CN105736000A - Construction method for detaching shield forming tunnel zero ring duct pieces through static blasting - Google Patents

Construction method for detaching shield forming tunnel zero ring duct pieces through static blasting Download PDF

Info

Publication number
CN105736000A
CN105736000A CN201610129540.9A CN201610129540A CN105736000A CN 105736000 A CN105736000 A CN 105736000A CN 201610129540 A CN201610129540 A CN 201610129540A CN 105736000 A CN105736000 A CN 105736000A
Authority
CN
China
Prior art keywords
jurisdiction
section
static
construction method
static blasting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610129540.9A
Other languages
Chinese (zh)
Other versions
CN105736000B (en
Inventor
王文兵
张兆龙
成果
郭军立
潘娜娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING ZHUZONG GROUP Co Ltd
Original Assignee
BEIJING ZHUZONG GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ZHUZONG GROUP Co Ltd filed Critical BEIJING ZHUZONG GROUP Co Ltd
Priority to CN201610129540.9A priority Critical patent/CN105736000B/en
Publication of CN105736000A publication Critical patent/CN105736000A/en
Application granted granted Critical
Publication of CN105736000B publication Critical patent/CN105736000B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E21—EARTH OR ROCK DRILLING; MINING
    • E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种静态爆破拆除盾构成型隧道零环管片的施工方法,包括以下步骤:步骤1,在所述零环管片的外侧圆环面布孔,在布孔位置钻孔;步骤2,分步对管片进行静态爆破,对破碎的管片进行清理;首先将拌制好的静态破碎剂填充到上部的管片内对其进行静态爆破,对破碎的管片进行清理;然后将拌制好的静态破碎剂填充到中部的管片内对其进行静态爆破,对破碎的管片进行清理;最后将拌制好的静态破碎剂填充到下部的管片内对其进行静态爆破,对破碎的管片进行清理。本发明采用静态爆破技术进行成型隧道管片的拆除,避免由于人工或机械破除带来的人身伤害和结构实体质量的损害,达到安全、高效、无噪声的施工,其社会效益不可小觑。

The invention discloses a construction method for static blasting to remove a zero-ring segment of a shield-shaped tunnel, which comprises the following steps: Step 1, arranging holes on the outer circular surface of the zero-ring segment, and drilling holes at the hole arrangement position; Step 2, perform static blasting on the segments step by step, and clean up the broken segments; first, fill the mixed static breaking agent into the upper segments for static blasting, and clean up the broken segments; Then fill the prepared static breaking agent into the middle segment for static blasting, and clean the broken segment; finally, fill the mixed static breaking agent into the lower segment for static blasting. Blast and clean up the broken segments. The invention adopts the static blasting technology to dismantle the formed tunnel segment, avoids personal injury and structural entity quality damage caused by manual or mechanical demolition, and achieves safe, efficient, and noiseless construction, and its social benefits cannot be underestimated.

Description

一种静态爆破拆除盾构成型隧道零环管片的施工方法A Construction Method for Demolishing Zero-ring Segment of Shield Formed Tunnel by Static Blasting

技术领域 technical field

本发明属于盾构法隧道施工技术领域,特别是涉及一种静态爆破拆除盾构成型隧道零环管片的施工方法。 The invention belongs to the technical field of shield tunnel construction, and in particular relates to a construction method for static blasting to remove zero-ring segment of a shield-shaped tunnel.

背景技术 Background technique

盾构法隧道施工是地下区间结构工程施工的主要方法之一,根据该工法的施工程序和特点,在完成整条隧道贯通后,需要进行进洞、出洞零环管片拆除,进而施工钢筋混凝土环梁。 Shield method tunnel construction is one of the main construction methods of underground interval structure engineering. According to the construction procedures and characteristics of this construction method, after the completion of the entire tunnel penetration, it is necessary to remove the zero-ring segment from the hole and then construct the reinforcement Concrete ring beam.

一般而言,零环管片由3个标准块、2个邻接块和1个封顶块组成,各块间纵向、环向均通过高强螺栓连接。按隧道直径6200mm计,最小块封顶块重量约1.3t,其他块重量约4.6t。隧道施工期间,管片除了支护土体、形成主体结构外,还提供盾构机反力,各分块在环向、纵向均被挤压紧密,且同步注浆及二次背后注浆后,混凝土凝结使管片粘接牢固,拆除困难,特别是1块封顶块和2块邻接块位于隧道拱顶位置,拆除存在极大的安全隐患。 Generally speaking, the zero-ring segment is composed of 3 standard blocks, 2 adjacent blocks and 1 capping block, and the longitudinal and circumferential directions of each block are connected by high-strength bolts. Based on the tunnel diameter of 6200mm, the weight of the smallest capping block is about 1.3t, and the weight of other blocks is about 4.6t. During tunnel construction, in addition to supporting the soil and forming the main structure, the segments also provide the reaction force of the shield machine. Each block is squeezed tightly in the circumferential and longitudinal directions, and after synchronous grouting and secondary back grouting , Concrete coagulation makes the segments bonded firmly, making it difficult to dismantle, especially when one capping block and two adjoining blocks are located at the vault of the tunnel, there is a great safety hazard in dismantling.

目前盾构成型隧道零环管片拆除,多为人工搭设平台,使用风镐或水钻进行破除。但是对于拱顶部分管片,需仰面操作,施工难度大,操作不方便;另外,拱顶管片处于悬空状态,重量大,作业人员处于极不安全环境中,安全隐患极大。若采用机械凿除,一方面振动大,导致正环管片破坏,影响隧道结构受力及防水效果,另一方面,噪音大,不利于文明施工。因此,寻求一种安全、高效、无噪声的拆除方法,尤为重要。 At present, the demolition of the zero-ring segment of the shield-shaped tunnel is mostly manually erected platforms, which are broken by pneumatic picks or rhinestones. However, for some segments of the vault, it needs to be operated on the upside, which is difficult to construct and inconvenient to operate. In addition, the segments of the vault are in a suspended state and are heavy, and the operators are in an extremely unsafe environment, which poses a great safety hazard. If mechanical chiseling is used, on the one hand, the vibration will be large, which will lead to the damage of the positive ring segments, affecting the force and waterproof effect of the tunnel structure; on the other hand, the noise will be large, which is not conducive to civilized construction. Therefore, it is particularly important to seek a safe, efficient and noiseless demolition method.

发明内容 Contents of the invention

本发明的目的是提供一种静态爆破拆除盾构成型隧道零环管片的施工方法,以解决利用风镐或水钻清除时操作不便,施工难度大且作业人员施工危险性大的问题;以及机械凿除导致正环管片破坏及噪音大的问题。 The purpose of the present invention is to provide a construction method for static blasting to remove the zero-ring segment of a shield-shaped tunnel, so as to solve the problems of inconvenient operation when using pneumatic picks or water drills to remove, difficult construction and great danger for operators; and mechanical Chisel out the problems that lead to the damage of positive ring segments and high noise.

本发明解决上述技术问题的技术方案如下: The technical scheme that the present invention solves the problems of the technologies described above is as follows:

一种静态爆破拆除盾构成型隧道零环管片的施工方法,所述零环管片由位于上部的管片、位于中部的管片和位于下部的管片构成,相邻的管片之间利用螺栓连接;该施工方法包括以下步骤: A construction method for static blasting to remove a zero-ring segment of a shield-shaped tunnel. The zero-ring segment is composed of an upper segment, a middle segment, and a lower segment. Between adjacent segments Utilize bolted connections; the construction method includes the following steps:

步骤1,在所述零环管片的外侧圆环面布孔,在布孔位置钻孔; Step 1, distributing holes on the outer annular surface of the zero-ring segments, and drilling holes at the positions of the distributing holes;

步骤2,分步对管片进行静态爆破,对破碎的管片进行清理; Step 2, carry out static blasting on the segments step by step, and clean up the broken segments;

首先将拌制好的静态破碎剂填充到上部的管片内对其进行静态爆破,对破碎的管片进行清理; First, fill the prepared static breaking agent into the upper segment for static blasting, and clean up the broken segments;

然后将拌制好的静态破碎剂填充到中部的管片内对其进行静态爆破,对破碎的管片进行清理; Then fill the mixed static breaking agent into the middle segment for static blasting, and clean up the broken segments;

最后将拌制好的静态破碎剂填充到下部的管片内对其进行静态爆破,对破碎的管片进行清理。 Finally, fill the mixed static breaking agent into the lower segment for static blasting, and clean up the broken segments.

本发明如上所述的静态爆破拆除盾构成型隧道零环管片的施工方法,进一步,位于上部的管片具有两块,分别为F型管片和L2型管片;位于中部的管片具有两块,分别为L1型管片和B2型管片;位于下部的管片具有两块,分别为B1型管片和B3型管片。 According to the construction method of the zero-ring segment of the shield-shaped tunnel by static blasting as described above in the present invention, further, the upper segment has two segments, which are respectively an F-type segment and an L2-type segment; the middle segment has a There are two pieces, which are L1-type segment and B2-type segment; the lower segment has two pieces, which are B1-type segment and B3-type segment.

本发明如上所述的静态爆破拆除盾构成型隧道零环管片的施工方法,进一步,步骤1中,相邻的钻孔中心之间相距20cm~50cm,所述钻孔的深度为管片长度的0.7~0.9倍,所述钻孔的孔径为30mm~50mm。 The above-mentioned construction method of static blasting demolition of the zero-ring segment of the shield-shaped tunnel of the present invention, further, in step 1, the distance between the centers of adjacent boreholes is 20cm to 50cm, and the depth of the boreholes is the length of the segment 0.7 to 0.9 times of that, and the diameter of the drilled hole is 30 mm to 50 mm.

本发明如上所述的静态爆破拆除盾构成型隧道零环管片的施工方法,优选地,根据不同季节选用不同类型的静态破碎剂;静态破碎剂为药卷型破碎剂,或者常规破碎剂,但是在拌制静态破碎剂时将推荐的水灰比减少,宜为20%~25%。 According to the above-mentioned construction method of static blasting demolition of the zero-ring segment of shield-shaped tunnel in the present invention, preferably, different types of static breaking agents are selected according to different seasons; the static breaking agents are drug roll type breaking agents, or conventional breaking agents, However, when mixing the static breaker, reduce the recommended water-cement ratio, which should be 20% to 25%.

本发明如上所述的静态爆破拆除盾构成型隧道零环管片的施工方法,优选地,所述步骤1具体包括,人工搭设施工平台,利用风钻在布孔位置成孔,然后将钻孔清理干净使钻孔内无水或杂物。 According to the above-mentioned construction method of the static blasting demolition of the zero-ring segment of the shield-shaped tunnel in the present invention, preferably, the step 1 specifically includes, manually erecting the construction platform, using a pneumatic drill to form holes at the positions where the holes are arranged, and then cleaning the boreholes Clean so that there is no water or debris in the borehole.

本发明如上所述的静态爆破拆除盾构成型隧道零环管片的施工方法,优选地,在步骤2中,将拌制好的静态破碎剂填充到管片前,检查钻孔内的干湿程度,若孔壁干燥吸水性强则先用净水湿润孔壁。 According to the construction method of the static blasting demolition of the zero-ring segment of the shield tunnel as described above in the present invention, preferably, in step 2, before filling the static breaking agent prepared into the segment, check the dryness and wetness in the borehole. If the hole wall is dry and has strong water absorption, wet the hole wall with clean water first.

本发明如上所述的静态爆破拆除盾构成型隧道零环管片的施工方法,优选地,在步骤2中,在发烫前将拌制好的静态破碎剂装入管片的钻孔内。 According to the construction method of static blasting demolition shield tunnel zero-ring segment of the present invention, preferably, in step 2, the static breaker that has been mixed is loaded into the drill hole of the segment before heating.

本发明如上所述的静态爆破拆除盾构成型隧道零环管片的施工方法,优选地,在零度以下温度环境中施工时,利用重量百分比浓度为1%~2%的盐水或大于零摄氏度的温水拌制静态破碎剂。 According to the above-mentioned construction method of the static blasting demolition of the zero-ring segment of the shield-shaped tunnel of the present invention, preferably, when the construction is carried out in a sub-zero temperature environment, salt water with a concentration of 1% to 2% by weight or a temperature greater than zero degrees Celsius is used. Mix warm water to prepare static breaker.

本发明的有益效果是: The beneficial effects of the present invention are:

拆除分两部分工作:混凝土破碎和钢筋割除。利用静态爆破技术在管片外侧圆周上均匀布置孔位,操作方便施工便捷;填入静态爆破膨胀剂,使管片自身膨胀破裂,将大块大重量的拱顶混凝土块破碎、脱落。然后再配合人工清理,避免作业人员直接进行破碎,消除安全隐患。最后割除剩余钢筋,完成拆除施工。本发明的最大优点在于混凝土破碎和混凝土块清除在时间上先后进行,也就避免了施工人员暴露在可能下落的混凝土块环境中,极大的提高了施工的安全性。此外,混凝土破碎过程中无任何振动产生,不会破坏正环管片,实现了安全、高效、无噪声环保的目的。 Demolition works in two parts: concrete breaking and reinforcement removal. Use static blasting technology to evenly arrange holes on the outer circumference of the segment, which is convenient for operation and construction; fill in static blasting expansion agent to make the segment itself expand and rupture, and break and fall off large and heavy vault concrete blocks. Then cooperate with manual cleaning to avoid direct crushing by operators and eliminate potential safety hazards. Finally, the remaining steel bars are cut off to complete the demolition construction. The greatest advantage of the present invention is that concrete breaking and concrete block removal are carried out successively in time, which avoids construction personnel from being exposed to the environment of possible falling concrete blocks, and greatly improves the safety of construction. In addition, there is no vibration during the crushing process of concrete, and the positive ring segment will not be damaged, which achieves the purpose of safety, high efficiency, noise-free and environmental protection.

附图说明 Description of drawings

通过结合以下附图所作的详细描述,本发明的上述和/或其他方面和优点将变得更清楚和更容易理解,这些附图只是示意性的,并不限制本发明,其中: The above and/or other aspects and advantages of the present invention will become clearer and easier to understand through the detailed description made in conjunction with the following drawings, which are only schematic and do not limit the present invention, wherein:

图1为本发明一种实施例的静态爆破拆除盾构成型隧道零环管片的施工方法流程示意图; Fig. 1 is a schematic flow chart of the construction method of the zero-ring segment of a shield-shaped tunnel demolished by static blasting according to an embodiment of the present invention;

图2为本发明一种实施例的零环管片组成及布孔示意图; Fig. 2 is a zero-ring segment composition and a schematic diagram of hole layout of an embodiment of the present invention;

图3为本发明一种实施例的零环管片爆破顺序示意图。 Fig. 3 is a schematic diagram of the blasting sequence of a zero-ring segment in an embodiment of the present invention.

附图中,各标号所代表的部件列表如下: In the accompanying drawings, the list of parts represented by each label is as follows:

1、B1型管片,2、B2型管片,3、B3型管片,4、L1型管片,5、L2型管片,6、F型管片,7、连接螺栓,8、钻孔。 1. B1-type segment, 2. B2-type segment, 3. B3-type segment, 4. L1-type segment, 5. L2-type segment, 6. F-type segment, 7. connecting bolts, 8. drill hole.

具体实施方式 detailed description

在下文中,将参照附图描述本发明的静态爆破拆除盾构成型隧道零环管片的施工方法的实施例。 Hereinafter, embodiments of the construction method of the static blasting demolition of the zero-ring segment of a shield-shaped tunnel according to the present invention will be described with reference to the accompanying drawings.

在此记载的实施例为本发明的特定的具体实施方式,用于说明本发明的构思,均是解释性和示例性的,不应解释为对本发明实施方式及本发明范围的限制。除在此记载的实施例外,本领域技术人员还能够基于本申请权利要求书和说明书所公开的内容采用显而易见的其它技术方案,这些技术方案包括采用对在此记载的实施例的做出任何显而易见的替换和修改的技术方案。 The examples described here are specific specific implementations of the present invention, and are used to illustrate the concept of the present invention. They are all explanatory and exemplary, and should not be construed as limiting the implementation of the present invention and the scope of the present invention. In addition to the embodiments described here, those skilled in the art can also adopt other obvious technical solutions based on the claims of the application and the contents disclosed in the description, and these technical solutions include adopting any obvious changes made to the embodiments described here. Replacement and modified technical solutions.

本说明书的附图为示意图,辅助说明本发明的构思,示意性地表示各部分的形状及其相互关系。请注意,为了便于清楚地表现出本发明实施例的各部件的结构,各附图之间并未按照相同的比例绘制。相同的参考标记用于表示相同的部分。 The accompanying drawings in this specification are schematic diagrams, which assist in explaining the concept of the present invention, and schematically represent the shapes of various parts and their interrelationships. Please note that in order to clearly show the structures of the components in the embodiments of the present invention, the drawings are not drawn in the same scale. The same reference numerals are used to designate the same parts.

图1示出本发明一种实施例的静态爆破拆除盾构成型隧道零环管片的施工方法,其包括: Fig. 1 shows the construction method of the zero-ring segment of the static blasting demolition shield shaped tunnel of an embodiment of the present invention, and it comprises:

本发明解决上述技术问题的技术方案如下:一种静态爆破拆除盾构成型隧道零环管片的施工方法,所述零环管片由位于上部的管片、位于中部的管片和位于下部的管片构成,相邻的管片之间利用螺栓7连接;在如图2所示的一种零环管片的实施例中,位于上部的管片具有两块,分别为F型管片6和L2型管片5;位于中部的管片具有两块,分别为L1型管片4和B2型管片2;位于下部的管片具有两块,分别为B1型管片1和B3型管片3。 The technical solution of the present invention to solve the above-mentioned technical problems is as follows: a construction method for static blasting to remove zero-ring segment of a shield-shaped tunnel, the zero-ring segment is composed of an upper segment, a middle segment and a lower segment Segments are formed, and adjacent segments are connected by bolts 7; in an embodiment of a zero-ring segment as shown in Figure 2, the upper segment has two pieces, which are respectively F-type segments 6 and L2-type segment 5; the segment in the middle has two pieces, namely L1-type segment 4 and B2-type segment 2; the lower segment has two pieces, respectively, B1-type segment 1 and B3-type tube slice 3.

该施工方法包括以下步骤: This construction method comprises the following steps:

步骤1,在所述零环管片的外侧圆环面布孔,在布孔位置钻孔8;在如图1所示的实施例中,相邻的钻孔8中心之间相距20cm~50cm,所述钻孔8的深度为管片长度的0.7~0.9倍,所述钻孔8的孔径为30mm~50mm。例如,相邻的钻孔8中心之间相距30cm,所述钻孔8的深度为管片长度的0.9倍,所述钻孔8的孔径为40mm。钻孔的深度及孔径不应低于上述数值范围的下限,防止破碎剂产生的膨胀力不足以破碎管片。在一种具体施工过程中,所述步骤1包括,人工搭设施工平台,利用风钻在布孔位置成孔,然后将钻孔清理干净使钻孔内无水或杂物。 Step 1, arrange holes on the outer annular surface of the zero-ring segments, and drill holes 8 at the positions of the holes; in the embodiment shown in Figure 1, the distance between the centers of adjacent drill holes 8 is 20cm to 50cm , the depth of the borehole 8 is 0.7-0.9 times the length of the segment, and the diameter of the borehole 8 is 30mm-50mm. For example, the distance between the centers of adjacent boreholes 8 is 30 cm, the depth of the boreholes 8 is 0.9 times the length of the segment, and the diameter of the boreholes 8 is 40 mm. The depth and diameter of the drilled holes should not be lower than the lower limit of the above numerical range to prevent the expansion force generated by the breaker from being insufficient to break the segments. In a specific construction process, the step 1 includes manually setting up a construction platform, using a pneumatic drill to form holes at the positions where the holes are arranged, and then cleaning the holes so that there is no water or debris in the holes.

步骤2,分步对管片进行静态爆破,对破碎的管片进行清理;将拌制好的静态破碎剂填充到管片前,检查钻孔内的干湿程度,若孔壁干燥吸水性强则先用净水湿润孔壁。 Step 2: Perform static blasting on the segments step by step, and clean up the broken segments; fill the mixed static breaking agent into the segments, check the dryness and humidity in the borehole, if the hole wall is dry and has strong water absorption Moisten the hole wall with clean water first.

首先将拌制好的静态破碎剂填充到上部的管片内对其进行静态爆破,对破碎的管片进行清理; First, fill the prepared static breaking agent into the upper segment for static blasting, and clean up the broken segments;

然后将拌制好的静态破碎剂填充到中部的管片内对其进行静态爆破,对破碎的管片进行清理; Then fill the mixed static breaking agent into the middle segment for static blasting, and clean up the broken segments;

最后将拌制好的静态破碎剂填充到下部的管片内对其进行静态爆破,对破碎的管片进行清理。上述步骤中,在拌制好的静态破碎剂发烫前将其装入管片的钻孔内。 Finally, fill the mixed static breaking agent into the lower segment for static blasting, and clean up the broken segments. In the above-mentioned steps, the static breaking agent that has been mixed is loaded into the drilled holes of the segments before it is heated.

上述步骤中,在零度以下温度环境中施工时,利用重量百分比浓度为1%~2%的盐水或大于零摄氏度的温水拌制静态破碎剂。 In the above steps, when the construction is carried out in a temperature environment below zero, the static breaking agent is mixed with salt water with a concentration of 1% to 2% by weight or warm water above zero degrees Celsius.

在本发明上述实施例的静态爆破拆除盾构成型隧道零环管片的施工方法中,根据不同季节选用不同类型的静态破碎剂,例如春、秋季使用中科新材北京科技有限公司的HSCA-Ⅱ型高效无声破碎剂,适用温度25±5℃;夏季使用中科新材北京科技有限公司的HSCA-Ⅰ型高效无声破碎剂,适用温度35±5℃;冬季使用中科新材北京科技有限公司的HSCA-Ⅲ型高效无声破碎剂,适用温度10±5℃,再辅以保温覆盖等冬季养护措施;由于钻孔为水平孔,优选地,静态破碎剂为药卷型破碎剂,或者常规破碎剂,但是在拌制静态破碎剂时将推荐的水灰比减少,宜为20%~25%,均匀拌合,成为湿而松散的面絮状或胶泥状,再搓成条塞入孔中捣实并从外部封堵,如HSCA-Ⅱ型破碎剂水灰比一般采用28%~33%,但本发明中,宜为20%~25%。 In the construction method of the static blasting demolition of the zero-ring segment of the shield-shaped tunnel in the above-mentioned embodiment of the present invention, different types of static breaking agents are selected according to different seasons, for example, the HSCA- Type II high-efficiency silent breaking agent, applicable temperature 25±5°C; use HSCA-Ⅰ type high-efficiency silent breaking agent of Zhongke New Material Beijing Technology Co., Ltd. in summer, applicable temperature 35±5°C; use Zhongke New Material Beijing Technology Co., Ltd. in winter The company's HSCA-Ⅲ high-efficiency silent breaking agent is suitable for a temperature of 10±5°C, supplemented by winter maintenance measures such as thermal insulation covering; since the drilled hole is a horizontal hole, preferably, the static breaking agent is a medicine roll type breaking agent, or a conventional Breaking agent, but when mixing the static breaking agent, reduce the recommended water-cement ratio, which should be 20% to 25%, and mix evenly to form a wet and loose flour floc or cement, and then knead it into strips and stuff it into the hole Compact it in the middle and seal it from the outside. For example, the water-cement ratio of HSCA-II type breaker is generally 28% to 33%, but in the present invention, it is preferably 20% to 25%.

上述披露的各技术特征并不限于已披露的与其它特征的组合,本领域技术人员还可根据发明之目的进行各技术特征之间的其它组合,以实现本发明之目的为准。 The technical features disclosed above are not limited to the disclosed combination with other features, and those skilled in the art can also make other combinations among the technical features according to the purpose of the invention, so as to achieve the purpose of the present invention.

Claims (9)

1. a construction method for nullring section of jurisdiction, shield molding tunnel is removed in static blasting, described nullring section of jurisdiction by superposed section of jurisdiction, be positioned at the section of jurisdiction at middle part and be positioned at the section of jurisdiction of bottom and constitute, between adjacent section of jurisdiction, profit is connected with;It is characterized in that, comprise the following steps:
Step 1, in the cloth hole, outer annular face of described nullring section of jurisdiction, holes in cloth hole site;
Step 2, section of jurisdiction is carried out static blasting by substep, and broken section of jurisdiction is cleared up;
First the static breaking agent that mixing is good is filled in the section of jurisdiction on top and it is carried out static blasting, broken section of jurisdiction is cleared up;
Then the static breaking agent that mixing is good is filled in the section of jurisdiction at middle part and it is carried out static blasting, broken section of jurisdiction is cleared up;
Finally the static breaking agent that mixing is good is filled in the section of jurisdiction of bottom and it is carried out static blasting, broken section of jurisdiction is cleared up.
2. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in static blasting according to claim 1, it is characterised in that superposed section of jurisdiction has two pieces, respectively F type section of jurisdiction and L2 type section of jurisdiction;The section of jurisdiction being positioned at middle part has two pieces, respectively L1 type section of jurisdiction and B2 type section of jurisdiction;The section of jurisdiction being positioned at bottom has two pieces, respectively B1 type section of jurisdiction and B3 type section of jurisdiction.
3. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in static blasting according to claim 1, it is characterized in that, in step 1, at a distance of 20cm~50cm between adjacent drill center, the degree of depth of described boring is 0.7~0.9 times of chip length, and the aperture of described boring is 30mm~50mm.
4. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in static blasting according to claim 1, it is characterised in that select different types of static breaking agent according to Various Seasonal;Static breaking agent is powder stick type cracking agent, or conventional cracking agent, but is reduced by the ratio of mud recommended when mixing static breaking agent, is preferably 20%~25%.
5. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in static blasting according to claim 1, it is characterized in that, described step 1 specifically includes, artificial erection construction platform, utilize air drill at cloth hole site pore-forming, then boring is cleaned out and make anhydrous in boring or foreign material.
6. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in the static blasting according to any one of claim 1-5, it is characterized in that, in step 2, before the static breaking agent that mixing is good is filled into section of jurisdiction, check the dry and wet degree in boring, if the dry water absorption of hole wall is strong, first with the moistening hole wall of water purification.
7. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in static blasting according to any one of claim 1-5, it is characterised in that in step 2, in the boring of static breaking agent loading section of jurisdiction mixing is good before hot.
8. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in the static blasting according to any one of claim 1-5, it is characterized in that, in subzero temperature environment during construction, the saline that utilizes weight percent concentration to be 1%~2% or the warm water mixing static breaking agent more than zero degrees celsius.
9. the construction method of nullring section of jurisdiction, shield molding tunnel is removed in the static blasting according to any one of claim 6, it is characterized in that, in subzero temperature environment during construction, the saline that utilizes weight percent concentration to be 1%~2% or the warm water mixing static breaking agent more than zero degrees celsius.
CN201610129540.9A 2016-03-08 2016-03-08 The construction method of shield molding tunnel nullring section of jurisdiction is removed in a kind of static blasting Expired - Fee Related CN105736000B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610129540.9A CN105736000B (en) 2016-03-08 2016-03-08 The construction method of shield molding tunnel nullring section of jurisdiction is removed in a kind of static blasting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610129540.9A CN105736000B (en) 2016-03-08 2016-03-08 The construction method of shield molding tunnel nullring section of jurisdiction is removed in a kind of static blasting

Publications (2)

Publication Number Publication Date
CN105736000A true CN105736000A (en) 2016-07-06
CN105736000B CN105736000B (en) 2018-12-21

Family

ID=56249173

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610129540.9A Expired - Fee Related CN105736000B (en) 2016-03-08 2016-03-08 The construction method of shield molding tunnel nullring section of jurisdiction is removed in a kind of static blasting

Country Status (1)

Country Link
CN (1) CN105736000B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368718A (en) * 2016-10-25 2017-02-01 陕西铁路工程职业技术学院 Metro deep-buried tunnel reinforced concrete duct piece dismounting operation vehicle
CN108915706A (en) * 2018-08-14 2018-11-30 中国铁建大桥工程局集团有限公司 High hydraulic pressure shield launching portal horizontal grouting and static breaking construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101144905B1 (en) * 2009-12-31 2012-05-14 강릉건설 주식회사 Tunnel process using protective shield
CN102733399A (en) * 2012-07-04 2012-10-17 江苏省华建建设股份有限公司 Method for removing internal support concrete by static expansion
CN103234403A (en) * 2013-04-24 2013-08-07 中国科学院武汉岩土力学研究所 Static blasting construction method for highway tunnel
CN103742155A (en) * 2013-12-24 2014-04-23 中国神华能源股份有限公司 Long-span segment removing method
CN103967010A (en) * 2014-05-14 2014-08-06 中铁西北科学研究院有限公司深圳南方分院 Method for safely detaching anchor sealing concrete
CN104500082A (en) * 2014-12-29 2015-04-08 上海市基础工程集团有限公司 Mining-method tunnel inner shield receiving construction method
CN104564085A (en) * 2014-12-23 2015-04-29 中铁十一局集团第五工程有限公司 Comprehensive construction method for excavating tunnel with super large cross-section under urban super shallow-buried condition
CN104695968A (en) * 2015-02-11 2015-06-10 河南工程学院 Method for in-tunnel starting of shield tunneling machine
CN105840199A (en) * 2016-05-12 2016-08-10 中国矿业大学(北京) Rock-roadway comprehensive tunneling method for static-blasting-matching tunneling machine

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101144905B1 (en) * 2009-12-31 2012-05-14 강릉건설 주식회사 Tunnel process using protective shield
CN102733399A (en) * 2012-07-04 2012-10-17 江苏省华建建设股份有限公司 Method for removing internal support concrete by static expansion
CN103234403A (en) * 2013-04-24 2013-08-07 中国科学院武汉岩土力学研究所 Static blasting construction method for highway tunnel
CN103742155A (en) * 2013-12-24 2014-04-23 中国神华能源股份有限公司 Long-span segment removing method
CN103967010A (en) * 2014-05-14 2014-08-06 中铁西北科学研究院有限公司深圳南方分院 Method for safely detaching anchor sealing concrete
CN104564085A (en) * 2014-12-23 2015-04-29 中铁十一局集团第五工程有限公司 Comprehensive construction method for excavating tunnel with super large cross-section under urban super shallow-buried condition
CN104500082A (en) * 2014-12-29 2015-04-08 上海市基础工程集团有限公司 Mining-method tunnel inner shield receiving construction method
CN104695968A (en) * 2015-02-11 2015-06-10 河南工程学院 Method for in-tunnel starting of shield tunneling machine
CN105840199A (en) * 2016-05-12 2016-08-10 中国矿业大学(北京) Rock-roadway comprehensive tunneling method for static-blasting-matching tunneling machine

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
翟志国等: "《大直径盾构负环管片拆除及隧道换装技术》", 《中国工程科学》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368718A (en) * 2016-10-25 2017-02-01 陕西铁路工程职业技术学院 Metro deep-buried tunnel reinforced concrete duct piece dismounting operation vehicle
CN108915706A (en) * 2018-08-14 2018-11-30 中国铁建大桥工程局集团有限公司 High hydraulic pressure shield launching portal horizontal grouting and static breaking construction method

Also Published As

Publication number Publication date
CN105736000B (en) 2018-12-21

Similar Documents

Publication Publication Date Title
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN100564802C (en) The method of crushing rock formation in the colliery
CN103670420B (en) Tunneling boring shaft drilling machine
CN103993888B (en) An improved structure of the shield machine for the reinforcement construction of the tunnel surface in the shield machine cabin
CN105804410B (en) Prefabricated concrete structure is vertically connected with dividing storehouse slip casing by pressure method
CN102052079A (en) Method for exchanging tool of shield machine for tunnel construction
CN108868784B (en) Construction method for breaking tunnel portal enclosure structure at end of shield region
CN108999188A (en) Crushing device, restructuring bankrupt and the application of cast-in-situ bored pile pile crown
CN114109421B (en) Construction method for open TBM through long fault fracture zone
CN102704936A (en) Caving control method for fully mechanized mining face tip mining road way top plate
CN201407053Y (en) Supporting and Waterproofing Structures for Subway Sectional Tunnels Used in Tunnel Boring Machine Construction
CN105003296A (en) Method for treating low air permeability coal seam gas discharge
CN116677391B (en) A static fracturing agent excavation method for subway connecting passages
CN104389608A (en) Air shaft shield crossing construction method
CN109457690A (en) A kind of application static(al) abolishes pile crown system and its restructuring bankrupt
CN105114117A (en) Gas drainage method based on expansion material
CN106679519A (en) Static blasting demolition method for interior reinforced concrete supports
CN103233476A (en) Deep foundation pit supporting structure as well as construction method and demolishing method thereof
CN115467673A (en) Construction method based on urban subway tunnel shield receiving
CN102733399A (en) Method for removing internal support concrete by static expansion
CN109630131B (en) A kind of underground chamber construction method
CN118462182A (en) Construction method of tunnel ultra-deep vertical shaft reverse well method based on ecological slope protection
CN114635713A (en) Emergency treatment method for secondary caving area after collapse column uncovering of main air return roadway of production mine
CN102337925A (en) Method for enlarging, filling and supporting coal-pillar-free mining roadway for fully-mechanized top coal caving
CN203603910U (en) Full-face vertical shaft drill

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181221