CN105756245A - Method for mounting curtain wall skeleton and structural beam - Google Patents

Method for mounting curtain wall skeleton and structural beam Download PDF

Info

Publication number
CN105756245A
CN105756245A CN201410788504.4A CN201410788504A CN105756245A CN 105756245 A CN105756245 A CN 105756245A CN 201410788504 A CN201410788504 A CN 201410788504A CN 105756245 A CN105756245 A CN 105756245A
Authority
CN
China
Prior art keywords
transmission rod
fixed structure
curtain wall
structural beam
oblong hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410788504.4A
Other languages
Chinese (zh)
Other versions
CN105756245B (en
Inventor
张士元
李博群
魏万姝
王成波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing New Building Material Group Co Ltd
Original Assignee
Beijing New Building Material Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing New Building Material Group Co Ltd filed Critical Beijing New Building Material Group Co Ltd
Priority to CN201410788504.4A priority Critical patent/CN105756245B/en
Publication of CN105756245A publication Critical patent/CN105756245A/en
Application granted granted Critical
Publication of CN105756245B publication Critical patent/CN105756245B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

本发明涉及一种幕墙骨架与结构梁的安装方法,包括如下步骤:根据结构梁上的测量放线将第二固定结构安装在结构梁的上表面,将第四固定结构安装在结构梁的下表面;将第一固定结构安装在幕墙骨架靠下位置,将第三固定结构安装在幕墙骨架靠上位置;吊装幕墙骨架到预定位置,第一固定结构与第二固定结构通过三维六度移动调整相对位置并使第三固定结构移动至第四固定结构安装位置后,固定第一固定结构与第二固定结构;第三固定结构和第四固定结构平面相对位置微调,微调结束后固定第三固定结构和第四固定结构。此安装方法可实现安装过程中幕墙骨架和结构梁的相对位置进行调节,从而满足了幕墙骨架与结构梁节点的安装精度并实现安装完成后良好的抗震性能。

The invention relates to a method for installing a curtain wall skeleton and a structural beam, comprising the following steps: installing a second fixed structure on the upper surface of the structural beam according to the measurement setting out on the structural beam, and installing a fourth fixed structure on the lower surface of the structural beam Surface; install the first fixed structure at the lower position of the curtain wall skeleton, install the third fixed structure at the upper position of the curtain wall skeleton; hoist the curtain wall skeleton to the predetermined position, and adjust the first fixed structure and the second fixed structure through three-dimensional six-degree movement After moving the third fixed structure to the installation position of the fourth fixed structure, fix the first fixed structure and the second fixed structure; fine-tune the relative position of the third fixed structure and the fourth fixed structure, and fix the third fixed structure after fine-tuning structure and a fourth fixed structure. This installation method can realize the adjustment of the relative position of the curtain wall skeleton and the structural beam during the installation process, so as to meet the installation accuracy of the curtain wall skeleton and the structural beam joint and achieve good seismic performance after installation.

Description

幕墙骨架与结构梁的安装方法Installation method of curtain wall skeleton and structural beam

技术领域technical field

本发明涉及一种建筑结构施工工程领域,特别是涉及一种预制的幕墙骨架和结构梁之间的连接施工工艺。The invention relates to the field of building structure construction engineering, in particular to a connection construction process between a prefabricated curtain wall skeleton and a structural beam.

背景技术Background technique

FK轻钢幕墙是单元式幕墙的一种,主要构件均在工厂里预制组装,幕墙的高度一般为楼层高度,能直接挂在楼层的预埋件上。施工的时候从楼层下部开始依次往上进行,能够配合楼层主体土建进行同步施工,大大缩短了施工工期。具有非常明显的优势。FK light steel curtain wall is a kind of unitized curtain wall. The main components are prefabricated and assembled in the factory. The height of the curtain wall is generally the height of the floor and can be directly hung on the embedded parts of the floor. During the construction, it starts from the lower part of the floor and proceeds upwards sequentially, which can be carried out synchronously with the main civil work of the floor, greatly shortening the construction period. has very obvious advantages.

但目前的FK轻钢幕墙节点安装方法,存在工艺复杂,安装精度较差的技术问题。However, the current installation method of FK light steel curtain wall nodes has the technical problems of complicated process and poor installation accuracy.

发明内容Contents of the invention

本发明提供一种幕墙骨架与结构梁的安装方法,其目的是通过在幕墙与结构梁连接过程中对幕墙骨架和结构梁的相对位置进行调节,从而满足幕墙骨架与结构梁节点的安装精度以及安装完成后良好的抗震性能。The invention provides a method for installing a curtain wall skeleton and a structural beam, the purpose of which is to adjust the relative position of the curtain wall skeleton and the structural beam during the connection process of the curtain wall and the structural beam, thereby satisfying the installation accuracy of the joint of the curtain wall skeleton and the structural beam and Good anti-seismic performance after installation.

为了实现上述发明目的,本发明采取的技术方案如下:In order to realize the foregoing invention object, the technical scheme that the present invention takes is as follows:

一种幕墙骨架与结构梁的安装方法,包括如下步骤:根据在结构梁上的测量放线将第二固定结构安装在结构梁的上表面,将第四固定结构安装在结构梁的下表面;将第一固定结构安装在幕墙骨架靠下位置,将第三固定结构安装在幕墙骨架靠上位置;吊装幕墙骨架到预定位置,第一固定结构与第二固定结构通过三维六度移动调整相对位置并使第三固定结构移动至第四固定结构安装位置后,固定第一固定结构与第二固定结构;第三固定结构和第四固定结构平面相对位置微调,微调结束后固定第三固定结构和第四固定结构。A method for installing a curtain wall skeleton and a structural beam, comprising the following steps: installing a second fixed structure on the upper surface of the structural beam according to the measurement and setting out on the structural beam, and installing a fourth fixed structure on the lower surface of the structural beam; Install the first fixed structure at the lower position of the curtain wall skeleton, install the third fixed structure at the upper position of the curtain wall skeleton; hoist the curtain wall skeleton to the predetermined position, and adjust the relative position of the first fixed structure and the second fixed structure through three-dimensional six-degree movement After the third fixed structure is moved to the installation position of the fourth fixed structure, the first fixed structure and the second fixed structure are fixed; the relative positions of the third fixed structure and the fourth fixed structure are fine-tuned, and the third fixed structure and the fourth fixed structure are fixed after the fine-tuning is completed. The fourth fixed structure.

进一步地,第一固定结构包括第一十字件和第一传动杆,所述第一十字件上有第一通孔,当第一固定结构安装在幕墙骨架靠下位置时,第一十字件与幕墙骨架固定,所述第一传动杆上端部与所述第一通孔螺纹连接。Further, the first fixing structure includes a first cross piece and a first transmission rod, the first cross piece has a first through hole, when the first fixing structure is installed at the lower position of the curtain wall skeleton, the first cross piece and the first transmission rod The curtain wall frame is fixed, and the upper end of the first transmission rod is screwed into the first through hole.

进一步地,所述第二固定结构包括槽型构件,所述槽型构件的双肢与所述结构梁焊接,所述槽型构件的背板上开有供第一传动杆穿过的第二通孔,吊装幕墙骨架到预定位置后,调整所述第一传动杆的下端部与所述第二通孔对正,所述第一传动杆下端部依次穿过位于所述槽型构件顶面的第一螺母、与所述槽型构件上开有对应第三通孔的垫板以及所述槽型构件上的第二通孔,通过上下移动所述第一传动杆调整所述墙体骨架的上下位置,调整结束,使所述第一传动杆的下端部穿过与所述槽型构件上开有对应第四通孔的垫圈,并将第一传动杆的下端部通过所述用第二螺母固定,同时拧紧第一螺母。Further, the second fixing structure includes a channel member, the two limbs of the channel member are welded to the structural beam, and the back plate of the channel member is provided with a second hole through which the first transmission rod passes. Through hole, after hoisting the curtain wall skeleton to the predetermined position, adjust the lower end of the first transmission rod to align with the second through hole, and the lower end of the first transmission rod passes through the top surface of the channel member in turn The first nut, the backing plate with the corresponding third through hole on the channel member and the second through hole on the channel member, adjust the wall skeleton by moving the first transmission rod up and down After the adjustment is completed, the lower end of the first transmission rod passes through the washer corresponding to the fourth through hole on the channel member, and the lower end of the first transmission rod passes through the second The second nut is fixed, and the first nut is tightened at the same time.

进一步地,所述槽型构件上开有第一长圆孔,所述垫板上开有第二长圆孔,所述第一长圆孔和所述第二长圆孔中心重合,长轴相互垂直,所述第一长圆孔和所述第二长圆孔通过第三传动杆连接形成所述第一固定结构和所述第二固定结构位置调整过程中的随动结构,其随着所述第一传动杆的平面移动而移动。Further, the channel member is provided with a first oblong hole, and the backing plate is provided with a second oblong hole, the centers of the first oblong hole and the second oblong hole are coincident, and the major axes are perpendicular to each other, so The first oblong hole and the second oblong hole are connected by a third transmission rod to form a follow-up structure during the position adjustment process of the first fixed structure and the second fixed structure, which follows the first transmission rod The plane moves while moving.

进一步地,第三固定结构包括第二十字件和第二传动杆,所述第二十字件与所述墙体骨架固定,所述第二传动杆一端与所述第二十字件固定连接,另一端向外延伸。Further, the third fixing structure includes a second cross member and a second transmission rod, the second cross member is fixed to the wall frame, one end of the second transmission rod is fixedly connected to the second cross member, and One end extends outward.

进一步地,所述第四固定结构包括槽型件和角钢,所述槽型件的双肢与所述结构梁底面固定,所述角钢的一肢与所述槽型件的背板采用滑动连接结构连接,所述角钢的另一肢上开设有供所述第二传动杆上下移动的第四长圆孔,当所述第二传动杆端部伸入所述第四长圆孔并调整至合适位置,通过第三螺母固定所述第二传动杆端部。Further, the fourth fixing structure includes a channel-shaped piece and an angle steel, the two legs of the channel-shaped piece are fixed to the bottom surface of the structural beam, and one leg of the angle-shaped steel is slidingly connected to the back plate of the channel-shaped piece Structural connection, the other limb of the angle steel is provided with a fourth oblong hole for the second transmission rod to move up and down, when the end of the second transmission rod extends into the fourth oblong hole and adjusted to a suitable position , fixing the end of the second transmission rod through a third nut.

进一步地,所述滑动连接结构包括开设在所述槽型件背板上的第三长圆孔、开设在所述角钢一肢上的第五长圆孔和第四传动杆,所述第三长圆孔和所述第五长圆孔中心重合,长轴相互垂直,所述第四传动杆插入所述第三长圆孔和所述第五长圆孔内,并随着所述第二传动杆的平面移动而移动。Further, the sliding connection structure includes a third oblong hole on the back plate of the channel member, a fifth oblong hole and a fourth transmission rod on one limb of the angle steel, and the third oblong hole Coinciding with the center of the fifth oblong hole, the long axes are perpendicular to each other, the fourth transmission rod is inserted into the third oblong hole and the fifth oblong hole, and moves along with the plane movement of the second transmission rod move.

进一步地,所述第一固定结构和第三固定结构轴线之间的距离与相邻层两根结构梁之间的轴线之间的垂直距离相等。Further, the distance between the axes of the first fixed structure and the third fixed structure is equal to the vertical distance between the axes of two structural beams on adjacent floors.

进一步地,所述结构梁腰部焊接有支撑牛腿,所述支撑牛腿与所述结构梁等高。Further, a supporting corbel is welded at the waist of the structural beam, and the supporting corbel is at the same height as the structural beam.

本发明和现有技术相比,具有如下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

本方法通过上下节点之间的联动,实现对安装位置的快速调整,确保了安装精度,且安装完成后,节点有微小的三维六度移动余地,当结构遭遇地震等振动作用时,具有良好的吸能能力。This method realizes the rapid adjustment of the installation position through the linkage between the upper and lower nodes, ensuring the installation accuracy, and after the installation is completed, the nodes have a small room for three-dimensional and six-degree movement. When the structure encounters vibrations such as earthquakes, it has good performance. Energy absorption capacity.

另外,本安装方法采用的均为可拆卸连接,更好的发挥了装配式结构拆装方便的优势。In addition, this installation method adopts detachable connections, which better exerts the advantages of convenient disassembly and assembly of the assembled structure.

附图说明Description of drawings

图1是采用本发明所述安装方法形成的幕墙骨架和结构梁之间的连接结构。Fig. 1 is the connection structure between the curtain wall skeleton and the structural beam formed by the installation method of the present invention.

图2是幕墙骨架俯视图。Figure 2 is a top view of the curtain wall skeleton.

图3是第一十字件4详图。FIG. 3 is a detailed view of the first cross member 4 .

图4是垫圈详图。Figure 4 is a detailed view of the gasket.

图5是垫板俯视图。Figure 5 is a plan view of the backing plate.

图6是槽型构件11俯视图。FIG. 6 is a top view of the channel member 11 .

图7是垫板7与槽型构件11叠合俯视图。FIG. 7 is a superimposed top view of the backing plate 7 and the channel member 11 .

图8是角钢10展开图。FIG. 8 is an expanded view of the angle steel 10 .

图9是槽型件13俯视图。FIG. 9 is a top view of the channel member 13 .

图10是槽型件13和角钢10叠合图。FIG. 10 is a superimposed view of the channel member 13 and the angle steel 10 .

图11是第二十字件8立体图。FIG. 11 is a perspective view of the second cross member 8 .

附图标记:1-上幕墙骨架、2-下幕墙骨架、3-结构梁、4-第一十字件、401-第一十字件本体、402-连接部、403-第一通孔、5-第一传动杆、6-螺栓、7-垫板、701-第三通孔、702-第二长圆孔、8-第二十字件、801-第二十字件本体、802-安装孔、9-垫圈、901-第四通孔、10-角钢、1001-第四长圆孔、1002-第五长圆孔、11-槽型构件、1101--第二通孔、1102-第一长圆孔、12-第二传动杆、13-槽型件、1301-第三长圆孔、14-第三螺母、15-第二螺母、16-第一螺母、17-第三传动杆、18-第四传动杆。Reference signs: 1-upper curtain wall skeleton, 2-lower curtain wall skeleton, 3-structural beam, 4-first cross member, 401-first cross member body, 402-connecting part, 403-first through hole, 5- The first transmission rod, 6-bolt, 7-backing plate, 701-the third through hole, 702-the second oblong hole, 8-the second cross piece, 801-the second cross piece body, 802-installation hole, 9- Washer, 901-the fourth through hole, 10-angle steel, 1001-the fourth oblong hole, 1002-the fifth oblong hole, 11-channel member, 1101-the second through hole, 1102-the first oblong hole, 12- The second transmission rod, 13-slotted part, 1301-the third oblong hole, 14-the third nut, 15-the second nut, 16-the first nut, 17-the third transmission rod, 18-the fourth transmission rod.

具体实施方式detailed description

为使本发明的发明目的、技术方案和有益效果更加清楚明了,下面结合附图对本发明的实施例进行说明,需要说明的是,在不冲突的情况下,本申请中的实施例和实施例中的特征可以相互任意组合。In order to make the purpose of the invention, technical solutions and beneficial effects of the present invention clearer, the embodiments of the present invention will be described below in conjunction with the accompanying drawings. The features in can be combined arbitrarily with each other.

本申请是针对图1所示幕墙骨架与结构梁的连接结构提出的安装方法,如图1所示,幕墙骨架与结构梁的连接结构,参见图1和图3,本图中,仅示出了一根结构梁3的上下两个节点。实际施工时,上下两个节点位于相邻两层结构梁的上表面及下表面。图1中的连接结构包括与上幕墙骨架1下部固定连接的第一固定结构,与下幕墙骨架2上部的第三固定结构,与结构梁3上表面固定的第二固定结构,与结构梁3下表面固定的第四固定结构。安装完成后,第一固定结构和第二固定结构连接形成结构梁和幕墙骨架的下连接节点,第三固定结构和第四固定结构连接形成结构梁和幕墙骨架的上连接节点。This application is an installation method proposed for the connection structure between the curtain wall skeleton and the structural beam shown in Figure 1. As shown in Figure 1, the connection structure between the curtain wall skeleton and the structural beam is shown in Figures 1 and 3. In this figure, only The upper and lower nodes of a structural beam 3 are established. During actual construction, the upper and lower nodes are located on the upper and lower surfaces of the adjacent two-story structural beams. The connecting structure in Fig. 1 includes the first fixed structure fixedly connected with the lower part of the upper curtain wall skeleton 1, the third fixed structure connected with the upper part of the lower curtain wall skeleton 2, the second fixed structure fixed with the upper surface of the structural beam 3, and the second fixed structure connected with the structural beam 3 The fourth fixing structure fixed on the lower surface. After the installation is completed, the first fixed structure and the second fixed structure are connected to form the lower connection node of the structural beam and the curtain wall skeleton, and the third fixed structure and the fourth fixed structure are connected to form an upper connection node of the structural beam and the curtain wall skeleton.

第一固定结构参见图1和图3,第一固定结构包括第一十字件4和第一传动杆5,第一十字件4上有第一通孔403,第一通孔403的内壁有内螺纹,第一传动杆5上端部有外螺纹,第一通孔403与第一传动杆5上端部螺纹连接,第一传动杆5向下延伸至第二连接结构。Referring to Fig. 1 and Fig. 3 for the first fixed structure, the first fixed structure includes a first cross member 4 and a first transmission rod 5, a first through hole 403 is arranged on the first cross member 4, and the inner wall of the first through hole 403 has an inner wall. Thread, the upper end of the first transmission rod 5 has external threads, the first through hole 403 is threadedly connected with the upper end of the first transmission rod 5, and the first transmission rod 5 extends downward to the second connection structure.

第二固定结构参见图1、图4、图5和图6,第二固定结构包括槽型构件11,槽型构件11的双肢与结构梁3顶面焊接,槽型构件11的背板上开有供第一传动杆5下端部穿过的第二通孔1101参见图6,(第二通孔1101的直径比第一传动杆5的直径大,第一传动杆5可在第二通孔1101内上下左右前后移动)。安装时,第一传动5下端部依次穿过位于槽型构件11顶面的第一螺母16、与槽型构件11上开有对应第三通孔701(此第三通孔701直径与第一传动杆5的直径相匹配)的垫板7,垫板结构参见图5,槽型构件11上的第二通孔1101,槽型构件11的结构参见图6。安装时为了实现平面随动,参见图1、图5、图6和图7,槽型构件11上开有对称开有两个第一长圆孔1102,垫板7上开有与第一长圆孔1102对应的两个第二长圆孔702,第一长圆孔1102和第二长圆孔702中心重合,长轴相互垂直,第一长圆孔1102和第二长圆孔702通过第三传动杆17连接。当第一传动杆5在第二通孔1101内前后左右平面移动时,带动第三传动杆17在第一长圆孔1102及第二长圆孔702移动实现同步调整。Referring to Fig. 1, Fig. 4, Fig. 5 and Fig. 6 for the second fixed structure, the second fixed structure includes a channel member 11, the two limbs of the channel member 11 are welded to the top surface of the structural beam 3, and the back plate of the channel member 11 Have the second through hole 1101 that passes through for the first transmission rod 5 lower ends see Fig. Move up, down, left, right, back and forth in the hole 1101). During installation, the lower end of the first transmission 5 passes through the first nut 16 positioned at the top surface of the channel member 11 successively, and has a corresponding third through hole 701 on the channel member 11 (the diameter of the third through hole 701 is the same as that of the first through hole 701). The diameter of the transmission rod 5 matches) the backing plate 7, the backing plate structure is shown in FIG. In order to realize plane follow-up during installation, referring to Fig. 1, Fig. 5, Fig. 6 and Fig. 7, there are two first oblong holes 1102 symmetrically arranged on the channel member 11, and there are two first oblong holes 1102 on the backing plate 7, which are consistent with the first oblong holes. 1102 corresponds to the two second oblong holes 702 , the centers of the first oblong hole 1102 and the second oblong hole 702 coincide, and the long axes are perpendicular to each other. The first oblong hole 1102 and the second oblong hole 702 are connected by the third transmission rod 17 . When the first transmission rod 5 moves forward, backward, left and right in the second through hole 1101 , it drives the third transmission rod 17 to move in the first oblong hole 1102 and the second oblong hole 702 to realize synchronous adjustment.

当上述前后左右上下调整都完成后,第一传动杆5的下端部穿过垫圈9上的第四通孔901,第一传动杆5的下端部通过用第二螺母15固定,同时拧紧垫板7顶面的第一螺母16。When the above-mentioned front, rear, left, right, up and down adjustments are all completed, the lower end of the first transmission rod 5 passes through the fourth through hole 901 on the washer 9, and the lower end of the first transmission rod 5 is fixed by the second nut 15, and the backing plate is tightened at the same time 7 the first nut 16 on the top surface.

垫圈9结构参见图4,垫圈9为圆形垫片,第四通孔901与槽型构件11上的第二通孔1101对应,但第四通孔901的直径与第一传动杆5的直径相等。Referring to Figure 4 for the structure of the gasket 9, the gasket 9 is a circular gasket, the fourth through hole 901 corresponds to the second through hole 1101 on the channel member 11, but the diameter of the fourth through hole 901 is the same as the diameter of the first transmission rod 5 equal.

参见图1,第三固定结构包括第二十字件8和第二传动杆12,第二十字件8与墙体骨架固定,第二传动杆12一端与第二十字件8固定连接,另一端向外延伸至第四固定结构。Referring to Fig. 1, the third fixing structure includes a second cross member 8 and a second transmission rod 12, the second cross member 8 is fixed to the wall skeleton, one end of the second transmission rod 12 is fixedly connected to the second cross member 8, and the other end is connected to the second cross member 8. extending outward to the fourth fixing structure.

参见图1,第四固定结构包括槽型件13和角钢10,槽型件13的双肢与结构梁3的底面固定,角钢10的一肢与槽型件13的背板通过滑动连接结构,角钢10的另一肢上开设有供第二传动杆12上下移动的第五长圆孔1001。通过第二传动杆12在第五长圆孔1001内上下移动实现上下位置的调整,上下位置调整完成后,采用第三螺母14固定第二传动杆12的外伸端。然后通过滑动连接结构调整水平位置。所述的滑动连接结构包括开设在槽型件13背板上的第三长圆孔1301、开设在角钢10一肢上的第四长圆孔1001和第四传动杆18。第三长圆孔1301和第五长圆孔1002的相对位置参见图10,第三长圆孔1301和第五长圆孔1002中心重合,长轴相互垂直,第四传动杆18插入第三长圆孔1301和第五长圆孔1002内,并随着第二传动杆12的平面移动而移动。Referring to Fig. 1, the fourth fixed structure includes a channel member 13 and an angle steel 10, the two limbs of the channel member 13 are fixed to the bottom surface of the structural beam 3, and one limb of the angle steel 10 is connected to the back plate of the channel member 13 through a sliding connection structure, The other limb of the angle steel 10 is provided with a fifth oblong hole 1001 for the second transmission rod 12 to move up and down. The vertical position adjustment is realized by the second transmission rod 12 moving up and down in the fifth oblong hole 1001 . After the vertical position adjustment is completed, the third nut 14 is used to fix the extended end of the second transmission rod 12 . Then adjust the horizontal position through the sliding connection structure. The sliding connection structure includes a third oblong hole 1301 provided on the back plate of the channel member 13 , a fourth oblong hole 1001 provided in one limb of the angle steel 10 and a fourth transmission rod 18 . The relative position of the 3rd oblong hole 1301 and the 5th oblong hole 1002 is referring to Fig. 10, and the center of the 3rd oblong hole 1301 and the 5th oblong hole 1002 are coincident, and long axis is perpendicular to each other, and the 4th transmission rod 18 is inserted into the 3rd oblong hole 1301 and the 5th oblong hole 1002. Five oblong holes 1002, and move along with the planar movement of the second transmission rod 12.

为了更清楚的阐述上述结构的具体结构,下面分别举例说明幕墙骨架、第一十字件4和第二十字件8的具体结构形式,此处给出的具体结构仅为了清楚阐明本申请的发明思想,本申请的保护范围不受此阐述限制。In order to illustrate the specific structure of the above-mentioned structure more clearly, the specific structural forms of the curtain wall skeleton, the first cross piece 4 and the second cross piece 8 are illustrated respectively below, and the specific structure given here is only to clearly illustrate the inventive concept of the present application , the protection scope of the present application is not limited by this description.

幕墙骨架参见图2,本实施例中的幕墙骨架包括横向龙骨101、纵向龙骨102、边龙骨104和加强龙骨103,横向龙骨101和纵向龙骨102交错设置,边龙骨104位于横向龙骨101和纵向龙骨102边缘,加强龙骨103设置在横向龙骨101或纵向龙骨102与边龙骨104之间,横向龙骨101、纵向龙骨102、边龙骨104和加强龙骨103形成的夹角处通过角钢连接件105连接,本图中,横向龙骨101采用方钢、纵向龙骨102采用方钢、边龙骨104采用C型钢和加强龙骨103采用C型钢,上述龙骨所选用型材仅为说明技术方案进行的列举,龙骨选材根据实际工程需要选择即可。Referring to Figure 2 for the curtain wall framework, the curtain wall framework in this embodiment includes a transverse keel 101, a longitudinal keel 102, a side keel 104 and a reinforcement keel 103, the transverse keel 101 and the longitudinal keel 102 are arranged alternately, and the side keel 104 is located between the transverse keel 101 and the longitudinal keel 102 edge, the reinforcing keel 103 is arranged between the transverse keel 101 or the longitudinal keel 102 and the side keel 104, and the angle formed by the transverse keel 101, the longitudinal keel 102, the side keel 104 and the reinforcing keel 103 is connected by an angle steel connector 105. In the figure, the horizontal keel 101 is made of square steel, the longitudinal keel 102 is made of square steel, the side keel 104 is made of C-shaped steel, and the reinforced keel 103 is made of C-shaped steel. Just need to choose.

第一十字件4参见图3,第一固定结构为第一十字件4,第一十字件4包括第一十字件本体401,第一十字件本体401的一面带有通长卡槽(通长卡槽卡在横向龙骨101和纵向龙骨102交接处,并通过螺栓6固定参见图2),第一十字件本体401的背面底部向外延伸形成平面连接部402,连接部402上开设有第一通孔403。Referring to Fig. 3 for the first cross piece 4, the first fixed structure is the first cross piece 4, the first cross piece 4 includes a first cross piece body 401, and one side of the first cross piece body 401 has a full-length draw groove (full length The card slot is stuck at the junction of the transverse keel 101 and the longitudinal keel 102, and is fixed by bolts 6 (see Fig. 2). through hole 403 .

第二十字件8参见图11,第二十字件8包括第二十字件本体801,第二十字件本体801的一面带有通长卡槽,其背面中心部位开有安装孔802。Referring to FIG. 11 for the second cross 8 , the second cross 8 includes a second cross body 801 , one side of the second cross body 801 has a long slot, and a mounting hole 802 is opened in the center of the back.

上述幕墙骨架与结构梁连接结构的安装方法,包括如下步骤:The installation method of the above-mentioned curtain wall skeleton and the connection structure of the structural beam includes the following steps:

步骤一、根据在结构梁3上的测量放线将第二固定结构安装在结构梁3的上表面,将第四固定结构安装在结构梁3的下表面;第二固定结构包括槽型构件11,槽型构件11的双肢与结构梁3焊接。第四固定结构包括槽型件13和角钢10,槽型件13的双肢与结构梁3底面固定,角钢10的一肢与槽型件13的背板采用滑动连接结构连接。Step 1. Install the second fixed structure on the upper surface of the structural beam 3 according to the measurement setting-out on the structural beam 3, and install the fourth fixed structure on the lower surface of the structural beam 3; the second fixed structure includes a channel member 11 , the two limbs of the channel member 11 are welded to the structural beam 3 . The fourth fixing structure includes a channel member 13 and an angle steel 10, the two limbs of the channel member 13 are fixed to the bottom surface of the structural beam 3, and one limb of the angle steel 10 is connected to the back plate of the channel member 13 by a sliding connection structure.

步骤二、将第一固定结构安装在幕墙骨架靠下位置,将第三固定结构安装在幕墙骨架靠上位置;第一固定结构包括第一十字件4和第一传动杆5,第一十字件4上有供第一传动杆5上下移动的第一通孔,在第一固定结构安装在幕墙骨架靠下位置时,第一十字件4上的卡槽卡在幕墙骨架的横向龙骨101和纵向龙骨102交接处,并通过螺栓6固定,并将第一传动杆5上端部与第一十字件4上的第一通孔螺纹连接,第一传动杆5竖向延伸。第三固定结构包括第二十字件8和第二传动杆12,第二十字件8的卡槽卡在幕墙骨架的横向龙骨101和纵向龙骨102交接处,并通过螺栓6固定,第二传动杆12一端与第二十字件8固定连接,另一端向外水平延伸。Step 2. Install the first fixing structure at the lower position of the curtain wall skeleton, and install the third fixing structure at the upper position of the curtain wall skeleton; the first fixing structure includes the first cross piece 4 and the first transmission rod 5, and the first cross piece 4 has a first through hole for the first transmission rod 5 to move up and down. When the first fixing structure is installed at the lower position of the curtain wall skeleton, the card slot on the first cross member 4 is stuck on the horizontal keel 101 and the vertical cross member 101 of the curtain wall skeleton. The junction of the keel 102 is fixed by the bolt 6, and the upper end of the first transmission rod 5 is screwed to the first through hole on the first cross member 4, and the first transmission rod 5 extends vertically. The third fixing structure includes the second cross piece 8 and the second transmission rod 12. The slot of the second cross piece 8 is stuck at the junction of the transverse keel 101 and the longitudinal keel 102 of the curtain wall skeleton, and is fixed by the bolt 6. The second transmission rod 12, one end is fixedly connected with the second cross member 8, and the other end extends horizontally outward.

步骤三、吊装幕墙骨架到预定位置,第一固定结构与第二固定结构通过三维六度移动(前后左右上下)调整位置,将第三固定结构调整到与第四固定结构安装位置后,将第一固定结构和第二固定结构固定。调整过程如下:吊装幕墙骨架到预定位置后,调整第一固定结构上的第一传动杆5的下端部与第二固定结构上第二通孔1101对正,然后第一传动杆5下端部依次穿过位于槽型构件11顶面的第一螺母16、垫板7上的第三通孔701、槽型构件11上的第二通孔1101,然后通过第一传动杆5上下移动实现第三固定结构上的第二传动杆12插入第四固定结构上的第四长圆孔1001内,并完成第三固定结构相对第四固定结构的竖向调整并将第三固定结构上的第二传动杆12的外伸端固定通过第三螺母14固定。竖向调整完成后,第一传动杆5的下端部穿出第二通孔1101部分穿过垫圈9上的第四通孔901,并将第一传动杆5的下端部穿出部分通过用第二螺母15固定。然后进行第一固定结构相对于第二固定结构的平面调整。调整过程可参考图7,在第一传动杆5前后移动时,由第一传动杆5带动垫板7产生相对槽型构件11的前后移动,第三传动杆17沿第二长圆孔702产生适用性前后移动。当第一传动杆5左右移动时,由第一传动杆5带动垫板7产生相对槽型构件11的左右移动,第三传动杆17沿第二通孔1101产生适应性左右移动,平面调整结束后拧紧第一螺母16。Step 3: Hoist the curtain wall skeleton to the predetermined position, adjust the position of the first fixed structure and the second fixed structure through three-dimensional six-degree movement (front, back, left, right, up, down), adjust the third fixed structure to the installation position of the fourth fixed structure, and then place the second fixed structure The first fixing structure and the second fixing structure are fixed. The adjustment process is as follows: After hoisting the curtain wall skeleton to the predetermined position, adjust the lower end of the first transmission rod 5 on the first fixed structure to align with the second through hole 1101 on the second fixed structure, and then adjust the lower end of the first transmission rod 5 in sequence Pass through the first nut 16 on the top surface of the channel member 11, the third through hole 701 on the backing plate 7, the second through hole 1101 on the channel member 11, and then move up and down through the first transmission rod 5 to realize the third The second transmission rod 12 on the fixed structure is inserted into the fourth oblong hole 1001 on the fourth fixed structure, and the vertical adjustment of the third fixed structure relative to the fourth fixed structure is completed and the second transmission rod on the third fixed structure The extended end of 12 is fixed by the third nut 14. After the vertical adjustment is completed, the lower end of the first transmission rod 5 passes through the second through hole 1101 and partially passes through the fourth through hole 901 on the washer 9, and passes the lower end of the first transmission rod 5 through the second through hole 1101 through the second through hole 901. Two nuts 15 are fixed. A planar adjustment of the first fixing structure relative to the second fixing structure is then performed. The adjustment process can refer to Figure 7. When the first transmission rod 5 moves back and forth, the backing plate 7 is driven by the first transmission rod 5 to move back and forth relative to the groove member 11, and the third transmission rod 17 generates a suitable Sex moves back and forth. When the first transmission rod 5 moves left and right, the backing plate 7 is driven by the first transmission rod 5 to move left and right relative to the groove member 11, and the third transmission rod 17 moves left and right adaptively along the second through hole 1101, and the plane adjustment is completed Then tighten the first nut 16.

步骤四,第三固定结构和第四固定结构平面相对位置微调后,固定第三固定结构和第四固定结构。第三固定结构和第四固定结构水平相对位置微调包括前后位置调整以及左右位置调整(调整过程可参见图1、图8、图9和图10),前后位置调整是通过第二传动杆12推动角钢10前后移动、角钢10带动第四传动杆18沿第五长圆孔1002进行适应性前后移动。左右位置调整是通过第二传动杆12推动角钢10左右移动,角钢10带动第四传动杆18沿第三长圆孔1301进行适应性左右移动,平面相对位置微调达到要求后,通过拧紧第四传动杆18两端的螺母固定第三固定结构和第四固定结构。Step 4: After fine-tuning the relative positions of the third fixed structure and the fourth fixed structure, fix the third fixed structure and the fourth fixed structure. The horizontal relative position fine-tuning of the third fixed structure and the fourth fixed structure includes front-back position adjustment and left-right position adjustment (see Figure 1, Figure 8, Figure 9 and Figure 10 for the adjustment process), and the front-back position adjustment is pushed by the second transmission rod 12 The angle steel 10 moves back and forth, and the angle steel 10 drives the fourth transmission rod 18 to move forward and backward adaptively along the fifth oblong hole 1002 . The left and right position is adjusted by pushing the angle steel 10 to move left and right through the second transmission rod 12, and the angle steel 10 drives the fourth transmission rod 18 to move adaptively left and right along the third oblong hole 1301. After fine-tuning the relative position of the plane to meet the requirements, tighten the fourth transmission rod 18 Nuts at two ends fix the third fixing structure and the fourth fixing structure.

为了确保安装精度,第一固定结构和第三固定结构轴线之间的距离与相邻层两根结构梁之间的轴线之间的垂直距离相等。In order to ensure installation accuracy, the distance between the axes of the first fixed structure and the third fixed structure is equal to the vertical distance between the axes of two structural beams on adjacent floors.

为了确保结构梁的支撑强度,结构梁腰部焊接有支撑牛腿,支撑牛腿与结构梁等高。In order to ensure the supporting strength of the structural beam, a supporting corbel is welded at the waist of the structural beam, and the supporting corbel is as high as the structural beam.

由于幕墙骨架一般为整面墙的尺寸,自重较大,因此,所有传动杆均采用高强螺栓,高强螺栓与构件的结合面之间应按要求检查处理,高强度螺栓应按规定初拧和终拧。Since the curtain wall skeleton is generally the size of the entire wall and has a large self-weight, high-strength bolts are used for all transmission rods. screw.

虽然本发明所揭示的实施方式如上,但其内容只是为了便于理解本发明的技术方案而采用的实施方式,并非用于限定本发明。任何本发明所属技术领域内的技术人员,在不脱离本发明所揭示的核心技术方案的前提下,可以在实施的形式和细节上做任何修改与变化,但本发明所限定的保护范围,仍须以所附的权利要求书限定的范围为准。Although the embodiments disclosed in the present invention are as above, the content thereof is only for the convenience of understanding the technical solutions of the present invention, and is not intended to limit the present invention. Anyone skilled in the technical field to which the present invention belongs can make any modifications and changes in the form and details of implementation without departing from the core technical solution disclosed in the present invention, but the scope of protection defined by the present invention remains The scope defined by the appended claims shall prevail.

Claims (9)

1.一种幕墙骨架与结构梁的安装方法,其特征在于,包括如下步骤:1. an installation method of curtain wall skeleton and structural beam, is characterized in that, comprises the steps: 根据在结构梁上的测量放线将第二固定结构安装在结构梁的上表面,将第四固定结构安装在结构梁的下表面;Installing the second fixed structure on the upper surface of the structural beam according to the measurement setting out on the structural beam, and installing the fourth fixed structure on the lower surface of the structural beam; 将第一固定结构安装在幕墙骨架靠下位置,将第三固定结构安装在幕墙骨架靠上位置;Install the first fixed structure at the lower position of the curtain wall skeleton, and install the third fixed structure at the upper position of the curtain wall skeleton; 吊装幕墙骨架到预定位置,第一固定结构与第二固定结构通过三维六度移动调整相对位置并使第三固定结构移动至第四固定结构安装位置后,固定第一固定结构与第二固定结构;Lift the curtain wall skeleton to the predetermined position, adjust the relative position of the first fixed structure and the second fixed structure through three-dimensional six-degree movement and move the third fixed structure to the installation position of the fourth fixed structure, then fix the first fixed structure and the second fixed structure ; 第三固定结构和第四固定结构平面相对位置微调,微调结束后固定第三固定结构和第四固定结构。The relative positions of the third fixed structure and the fourth fixed structure are fine-tuned, and the third fixed structure and the fourth fixed structure are fixed after the fine-tuning is completed. 2.如权利要求1所述的幕墙骨架与结构梁的安装方法,其特征在于:第一固定结构包括第一十字件和第一传动杆,所述第一十字件上有第一通孔,当第一固定结构安装在幕墙骨架靠下位置时,第一十字件与幕墙骨架固定,所述第一传动杆上端部与所述第一通孔螺纹连接。2. The installation method of curtain wall frame and structural beams according to claim 1, characterized in that: the first fixing structure comprises a first cross piece and a first transmission rod, the first cross piece has a first through hole, When the first fixing structure is installed at the lower position of the curtain wall skeleton, the first cross member is fixed to the curtain wall skeleton, and the upper end of the first transmission rod is screwed into the first through hole. 3.如权利要求2所述的幕墙骨架与结构梁的安装方法,其特征在于:所述第二固定结构包括槽型构件,所述槽型构件的双肢与所述结构梁焊接,所述槽型构件的背板上开有供第一传动杆穿过的第二通孔,吊装幕墙骨架到预定位置后,调整所述第一传动杆的下端部与所述第二通孔对正,所述第一传动杆下端部依次穿过位于所述槽型构件顶面的第一螺母、与所述槽型构件上开有对应第三通孔的垫板以及所述槽型构件上的第二通孔,通过上下移动所述第一传动杆调整所述墙体骨架的上下位置,调整结束,使所述第一传动杆的下端部穿过与所述槽型构件上开有对应第四通孔的垫圈,并将第一传动杆的下端部通过所述用第二螺母固定,同时拧紧第一螺母。3. The installation method of the curtain wall skeleton and the structural beam as claimed in claim 2, characterized in that: the second fixing structure comprises a channel member, the two limbs of the channel member are welded to the structural beam, and the There is a second through hole on the back plate of the channel member for the first transmission rod to pass through. After hoisting the curtain wall skeleton to the predetermined position, adjust the lower end of the first transmission rod to align with the second through hole. The lower end of the first transmission rod sequentially passes through the first nut on the top surface of the channel member, the backing plate corresponding to the third through hole on the channel member, and the first nut on the channel member. Two through holes, adjust the up and down position of the wall frame by moving the first transmission rod up and down, after the adjustment is completed, let the lower end of the first transmission rod pass through the corresponding fourth opening on the grooved member. The washer of the through hole is used, and the lower end of the first transmission rod is fixed by the second nut, and the first nut is tightened at the same time. 4.如权利要求3所述的幕墙骨架与结构梁的安装方法,其特征在于:所述槽型构件上开有第一长圆孔,所述垫板上开有第二长圆孔,所述第一长圆孔和所述第二长圆孔中心重合,长轴相互垂直,所述第一长圆孔和所述第二长圆孔通过第三传动杆连接形成所述第一固定结构和所述第二固定结构位置调整过程中的随动结构,其随着所述第一传动杆的平面移动而移动。4. The installation method of curtain wall framework and structural beams as claimed in claim 3, characterized in that: the first oblong hole is opened on the channel member, the second oblong hole is opened on the backing plate, and the first oblong hole is opened on the backing plate. An oblong hole coincides with the center of the second oblong hole, and the major axes are perpendicular to each other. The first oblong hole and the second oblong hole are connected by a third transmission rod to form the first fixing structure and the second fixing structure. The follower structure in the process of structure position adjustment moves along with the planar movement of the first transmission rod. 5.如权利要求3所述的幕墙骨架与结构梁的安装方法,其特征在于:第三固定结构包括第二十字件和第二传动杆,所述第二十字件与所述墙体骨架固定,所述第二传动杆一端与所述第二十字件固定连接,另一端向外延伸。5. The installation method of curtain wall frame and structural beam as claimed in claim 3, characterized in that: the third fixing structure includes a second cross piece and a second transmission rod, and the second cross piece is fixed to the wall frame , one end of the second transmission rod is fixedly connected to the second cross member, and the other end extends outward. 6.如权利要求3所述的幕墙骨架与结构梁的安装方法,其特征在于:所述第四固定结构包括槽型件和角钢,所述槽型件的双肢与所述结构梁底面固定,所述角钢的一肢与所述槽型件的背板采用滑动连接结构连接,所述角钢的另一肢上开设有供所述第二传动杆上下移动的第四长圆孔,当所述第二传动杆端部伸入所述第四长圆孔并调整至合适位置,通过第三螺母固定所述第二传动杆端部。6. The installation method of the curtain wall skeleton and the structural beam as claimed in claim 3, characterized in that: the fourth fixing structure comprises a channel piece and an angle steel, and the two limbs of the channel piece are fixed to the bottom surface of the structural beam , one limb of the angle steel is connected with the back plate of the groove-shaped piece by a sliding connection structure, and the other limb of the angle steel is provided with a fourth oblong hole for the second transmission rod to move up and down, when the The end of the second transmission rod extends into the fourth oblong hole and is adjusted to a proper position, and the end of the second transmission rod is fixed by a third nut. 7.如权利要求6所述的幕墙骨架与结构梁的安装方法,其特征在于:所述滑动连接结构包括开设在所述槽型件背板上的第三长圆孔、开设在所述角钢一肢上的第五长圆孔和第四传动杆,所述第三长圆孔和所述第五长圆孔中心重合,长轴相互垂直,所述第四传动杆插入所述第三长圆孔和所述第五长圆孔内,并随着所述第二传动杆的平面移动而移动。7. The installation method of curtain wall skeleton and structural beam as claimed in claim 6, characterized in that: said sliding connection structure includes a third oblong hole opened on the back plate of said channel member, a third oblong hole opened on said angle steel The fifth oblong hole on the limb and the fourth transmission rod, the centers of the third oblong hole and the fifth oblong hole coincide with each other, and the major axes are perpendicular to each other, and the fourth transmission rod is inserted into the third oblong hole and the fifth oblong hole in the fifth oblong hole, and moves along with the planar movement of the second transmission rod. 8.如权利要求1所述的幕墙骨架与结构梁的安装方法,其特征在于:所述第一固定结构和第三固定结构轴线之间的距离与相邻层两根结构梁之间的轴线之间的垂直距离相等。8. The installation method of curtain wall framework and structural beams according to claim 1, characterized in that: the distance between the axes of the first fixed structure and the third fixed structure is the same as the axis between two structural beams on adjacent floors The vertical distance between them is equal. 9.如权利要求1所述的幕墙骨架与结构梁的安装方法,其特征在于:所述结构梁腰部焊接有支撑牛腿,所述支撑牛腿与所述结构梁等高。9. The installation method of the curtain wall skeleton and the structural beam according to claim 1, characterized in that: the waist of the structural beam is welded with a supporting corbel, and the supporting corbel is of the same height as the structural beam.
CN201410788504.4A 2014-12-17 2014-12-17 The installation method of Curtain wall frame and structural beams Active CN105756245B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410788504.4A CN105756245B (en) 2014-12-17 2014-12-17 The installation method of Curtain wall frame and structural beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410788504.4A CN105756245B (en) 2014-12-17 2014-12-17 The installation method of Curtain wall frame and structural beams

Publications (2)

Publication Number Publication Date
CN105756245A true CN105756245A (en) 2016-07-13
CN105756245B CN105756245B (en) 2019-01-15

Family

ID=56340221

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410788504.4A Active CN105756245B (en) 2014-12-17 2014-12-17 The installation method of Curtain wall frame and structural beams

Country Status (1)

Country Link
CN (1) CN105756245B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522391A (en) * 2016-11-11 2017-03-22 浙江绿筑建筑系统集成有限公司 Extended type prefabricated sandwich insulation and decoration integrated external wall plate
CN107165287A (en) * 2017-05-02 2017-09-15 黄淮学院 A kind of attachment structure of assembled wall and plate-girder
CN111622398A (en) * 2020-06-02 2020-09-04 徐秀玲 Anti-falling mechanism for installation based on external curtain wall for urban building
CN113089903A (en) * 2021-04-21 2021-07-09 江苏恒龙装饰工程有限公司 Curtain wall mounting structure and construction process
CN113374137A (en) * 2021-07-08 2021-09-10 王梓楠 Building curtain wall convenient to disassemble and assemble
CN114263336A (en) * 2021-10-29 2022-04-01 成都建工第二建筑工程有限公司 Construction method of KTC plate composite outer wall decoration system
CN116146916A (en) * 2021-11-19 2023-05-23 苏州欧普照明有限公司 a curtain wall light

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0313644A (en) * 1989-06-08 1991-01-22 Misawa Homes Co Ltd Fitting method for curtain wall
JPH0827930A (en) * 1994-07-11 1996-01-30 Tateyama Alum Ind Co Ltd Curtain wall
CN2275606Y (en) * 1996-09-06 1998-03-04 邓勇 Sliding full-opening concealed frame safety curtain wall
CN201801985U (en) * 2010-07-27 2011-04-20 深圳市方大特种结构有限公司 Framework structure of stone curtain wall
CN202157438U (en) * 2011-07-11 2012-03-07 北京嘉寓门窗幕墙股份有限公司 Support frame for exposed frame glass curtain wall with cross rubber mat
CN102926490A (en) * 2012-03-19 2013-02-13 南京旭建新型建材股份有限公司 Dry-hung self-insulation curtain wall body based on autoclaved lightweight aerated concrete slab
CN104153495A (en) * 2014-07-15 2014-11-19 广东莲田金属工程建筑有限公司 Multifunctional lightweight concrete curtain wall connecting structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0313644A (en) * 1989-06-08 1991-01-22 Misawa Homes Co Ltd Fitting method for curtain wall
JPH0827930A (en) * 1994-07-11 1996-01-30 Tateyama Alum Ind Co Ltd Curtain wall
CN2275606Y (en) * 1996-09-06 1998-03-04 邓勇 Sliding full-opening concealed frame safety curtain wall
CN201801985U (en) * 2010-07-27 2011-04-20 深圳市方大特种结构有限公司 Framework structure of stone curtain wall
CN202157438U (en) * 2011-07-11 2012-03-07 北京嘉寓门窗幕墙股份有限公司 Support frame for exposed frame glass curtain wall with cross rubber mat
CN102926490A (en) * 2012-03-19 2013-02-13 南京旭建新型建材股份有限公司 Dry-hung self-insulation curtain wall body based on autoclaved lightweight aerated concrete slab
CN104153495A (en) * 2014-07-15 2014-11-19 广东莲田金属工程建筑有限公司 Multifunctional lightweight concrete curtain wall connecting structure

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522391A (en) * 2016-11-11 2017-03-22 浙江绿筑建筑系统集成有限公司 Extended type prefabricated sandwich insulation and decoration integrated external wall plate
CN107165287A (en) * 2017-05-02 2017-09-15 黄淮学院 A kind of attachment structure of assembled wall and plate-girder
CN111622398A (en) * 2020-06-02 2020-09-04 徐秀玲 Anti-falling mechanism for installation based on external curtain wall for urban building
CN113089903A (en) * 2021-04-21 2021-07-09 江苏恒龙装饰工程有限公司 Curtain wall mounting structure and construction process
CN113089903B (en) * 2021-04-21 2022-06-03 江苏恒龙装饰工程有限公司 Curtain wall mounting structure and construction process
CN113374137A (en) * 2021-07-08 2021-09-10 王梓楠 Building curtain wall convenient to disassemble and assemble
CN114263336A (en) * 2021-10-29 2022-04-01 成都建工第二建筑工程有限公司 Construction method of KTC plate composite outer wall decoration system
CN116146916A (en) * 2021-11-19 2023-05-23 苏州欧普照明有限公司 a curtain wall light

Also Published As

Publication number Publication date
CN105756245B (en) 2019-01-15

Similar Documents

Publication Publication Date Title
CN105756245A (en) Method for mounting curtain wall skeleton and structural beam
CN205604464U (en) Exterior wall cladding antidetonation is connecting piece down
CN204983145U (en) Connection structure of square steel column and steel I -beam
CN103491737A (en) Equipment cabinet changeover base
CN103132650B (en) C-shaped steel structure component and method for combining beam column by employing C-shaped steel structure component
CN101949187B (en) Force bearing device three-dimensionally adjusted and positioned by unitized curtain wall
CN105756246A (en) Adjustable wall and beam connecting structure
CN209243957U (en) The pre-buried weldment of curtain wall slot type
CN107740520B (en) High strength curtain bearing structure for building
CN204401823U (en) Embedded wallboard connecting component in assembling type steel structure system
CN211526366U (en) Ceiling lamp light trough connecting piece for indoor ceiling decoration
CN109577530B (en) Curtain wall adjustable connecting node structure based on conversion angle steel and construction method
CN204370639U (en) The syndeton of adjustable body of wall and beam
CN206693449U (en) A kind of lightgage steel joist framework
CN201747052U (en) Novel nondestructive tight bind type attachment device of creeping climbing formwork and climbing frame
CN213927028U (en) Indoor assembled type special-shaped top surface supporting steel frame mounting structure
CN205276487U (en) Connection structure of light steel prefabricated exterior wall and major structure with adjustable it is three -dimensional
CN205348477U (en) Steel aluminium combines curtain stand form
CN205776748U (en) Box column and unequal-height steel beam connecting structure
CN204370638U (en) A kind of wall skeleton and body of wall
CN115559460A (en) Outer wallboard splicing and positioning device for assembly type building
CN204590975U (en) The connecting structure of light cellular partition board door and window upper board
CN205077677U (en) A tie-rod steel structure point glass curtain wall
CN205502621U (en) Reinforcing apparatus that is connected of assemblyization building wall and post
CN217871391U (en) Engineering frame roof beam reinforced structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant