with loading demand in same day operational process, if also pressed The safety problem of system will necessarily be caused according to the operation of scheduling result a few days ago, when weather condition changes greatly, in some instances it may even be possible to Cause the collapse of whole system.In order to enable a system to safely and effectively run, the battery of certain capacity is often configured in micro-capacitance sensor Peak load shifting is carried out, improves renewable energy utilization rate, and if overcharged to battery under inclement weather conditions or mistake The service life of battery can be substantially reduced by putting.Therefore the necessary EMS to existing micro-capacitance sensor is explored and is studied, and is improved micro- Safety, reliability and the economy of operation of power networks.
Invention content
The technical problem to be solved in the present invention is:A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System is provided, is solved The certainly demand of isolated island type micro-capacitance sensor Real-Time Scheduling reduces in system operation the uncertain factors such as weather conditions, fluctuation of load to being The influence that system operation is brought, promotes micro-capacitance sensor reliability of operation and economic benefit.
The technical solution that the present invention takes is specially:A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System, isolated island Type micro-capacitance sensor include respectively by energy converter connect the photovoltaic generation unit of power bus-bar, wind turbine power generation unit, diesel engine, Accumulator, AC load and DC load;Real-Time Scheduling Energy Management System includes:Energy management unit, real-time monitoring unit, PREDICTIVE CONTROL unit and distributed unit breaker;
Real-time monitoring unit connects respectively with connecting the energy converter of diesel engine and accumulator, charged to obtain accumulator The running state data of status data and diesel engine, and by the data transmission got to energy management unit;The diesel engine Running state data refer mainly to the start and stop state parameter data of diesel engine;
PREDICTIVE CONTROL unit receives Weather information data and historical load data, and according to the Weather information data received It predicts the output power of photovoltaic generation unit and wind turbine power generation unit, loading demand is predicted according to historical load data, then will Prediction result data transmission is to energy management unit;
Energy management unit receives the data that real-time monitoring unit and PREDICTIVE CONTROL unit are sent out, based on PREDICTIVE CONTROL list The generator unit output power data and loading demand data of member output, with the minimum object function of system operation expense, system Safe operation is constraints, asks for Optimization of Unit Commitment;And in the case where not changing original Unit Commitment state status, calculate next The operating status and output power of period photovoltaic generation unit and wind turbine power generation unit calculate to get to the scheduling of each period As a result;
Distributed unit breaker includes the breaker being connected between each energy converter and power bus-bar, each disconnected Road device connects energy management unit respectively;Energy management unit obtains the state of cut-offfing of current each breaker, and is counted according to scheduling Being opened or closed for each breaker of output control is calculated, so as to the corresponding work for controlling each generator unit.
The present invention is in use, energy management unit determines that each generator unit is contributed according to the size of net power in micro-capacitance sensor Size determines control accumulator cell charging and discharging power according to the state-of-charge of accumulator.When dispatching calculating, with system operation expense Minimum object function is calculated, and each distributed generation unit can be made to be operated within its safe operation power bracket, and And regenerative resource can be used to greatest extent;Battery-operated is within the scope of maximum charge-discharge electric power simultaneously, effectively to prolong The service life of long accumulator;Diesel engine is operated in the higher range of operation of its efficiency, to reduce whole system to environment Pollution;Make whole system safe and stable operation.
Further, in the present invention, the Weather information data that PREDICTIVE CONTROL unit receives include the day in the following short time Gas forecast information data and a few days ago weather forecast information data:
PREDICTIVE CONTROL unit is daily unit, using neural net prediction method according to weather forecast information data a few days ago The output power of photovoltaic generation unit and wind turbine power generation unit and the demand of load are calculated with autoregression model, is predicted a few days ago Data;
PREDICTIVE CONTROL unit is according to the weather forecast information data in the following short time, using BP neural network prediction algorithm The output power of photovoltaic generation unit and wind turbine power generation unit and negative after being calculated 5 minutes, 15 minutes, 30 minutes with autoregression model Load demand, and it is transmitted to energy management unit.Real-Time Scheduling for energy management unit provides data basis, correspondingly, energy Administrative unit is scheduled calculating and then is 5 minutes/time to the period that micro-capacitance sensor is scheduled, to cope with system operation mistake in time Emergency situations in journey, for example weather condition burst changes or loading demand changes.
Correspondingly, energy management unit is needed based on the generator unit output power data that PREDICTIVE CONTROL unit exports and load Data are sought, using prediction data a few days ago as input, with the minimum object function of system operation expense, system safety operation is constraint item Part asks for Optimization of Unit Commitment using mixed integer programming algorithm;
The object function of wherein system operation expense minimum is:
In formula, F is operating cost, and T is the cycle of operation, tcFor current time;L is renewable generator unit number;pi(t) For renewable generator unit power generation electricity price, Pi(t), it is renewable generator unit output power;ponCost is opened for diesel engine;pd Power generation unit price for diesel engine;PgenFor diesel power generation power;U (t) is diesel engine state variable, and u (t)=0 represents diesel engine In shutdown status, u (t)=1 represents that diesel engine is opened;U (t) is the result that Integer programming obtains;Cbat(T) it is Energy storage device operating cost;
Isolated island type micro-capacitance sensor, which needs to meet certain constraints in running optimizatin, can just make real system reach technology Feasible and economically feasible;Present system safe operation constraints includes:
1) wind turbine, the constraint of photovoltaic output power:
In formula (2), PW_max、PPV_maxWind turbine, photovoltaic peak power output are represented respectively;
2) energy storage device, that is, battery power is constrained with SOC:
Since energy storage device is related with the battery status of last moment during charge and discharge, and current state can influence To the operation of subsequent time period system, in order to weaken influence of the energy storage device in the process of running between execution cycle, calculating The initial value of middle setting energy storage device SOC is equal to end value, and to meet during operation the limitation of SOC bounds with And the constraints such as limitation of charge-discharge electric power, it is specific as follows:
In formula (3), SOCmin、SOCmaxThe lower limiting value and upper limit value of accumulator SOC is represented respectively, and it is 0.2 that can distinguish value With 0.9;Pmax_charge、Pmax_dischargeAccumulator maximum charge-discharge electric power is represented respectively;η is accumulator transfer efficiency, during charging Take charge efficiency ηc, when electric discharge picks and places electrical efficiency ηd1/ η of inversed;Pbat,tΔt/EcCharge and discharge for the accumulator within the Δ t times The remaining capacity value for the energy storage device that electrical power generates;
3) diesel power generation power constraint:
kde_minPde_rate≤Pgen(t)≤Pde_rate (4)
In formula (4), Pde_rateFor diesel-driven generator rated power;kde_rateWhen being run for diesel-driven generator minimum power Proportionality coefficient;
Diesel engine its operation power after unlatching should be operated in certain power bracket, otherwise can influence making for diesel engine With efficiency and economy.
4) system-level operation constraints is balanced including system power:
In formula (5), PriRepresent regenerative resource output power, PnmRepresent non-regeneration energy output power, PLkFor load Demand power;
The regenerative resource output power is to include the output power of photovoltaic generation unit and wind turbine power generation unit, it is non-can Renewable sources of energy output power includes diesel engine and accumulator output power.
While Optimization of Unit Commitment is asked for, energy management unit in the case where not changing original Unit Commitment state status, Using genetic algorithm calculate operating status and the output power of subsequent time period photovoltaic generation unit and wind turbine power generation unit to get To the scheduling result of calculation of each period.
The invention described above system is respectively the prior art to the application of genetic algorithm and mixed integer programming algorithm.
If the weather conditions of some day occur that weather condition is unstable in cataclysm or one day in operational process, this When each generator unit output-power fluctuation can be bigger, then real-time monitoring unit of the invention can be real with PREDICTIVE CONTROL unit When the running state information of system and corresponding predictive information be transferred to energy management unit, energy management unit is according to acquisition Information calculates subsequent time period and scheduling information later, and sends and instruct accordingly to distributed unit breaker and each electricity Energy converter, makes the influence that uncertain factor is brought in reply system in advance, ensures system safe and stable operation.
The SOC value for the accumulator that energy management unit is obtained according to real-time monitoring unit ensures that energy storage operates in peace always In gamut;Energy management unit is by regenerative resource output power, the prediction data a few days ago of load demand power data simultaneously In the corresponding period data, compared with the prediction data in following short time interval;For renewable in prediction data a few days ago When energy output power, loading demand data have differences with following short time interval interior prediction data, energy management unit is counted again Scheduling result is calculated, system is scheduled again further according to scheduling result.
Aforementioned prediction data a few days ago is temporally carried out when calculating, it is assumed that between 2 points of operation (continuous two hours) Power is constant, and in following short time interval the result is that being calculated by the period rolling of 5min/ time, the data compared are just It is the data control for running the cycle of operation between two points the same day and the data in this point-to-point transmission predicted a few days ago.Such as same day fortune Calculate that 2 pm 45 divides as a result, comparison is exactly that the regenerative resource output power predicted at this time predicted to come with the previous day The same day 2 pm output results contrast.
It is of the present invention a few days ago be actual motion proxima luce (prox. luc) namely present system every day all on the day of to secondary The predicting condition (weather forecast information data before this day) of day Weather information predicts the regenerative resource output power of next day and negative Carry demand power data, i.e. prediction data a few days ago.
Advantageous effect
The present invention for the energy management system based on international standards such as IEC61970, system by monitor in real time including The micro-capacitance sensor data of accumulator status, generator unit output power and diesel engine operating status, while according to getting weather Data and load data prediction workload demand amount, so according to workload demand amount and micro-capacitance sensor data calculate next renewable time and The scheduling information of the time of running later then according to the work of each functional unit in scheduling result of calculation control micro-capacitance sensor, is realized Energy management and scheduling.Specifically effect is:
1) when same day renewable resource and predicted value are variant, system can react to that, it is reliable to improve power supply Property;
2) renewal speed of energy management unit is fast, when being in an emergency for the demand of load-side, can solve in time Certainly, the safety of system operation is improved;
3) operating mode of renewable generator unit is not limited to maximal power tracing, can according to the actual motion of power grid into Row adjustment, maximal power tracing is operated in range of safety operation, when there is weather or loading demand exception, can be adjusted Whole renewable generator unit operation in the secure mode, improves the comprehensive effectiveness of system overall operation;
4) present invention, with reference to the charge-discharge characteristic of battery, can effectively be kept away with the minimum object function of system operation expense Exempt to occur over-charging of battery in the process of running to cross and put phenomenon, improve the service life of battery, efficiently use regenerative resource pair System power supply improves the economy of system operation.
Description of the drawings
Fig. 1 show present system structural schematic block diagram;
Fig. 2 show genetic algorithm flow diagram.
Specific embodiment
It is further described below in conjunction with the drawings and specific embodiments.
With reference to figure 1, isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System of the invention include energy management unit, in real time Monitoring unit, PREDICTIVE CONTROL unit and distributed unit breaker;Isolated island type micro-capacitance sensor includes passing through energy converter respectively Connect photovoltaic generation unit, wind turbine power generation unit, diesel engine, accumulator, AC load and the DC load of power bus-bar;Each electricity The control terminal connection energy management unit of energy converter;
Real-time monitoring unit connects respectively with connecting the energy converter of diesel power generation unit and accumulator, is stored with obtaining The running state data of battery charge state data and diesel engine, and by the data transmission got to energy management unit;
PREDICTIVE CONTROL unit receives Weather information data and historical load data, and according to the data prediction photovoltaic received The output power and loading demand of generator unit and wind turbine power generation unit, and by prediction result data transmission to energy management Unit;
Energy management unit receives the data that real-time monitoring unit and PREDICTIVE CONTROL unit are sent out, based on PREDICTIVE CONTROL list The generator unit output power data and loading demand data of member output, with the minimum object function of system operation expense, system Safe operation is constraints, asks for Optimization of Unit Commitment;And in the case where not changing original Unit Commitment state status, calculate next The operating status and output power of period photovoltaic generation unit and wind turbine power generation unit calculate to get to the scheduling of each period As a result;
Distributed unit breaker includes the breaker being connected between each energy converter and power bus-bar, energy Administrative unit obtains the state of current each breaker, and according to the work of scheduling each breaker of result of calculation, to control each open circuit Device contact is opened or closed, and then the corresponding work for controlling each generator unit.
Embodiment
In embodiment shown in FIG. 1, energy converter connects power bus-bar and photovoltaic generation unit, wind turbine power generation unit With the DC converter of DC load, connection power bus-bar and diesel engine, the rectifier converter of accumulator and connection electric power are female The inverter of line and AC load.
The Weather information data that PREDICTIVE CONTROL unit receives include weather forecast information data and day in the following short time Preceding weather forecast information data;
PREDICTIVE CONTROL unit is daily unit, using neural net prediction method according to weather forecast information data a few days ago The output power of photovoltaic generation unit and wind turbine power generation unit and the demand of load are calculated with autoregression model, is predicted a few days ago Data;
PREDICTIVE CONTROL unit is according to the weather forecast information data in the following short time, using BP neural network prediction algorithm The output power of photovoltaic generation unit and wind turbine power generation unit and negative after being calculated 5 minutes, 15 minutes, 30 minutes with autoregression model Load demand, and it is transmitted to energy management unit.Real-Time Scheduling for energy management unit provides data basis, correspondingly, energy Administrative unit is scheduled calculating and then is 5 minutes/time to the period that micro-capacitance sensor is scheduled, to cope with system operation mistake in time Emergency situations in journey, for example weather condition burst changes or loading demand changes.
Real-time monitoring unit connects two rectifier converters, is transported with monitoring storage battery charge state SOC and diesel engine in real time Row state, and by the data transmission monitored to energy management unit.
Energy management unit receives the real time information of distributed unit breaker, real-time monitoring unit, PREDICTIVE CONTROL unit, And according to the micro-capacitance sensor operation data and prediction result data received, using prediction data a few days ago as input, with systematic running cost With minimum object function, using system safety operation as constraints, set optimization group is asked for using Integer programming It closes, on this basis, the output power of photovoltaic generation unit and wind turbine power generation unit further according to following short time period interior prediction, And loading demand information, in the state of original Unit Commitment is not changed, subsequent time period is calculated using genetic algorithm and is respectively sent out The operating status and output power of electric unit by the period rolling calculation of 5 minutes/time, obtain scheduling result of calculation.
When present system is run, the application to genetic algorithm, mixed integer programming algorithm is respectively the prior art.
When asking for Optimization of Unit Commitment, the object function of system operation expense minimum is energy management unit:
In formula, F is operating cost, and T is the cycle of operation, tcFor current time;L is renewable generator unit number;pi(t) For renewable generator unit power generation electricity price, Pi(t), it is renewable generator unit output power;ponCost is opened for diesel engine;pd Power generation unit price for diesel engine;PgenFor diesel power generation power;U (t) is diesel engine state variable, and u (t)=0 represents diesel engine In shutdown status, u (t)=1 represents that diesel engine is opened;U (t) is the result that Integer programming obtains;Cbat(T) it is Energy storage device operating cost;
Isolated island type micro-capacitance sensor, which needs to meet certain constraints in running optimizatin, can just make real system reach technology Feasible and economically feasible;Present system safe operation constraints includes:
1) wind turbine, the constraint of photovoltaic output power:
In formula (2), PW_max、PPV_maxWind turbine, photovoltaic peak power output are represented respectively;
2) energy storage device, that is, battery power is constrained with SOC:
Since energy storage device is related with the battery status of last moment during charge and discharge, and current state can influence To the operation of subsequent time period system, in order to weaken influence of the energy storage device in the process of running between execution cycle, calculating The initial value of middle setting energy storage device SOC is equal to end value, and to meet during operation the limitation of SOC bounds with And the constraints such as limitation of charge-discharge electric power, it is specific as follows:
In formula (3), SOCmin、SOCmaxThe lower limiting value and upper limit value of accumulator SOC is represented respectively, and it is 0.2 that can distinguish value With 0.9;Pmax_charge、Pmax_dischargeAccumulator maximum charge-discharge electric power is represented respectively;η is accumulator transfer efficiency, during charging Take charge efficiency ηc, when electric discharge picks and places electrical efficiency ηd1/ η of inversed;Pbat,tΔt/EcCharge and discharge for the accumulator within the Δ t times The remaining capacity value for the energy storage device that electrical power generates;
3) diesel power generation power constraint:
kde_minPde_rate≤Pgen(t)≤Pde_rate (4)
In formula (4), Pde_rateFor diesel-driven generator rated power;kde_rateWhen being run for diesel-driven generator minimum power Proportionality coefficient;
Diesel engine its operation power after unlatching should be operated in certain power bracket, otherwise can influence making for diesel engine With efficiency and economy.
4) system-level operation constraints is balanced including system power:
In formula (5), PriRepresent regenerative resource output power, PnmRepresent non-regeneration energy output power, PLkFor load Demand power;
The regenerative resource output power is to include the output power of photovoltaic generation unit and wind turbine power generation unit, it is non-can Renewable sources of energy output power includes diesel engine and accumulator output power.
To sum up, the mathematical model of present system can be described as:
s.t.hi..., (x)=0, i=1 m (6)
gj..., (x)≤0, j=1 l
Independent variable x in more than mathematical model*The optimal solution of as each distributed unit output power, wherein x are vector Value, each component is the output power of each distributed unit.
Formula (6) be the present system model condition to be met, wherein hi(x)=0 the balance of supply and demand need to be met by representing, i.e., Output power and the balance of actual demand;gj(x)≤0 representing each distributed generation unit needs to meet in the operation of its own Within safety condition.
Problem of the present invention is solved to optimization problem, and genetic algorithm has the function of global optimizing, and genetic algorithm has There are simple general-purpose, strong robustness, suitable for parallel processing, the present invention transports the economy of micro-grid system using genetic algorithm Row optimization problem carries out solution analysis, obtains the optimal solution of whole system.Genetic algorithm mainly includes coding, initialization, adapts to Degree assessment, selection, intersect, variation and etc., flow chart is as shown in Figure 2.
It may be configured as the calculating of energy management unit and dispatching cycle carrying out within every 5 to 15 minutes once, are to successfully manage Emergency situations in system operational process, for example weather condition burst changes or loading demand changes.Energy management system System adjusts scheduling result in time according to the data information of acquisition, is calculated with the minimum object function of system operation expense, can So that each distributed unit is operated within its safe operation power bracket, and regenerative resource can be used to greatest extent; Battery-operated is within the scope of maximum charge-discharge electric power, effectively to extend the service life of accumulator;Diesel engine is operated in it In the higher range of operation of efficiency, to reduce pollution of the whole system to environment;Make whole system safe and stable operation.
It, can if the weather conditions of some day occur that weather condition is unstable in cataclysm or one day in operational process The output-power fluctuation of regenerative electric power unit can be bigger, and real-time monitoring unit can be in real time by phase with PREDICTIVE CONTROL unit at this time Data information transfer is closed to energy management unit, energy management unit is according to the predictive information of acquisition and system real time execution shape Condition calculates subsequent time and scheduling information later, and sends and instruct accordingly to distributed unit, makes reply system in advance The influence that middle uncertain factor is brought ensures system safe and stable operation.
Photovoltaic generation unit normally may be configured as maximum power tracing pattern with wind turbine power generation unit operational mode in system, When encounter energy fluctuation that burst weather conditions bring it is larger when, it is distributed single that droop control mode tuning can be converted to The output power of member improves the reliability of system operation.Above-mentioned operational mode control to generator unit is the prior art.
To sum up, for the uncertainty of the intermittence of renewable resource, randomness and load-side demand in micro-capacitance sensor, this hair It is bright effectively to adjust these uncertain influences to system operation, reach the safe and reliable operation of system.The present invention simultaneously By effectively controlling the charge and discharge process of energy storage device, extend the service life of battery;By being carried out with the minimum target of operating cost Scheduling calculates, and then utilizes Unit Combination, control energy storage device charge-discharge electric power, the adjusting diesel engine to distributed generation unit Output power reaches the purpose of maximization uses regenerative resource, extends the service life of accumulator.
It these are only specific embodiments of the present invention, be not intended to limit the present invention, it is all in the spirit and principles in the present invention Within all any modification, equivalent and improvement made etc., should be included in protection scope of the present invention.

Claims (4)

1. a kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System, isolated island type micro-capacitance sensor includes passing through energy converter respectively Connect photovoltaic generation unit, wind turbine power generation unit, diesel engine, accumulator, AC load and the DC load of power bus-bar;It is special Sign is that Real-Time Scheduling Energy Management System includes:Energy management unit, real-time monitoring unit, PREDICTIVE CONTROL unit and distribution Formula unit breaker;
Real-time monitoring unit connects respectively with connecting the energy converter of diesel engine and accumulator, to obtain storage battery charge state The running state data of data and diesel engine, and by the data transmission got to energy management unit;
PREDICTIVE CONTROL unit receives Weather information data and historical load data, and according to the Weather information data prediction received The output power of photovoltaic generation unit and wind turbine power generation unit predicts loading demand according to historical load data, then will prediction Result data is transmitted to energy management unit;The Weather information data that PREDICTIVE CONTROL unit receives include the day in the following short time Gas forecast information data and a few days ago weather forecast information data;PREDICTIVE CONTROL unit is pressed according to weather forecast information data a few days ago It is unit, using neural net prediction method and autoregression model, calculates the defeated of photovoltaic generation unit and wind turbine power generation unit Go out the demand of power and load, obtain prediction data a few days ago;PREDICTIVE CONTROL unit is believed according to the weather forecast in the following short time Data are ceased, the output power and load of photovoltaic generation unit and wind turbine power generation unit need after calculating 5 minutes, 15 minutes, 30 minutes It asks;
Energy management unit receives the data that real-time monitoring unit and PREDICTIVE CONTROL unit are sent out, defeated based on PREDICTIVE CONTROL unit The generator unit output power data and loading demand data gone out, with the minimum object function of system operation expense, system safety Constraints is operated to, asks for Optimization of Unit Commitment;And in the case where not changing original Unit Commitment state status, future time is calculated The operating status and output power of section photovoltaic generation unit and wind turbine power generation unit calculate knot to get to the scheduling of each period Fruit;
Distributed unit breaker includes the breaker being connected between each energy converter and power bus-bar, each breaker Energy management unit is connected respectively;Energy management unit obtains the state of cut-offfing of current each breaker, and calculates knot according to scheduling Fruit controls being opened or closed for each breaker, so as to the corresponding work for controlling each generator unit.
2. isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System according to claim 1, it is characterized in that, energy management list The generator unit output power data and loading demand data that member is exported based on PREDICTIVE CONTROL unit, using prediction data a few days ago to be defeated Enter, with the minimum object function of system operation expense, system safety operation is constraints, is asked using mixed integer programming algorithm Take Optimization of Unit Commitment;
The object function of wherein system operation expense minimum is:
In formula, F is operating cost, and T is the cycle of operation, tcFor current time;L is renewable generator unit number;pi(t) being can Regenerative electric power unit power generation electricity price, Pi(t), it is renewable generator unit output power;ponCost is opened for diesel engine;pdFor bavin The power generation unit price of oil machine;PgenFor diesel power generation power;U (t) is diesel engine state variable, and u (t)=0 represents that diesel engine is in Shutdown status, u (t)=1 represent that diesel engine is opened;U (t) is the result that Integer programming obtains;Cbat(T) it is energy storage Device operating cost;
System safety operation constraints includes:
1) wind turbine, the constraint of photovoltaic output power:
In formula (2), PW_max、PPV_maxWind turbine, photovoltaic peak power output are represented respectively;
2) energy storage device, that is, battery power is constrained with SOC:
Since energy storage device is related with the battery status of last moment during charge and discharge, and current state influences whether down The operation of one period system in order to weaken influence of the energy storage device in the process of running between execution cycle, is set in the calculation Determine the initial value SOC of energy storage device SOCinitialEqual to end value SOCend, and to meet above and below SOC during operation The limitation of limit and the restriction of charge-discharge electric power, it is specific as follows:
In formula (3), SOCmin、SOCmaxThe lower limiting value and upper limit value of accumulator SOC is represented respectively, and value is 0.2 and 0.9 respectively; Pmax_charge、Pmax_dischargeAccumulator maximum charge-discharge electric power is represented respectively;η is accumulator transfer efficiency, and when charging takes charging Efficiency etac, when electric discharge picks and places electrical efficiency ηd1/ η of inversed;Pbat,tΔt/EcCharge-discharge electric power for the accumulator within the Δ t times The remaining capacity value of the energy storage device of generation;
3) diesel power generation power constraint:
kde_minPde_rate≤Pgen(t)≤Pde_rate (4)
In formula (4), Pde_rateFor diesel-driven generator rated power;kde_rateRatio when being run for diesel-driven generator minimum power Coefficient;
4) system-level operation constraints is balanced including system power:
In formula (5), PriRepresent regenerative resource output power, PnmRepresent non-regeneration energy output power, PLkFor loading demand Power.
3. isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System according to claim 1, energy management unit are not changing Become under original Unit Commitment state status, subsequent time period photovoltaic generation unit and wind turbine power generation unit are calculated using genetic algorithm Operating status and output power to get to the scheduling result of calculation of each period.
4. isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System according to any one of claims 1 to 3, it is characterized in that, Real-time monitoring unit connects energy management unit to transmit data with PREDICTIVE CONTROL unit by Ethernet.
CN201610327926.0A 2016-05-17 2016-05-17 A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System Active CN105846418B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610327926.0A CN105846418B (en) 2016-05-17 2016-05-17 A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610327926.0A CN105846418B (en) 2016-05-17 2016-05-17 A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System

Publications (2)

Publication Number Publication Date
CN105846418A CN105846418A (en) 2016-08-10
CN105846418B true CN105846418B (en) 2018-06-22

Family

ID=56592900

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610327926.0A Active CN105846418B (en) 2016-05-17 2016-05-17 A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System

Country Status (1)

Country Link
CN (1) CN105846418B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3869655A4 (en) * 2018-10-18 2022-07-13 NGK Insulators, Ltd. Energy management system, independent system, and independent system operation method

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106451541B (en) * 2016-10-31 2019-01-01 中国地质大学(武汉) A kind of energy control method and control system of isolated island type micro-capacitance sensor
CN106786555A (en) * 2017-01-20 2017-05-31 南京南瑞继保电气有限公司 A kind of intelligent dispatching method of household energy management system
CN107039975B (en) * 2017-05-27 2020-03-24 上海电气分布式能源科技有限公司 Energy management method for distributed energy system
CN108155672B (en) * 2017-12-22 2021-05-18 广西电网有限责任公司电力科学研究院 Micro-grid real-time optimization scheduling method and system
CN108123493A (en) * 2017-12-26 2018-06-05 国网安徽省电力有限公司安庆供电公司 It is a kind of to be applied to the micro-grid energy storage system away from land isolated island
CN109119983B (en) * 2018-09-20 2021-09-03 西南交通大学 Energy management method for electricity-hydrogen island direct-current micro-grid
CN109494883A (en) * 2018-11-30 2019-03-19 国网江苏省电力有限公司连云港供电分公司 Island microgrid panorama based on LoRa communication monitors system
CN109560577B (en) * 2018-12-04 2021-07-06 东莞理工学院 Control method and system for alternating current-direct current hybrid distributed renewable energy system
CN109586286A (en) * 2018-12-07 2019-04-05 国网辽宁省电力有限公司大连供电公司 A kind of energy-accumulating power station capacity determining methods based on Unit Combination
DE102018222753A1 (en) * 2018-12-21 2020-06-25 Siemens Aktiengesellschaft Method for operating an energy management system and electronic computing device for performing the method, computer program and data carrier
CN111585301A (en) * 2019-02-19 2020-08-25 武汉市炫能清洁能源科技有限公司 Modularization regulation and control platform to unstable input electric energy
TW202123156A (en) * 2019-12-12 2021-06-16 億鴻系統科技股份有限公司 Distributed smart charging network control method and distributed smart grid controller capable of avoiding contract capacity exceeding the agreed load
CN111817326B (en) * 2020-06-18 2021-12-14 浙江大学 Distributed energy storage SOC control and integration method under alternating current micro-grid island mode
CN111981643B (en) * 2020-08-03 2022-02-11 珠海格力电器股份有限公司 Energy regulation and control system, method and device
CN112311078B (en) * 2020-11-04 2022-03-22 华侨大学 Solar load adjusting method and device based on information fusion
CN112636334B (en) * 2020-12-10 2021-11-19 中腾微网(北京)科技有限公司 Solar-based micro-grid system
CN113708402A (en) * 2021-08-12 2021-11-26 广东海洋大学 Energy distribution management system and method for off-grid micro-grid
CN117374979B (en) * 2023-12-08 2024-03-15 浙江浙石油综合能源销售有限公司 Response capability assessment method of comprehensive energy supply station

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103236712A (en) * 2013-04-08 2013-08-07 嘉兴清源电气科技有限公司 Direct-current micro-grid system and control method thereof
CN103996075A (en) * 2014-05-08 2014-08-20 南方电网科学研究院有限责任公司 Micro-grid multi-objective optimization scheduling method considering diesel storage coordination and synergy

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009065778A (en) * 2007-09-06 2009-03-26 Tokyo Electric Power Co Inc:The Power system monitor control system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103236712A (en) * 2013-04-08 2013-08-07 嘉兴清源电气科技有限公司 Direct-current micro-grid system and control method thereof
CN103996075A (en) * 2014-05-08 2014-08-20 南方电网科学研究院有限责任公司 Micro-grid multi-objective optimization scheduling method considering diesel storage coordination and synergy

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3869655A4 (en) * 2018-10-18 2022-07-13 NGK Insulators, Ltd. Energy management system, independent system, and independent system operation method

Also Published As

Publication number Publication date
CN105846418A (en) 2016-08-10

Similar Documents

Publication Publication Date Title
CN105846418B (en) A kind of isolated island type micro-capacitance sensor Real-Time Scheduling Energy Management System
Abdalla et al. Integration of energy storage system and renewable energy sources based on artificial intelligence: An overview
CN102289566B (en) Multiple-time-scale optimized energy dispatching method for micro power grid under independent operation mode
Falahati et al. A new smart charging method for EVs for frequency control of smart grid
CN103001225B (en) MAS-based (multi-agent system) multi-microgrid energy management system simulation method
CN102324752B (en) Wind power generation-combined ordered charge and discharge coordinated control system of pure electric vehicle
CN102591278B (en) Microgrid control system having power generation and load forecast functions and microgrid control method
CN111293691A (en) Micro-grid multi-time scale optimization scheduling method based on model predictive control
US12040617B2 (en) Electric power system, server, charge-and-discharge controller, and power demand-and-supply adjustment method
CN104348189B (en) A kind of distributed power supply system
Lu et al. Multi-objective optimal scheduling of a DC micro-grid consisted of PV system and EV charging station
CN103872701A (en) Energy-storage type alternating current and direct current mixed micro-grid and control method thereof
Akshya et al. Grid integration for electric vehicle and photovoltaic panel for a smart home
Amir et al. Integration of EVs aggregator with microgrid and impact of V2G power on peak regulation
CN116780588A (en) Method of controlling a battery energy storage system of an electrical power system with a high dynamic load
CN106712082B (en) A kind of distributed generation system based on multiple agent
Wang et al. Stochastic dynamic programming based optimal energy scheduling for a hybrid fuel cell/PV/battery system under uncertainty
CN104281984A (en) Power supply method for microgrid economical operation
Mahmud et al. A day-ahead peak shaving strategy using aggregated electric vehicles
CN108462166A (en) A kind of micro-capacitance sensor spare capacity computational methods and micro-capacitance sensor regulate and control method
CN202548611U (en) Micro grid control system with functions of power generation and load prediction
CN104184141A (en) Renewable energy power generation control method and device
CN110768274B (en) Power control method and device for isolated microgrid
Sharma et al. Optimized Electric vehicle Charging and discharging with sporadic Renewable energy source
Tutkun et al. Design of a PV Powered Charging Station for PHEVs

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant