CN105781551A - 一种适用于三下矿体开采的水平条带式混合充填采矿法 - Google Patents

一种适用于三下矿体开采的水平条带式混合充填采矿法 Download PDF

Info

Publication number
CN105781551A
CN105781551A CN201610216726.8A CN201610216726A CN105781551A CN 105781551 A CN105781551 A CN 105781551A CN 201610216726 A CN201610216726 A CN 201610216726A CN 105781551 A CN105781551 A CN 105781551A
Authority
CN
China
Prior art keywords
mining
segmentation
filling
orebody
ore
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610216726.8A
Other languages
English (en)
Inventor
龚新华
王学杰
陈发吉
龙秀才
杨飏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
GUIZHOU CHENHUIDA MINING ENGINEERING DESIGN Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU CHENHUIDA MINING ENGINEERING DESIGN Co Ltd filed Critical GUIZHOU CHENHUIDA MINING ENGINEERING DESIGN Co Ltd
Priority to CN201610216726.8A priority Critical patent/CN105781551A/zh
Publication of CN105781551A publication Critical patent/CN105781551A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Abstract

本发明公开了一种适用于三下矿体开采的水平条带式混合充填采矿法,即将矿体沿倾向方向划分为若干小分段,小分段内沿走向再划分为若干矿房,同一分段内的矿房回采后用同种材料(废石、胶结)充填,不同分段内矿房用不同材料充填,最终形成水平条带式混合充填体。该采矿方法形成的水平条带式混合充填体较传统的充填采矿法具有更好的控制上覆岩体变形的效果。本发明只需在中段高度的最上面留设顶柱,其余小分段均不用留设顶柱,胶结充填的小分段矿房之间不需要留设间柱,能够实现胶结充填小分段矿体全采,只需要在废石充填的小分段矿房之间留设间柱,极大减少了矿柱的矿量,提高了矿体回收率。此外间隔废石充填相对于传统的胶结充填可节省大量的充填成本,大量减少地下掘进产生的废石,对于实现“废石不出坑”的绿色开采目标具有重要意义。

Description

一种适用于三下矿体开采的水平条带式混合充填采矿法
技术领域
本发明涉及一种适用于三下矿体开采的水平条带式混合充填采矿法,属于地下矿山开采技术领域,特别适合于倾斜中厚的三下矿体开采。
背景技术
目前,在“三下矿体”开采中广泛使用充填采矿法。充填采矿法都是通过利用充填材料对矿体开采后的空区进行充填,具有良好的控制围岩移动变形的特点,适用于对地表沉降控制要求较高的矿体开采条件。
现有的充填采矿法包括上向水平分层充填采矿法、下向水平分层充填采矿法、空场嗣后充填采矿法等。这些充填采矿法普遍存在以下不足:
1、全废石充填难以接顶,同时覆岩位移变形控制效果较差,而全胶结充填采矿法虽能够较好的控制覆岩的位移变形,但是充填工艺复杂、充填成本高昂,难以满足经济指标。
2、全胶结充填采矿法需要考虑掘进废石的处理问题,通常需要花费大量的人力物力将废石从地下运出地表堆存,同时废石堆场存在一定的安全隐患,矿山必须花费大量财力用于废石场安全维护。
3、普通空场嗣后充填采矿法通常需要留设4~6m的间柱和分段顶柱作为永久矿柱,矿石回收率低,造成了大量的矿石资源浪费。
发明内容
本发明要解决的技术问题是:提供一种适用于三下矿体开采的水平条带式混合充填采矿法,更好的控制上覆岩体变形效果,解决纯废石充填的接顶质量以及控制覆岩变形量的问题,同时解决纯胶结充填的成本问题;解决掘进废石的处理问题,避免矿山花费大量的人力物力将废石从地下运出地表堆存;提高矿石回收率,避免大量的矿石资源浪费。
本发明采用的技术方案是:将矿体沿倾向方向划分为若干10~12m的小分段,小分段内沿走向每隔15~20m再划分为若干矿房,同一分段内的矿房回采后用同种材料(废石、胶结)充填,不同分段内矿房用不同材料充填,最终形成水平条带式混合充填体。
本发明与传统的充填采矿法都是通过利用充填材料对矿体开采后的空区进行充填,具有良好的控制围岩移动变形的特点,适用于对地表沉降要求较高的三下矿体开采条件;本采矿方法与现有的矿房、矿柱间隔嗣后充填采矿法的不同之处在于:将矿体沿倾向方向划分为若干10~15m的小分段,小分段内沿走向每隔15~20m再划分为若干矿房,同一分段内的矿房回采后用同种材料(废石、胶结)充填,不同分段内矿房用不同材料充填,最终形成水平条带式混合充填体。该采矿方法形成的水平条带式混合充填体较传统的充填采矿法具有更好的控制上覆岩体变形的效果;本采矿方法只需要在100m中段高度的最上面留设4m厚的顶柱,其余小分段均不用留设顶柱,胶结充填的小分段矿房之间不需要留设间柱,能够实现胶结充填小分段矿体全采,只需要在废石充填的小分段矿房之间留设间柱,极大减少了矿柱的矿量,提高了矿体回收率。此外废石充填相对于传统的胶结充填可节省大量的充填成本,大量减少地下掘进产生的废石,对于实现“废石不出坑”的绿色开采目标具有重要意义。
具体来说,本发明的技术方案包括以下步骤:
(1)矿房结构:将倾斜中厚矿体沿倾向每100m划分一个中段,在中段内沿矿体走向每400m划分为一个盘区,盘区高为中段高度100m,中段内沿倾向再分为8个小分段,分段高度10~12m,中段顶部留设4m的顶柱;在单个小分段内沿走向每隔15~20m划分为一个矿房,矿房宽度为小分段高度;为防止充填废石侧漏,废石充填的分段中矿房之间留设3m宽的间柱,胶结充填的矿房之间不用留设间柱;
(2)采准:在盘区中央距矿体底板至少15m处布置一条盘区斜坡道,坡度10%,达到各分段标高时分别施工分段石门进入各分段矿体,然后在各小分段底部施工各分段沿脉巷道;
(3)切割:各分段沿脉巷道掘通后在盘区边界沿矿体倾向施工一条切割上山,连接上一分段沿脉巷道,该切割上山作为首个矿房(沿走向20m长)的采矿爆破自由面;
(4)回采顺序:在倾向上为至下而上,在走向上为两端向盘区中央退采;一端在回采的同时,另一端充填,依次交替进行;
(5)凿岩落矿:在分段沿脉巷道内沿矿体倾向施工上向中深孔爆破落矿;
(6)运搬:爆破崩落的矿石采用铲运机装车,由铲运机装至分段沿脉巷道中的汽车上,经分段沿脉巷道、分段石门、盘区斜坡道运至地面;
(7)水平条带式混合充填:单个矿房回采完,在分段沿脉巷道内施工一面混凝土挡墙后,即可从上分段沿脉巷道对矿房采空区进行充填,接着即可对下一个矿房回采;中段内最下一个分段采用胶结充填,第二分段废石充填,第三中段胶结充填,如此形成不同充填材料的水平条带式混合充填体。
本发明采用中深孔落矿、铲运机装矿、废石与胶结料间隔充填,与现有技术相比本发明的有益效果体现在以下方面:
1、本发明形成的水平条带式混合充填体具有更好的控制上覆岩体变形的效果,解决了纯废石充填的接顶质量以及控制覆岩变形量的问题,同时也解决了纯胶结充填的成本问题。同时水平条带式混合充填体相对于传统的胶结充填可节省大量的充填成本,大量减少地下掘进产生的废石,对于实现“废石不出坑”的绿色开采目标具有重要意义
2、本发明以废石作为一半的充填料,基本能够解决掘进废石的处理问题,避免矿山花费大量的人力物力将废石从地下运出地表堆存,对于实现“废石不出坑”的绿色开采目标具有重要意义。
3、本发明只需要在100m中段高度的最上面留设4m厚的顶柱,其余小分段均不用留设顶柱,胶结充填的小分段矿房之间不需要留设间柱,能够实现胶结充填小分段矿体全采,只需要在废石充填的小分段矿房之间留设间柱,极大减少了矿柱的矿量,提高了矿体回收率。
附图说明
图1是本发明正面A--A示意图;
图2是本发明剖面B—B示意图;
图3是本发明剖面C--C示意图;
其中1.阶段运输巷道2.混凝土充填体3.废石充填体4.充填挡墙5.沿脉分段巷道6.矿体7.分段石门8.顶柱9.斜坡道10.间柱11.切割上山12.炮眼。
具体实施方式
下面结合说明书附图对本发明进一步说明,附图中各数字标记的含义如下:1.阶段运输巷道2.混凝土充填体3.废石充填体4.充填挡墙5.沿脉分段巷道6.矿体7.分段石门8.顶柱9.斜坡道10.间柱11.切割上山12.炮眼。
1、盘区布置及构成要素
将矿体沿倾向每100m划分一个中段,在中段内沿矿体6走向每400m划分为一个盘区,盘区高为中段高度100m,中段内沿倾向再分为8各小分段,分段高度10~12m,中段顶部留设4m的顶柱8。在单个小分段内沿走向每隔15~20m划分为一个矿房,矿房宽度为小分段高度。为防止充填废石侧漏,废石充填的分段中矿房之间留设3m宽的间柱10,胶结充填的矿房之间不用留设间柱10。
2、采切布置
采准工程包括盘区斜坡道9、分段石门7和分段沿脉巷道5及切割上山11。
盘区中央距矿体底板至少15m处布置一条盘区斜坡道9,坡度10%,达到各分段标高时分别施工分段石门7进入各分段矿体,然后在各小分段底部施工各分段沿脉巷道。
各分段沿脉巷道掘通后在盘区边界沿矿体倾向施工一条切割上山11,连接上一分段沿脉巷道5,该切割上山11作为首个矿房(沿走向20m长)的采矿爆破自由面。
3、采场支护
分段沿脉巷道采用锚网支护,切割上山11视矿层顶板情况采用锚网或锚杆支护,顶板稳固时,在保证安全的前提,经矿总工程师或矿山主要负责人签字批准,确认顶板稳固时可不支护。
4、回采落矿
在倾向上为至下而上,在走向上为两端向盘区中央退采。一端在回采的同时,另一端充填,依次交替进行。
凿岩:在分段沿脉巷道内沿矿体6倾向施工上向中深孔。
落矿:采用岩石硝铵炸药,人工装药,电雷管或导爆管起爆。每次爆破一排或数排炮孔。
运搬:爆破崩落的矿石采用铲运机装车,由铲运机装至分段沿脉巷道中的汽车上,经分段沿脉巷道、分段石门7、盘区斜坡道9运至地面。
5、采场通风
爆破之后,需进行30min的通风,新鲜风流从分段沿脉巷道经采场下部进入采场,冲洗工作面后从采场上部出口进入上分段回风巷,再经回风斜坡道、风井排出地表。采场局部通风不良地段,可用局扇进行加强通风。
6、采空区处理
中段内最上面留设4m宽的连续顶柱,充填废石的分段中每个矿房留设宽3米的间柱10,胶结充填分段不需留设间柱。对采空区采用浇灌混凝土和废石进行充填支撑顶板。单个矿房回采完,在分段沿脉巷道内施工一面混凝土挡墙后(图中充填挡墙4),即可从上分段沿脉巷道对矿房采空区进行充填,接着即可对下一个矿房回采。中段内最下一个分段采用胶结充填(图中混凝土充填体2),第二分段废石充填(图中废石充填体3),第三中段胶结充填(图中混凝土充填体2),如此形成不同充填材料的水平条带式混合充填体。

Claims (2)

1.一种适用于三下矿体开采的水平条带式混合充填采矿法,包括利用充填材料对矿体开采后的空区进行充填,其特征在于:将矿体沿倾向方向划分为若干个10~12m的小分段,小分段内沿走向每隔15~20m再划分为若干矿房,同一分段内的矿房回采后用同种材料充填,不同分段内矿房用不同材料充填,最终形成水平条带式混合充填体。
2.根据权利要求1所述的一种适用于三下矿体开采的水平条带式混合充填采矿法,其特征在于,包括如下步骤:
(1)矿房结构:将倾斜中厚矿体沿倾向每100m划分一个中段,在中段内沿矿体走向每400m划分为一个盘区,盘区高为中段高度100m,中段内沿倾向再分为8个小分段,分段高度10~12m,中段顶部留设4m的顶柱;在单个小分段内沿走向每隔15~20m再划分为一个矿房,矿房宽度为小分段高度10~12m;为防止充填废石侧漏,废石充填的分段中矿房之间留设3m宽的间柱,胶结充填的矿房之间不用留设间柱;
(2)采准:在盘区中央距矿体底板至少15m处布置一条盘区斜坡道,坡度10%,达到各分段标高时分别施工分段石门进入各分段矿体,然后在各小分段底部施工各分段沿脉巷道;
(3)切割:各分段沿脉巷道掘通后在盘区边界沿矿体倾向施工一条切割上山,连接上一分段沿脉巷道,该切割上山作为首个矿房的采矿爆破自由面;
(4)回采顺序:在倾向上为至下而上,在走向上为两端向盘区中央退采,一端在回采的同时,另一端充填,依次交替进行;
(5)凿岩落矿:在分段沿脉巷道内沿矿体倾向施工上向中深孔爆破落矿;
(6)运搬:爆破崩落的矿石采用铲运机装车,由铲运机装至分段沿脉巷道中的汽车上,经分段沿脉巷道、分段石门、盘区斜坡道运至地面;
(7)水平条带式混合充填:单个矿房回采完,在分段沿脉巷道内施工一面混凝土挡墙后,即可从上分段沿脉巷道对矿房采空区进行充填,接着即可对下一个矿房回采;中段内最下一个分段采用胶结充填,第二分段废石充填,第三中段胶结充填,如此形成不同充填材料的水平条带式混合充填体。
CN201610216726.8A 2016-04-11 2016-04-11 一种适用于三下矿体开采的水平条带式混合充填采矿法 Pending CN105781551A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610216726.8A CN105781551A (zh) 2016-04-11 2016-04-11 一种适用于三下矿体开采的水平条带式混合充填采矿法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610216726.8A CN105781551A (zh) 2016-04-11 2016-04-11 一种适用于三下矿体开采的水平条带式混合充填采矿法

Publications (1)

Publication Number Publication Date
CN105781551A true CN105781551A (zh) 2016-07-20

Family

ID=56395046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610216726.8A Pending CN105781551A (zh) 2016-04-11 2016-04-11 一种适用于三下矿体开采的水平条带式混合充填采矿法

Country Status (1)

Country Link
CN (1) CN105781551A (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894817A (zh) * 2017-03-03 2017-06-27 中南大学 一种机械化上向分层楔合混合充填采矿法
CN109505604A (zh) * 2018-09-25 2019-03-22 南京银茂铅锌矿业有限公司 应用于上向分层充填采矿法采场的斜坡道布置方法
CN110486082A (zh) * 2019-09-09 2019-11-22 河北充填采矿技术有限公司 一种采空区不同材料交替充填的方法
CN111322109A (zh) * 2020-04-26 2020-06-23 锡林郭勒盟山金阿尔哈达矿业有限公司 一种废石尾砂协同胶结充填的方法
CN111894592A (zh) * 2020-08-05 2020-11-06 长沙矿山研究院有限责任公司 壁柱式上向水平分层充填采矿法
WO2021068691A1 (zh) * 2019-10-09 2021-04-15 巨峰 一种煤矿强弱强全采全充方法
CN113700482A (zh) * 2021-10-29 2021-11-26 矿冶科技集团有限公司 采矿方法
CN113931630A (zh) * 2021-12-17 2022-01-14 北京科技大学 一种深部金属矿床的机械化无废开采方法
CN116335665A (zh) * 2023-05-30 2023-06-27 北京科技大学 构筑护顶层回采水体下近水平薄矿体的采矿方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5314268A (en) * 1993-01-13 1994-05-24 Jennmar Corporation Non-metallic reinforcing rod and method of use in supporting a rock formation
US5368369A (en) * 1993-03-23 1994-11-29 Council Of Scientific & Industrial Research Equipment useful for winning ores particularly coal in longwall mining
CN102434160A (zh) * 2011-11-23 2012-05-02 彭康 两翼预切割中央无房柱式联合横巷连续分段充填采矿法
CN102953733A (zh) * 2011-08-19 2013-03-06 彭康 中央脉外房柱式联合横巷两端脉内连续分段充填采矿法
CN103244123A (zh) * 2013-05-14 2013-08-14 贵州晨辉达矿业工程设计有限公司 一种急倾斜中厚矿体采矿方法
CN104100270A (zh) * 2014-06-13 2014-10-15 贵州开磷(集团)有限责任公司 一种缓倾斜矿脉无轨开采方法
CN104806244A (zh) * 2015-04-03 2015-07-29 东北大学 一种倾斜中厚矿体充填采矿方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5314268A (en) * 1993-01-13 1994-05-24 Jennmar Corporation Non-metallic reinforcing rod and method of use in supporting a rock formation
US5368369A (en) * 1993-03-23 1994-11-29 Council Of Scientific & Industrial Research Equipment useful for winning ores particularly coal in longwall mining
CN102953733A (zh) * 2011-08-19 2013-03-06 彭康 中央脉外房柱式联合横巷两端脉内连续分段充填采矿法
CN102434160A (zh) * 2011-11-23 2012-05-02 彭康 两翼预切割中央无房柱式联合横巷连续分段充填采矿法
CN103244123A (zh) * 2013-05-14 2013-08-14 贵州晨辉达矿业工程设计有限公司 一种急倾斜中厚矿体采矿方法
CN104100270A (zh) * 2014-06-13 2014-10-15 贵州开磷(集团)有限责任公司 一种缓倾斜矿脉无轨开采方法
CN104806244A (zh) * 2015-04-03 2015-07-29 东北大学 一种倾斜中厚矿体充填采矿方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨飏等: "《河床下矿体分段空场嗣后充填法开采研究》", 《矿业研究与开发》 *
陈发吉等: "《脉内采准中深孔落矿嗣后充填法在沙坝土矿的应用》", 《现代矿业》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894817A (zh) * 2017-03-03 2017-06-27 中南大学 一种机械化上向分层楔合混合充填采矿法
CN109505604A (zh) * 2018-09-25 2019-03-22 南京银茂铅锌矿业有限公司 应用于上向分层充填采矿法采场的斜坡道布置方法
CN109505604B (zh) * 2018-09-25 2020-07-07 南京银茂铅锌矿业有限公司 应用于上向分层充填采矿法采场的斜坡道布置方法
CN110486082A (zh) * 2019-09-09 2019-11-22 河北充填采矿技术有限公司 一种采空区不同材料交替充填的方法
WO2021068691A1 (zh) * 2019-10-09 2021-04-15 巨峰 一种煤矿强弱强全采全充方法
CN111322109A (zh) * 2020-04-26 2020-06-23 锡林郭勒盟山金阿尔哈达矿业有限公司 一种废石尾砂协同胶结充填的方法
CN111894592A (zh) * 2020-08-05 2020-11-06 长沙矿山研究院有限责任公司 壁柱式上向水平分层充填采矿法
CN113700482A (zh) * 2021-10-29 2021-11-26 矿冶科技集团有限公司 采矿方法
CN113931630A (zh) * 2021-12-17 2022-01-14 北京科技大学 一种深部金属矿床的机械化无废开采方法
CN113931630B (zh) * 2021-12-17 2022-03-11 北京科技大学 一种深部金属矿床的机械化无废开采方法
CN116335665A (zh) * 2023-05-30 2023-06-27 北京科技大学 构筑护顶层回采水体下近水平薄矿体的采矿方法
CN116335665B (zh) * 2023-05-30 2023-08-01 北京科技大学 构筑护顶层回采水体下近水平薄矿体的采矿方法

Similar Documents

Publication Publication Date Title
CN105781551A (zh) 一种适用于三下矿体开采的水平条带式混合充填采矿法
CN105587318B (zh) 一种缓倾斜平行中厚矿体群连续回采的充填采矿法
CN110778316B (zh) 一种采用拱弧形顶柱结构的分段凿岩阶段空场嗣后充填采矿法
CN102678121B (zh) 无盘区中深孔留矿分层控顶嗣后充填采矿法
CN102562065B (zh) 一种分段空场嗣后充填采矿方法
CN103527200B (zh) 无底柱分段菱形矿房嗣后充填采矿法
CN111828007B (zh) 一种地下矿山采空区遗留间柱的回采方法
CN103362510B (zh) 分段凿岩并段出矿分段矿房采矿法
CN103590831A (zh) 一种缓倾斜薄-中厚矿体的新型采矿方法
CN105041314A (zh) 一种深部嗣后回采矿房—分层回采矿柱的联合采矿法
CN102168579A (zh) 中厚倾斜破碎矿体脉内采准无间柱连续分段充填法
CN110259451A (zh) 一种缓倾斜中厚矿体预控顶高效采矿方法
CN104632220B (zh) 缓倾斜中厚矿体条柱再造采场结构尺寸可调可控采矿方法
CN108661646A (zh) 一种假顶房柱式留矿嗣后充填采矿法
CN104018836A (zh) 一种有不稳固假顶倾斜中厚矿体的分采方法
CN109057798B (zh) 一种适用于缓倾斜磷矿床的壁式充填采矿方法
CN111706328B (zh) 一种用于充填法处理采空区遗留间柱的开采方法
CN105422102B (zh) 一种垂直中深孔落矿小分段进路充填采矿法
CN109505606B (zh) 一种预控顶机械化分段空场嗣后充填采矿方法
CN108625855B (zh) 一种充填体下的采矿方法
CN106761745A (zh) 脉外分段空场采矿法
CN104453900A (zh) 一种近水平矿体充填采矿方法
CN112727463A (zh) 一种软弱岩层条件下急倾斜薄矿脉的机械化充填采矿方法
CN104265294A (zh) 大倾角煤层炮采面无煤柱开采技术
CN113153303B (zh) 一种用于急倾斜薄矿体的下向单一进路胶结充填采矿方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180214

Address after: Jinzhu Road Lake District 550081 Guizhou city of Guiyang province No. 2

Applicant after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550014 room B408 room B408 room for the standard workshop of Jinyang science and Technology Industrial Park, Guiyang state high tech Zone, Guizhou Province

Applicant before: Guizhou Chenhuida Mining Engineering Design Co., Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20160720